Anda di halaman 1dari 45

FORMULIR STANDAR UNTUK

PEREKAMAN ANALISA HARGA SATUAN PEKERJAAN

KEGIATAN : PEMBANGUNAN LAPANGAN TERBAK DISTRIK


PEKERJAAN : PEMBANGUNAN LAPANGAN TERBANG ENGGOLOK KAB. NDUGA
KABUPATEN : NDUGA
JENIS PEKERJAAN : MOBILISASI DAN DEMOBILISASI
SATUAN PEMBAYARAN : Ls

PERKIRAAN HARGA JUMLAH


NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp) (Rp)

A. SEWA TANAH M2 - - -

B PERALATAN DAN TENAGA KERJA


Tire Roller Unit -
Tandem Roller Unit -
Dump Truck 5 Ton Unit -
Compressor Unit -

C FASILITAS KANTOR
1 Base Camp M2
2 Kantor M2 - - -
3 Barak M2
4 Bengkel M2
5 Gudang dll M2

D FASILITAS DIREKSI TEKNIS


1 Kantor M2
2 Akomodasi untuk Wakil Direksi M2
3 Bangunan Laboratorium M2
4 Test dan Uji Laboratorium Ls
5 Perabotan dan Pelayanan Set

E. LAIN - LAIN
1 Pengukuran & As-Built Drawings Set 1.00 ### 25,000,000.00
2 Dokumentasi Proyek Ls 1.00 4,500,000.00 4,500,000.00
3 Papan Nama Proyek Ls 1.00 1,000,000.00 1,000,000.00
4 Pembersihan Akhir Ls
TOTAL BIAYA MOBILISASI DIBULATKAN 30,500,000.00
DIBULATKAN 30,500,000.00

Note : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over head dan laba s
seluruh pajak dan bea (kecuali PPN), dan pengeluaran lainnya.
### ###
JENIS PEKERJAAN : MOBILISASI

HARGA
No. JENIS ALAT SATUAN VOLUME SATUAN
(Rp.)

B. PERALATAN

1 ASPHALT MIXING PLANT Unit


2 ASPHALT FINISHER Unit 1.00 6,500,000.00
3 ASPHALT SPRAYER Unit 1.00 6,500,000.00
4 BULLDOZER 100-150 HP Unit 1.00 6,500,000.00
5 COMPRESSOR 4000-6500 L\M Unit
6 CONCRETE MIXER 0.3-0.6 M3 Unit
7 DUMP TRUCK 3-4 M3 Unit
8 DUMP TRUCK Unit
9 EXCAVATOR 80-140 HP Unit 1.00 6,500,000.00
10 FLAT BED TRUCK 3-4 M3 Unit
11 GENERATOR SET Unit
12 MOTOR GRADER >100 HP Unit 1.00 6,500,000.00
13 WHEEL LOADER 1.0-1.6 M3 Unit
14 THREE WHEEL ROLLER 6-8 T Unit
15 TANDEM ROLLER 6-8 T. Unit 1.00 6,500,000.00
16 TIRE ROLLER 8-10 T. Unit
17 VIBRATORY ROLLER 5-8 T. Unit 1.00 6,500,000.00
18 CONCRETE VIBRATOR Unit
19 STONE CRUSHER Unit
20 WATER PUMP 70-100 mm Unit
21 WATER TANKER 3000-4500 L. Unit 1.00 6,500,000.00
22 JACK HAMMER Unit
23 CHAIN SAW Unit

MOBILISASI

DEMOBILISASI ( 25% x MOBILISASI)

JUMLAH MOBILISASI DAN DEMOBILISASI


JUMLAH
HARGA
(Rp.)

6,500,000.00
6,500,000.00
6,500,000.00

6,500,000.00

6,500,000.00

6,500,000.00

6,500,000.00

6,500,000.00

52,000,000.00

13,000,000.00

65,000,000.00
JENIS PEKERJAAN : Cement Trated Base (CTB)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HA

No. URAIAN KODE KOEF. SATUAN

I ASUMSI

1 Pekerjaan dilakukan secara mekanik


2 Lokasi pekerjaan di sepanjang jalan

3 jarak rata-rata sumber material tambahan ke lokasi pekerjaan L 0.10 km


4 jam kerja efektif per hari Tk 8.00 jam
5 Faktor kembang agregat Fk 1.20
6 Dalam sehari dapat diselesaikan penghamparan sepanjang La 525.00 m
7 Tebal hamparan padat t 0.20 m
8 Agregat dibawa dari sumber material ke lokasi pekerjaan
9 Berat isi padat agregat Bip 2.20 ton/m3

II URUTAN KERJA

1 Wheel Loader memuat agregat tambahan keatas Dump Truk


2 Dump Truk membawa agregat kelokasi pekerjaan, langsung ditumpahkan
keatas permukaan jalan di lokasi pekerjaan
3 Motor Grader meratakan hamparan agregat
4 Semen dihampar merata di atas permukaan agregat secara manual

5 Hamparan hasil penggarukan dan pencampuran dipadatkan awal


memakai Vibro Compactor
6 Motor Grader meratakan dan mengatur ketebalan lapisan
7 Pneumatic Tyre Roller memadatkan lapisan
8 Selama pemadatan disemprotkan air secukupnya memakai Water Tank
Truck.

