Volume by desain RENTAL ALAT PA

Waste ore pit 24 W+S+R


377,000 pit1
307,000 pit3 PA *=(W+S )/ 24
*=(24-R) /24
Target Prod Rental PC 200 , min jam 3
1000 day 30 30,000 month UA *=W/(W+S)
5
Equipment Capacity
PA
R 2.4 HM
S 8.75
W 12.85
24

UA 59%

1 PC 200 80 bcm/jam
stanby :
Produksi 370,080 bcm/year rest and meal
1,028 bcm/day change shift
30,840 bcm/month sholat
safety talk
prepare front,road,dispos
rain
slepry

total stb
RENTAL ALAT PA 90%

R 2.4 JAM/DAY 72 month


W+S 21.6 JAM/DAY 648 month

Rental PC 200 , min jam 300 jam/bulan dengan PA 85 % , Rp 300.000 /jam

120

83%
1000 start
1008 stop
8 jam/day

200 jam

60,000,000

stanby wajib dlm setahun


rest and meal 2 jam idul fitri 1
change shift 2 idul adha 1
1 HUT RI 1
safety talk 0.25 Natal 1
prepare front,road,disposal 0.5 tahun baru 1
2
1

8.75 jam/day 5 day/year

day available 360


setting disposal

elv 200 50 m

elv 195
50

geotek kepmen esdm 1827


over all slope 27 hal 57

single slope 45
kepmen 1827 esdm 2018
hal 98 gradien jalan maks 12 %
gradien 10%

10%

elv 190

single slope 45
overall slope 27
bench height 5
bench width 5
Kepmen esdm 1827 th 2018 hal 116
peraturan Peralatan Tambang

Produksi nikel /month W+S+R 24 jam


Ore 50,000
waste 75,000 W 15.18 jam
Total 125,000.00

PA= (24 - R)/24 90% alat Baru < 3thn


PA 90% 85% >3thn
W+S 21.60 jam
R 2.40 jam Dalam sehari rusak maksimal 2.4 jam

UA=w/(w+S)
UA 70%
alasan pemilihan alat nikel
Unit Productivity thickness tipis
1 PC 300 133 bcm/hour Working Area sempit 2 x radius alat
PC 400 220 bcm/hour Selective pemisahan ore dan waste ( saprolit dan l
PC 800 350 bcm/hour
PC 1250 450 bcm/hour
PC 2000 800 bcm/hour Produksi = n x Sch Hour x PA x UA x Productivity
2 PC 200 80 bcm/hour
n= Jumlah Fleet

PC 300 60,733.33
PC 200 72,880
Total 133,613.33
Match
pit1 375,000
pit3 308,000 Equipment VS Target prod VS
Total 683,000

Prod Life
month 30,000.00 23 month
day 1000
Stanby
W work Rest 2
S standby Change shift 2
R repair loading point / Front 0.5
Refuelling 0.25
Safety Talk 0.166667
Rain 1
Slipery 0.5
Total 6.42 jam

2 x radius alat
n ore dan waste ( saprolit dan limonit )

Productivity

Equipment VS Target prod VS Sequen