PLN

UIW SULSELBAR UP3 KENDARI

RENCANA ANGGARAN BIAYA (RAB)


NO.........../DIS-RAB.00.01/UP3-KDI/2023

NAMA PEKERJAAN : Pemasangan JUTR LVTC Untuk PT REZKI NUR PRATAMA PERUMAHAN NUR PRATAMA

LOKASI 1 : Jl. Kharil Anwar Lrg Lalombaku Kel. Puwatu (PB. 1.300 VA .21. Unit)

HARGA VOL.
URAIAN PEKERJAAN SATUAN JUM. HARGA (RP) KET
SATUAN PLN REKANAN
MATERIAL MDU JUTR
1 CABLE PWR;NFA2X-T;3x70+N50mm2;230/380;OH mtr 53.005 - - -
2 CABLE PWR;NFA2X-T;3x50+N35mm2;230/380;OH mtr - - -
3 CABLE PWR;NFA2X-T;3x35+N50mm2;230/380;OH mtr 30.870 360,00 - 11.113.200
4 POLE;CONCRETE;20kV;CIRCL;9m;200daN-E;; btg 4.506.590 8 - 36.052.720
5 POLE;CONCRETE;20kV;CIRCL;11m;200daN;; btg 5.480.180 - - -
6 Tiang besi 9/100 daN btg 2.399.880 -
7 Tiang besi 9/156 daN btg 4.175.630 -
8 Tiang besi 9/200 daN btg 4.175.630 -
JUMLAH MATERIAL MDU JTR 47.165.920
JUMLAH MATERIAL MDU UTK SEMUA LOKASI 47.165.920
MATERIAL PELENGKAP JUTR
1 Small angle/Suspension Assembly 25-70 mm2 set 85.255 4 341.021
2 Large angle assembly 50-70 mm2 set 131.951 - -
3 Fixed Dead end assembly 50-70 mm2 set 111.316 2 222.631
4 Electrical & Mechanical Protection Set 25-70 mm2 set 125.274 - -
5 Stainless Steel Strap mtr 19.476 12 233.712
6 Stopping Buckle Stainless Steel bh 5.642 12 67.704
7 Link 25 x 50 mm bh 5.003 - -
8 Connector kedap air 35-70mm2 bh 35.570 4 142.279
9 Pipa Arde 1,5 " x 3.000 mm lengkap Set 538.815 - -
10 Ground Rod + Clamp 5/8 x 2,5 mtr Set 221.298 - -
11 Live Line Clamp (LLC) 95 - 150 mm Bh 339.362 - -
12 Kawat BC draad 50 mm2 Mtr 77.244 - -
13 Unimax clamp 50 mm2 Buah 36.624 - -
14 Tupang tarik TR set 3 -
- POLE ACC;GUY INSULATOR MV bh 84.409 3 253.226
- Eye bolt 5/8" x 300 mm bh 18.315 3 54.944
- Turn Buckle Medium /Span scroef 5/8" bh 53.729 3 161.187
- Plat beton bertulang 50x50x10 cm bh 96.756 3 290.267
- Angker rod + klem penyambung + mur baut set 265.558 3 796.674
- Kaos baja / Thimble TM 5/8" bh 13.854 6 83.126
- U - klem 35 - 50 mm bh 9.940 24 238.558
- POLE ACC;STEEL WIRE GALV 50mm2 mtr 30.694 36 1.104.986
15 Bimetal compression joint (Al / Cu) 50-70 mm4 buah 82.080 - -
16 Piercing Tap Connector Overtorque Kedap Air 6-25/35-70 mm2 buah - -
17 Service Wedge Clamp 616 (3 Phasa) 6-10-16-25 mm2 buah - -
18 CCO 16/35 Al + HS buah - -
19 CCO 35/35 Al + HS buah - -
20 CCO 35/70 Al + HS buah - -
21 CCO 70/70 Al + HS buah - -
22 CCO 10-16/10-16 Al + HS buah - -
23 CCO 35-25/10-16 Al + HS buah - -
24 CCO 50-70/10-16 Al + HS buah - -
25 Insulated tension joint 35 mm2 buah - -
26 Insulated tension joint 50 mm2 buah - -
27 Insulated tension joint 70 mm2 buah - -
28 Plastic Strap For JTR (30 Cm) Buah 2.835 - -
JUMLAH MATERIAL PELENGKAP JTR 3.990.315
JUMLAH MATERIAL PELENGKAP 3.990.315

