REKAPITULASI

DAFTAR KUANTITAS DAN HARGA


PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI LISTRIK PERDESAAN
TAHUN ANGGARAN 2012
NAMA PAKET

PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU


DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO

DOKUMEN PENGADAAN

No. DP.018.J/APBN-DM/LISDES-J/2012

No.

URAIAN PEKERJAAN

I.

Spesifikasi Tehnik
SPLN

Kabel

SQM

PENGADAAN DAN PEMASANGAN J.T.M


MURNI TIANG BETON + ACCESSORIES

AAAC

70 mm

SPLN 41-8

10,650 Kms

II.

PEMASANGAN TOWER MONO POLE DAN


SUTM ACSR 70MM + ACCESSORIES

ACSR

70 mm

SPLN 42-10

0,225 Kms

III.

PENGADAAN DAN PEMASANGAN J.T.R


TP. TIANG T. BETON+ ACCESSORIES

SPLN 42-10

2,250 Kms

IV.

PENGADAAN DAN PEMASANGAN GARDU


CANTOL + ACCESSORIES

Terbilang :

Twisted 3x35+25mm

NYY

50 kVA

SPLN D3 ; 2007

Volume

Material

Jumlah Harga (Rp.)


Upah

1 UNIT
50 KVA

JUMLAH
PPN 10 %
TOTAL
DIBULATKAN

Jambi,

.. 2012

Penawar,
PT./CV.

Nama jelas
Jabatan

Total

DAFTAR KUANTITAS DAN HARGA


PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI LISTRIK PERDESAAN
TAHUN ANGGARAN 2012
NAMA PAKET

: PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU


DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO

DOKUMEN PENGADAAN

: No. DP.018.J/APBN-DM/LISDES-J/2012

PEMASANGAN J.T.M MURNI TIANG BETON AAAC 3x70 MM

I.
NO

I.1
1
2
3

URAIAN PEKERJAAN

MATERIAL UTAMA
Konduktor AAAC 70 mm
Isolator Tumpu 20 KV
Isolator Tarik 20 KV + Strain Clamp

STN

VOLUME

Mtr
Bh
Set

32.908
758
138

Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set

135
55
1
22
1
25
33
32
213
1

10,650 KMS

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

JUMLAH HARGA
BAHAN
UPAH
(Rp.)
(Rp.)

TOTAL
(Rp.)

JUMLAH I.1
I.2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18

I.3

II.

MATERIAL NON UTAMA


TM - 1
TM - 3
TM - 4
TM - 4X
TM - 5
TM - 8
TM - 8X
TM - 10
TM Portal type pole
TM Khusus kooi
Perlengkapan Guy Wire (GW)
Perlengk. Horizontal Guy Wire (HGW)
Joint Sleve 70 mm
Plat Tanda Bahaya
Bayonet Pipa Galvanis 4" @ 3 Mtr
Cross Arm UNP.8-2.500 palang tiang double
Sectionalizer 20 kV 630 A
Angkutan AAAC 70 mm dan Isolator
dari pabrikan ke Jambi.

T/M3

24,20

JUMLAH I.2
TOTALI. =JUMLAH I.1+JUMLAH I.2

PEMASANGAN TOWER MONO POLE DAN SUTM ACSR 70MM SEPANJANG


=
NO

II.1
1
2
3

URAIAN PEKERJAAN

MATERIAL UTAMA
Konduktor ACSR 70 mm
Isolator Tumpu 20 KV
Isolator Tarik 20 KV + Strain Clamp

STN

VOLUME

Mtr
Bh
Set

710
6
12

JUMLAH II.1
II.2
1
2
3
4
5
6
7
8
9
10
11
12
13
14

II.3

MATERIAL NON UTAMA


Pemasangan Bouwplank
M'
Galian Tanah Pondasi
M
Urugan Tanah Kembali
M
Urugan Pasir Bawah Pondasi
M
Urugan Pasir Bawah Bor Pile
M
Beton 1 : 3 : 5 Lantai Kerja Pondasi Tapak t.5 cmM
Beton 1 : 3 : 5 Lantai Kerja Bor Pile t.5 cm
M
Bor Pile Dia 250mm
M'
Pondasi Tapak ( K 225 )
M
Lab. Quantity
Ls
Tower Mono Pole
Kg
Angkutan Besi
T/M
Perlengkapan Guy Wire (GW-Tower)
Set
Angkutan Material ACSR dan Isolator
T/M
JUMLAH II.2
TOTALII. =JUMLAH II.1+JUMLAH II.2

