PEKERJAAN : GAMAS FEEDER 01 TPS (FA, FB, GCL)

PENYEBAB : PERABASAN
LOKASI : TAMPAKSIRING
STO :TPS

HARGA SATUAN TOTAL


MATERIAL JASA
NO. URAIAN PEKERJAAN SAT VOL
DESIGNATOR DESIGNATOR MATERIA JASA MATERIAL JASA TOTAL
L

PENGADAAN DAN PEMASANGAN KABEL UDARA


11 M-AC-OF-SM-96D J-AC-OF-SM-96D Mtr 800 34,560 4,940 27,648,000 3,952,000 31,600,000
FIBER OPTIK SINGLE MODE 96 CORE G 652 D
3 J-CO-OF PEKERJAAN CUT OVER KABEL SERAT OPTIK Core 192 - 61,030 - 11,717,760 11,717,760
PENGADAAN ALAT SAMBUNG (CABANG/ LURUS)
9 M-SC-OF-SM-96 J-SC-OF-SM-96 Pcs 2 908,820 35,100 1,817,640 70,200 1,887,840
UNTUK FIBER OPTIK KAPASITAS 12 - 96 CORE

PEKERJAAN GALIAN, PENGURUGAN KEMBALI


DAN PERBAIKAN KEMBALI, PENGISIAN PASIR,
7 J-BC-TR-5 Mtr 20 - 44,820 - 896,400 896,400
WARNING TAPE DAN TANDA RUTE KABEL SERTA
TEMPAT SAMBUNG KEDALAMAN 1,5 METER

PENGADAAN RISER PIPE UNTUK PENGAMAN


6 M-TC-02-ODC J-TC-02-ODC KABEL OPTIK KE ODC POLE / TITIK NAIK KU Unit 2 234,210 62,640 468,420 125,280 593,700
DIAMATER 2 INCH PANJANG 3 METER

PENGADAAN DAN PEMASANGAN PIPA HDPE


1 M-DD-HDPE-40-1 J-DD-HDPE-40-1 Mtr 25 12,580 1,610 314,500 40,250 354,750
40/33 MM 1 PIPA DENGAN KEDALAMAN 1,5 METER

PENGADAAN & PEMASANGAN ACCESSORIES


6 M-PU-AS J-PU-AS Btg 25 31,540 41,520 788,500 1,038,000 1,826,500
TIANG 7 M DAN 9 M
9 M-SLACK-SUPP J-SLACK-SUPP PENGADAAN SLACK SUPPORT Pcs 2 142,560 17,280 285,120 34,560 319,680
31,322,180 17,874,450 49,196,630

PT TELKOM AKSES PT. TELKOM

GEDE SUMATERA WHILDAN PAKARTIPANGI


MGR OPERATION SINGARAJA OFF 2 CONSTRUCTION SUPERVISION