III PEMAKAIAN BAHAN, ALAT DAN TENAGA


1 BAHAN
Agregat Ca 87.00 %

Semen FF 13.00 %

2 ALAT
2a WHEEL LOADER E15
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.85
Faktor efesiensi alat Fa 0.83
Waktu siklus :
- waktu muat T1 0.45 menit
Ts1 0.45 menit

Kapasitas Prod/jam V x Fb x Fa x 60 Q1 117.58 m3


Fk x Ts1
Koefesiensi alat / M3 1 / Q1 0.0085 jam
2b DUMP TRUCK (E09)
Kapasitas bak V 10.00 Ton
Faktor Efisiensi alat Fa 0.80 -
Kecepatan rata-rata bermuatan v1 20.00 KM / Jam
Kecepatan rata-rata kosong v2 30.00 KM / Jam
Waktu Siklus Ts2
- waktu isi = (V x 60) / (Q1 x Bip) T1 2.32 menit
- waktu tempuh isi = (L : v1) x 60 T2 0.30 menit
- waktu tempuh kosong = (L : v2) x 60 T3 0.20 menit
- lain lain T4 2.00 menit
Ts2 4.82 menit

Kap.Prod. / jam = V x Fa x 60 Q2 45.27 M3


Ts2 x Bip
Koefisien Alat/M2 = 1 : Q2 (E09) 0.0221 Jam

ITEM PEMBAYARAN NO. 0


JENIS PEKERJAAN : Cement Trated Base (CTB)
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HA

No. URAIAN KODE KOEF. SATUAN

2c MOTOR GRADER (E13)


Panjang hamparan La 525.00 M
lebar efektif kerja blade b 2.00 M
Faktor efesiensi alat Fa 0.80 -
kecepatan rata-rata alat v 2.50 km/jam
Jumlah lintasan n 4.00 Lintasan
Waktu siklus
- Perataan 1 kali lintasan = La x 60 / V x 1000 T1 12.60 menit
- Lain-lain T2 2.00 menit
Ts3 14.60 menit
Kapasitas Produksi = Q2 x Fa x 60 Q3 37.21 M3
n x Ts3
Koefesien Alat / m3 = 1 / Q3 0.0269 jam

2e VIBRATORY ROLLER (COMPACTOR) (E19)


Kecepatan rata-rata pemadatan v 1.50 km/jam
Lebar efektif pemadatan b 1.20 m
Faktor Efesiansi alat Fa 0.83
Jumlah lintasan n 2.00 lintasan

Kapasitas Produksi / m3 = (v x 1000) x b x t x Fa Q5 597.60 m3


n
Koefesiensi alat / m3 = 1/ Q5 0.0017 jam
2f MOTOR GRADER (E13)
Panjang hamparan L 525.00 M
lebar efektif kerja blade b 2.00 M
Faktor efesiensi alat Fa 0.80 -
kecepatan rata-rata alat v 2.50 km/jam
Jumlah lintasan n 4.00 Lintasan
Waktu siklus Ts4
- Perataan 1 kali lintasan = (L x 60)/(v x 1000) T1 12.60 menit
- Lain-lain T2 2.00 menit
Ts4 14.60 menit
Kapasitas Produksi = Q4 x Fa x 60 Q6 0.82 M3
n x Ts4
Koefesien Alat / m3 = 1 / Q6 1.2167 jam

JENIS PEKERJAAN : Cement Trated Base (CTB)


SATUAN PEMBAYARAN : M3 URAIAN ANALISA HA

No. URAIAN KODE KOEF. SATUAN

2.i PNEUMATIC TIRED ROLLER (E18)


Kecepatan rata-rata pemadatan v 2.50 KM / jam
Lebar efektif pemadatan b 1.99 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod./jam = (v x 1000) x b x t x Fa Q7 103.23 M3


n
Koefisien Alat/M2 = (1 / Q7) 0.0097 Jam

2h WATER TANK TRUK (E 23)


Koefesien alat sama dengan PNEUMATIC TIRED ROLER 0.0097 Jam

3 TENAGA
Produksi menentukan : Q4 103.23 m3/jam
Produksi CTB/ hari = Tk x Q4 Qt 825.85 m3
Kebutuhan tenaga : P 8.00 orang
M 1.00 orang