20,00
4,50
1,50
0,225
0,0196
0,225
0,0196
120,00
7,59
1,00
14.824,16
14,82416
4,00
0,59

0,225 KMS

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

JUMLAH HARGA
BAHAN
UPAH
(Rp.)
(Rp.)

TOTAL
(Rp.)

DAFTAR KUANTITAS DAN HARGA


PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI LISTRIK PERDESAAN
TAHUN ANGGARAN 2012
NAMA PAKET

: PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU


DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO

DOKUMEN PENGADAAN

: No. DP.018.J/APBN-DM/LISDES-J/2012

III.
NO

III.1
1

PEMASANGAN J.T.R Tp. TIANG T.BETON 3x35+1x25 MM


URAIAN PEKERJAAN

MATERIAL UTAMA
TIC NFA2X-T 3x35 + 1x25 mm

STN

VOLUME

Mtr

2.362

Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Set
Rol
Bh

32
11
2
2
9
2
-

2,250 KMS

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

JUMLAH HARGA
BAHAN
UPAH
(Rp.)
(Rp.)

TOTAL
(Rp.)

JUMLAH HARGA
BAHAN
UPAH
(Rp.)
(Rp.)

TOTAL
(Rp.)

JUMLAH III.1
III.2
1
2
3
4
5
6
7
8
9
10
11
12
13
14

III.3

IV.
NO
IV.1
1

MATERIAL NON UTAMA


TR - 1
TR - 2
TR - 3
TR - 4
TR - 5
TR - 6
TR - 6A
TR - 7
Ardhe TR.2 ( Luar tiang )
Perlengkapan Guy Wire (GW) - TR
Perlengk. Horizontal Guy Wire (HGW) - TR
Adhesive Insulating Tape
Joint Compression
Angkutan TIC NFA2X-T 3x35 + 1x25 mm
dari pabrikan ke Jambi.

T/M3

2,83

JUMLAH III.2
TOTAL III. =JUMLAH III.1+JUMLAH III.2

PEMASANGAN GARDU CANTOL 50 KVA


URAIAN PEKERJAAN
MATERIAL UTAMA
Trafo Distribusi 50KVA-20KV/B - 3Phase

STN

1 UNIT

VOLUME

Bh

Set
Bh
Set
Mtr
Bh
Bh
Set
Bh
Bh
Mtr
Mtr
Bh
Bh

M3
Set
Bh

1
3
3
9
6
3
1
1
2
36
72
8
8
1
2
2
0,25
2
9

T/M3

0,96

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

JUMLAH IV.1
IV.2
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19

20

IV.3

MATERIAL NON UTAMA


Cross Arm UNP.10 u/Arrester,Cut Out
Lightning Arrester 20 KV
Cut Out 20 KV + Fuse link
Konduktor AAAC 70 mm
Tap Connector 35 - 70 mm
Bimetal Terminal Lug 70 mm
Rangka Tempat Dudukan Trafo Cantol
LV. Panel lengkap
Single Arm Tie Band (Klem Peg. LV Panel)
Kabel NYY 1x70 mm
Kabel NYY 1x50 mm
Cable Schoen 70 mm
Cable Schoen 50 mm
Pipa Galvanis 3" + L. Bouw
Pipa Galvanis 2" + L. Bouw
UNP.8 Klem Pegangan Pipa Galvanis
Manset tiang beton ad. 1pc:2ps:3krl
BC 50 mm Ardhe dan Accessories
Cable Schoen 70 mm untuk :
- Cut Out 20 KV
- Lightning Arrester dan AAAC
Angkutan Trafo, CO dan Lightning Arrester
dari pabrikan ke Jambi.
JUMLAH IV.2
TOTAL IV. =JUMLAH IV.1+JUMLAH IV.2

Set
Set
Set

ANALISA HARGA SATUAN MATERIAL SUTM


NAMA PAKET
: PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU
LOKASI
: DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO
DOKUMEN PENGADAAN : No. DP.018.J/APBN-DM/LISDES-J/2012

No.

