Anda di halaman 1dari 11

Schedule Cleaning Condensor Steam 24" Barat PT.

Surya Pamenang – Kedi


27/02/2023 - 03/03/2023
• Persiapan Sebelum Cleaning :

No Tanggal Waktu Manpower

1 2/25/2023 08.00 - 17.00 2 Orang

• Cleaning :
No Tanggal Waktu Manpower

5 Orang
1 2/27/2023 08.00 - 20.00

5 Orang
2 2/28/2023 08.00 - 20.00

3 3/1/2023 08.00 - 20.00 5 Orang

4 3/2/2023 08.00 - 20.00 5 Orang

5 3/3/2023 08.00 - 20.00 5 Orang

• Estimasi Perhitungan Gaji, Uang Makan & Transport :

No Nama

1 Rizqi AD
2 Muis (Fitter)
3 Ardi (Welder)
4 Andre (Semi)
5 Roni (Semi)
Uang Makan : 3 x 5 org x 5 hr @20000 =
Transport : 5 org x PP @60000 =
TOTAL :

• DETAIL MATERIAL, CONSUMABLE & TOOLS : NEXT SHEET ----->


• DETAIL MATERIAL, CONSUMABLE & TOOLS : NEXT SHEET ----->

GRAND TOTAL =

*) NOTE : - MUR, BAUT FLANGE, PLUG TUBBING, GASKET DARI PT. SURYA PAMENANG.
g Condensor Steam 24" Barat PT. Surya Pamenang – Kediri
27/02/2023 - 03/03/2023

Aktivitas Lokasi
Pembelian material & consumable pekerjaan Krian/SBY
Sewa Scaffolding 3 Set Krian
Persiapan alat, Safety equipment, rapid test dll Workshop

Aktivitas Lokasi
Pengiriman alat & Perizinan
Persiapan alat, & Pasang scaftfolding
Bongkar koneksi (cek kondisi tubbing)
Mechanical cleaning bor (2 Sisi)
Mechanical cleaning bor (2 Sisi) + Pembuatan gasket blind flange
Pasang koneksi & pasang gasket blind flange
Chemical Cleaning (12 Jam*) + Pembuatan gasket flange (10 titik)
Chemical Cleaning (12 Jam*)
PT SP
Bongkar koneksi (cek kondisi tubbing)
Mechanical cleaning brush (2 Sisi)
Hydrotest (6 Bar - 2 jam) - (internal)
Hydrotest & Cek kondisi tubbing after cleaning (External)
Rekondisi instalasi (bongkar blind & pasang koneksi instalasi)
Rekondisi instalasi (bongkar blind & pasang koneksi instalasi)
Pengecekkan kebocoran & Trial normal running
Pembersihan area kerja

n & Transport :
..-02-23 TOTAL
x 5 Hari
08.00 - 20.00 (1 Hari)
-
Rp 260,000
Rp 278,571 Rp 910,003 Rp 4,550,015
Rp 185,716
Rp 185,716
Rp 1,500,000
Rp 300,000
Rp 6,350,015

MATERIAL, CONSUMABLE & TOOLS : NEXT SHEET -----> TOTAL = Rp 9,652,000


MATERIAL, CONSUMABLE & TOOLS : NEXT SHEET -----> TOTAL = Rp 9,652,000

Rp 16,002,015

MUR, BAUT FLANGE, PLUG TUBBING, GASKET DARI PT. SURYA PAMENANG.
p 9,652,000
p 9,652,000
Material & Tools Cleaning Condensor Steam 24" Barat PT. Surya Pamenang
27/02/2023 - 03/03/2023
• MESIN & CHEMICAL :

No Mesin Spesifikasi Holding Vol. (m3) Chemical


Tubbing : 5/8" Descaler 50
Condn. HE Steam Barat Qty : 624 Pcs (1 Pail @30kg)
1 (Terakhir 1.2
cleaning 11/01/2022)
Press : 6 Bar Passivator
H.Vol. : 1,2 m3 (Maxtrol 2721)

*) Harga :
1 Descaler 50 (1 Pail @30kg) Rp 40,000 X 180
2 Maxtrol 2721 ( 6 kg) Rp 60,000 X 6

