CATATAN : Sebelum menekan tombol SETUJU atau tombol TIDAK SETUJU , terleb
KENYAM
LOKASI PEKERJAAN
BASE CAMP
KM 245+600
BATASBATU
SEGMENT 6
284+100 290+100
URUGAN PILIHAN
URUGAN BIASA
PASIR PASANG
PASIR BETON
KM 265+000
BATAS BATU
MAMUGU
ITEM PEMBAYARAN NO. : 1.2
JENIS PEKERJAAN : MOBILISASI
HARGA
No. URAIAN SATUAN VOL. SATUAN
(Rp.)
B. PERALATAN
Periksa lembar 1.2-2
3 Bituminous Testing
Marshall Asphalt Test
Extraction Test, Centrifuge/Refflux Method
Specific Gravity for Coarse Aggregate
Specific Gravity for Fine Aggregate
Mix Air Viod Content (Accurate Method)
Core Drill
Metal Thermometer
Accessories and Tolls
Penetration Test
Softening Point
Refusal Density Compactor
4 Concrete Testing
Slump Cone
Cylinder/Cube Mould for Compressive Strength
Beam Mould for Flexural Strength (RIGID)
Crushing Machine
E. MOBILISASI LAINNYA
E.I. PEKERJAAN DARURAT LS 0 100,000,000
1 Perkuatan Jembatan Lama
2 Pemeliharaan Jalan Kerja / Samping
3 ...................... ....
4 ...................... ....
5 ...................... ....
6 ...................... ....
G. DEMOBILISASI LS 1 28,800,000
Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
KODE HARGA
No. JENIS ALAT ALAT SATUAN VOL. SATUAN
(Rp.)
B. PERALATAN
96,000,000
II. Soil & Aggregate Testing
1. Compaction Test
50,000 2. CBR Test
500,000,000 3 Specifc Gravity
4 Atterberg Limits
5 Grain Size Analysis
6 Field Density Test by Sand Cone Methode
7 Moisture Content
8 Abrasion of Aggregate by Los Angeles Machine
V. Peralatan pendukung
1 Mobil Pick Up
2 Komputer + Printer
3 Furniture
VI. Operasional
VII. Test Luar
Test Luar, sesuai kebutuhan atau atas
perintah Direksi
Catatan :
0 1. Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang
yang dibayar kontrak) dan biaya lain-lainnya.
2. Test luar adalah test ke lembaga pengujian yang disetujui oleh Konsu
96,000,000
BILISASI FASILITAS LABORATORIUM
: Lump sum
: Rp. 35,940,000.00
HARGA
SATUAN VOLUME TOTAL KETERANGAN
SATUAN
10,000,000.00
0.00
0.00
10,000,000.00
10,000,000.00
Rp 35,940,000.00
buah 8 8 8 4
buah 2 2
buah
buah 1
buah 2
buah
buah
buah 4
buah 8 8 8 4
buah 4 4 4 2
buah
buah
buah
buah
buah
buah
buah 2
buah
4 8 20 12
2 1 4 1
2 4
4
2
4 16 24 10
2 4 4 4
2
Biaya
ZONA 9 VOLUME TOTAL KETERANGAN
mobilisasi
12 -
1 -
- lihat spesifikasi
-
-
-
-
-
10 -
4 -
4 -
- lihat spesifikasi
- lihat spesifikasi
- lihat spesifikasi
- lihat spesifikasi
- lihat spesifikasi
-
- lihat spesifikasi
ITEM PEMBAYARAN NO. : 1.8 (2)
JENIS PEKERJAAN : Pemasangan & Pemeliharaan Jembatan Sementara
HARGA JUMLAH
No. URAIAN SATUAN VOL. SATUAN HARGA
(Rp.) (Rp.)
Catatan : Jumlah yang tercantum pada masing-masing item di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
INFORMASI UMUM
No. URAIAN INFORMASI
7. Lebar jalan lama ( bahu + perkerasan + bahu ) ( 1.00 + 4.50 + 1.00 ) meter
11. Jarak rata-rata Base Camp ke lokasi pekerjaan ---> L= 5.75 Kilometer
10.50 Km = a C 10.50 Km = b
A B
0.5 Km = c
Base Camp --------->
D
7. Lebar jalan lama ( bahu + perkerasan + bahu ) ( 1.50 + 5.00 + 1.50 ) meter
11. Jarak rata-rata Base Camp ke lokasi pekerjaan ---> L= 0.60 Kilometer
1.00 Km = a C 1.00 Km = b
A Km = c B
0.1
Base Camp ---->
D
Kalkulasi Jarak Rata-Rata =
20 ....................................
21 ....................................
22 ....................................
No Jenis Peralatan Satuan Harga
Total 225,000.00
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 19.80 Km
4 Harga satuan pasir di Quarry RpM01 1.00 M3 1,150,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 543,541.30
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 485,944.05
7 Berat volume pasir Bil 1.42 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M01a - Pasir Pasang
Lokasi : Quarry
Tujuan : Base Camp
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke Lokasi Pekerjaan L 19.70 Km
4 Harga satuan batu kali di Quarry RpM02 1.00 M3 950,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 543,541.30
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 485,944.05
7 Berat volume batu kali Bil 1.44 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.75 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.75 menit
- Lain-lain T2 0.50 menit
Ts1 1.25 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 27.7884 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M02 - Batu Kali
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke Lokasi Pekerjaan L 19.70 Km
4 Harga satuan batu kali di Quarry RpM06 1.00 M3 950,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 543,541.30
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 485,944.05
7 Harga Satuan Dasar Wheel Loader RpE15 1.00 Jam 386,581.57
8 Harga Satuan Upah Pekerja RpL01 1.00 Jam 10,125.00
9 Berat volume batu belah Bil 1.60 ton/m3
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M06 - Batu Belah
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
3.d PEKERJA
Biaya Pekerja / M3 =
{ (7 Jam x P) : Qt } x RpL01 Rp4 5,465.41 Rupiah
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke Lokasi Pekerjaan L 19.80 Km
4 Harga satuan Gravel di Quarry RpM07 1.00 M3 950,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 543,541.30
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 485,944.05
7 Berat volume gravel Bil 2.20 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.75 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.75 menit
- Lain-lain T2 0.50 menit
Ts1 1.25 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 27.7884 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M07 - Gravel
Lokasi : Quarry
Tujuan : Base Camp
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 19.70 Km
4 Harga satuan Sirtu di Quarry RpM16 1.00 M3 550,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 543,541.30
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 485,944.05
7 Berat volume sirtu Bil 1.51 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M16 - Sirtu
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi pekerjaan L 19.70 Km
4 Harga satuan pasir urug di Quarry RpM44 1.00 M3 550,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 543,541.30
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 485,944.05
7 Berat volume pasir urug Bil 1.42 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 41.6826 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M44 - Pasir Urug
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi pekerjaan L 19.70 Km
4 Harga satuan pasir urug di Quarry RpM44 1.00 M3 1,150,000.00
5 Harga Satuan Dasar Excavator RpE10 1.00 Jam 543,541.30
6 Harga Satuan Dasar Dump Truck RpE09 1.00 Jam 485,944.05
7 Berat isi volume pasir beton Bil 1.69 ton/m3
III. PERHITUNGAN
EXCAVATOR (E10)
Kapasitas Bucket V 0.50 M3
Faktor Bucket Fb 0.90 -
Faktor Efisiensi alat Fa 0.83 -
Waktu siklus Ts1
- Menggali / memuat T1 0.50 menit
- Lain-lain T2 0.50 menit
Ts1 1.00 menit
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 22.41 M3 / Jam
Ts1
Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M1c- Pasir Beton
Lokasi : Quarry
Tujuan : Lokasi Pekerjaan
Lanjutan
HARGA
No. URAIAN KODE KOEF. SATUAN SATUAN
(Rp.)
Bahan : Aspal
Bahan : Aspal
9112.5
8,391,779.79
19,654,220.21
779.09 US$/M.Ton
7,191,779.79 Rupiah/M.Ton
19,654,220.21
7,191.78
8,391,779.00
8,391,779.79
###
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT MIXING PLANT E01
2. Tenaga Pw 294.0 HP
3. Kapasitas Cp 60.0 T/Jam
4. Alat a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 3,795,108,800.0 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Rp./liter
5. Bahan Bakar Solar Ms 30,000.00 Rp./liter
6. Minyak Pelumas Mp 60,000.00 Rp./liter
7 PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
8 Bahan bakar Batubara 500.00 Rp/kg
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT FINISHER E02
2. Tenaga Pw 72.4 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,400.0 Jam
c. Harga Alat B 408,940,000 Rupiah
5.
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT SPRAYER E03
2. Tenaga Pw 4.0 HP
3. Kapasitas Cp 850.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 68,751,600 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan COMPRESSOR 4000-6500 L\M E05
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 5,000.0 CPM/(L/m)
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 232,685,200 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE MIXER 0.3-0.6 M3 E06
2. Tenaga Pw 20.0 HP
3. Kapasitas Cp 500.0 Liter
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 93,187,000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 9,318,700 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CRANE 10-15 TON E07
2. Tenaga Pw 138.0 HP
3. Kapasitas Cp 15.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 547,516,000 Rupiah
5.
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 54,751,600 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3.5 TON E08
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 3.5 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 272,239,800 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 10 TON E09
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 364,385,400 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan EXCAVATOR 80-140 HP E10
2. Tenaga Pw 133.0 HP
3. Kapasitas Cp 0.93 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 1,117,830,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan FLAT BED TRUCK 3-4 M3 E11
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 10.0 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 233,845,800 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan GENERATOR SET E12
2. Tenaga Pw 180.0 HP
3. Kapasitas Cp 135.0 KVA
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 459,209,800 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan MOTOR GRADER >100 HP E13
2. Tenaga Pw 135.0 HP
3. Kapasitas Cp 10,800.0 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 888,865,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TRACK LOADER 75-100 HP E14
2. Tenaga Pw 70.0 HP
3. Kapasitas Cp 0.8 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 712,252,600 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WHEEL LOADER 1.0-1.6 M3 E15
2. Tenaga Pw 96.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 746,807,200 Rupiah
A. URAIAN PERALATAN
1. Jenis Peralatan THREE WHEEL ROLLER 6-8 T E16
2. Tenaga Pw 55.0 HP
3. Kapasitas Cp 8.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 287,359,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TANDEM ROLLER 6-8 T. E17
2. Tenaga Pw 82.0 HP
3. Kapasitas Cp 8.1 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 643,143,400 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TIRE ROLLER 8-10 T. E18
2. Tenaga Pw 100.5 HP
3. Kapasitas Cp 9.0 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 589,391,800 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT
A. URAIAN PERALATAN
1. Jenis Peralatan VIBRATORY ROLLER 5-8 T. E19
2. Tenaga Pw 82.0 HP
3. Kapasitas Cp 7.050 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 744,247,600 Rupiah
B. BIAYA PASTI PER JAM KERJA BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 74,424,760 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE VIBRATOR E20
2. Tenaga Pw 5.5 HP
3. Kapasitas Cp 25.0 -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 11,458,600 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan STONE CRUSHER E21
2. Tenaga Pw 220.0 HP
3. Kapasitas Cp 60.0 T/Jam
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 938,865,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WATER PUMP 70-100 mm E22
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 10,598,500 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WATER TANKER 3000-4500 L. E23
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 187,773,000 Rupiah
B. BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 18,777,300 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan PEDESTRIAN ROLLER E24
2. Tenaga Pw 8.8 HP
3. Kapasitas Cp 835.000 Ton
4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 102,145,600 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TAMPER E25
2. Tenaga Pw 4.7 HP
3. Kapasitas Cp 121.000 Ton
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 22,756,600 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan JACK HAMMER E26
2. Tenaga Pw 0.0 HP
3. Kapasitas Cp 1,330.000 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 52,192,000 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan FULVI MIXER E27
2. Tenaga Pw 345.0 HP
3. Kapasitas Cp 2,005 -
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,000.0 Jam
c. Harga Alat B 238,983,200 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CONCRETE PUMP E28
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 8.00 M3
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 100 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan TRAILER 20 TON E29
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 20.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 100 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan PILE DRIVER + HAMMER E30
2. Tenaga Pw 25.0 HP
3. Kapasitas Cp 2.50 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 100 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan CRANE ON TRACK 35 TON E31
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 35.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 100 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan WELDING SET E32
2. Tenaga Pw 40.0 HP
3. Kapasitas Cp 250.00 Amp
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 100 Rupiah
A. URAIAN PERALATAN
1. Jenis Peralatan BORE PILE MACHINE E33
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 2,000.00 Meter
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 100 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT LIQUID MIXER E34
2. Tenaga Pw 5.0 HP
3. Kapasitas Cp 1,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 100 Rupiah
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
A. URAIAN PERALATAN
1. Jenis Peralatan ASPHALT LIQUID MIXER E34a
2. Tenaga Pw 40.0 HP Kapasitas 20.000
3. Kapasitas Cp 20,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 4.0 Tahun Khusus digunakan
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam untuk Asphalt
c. Harga Alat B 100 Rupiah Modifikasi
E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir U1 50,156.25 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 25,299.11 Rp./Jam
4. Bahan Bakar Bensin Mb 30,000.00 Liter
5. Bahan Bakar Solar Ms 30,000.00 Liter
6. Minyak Pelumas Mp 60,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
TENAGA KAPASITAS HARGA ALAT YANG DIPAKAI
ALAT ALAT ALAT JAM
UMUR KERJA HARGA
ALAT 1 TAHUN ALAT
HP Cp B A W B
1 2 2a 3 4 5 6 7 8
1. ASPHALT MIXING PLANT E01 294.0 60.0 T/Jam 3,795,108,800 10.0 1,500.0 3,795,108,800
2. ASPHALT FINISHER E02 72.4 10.0 Ton 408,940,000 6.0 1,400.0 408,940,000
3. ASPHALT SPRAYER E03 4.0 850.0 Liter 68,751,600 5.0 2,000.0 68,751,600
4. BULLDOZER 100-150 HP E04 155.0 - - 1,560,760,000 5.0 2,000.0 1,560,760,000
5. COMPRESSOR 4000-6500 L\M E05 60.0 5,000.0 CPM/(L/m) 232,685,200 5.0 2,000.0 232,685,200
6. CONCRETE MIXER 0.3-0.6 M3 E06 20.0 500.0 Liter 93,187,000 2.0 1,500.0 93,187,000
7. CRANE 10-15 TON E07 138.0 15.0 Ton 547,516,000 5.0 2,000.0 547,516,000
8. DUMP TRUCK 3.5 TON E08 100.0 3.5 Ton 272,239,800 5.0 2,000.0 272,239,800
9. DUMP TRUCK 10 TON E09 190.0 10.0 Ton 364,385,400 5.0 2,000.0 364,385,400
10. EXCAVATOR 80-140 HP E10 133.0 0.9 M3 1,117,830,000 5.0 2,000.0 1,117,830,000
11. FLAT BED TRUCK 3-4 M3 E11 190.0 10.0 ton 233,845,800 5.0 2,000.0 233,845,800
12. GENERATOR SET E12 180.0 135.0 KVA 459,209,800 5.0 2,000.0 459,209,800
13. MOTOR GRADER >100 HP E13 135.0 10,800.0 - 888,865,000 5.0 2,000.0 888,865,000
14. TRACK LOADER 75-100 HP E14 70.0 0.8 M3 712,252,600 5.0 2,000.0 712,252,600
15. WHEEL LOADER 1.0-1.6 M3 E15 96.0 1.5 M3 746,807,200 5.0 2,000.0 746,807,200
16. THREE WHEEL ROLLER 6-8 T E16 55.0 8.0 Ton 287,359,000 5.0 2,000.0 287,359,000
17. TANDEM ROLLER 6-8 T. E17 82.0 8.1 Ton 643,143,400 5.0 2,000.0 643,143,400
18. TIRE ROLLER 8-10 T. E18 100.5 9.0 Ton 589,391,800 5.0 2,000.0 589,391,800
19. VIBRATORY ROLLER 5-8 T. E19 82.0 7.1 Ton 744,247,600 5.0 2,000.0 744,247,600
20. CONCRETE VIBRATOR E20 5.5 25.0 - 11,458,600 4.0 1,000.0 11,458,600
21. STONE CRUSHER E21 220.0 60.0 T/Jam 938,865,000 5.0 2,000.0 938,865,000
22. WATER PUMP 70-100 mm E22 6.0 - - 10,598,500 3.0 2,000.0 10,598,500
23. WATER TANKER 3000-4500 L. E23 100.0 4,000.0 Liter 187,773,000 5.0 2,000.0 187,773,000
24. PEDESTRIAN ROLLER E24 8.8 835.0 Ton 102,145,600 3.0 2,000.0 102,145,600
25. TAMPER E25 4.7 121.0 Ton 22,756,600 4.0 1,000.0 22,756,600
26. JACK HAMMER E26 0.0 1,330.0 - 52,192,000 5.0 2,000.0 52,192,000
27. FULVI MIXER E27 345.0 2,005.0 - 238,983,200 4.0 1,000.0 238,983,200
28. CONCRETE PUMP E28 100.0 8.00 M3 100 6.0 2,000.0 100
29. TRAILER 20 TON E29 175.0 20.00 Ton 100 6.0 2,000.0 100
30 PILE DRIVER + HAMMER E30 25.0 2.50 Ton 100 5.0 2,000.0 100
31. CRANE ON TRACK 35 TON E31 125.0 35.00 Ton 100 6.0 2,000.0 100
32. WELDING SET E32 40.0 250.00 Amp 100 5.0 2,000.0 100
33. BORE PILE MACHINE E33 150.0 2,000.0 Meter 100 6.0 2,000.0 100
34. ASPHALT LIQUID MIXER E34 5.0 1,000.0 Liter 100 4.0 2,000.0 100
KETERANGAN : 1 Tingkat Suku Bunga = 10.00
2 Upah Operator / Sopir / Mekanik = 50,156
3 Upah Pembantu Operator/Sopir/Mekanik = 25,299
4 Harga Bahan Bakar Bensin = 30,000
5 Harga Bahan Bakar Solar = 30,000
6 Minyak Pelumas = 60,000
7 Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas
HP Cp B A W B
1 2 2a 3 4 5 6 7 8
35. TRONTON E35 150.0 15.0 Ton 100 10.0 1,500.0 100
36. COLD MILLING MACHINE E37 248.0 1,000.0 m 100 5.0 2,000.0 100
37. ROCK DRILL BREAKER E36 3.0 - - 100 10.0 1,500.0 100
38. COLD RECYCLER E38 900.0 2,200.0 M 100 5.0 2,000.0 100
39. HOT RECYCLER E39 400.0 3.0 M 100 5.0 2,000.0 100
40. AGGREGAT (CHIP) SPREADER E40 115.0 3.5 M 100 4.0 1,000.0 100
41. ASPHALT DISTRIBUTOR E41 115.0 4,000.0 Liter 305,602,400 5.0 2,000.0 305,602,400
42. SLIP FORM PAVER E42 105.0 2.5 M 387,509,600 6.0 2,000.0 387,509,600
43. CONCRETE PAN MIXER E43 134.0 600.0 Liter 100 10.0 1,500.0 100
44. CONCRETE BREAKER E44 290.0 20.0 m3/jam 100 5.0 2,000.0 100
45. ASPAHLT TANKER E45 190.0 4,000.0 liter 100 6.0 2,000.0 100
46. CEMENT TANKER E46 190.0 4,000.0 liter 100 6.0 2,000.0 100
47. CONDRETE MIXER (350) E47 20.0 350.0 liter 100 2.0 2,000.0 100
48. VIBRATING RAMMER E48 4.2 80.0 KG 100 4.0 1,000.0 100
49. TRUK MIXER (AGITATOR) E49 220.0 5.0 M3 606,355,400 5.0 2,000.0 606,355,400
50. BORE PILE MACHINE E50 125.0 60.0 CM 100 10.0 1,500.0 100
51. CRANE ON TRACK 75-100 TON E51 200.0 75.0 Ton 100 5.0 2,000.0 100
52. BLENDING EQUIPMENT E52 50.0 30.0 Ton 100 10.0 1,500.0 100
53. ASPHALT LIQUID MIXER E34a 40.0 20,000.0 Liter 100 4.0 2,000.0 100
54. BAR BENDER E53 3.0 0.0 0.0 0 8.0 1,250.0 0
55. BAR CUTTER E54 3.0 0.0 0.0 0 8.0 1,250.0 0
56. BREAKER E55 80.0 3.0 m3/jam 0 5.0 2,000.0 0
57. GROUTING PUMP E56 100.0 15.0 Ton 0 5.0 2,000.0 0
58. JACK HIDROLIC E57 3.0 150.0 Ton 0 5.0 2,000.0 0
59. MESIN LAS E58 3.0 0.2 Ton 0 3.0 900.0 0
60. PILE DRIVER LEADER, 75 kw E59 70.0 75.0 kw 0 5.0 9,600.0 0
61. PILE HAMMER E60 10.0 0.0 0.0 0 3.0 800.0 0
62. PILE HAMMER, 2,5 Ton E61 1.0 2.50 Ton 0 5.0 8,000.0 0
63. STRESSING JACK E62 89.0 15.00 Ton 0 5.0 1,800.0 0
64. WELDING MACHINE, 300 A E63 5.0 0.00 0 0 5.0 10,000.0 0
65.