URAIAN PEKERJAAN

TM. 1
- Cross Arm Type 2.000 UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Bending Wire 20 mm
- Single Arm Tie Band

S
T
N

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

VOLUME

Btg
Btg
Set
Bh
Mtr
Set

1
2
1
2
6
1
Jumlah

TM. 3
- Cross Arm Type 2.000 UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Bending Wire 20 mm
- Double Arm Tie Band

Btg
Btg
Set
Set
Mtr
Set

2
4
3
4
12
1
Jumlah

TM. 4
- Cross Arm Type 2.000, UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Double Arm Tie Band

Btg
Btg
Set
Set
Set

2
4
3
4
1
Jumlah

TM. 4.X
- Alluminium Bending Wire 20 mm
- Joint Sleeve 35 - 70 mm

Mtr
Bh

2
3
Jumlah

TM. 5
- Cross Arm Type 2.000, UNP. 8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Binding Wire
- Joint Sleeve 35 - 70 mm
- Double Arm Tie Band

Btg
Btg
Set
Bh
Mtr
Bh
Set

2
4
3
4
2
3
1
Jumlah

TM. 8
- Cross Arm 2.000, UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Binding Wire
- Joint Sleve 70 mm
- Bolt & Nut M.16 x 250 mm + Washer
- Double Arm Tie Band
- Double Arm Band

Btg
Btg
Set
Set
Mtr
Bh
Bh
Set
Set

3
6
3
6
8
3
1
1
1
Jumlah

TM. 8.X
- Cross Arm 2.000, UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Binding Wire
- Joint Sleve 70 mm
- Double Arm Tie Band
- Double Arm Band

Btg
Btg
Set
Set
Mtr
Bh
Bh
Set

2
4
2
4
2
3
1
1
Jumlah

JUMLAH
HARGA
(Rp.)

No.

URAIAN PEKERJAAN

TM. 10
- Cross Arm Type 2.000, UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Binding Wire
- Joint Sleve 70 mm
- Double Arm Tie Band
- Double Arm Band

S
T
N

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

VOLUME

Btg
Btg
Set
Bh
Mtr
Bh
Set
Set

4
8
5
8
4
3
2
1
Jumlah

TM. KHUSUS TYPE POLE


- Cross Arm Type 2.500, UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Binding Wire
- Joint Sleve 70 mm
- Double Arm Tie Band
- Double Arm Band

Btg
Btg
Set
Bh
Mtr
Bh
Set
Set

2
4
2
4
4
3
1
1
Jumlah

10

TM. KHUSUS KOOI


- Cross Arm Type 2.500, UNP.8
- Arm Tie Type 810 (Besi L.50.50.5)
- Double Bolt & Nut M.16 x 300 mm + Washer
- Bolt & Nut M.16 x 50 mm + Washer
- Alluminium Binding Wire
- Joint Sleve 70 mm
- Double Arm Tie Band
- Single Arm Band

Btg
Btg
Set
Bh
Mtr
Bh
Set
Set

4
4
2
16
12
3
2
2
Jumlah

11

Perlangkapan Guy Wire (GW - TM)


- Galvanis Steel Wire 35 mm
- Patok Schoor UNP 8 Rod Stay
- Guy Isolator
- Spanschroef / Turn Bucle 5 / 8"
- Wire Clip
- Double Guy Wire Band

Mtr
Set
Bh
Bh
Bh
Set

14
1
1
1
4
1
Jumlah

12

Perleng. Harizontal Guy Wire (HGW - TM)


- Galvanis Steel Wire 35 mm
- Patok Schoor UNP 8 Rod Stay
- Guy Isolator
- Spanschroef / Turn Bucle 5 / 8"
- Wire Clip
- Double Guy Wire Band

Mtr
Set
Bh
Bh
Bh
Set

30
1
2
1
6
2
Jumlah

13

Bayonet TM
- Pipa Galvanis 4"
- Double Band 10" 4"
- Bolt and Nut M.16x50 + washer

Mtr
Set
Bh

3
2
3
Jumlah

JUMLAH
HARGA
(Rp.)

