Proyek Pile Work Of Acid Plant AIM Di Morowali JAM KERJA

LAPORAN HARIAN JAM DATANG JAM PULANG


6 DESEMBER 2021 6:00 23:00
PT. MERDEKA TSINGSHAN INDONESIA
KONDISI CERAH
DAFTAR PERSONIL KEGIATAN
CUACA
NO JABATAN JML CRANE PANCANG KERUSAKAN ALAT
1 SPV. PELAKSANA 1
2 ENGINEERING 1 RIG ( C-1579 ) RIG ( C-1572K ) RIG ( C-1572K )
3 DRIVER 2 DIDIK UMBARIYONO MUBASIRIN GURU ARIWIBOWO
4 HSE OFFICER 0 TITIK 8 TITIK 7 TITIK
5 PILLING CRANE OPERATOR 3 METER 189 METER 152 METER
6 SERVICE CRANE OPERATOR 1 Catatan : Stand By CATATAN
7 WELDER 4 Menunggu Tititk
8 REEGER 7 Pancang
9 MACHANIC 1 `
10 LOGISTIK 1
DIBUAT OLEH
DOKUMENTASI

JUMLAH 21

DAFTAR PERALATAN MENGETAHUI


NO JENIS ALAT JML
1 PILLING CRANE 3 UNIT
2 SERVICE CRANE 1 UNIT
3 WELDING MACHINE 4 UNIT
4 HAMMER DD.65 3 UNIT
5 SEMI TRAILLER 1 UNIT
6 KENDARAAN OPRASIONAL 1 UNIT
7
8 TOTAL PEKERJAAN NOTED
JUMLAH 13 UNIT PEMANCANGAN FINAL SET 15 TITIK