66.
67.
68.
KETERANGAN : 1 Tingkat Suku Bunga = 10.00
2 Upah Operator / Sopir / Mekanik = 50,156
3 Upah Pembantu Operator/Sopir/Mekanik = 25,299
4 Harga Bahan Bakar Bensin = 30,000
5 Harga Bahan Bakar Solar = 30,000
6 Minyak Pelumas = 60,000
7 Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya Pekerjaan
8 Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12 Liter x (Kapasitas
9 AMP , Aspal Sprayer, Aspal Distribusi ditambah bahan bakar untuk pemanasan Aspal = 1/1000 x Kapas
#REF!
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (I)
NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PER JAM
SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS WORKSHOP
ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK
MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA
MODAL
(Rp.) - (Rp.) (Rp.) (Rp.) % % (Rp.) - (Rp.)
f1 x HP x
i(1+i)^A (B - C) x D 0.002 x B 12 2.5 Harga BBM 0.0625 (g1 x B')
(10% X B) ----------- ----------- ----------- (e1 + e2) s/d s/d + s/d -----
(1+i)^A-1 W W 15 3 f2 x HP x 0.0875 W
Harga Olie
C D e1 e2 E f1 f2 F g1 G
9 10 11 12 13 14 15 16 17 18
379,510,880 0.16275 370,581.89 5,060.15 375,642.03 0.1500 0.0300 16,972,200.00 0.0875 221,381
40,894,000 0.22961 60,361.48 584.20 60,945.68 0.1500 0.0300 456,120.00 0.0625 18,256.25
6,875,160 0.26380 8,161.42 68.75 8,230.18 0.1200 0.0250 20,400.00 0.0875 3,007.88
156,076,000 0.26380 185,276.05 1,560.76 186,836.81 0.1200 0.0250 790,500.00 0.0875 68,283.25
23,268,520 0.26380 27,621.80 232.69 27,854.48 0.1200 0.0250 306,000.00 0.0875 10,179.98
9,318,700 0.57619 32,216.08 124.25 32,340.33 0.1500 0.0300 126,000.00 0.0875 5,435.91
54,751,600 0.26380 64,995.00 547.52 65,542.52 0.1200 0.0250 703,800.00 0.0875 23,953.83
27,223,980 0.26380 32,317.28 272.24 32,589.52 0.1200 0.0250 510,000.00 0.0875 11,910.49
36,438,540 0.26380 43,255.78 364.39 43,620.16 0.1200 0.0250 969,000.00 0.0875 15,941.86
111,783,000 0.26380 132,696.33 1,117.83 133,814.16 0.1200 0.0250 678,300.00 0.0875 48,905.06
23,384,580 0.26380 27,759.57 233.85 27,993.42 0.1200 0.0250 969,000.00 0.0875 10,230.75
45,920,980 0.26380 54,512.27 459.21 54,971.48 0.1200 0.0250 918,000.00 0.0875 20,090.43
88,886,500 0.26380 105,516.16 888.87 106,405.02 0.1200 0.0250 688,500.00 0.0875 38,887.84
71,225,260 0.26380 84,550.70 712.25 85,262.95 0.1200 0.0250 357,000.00 0.0875 31,161.05
74,680,720 0.26380 88,652.64 746.81 89,399.44 0.1200 0.0250 489,600.00 0.0875 32,672.82
28,735,900 0.26380 34,112.06 287.36 34,399.42 0.1200 0.0250 280,500.00 0.0875 12,571.96
64,314,340 0.26380 76,346.82 643.14 76,989.97 0.1200 0.0250 418,200.00 0.0875 28,137.52
58,939,180 0.26380 69,966.03 589.39 70,555.42 0.1200 0.0250 512,550.00 0.0875 25,785.89
74,424,760 0.26380 88,348.79 744.25 89,093.04 0.1200 0.0250 418,200.00 0.0875 32,560.83
1,145,860 0.31547 3,253.37 22.92 3,276.29 0.1500 0.0300 34,650.00 0.0625 716.16
93,886,500 0.26380 111,451.60 938.87 112,390.46 0.1200 0.0250 1,122,000.00 0.0875 41,075.34
1,059,850 0.40211 1,917.82 10.60 1,928.41 0.1200 0.0250 30,600.00 0.0875 463.68
18,777,300 0.26380 22,290.32 187.77 22,478.09 0.1200 0.0250 510,000.00 0.0875 8,215.07
10,214,560 0.40211 18,483.42 102.15 18,585.56 0.1200 0.0250 44,880.00 0.0875 4,468.87
2,275,660 0.31547 6,461.14 45.51 6,506.65 0.1500 0.0300 29,610.00 0.0625 1,422.29
5,219,200 0.26380 6,195.65 52.19 6,247.85 0.1200 0.0250 0.00 0.0875 2,283.40
23,898,320 0.31547 67,853.00 477.97 68,330.97 0.1500 0.0300 2,173,500.00 0.0625 14,936.45
10 0.22961 0.01 0.00 0.01 0.1200 0.0250 510,000.00 0.0875 0.00
10 0.22961 0.01 0.00 0.01 0.1200 0.0250 892,500.00 0.0875 0.00
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 127,500.00 0.0875 0.00
10 0.22961 0.01 0.00 0.01 0.1200 0.0250 637,500.00 0.0875 0.00
10 0.26380 0.01 0.00 0.01 0.1200 0.0250 204,000.00 0.0875 0.00
10 0.22961 0.01 0.00 0.01 0.1200 0.0250 765,000.00 0.0875 0.00
10 0.31547 0.01 0.00 0.01 0.1200 0.0250 25,500.00 0.0875 0.00
% per-tahun
Rupiah per-orang/jam
Rupiah per-orang/jam
Rupiah per-liter
Rupiah per-liter
Rupiah per-liter
si Biaya Pekerjaan
sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom 16)
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA (II)
NILAI FAKTOR BIAYA PASTI PER JAM BIAYA OPERASI PER JAM
SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS WORKSHOP
ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK
MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA KOEF. BIAYA
MODAL
(Rp.) - (Rp.) (Rp.) (Rp.) Lt/HP/Jam Ltr/HP/Jam (Rp.) - (Rp.)
f1 x HP x
i(1+i)^A (B - C) x D 0.002 x B 0.125 0.01 Harga BBM 0.0625 (g1 x B')
(10% X B) ----------- ----------- ----------- (e1 + e2) s/d s/d + s/d -----
(1+i)^A-1 W W 0.175 0.02 f2 x HP x 0.0875 W
Harga Olie
C D e1 e2 E f1 f2 F g1 G
9 10 11 12 13 14 15 16 17 18
% per-tahun
Rupiah per-orang/jam
Rupiah per-orang/jam
Rupiah per-liter
Rupiah per-liter
Rupiah per-liter
si Biaya Pekerjaan
sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom 16)
anasan Aspal = 1/1000 x Kapasitas tangki aspal x harga bahan bakar solar ( lihat E 01 , E 03, E 41)
BIAYA OPERASI PER JAM KERJA TOTAL No. URAIAN
PERBAIKAN dan PERAWATAN UPAH TOTAL BIAYA
OPERATOR PEMBANTU BIAYA SEWA ALAT
KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
/ SOPIR / JAM JAM KERJA 1
- (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET. 2
1 Orang 1 Orang 3
0.125 (g1 x B') Per Per 4
s/d ----------- Jam Kerja Jam Kerja F+G+H+I E+J 5
0.175 W = = 6
Rp50,156.3 Rp25,299.1 7
g1 G H I J K L 8
17 18 19 20 21 22 23 9
10
0.1750 442,762.69 50,156.25 75,897.32 18,662,397.61 19,038,039.64 Pek. Ringan 11
0.1750 51,117.50 50,156.25 25,299.11 600,949.11 661,894.79 Pek. Ringan 12
0.1250 4,296.98 50,156.25 25,299.11 128,660.21 136,890.39 Pek. Berat 13
0.1250 97,547.50 50,156.25 25,299.11 1,031,786.11 1,218,622.92 Pek. Berat 14
0.1250 14,542.83 50,156.25 25,299.11 406,178.16 434,032.64 Pek. Berat 15
0.1750 10,871.82 50,156.25 25,299.11 217,763.08 250,103.41 Pek. Ringan 16
0.1250 34,219.75 50,156.25 25,299.11 837,428.93 902,971.45 Pek. Berat 17
0.1250 17,014.99 50,156.25 25,299.11 614,380.84 646,970.35 Pek. Berat 18
0.1250 22,774.09 50,156.25 25,299.11 1,083,171.31 1,126,791.47 Pek. Berat 19
0.1250 69,864.38 50,156.25 25,299.11 872,524.79 1,006,338.96 Pek. Berat 20
0.1250 14,615.36 50,156.25 25,299.11 1,069,301.47 1,097,294.89 Pek. Berat 21
0.1250 28,700.61 50,156.25 25,299.11 1,042,246.40 1,097,217.88 Pek. Berat 22
0.1250 55,554.06 50,156.25 25,299.11 858,397.26 964,802.28 Pek. Berat 23
0.1250 44,515.79 50,156.25 25,299.11 508,132.20 593,395.15 Pek. Berat 24
0.1250 46,675.45 50,156.25 25,299.11 644,403.62 733,803.07 Pek. Berat 25
0.1250 17,959.94 50,156.25 25,299.11 386,487.25 420,886.67 Pek. Berat 26
0.1250 40,196.46 50,156.25 25,299.11 561,989.34 638,979.31 Pek. Berat 27
0.1250 36,836.99 50,156.25 25,299.11 650,628.24 721,183.66 Pek. Berat 28
0.1250 46,515.48 50,156.25 25,299.11 572,731.66 661,824.70 Pek. Berat 29
0.1750 2,005.26 50,156.25 25,299.11 112,826.77 116,103.06 Pek. Ringan 30
0.1250 58,679.06 50,156.25 50,598.21 1,322,508.87 1,434,899.34 Pek. Berat 31
0.1250 662.41 50,156.25 25,299.11 107,181.45 109,109.86 Pek. Berat 32
0.1250 11,735.81 50,156.25 25,299.11 605,406.24 627,884.33 Pek. Berat 33
0.1250 6,384.10 50,156.25 25,299.11 131,188.33 149,773.89 Pek. Berat 34
0.1750 3,982.41 50,156.25 25,299.11 110,470.05 116,976.70 Pek. Ringan 35
0.1250 3,262.00 50,156.25 25,299.11 81,000.76 87,248.60 Pek. Berat 36
0.1750 41,822.06 50,156.25 25,299.11 2,305,713.87 2,374,044.83 Pek. Ringan 37
0.1250 0.01 50,156.25 25,299.11 585,455.37 585,455.38 Pek. Berat 38
0.1250 0.01 50,156.25 25,299.11 967,955.37 967,955.38 Pek. Berat 39
0.1250 0.01 50,156.25 25,299.11 202,955.37 202,955.38 Pek. Berat 40
0.1250 0.01 50,156.25 25,299.11 712,955.37 712,955.38 Pek. Berat 41
0.1250 0.01 50,156.25 25,299.11 279,455.37 279,455.38 Pek. Berat 42
0.1250 0.01 50,156.25 25,299.11 840,455.37 840,455.38 Pek. Berat 43
0.1250 0.01 50,156.25 25,299.11 100,955.37 100,955.38 Pek. Berat 44
45
46
47
48
49
50
51
52
53
54
55
BIAYA OPERASI PER JAM KERJA TOTAL 56
PERBAIKAN & PERAWATAN UPAH TOTAL BIAYA 57
OPERATOR PEMBANTU BIAYA SEWA ALAT 58
KOEF. BIAYA / SOPIR OPERATOR OPERASI PER 59
/ SOPIR / JAM JAM KERJA 60
- (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET. 61
1 Orang 1 Orang 62
0.125 (g1 x B') Per Per 63
s/d ----------- Jam Kerja Jam Kerja F+G+H+I E+J 64
0.175 W = =
Rp50,156.3 Rp25,299.1
g1 G H I J K L
17 18 19 20 21 22 23
BIAYA
URAIAN KO HP KAP. HARGA SEWA
DE ALAT ALAT/JAM
(di luar PPN)
T x Te1 x Te2 x Fa
T x Te1 x Te2 x Fa
REKAPITULASI
PERKIRAAN HARGA PEKERJAAN
Proyek / Bagpro :
No. Paket Kontrak : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
Nama Paket : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
Prop / Kab / Kodya : Papua Barat/Raja Ampat
Jumlah Harga
No. Divisi Uraian Pekerjaan
(Rupiah)
(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 638,060,887,471.69
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 63,806,088,747.17
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 701,866,976,218.86
(D) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B)DIBULATKAN 701,866,977,000.00
Terbilang : Tujuh Ratus Satu Milyar Delapan Ratus Enam Puluh Enam Juta Sembilan Ratus Tujuh Puluh Tujuh Ribu
Rupiah
( ........................................... ) ( ………………………………... )
NIP :
DAFTAR KUANTITAS DAN HARGA
SPESIFIKASI 2010 Revisi 3
PPK : ………………………………………………
No. Paket Kontrak : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
Nama Paket : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
Ruas Kapadiri - Go - Kabilol 25 KM
Prop / Kab / Kodya : Papua Barat/Raja Ampat
DIVISI 1. UMUM
1.2 Mobilisasi LS 1.00 905,790,000.00 905,790,000.00
1.21 Manajemen Mutu LS 1.00 231,600,000.00 231,600,000.00
Jumlah Harga Pekerjaan DIVISI 1 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 1,137,390,000.00
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 19,675.71 107,853.74 2,122,099,298.93