ANALISA HARGA SATUAN MATERIAL SUTR


NAMA PAKET
LOKASI

:
:

PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU


DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO

DOKUMEN PENGADAAN

No. DP.018.J/APBN-DM/LISDES-J/2012

NO.

URAIAN PEKERJAAN

1 TR. 1
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Suspension Clamp
- Suspension Clamp Bracket

S
N
T

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

VOLUME

Bh
Bh
Bh
Set
Set

3
2
2
1
1
Jumlah

2 TR. 2
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Strain Clamp
- Tension Bracket

Bh
Bh
Bh
Set
Set

3
2
2
2
1
Jumlah

3 TR. 3
- Turn Buckle
- Dead End Tubes
- Link
- PVC 2" = 50 cm
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Strain Clamp
- Tension Bracket

Bh
Bh
Bh
Bh
Bh
Bh
Bh
Set
Set

1
4
2
1
2
4
4
1
1
Jumlah

4 TR. 4
- Tap Connector 25-50 mm
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Strain Clamp
- Tension Bracket

Bh
Bh
Bh
Bh
Set
Set

8
6
4
4
2
2
Jumlah

5 TR. 5
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Strain Clamp
- Tension Bracket

Bh
Bh
Bh
Set
Set

4
4
4
2
2
Jumlah

6 TR. 6
- Tap Connector 25-50 mm
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Strain Clamp
- Tension Bracket
- Suspension Clamp
- Suspension Clamp Bracket

Bh
Bh
Bh
Bh
Set
Set
Set
Set

4
4
4
4
1
1
1
1
Jumlah

7 TR. 6.A
- Tap Connector 25-50 mm
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Strain Clamp
- Tension Bracket

Bh
Bh
Set
Bh
Set
Set

4
4
4
4
3
2
Jumlah

JUMLAH
HARGA
(Rp.)

NO.

URAIAN PEKERJAAN

8 TR. 7
- Tap Connector 25-50 mm
- Plastis Strap
- Stoping Buckle
- Stainless Steel Strip @ 0,75 mtr
- Strain Clamp
- Tension Bracket

S
N
T

HARGA SATUAN
BAHAN
UPAH
(Rp.)
(Rp.)

VOLUME

Bh
Bh
Bh
Bh
Set
Set

4
2
2
2
1
1
Jumlah

9 ATR. + E ( Dalam Tiang )


- Earthing Rod 16 mm + Clamp
- Kawat Arde AAAC 70 mm
- Tap Connector 25-50 mm
- Bimetal Terminal lug 70 mm
- Baut M.12 x 45 mm

Set
Mtr
Bh
Bh
Bh

1
3
1
1
2
Jumlah

10 ATR - 2 ( Luar Tiang )


- Stoping Buckle
- Link
- Bimetal Connector 50/35'-150
- Stainless Steel Strip @ 0,75 mtr
- Water Pipe 3/4" 3 Mtr
- Kawat Arde AAAC 70 mm
- Earthing Rod 16 mm + Clamp
- Tap Connector 25-50 mm

Bh
Bh
Set
Bh
Btg
Mtr
Set
Set

3
3
1
3
0,5
9
1
1
Jumlah

11 Perlengkapan GW - TR.
- Galvanis Stell Wire 22 mm
- Patok Schoor UNP 8 Rod Stay
- Wire Clip
- Spanschroef / Turn Bucle 1 / 2"
- Double Guy Wire Band

Mtr
Set
Bh
Bh
Bh

14
1
4
1
1
Jumlah

12 Perlengkapan HGW - TR.


- Galvanis Stell Wire 22 mm
- Patok Schoor UNP 8 Rod Stay
- Wire Clip
- Spanschroef / Turn Bucle 1 / 2"
- Double Guy Wire Band

Mtr
Set
Bh
Bh
Bh

30
1
6
2
2
Jumlah

JUMLAH
HARGA
(Rp.)

