TIME SCHEDULE PROJECT

Mechanical & Electrical Work (ME)


Kawasan Industri Suryacipta - Karawang Timur
Owner : PT. Kadi International - PT.Suryacipta Swadaya (City Of Industry)
Contractor : CV. Dunia Induksi
Project Manager : Ahmad Darajat
Site Enngineer : Ahmad Jaelani
Site Enngineer : Solihin Suppriyadi
Pelaksana : Suhaidi
Waktu Pelaksanaan Pekerjaan (2 Bulan)
Agust-19 Sep-19 Okt-19
Jumlah Harga 1-Aug 8-Aug 15-Aug 22-Aug 29-Aug 5-Sep 12-Sep 19-Sep 26-Sep 3-Oct 10-Oct 17-Oct
No. Uraian Pekerjaan Bobot KET.
(Rp.) s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d
7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12

I. Pekerjaan Persiapan Rp 5,000,000 1.01 0.51 0.51 Waktu pelaksanaan

A Water Supply - 60 hari kalender

1 HDPE PIPE - (2 bulan)

- Pipa HDPE (Unilon SDR 17 PN 10), dia.150mm Rp 50,000,000 10.10 3.37 3.37 3.37

- Galian Rp 15,752,752 3.18 0.64 0.64 0.64 0.64 0.64

- Pemasangan/Instal/Penyambungan Rp 75,000,000 15.15 2.16 2.16 2.16 2.16 2.16 2.16 2.16

- Urugan Rp 37,000,000 7.48 2.49 2.49 2.49

Rp 182,752,752 -

2 VALVE + BOX -

- Gate valve ex. Amri / Toyo Rp 71,656,000 14.48 7.24 7.24

150 mm diameter Gate Valve (DCI) -

- Pengadaan Rp 35,828,000 7.24 3.62 3.62

- Install Rp 35,828,000 Rp 143,312,000 7.24 2.41 2.41 2.41

Hydrant Pillar lengkap -

- Pengadaan, set komplit Rp 16,496,346 3.33 1.67 1.67

- Install Rp 25,000,000 Rp 41,496,346 5.05 1.01 1.01 1.01 1.01 1.01

B Street Lighting -

Street Lighting Pole (h=11 m') – Galvanis, -

- Produksi PJU type Octagonal Rp 45,000,000 9.09 1.30 1.30 1.30 1.30 1.30 1.30 1.30

- Pengdaan Lampu LED 120 Watt Rp 20,000,000 4.04 1.35 1.35 1.35

- Pengdaan Baterry Lampu Rp 26,000,000 5.25 1.75 1.75 1.75

- Pengdaan Armature Solar Cell Rp 15,000,000 3.03 1.01 1.01 1.01

- Pemasangan/Instalasai Rp 10,000,000 2.02 0.29 0.29 0.29 0.29 0.29 0.29 0.29

- Comisioning Rp 6,400,000 1.29 0.65 0.65

C FHO Rp 1,500,000 0.30 0.30

D Maintenance/Pemeliharaan Rp 3,500,000 Rp 127,400,000 0.71 0.24 0.24 0.24

Sub Total Rp 494,961,098 100.00

Terbilang

Rencana Progress (Mingguan) (%) 7.97 12.37 24.39 24.44 10.30 9.67 7.90 2.48 0.24 0.24 - -

Rencana Progress Komulatif (%) 7.97 20.34 44.73 69.17 79.48 89.14 97.04 99.53 99.76 100.00 100.00 100.00

f:\Schedule Pekerjaan Pipa HDPE - Suryacipta