2.2.(1) Pasangan Batu dengan Mortar M3 1,860.99 8,500,025.11 15,818,500,638.59
Jumlah Harga Pekerjaan DIVISI 2 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 18,502,431,259.67
Jumlah Harga Pekerjaan DIVISI 3 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 326,212,767,668.07
Jumlah Harga Pekerjaan DIVISI 5 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 133,980,920,372.16
Jumlah Harga Pekerjaan DIVISI 6 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 45,799,845,968.82
DIVISI 7. STRUKTUR
7.9.(1) Pasangan Batu M3 3,106.17 11,118,168.75 34,534,894,425.99
Jumlah Harga Pekerjaan DIVISI 7 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 34,534,894,425.99
Jumlah Harga Pekerjaan DIVISI 8 (masuk pada Rekapitulasi Perkiraan Harga Pekerjaan) 77,892,637,776.98
Volume Report
2,510,423.83 115,390.75
KANAN KIRI
1 0+000.00 0+025.00 0+025.00 1+450.00
2 0+025.00 1+450.00 1+625.00 1+950.00
3 1+600.00 1+625.00 2+000.00 2+125.00
4 1+625.00 1+950.00 2+125.00 2+175.00
5 1+950.00 2+000.00 2+175.00 2+200.00
6 2+000.00 2+125.00 3+100.00 3+400.00
7 2+175.00 2+200.00 3+400.00 3+450.00
8 3+100.00 3+400.00 3+450.00 3+875.00
9 3+450.00 3+875.00 3+900.00 4+325.00
10 3+875.00 3+900.00 4+350.00 4+375.00
11 3+900.00 4+325.00 4+475.00 5+025.00
12 4+325.00 4+350.00 5+200.00 5+400.00
13 4+350.00 4+375.00 5+475.00 5+975.00
14 4+375.00 4+475.00 6+050.00 6+100.00
15 4+475.00 5+025.00 6+100.00 6+125.00
16 5+025.00 5+100.00 6+300.00 6+350.00
17 5+150.00 5+200.00 6+600.00 6+625.00
18 5+200.00 5+400.00 6+800.00 6+825.00
19 5+400.00 5+475.00 6+825.00 6+850.00
20 5+475.00 5+975.00 6+850.00 6+875.00
21 5+975.00 6+050.00 6+900.00 6+950.00
22 6+050.00 6+100.00 7+825.00 7+875.00
23 6+125.00 6+300.00 8+150.00 8+200.00
24 6+300.00 6+350.00 8+975.00 9+100.00
25 6+350.00 6+600.00 9+250.00 9+500.00
26 6+625.00 6+800.00 10+700.00 10+800.00
27 6+800.00 6+825.00 11+050.00 11+075.00
28 6+850.00 6+875.00 11+150.00 11+500.00
29 6+875.00 6+900.00 12+050.00 12+100.00
30 6+950.00 7+825.00 12+500.00 12+525.00
31 7+825.00 7+875.00 12+800.00 12+925.00
32 7+875.00 8+150.00 13+925.00 13+950.00
33 8+150.00 8+200.00 14+400.00 14+575.00
34 8+200.00 8+975.00 14+700.00 14+725.00
35 8+975.00 9+100.00 15+000.00 15+075.00
36 9+100.00 9+250.00 16+200.00 16+300.00
37 9+250.00 9+500.00 17+700.00 17+825.00
38 9+500.00 10+700.00 18+275.00 19+825.00
39 10+700.00 10+800.00 21+000.00 21+251.19
40 10+800.00 11+050.00
41 11+050.00 11+075.00
42 11+075.00 11+150.00
43 11+150.00 11+500.00
44 11+500.00 12+050.00
45 12+050.00 12+100.00
46 12+125.00 12+500.00
47 12+500.00 12+525.00
48 12+525.00 12+600.00
49 12+625.00 12+800.00
50 12+800.00 12+925.00
51 12+925.00 13+075.00
52 13+125.00 13+150.00
53 13+200.00 13+500.00
54 13+625.00 13+925.00
55 13+925.00 13+950.00
56 13+950.00 14+300.00
57 14+375.00 14+400.00
58 14+400.00 14+575.00
59 14+575.00 14+700.00
60 14+700.00 14+725.00
61 14+725.00 14+900.00
62 14+925.00 15+000.00
63 15+000.00 15+075.00
64 15+075.00 15+175.00
65 15+200.00 15+300.00
66 15+450.00 16+075.00
67 16+200.00 16+300.00
68 16+300.00 16+625.00
69 16+650.00 17+575.00
70 17+625.00 17+700.00
71 17+700.00 17+825.00
72 17+825.00 18+275.00
73 18+275.00 19+825.00
74 19+825.00 20+500.00
75 20+525.00 21+000.00
76 21+000.00 21+251.19
BACKUP KUANTITAS
1 - -
2 - -
3 - -
4 - -
5 - -
1 - 0.1685 -
2 - 0.2043 -
3 - -
4 - -
Jumlah Total - -
Jumlah 46752.6
B. Urugan Pilihan Bahu Jalan
Panjang Lebar Tebal Volume
No Km. to Km
(m) (m) (m) (m3)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
Jumlah 0.0
Jumlah -
BACKUP KUANTITAS
Nama Paket : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
Jumlah 51,427.87
3 Filler = 1.90 %
= 186.61 ton
4 Anti Stripping Agent = 0.30 %aspal
= 29.47 ton
5 Berat Agregat = 9,605.62 ton
Jumlah -
Jumlah 3,106.17
BACKUP KUANTITAS
Nama Paket
: Perencanaan Teknis Jalan Sentani - Genyem - Bongkrang
No. Paket Kontrak :
Prop / Kab / Kodya Papua
Tikungan
0+080.943 33.81
0+209.700 42.12
0+290.834 44.69
0+343.925 22.47
jumlah 143.09
Jumlah 5,056.10 Jumlah Keseluruhan
Jumlah
Jml Item
No Nama Item Rambu Kode Rambu
1 Tikungan ke kiri 18 36 1a
2 Tikungan ke kanan 13 26 1b
3 Jembatan 0 0 3d
4 Turunan 0 0 2a
5 Tanjakan 6 12 2c
6 Turunan Curam 5 10 2b
7 Tanjakan Curam 5 10 2c
Jumlah 84 buah
No. Mata Pembayaran : 8.4.(7)
Mata Pembayaran : Rel Pengaman
Satuan Pembayaran : M1
Panjang
No Km. to Km
(m)
1 2+200 - 2+300 100.00
2 2+275 - 2+325 50.00
3 2+325 - 2+550 225.00
4 2+350 - 2+550 200.00
5 2+600 - 3+100 500.00
6 2+625 - 3+100 475.00
7 4+400 - 4+425 25.00
8 5+050 - 5+175 125.00
9 5+125 - 5+150 25.00
10 6+175 - 6+200 25.00
11 6+450 - 6+550 100.00
12 6+700 - 6+750 50.00
13 6+875 - 6+900 25.00
14 7+100 - 7+125 25.00
15 7+225 - 7+300 75.00
16 7+500 - 7+650 150.00
17 7+275 - 7+775 500.00
18 7+900 - 8+125 225.00
19 8+350 - 8+425 75.00
20 8+525 - 8+700 175.00
21 8+775 - 8+825 50.00
22 9+175 - 9+225 50.00
23 9+525 - 10+700 1,175.00
24 10+825 - 11+050 225.00
25 11+100 - 11+150 50.00
26 11+500 - 11+950 450.00
27 12+025 - 12+050 25.00
28 12+100 - 12+500 400.00
29 12+550 - 12+575 25.00
30 12+700 - 12+725 25.00
31 12+950 - 13+225 275.00
32 13+400 - 13+800 400.00
33 13+825 - 13+900 75.00
34 13+950 - 14+400 450.00
35 14+575 - 14+675 100.00
36 14+800 - 15+000 200.00
37 15+075 - 16+200 1,125.00
38 16+500 - 17+125 625.00
39 17+200 - 17+375 175.00
40 17+450 - 17+675 225.00
41 17+850 - 18+250 400.00
42 19+850 - 21+000 1,150.00
Jumlah 10,825.00
Panjang
No Km. to Km
(m)
1 0+000 - 21+251 21,251.19
2
3
4
5
6
Panjang 21,251.19
Buah 10,625.59
10,626.00
Analisa El - 121
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia setelah menerima SPMK mengusulkan personil
Tenaga Ahli Mutu Pekerjaan sbg Manajer Kendali Mutu
2 Tenaga Ahli dibantu oleh Asisten Kendali Mutu yang
berpengalaman dibidangnya dan tenaga pendukung
3 Membuat RMK dan laporan mutu yg disetujui PPK
4 Melakukan pengendalian mutu semua pekerjaan dan
membuat laporan secara berkala
C. TENAGA / PERSONIL
Catatan : 1. Harga Satuan Personil tersebut sudah termasuk seluruh pajak dan bea (kecuali PPN),
Asuransi Tenaga Kerja dan pengeluaran lainnya.
2. Biaya tersebut sudah termasuk biaya pembuatan laporan yang terkait dengan mutu pekerjaan
3. Biaya satuan tersebut sudah termasuk kebutuhan perlengkapan dan peralatan pendukung yang
diperlukan pembuatan laporan mutu seperti komputer, printer, kertas dan sebagainya.
Analisa El - 18
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan keselamatan jalan selama
periode konstruksi sesuai ketentuan
2 Buat rencana kerja manajemen lalu-lintas sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Kelompok kerja pengatur lalu-lintas selama konstruksi
menggunakan tenaga pengatur dan flagman dengan 3 shift
4 Pengalihan arus lalu-lintas harus ijin PPK dan pihak terkait
5 Semua rambu harus jelas dan terbaca oleh Pengguna Jalan
D. TENAGA / PERSONIL
Catatan : 1. Harga Satuan Personil tersebut sudah termasuk seluruh pajak dan bea (kecuali PPN),
Asuransi Tenaga Kerja dan pengeluaran lainnya.
2. Biaya Satuan tersebut sudah termasuk biaya perlengkapan personil pengatur lalu-lintas dan
biaya perijinan yang diperlukan dengan pihak terkait dengan manajemen lalu-lintas
3. Biaya satuan tersebut sudah termasuk kebutuhan perlengkapan dan peralatan pendukung yang
diperlukan seperti material habis pakai baterai, lampu dan sebagainya
Analisa El - 1201
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN
B. URUTAN KERJA
1 Penyedia memobilisasi peralatan pengeboran kelokasi yang
telah disetujui oleh PPK
2 Pengeboran dilakukan dengan mengambil SPT dan sampel
tanah terganggu (Disturb) dengan interval mak.2 meter atau
setiap ada perubahan strata tanah
3 Benda uji diambil dan dilakukan pengujian laboratorium
Pengeboran dilakukan hingga mencapai tanah keras atau
SPT hingga nilai >40
4 Dibuat laporan hasil pengujian
D. TENAGA/PERSONIL
Estimasi kedalaman boring per titik M 40.00
1 Tenaga Ahli Pengeboran OH 3.00 200,000.00 600,000.00
2 Tenaga Pendukung OH 9.00 100,000.00 900,000.00
3 Mobilisasi dan Demobilisasi Tenaga Ls 1.00 1,500,000.00 1,500,000.00
B. URUTAN KERJA
1 Penyedia memobilisasi peralatan sondir kelokasi yang
telah disetujui oleh PPK
2 Sondir dilakukan untuk mengukur tahanan ujung dan
hambatan akibat gesekan dengan interval 0,20m sampai
tahanan ujung mak.sebesar 250 Kg/Cm2
3 Dibuat laporan hasil pengujian
D. TENAGA/PERSONIL
Estimasi kedalaman boring per titik M 30.00
1 Tenaga Ahli Sondir OH 1.00 200,000.00 200,000.00
2 Tenaga Pendukung OH 4.00 100,000.00 400,000.00
3 Mobilisasi dan Demobilisasi Tenaga Ls 1.00 500,000.00 500,000.00
B. URUTAN KERJA
1 Penyedia menyiapkan perlengkapan pengujian lingkungan
(air, udara dan kebisingan)
2 Buat rencana kerja pengujian lingkungan sesuai schedule
pekerjaan dan koordinasikan dengan seluruh personil yang terkait
3 Pemilihan lokasi pengujian
4 Melaksanakan pengujian
D Biaya Operasional
Biaya peralatan Ls
Personil Ls
Transportasi Ls
Catatan :
Analisa EI-211
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 2.1.(1) PERKIRAAN VOL. PEK. : 19,675.71
JENIS PEKERJAAN : Galian untuk Selokan Drainase dan SaluTOTAL HARGA (Rp.) : 2,122,099,298.93
SATUAN PEMBAYARAN : M3 0 % THD. BIAYA PROYEK : 0.30
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Berat volume bahan D 1.60 Ton/M3
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83 -
Faktor Konversi
Waktu siklus = T1 + T2 Ts1 0.42 menit masuk dalam
- Menggali, memuat dan berputar T1 0.32 menit waktu siklus
- Lain lain T2 0.10 menit disesuaikan dgn
Kap. Prod. / jam = V x Fb x Fa x 60 x Fk Q1 132.33 M3 lapangan
Ts1
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 132.33 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 926.28 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0302 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0076 Jam
Rp. 107,853.74 / M3
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.8 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Perbandingan Pasir & Semen : - Volume Semen Sm 20 % Kuat Tekan min.
