EVALUASI VOLUME LAPORAN PEKERJAAN HAULING ROAD PT.

LBR
PERIODE 17 - 30 APRIL 2020 1 - 5 MEI 2020 ESTIMASI VOLUME YANG TERKUPAS (bcm)
APRIL MEI
SEGMEN ALAT QUANTITY VOL TOT TARGET TIME AVERAGE SATUAN DUE DATE KETERANGAN 29 30 1 2 3 4 5
R1 PC 200 2 760 5 HARI 76 BCM/UNIT/DAY 30-Apr Depan pos 2 motong PROGRES 0 0
bukit , pelebaran
DZ 1 dan urugan SISA
R2 PC 200 2 2,372 9 HARI 131.78 BCM/UNIT/DAY 30-Apr Creek, timbun finish
DZ 1 sambung jalan
R3 FINISH
finish
R4 FINISH
R5 PC 200 3 3,209 14 HARI 76.40 BCM/UNIT/DAY 1 MEI PROGRES 3704 4035 789.75
finish
DZ 2 SISA - 495 - 4,530 - 5,320
R6 PC 200 2 17,245 16 HARI 538.91 BCM/UNIT/DAY 5 MEI PROGRES 1750
DZ 2 SISA 12,715 10,965
R7 PC 200 3 24,738 14 HARI 589.00 BCM/UNIT/DAY 3 MEI PROGRES 4760 760 5904
HITACHI 350 1,4BCM 1 SISA 19,978 19,218 13,314
DZ 2
R8
R9 30-May
R 10
R 11 30 MEI
R 12
JUMLAH R1 - R 7 48,324 16 HARI 3,020.25 BCM/DAY 5 MEI progres 8464 4795 8,444
ESTIMASI VOL BY DESIGN LBR 75,881 sisa 39,860 35,065 26,621

FORECAST BY ALAT
EXC PC 200 8 UNIT JAM KERJA YIELD 3 JAM PER DAY
SWING 3 RPM 60 MENIT
BUCKET 0.9 BCM CAPACITY PER DAY 486 BCM/UNIT/DAY
3,888 BCM/DAY
EXC PC 350 2 UNIT JAM KERJA YIELD 3 JAM PER DAY
SWING 3 RPM 60 MENIT
BUCKET 1.3 BCM CAPACITY PER DAY 702 BCM/UNIT/DAY
DZ 5 UNIT 1,404 BCM/DAY
TOTAL PRODUKSI MATERIAL 5,292 PER DAY

ASUMSI DIANGGAP BENAR


VOLUME HITUNGAN LBR 75,000 BCM
WAKTU DIBUTUHKAN 24.83 HARI menurut versi LBR
menurut versi alat, dan hanya dengan 3 jam kerja. Suatu hal yang sangat
WAKTU DIBUTUHKAN 14.17 HARI tidak minimalis