PEMBANGUNAN JALAN TOL RUAS SIGLI - BANDA ACEH SEKSI 1B

LAPORAN HARIAN
HARI : Rabu
TANGGAL : 26-05-21

A. PEKERJAAN B. MATERIAL YANG DIGUNAKAN


No. ITEM PEKERJAAN SAT VOLUME POSISI L/R LOKASI No. TIPE SAT VOLUME LOKASI

1 Timbunan Untuk Akses Road m3 3800 1+900 - 2+225 Galian Main Road 3800 5+650
1+100 - 1+300

2 Pemadatan Akses Road 1+900 - 2+225


1+100 - 1+300

3 Galian Replacement 1+100 - 1+300

Total Volume Estimasi Timbunan m3 3800 Total Volume Galian Main Road m3 3800
*) Volume yang dicatat hanya perkiraan bukan untuk persetujuan pembayaran
C. PENGUJIAN LAPANGAN DAN LABORATORIUM D. ALAT YANG DIGUNAKAN
No. JENIS PENGUJIAN SAT VOLUME LOKASI No. NAMA ALAT SAT VOLUME LOKASI
1 Excavator Kobelco SK200 unit 4 Seksi 1
2 Excavator Kobelco SK330 unit 4
3 Bulldozer Komatsu D65EX unit 2
4 Bulldozer Shantui unit 2
5 Vibro Roller XGMA unit 4
6 Sheep Foot Roller XGMA unit 2
7 Dump Truk unit 15
8 Motor Grader XGMA unit 1
9 Water Tank Unit 1
No. JABATAN JUMLAH KET No. KETERANGAN JAM LOKASI CATATAN
1 Project Manager 1 1 Cerah 08.00 - 12.00 4 Jam
2 Opr & Eng Mgr. 1 Cerah 13.00 - 16.00 3 Jam
3 Hse Mgr 0
4 Adm & Keu 1
5 Engineering 1
6 Quantity Surveyor 1
7 Surveyor 1
8 Hse Supervisor 1
9 Supervisor 6
10 Drafter 1
11 Ass. Surveyor 2
12 Logistik 2
13 Driver & Operator 29
14 Mekanik 2 Total 7 Jam

G. KENDALA / MASALAH DLL

KETERANGAN
Kapasitas 1 Dump Truk = 20 m3 = Ritase x Kapasitas
Timbunan Main road = 3800 m3 Ritase = 190 Rit

H. CATATAN
URAIAN NAMA TANDA TANGAN
PEMBERI TUGAS : PT. ADHI KARYA ( Persero ) Tbk
KONSULTAN SUPERVISI :
KONTRAKTOR : PT. BINA MITRA INDOSEJAHTERA
PEMBANGUNAN JALAN TOL RUAS SIGLI - BANDA ACEH

LAPORAN HARIAN
HARI : Rabu
TANGGAL : 26-05-21

DOKUMENTASI
PEMBANGUNAN JALAN TOL RUAS SIGLI - BANDA ACEH

LAPORAN HARIAN
HARI : Rabu
TANGGAL : 26-05-21

DOKUMENTASI
PEMBANGUNAN JALAN TOL RUAS SIGLI - BANDA ACEH

LAPORAN HARIAN
HARI : Rabu
TANGGAL : 26-05-21

DOKUMENTASI

Anda mungkin juga menyukai