ANALISA HARGA SATUAN MATERIAL


NAMA PAKET
LOKASI
DOKUMEN PENGADAAN

:
:
:

PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU


DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO
No. DP.018.J/APBN-DM/LISDES-J/2012

No.

U R AIAN

1. a.

b.

c.

d.

2. a.

b.

c.

d.

3. a.

b.

4. a.

b.

5.

6.

STN

VOLUME

CROSS ARM TYPE 2.000 BESI KANAL UNP 10 :


- Besi UNP 10.
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,333
1,000
1,000

CROSS ARM TYPE 2.500 BESI KANAL UNP 10 :


- Besi UNP 10.
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,417
1,000
1,000

CROSS ARM TYPE 3.000 BESI KANAL UNP 10 :


- Besi UNP 10.
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,500
1,000
1,000

CROSS ARM TYPE 0,200 BESI KANAL UNP 10 :


- Besi UNP 10.
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,033
1,000
1,000

CROSS ARM TYPE 2.000 BESI KANAL UNP 8 :


- Besi UNP 8.
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,333
1,000
1,000

CROSS ARM TYPE 2.500 BESI KANAL UNP 8 :


- Besi UNP 8.
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,417
1,000
1,000

CROSS ARM TYPE 800 BESI KANAL UNP 8 :


- Besi UNP 8.
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,133
1,000
1,000

CROSS ARM TYPE 600 BESI KANAL UNP 8 :


- Besi UNP 8
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,100
1,000
1,000

ARM TIE TYPE 810 :


- Besi Siku L.50.50.5
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,135
1,000
1,000

ARM TIE TYPE 900 :


- Besi Siku L.50.50.5
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,150
1,000
1,000

SINGLE ARM TIE BAND :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,120
3,000
1,000
1,000

DOUBLE ARM TIE BAND :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,120
4,000
1,000
1,000

CROSS ARM CLEVIS :


- Besi Plat Strip 50.5
- Biaya pembuatan
- Galvanis.

Btg
Lot
Lot

0,055
1,000
1,000

Btg
Buah
Lot

0,160
1,000
1,000

PATOK SCHOOR UNP 8 :


- Besi UNP 8
- U Bolt.
- Biaya pembuatan

HRG SATUAN
( Rp. )

JUMLAH
( Rp.)

No.

U R AIAN

7.

8.

9.
a.

STN

VOLUME

SINGLE ARM BAND :


- Double Arming M.16 - 50 mm.
- Besi Plat Strip 50.5
- Biaya pembuatan
- Galvanis ( 1/2 dari galvanis Cross Arm Clevis

Buah
Btg
Lot
Lot

2,000
0,125
1,000
1,000

DOUBLE ARM BAND :


- Double Arming M.16 - 50 mm.
- Besi Plat Strip 50.5
- Biaya pembuatan
- Galvanis ( 1/2 dari galvanis Cross Arm Clevis

Buah
Btg
Lot
Lot

4,000
0,125
1,000
1,000

RAK TR :
RAK TR GARDU CANTOL - 2 (DUA) JURUSAN :
- Besi Plat 1,2 mm (120 x 240 cm)
- Besi Siku L.50.50.5
- Besi Plat Strip 50.5
- NH Fuse. 160 A + Holder
- Plat Copper (50x5x4)
- Isolator mika u/Netral
- Kunci
- Engsel.
- Besi UNP 8 Type 600
- Single Arm band
- Bolt & Nut M.16 - 50 mm.
- Galvanis
- Biaya pembuatan
- Pengecatan.