Koefesien tenaga / m3 : - Pekerja = (Tk x P) : Qt 0.0775 jam


- Mandor = (Tk x M) : Qt 0.0097 jam
URAIAN ANALISA HARGA SATUAN

KETERANGAN

asumsi sesuaikan
dengan spek

padat
URAIAN ANALISA HARGA SATUAN

KETERANGAN
URAIAN ANALISA HARGA SATUAN

KETERANGAN
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : ………………………………………………………………….
No. PAKET KONTRAK :
NAMA PAKET : ………………………………………………………………….
PROP / KAB / KODYA : ………………………………………………………………….
ITEM PEMBAYARAN NO. : ………………………………………………………………….
JENIS PEKERJAAN : Cement Trated Base (CTB)

SATUAN PEMBAYARAN : M3

NO KOMPONEN SAT. PERKIRAAN


KUANTITAS

I TENAGA

1 Pekerja Jam 0.0775


2 Mandor Jam 0.0097

JUMLAH HARGA TENAGA

II BAHAN
1 Agregat Kg 66.0

3 Semen M3 0.0820

JUMLAH HARGA BAHAN

III PERALATAN
1 WHEEL LOADER Jam 0.0085
2 DUMP TRUCK Jam 0.0221
3 MOTOR GRADER Jam 0.0269

5 VIBRATORY ROLLER (COMPACTOR) Jam 0.0017

7 PNEUMATIC TIRED ROLLER Jam 0.0097


8 WATER TANK TRUK Jam 0.0097
9 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

A JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


B OVERHEAD & PROFIT ( 10% x A )
C HARGA SATUAN PEKERJAAN ( D + E )
D HARGA PEKERJAAN PER M2 t=10 CM
UNTUK
ING HARGA SATUAN

PERKIRAAN VOL. PEK.


TOTAL HARGA (Rp.)
% THD. BIAYA PROYEK

HARGA SATUAN JUMLAH


(Rp.) (Rp.)

#REF! #REF! 5,000.00 #REF! 5,000.00 -


#REF! #REF! 6,250.00 #REF! 6,250.00 -

#REF! #REF!

-
488.89 32,266.67 850.00 (361.11) 850.00 -
4,737.50 (4,737.50) 5,587.50 850.00
#REF! #REF! 106,000.00 #REF! 106,000.00 -
111,000.00 ### 111,000.00 -

#REF! #REF!

#REF! #REF! 4,750,000.00 #REF! 4,987,500.00 237,500.00


#REF! #REF! 150,000.00 #REF! 157,500.00 7,500.00
581,581.32 15,644.54 195,000.00 386,581.32 250,000.00 55,000.00
375,000.00 ### 393,750.00 18,750.00
422,838.86 718.83 400,000.00 22,838.86 500,000.00 100,000.00
135,000.00 ### 140,000.00 5,000.00
#REF! #REF! 185,000.00 #REF! 195,000.00 10,000.00
#REF! #REF! 180,000.00 #REF! 185,000.00 5,000.00
0.00 - 750,000.00 ### 787,500.00 37,500.00
135,000.00 ### 150,000.00 15,000.00
2,000.00 (2,000.00) 2,000.00 -

#REF!
#REF! #REF! #REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

361.11
5,587.50
#REF!
111,000.00

#REF!
#REF!
###
393,750.00
77,161.14
140,000.00
#REF!
#REF!
787,500.00
150,000.00
2,000.00
DAFTAR
HARGA DASAR SATUAN UPAH
HARGA HARGA
No. URAIAN KODE SATUAN SATUAN KETERANGAN
KETERANGAN ( Rp.)
( Rp.)
1. Pekerja L01 Jam 15,714.29 Jam kerja

2. Tukang L02 Jam 17,857.14


125000
3. Mandor L03 Jam 21,428.57
150000
4. Operator L04 Jam 19,285.71
135000
5. Pembantu Operator L05 Jam 17,857.14
125000
6. Sopir / Driver L06 Jam 17,857.14