• MATERIAL CONSUMABLE :

No Nama Qty Harga Total Harga


1 Tangga Lipat 1 set Ada
2 Scafolding T.90 2 set 30.000/set/bln Rp 60,000
3 Scafolding T.70 1 set 25.000/set/bln Rp 25,000
4 Leader Frame T.90 2 set 25.000/set/bln Rp 50,000
5 Kunci Pipa 1 Unit Ada
6 Handbor Besar Wipro W6162 (1 Unit) Ada
7 Handbor Tanggung Bosch GSB 550 (1 Unit) 620.000/Unit Rp 620,000
8 Mata Bor Bor Beton M6 (4 Pcs) 20.000/Pcs Rp 80,000
9 Rotary Brush GOODWAY SGB 100 (1 Pcs) 165.000/Pcs Rp 165,000
10 As Mata Bor Besi d.6 mm x 2 Meter (4 Pcs) 35.000/12mtr Rp 35,000
11 Pompa Hydrotest 1 Unit Ada
12 Clamp Selang 1" (6 Pcs) 12,000 Rp 72,000
13 Wrench Impact SET 1 Unit Ada
14 Sikat Baja 3 Pcs 15.000/Pcs Rp 45,000
15 Kabel Power 3P & 1P 20 Meter (2 Set) Ada
16 Lampu Sorot 1 Unit Ada
17 Box Alat 1 Unit Ada
18 Tambang 15 Meter Ada
19 Pompa Cleaning SET 2 Unit Ada

D. 225 = 3 Pcs

D. 175 = 7 Pcs 15.000/kg


20 Fitting Blind Flange D. 120 = 2 Pcs (Estimasi Berat Total Rp 300,000
( Plat Besi 6 mm )
D. 95 = 5 Pcs 20 kg)
D. 65 = 2 Pcs
D. 12" = 6 Pcs
21 Terpal 1 Pcs Ada
22 Las Stick 1 Unit Ada
23 Gerinda 1 Unit Ada
24 Linggis kobut 40cm 2 Unit Ada
25 Degreaser WD40-191ml 2 Botol 70000/btl Rp 140,000
26 Pipa 2" - 2mtr 1 Btg Ada
27 Chainblock & belt 2 set Ada
28 Hand pallet 1 Unit Ada
29 Red silicon 70 gr (20 Pcs) 20.000/Pcs Rp 400,000
30 Seal tape 20 Pcs 5000/Pcs Rp 100,000
Total : 2,092,000

Harga Chemical, Material Consumable & Tools,


TOTAL = 9,652,000
T. Surya Pamenang – Kediri

Konsentrasi Qty Chemical (Liter)


15% 180 → *) Note: Konsentrasi & Harga mengacu pada penawaran clean

0.5% 6

Kg = Rp 7,200,000
Kg = Rp 360,000
Total = Rp 7,560,000

Vendor Keterangan
Workshop

UD. Tekad Saudara sewa

Workshop
Workshop
Sinar Jaya Beli → PEMBELIAN DILAKUKAN KARENA BIAYA SERVISE CUKUP MAHA
Sinar Jaya Beli KARENA ROTOR ANCHOR BOR TERBAKAR & SPEK BOR MEKTEC
CV Surabaya Cool Beli
Toko bangunan Krian Beli
Workshop
Sinar Jaya Beli
Workshop
Sinar Jaya Beli
Workshop
Workshop
Workshop
Workshop
PT MSJ & Workshop

Beli & Sebagian ada di


Loak Krian
Workshop
Workshop
Workshop
Workshop
Workshop
Sinar Jaya Beli
Workshop
Workshop
Workshop
Sinar Jaya Beli
Sinar Jaya Beli
mengacu pada penawaran cleaning HE Steam Barat PT.SP tgl - 27/12/2021

A BIAYA SERVISE CUKUP MAHAL RP. 250.000 & TIDAK MENJAMIN TAHAN LAMA,
TERBAKAR & SPEK BOR MEKTECH MT60 CUKUP KECIL.

Anda mungkin juga menyukai