Lbr
Btg
Btg
Set
Btg
Buah
Buah
Buah
Btg
Set
Buah
Lot
Lot
Lot

1,300
1,600
1,200
6,000
0,500
2,000
1,000
4,000
0,200
2,000
4,000
1,000
1,000
1,000

Lbr
Btg
Btg
Set
Set
Btg
Mtr
Bh
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Mtr
Lot
Lot

2,000
1,820
1,350
0,000
12,000
0,500
3,000
6,000
24,000
1,000
4,000
1,000
1,000
1,000
2,000
3,000
1,000
1,000

BRACKET PALANG UNTUK MENAHAN RAK TR :


- UNP 8 Type 2.500.
- Single arm band
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,417
2,000
1,000
1,000

BRACKET PALANG UNTUK CUT OUT / ARRESTER :


- UNP 8 Type 2.500.
- Single arm tie band
- Double Bolt & Nut M.16 x 300 mm + Washer
- Biaya pembuatan
- Galvanis.

Btg
Set
Set
Lot
Lot

0,833
2,000
2,000
1,000
1,000

Btg
Btg
Buah
Lot
Lot

0,215
0,112
3,000
1,000
1,000

a.1 LV PANEL 400 A - 4 (EMPAT) JURUSAN :


- Besi Plat 1,2 mm (120 x 240 cm)
- Besi Siku L.50.50.5
- Besi Plat Strip 50.5
- On load Switch 400 A
- NH Fuse. 160 A + Holder
- Plat Copper (50x5x4)
- Kabel NYY 150 mm ( OLS - NH Fuse)
- Kabel Schoen 150 mm
- Bolt & Nut M.16 - 50 mm.
- Kunci Sejenis Yale
- Engsel
- Zekering 1 Ph, 6 A
- Stop Kontak +Saklar
- Lampu Pijar + Fitting
- Isolator mika u/Netral
- Kabel NYA 2,5 mm2
- Biaya pembuatan
- Pengecatan
b.

c.

10. a.

ARM BAND 2".2".


- Plat Strip 50.5
- Besi Siku L.50.50.5
- Bolt M.16 - 50 mm.
- Biaya pembuatan
- Galvanis.

HRG SATUAN
( Rp. )

JUMLAH
( Rp.)

No.

U R AIAN
b.

c.

d.

11.
a.

b.

STN

VOLUME

ARM BAND 3".


- Besi Plat Strip 50.5
- Bolt & Nut M.16 x 50 mm
- Biaya pembuatan
- Galvanis.

Btg
Bh
Lot
Lot

0,055
2,000
1,000
1,000

INVORING 3".
- Pipa 3".
- Plat 1,2 mm.
- Biaya pembuatan

Btg
Lbr
Lot

0,025
0,018
1,000

INVORING 2".
- Pipa 2".
- Plat 1,2 mm.
- Biaya pembuatan

Btg
Lbr
Lot

0,025
0,010
1,000

PONDASI COR BETON MANSET


1 M3 COR BETON 1:2:3 :
- Semen ( PC ).
- Kerikil Beton
- Pasir Pasangan.
- Pekerja.
- Tukang Batu
- Kepala Tukang
- Mandor

Zak
M3
M3
Org
Org
Org
Org

8,300
0,830
0,540
6,000
1,000
0,000
0,300

BEKISTING u/ 1 M3 BETON :
- Papan Kayu
- Paku
- Pekerja.
- Tukang kayu
- Kepala Tukang
- Mandor
- Pek.Bongkar Cetakan

M3
Kg
Org
Org
Org
Org
Org

0,400
4,000
5,000
2,000
0,500
0,100
0,000

Btg
Mtr
Buah
Buah
Btg
Btg
Buah
Buah
Buah

1,000
20,000
1,000
2,000
2,000
0,500
3,000
3,000
3,000

PLAT TANDA BAHAYA PADA TIANG TM.