: - Volume Pasir Ps 80 % 50 kg/cm2
7 Perbandingan Batu & Mortar :
- Batu Bt 60 %
- Mortar (campuran semen & pasir) Mr 40 %
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.40 ton/M3
- Batu D2 1.60 ton/M3
- Adukan (mortar) D3 1.80 ton/M3
- Pasir D4 1.67 ton/M3
- Semen Portland D5 1.44 ton/M3
1. BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x 1.20 (M02) 1.1 M3 Lepas
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x 1.05 0.1120
x {D5 x (1000)} (M12) 161 Kg
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x 1.05 (M01) 0.4829 M3
2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 Liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4)
- Memuat T1 5.00 menit
- Mengaduk T2 3.00 menit
- Menuang T3 1.00 menit
- Menunggu, dll. T4 1.00 menit
Ts1 10.00 menit
3. TENAGA
Produksi Pas. Batu yang menentukan( Prod. C. Mixer ) Q1 2.49 M3/Jam
Produksi Pasangan Batu dalam 1 hari = Tk x Q1 Qt 17.43 M3
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.4016 jam
- Tukang = (Tk x Tb) : Qt (L02) 1.2048 jam
- Pekerja = (Tk x P) : Qt (L01) 4.0161 jam
Rp. 8,500,025.11 / M3
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 2.2.(1) PERKIRAAN VOL. PEK. : 1,860.99
JENIS PEKERJAAN : Pasangan Batu dengan Mortar TOTAL HARGA (Rp.) : ###
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 2.25
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Berat volume tanah (lepas) D 1.60 ton/m3 1.40 - 1.80
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83
Faktor konversi , kedalaman < 40 % Fv 0.90 Faktor konversi
Waktu siklus Ts1 menit dihapus, masuk
- Menggali , memuat T1 1.320 menit dalam waktu siklus
- Lain lain T2 0.100 menit disesuaikam
Waktu siklus = T1 x Fv Ts1 1.42 menit
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 39.14 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 273.97 M3
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0511 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0256 Jam
Rp. 75,305.13 / M3
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 3.1.(1a) PERKIRAAN VOL. PEK. : 2,239,705.74
JENIS PEKERJAAN : Galian Biasa TOTAL HARGA (Rp.) : 168,661,331,733.97
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 24.03
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Berat volume tanah (lepas) D 1.80 ton/m3
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. COMPRESSOR, EXCAVATOR, JACK HAMMER & LOADER (E05/26/10/15)
EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83
Faktor konversi , kedalaman < 40 % Fv 0.90
Waktu siklus Ts1 menit
- Menggali , memuat T1 4.000 menit
- Lain lain T2 0.100 menit
Waktu siklus = T1 x Fv Ts1 4.10 menit
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 13.56 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 94.89 M3
Kebutuhan tenaga :
- Pekerja P 8.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.5902 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0738 Jam
Rp. 286,800.86 / M3
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 3.1.(2) PERKIRAAN VOL. PEK. : 251,042.38
JENIS PEKERJAAN : Galian Batu TOTAL HARGA (Rp.) : 71,999,171,475.65
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 10.26
A. TENAGA
B. BAHAN
C. PERALATAN
1. Compressor (E05) Jam 0.0738 434,032.64 32,019.36
2. Jack Hammer (E26) Jam 0.0738 87,248.60 6,436.49
3. Wheel Loader (E15) Jam 0.0738 733,803.07 54,133.97
4. Excavator (E10) Jam 0.0738 1,006,338.96 74,239.43
5 Dump Truck (E08) Jam 0.1095 646,970.35 70,866.36
Alat bantu Ls 1.0000 0.00 0.00
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 3.2.(1b) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Timbunan Biasa Dari Galian TOTAL HARGA (Rp.) : 45,621,182,320.32
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 6.50
A. TENAGA
B. BAHAN
Retribusi 1.0000 50,000.00 50,000.00
C. PERALATAN
1. Excavator (E15) Jam 0.0264 733,803.07 19,365.00
2. Dump Truck (E08) Jam 0.0438 646,970.35 28,361.49
3. Motor Grader (E13) Jam 0.0037 964,802.28 3,607.70
4 Vibro Roller (E19) Jam 0.0042 661,824.70 2,768.68
5. Water tank truck (E23) Jam 0.0070 627,884.33 4,412.84
6 Alat Bantu Ls 1.0000 0.00 0.00
I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan (padat ke asli) Fv 1.11 -
6 Tebal hamparan padat t 0.15 M
7 Berat volume bahan (lepas) D 1.60 Ton/M3
8 Retribusi bahan timbunan Ret 5,000.00 Rp
2. ALAT
2.a. EXCAVATOR (E15)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi Alat Fa 0.83 -
Faktor Konversi asli ke padat Fv1 0.90
Waktu sklus Ts1
- Menggali, memuat T1 1.00 menit
- Lain lain T2 0.10 menit
Waktu Siklus = T1 x Fv Ts1 1.10 menit
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 37.89 M3/Jam
Produksi Timbunan / hari = Tk x Q1 Qt 265.25 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1056 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0264 Jam
Rp. 127,678.19 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Faktor pengembangan bahan (padat ke asli) Fv 1.11 -
7 Tebal hamparan padat t 0.15 M
8 Berat volume bahan (lepas) D 1.60 Ton/M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas Bucket V 1.50 M3
Faktor Bucket Fb 0.85 -
Faktor Efisiensi Alat Fa 0.83 -
Waktu sklus Ts1
- Muat T1 1.00 menit
Ts1 1.00 menit
3. TENAGA
Produksi menentukan : DUMP TRUCK Q1 2.34 M3/Jam
Produksi Timbunan / hari = Tk x Q1 Qt 16.38 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 1.7093 Jam
- Mandor = (Tk x M) : Qt (L03) 0.4273 Jam
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 3.2.(2a) PERKIRAAN VOL. PEK. : 46,752.61
JENIS PEKERJAAN : Timbunan Pilihan Dari Sumber Gaian TOTAL HARGA (Rp.) : 38,767,121,420.71
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 5.52
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader (E15) Jam 0.0189 733,803.07 13,868.24
2. Dump Truck (E08) Jam 0.4273 1,126,791.47 481,515.45
3. Motor Grader (E13) Jam 0.0040 964,802.28 3,828.58
3. Tandem (E17) Jam 0.0161 638,979.31 10,290.45
4. Water Tanker (E23) Jam 0.0070 627,884.33 4,412.84
5. Alat Bantu Ls 1.0000 0.00 0.00
I. ASUMSI
1 Pekerjaan dilaksanakan hanya pada tanah galian
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan
4 Kondisi Jalan : jelek / belum padat
5 Jam kerja efektif per-hari Tk 7.00 Jam
2. ALAT
2.a. MOTOR GRADER (E13)
Panjang operasi grader sekali jalan Lh 50.00 M
Lebar Efektif kerja Blade b 2.60 M
Lebae overlap bo 0.30
Faktor Efisiensi Alat Fa 0.80 -
Kecepatan rata-rata alat v 4.00 Km / Jam
Jumlah lintasan n 4.00 lintasan
Jumlah lajur lintasan N 2.00 lajur
Waktu siklus Ts1
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts1 1.75 menit
3. TENAGA
Produksi menentukan : MOTOR GRADER Q1 1,680.00 M2/Jam
Produksi Pekerjaan / hari = Tk x Q1 Qt 11,760.00 M2
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M2
- Pekerja = (Tk x P) : Qt (L01) 0.0024 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0006 Jam
Rp. 1,083.70 / M2
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 3.3.(1) PERKIRAAN VOL. PEK. : 127,507.12
JENIS PEKERJAAN : Penyiapan Badan Jalan TOTAL HARGA (Rp.) : 138,179,895.73
SATUAN PEMBAYARAN : M2 0 % THD. BIAYA PROYEK : 0.02
A. TENAGA
B. BAHAN
C. PERALATAN
1. Motor Grader (E13) jam 0.0006 964,802.28 574.29
2. Vibro Roller (E19) jam 0.0005 661,824.70 311.48
3 Alat Bantu Ls 1.0000 0.00 0.00
I. ASUMSI
1 Menggunakan tenaga pekerja/peralatan
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 1 Pohon diameter 15-30 cm setara dengan volume Vp 2.00 M3
6 Berat Jenis Kayu BjK 0.90 ton/M3
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. DUMP TRUCK (E09)
Kapasitas bak V 10.0 TON
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 20.00 Km/Jam
Kecepatan rata-rata kosong v2 30.00 Km/Jam
Waktu siklus Ts2 menit
- Muat T1 35.00 menit
- Waktu tempuh isi = (L : v1) x 60 T2 0.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 0.00 menit
- Lain-lain T4 10.00 menit
Ts 45.00
3. TENAGA
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 3.4.(2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Pemotongan Pohon Pilihan diameter 15TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : buah % THD. BIAYA PROYEK : 0.00
(Rp.) (Rp.)
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Berat isi padat Bip 1.81 -
7 Jam kerja efektif per-hari Tk 7.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 28.00 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 42.00 % memenuhi Spec.
-Fraksi lolos Scalping Screen 0 - 5 mm PU 30.00 %
10 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
Faktor kehilangan - Agregat A Fh 1.05
1. BAHAN
- Agregat A = 1 M3 x (Bip/Bil) x Fh (M26) 1.25861 M3
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3 (lepas)
Faktor bucket Fb 0.85 - kondisi sedang
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus :
- Memuat dan lain-lain Ts1 0.45 menit panduan
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 117.71 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 823.99 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0595 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0085 Jam
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
5 Tebal lapis Agregat padat t 0.15 M
6 Berat isi padat Bip 1.81
7 Jam kerja efektif per-hari Tk 7.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 18.00 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 18.00 % memenuhi
- Fraksi lolos Scalping Screen 0 - 5 mm St 64.00 % Spesifikasi
10 Berat volume agregat (lepas) Bil 1.51 ton/m3
- Agregat B Fh 1.05
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.85 - Pemuatan lepas
Faktor Efisiensi alat Fa 0.83 - sedang
Waktu siklus Ts1
- Memuat dan lain-lain T1 0.45 menit panduan
ALAT BANTU
diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 117.71 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 823.99 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0595 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0085 Jam
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 4.2.(2a) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 4.2.(1) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
5 Tebal lapis agregat padat t 0.15 M
6 Berat isi padat Bip 1.81
7 Jam kerja efektif per-hari Tk 7.00 jam
8 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 18.00 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 18.00 % memenuhi
- Fraksi lolos Scalping Screen 0 - 5 mm St 64.00 % Spesifikasi
9 Berat volume agregat (lepas) Bil 1.51 ton/m3
Faktor kehilangan - Agregat Pecah Mesin 20 - 30 mm Fh1 1.05
Faktor kehilangan - Agregat Pecah Mesin 5 - 10 & 10 - 20 mm Fh2 1.05
Faktor kehilangan - Fraksi lolos Scalping Screen 0 - 5 mm Fh3 1.05
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.85 - lepas
Faktor Efisiensi alat Fa 0.83 - kondisi sedang
Waktu Siklus : Ts1
- Memuat dan lain-lain T1 0.45 menit panduan
Ts1 0.45 menit
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 117.71 M3/jam
Produksi agregat / hari = Tk x Q1 Qt 823.99 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt - 0.0595 jam
- Mandor = (Tk x M) : Qt - 0.0085 jam
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 4.2.(2b) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas S TOTAL HARGA : 0.00
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader (E15) jam 0.0085 733,803.07 6,233.82
2. Dump Truck (E08) jam 0.3316 646,970.35 214,528.14
3. Motor Grader (E13) jam 0.0043 964,802.28 4,109.54
4. Tandem Roller (E17) jam 0.0054 638,979.31 3,421.58
5. Water Tanker (E23) jam 0.0141 627,884.33 8,825.68
6. Alat Bantu Ls 1.0000 0.00 0.00
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.10 -
6 Komposisi campuran :
- Aspal Pen 60 atau Pen 80 As 56 % 100 bagian
- Kerosene K 44 % 80 bagian
7 Berat jenis bahan :
- Aspal Pen 60 atau Pen 80 D1 1.03 Kg / liter
- Minyak Flux / Pencair D2 0.80 Kg / liter
8 Bahan dasar (aspal & minyak pencair) semuanya
diterima di lokasi pekerjaan
1. BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat
diperlukan : ( 1 liter x Fh ) PC 1.10 liter Campuran
2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 3.00 M
Kecepatan penyemprotan V 30.00 m/menit Asumsi
Kapasitas pompa aspal pas 100 liter/menit Panduan
Faktor effisiensi kerja Fa 0.80 Sedang
3. TENAGA
Produksi menentukan : ASPHALT DISTRIBUTOR Q4 4,800.00 liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 33,600.00 liter
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 2.00 orang
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 4.2.(7) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Resap Pengikat TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
5 Tebal lapis agregat padat t 0.15 M
6 Berat isi padat Bip 1.81 -
7 Jam kerja efektif per-hari Tk 7.00 jam
8 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 28.00 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 42.00 % memenuhi Spec.
- Fraksi lolos Scalping Screen 0 - 5 mm PU 30.00 %
9 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
Faktor kehilangan - Agregat A Fh1 1.05
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3 (lepas)
Faktor bucket Fb 0.85 - kondisi sedang
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus :
- Memuat dan lain-lain Ts1 0.45 menit panduan
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 117.71 M3/jam
Produksi agregat / hari = Tk x Q1 Qt 823.99 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0595 jam
- Mandor = (Tk x M) : Qt (L03) 0.0085 jam
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
5 Tebal lapis agregat padat t 0.15 M
6 Berat isi padat Bip 1.81
7 Jam kerja efektif per-hari Tk 7.00 jam
8 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 18.00 % Gradasi harus
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 22.00 % memenuhi
- Fraksi lolos Scalping Screen 0 - 5 mm St 60.00 % Spesifikasi
9 Berat volume agregat (lepas) Bil 1.51 ton/m3
Faktor kehilangan - Agregat Pecah Mesin 20 - 30 mm Fh1 1.05
Faktor kehilangan - Agregat Pecah Mesin 5 - 10 & 10 - 20 mm Fh2 1.05
Faktor kehilangan - Fraksi lolos Scalping Screen 0 - 5 mm Fh3 1.05
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.85 - lepas
Faktor Efisiensi alat Fa 0.83 - kondisi sedang
Waktu Siklus : Ts1
- Memuat dan lain-lain T1 0.45 menit panduan
Ts1 0.45 menit
3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 117.71 M3/jam
Produksi agregat / hari = Tk x Q1 Qt 823.99 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt - 0.0595 jam
- Mandor = (Tk x M) : Qt - 0.0085 jam
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 5.1.(2) PERKIRAAN VOL. PEK. : 35,064.46
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B TOTAL HARGA : 50,411,028,304.68
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 7.18
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader (E15) jam 0.0085 733,803.07 6,233.82
2. Dump Truck (E08) jam 0.3316 646,970.35 214,528.14
3. Motor Grader (E13) jam 0.0043 964,802.28 4,109.54
4. Tandem Roller (E17) jam 0.0054 638,979.31 3,421.58
5. Water Tanker (E23) jam 0.0141 627,884.33 8,825.68
6. Alat Bantu Ls 1.0000 0.00 0.00
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 5.1.(1) PERKIRAAN VOL. PEK. : 51,427.87
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A TOTAL HARGA : 83,569,892,067.48
SATUAN PEMBAYARAN : M3 % THD. BIAYA PROYEK : 11.91
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader (E15) jam 0.0085 733,803.07 6,233.82
2. Dump Truck (E08) jam 0.3440 646,970.35 222,572.95
3. Motor Grader (E13) jam 0.0043 964,802.28 4,109.54
4. Tandem Roller (E17) jam 0.0134 638,979.31 8,553.94
5. Water Tanker (E23) jam 0.0141 627,884.33 8,825.68
6. Alat Bantu Ls 1.0000 0.00 0.00
7.