7. Pembantu Sopir / Driver L07 Jam 15,714.29

8. Mekanik L08 Jam 19,285.71

9. Pembantu Mekanik L09 Jam 17,857.14


125000
10. Kepala Tukang L10 Jam 19,285.71
135000
ANALISA BIAYA

TENAGA KAPASITAS NILAI FAKTOR


ALAT ALAT UMUR JAM HARGA SISA PENGEM-
ALAT KERJA ALAT ALAT BALIAN
1 TAHUN MODAL

(HP) - (Tahun) (Jam) (Rp.) (Rp.) -


No. JENIS PERALATAN
i(1+i)^A
(10% X B) ------
(1+i)^A-1

HP Cp A W B C D
1 2 3 4 6 7 8 9 10

1. ASPHALT MIXING PLANT 150.0 50.0 T/Jam 10.0 1,500.0 3,500,000,000 350,000,000 0.22251
2. ASPHALT FINISHER 47.0 6.0 Ton 6.0 2,000.0 700,000,000 70,000,000 0.28591
3. ASPHALT SPRAYER 15.0 800.0 Liter 5.0 2,000.0 110,000,000 11,000,000 0.31978
4. BULLDOZER 100-150 HP 140.0 - 5.0 2,000.0 1,500,000,000 150,000,000 0.31978
5. COMPRESSOR 4000-6500 L\M 80.0 - 5.0 2,000.0 150,000,000 15,000,000 0.31978
6. CONCRETE MIXER 0.3-0.6 M3 15.0 500.0 Liter 4.0 2,000.0 55,000,000 5,500,000 0.37174
7. DUMP TRUCK 3-4 M3 100.0 6.0 Ton 5.0 2,000.0 200,000,000 20,000,000 0.31978
8. DUMP TRUCK 125.0 8.0 Ton 5.0 2,000.0 275,000,000 27,500,000 0.31978
9. EXCAVATOR 80-140 HP 80.0 0.8 M3 5.0 2,000.0 1,000,000,000 100,000,000 0.31978
10. FLAT BED TRUCK 3-4 M3 100.0 4.0 M3 5.0 2,000.0 500,000,000 50,000,000 0.31978
11. GENERATOR SET 175.0 125.0 KVA 5.0 2,000.0 340,000,000 34,000,000 0.31978
12. MOTOR GRADER >100 HP 125.0 - 5.0 2,000.0 860,000,000 86,000,000 0.31978
13. WHEEL LOADER 1.0-1.6 M3 105.0 1.5 M3 5.0 2,000.0 1,000,000,000 100,000,000 0.31978
14. THREE WHEEL ROLLER 6-8 T 55.0 8.0 Ton 5.0 2,000.0 700,000,000 70,000,000 0.31978
15. TANDEM ROLLER 6-8 T. 50.0 8.0 Ton 5.0 2,000.0 780,000,000 78,000,000 0.31978
16. TIRE ROLLER 8-10 T. 60.0 10.0 Ton 5.0 1,800.0 750,000,000 75,000,000 0.31978
17. VIBRATORY ROLLER 5-8 T. 75.0 7.0 Ton 4.0 2,000.0 675,000,000 67,500,000 0.37174
18. CONCRETE VIBRATOR 10.0 - 4.0 1,000.0 23,000,000 2,300,000 0.37174
19. STONE CRUSHER 120.0 50.0 T/Jam 5.0 2,000.0 1,500,000,000 150,000,000 0.31978
20. WATER PUMP 70-100 mm 6.0 - 2.0 2,000.0 13,500,000 1,350,000 0.63872
21. WATER TANKER 3000-4500 L. 100.0 4,000.0 Liter 5.0 2,000.0 210,000,000 21,000,000 0.31978
22. JACK HAMMER 3.0 - 5.0 1,000.0 65,000,000 6,500,000 0.31978
23 CHAIN SAW 2.0 4.0 500.00 17,500,000 1,750,000 0.37174

KETERANGAN :
1. Tingkat Suku Bunga = 18.0 % per-tahun
2. Upah Operator / Sopir / Mekanik = 25,714 Rupiah per-orang/jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik = 32,143 Rupiah per-orang/jam
4. Harga Bahan Bakar Bensin = 11,217 Rupiah per-liter
5. Harga Bahan Bakar Solar = 13,243 Rupiah per-liter
6. Minyak Pelumas = 46,030 Rupiah per-liter
7. Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
ALISA BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA PASTI PER JAM BIAYA OPERASI PER JAM KERJA


BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS PERBAIKAN & PERAWATAN UPAH
PENGEM- DAN BIAYA BAHAN MINYAK OPERATOR PEMBANTU
BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA / SOPIR OPERATOR
MODAL / SOPIR
(Rp.) (Rp.) (Rp.) Lt/HP/Jam Ltr/HP/Jam (Rp.) - (Rp.) (Rp.) (Rp.)
f1 x HP x 1 Orang 1 Orang
(B - C) x D 0.002 x B 0.125 0.01 Harga BBM 0.125 (g1 x B') Per Per
------- ----- (e1 + e2) s/d s/d + s/d ----- Jam Kerja Jam Kerja
W W 0.175 0.02 f2 x HP x 0.175 W = =
Harga Olie Rp25,714.3 Rp32,142.9
e1 e2 E f1 f2 F g1 G H I
11 12 13 14 15 16 17 18 19 20