JASA JUTR
1 Pembetonan Tiang 9/200 Type A + Material Batang 339.332 - -
2 Pembetonan Tiang 11/200 Type A + Material Batang 429.275 - -
3 Pengecatan tiang besi TR + Material Batang 465.474 - -
4 Pemasangan / penarikan LVTC 3x35+25 mm2 kms 4.724.451 0,36 1.700.802
5 Pemasangan / penarikan LVTC 3x50+35 mm2 kms 5.511.859 - -
6 Pemasangan / penarikan LVTC 3x70+50 mm2 kms 6.299.267 - -
7 Pemasangan Assecsories LVTC ( SAA) set 47.530 4 190.120
8 Pemasangan Assecsories LVTC ( DEA, LAA ) set 54.011 2 108.022
9 Pemasangan Bundled End Protection set set 43.210 - -
10 Pemasangan Tupang tarik TR set 388.881 3 1.166.644
11 Pemasangan Tupang tarik dengan tiang bantu TR set 572.918 - -
12 Pemasangan CONNEKTOR Double baut Bh 30.203 4 120.812
13 Pemasangan tupang tekan TR set 724.947 - -
14 Pembetonan Tiang 9/100 Type D + Material Btg 781.335 - -
15 Pemasangan Pentanahan ujung / percabangan JTR set 259.254 - -
- -
JUMLAH JASA JTR 3.286.401
PEKERJAAN JASA LAINNYA
HARGA VOL.
URAIAN PEKERJAAN SATUAN JUM. HARGA (RP) KET
SATUAN PLN REKANAN
1 Angkutan Darat Rp/Ton.km 10.635 21 224.021
2 Angkutan Darat Medan Berat Rp/Ton.km 20.080 -
3 Angkutan Laut Rp/Ton.km 575.820 -
4 Pembetonan selubung tiang besi 9-11 mm batang 286.896 - -
5 Pembetonan selubung tiang besi 12 mm batang 328.125 -
6 Pembetonan selubung tiang besi 13 mm batang 418.245 -
7 -
8 Jasa Angkutan laut kepulauan dalam propinsi Rp/Ton.km 575.820 -
9 Pekerjaan perampalan pohon kms 448.335 - -
Pekerjaan Tebang Pohon (setara pohon kelapa/pohon berkayu dengan diameter
10 pohon 358.668 -
diatas 30 cm/pohon produktif) -
JUMLAH JASA LAINNYA -
JUMLAH JASA 3.286.401
REKAPITULASI RAB
JUMLAH MATERIAL MDU Rp 47.165.920
JUMLAH MATERIAL PELENGKAP Rp 3.990.315
JUMLAH JASA Rp 3.286.401
JUMLAH MATERIAL DAN JASA Rp. 54.442.636
DIBULATKAN Rp. 54.442.000
PPN 11 % Rp. 5.988.620
GRAND TOTAL Rp. 60.430.620
Terbilang : Enam Puluh Juta Empat Ratus Tiga Puluh Ribu Enam Ratus Dua Puluh Rupiah

PENERIMAAN Satuan HS Jum. KVA jum. Plg JUMLAH (Rp)


1 BP ( Biaya Penyambungan Daya 900 VA) VA 937 900,00 - -
2 BP ( Biaya Penyambungan Daya 13.00 VA) VA 937 1.300,00 24 29.234.400
3 BP ( Biaya Penyambungan Daya 2.200 VA) VA 937 2.200,00 - -
4 BP ( Biaya Penyambungan Daya 3.500 VA) VA 969 3.500,00 - -
5 BP ( Biaya Penyambungan Daya 4.400 VA) VA 969 4.400,00 -
JUMLAH PENERIMAAN 12.300 24 29.234.400
1 BIAYA INVESTASI PERLUASAN JARINGAN LOKASI LS 1 60.430.620 PBP (THN)
2 BIAYA INVESTASI SP APP TERMASUK PPN 11 % Pelanggan 754.345 24 18.104.278 5
JUMLAH BIAYA INVESTASI 78.534.898
SALDO PENRIMAAN DIKURANG BIAYA INVESTASI (49.300.498)
Kesimpulan : KKF di nyatakan Layak Karena PBP di bawah (≤) 5 tahun
KENDARI 05 Mei 2023

MANAJER MANEJER BAGIAN PERENCANAAN

EKO RIDUWAN SUYATNO