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.03 -
6 Komposisi campuran :
- Aspal Emulsi Ae 100 % Bahan Aspal Emulsi
harus memenuhi
7 Berat isi bahan : spesifikasi
- Aspal Emulsi D1 1.01 Kg / liter
1. BAHAN
Untuk mendapatkan 1 liter Lapis Resap Pengikat Aspal Emulsi
diperlukan : ( 1 liter x Fh ) PC 1.03 liter
2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 3.00 M
Kecepatan penyemprotan V 30.00 m/menit Asumsi Panduan
Kapasitas pompa aspal pas 100 liter/menit Sedang
Faktor effisiensi kerja Fa 0.80
3. TENAGA
Produksi menentukan : ASPHALT DISTRIBUTOR Q4 4,800.00 liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 33,600.00 liter
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 2.00 orang
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 6.1 (1)(b) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Resap Pengikat - Aspal Emulsi TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor kehilangan bahan Fh 1.03 -
6 Komposisi campuran :
- Aspal Emulsi Ae 50 % terhadap volume
- Air A 50 % terhadap volume
7 Berat isi bahan :
- Aspal Emulsi D1 1.01 Kg / liter
- Air D2 1.00 Kg / liter
8 Bahan dasar aspal emulsi kationik / anionik
diterima di lokasi pekerjaan
1. BAHAN
Untuk mendapatkan 1 liter Lapis Perekat
diperlukan : ( 1 liter x Fh ) PC 1.03 liter
2. ALAT
2.a. ASPHALT DISTRIBUTOR (E41)
Lebar penyemprotan b 3.00 M
Kecepatan penyemprotan V 30.00 m/menit Asumsi
Kapasitas pompa aspal pas 100 liter/menit Panduan
Faktor effisiensi kerja Fa 0.80 Sedang
Kap. Prod. / jam = pas x Fa x 60 Q1 4,800.00 liter
Koefisien Alat / Ltr = 1 : Q1 (E41) 0.0002 Jam
3. TENAGA
Produksi menentukan : ASPHALT DISTRIBUTOR Q4 4,800.00 liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 33,600.00 liter
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 2.00 orang
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 6.1 (2)(b) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Lapis Perekat - Aspal Emulsi TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : Liter % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
5 Tebal Lapis (AC-WC L) padat t 0.04 M
6 Jam kerja efektif per-hari Tk 7.00 Jam
7 Faktor kehilanganmaterial : - Agregat Fh1 1.05 -
- Aspal Fh2 1.03 -
8 Berat isi Agregat (padat) Bip 1.81 ton/m3
9 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
10 Komposisi campuran AC-WC :
- Agr Pch Mesin 5 - 10 & 10 - 15 mm 5-10&10-15 40.28 % Gradasi harus -
- Agregat Pecah Mesin 0 - 5 mm 0-5 52.68 % memenuhi -
- Semen FF 0.94 % Spesifikasi
- Asphalt As 6.10 %
- Anti Stripping Agent Asa 0.30 %As
11 Berat isi bahan :
- AC-WC D1 2.32 ton / M3
- Agr Pch Mesin 5 - 10 & 10 - 15 mm D2 1.42 ton / M3
- Agr Pch Mesin 0 - 5 mm D3 1.57 ton / M3
12 Jarak Stock pile ke Cold Bin l 0.05 km
1. BAHAN
1.a. Agr 5-10 & 10-15 = ("5-10&10-15" x Fh1) : D2 (M92) 0.2978 M3
1.b. Agr 0-5 = ("0-5" x Fh1) : D3 (M91) 0.3523 M3
1.c. Semen = (FF x Fh1) x 1000 (M05) 9.8700 Kg
1.d. Aspal = (As x Fh2) x 1000 (M10) 62.8300 Kg
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3 panduan
Faktor bucket Fb 0.85 -
Faktor efisiensi alat Fa 0.83 -
Waktu Siklus T1 + T2 + T3 Ts1
- Kecepatan maju rata rata Vf 15.00 km/jam panduan
- Kecepatan kembali rata rata Vr 20.00 km/jam panduan
- Muat ke Bin = (l x 60) / Vf T1 0.20 menit
- Kembali ke Stock pile = (l x 60) / Vr T2 0.15 menit
- Lain - lain (waktu pasti) T3 0.75 menit
Ts1 1.10 menit
3. TENAGA
Produksi menentukan : A M P Q2 49.80 M2 / Jam
Produksi AC-WC / hari = Tk x Q2 Qt 348.60 M2
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 6.3(5a) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN : Laston Lapis Aus (AC-WC) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0.0096 733,803.07 7,023.51
2. AMP E01 Jam 0.0201 19,038,039.64 382,289.95
3. Genset E12 Jam 0.0201 1,097,217.88 22,032.49
4. Dump Truck E08 Jam 0.2813 646,970.35 181,960.41
5. Asp. Finisher E02 Jam 0.0137 661,894.79 9,093.50
6. Tandem Roller E17 Jam 0.0135 638,979.31 8,641.51
7 P. Tyre Roller E18 Jam 0.0058 721,183.66 4,184.63
8 Alat Bantu Ls 1.0000 0.00 0.00
I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : rusak
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 5.75 KM
5 Tebal Lapis (AC) padat t 0.05 M
6 Jam kerja efektif per-hari Tk 7.00 Jam
7 Faktor kehilanganmaterial : - Agregat Fh1 1.05 -
- Aspal Fh2 1.03 -
8 Berat isi Agregat (padat) Bip 1.81 ton/m3
9 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
10 Komposisi campuran AC-BC :
- Agr Pch Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 46.75 % Gradasi harus -
- Agregat Pecah Mesin 0 - 5 mm 0-5 46.75 % memenuhi -
- Semen FF 0.90 % Spesifikasi
- Asphalt As 5.60 %
- Anti Stripping Agent Asa 0.30 %As
11 Berat Isi bahan :
- AC-BC D1 2.32 ton / M3
- Agr Pch Mesin 5 - 10 & 10 - 20 mm D2 1.41 ton / M3
- Agr Pch Mesin 0 - 5 mm D3 1.57 ton / M3
12 Jarak Stock file ke cold bin l 0.05 km
1. BAHAN
1.a. Agr 5-10 & 10-20 = ("5-10&10-20" x Fh1) : D2 (M92) 0.3481 M3
1.b. Agr 0-5 = ("0-5" x Fh1) : D3 (M91) 0.3127 M3
1.c. Semen = (FF x Fh1) x 1000 (M05) 9.4500 Kg
1.d. Aspal = (As x Fh2) x 1000 (M10) 57.6800 Kg
2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.85 -
Faktor efisiensi alat Fa 0.83 -
Waktu Siklus T1 + T2 + T3 Ts1 1.10 menit
- Kecepatan maju rata rata Vf 15.00 km/jam panduan
- Kecepatan kembali rata rata Vr 20.00 km/jam panduan
- Muat ke Bin = (l x 60) / Vf T1 0.20 menit
- Kembali ke Stock pile = (l x 60) / Vr T2 0.15 menit
- Lain - lain (waktu pasti) T3 0.75 menit
Ts1 1.10 menit
3. TENAGA
Produksi menentukan : AMP Q2 49.80 ton
Produksi AC-BC / hari = Tk x Q5 Qt 348.60 ton
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 6.3(6a) PERKIRAAN VOL. PEK. : #NAME?
JENIS PEKERJAAN : Laston Lapis Antara (AC-BC) TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : Ton % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
1. Wheel Loader E15 Jam 0.0096 733,803.07 7,023.51
2. AMP E01 Jam 0.0201 19,038,039.64 382,289.95
3. Genset E12 Jam 0.0201 1,097,217.88 22,032.49
4. Dump Truck E08 Jam 0.2813 646,970.35 181,960.41
5. Asphalt Finisher E02 Jam 0.0110 661,894.79 7,274.80
6. Tandem Roller E17 Jam 0.0108 638,979.31 6,913.21
7 P. Tyre Roller E18 Jam 0.0046 721,183.66 3,347.70
8 Alat Bantu Ls 1.0000 0.00 0.00
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Kadar Semen Minimum Ks 340 Kg/M3
7 Ukuran Agregat Maksimum Ag 19 mm
8 Perbandingan Air/Semen Maksimum Wcr 0.50 -
9 Perbandingan Camp. : Semen Sm 410.0 Kg/M3 Berdasarkan
: Pasir Ps 670.0 Kg/M3 JMF dari EE
: Agregat Kasar Kr 992.0 Kg/M3
10 Berat Isi :
- Beton D1 2.40 T/M3
- Semen D2 1.25 T/M3
- Pasir D3 1.30 T/M3
- Agregat Kasar D4 1.40 T/M3
1. BAHAN
1.a. Semen (PC) = Sm x 1.03 (M12) 422.300 Kg
1.b. Pasir Beton = (Ps/1000 : D3) x 1.05 (M01a) 0.5412 M3
1.c. Agregat Kasar = (Kr/1000 : D4) x 1.05 (M03) 0.7440 M3
1.d. Kayu Perancah dan/atau Bekisting (M19) 0.2000 M3
1.e. Paku (M18) 1.6000 Kg
2. ALAT
2.a. CONCRETE PAN MIXER (BATCHING PLANT) (E43)
Kapasitas Alat V 600.00 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 1.00 menit
- Mengaduk T2 1.00 menit
- Menuang T3 0.50 menit
- Tunggu, dll. T4 0.50 menit
Ts 3.00 menit
3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q1 Qt 69.72 M3
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.1004 jam
- Tukang = (Tk x Tb) : Qt (L02) 1.1044 jam
- Pekerja = (Tk x P) : Qt (L01) 0.8032 jam
Rp. 24,046,349.01 / M3
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. :7.1 (7) a PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN :Beton mutu sedang fc’= 20 MPa TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN :M3 % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Kadar Semen Minimum Ks 250 Kg/M3
1. BAHAN
1.a. Semen (PC) = Sm x 1.03 (M12) 311.060 Kg
1.b. Pasir Beton = (Ps/1000 : D3) x 1.05 (M01a) 0.5113 M3
1.c. Kerikil Pecah = (Kr/1000 : D4) x 1.05 (M03) 0.9053 M3 Agregat Kasar
1.e. Kayu Perancah (M19) 0.0500 M3
1.f Paku (M18) 0.4000 Kg
2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00 liter
Faktor Efisiensi Alat Fa 0.83 -
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 8.00 menit
- Mengaduk T2 4.00 menit
- Menuang T3 2.00 menit
- Tunggu, dll. T4 3.00 menit
Ts 17.00 menit
3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q1 Qt 10.25 M3
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.6827 jam
- Tukang = (Tk x Tb) : Qt (L02) 1.3655 jam
- Pekerja = (Tk x P) : Qt (L01) 1.3655 jam
Rp. 17,744,763.8 / M3
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. :7.1 (10) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN :Beton mutu rendah fc’= 10 Mpa TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN :M3 % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (besi dan kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor Kehilangan Besi Tulangan Fh 1.10 -
1. BAHAN
1.a. Baja Tulangan (Polos) U32 (M57a) 1.1000 Kg
1.b. Kawat beton (M14) 0.0200 Kg
2. ALAT
2.a. ALAT BANTU Ls
Diperlukan :
- Gunting Potong Baja = 2 buah
- Kunci Pembengkok Tulangan = 2 buah
- Alat lainnya
3. TENAGA
Produksi kerja satu hari Qt 200.00 Kg
dibutuhkan tenaga : - Mandor M 1.00 orang
- Tukang Tb 1.00 orang
- Pekerja P 3.00 orang
Koefisien Tenaga / Kg :
- Mandor = ( M x Tk ) : Qt (L03) 0.0350 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 0.0350 jam
- Pekerja = ( P x Tk ) : Qt (L01) 0.1050 jam
Rp. 16,315.45 / Kg
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.3 (2) PERKIRAAN VOL. PEK. : 0.00
JENIS PEKERJAAN :Baja Tulangan U 32 Polos TOTAL HARGA (Rp.) : 0.00
SATUAN PEMBAYARAN : Kg % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Dilakukan secara manual
2 Bahan diterima di lokasi Jembatan
3 Jam kerja efektif per-hari Tk 7.00
1. BAHAN
1.a. Bahan pondasi cerucuk (M52) 1.0000
2. ALAT
2.e. ALAT BANTU
Diperlukan alat bantu untuk pek pondasi cerucuk
- 1 set palu tripot
- Alat pertukangan
3. TENAGA
Produksi Tiang dalam 1 hari Qt 28.00
Rp. 84,369.70 / M1
I. ASUMSI
1 Bahan diterima di lokasi Jembatan
2 Jam kerja efektif per-hari Tk 7.00
3 Diameter tiang pancang kayu sesuai keperluan 200
1. BAHAN
1.a. Bahan tiang pancang kayu tanpa pengawetan (M52) 1.0000
2. ALAT
2.e. ALAT BANTU
- Alat bantu
-
-
3. TENAGA
Produksi Tiang dalam 1 hari Qt 21.00
Kebutuhan tenaga tambahan di lokasi ::
- Mandor M 1.00
- Tukang Tb 2.00
- Pekerja P 10.00
Rp. 106,742.93 / Kg
I. ASUMSI
1 Bahan diterima di lokasi Jembatan
2 Jam kerja efektif per-hari Tk 7.00
3 Diameter tiang pancang kayu sesuai keperluan 200
II. URUTAN KERJA
1 Pekerjaan ini hanya satu tahapan pekerjaan, yaitu
Pengadaan
1. BAHAN
1.a. - Bahan tiang pancang kayu (M52) 1.00
- Bahan pengawet: kreosot 1 liter/M1 0.25
2. ALAT
2.e. ALAT BANTU
- Alat bantu
3. TENAGA
Produksi Tiang dalam 1 hari Qt 21.00
Rp. 108,847.84 / Kg
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di sepanjang jalan
3 Turap baja diterima di base camp
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
4 Jam kerja efektif per-hari Tk 7.00
5 Ukuran dan tipe turap baja sesuai keperluan Uk 600.0
6 Tebal tiang t
7 Berat per-meter tiang b 187.00
8 Panjang Turap Baja (sesuai keperluan) p 12.0
1. BAHAN
1.a. Turap Baja (M52) 1.05
Plat Baja (untuk penyambungan) (M48) 0.21
Kawat Las (untuk sepatu & penyambungan) (M51) 0.05
2. ALAT
2.a. TRAILER (E29)
Kapasitas bak sekali muat V 10.00
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 20.00
Kecepatan rata-rata kosong v2 30.00
Waktu siklus : Ts1
- Waktu tempuh isi = (L : v1 ) x 60 T1 17.25
- Waktu tempuh kosong = (L : v2) x 60 T2 11.50
- Lain-lain (bongkar dan muat) T3 80.00
Ts1 108.75
Kapasitas Produksi / Jam = V x p x Fa x 60 x b Q1 10,275.97
Ts1
3. TENAGA Qt 10.00
Produksi Tiang dalam 1 hari Qt 120.00
Qt 22,440
Kebutuhan tenaga tambahan di lokasi ::
- Mandor M 1.00
- Tukang Tb 4.00
- Pekerja P 12.00
Rp. 39,106.06 / Kg
1. BAHAN
1.a. Pipa baja tiang pancang (M52) 1.05
Plat Baja (untuk penyambungan) (M48) 0.21
2. ALAT
2.a. TRAILER (E29)
Kapasitas bak sekali muat V 12.00
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 20
Kecepatan rata-rata kosong v2 30
Waktu siklus : Ts1
- Waktu tempuh isi = (L : v1 ) x 60 T1 17.25
- Waktu tempuh kosong = (L : v2) x 60 T2 11.50
- Lain-lain (bongkar dan muat) T3 80
Ts1 108.75
3. TENAGA Qt 12.00
Produksi Tiang dalam 1 hari Qt 144.00
Qt 22,320
Kebutuhan tenaga tambahan di lokasi ::
- Mandor M 1.00
- Tukang Tb 4.00
- Pekerja P 12.00
Koefisien Tenaga / kg :
- Mandor = (Tk x M) : Qt (L03) 0.5833
- Tukang = (Tk x Tb) : Qt (L02) 2.3333
- Pekerja = (Tk x P) : Qt (L01) 7.0000
Rp. 227,955.92 / Kg
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi jembatan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
4 Jam kerja efektif per-hari Tk 7.00
4 Ukuran diameter tiang pancang (sesuai keperluan) Uk 500.0
5 Tebal tiang t ??
6 Berat per-meter tiang b 155.00
7 Panjang Tiang (sesuai keperluan) p 12.0
1. BAHAN
1.a. Pipa baja tiang pancang (M52) 1.05
Plat Baja (untuk penyambungan) (M48) 0.21
2. ALAT
2.a. TRAILER (E29)
Kapasitas bak sekali muat V 12.00
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 20
Kecepatan rata-rata kosong v2 30
Waktu siklus : Ts1
- Waktu tempuh isi = (L : v1 ) x 60 T1 17.25
- Waktu tempuh kosong = (L : v2) x 60 T2 11.50
- Lain-lain (bongkar dan muat) T3 80
Ts1 108.75
3. TENAGA Qt 12.00
Produksi Tiang dalam 1 hari Qt 144.00
Qt 22,320
Kebutuhan tenaga tambahan di lokasi ::
- Mandor M 1.00
- Tukang Tb 4.00
- Pekerja P 12.00
Koefisien Tenaga / kg :
- Mandor = (Tk x M) : Qt (L03) 0.5833
- Tukang = (Tk x Tb) : Qt (L02) 2.3333
- Pekerja = (Tk x P) : Qt (L01) 7.0000
Rp. 227,955.92 / Kg
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi jembatan
3 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
4 Jam kerja efektif per-hari Tk 7.00
4 Ukuran diameter tiang pancang (sesuai keperluan) Uk 600.0
5 Tebal tiang t 12.00
6 Berat per-meter tiang b 187.00
7 Panjang Tiang (sesuai keperluan) p 12.0
1. BAHAN
1.a. Pipa baja tiang pancang (M52) 1.05
Plat Baja (untuk penyambungan) (M48) 0.21
2. ALAT
2.a. TRAILER (E29)
Kapasitas bak sekali muat V 10.00
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 20
Kecepatan rata-rata kosong v2 30
Waktu siklus : Ts1
- Waktu tempuh isi = (L : v1 ) x 60 T1 17.25
- Waktu tempuh kosong = (L : v2) x 60 T2 11.50
- Lain-lain (bongkar dan muat) T3 80
Ts1 108.75
3. TENAGA Qt 10.00
Produksi Tiang dalam 1 hari Qt 120.00
Qt 22,440
Kebutuhan tenaga tambahan di lokasi ::
- Mandor M 1.00
- Tukang Tb 4.00
- Pekerja P 12.00
Koefisien Tenaga / kg :
- Mandor = (Tk x M) : Qt (L03) 0.7000
- Tukang = (Tk x Tb) : Qt (L02) 2.8000
- Pekerja = (Tk x P) : Qt (L01) 8.4000
Rp. 269,280.13 / Kg
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Tiang pancang kayu diterima di lokasi jembatan
3 Lokasi pekerjaan : di lokasi jembatan
4 Jam kerja efektif per-hari Tk 7.00
5 Panjang Tiang p 6.00
1. BAHAN
Pemakaian bahan pada pekerjaan penyiapan
material tiang pancang
2. ALAT
3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 15.49
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang Tb 2.00
- Pekerja P 8.00
Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03) 0.4518
- Tukang = ( Tk x Tb ) : Qt (L02) 0.9036
- Pekerja = ( Tk x P ) : Qt (L01) 3.6145
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk 7.00
4 Panjang Tiang p 20.0
5 Pemakaian Kawat las dan alat Las utk penyambungan
termasuk dalam item Penyediaan Tiang Pancang
1. BAHAN
Pemakaian bahan pada pekerjaan penyiapan
material tiang pancang
2. ALAT
3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 46.48
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang Tb 2.00
- Pekerja P 8.00
Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03) 0.1506
- Tukang = ( Tk x Tb ) : Qt (L02) 0.3012
- Pekerja = ( Tk x P ) : Qt (L01) 1.2048
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk 7.00
4 Panjang Tiang p 20.0
5 Pemakaian Kawat las dan alat Las utk penyambungan
termasuk dalam item Penyediaan Tiang Pancang
2. ALAT
3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 46.48
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang Tb 2.00
- Pekerja P 8.00
Koefisien Tenaga / M1 :