467,280.75 4,666.67 471,947.41 0.1500 0.0150 401,532.19 0.1500 350,000.00 25,714.29 32,142.86
90,061.69 700.00 90,761.69 0.1500 0.0150 125,813.42 0.1500 52,500.00 25,714.29 32,142.86
15,829.00 110.00 15,939.00 0.1500 0.0150 40,153.22 0.1500 8,250.00 25,714.29 32,142.86
215,850.04 1,500.00 217,350.04 0.1500 0.0150 374,763.38 0.1500 112,500.00 25,714.29 32,142.86
21,585.00 150.00 21,735.00 0.1500 0.0150 214,150.50 0.1500 11,250.00 25,714.29 32,142.86
9,200.53 55.00 9,255.53 0.1500 0.0150 40,153.22 0.1500 4,125.00 25,714.29 32,142.86
28,780.01 200.00 28,980.01 0.1500 0.0150 267,688.13 0.1500 15,000.00 25,714.29 32,142.86
39,572.51 275.00 39,847.51 0.1500 0.0150 334,610.16 0.1500 20,625.00 25,714.29 32,142.86
143,900.03 1,000.00 144,900.03 0.1500 0.0150 214,150.50 0.1500 75,000.00 25,714.29 32,142.86
71,950.01 500.00 72,450.01 0.1500 0.0150 267,688.13 0.1500 37,500.00 25,714.29 32,142.86
48,926.01 340.00 49,266.01 0.1500 0.0150 468,454.22 0.1500 25,500.00 25,714.29 32,142.86
123,754.02 860.00 124,614.02 0.1500 0.0150 334,610.16 0.1500 64,500.00 25,714.29 32,142.86
143,900.03 1,000.00 144,900.03 0.1500 0.0150 281,072.53 0.1500 75,000.00 25,714.29 32,142.86
100,730.02 700.00 101,430.02 0.1500 0.0150 147,228.47 0.1500 52,500.00 25,714.29 32,142.86
112,242.02 780.00 113,022.02 0.1500 0.0150 133,844.06 0.1500 58,500.00 25,714.29 32,142.86
119,916.69 833.33 120,750.02 0.1500 0.0150 160,612.88 0.1500 62,500.00 25,714.29 32,142.86
112,915.62 675.00 113,590.62 0.1500 0.0150 200,766.09 0.1500 50,625.00 25,714.29 32,142.86
7,694.99 46.00 7,740.99 0.1500 0.0150 26,768.81 0.1500 3,450.00 25,714.29 32,142.86
215,850.04 1,500.00 217,350.04 0.1500 0.0150 321,225.75 0.1500 112,500.00 25,714.29 64,285.71
3,880.20 13.50 3,893.70 0.1500 0.0150 16,061.29 0.1500 1,012.50 25,714.29 32,142.86
30,219.01 210.00 30,429.01 0.1500 0.0150 267,688.13 0.1500 15,750.00 25,714.29 32,142.86
18,707.00 130.00 18,837.00 0.1500 0.0150 7,118.92 0.1500 9,750.00 25,714.29 32,142.86
11,709.77 70.00 11,779.77 0.1500 0.0150 4,745.94 0.1500 5,250.00 25,714.29 0.00
BIAYA OPERASI PER JAM KERJA TOTAL
TOTAL BIAYA
BIAYA SEWA ALAT
OPERASI PER
/ JAM JAM KERJA
(Rp.) (Rp.) KET.

F+G+H+I E+J

J K L
21 22 23

809,389.33 1,281,336.74
236,170.56 326,932.25
106,260.36 122,199.36
545,120.52 762,470.56
283,257.64 304,992.65
102,135.36 111,390.89
340,545.27 369,525.27
413,092.30 452,939.81
347,007.64 491,907.67
363,045.27 435,495.28
551,811.36 601,077.37
456,967.30 581,581.32
413,929.67 558,829.70
257,585.61 359,015.63
250,201.21 363,223.23
280,970.02 401,720.04
309,248.24 422,838.86
88,075.96 95,816.95
523,725.75 741,075.79
74,930.93 78,824.63
341,295.27 371,724.27
74,726.06 93,563.06
35,710.23 47,490.00
RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN LAPANGAN TERBANG ENGGOLOK KAB. NDUGA


KEGIATAN : PEMBANGUNAN LAPANGAN TERBAK DISTRIK
LOKASI : BANDARA PERINTIS ENGGOLOK DISTRIK KORA
TAHUN : 2017

N0 URAIAN SATUAN VOLUME

A. PEKERJAAN PERSIAPAN
1 Pengukuran Awal dan Akhir M2 11,250.00
2 Pekerjaan mobilisasi dan demobilisasi Lot 1.00
3 Direksi keet M2 45.00