- Stainless Steel Srip @ 0,75 mtr
- besi Plat 2 mm.
- Baut seng
- Cat dasar / Manie.
- Cat Kuning.
- Cat Merah.
- Biaya pembuatan

Bh
Lbr
Buah
Kg
Kg
Kg
Lot

1,000
0,010
3,000
0,085
0,085
0,009
1,000

RANGKA DUDUKAN TRAFO 25-50 KVA (CANTOL) :


- Besi UNP 8.
- Arm Tie type 810 Besi Siku L.50.50.5
- Single Arm Tie band.
- Bolt & Nut M.16 - 250 mm + Washer.
- Bolt & Nut M.16 - 50 mm + Washer.
- Single Arm band.
- Galvanis.
- Biaya pembuatan

Btg
Btg
set
Buah
Buah
set
Lot
Lot

0,683
1,000
1,000
2,000
9,000
2,000
1,000
1,000

1 m3 Cor Beton Manset :


Material
Upah
12.

13.

14.

GROUNDING ROD.
a. GROUNDING GARDU
- Pipa 1,5" 6 meter.
- BC 50 m.
- Bolt M.16 - 50 mm.
- Terminal Lug. 50 mm2
- Timah.
- Pipa Galvanis 1/2"
- Klem Steinless Steel @ 0,75 mtr
- Link.
- Stoping Buckle

HRG SATUAN
( Rp. )

JUMLAH
( Rp.)

No.

U R AIAN

15. a.

b.

c.

16.

17.

18.

20.

21.

22.

23.

24.

STN

VOLUME

PIPA 3" UNTUK JURUSAN (GARDU CANTOL)


- Pipa 3"
- invoring 3".

Btg
Set

1,000
1,000

PIPA 2" UNTUK JURUSAN (GARDU CANTOL)


- Pipa 2"
- invoring 2".

Btg
Set

1,000
1,000

KLEM PEG. PIPA 3".2" U/ 2 JURUSAN (GARDU CANTOL/PORTAL)


- UNP. 8 Type 600 untuk menahan pipa.
Btg
- Klem 3". 2". 2".
Set
- Single Arm band.
Set
- Bolt & Nut M.16 - 50 mm.
Buah

1,000
1,000
1,000
2,000

PONDASI T.BETON ENGKEL/TIANG BESI 11 M


-

Pondasi tiang 11 mtr

M3

0,250

Pondasi Tiang 9 mtr

M3

0,150

Pondasi Tiang Double

M3

0,940

BRIDLE FOR HEAVY GUY.


- Besi plat strip 50.5
- Galvanis.
- Biaya pembuatan

Btg
Lot
Lot

0,160
1,000
1,000

1
-

Kg
Ltr
Kg
Lbr
Hari
Hari
Hari

0,018
0,027
0,355
1,000
0,250
0,015
0,038

Lbr
Kg
Kg
Kg
Hari
Hari
Hari

3,000
0,021
0,021
0,435
0,250
0,015
0,375

- Pengecatan 1 unit Rak TR (2 x 3,16 m2)

m2

6,320

CROSS ARM TYPE 2.400 BESI KANAL UNP.10 :


- Besi UNP.10
- Biaya pembuatan
- Galvanis

Btg
Lot
Lot

0,400
1,000
1,000

KLEM PIPA 3" :


- Besi Plat Strip 50.5
- Bolt & Nut M.16 x 50
- Biaya pembuatan
- Galvanis

Btg
Bh
Lot
Lot

0,055
2,000
1,000
1,000

KLEM TIANG BETON :


- Besi Plat Strip 50.5
- Bolt & Nut M.16 x 50
- Biaya pembuatan
- Galvanis

Btg
Bh
Lot
Lot

0,110
2,000
1,000
1,000

1 SET KLEM BEUGEL :


- Besi Plat Strip 70.5
- Bolt & Nut M.16 x 50
- Biaya pembuatan
- Galvanis

Btg
Bh
Lot
Lot

0,052
2,000
1,000
1,000

M2 CAT TIANG BESI/TIANG KAYU


Cat dasar
Minyak Cat
Cat besi
Amplas
Pekerja.
Mandor.
Tukang.