- Mandor = ( Tk x M ) : Qt (L03) 0.1506
- Tukang = ( Tk x Tb ) : Qt (L02) 0.3012
- Pekerja = ( Tk x P ) : Qt (L01) 1.2048
I. ASUMSI
1 Bahan diterima di lokasi Jembatan
2 Jam kerja efektif per-hari Tk 7.00
3 Diameter tiang pancang kayu sesuai keperluan …..
1. BAHAN
1.a. Bahan tiang pancang kayu tanpa pengawetan (M52) 1.0000
2. ALAT
2.e. ALAT BANTU
- Alat bantu
-
-
3. TENAGA
Produksi Tiang dalam 1 hari Qt 21.00
Rp. 106,742.93 / Kg
I. ASUMSI
1 Bahan diterima di lokasi Jembatan
2 Jam kerja efektif per-hari Tk 7.00
3 Diameter tiang pancang kayu sesuai keperluan 200
1. BAHAN
1.a. - Bahan tiang pancang kayu (M52) 1.00
- Bahan pengawet: kreosot 1 liter/M1 0.25
2. ALAT
2.e. ALAT BANTU
- Alat bantu
3. TENAGA
Produksi Tiang dalam 1 hari Qt 21.00
Rp. 101,660.34 / Kg
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
5 Jam kerja efektif per-hari Tk 7.00
6 Perbandingan Pasir & Semen : - Volume Semen Sm 25
: - Volume Pasir Ps 75
7 Perbandingan Batu & Mortar :
- Batu Bt 65
- Mortar (campuran semen & pasir) Mr 35
8 Berat Jenis Bahan :
- Pasangan Batu Dengan Mortar D1 2.40
- Batu D2 1.60
- Adukan (mortar) D3 1.80
- Pasir D4 1.30
- Semen Portland D5 1.44
1. BAHAN
1.a. Batu -----> {(Bt x D1 x 1 M3) : D2} x 1.20 (M02) 1.1700
1.b. Semen ----> Sm x {(Mr x D1 x 1 M3} : D3} x 1.05 (M12) 0.1225
x {D5 x (1000)} (M12) 176.00
1.c. Pasir -----> Ps x {(Mr x D1 x 1 M3) : D4} x 1.05 (M01) 0.5088
2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00
Faktor Efisiensi Alat Fa 0.83
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 8.00
- Mengaduk T2 4.00
- Menuang T3 3.00
- Tunggu, dll. T4 2.00
Ts 17.00
PROYEK : 7.9.(1)
JENIS PEKERJAAN : Pasangan Batu
SATUAN PEMBAYARAN : M3 URAIAN ANALIS
3. TENAGA
Produksi menetukan : Produksi Concrete Mxer Q1 1.465
Produksi Pasangan Batu dengan Mortar / hari = Tk x Q1 Qt 10.25
Kebutuhan tenaga : - Mandor M 1.00
- Tukang Batu Tb 2.00
- Pekerja P 8.00
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.6827
- Tukang = (Tk x Tb) : Qt (L02) 1.3655
- Pekerja = (Tk x P) : Qt (L01) 5.4618
Rp. 11,118,168.75 / M3
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu, pasir dan semen) diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
5 Jam kerja efektif per-hari Tk 7.00
6 Adukan encer sebagai pengisi adalah beton K-175 - -
7 Kadar Semen Adukan (Spec.K-175) : - Minimum Ks1 220
: - Maksimum Ks2 300
8 Perbandingan Air/Semen Maksimum (Spec.K-175) Wcr 0.57
9 Perbandingan Adukan (K-175) : Semen Sm 12.5
: Pasir Ps 37.5
: Kerikil Kr 50.0
10 Berat Jenis Material :
- Beton / Pasangan Batu Kosong Diisi Adukan D1 2.40
- Semen D2 1.25
- Pasir D3 1.30
- Kerikil / Batu D4 1.40
11 Perbandingan Batu & Adukan : - Batu Bt 70
- Adukan encer Ae 30
1. BAHAN
1.a. Semen (PC) = {Sm x D1 x Ae x 1000} : 40 (M12) 2.2500
1.b. Pasir = {(Ps x D1) : D3} x Ae x 1.05 (M01) 0.2181
1.c. Agregat Kasar = {(Kr x D1) : D4} x Ae x 1.1 (M03) 0.2829
1.d. Batu Belah = {(Bt x D1) : D4 x 1.1 (M06) 1.3200
2. ALAT
2.a. CONCRETE MIXER (E06)
Kapasitas Alat V 500.00
Faktor Efisiensi Alat Fa 0.83
Waktu siklus : (T1 + T2 + T3 + T4) Ts
- Memuat T1 8.00
- Mengaduk T2 4.00
- Menuang T3 2.00
- Tunggu, dll. T4 3.00
Ts 17.00
3. TENAGA
Produksi Beton dalam 1 hari = Tk x Q1 Qt 10.25
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.6827
- Tukang = (Tk x Tb) : Qt (L02) 2.0482
- Pekerja = (Tk x P) : Qt (L01) 6.8273
Rp. 6,064,933.12 / M3
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (batu dan pasir) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
5 Jam kerja efektif per-hari Tk 7.00
6 Faktor kehilangan material Fh 1.10
1. BAHAN
1.a. Batu Belah (M06) 1.1000
2. ALAT
2.a. ALAT BANTU
Diperlukan :
- Gerobak Dorong = 4 buah
- Palu Batu = 2 buah
3. TENAGA
Produksi pasangan batu kosong dalam 1 hari Qt 8.00
Kebutuhan tenaga : - Mandor M 1.00
- Tukang Tb 2.00
- Pekerja P 6.00
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.8750
- Tukang = (Tk x Tb) : Qt (L02) 1.7500
- Pekerja = (Tk x P) : Qt (L01) 5.2500
Rp. 898,668.04 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bronjong dengan kawat dilapisi galvanis diterima
seluruhnya di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
5 Jam kerja efektif per-hari Tk 7.00
6 Faktor Kehilangan Material Fh 1.10
1. BAHAN
1.a. Bronjong dengan kawat dilapisi galvanis (M15) 15.00
1.b. Batu (M02) 1.1000
2. ALAT
2.a. ALAT BANTU
Diperlukan :
- Tang = 2 buah
- Pemotong kawat = 2 buah
- Palu pemecah batu = 2 buah
3. TENAGA
Produksi pekerjaan per hari Qt 8.00
dibutuhkan tenaga : - Mandor M 1.00
- Tukang Tb 3.00
- Pekerja P 6.00
Koefisien Tenaga / Kg :
- Mandor = ( M x Tk ) : Qt (L03) 0.8750
- Tukang = ( Tb x Tk ) : Qt (L02) 2.6250
- Pekerja = ( P x Tk ) : Qt (L01) 5.2500
Rp. 1,567,009.77 / M3
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.8
5 Jam kerja efektif per-hari Tk 7.00
1. BAHAN
1.a. Pipa d = 8.91 cm Galvanised (MXX) 1.000
2. ALAT
2.a. Alat pertukangan dan lain-lain
3. TENAGA
Produksi pasang Railingk dalam 1 hari
= Tk x Q1 = Qt 25.00
Rp. 54,733 / M1
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan di lokasi jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
5 Jam kerja efektif per-hari Tk 7.00
1. BAHAN
1.a. Marmer 0.750
2. ALAT
2.a. Alat bantu pertukangan
3. TENAGA
Produksi Papan Nama dalam 1 hari
= Tk x Q1 = Qt 1.00
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 7.00
- Tukang = (Tk x Tb) : Qt (L02) 0.00
- Pekerja = (Tk x P) : Qt (L01) 14.00
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.0
5 Faktor pengembangan bahan Fk 1.24
6 Berat volume beton lepas D1 2.40
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. JACK HAMMER & COMPRESSOR (E05 & E26)
Kapasitas bongkar bk 50.00
Faktor efesiensi Fa 0.80
Kapasitas prod/jam = Fa x 60 Q1 0.960
bk
Koefesien alat/M3 = 1 : Q1 1.0417
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 0.96
Produksi Galian / hari = Tk x Q1 Qt 6.72
Kebutuhan tenaga :
- Pekerja P 12.00
- Mandor M 1.00
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 12.5000
- Mandor = (Tk x M) : Qt (L03) 1.0417
Rp. 1,352,673.43 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00
5 Faktor pengembangan bahan Fk 1.20
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. COMPRESSOR, JACK HAMMER & LOADER
Produksi per jam Q1 3.00
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 3.00
Produksi Galian / hari = Tk x Q1 Qt 21.00
Kebutuhan tenaga :
- Pekerja P 16.00
- Mandor M 2.00
No. PAKET KONTRAK : 7.15.(5)
JENIS PEKERJAAN : Pembongkaran Rangka Baja
SATUAN PEMBAYARAN : M2 URAIAN ANALIS
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 5.3333
- Mandor = (Tk x M) : Qt (L03) 0.6667
Rp. 723,684.60 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00
5 Faktor pengembangan bahan Fk 1.20
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. CRANE; Palu; Linggis
Produksi per jam Q1 5.00
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 5.00
Produksi Galian / hari = Tk x Q1 Qt 35.00
Kebutuhan tenaga :
- Pekerja P 10.00
- Mandor M 1.00
PROYEK : 7.15.(6)
JENIS PEKERJAAN : Pembongkaran Balok Baja (Steel Stringers)
SATUAN PEMBAYARAN : M' URAIAN ANALIS
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.0000
- Mandor = (Tk x M) : Qt (L03) 0.2000
Rp. 474,079.91 / M3
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan : di lokasi
3 Jam kerja efektif per-hari Tk 7.00
4 Panjang Tiang p 20.00
5 Ukuran Tiang sesuai keperluan
6 Pemakaian Kawat las dan alat Las utk penyambungan
termasuk dlm item Penyediaan Tiang Pancang Beton
1. BAHAN
Pemakaian bahan pada pekerjaan penyiapan
material tiang pancang
2. ALAT
3. TENAGA
Produksi Tiang dalam 1 hari = Tk x Q1 Qt 46.48
Kebutuhan tenaga tambahan di lokasi ::
- Mandor M 1.00
- Tukang Tb 2.00
- Pekerja P 10.00
Koefisien Tenaga / M3 :
- Mandor = ( Tk x M ) : Qt (L03) 0.1506
- Tukang = ( Tk x Tb ) : Qt (L02) 0.3012
- Pekerja = ( Tk x P ) : Qt (L01) 1.5060
1. BAHAN
1.a. Beton K-250 = {1/4 Phi x (Uk)^2) x 1m (EI-715) 0.5027
1.b. Baja Tulangan = {EI-716 x Mb} (EI-731) 75.3982
1.c. Casing = Phi x Uk 2.5133
2. ALAT
3. TENAGA
Produksi Tiang dalam 1 titik bor = Q1 Qt 603.64
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang T 3.00
- Pekerja P 6.00
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Beton berdasarkan analisa item pekerjaan ybs
3 Baja tulangan berdasarkan analisa item ybs
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
5 Jam kerja efektif per-hari Tk 7.00
6 Panjang Tiang p 12.00
7 Ukuran diameter tiang bor beton Uk 1.00
8 Kebutuhan Baja tulangan Mb 150
1. BAHAN
1.a. Beton K-250 = {1/4 Phi x (Uk)^2) x 1m (EI-715) 0.7854
1.b. Baja Tulangan = {EI-716 x Mb} (EI-731) 117.8097
1.c. Casing = Phi x Uk 3.1416
2. ALAT
3. TENAGA
Produksi Tiang dalam 1 titik bor = Q1 Qt 603.64
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang T 3.00
- Pekerja P 6.00
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Turap Beton Pracetak diterima di Base Camp t 0.07
3 Turap beto dari Base Camp & diangkut ke lokasi pek.
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.75
5 Jam kerja efektif per-hari Tk 7.00
6 Panjang Turap (sesuai kebutuhan) Lt 0.99
7 Ukuran turap (sesuai kebutuhan) Uk 0.30
1. BAHAN
1.a. Turap Beton Pracetak K 350 per-meter persegi (M72) 0.0700
1.b. Joint Sealent (M94) 0.35
1.c. Plat Baja utk Sepatu turap/sambungan (t=12mm) (M48) 15.2681
2. ALAT
2.a TRAILER (untuk angkut ke lokasi pek.) (E29)
Kapasitas bak sekali muat V 20.00
Faktor efisiensi alat Fa 0.83
Kecepatanrata-rata bermuatan v1 20.00
Kecepatan rata-rata kosong v2 30.00
Waktu siklus : Ts1
- Waktu tempuh isi = (L : v1 ) x 60 T1 17.25
- Waktu tempuh kosong = (L : v2) x 60 T2 11.50
- Lain-Lain (tunggu, bongkar dan muat) T3 5.00
Ts1 33.75
Ts2 15.00
Ts2 12.00
3. TENAGA Qt 116.90
Untuk pemasangan dalam 1 hari Qt 115.76
Qt 8.18
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang (kayu & besi) Tb 1.00
- Pekerja P 5.00
Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 0.8554
- Tukang = (Tk x Tb) : Qt (L02) 0.8554
- Pekerja = (Tk x P) : Qt (L01) 4.2772
Rp. 2,413,766.21 / M3
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan diatas air/sungai
3 Menggunakan ponton ditarik tag boat
4 Pengangkutan tiang pancang menggunakan crane
5 Jam kerja efektif per-hari Tk 7.00
6 Panjang Tiang sesuai kebutuhan
7 Ukuran diameter tiang pancang sesuai kebutuhan
1. BAHAN
2. ALAT
3. TENAGA
Produksi Tiang dalam 1 titik bor = Q1 Qt 6.27
Kebutuhan tenaga tambahan di lokasi :
- Mandor M 1.00
- Tukang T 2.00
- Pekerja P 6.00
I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan diatas air/sungai
3 Menggunakan ponton ditarik tag boat
4 Pengangkutan tiang pancang menggunakan crane
5 Jam kerja efektif per-hari Tk 7.00
6 Panjang Tiang sesuai kebutuhan
7 Ukuran diameter tiang pancang sesuai kebutuhan
2. ALAT
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.0
5 Faktor pengembangan bahan Fk 1.24
6 Berat volume beton lepas D1 2.40
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. JACK HAMMER ( E26)
Kapasitas bongkar bk 60.00
Faktor efesiensi Fa 0.83
Kapasitas prod/jam = Fa x 60 Q1 0.830
bk
Koefesien alat/M3 = 1 : Q1 1.2048
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 0.83
Produksi Galian / hari = Tk x Q1 Qt 5.81
Kebutuhan tenaga :
- Pekerja P 8.00
- Mandor M 1.00
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 9.6386
- Mandor = (Tk x M) : Qt (L03) 1.2048
Rp. 707,535.08 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00
5 Faktor pengembangan bahan Fk 1.20
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. COMPRESSOR, JACK HAMMER & LOADER
Produksi per jam Q1 5.00
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 5.00
Produksi Galian / hari = Tk x Q1 Qt 35.00
Kebutuhan tenaga :
- Pekerja P 12.00
- Mandor M 1.00
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.4000
- Mandor = (Tk x M) : Qt (L03) 0.2000
Rp. 618,742.54 / M3
6. WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan : . . . . . . . . . . . . bulan
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.00
5 Faktor pengembangan bahan Fk 1.20
2. ALAT
2.a. ASPAL CUTTER, COMPRESSOR, JACK HAMMER & LOADER
Produksi per jam Q1 20.00
3. TENAGA
Produksi menentukan : JACK HAMMER Q1 20.00
Produksi Galian / hari = Tk x Q1 Qt 140.00
Kebutuhan tenaga :
- Pekerja P 12.00
- Mandor M 1.00
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.6000
- Mandor = (Tk x M) : Qt (L03) 0.0500
Rp. 245,362.57 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.0
5 Faktor pengembangan bahan Fk 1.10
6 Berat volume kayu D1 1.50
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. JACK HAMMER ( E26)
Kapasitas bongkar bk
Faktor efesiensi Fa
Kapasitas prod/jam = Fa x 60 Q1
bk
Koefesien alat/M3 = 1 : Q1
3. TENAGA
Produksi menentukan : alat bantu Q3 3.48
Produksi Galian / hari = Tk x Q1 Qt 24.33
Kebutuhan tenaga :
- Pekerja P 8.00
- Mandor M 1.00
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.3013
- Mandor = (Tk x M) : Qt (L03) 0.2877
Rp. 266,476.99 / M3
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : sedang / baik
4 Jam kerja efektif per-hari Tk 7.0
5 Faktor pengembangan bahan Fk 1.10
6 Berat volume kayu D1 1.50
1. BAHAN
Tidak ada bahan yang diperlukan
2. ALAT
2.a. Mesin potong kayu (chainsaw)
Memotong diperkirakan = 0.50 jam per m2 0.50
3. TENAGA
Produksi menentukan : alat bantu Q3 3.80
Produksi Galian / hari = Tk x Q1 Qt 26.63
Kebutuhan tenaga :
- Pekerja P 8.00
- Mandor M 1.00
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 2.1025
- Mandor = (Tk x M) : Qt (L03) 0.2628
Rp. 492,677.93 / M3
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
jam PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (1)
JENIS PEKERJAAN : Fondasi Cerucuk Penyedian da
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
M1
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
Lumpsum
B. BAHAN
M1 1. Cerucuk M61
orang
orang
orang
C. PERALATAN
1 Alat Bantu
jam
jam
jam
Analisa EI-762
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
jam #NAME?