B. PEKERJAAN KONSTRUKSI DAN MARKING


1 Pengupasan top soil 10 cm (pembersihan lokasi) M3 7,083.65
2 Pekerjaan timbunan sirtu M3 2,466.73

C. PEKERJAAN AKHIR
1 Dokumentasi Foto Ls 1.00
2 Pekerjaan Pembersihan akhir Ls 1.00
REKAPITULASI

PEKERJAAN : PEMBANGUNAN LAPANGAN TERBANG ENGGOLOK KAB. NDUGA


KEGIATAN : PEMBANGUNAN LAPANGAN TERBAK DISTRIK
LOKASI : BANDARA PERINTIS ENGGOLOK DISTRIK KORA
TAHUN : 2017

N0 URAIAN

A. PEKERJAAN PERSIAPAN

B. PEKERJAAN KONSTRUKSI DAN MARKING

C. PEKERJAAN AKHIR
Real Cost
PPn 10%

Jumlah
Dibulatkan

Terbilang :
"Sembilan Ratus Sembilan Puluh Sembilan Juta Rupiah"

Nduga, Desemb

KEPALA DINAS PERHUBUN


SELAKU KUASA PENGGU

SIMON NIRIGI, S
Nip. 1960 0507 199
RENCANA ANGGARAN BIAYA

N TERBANG ENGGOLOK KAB. NDUGA

HARGA SATUAN JUMLAH HARGA


(Rp.) (Rp.)

1,501.69 16,893,996.43
30,500,000.00 30,500,000.00
1,418,489.29 63,832,017.86
111,226,014.29

23,192.37 164,286,619.27
253,280.80 624,775,339.55
789,061,958.82

3,000,000.00 3,000,000.00
5,000,000.00 5,000,000.00

8,000,000.00
REKAPITULASI

N TERBANG ENGGOLOK KAB. NDUGA

URAIAN JUMLAH HARGA

Rp. 111,226,014.29

Rp. 789,061,958.82

Rp. 8,000,000.00
Rp. 908,287,973.10
Rp. 90,828,797.31

Rp. 999,116,770.41
Rp. 999,000,000.00

Nduga, Desember 2017

KEPALA DINAS PERHUBUNGAN KAB. NDUGA


SELAKU KUASA PENGGUNA ANGGARAN

SIMON NIRIGI, SE, MS,i.


Nip. 1960 0507 199610 1001
HARGA PERKIRAAN SENDIRI

PEKERJAAN : PEMBANGUNAN TAXIWAY B DAN APRON BARU


LOKASI : BANDAR UDARA MOZES KILANGI
TAHUN : 2012

N0 URAIAN SATUAN VOLUME

A. PEKERJAAN PERSIAPAN
1 Pengukuran Awal dan Akhir M2 6,300.00
2 Pekerjaan mobilisasi dan demobilisasi Lot 1.00
3 Direksi keet M2 45.00

B. PEKERJAAN KONSTRUKSI DAN MARKING


1 Galian tanah konstruksi M3 3,782.60
2 Pengupasan top soil 20 cm (pembersihan lokasi) M2 5,985.00
3 Pekerjaan timbunan tanah pilihan CBR 6% M3 8,042.20
4 Pekerjaan sub base corse (sirtu 64 cm) CBR 20 % M2 3,622.50
5 Pekerjaan base corse (batu pecah 34 cm) CBR 80 % M2 3,622.50
6 Prime coat AC 60/70 2 Kg/m2 M2 3,622.50
7 Pekerjaan CTBC t = 10 cm M2 3,622.50
8 Tack coat 60/70 1 Kg/m2 M2 3,622.50
9 Pekerjaan ATB t = 7,5 cm M2 3,622.50
10 Tack coat 60/70 1 Kg/m2 M2 3,622.50
11 Pekerjaan surface (hotmix 5 cm) M2 3,622.50
12 Pekerjaan marking M2 141.75

C. PEKERJAAN GORONG2 BETON BERTULANG


1 Pekerjaan Gorong - Gorong Beton K-250 M3 57.60
2 Pekerjaan Tulangan Kg 11,520.00

D. PEKERJAAN AKHIR
1 Dokumentasi Foto Ls 1.00
2 Pekerjaan Pembersihan akhir LS 1.00
3 Asbuild Drawaing LS 1.00
REKAPITULASI

N0 URAIAN

A. PEKERJAAN PERSIAPAN

B. PEKERJAAN KONSTRUKSI DAN MARKING

C. PEKERJAAN GORONG2 BETON BERTULANG

D. PEKERJAAN AKHIR
Real Cost
PPn 10%

Jumlah
Dibulatkan

Timika, Nov

SATKER BANDAR UDARA M


RGA PERKIRAAN SENDIRI

HARGA SATUAN JUMLAH HARGA


(Rp.) (Rp.)