MM PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (2)
JENIS PEKERJAAN :Dinding Turap Kayu Tanpa Pen
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
M1
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
Lumpsum
JUMLAH HARGA TEN
B. BAHAN
M1 1. Cerucuk M61
orang
orang
orang
JUMLAH HARGA BA
C. PERALATAN
1. Alat Bantu
jam
jam
jam
Analisa EI-763
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
jam #NAME?
MM PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (3)
JENIS PEKERJAAN : Dinding Turap Kayu Dengan P
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
M1
liter A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
Lumpsum
JUMLAH HARGA TEN
B. BAHAN
orang
orang
orang
JUMLAH HARGA BA
C. PERALATAN
1. Alat Bantu
jam
jam
jam
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
Km ITEM PEMBAYARAN NO. : 7.6 (4)
jam JENIS PEKERJAAN : Dinding Turap Baja
mm SATUAN PEMBAYARAN : M1
mm
kg
M
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
Kg
Kg B. BAHAN
Dos
1. Turap baja M52
2. Plat Baja M48
3. Kawat Las M51
batang
Km/Jam
Km/Jam
menit C. PERALATAN
menit
menit 1. Trailer E29
menit 2. Crane 1 E07
3. Crane 2 E07
M' 4. Welding Set E32
Kg 5. Alat Bantu
Jam
batang
- D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT
menit F. HARGA SATUAN PEKERJAAN ( D + E )
menit Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
menit berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
M' dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
jam 3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
SATUAN KETERANGAN
batang
-
menit
menit
menit
M'
jam
M
jam
M/Jam
Lumpsum
batang
M
Kg
orang
orang
orang
jam
jam
jam
Analisa EI-768a
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
Km PROP / KAB / KODYA : Papua Barat/Raja Ampat
jam ITEM PEMBAYARAN NO. : 7.6 (8) a
mm JENIS PEKERJAAN :Penyediaan Tiang Pancang Ba
mm SATUAN PEMBAYARAN : M1
kg
M
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
batang
Km/Jam
Km/Jam JUMLAH HARGA BA
menit C. PERALATAN
menit
menit 1. Trailer E29
menit 2. Crane E07
3. Welding Set E32
Kg 4 Alat Bantu
Jam
M
jam
jam
SATUAN KETERANGAN
Lumpsum
batang
M
Kg
orang
orang
orang
jam
jam
jam
Analisa EI-768b
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
Km PROP / KAB / KODYA : Papua Barat/Raja Ampat
jam ITEM PEMBAYARAN NO. : 7.6 (8) b
mm JENIS PEKERJAAN : Penyediaan Tiang Pancang Ba
mm SATUAN PEMBAYARAN :M1
kg
M
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
batang
Km/Jam
Km/Jam JUMLAH HARGA BA
menit C. PERALATAN
menit
menit 1. Trailer E29
menit 2. Crane E07
3. Welding Set E32
Kg 4 Alat Bantu
Jam
M
jam
jam
SATUAN KETERANGAN
Lumpsum
batang
M
Kg
orang
orang
orang
jam
jam
jam
Analisa EI-768c
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
Km PROP / KAB / KODYA : Papua Barat/Raja Ampat
jam ITEM PEMBAYARAN NO. : 7.6 (8) c
mm asumsi JENIS PEKERJAAN : Penyediaan Tiang Pancang Ba
mm SATUAN PEMBAYARAN : M1
kg
M
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
Km/Jam
Km/Jam JUMLAH HARGA BA
menit C. PERALATAN
menit
menit 1. Trailer E29
menit 2. Crane E07
3. Welding Set E32
Kg 4 Alat Bantu
Jam
M
jam
jam
SATUAN KETERANGAN
Lumpsum
batang
M
Kg
orang
orang
orang
jam
jam
jam
Analisa EI-7613
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
jam ITEM PEMBAYARAN NO. : 7.6 (13)
M JENIS PEKERJAAN : Pemancangan Tiang Pancang
SATUAN PEMBAYARAN :M1
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
Titik
-
menit
menit
menit
menit
JUMLAH HARGA BA
M1
C. PERALATAN
Jam
1. Pile Driver E30
2. Alat Bantu
Lumpsum
M'
JUMLAH HARGA PERALA
orang
orang D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
orang E. OVERHEAD & PROFIT
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
jam berat untuk bahan-bahan.
jam 2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
jam dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
SATUAN KETERANGAN
Analisa EI-7614a
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
jam PROP / KAB / KODYA : Papua Barat/Raja Ampat
M ITEM PEMBAYARAN NO. : 7.6 (14) a
JENIS PEKERJAAN : Pemancangan Tiang Pancang
SATUAN PEMBAYARAN :M1
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
Titik
-
menit
menit
menit
menit
JUMLAH HARGA BA
M1/jam
C. PERALATAN
Jam
1. Pile Driver E30
2. Alat Bantu
Lumpsum
SATUAN KETERANGAN
Analisa EI-7614b
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
jam PROP / KAB / KODYA : Papua Barat/Raja Ampat
M ITEM PEMBAYARAN NO. : 7.6 (14) b
JENIS PEKERJAAN : Pemancangan Tiang Pancang
SATUAN PEMBAYARAN :M1
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
Titik
-
menit
menit
menit
menit
JUMLAH HARGA BA
M1/jam
C. PERALATAN
Jam
1. Pile Driver E30
2. Alat Bantu
Lumpsum
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
jam #NAME?
MM PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (6)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Ka
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
M1
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
Lumpsum
JUMLAH HARGA TEN
B. BAHAN
M1 1. Cerucuk M61
orang
orang
orang
JUMLAH HARGA BA
C. PERALATAN
1. Alat Bantu
jam
jam
jam
Analisa EI-766
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
jam #NAME?
MM PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (7)
JENIS PEKERJAAN : Penyediaan Tiang Pancang Ka
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
M1
liter A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
Lumpsum
JUMLAH HARGA TEN
B. BAHAN
orang
orang
orang
JUMLAH HARGA BA
C. PERALATAN
1. Alat Bantu
jam
jam
jam
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.9.(1)
KM JENIS PEKERJAAN : Pasangan Batu
jam SATUAN PEMBAYARAN : M3
% Spec.
% Spec.
% NO. KOMPONEN
%
ton/M3
ton/M3 A. TENAGA
ton/M3
ton/M3 1. Pekerja Biasa (L01)
ton/M3 2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
M3 Lepas
M3
Kg
M3 C. PERALATAN
menit
menit
menit
menit
menit
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
M3 E. OVERHEAD & PROFIT
F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
jam berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
M3 terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
M3 3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
- 4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
liter/menit yang dibayar dari kontrak) dan biaya-biaya lainnya.
M3
jam
SATUAN KETERANGAN
M3/Jam
M3
orang
orang
orang
jam
jam
jam
Analisa EI-7101
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.10 (1)
KM JENIS PEKERJAAN : Pasangan Batu Kosong Yang D
jam SATUAN PEMBAYARAN : M3
- Spec.
Kg/M3 Spec.
Kg/M3 Spec.
- Spec. NO. KOMPONEN
%
%
%
A. TENAGA
T/M3
T/M3 1. Pekerja Biasa (L01)
T/M3 2. Tukang (L02)
T/M3 3. Mandor (L03)
%
%
B. BAHAN
Zak
M3 C. PERALATAN
M3 Agregat Kasar
M3 1. Conc. Mixer (E06)
2. Water Tanker (E23)
3. Alat Bantu
liter
-
menit
menit
menit
menit D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
menit E. OVERHEAD & PROFIT
F. HARGA SATUAN PEKERJAAN ( D + E )
M3 Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
jam dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
M3 4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
M3 yang dibayar dari kontrak) dan biaya-biaya lainnya.
-
liter/menit
M3
jam
SATUAN KETERANGAN
M3
orang
orang
orang
jam
jam
jam
Analisa LI-7102
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.10 (2)
KM JENIS PEKERJAAN : Pasangan Batu Kosong
jam SATUAN PEMBAYARAN : M3
-
NO. KOMPONEN
A. TENAGA
jam
jam
jam C. PERALATAN
1. Alat Bantu
Analisa LI-7103a
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.10.(3) a.
KM JENIS PEKERJAAN : Bronjong dengan kawat yang d
jam SATUAN PEMBAYARAN : M3
-
NO. KOMPONEN
A. TENAGA
B. BAHAN
M3
orang
orang C. PERALATAN
orang
1. Alat Bantu
jam
jam
jam
Analisa EI-713
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.13.(1)
KM JENIS PEKERJAAN : Sandaran (Railing)
jam SATUAN PEMBAYARAN : M1
NO. KOMPONEN
A. TENAGA
M 1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
M
1. Pipa d = 8.91 cm Galvanised
2. Dudukan, mur, baut dll
orang
orang JUMLAH HARGA BA
orang
C. PERALATAN
jam
jam 1. Alat bantu
jam
Analisa EI-7141
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.14.(1)
KM JENIS PEKERJAAN : Papan Nama Jembatan
jam SATUAN PEMBAYARAN : buah
NO. KOMPONEN
A. TENAGA
M2 1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
Buah
1. Marmer
2. Adukan Semen
orang
orang JUMLAH HARGA BA
orang
C. PERALATAN
jam
jam 1. Alat bantu
jam
Analisa EI-7152
URAIAN ANALISA HARGA SATUAN FORMULIR STANDAR UNT
PEREKAMAN ANALISA MASING-MASING
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
Jam ITEM PEMBAYARAN NO. : 7.15.(2)
- JENIS PEKERJAAN : Pembongkaran Beton
Ton/M3 SATUAN PEMBAYARAN : M3
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
Menit/M3 (padat)
B. BAHAN
M3
jam
M3
Menit
M3 (padat) C. PERALATAN
1. Compressor E05
jam 2. Jack Hammer E26
3. Wheel Loader E15
4. Dump Truck E08
M3 5 Alat bantu
-
KM/Jam
KM/Jam
menit
menit
menit
menit D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
menit E. OVERHEAD & PROFIT
menit F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
berat untuk bahan-bahan.
M3 padat 2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
Jam 4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
Lump Sump
SATUAN KETERANGAN
M3/Jam
M3
orang
orang
Jam
Jam
Analisa EI-7155
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Bar
Jam ITEM PEMBAYARAN NO. : 7.15.(5)
- JENIS PEKERJAAN : Pembongkaran Rangka Baja
SATUAN PEMBAYARAN : M2
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
B. BAHAN
(E05/26/10/15)
M2 / Jam
Jam
M3
- C. PERALATAN
KM/Jam 1. Compressor E05
KM/Jam 2. Jack Hammer E26
menit 3. Wheel Loader E15
menit 4. Dump Truck E08
menit 5 Alat bantu
menit
menit
menit
M3 / Jam
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT
F. HARGA SATUAN PEKERJAAN ( D + E )
Jam Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
Lump Sump dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
M3/Jam
M3
orang
orang
Berlanjut ke halaman berikut
Analisa EI-7155
SATUAN KETERANGAN
Jam
Jam
Analisa EI-7156
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
Jam ITEM PEMBAYARAN NO. : 7.15.(6)
- JENIS PEKERJAAN : Pembongkaran Balok Baja (Ste
SATUAN PEMBAYARAN : M'
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
B. BAHAN
(E05/26/10/15)
M / Jam
Jam
TON
- C. PERALATAN
KM/Jam 1. Crane E07
KM/Jam 2. Trailer 20 ton E29
menit 3. Alat bantu
menit
menit
menit
menit
menit
M3 / Jam
D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
E. OVERHEAD & PROFIT
F. HARGA SATUAN PEKERJAAN ( D + E )
Jam Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
Lump Sump dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
M3/Jam
M3
orang
orang
SATUAN KETERANGAN
Jam
Jam
Analisa EI-7616
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
jam PROP / KAB / KODYA : Papua Barat/Raja Ampat
M ITEM PEMBAYARAN NO. : 7.6 (16)
JENIS PEKERJAAN : Pemancangan Tiang Pancang
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
Titik
-
menit
menit
menit
menit JUMLAH HARGA BA
M1/jam C. PERALATAN
SATUAN KETERANGAN
Analisa EI-7619a
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
KM ITEM PEMBAYARAN NO. : 7.6 (19) a
jam JENIS PEKERJAAN :Tiang Bor Beton, diameter 800
M SATUAN PEMBAYARAN : M1
M
Kg/M3
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
M1
Jam
JUMLAH HARGA PERALA
Lumpsum
SATUAN KETERANGAN
M'/jam
orang
orang
orang
jam
jam
jam
Analisa EI-7619b
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
KM ITEM PEMBAYARAN NO. : 7.6 (19) b
jam JENIS PEKERJAAN :Tiang Bor Beton, diameter …..
M SATUAN PEMBAYARAN : M1
M asumsi
Kg/M3
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
M1
Jam
JUMLAH HARGA PERALA
Lumpsum
SATUAN KETERANGAN
M'/jam
orang
orang
orang
jam
jam
jam
Analisa EI-765
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
m PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (5)
KM JENIS PEKERJAAN :Dinding Turap Beton
jam SATUAN PEMBAYARAN : M1
M
M
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
M3
Kg B. BAHAN
Kg
1. Beton Pracetak K 350 (M72)
2. Joint Sealent (M94)
3. Plat Baja M48
Ton
Km/Jam
Km/Jam C. PERALATAN
M2 BJ Beton kira2
M3 2.4 T/m3
Jam
M2
-
menit
menit
menit
M1
Jam
Lumpsum
Berlanjut ke hal. berikut.
Analisa EI-765
SATUAN KETERANGAN
M2
M3
M3
orang
orang
orang
jam
jam
jam
Analisa EI-7620
7.6.(18) bila Tiang Pancang dikerjakan
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (20)
jam JENIS PEKERJAAN : Tambahan Biaya untuk Nomor
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
B. BAHAN
M'
M'
Jam
Lanjutan
SATUAN KETERANGAN
Jam
Lumpsum
M'/jam
orang
orang
orang
jam
jam
jam
Analisa EI-7624
Tiang Bor Beton dikerjakan
SATUAN KETERANGAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.6 (21)
jam JENIS PEKERJAAN : Tambahan Biaya untuk Nomor
SATUAN PEMBAYARAN : M1
NO. KOMPONEN
A. TENAGA
1. Pekerja (L01)
2. Tukang (L02)
3. Mandor (L03)
M3 JUMLAH HARGA TEN
B. BAHAN
M'
M'
Jam
Lanjutan
SATUAN KETERANGAN
Jam
Lumpsum
M'/jam
orang
orang
orang
jam
jam
jam
Analisa EI-7151
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
Jam ITEM PEMBAYARAN NO. : 7.15.(1)
- JENIS PEKERJAAN :Pembongkaran Pasangan Batu
Ton/M3 SATUAN PEMBAYARAN : M3
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
Menit/M3 (padat)
B. BAHAN
M3
jam
M3
Menit
M3 (padat) C. PERALATAN
SATUAN KETERANGAN
Lump Sump
M3/Jam
M3
orang
orang
Jam
Jam
Analisa EI-7153
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencana
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.15.(3)
Jam JENIS PEKERJAAN :Pembongkaran Beton Pratekan
- SATUAN PEMBAYARAN : M3
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
B. BAHAN
(E05/26/10/15)
M3 / Jam
Jam
M3 C. PERALATAN
- 1. Compressor E05
KM/Jam 2. Jack Hammer E26
KM/Jam 3. Wheel Loader E15
menit 4. Dump Truck E08
menit 5 Alat bantu
menit
menit
menit
menit
SATUAN KETERANGAN
Lump Sump
M3/Jam
M3
orang
orang
Jam
Jam
Analisa EI-7154
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencana
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 7.15 (4)
Jam JENIS PEKERJAAN : Pembongkaran Bangunan Ged
- SATUAN PEMBAYARAN : M2
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
B. BAHAN
(E05/26/10/15)
M3 / Jam
Jam
M3 C. PERALATAN
- 1. Compressor E05
KM/Jam 2. Jack Hammer E26
KM/Jam 3. Wheel Loader E15
menit 4. Dump Truck E08
menit 5 Alat bantu
menit
menit
menit
menit
SATUAN KETERANGAN
Lump Sump
M3/Jam
M3
orang
orang
Jam
Jam
Analisa EI-7151
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
Jam ITEM PEMBAYARAN NO. : 7.15 (7)
- JENIS PEKERJAAN : Pembongkaran Lantai Jembata
Ton/M3 SATUAN PEMBAYARAN : M2
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
Menit/M3 (padat)
B. BAHAN
M3
jam
M3
Menit
M3 (padat) C. PERALATAN
SATUAN KETERANGAN
Lump Sump
M3/Jam
M3
orang
orang
Jam
Jam
Analisa EI-7151
SATUAN KETERANGAN
PROYEK
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WI
NAMA PAKET : Perencanaan Pembangunan J
#NAME?
PROP / KAB / KODYA : Papua Barat/Raja Ampat
Jam ITEM PEMBAYARAN NO. : 7.15 (8)
- JENIS PEKERJAAN : Pembongkaran Jembatan Kay
Ton/M3 SATUAN PEMBAYARAN : M2
NO. KOMPONEN
Km
A. TENAGA
1. Pekerja (L01)
2. Mandor (L03)
jam
B. BAHAN
M2
-
menit
menit
menit
menit
(padat) C. PERALATAN
jam 1 Chain Saw E07
2 Crane E07
3 Dump Truck E08
M3 4 Alat bantu
-
KM/Jam
KM/Jam
menit
menit
menit
menit D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )
menit E. OVERHEAD & PROFIT
menit F. HARGA SATUAN PEKERJAAN ( D + E )
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan P
berat untuk bahan-bahan.
M3 padat 2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk men
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis
Jam 4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berk
yang dibayar dari kontrak) dan biaya-biaya lainnya.
SATUAN KETERANGAN
Lump Sump
M3/Jam
M3
orang
orang
Jam
Jam
Analisa EI-761
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
Analisa EI-762
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 92,819.94
15.0 % x D 13,922.99
106,742.93
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
Analisa EI-763
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 94,650.30
15.0 % x D 14,197.54
108,847.84
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 34,005.27
15.0 % x D 5,100.79
39,106.06
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
PERALATAN ( A + B + C ) 198,222.53
15.0 % x D 29,733.38
227,955.92
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 198,222.53
15.0 % x D 29,733.38
227,955.92
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 234,156.63
15.0 % x D 35,123.50
269,280.13
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 182,834.70
15.0 % x D 27,425.20
210,259.90
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 60,944.90
15.0 % x D 9,141.73
70,086.63
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 60,944.90
15.0 % x D 9,141.73
70,086.63
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 92,819.94
15.0 % x D 13,922.99
106,742.93
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
Analisa EI-767
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 88,400.30
15.0 % x D 13,260.04
101,660.34
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 5,273,854.88
15.0 % x D 791,078.23
6,064,933.12
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 781,450.47
15.0 % x D 117,217.57
898,668.04
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
Analisa LI-7103a
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 1,362,617.19
15.0 % x D 204,392.58
1,567,009.77
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 47,593.75
15.0 % x D 7,139.06
54,732.81
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
Analisa EI-7141
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 443,281.25
15.0 % x D 66,492.19
509,773.44
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
Analisa EI-7152
FORMULIR STANDAR UNTUK
N ANALISA MASING-MASING HARGA SATUAN
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 1,176,237.76
15.0 % x D 176,435.66
1,352,673.43
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 629,290.96
15.0 % x D 94,393.64
723,684.60
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 412,243.40
15.0 % x D 61,836.51
474,079.91
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 65,725.18
15.0 % x D 9,858.78
75,583.96
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
PERALATAN ( A + B + C ) 11,212,440.17
15.0 % x D 1,681,866.03
12,894,306.20
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 17,511,407.50
15.0 % x D 2,626,711.12
20,138,118.62
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
: Papua Barat/Raja Ampat
PERKIRAAN VOL. PEK. : 0.00
:Dinding Turap Beton TOTAL HARGA (Rp.) : 0.00
% THD. BIAYA PROYEK : 0.00
PERALATAN ( A + B + C ) 2,098,927.14
15.0 % x D 314,839.07
2,413,766.21
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 7,377.73
15.0 % x D 1,106.66
8,484.39
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PERALATAN ( A + B + C ) 30,658.27
15.0 % x D 4,598.74
35,257.01
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 615,247.90
15.0 % x D 92,287.18
707,535.08
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 538,036.99
15.0 % x D 80,705.55
618,742.54
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 213,358.76
15.0 % x D 32,003.81
245,362.57
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
: Papua Barat/Raja Ampat
PERKIRAAN VOL. PEK. : 0.00
: Pembongkaran Lantai Jembatan Kayu TOTAL HARGA (Rp.) : 266,476.99
% THD. BIAYA PROYEK : 0.00
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 231,719.12
15.0 % x D 34,757.87
266,476.99
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
: 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
: Perencanaan Pembangunan Jalan Wilayah Raja Ampat
(Rp.) (Rp.)
PERALATAN ( A + B + C ) 428,415.60
15.0 % x D 64,262.34
492,677.93
asi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
I. ASUMSI
1 Menggunakan tenaga pekerja
2 Lokasi pekerjaan : di sepanjang jalan
3 Bahan dasar pohon dan bahan lainnya diterima di lokasi pekerjaan
4 ukuran lubang 0,5 x 0,5 x 0,5 m
1. BAHAN
1.a. - pohon (M32) 1.00 bh
1.b. - Tanah humus setebal 20 cm mxx 0.22 m3
1.c. - Pupuk mxx 0.50 kg
2. ALAT
2.a. ALAT BANTU
- Pacul/sekop = 4 buah
- Gerobak Dorong = 1 buah
- Pagar Bambu/kayu = sesuai kebutuhan
3. TENAGA
Produksi penanaman rumput dalam 1 hari Qt 100.00 M2
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 0.00 orang
- Pekerja P 6.00 orang
Koefisien Tenaga / M2 :
- Mandor = (Tk x M) : Qt (L03) 0.0700 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.0000 jam
- Pekerja = (Tk x P) : Qt (L01) 0.4200 jam
Rp. 14,233.05 / bh
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 8.3.(3) PERKIRAAN VOL. PEK. : 851.00
JENIS PEKERJAAN : Pohon TOTAL HARGA (Rp.) : 12,112,322.89
SATUAN PEMBAYARAN : Buah % THD. BIAYA PROYEK : 0.00
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Pekerjaan dilakukan secara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (besi dan kawat) diterima seluruhnya
di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.8 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor Kehilangan Material Fh 1.05 -
7 Tebal lapisan cat secara manual t 0.015 M Spec.10.4.3(2)(d)
8 Berat Jenis Bahan Cat BJ.Cat 1.00 Kg/Liter
9 Perbandingan pemakaian bahan : - Cat C 65 %
- Thinner T 35 %
II. URUTAN KERJA
1 Permukaan jalan dibersihkan dari debu/kotoran
2 Cat disemprotkan dengan Compressor di atas maal
tripleks yang dipasang di permukaan jalan
3 Glass Beat ditaburkan segera setelah cat marka selesai
disemprotkan
1. BAHAN
1.a. Cat Marka Thermoplastic = C x R x (BJ.Cat) (M17b) 1.9500 Kg
1.b. Minyak Pencair (Thinner) = TxR (M33) 1.0500 Liter
1.c. Glass Bead (M34) 0.4500 Kg
2. ALAT
2.a. COMPRESSOR (E05)
Kapasitas penyemprotan V 40.00 Ltr/Jam
Jumlah cat cair = (1 M x 1 M) x t x 1000 R 3.00 Ltr/M2
3. TENAGA
Produksi pekerjaan per hari = Q1 x Tk Qt 93.33 M2
dibutuhkan tenaga : - Mandor M 1.00 orang
- Tukang Cat Tb 3.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M2 :
- Mandor = ( M x Tk ) : Qt (L03) 0.0750 jam
- Tukang = ( Tb x Tk ) : Qt (L02) 0.2250 jam
- Pekerja = ( P x Tk ) : Qt (L01) 0.6000 jam
Rp. 298,244.44 / M2
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 8.4.(1) PERKIRAAN VOL. PEK. : 5,056.10
JENIS PEKERJAAN : Marka Jalan Termoplastik TOTAL HARGA (Rp.) : 1,507,953,660.23
SATUAN PEMBAYARAN : M2 % THD. BIAYA PROYEK : 0.21
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (plat rambu jadi, pipa dan beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.8 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
1. BAHAN
1.a. Pelat Rambu Jadi (Engineering Grade) (M35a) 2.00 BH
1.b. Pipa Galvanis Dia.1,6" (M24) 1.00 Batang
1.c. Beton K-175 (M60) 0.016 M3
1.d. Cat, dan bahan lainnya - 1.0000 Ls
2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.0 Buah
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 30.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 27.6 menit
- Menurunkan = Rata-rata 2.5 menit / buah T3 37.5 menit
- Lain-lain = geser, atur, tunggu, dll. T4 30.0 menit
Ts 125.1 menit
3. TENAGA
Produksi pemasangan rambu dalam 1 hari = Tk x Q1 Qt 50.36 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 3.00 orang
- Pekerja P 6.00 orang
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.1390 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.4170 jam
- Pekerja = (Tk x P) : Qt (L01) 0.8340 jam
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 8.4.(3) .(b) PERKIRAAN VOL. PEK. : 84.00
JENIS PEKERJAAN : Rambu Jalan Ganda dengan PermukaaTOTAL HARGA (Rp.) : 124,930,581.93
SATUAN PEMBAYARAN : BH % THD. BIAYA PROYEK : 0.02
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (patok kilometer beton cetak)
diangkut dengan Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.8 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
7 Tulangan praktis Rc 125.00 Kg/M3
2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 15.0 Buah
Waktu Siklus : Ts
- Memuat = muat, atur, ikat, dll T1 20.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 T2 27.60 menit
- Menurunkan = Rata-rata 1.5 menit / buah T3 22.5 menit
- Lain-lain = geser, tunggu, dll T4 10.0 menit
Ts 80.1 menit
3. TENAGA
Produksi pasang patok kilometer / hari = Tk x Q1 Qt 78.65 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 5.00 orang
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.0890 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1780 jam
- Pekerja = (Tk x P) : Qt (L01) 0.4450 jam
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 8.4.(6) .(a) PERKIRAAN VOL. PEK. : 10,626.00
JENIS PEKERJAAN : Patok Kilometer TOTAL HARGA (Rp.) : 33,086,277,888.47
SATUAN PEMBAYARAN : BH % THD. BIAYA PROYEK : 4.71
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 8.4.(5) PERKIRAAN VOL. PEK. : 21,251.19
JENIS PEKERJAAN : Patok Pengarah TOTAL HARGA (Rp.) : 16,847,104,715.09
SATUAN PEMBAYARAN : BH % THD. BIAYA PROYEK : 2.40
A. TENAGA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar (patok beton cetak, dll) diangkut dengan
Truk ke lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.8 KM
5 Jam kerja efektif per-hari Tk 7.00 jam
6 Faktor kehilangan bahan Fh 1.05 -
7 Tulangan praktis Rc 125.00 Kg/M3
2. ALAT
2.a. DUMP TRUCK (E08)
Kapasitas 1 kali Angkut Cp 20.0 Buah
Faktor Efisiensi Alat Fa 0.83 -
Waktu Siklus : Ts
- Memuat = atur, ikat, dll. T1 20.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 menit T2 27.6 menit
- Menurunkan = Rata-rata 1 menit / buah T3 20.0 menit
- Lain-lain = geser, atur, tunggu, dll. T4 10.0 menit
Ts 77.6 menit
3. TENAGA
Produksi pasang patok pengarah / hari = Tk x Q1 Qt 89.85 Buah
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 4.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.0779 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.3116 jam
- Pekerja = (Tk x P) : Qt (L01) 0.6233 jam
PROYEK :
No. PAKET KONTRAK : 73/HK.0203/P2JN-PB/PPK.WIL.II/PERN-PJLNRA/APBN/2015
NAMA PAKET : Perencanaan Pembangunan Jalan Wilayah Raja Ampat
PROP / KAB / KODYA : Papua Barat/Raja Ampat
ITEM PEMBAYARAN NO. : 8.4.(7) PERKIRAAN VOL. PEK. : 10,825.00
JENIS PEKERJAAN : Rel Pengaman TOTAL HARGA (Rp.) : 26,314,258,608.37
SATUAN PEMBAYARAN : M' % THD. BIAYA PROYEK : 3.75
A. PEKERJA
B. BAHAN
C. PERALATAN
I. ASUMSI
1 Menggunakan cara manual
2 Lokasi pekerjaan : sepanjang jalan
3 Bahan dasar rel pengaman diterima di lokasi pekerjaan
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 5.8 Km ukuran
5 Jam kerja efektif per-hari Tk 7.00 jam sesuai
6 Faktor kehilangan bahan Fh 1.00 - drawing
7 Tulangan praktis Rc 50.00 Kg/Cu.m
2. ALAT
2,a DUMP TRUCK (E08) (E08)
Kapasitas 1 kali Angkut Cp 15.0 M'
Waktu Siklus : Ts
- Memuat T1 50.0 menit
- Angkut = (2 x L : 25 Km/Jam) x 60 T2 27.60 menit
- Menurunkan T3 60.0 menit
- Lain-lain T4 30.0 menit
Ts 167.6 menit
3. TENAGA
Produksi pasang pagar pengaman / hari = Tk x Q1 Qt 37.59 M'
Kebutuhan tenaga : - Mandor M 1.00 orang
- Tukang Tb 2.00 orang
- Pekerja P 8.00 orang
Koefisien Tenaga / M' :
- Mandor = (Tk x M) : Qt (L03) 0.1862 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.3724 jam
- Pekerja = (Tk x P) : Qt (L01) 1.4898 jam
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROPINSI :
ITEM PEMBAYARAN NO. : 10.1 (1)
JENIS PEKERJAAN : Pemeliharaan Rutin Perkerasan
SATUAN PEMBAYARAN : Lump Sum / Bulan % THD. BIAYA PROYEK : 0.04
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROPINSI :
ITEM PEMBAYARAN NO. : 10.1 (2)
JENIS PEKERJAAN : Pemeliharaan Rutin Bahu Jalan
SATUAN PEMBAYARAN : Lump Sum / Bulan % THD. BIAYA PROYEK : 0.03
A. TENAGA
B. BAHAN
C. PERALATAN
PROYEK :
No. PAKET KONTRAK :
NAMA PAKET :
PROPINSI :
ITEM PEMBAYARAN NO. : 10.1 (3)
JENIS PEKERJAAN : Pemeliharaan Rutin Selokan, Saluran Air, Galian & Timbunan
SATUAN PEMBAYARAN : Lump Sum / Bulan % THD. BIAYA PROYEK : 0.06
A. TENAGA
B. BAHAN
C. PERALATAN