#REF! #REF!
30,000,000.00 30,000,000.00
#REF! #REF!
#REF!

#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
Err:509 Err:509
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF!

#REF! #REF!
#REF! #REF!
#REF!

3,000,000.00 3,000,000.00
4,000,000.00 4,000,000.00
6,000,000.00 6,000,000.00
13,000,000.00
REKAPITULASI

URAIAN JUMLAH HARGA

Rp. #REF!

Rp. #REF!

Rp. #REF!

Rp. 13,000,000.00
Rp. #REF!
Rp. #REF!

Rp. #REF!
Rp. #REF!

Timika, November 2012

SATKER BANDAR UDARA MOSES KILANGIN TIMIKA


JOHANNES RETTOB, S. Sos. MM
Nip. 19621019 198403 1 002
JENIS PEKERJAAN : URUGAN PILIHAN
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HAR

No. URAIAN KODE KOEF.

I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 8.00
5 Faktor pengembangan bahan Fk 1.20
6 Tebal hamparan padat t 0.15

II. URUTAN KERJA


1 Whell Loader memuat ke dalam Dump Truck
2 Dump Truck mengangkut ke lapangan dengan jarak
quari ke lapangan L 4.00
3 Material dihampar dengan menggunakan Motor Grader
4 Hamparan materian disiram air dengan Water Tank Truck
(sebelum pelaksanaan pemadatan) dan dipadatkan
dengan menggunakan Vibro Roller
5 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Material timbunan = 1 x Fk 1.20

2. ALAT
2.a. WHELL LOADER
Kapasitas Bucket V 1.50
Faktor Bucket Fb 0.90
Faktor Efisiensi Alat Fa 0.85
Waktu sklus Ts1
- Muat T1 0.50
- Lain-lain T2 0.50
Ts1 1.00

Kapasitas Produksi / Jam = V x Fb x Fa x 60 Q1 57.38


Fk x Ts1

Koefisienalat / M3 = 1 : Q1 0.0174

2.b. DUMP TRUCK


Kapasitas bak V 8.00
Faktor efisiensi alat Fa 0.85
Kecepatan rata-rata bermuatan v1 60.00
Kecepatan rata-rata kosong v2 70.00
Waktusiklus : Ts2
- Waktu tempuh isi = (L : v1) x 60 T1 4.00
- Waktu tempuh kosong = (L : v2) x 60 T2 3.43
- Lain-lain T3 0.50
Ts2 7.93
JENIS PEKERJAAN : URUGAN PILIHAN
SATUAN PEMBAYARAN : M3 URAIAN ANALISA H

No. URAIAN KODE KOEF.

Kapasitas Produksi / Jam = V x Fa x 60 Q2 42.88


Fk x Ts2

Koefisien Alat / M3 = 1 : Q2 0.0233

2.c. MOTOR GRADER


Panjang hamparan Lh 50.00
Lebar Efektif kerja Blade b 2.40
Faktor Efisiensi Alat Fa 0.85
Kecepatan rata-rata alat v 5.00
Jumlah lintasan n 5
Waktu siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.60
- Lain-lain T2 0.50
Ts3 1.10

Kapasitas Produksi / Jam = Lh x b x t x Fa x 60 Q3 166.91


n x Ts3
Koefisien Alat / M3 = 1 : Q3 0.0060

2.d. VIBRATOR ROLLER


Kecepatan rata-rata alat v 4.00
Lebar efektif pemadatan b 1.20
Jumlah lintasan n 6.00
Faktor efisiensi alat Fa 0.85

Kapasitas Prod./Jam = (v x 1000) x b x t x Fa Q4 102.00


n

Koefisien Alat / M3 = 1 : Q4 0.0098

2.e. WATER TANK TRUCK


Volume tangki air V 4,000.00
Kebutuhan air / M3 material padat Wc 0.07
Pengisian Tangki / jam n 3.00
Faktor efisiensi alat Fa 0.85
Kapasitas Produksi / Jam = V x n x Fa Q5 145,714.29
Wc
Koefisien Alat / M3 = 1 : Q5 0.000007

2.f. ALAT BANTU


Diperlukan alat-alat bantu kecil
- Sekop = 3 buah

3. TENAGA
Produksi menentukan : WHELL LOADER Q1 57.38
Produksi Galian / hari = Tk x Q1 Qt 459.00
Kebutuhan tenaga :
- Pekerja P 4.00
- Mandor M 1.00
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt 0.0697
- Mandor = (Tk x M) : Qt 0.0174
URAIAN ANALISA HARGA SATUAN

SATUAN KETERANGAN

Jam
-
M

Km

M3 Quarry

M3
-
-
menit
menit
menit
menit

M3

Jam

M3
-
KM/Jam
KM/Jam

menit
menit
menit
menit

Bersambung
URAIAN ANALISA HARGA SATUAN
Lanjutan

SATUAN KETERANGAN

M3

Jam

M
M
-
Km / Jam
lintasan

menit
menit
menit

M3

Jam

Km / Jam
M
lintasan
-

M3

Jam

M3
M3
kali
- Baik
M3

Jam

Lump Sump

M3/Jam
M3
orang
orang

Jam
Jam
HARGA PERKIRAAN SENDIRI

PEKERJAAN : PEMBANGUNAN APRON BARU 150 x 200 M2


LOKASI : BANDAR UDARA MOZES KILANGI
TAHUN : 2012

N0 URAIAN SATUAN VOLUME

A. PEKERJAAN PERSIAPAN
1 Pengukuran sebelum dan sesudah termasuk design profil M2 30,000.00
2 Pekerjaan mobilisasi dan demobilisasi Lot 1.00
3 Land Clearing (mekanik) M2 30,000.00
4 Direksi keet M2 45.00

B. PEKERJAAN KONSTRUKSI DAN MARKING


1 Galian tanah konstruksi M3 17,003.27
2 Pengupasan top soil 20 cm M2 30,000.00
3 Penyiapan Subgrade CBR > 6% M3 13,982.16
4 Lapis Perekat (Prime Coat) 2 Kg/m2 M2 30,000.00
5 Agregat Sub Base Course ( t = 30 cm ) CBR > 20 % M2 30,000.00
6 Pekerjaan base corse (batu pecah 30 cm) CBR 80 % M2 30,000.00

REKAPITULASI

N0 URAIAN

A. PEKERJAAN PERSIAPAN

B. PEKERJAAN KONSTRUKSI DAN MARKING

Real Cost
PPn 10%
Jumlah
Dibulatkan

Timika, Nov

SATKER BANDAR UDARA M

JOHANNES RETT
Nip. 19621019
RGA PERKIRAAN SENDIRI

HARGA SATUAN JUMLAH HARGA


(Rp.) (Rp.)

#REF! #REF!
30,000,000.00 30,000,000.00
#REF! #REF!
#REF! #REF!
#REF!

#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!

#REF!

REKAPITULASI

URAIAN JUMLAH HARGA

Rp. #REF!

Rp. #REF!

Rp. #REF!
Rp. #REF!
Rp. #REF!
Rp. #REF!

Timika, November 2012

SATKER BANDAR UDARA MOSES KILANGIN TIMIKA

JOHANNES RETTOB, S. Sos. MM


Nip. 19621019 198403 1 002
HARGA PERKIRAAN SENDIRI

PEKERJAAN : PEMBANGUNAN TAXIWAY DAN APRON BARU


LOKASI : BANDAR UDARA MOZES KILANGI
TAHUN : 2012

N0 URAIAN SATUAN VOLUME

A. PEKERJAAN PERSIAPAN
1 Pengukuran sebelum dan sesudah termasuk design profil M2 8,950.00
2 Pekerjaan mobilisasi dan demobilisasi Lot 1.00
4 Direksi keet M2 45.00

B. PEKERJAAN KONSTRUKSI DAN MARKING


1 Galian tanah (Mekanis) M3 15,605.26
2 Pasangan Batu dengan Mortal M3 3,288.05

REKAPITULASI

A. PEKERJAAN PERSIAPAN

B. PEKERJAAN KONSTRUKSI DAN MARKING


Real Cost
PPn 10%
Jumlah
Dibulatkan
RGA PERKIRAAN SENDIRI

HARGA SATUAN JUMLAH HARGA


(Rp.) (Rp.)

#REF! #REF!
65,000,000.00 65,000,000.00
#REF! #REF!
#REF!

#REF! #REF!
#REF! #REF!

#REF!

REKAPITULASI

Rp. #REF!

Rp. #REF!
Rp. #REF!
Rp. #REF!
Rp. #REF!
Rp. #REF!
DAFTAR HARGA SATUAN UPAH KERJA
-
UPAH/HARI UPAH/JAM
NO URAIAN KODE
(Rp) (Rp)

1 Pekerja L01 165,000.00 23,571.43


2 Tukang L02 190,000.00 27,142.86
3 Mandor L03 225,000.00 32,142.86
4 Operator L04 250,000.00 35,714.29
5 Pembantu operator L05 180,000.00 25,714.29
6 Sopir/Driver L06 225,000.00 32,142.86
7 Pembantu sopir L07 160,000.00 22,857.14
8 Mekanik L08 250,000.00 35,714.29
9 Pembantu mekanik L09 180,000.00 25,714.29
10 Kepala Tukang L10 190,000.00 27,142.86

Anda mungkin juga menyukai