1 M2 PENGECATAN RAK TR
- Amplas
- Dempul
- Cat Dasar
- Cat Besi
- Pekerja
- Mandor
- Tukang

HRG SATUAN
( Rp. )

JUMLAH
( Rp.)

No.

U R AIAN

25. a.

b.

c.

d.

e.

f.

g.

h.

STN

VOLUME

DOUBLE BAND 9",4" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,180
12,000
1,000
1,000

DOUBLE BAND 10",4" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,184
12,000
1,000
1,000

DOUBLE BAND 11",4" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,188
12,000
1,000
1,000

DOUBLE BAND 9",4",4" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,240
16,000
1,000
1,000

DOUBLE BAND 10",4",4" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,244
16,000
1,000
1,000

DOUBLE BAND 11",4",4" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,248
16,000
1,000
1,000

ARM BAND 9" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,036
2,000
1,000
1,000

ARM BAND 11" :


- Besi Plat Strip 50.5
- Bolt & Nut + Washer. ( M.16 x 50 )
- Biaya pembuatan
- Galvanis.

Btg
Set
Lot
Lot

0,044
2,000
1,000
1,000

HRG SATUAN
( Rp. )

JUMLAH
( Rp.)

ANALISA HARGA SATUAN UPAH PEMASANGAN SUTM


NAMA PAKET
:
LOKASI
:
DOKUMEN PENGADAAN :

No.

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU


DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO
No. DP.018.J/APBN-DM/LISDES-J/2012

URAIAN PEKERJAAN

STN

VOLUME

Cross Arm Type 2.000 UNP.8 / Btg


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,042
0,125
0,250

Arm Tie Type 810 (Besi L.50.50.5)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,030
0,120
0,120

Double Bolt & Nut M.16 x 300 + Washer


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,010
0,025
0,250

Bolt & Nut M.16 x 50 + Washer


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,009
0,007

Isolator Tumpu 20 KV
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,011
0,044
0,044

Isolator Tarik 20 KV
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,019
0,074
0,074

Alluminium Bending Wire 20 mm2 / Mtr


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,005
0,020
0,020

Double Bolt & Nut M.16 x 250 + Washer


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,010
0,025
0,025

Single Arm Tie Band, Single Arm Band, Double Arm


Tie Band dan Double Arm Band
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,030
0,120
0,120

Line Tap Connector/Non Tension Joint


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,010
0,040
0,040

Guy Wire TM (GW-TM)


Galvanis Stell Wire 35 mm / Mtr
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,005
0,020
0,010

Patok Schoor UNP.8 Rod Stay / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,033
0,150
0,080

Guy Insulator ( Isolator Belimbing ) / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,011
0,250
0,015

Span Schroef / Turn Buckle 5/8" / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,010
0,250
0,020

Double Guy Wire Band / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,300
0,130
0,120

HARGA
SATUAN
(Rp.)

JUMLAH
HARGA
(Rp.)

URAIAN PEKERJAAN

No.
16.

17.

18.

20.

21.

22.

23.

24.

25.

26.

27.

28.

29.

30.

STN

VOLUME

Wire Clip / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,030
0,030
0,150

Pipa Galvanis 4" @ 3 mtr / Btg


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,027
0,054
0,081

Besi Plat Strip 50.5 / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,030
0,120
0,120

Cross Arm Type 0,200 UNP.10 / Btg


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,042
0,125
0,250

Double Arm Band 9" ( u/ Atas ) / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,030
0,120
0,120

Double Arm Band 11" ( u/ Bawah ) / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,030
0,120
0,120

Tiang Listrik Penyangga / Btg


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,622
1,500
1,555

Pasang Konduktor AAAC 35 mm / Mtr


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,019
0,008

Pasang Konduktor AAAC 70 mm / Mtr


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,004
0,024
0,008

Pasang Konduktor AAAC 150 mm / Mtr


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,005
0,030
0,010

Pasang Konduktor AAAC 240 mm / Mtr


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,007
0,040
0,013

Joint Sleeve 70/150/240 mm / Bh


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,026
0,077
0,077

Plat Tanda Bahaya / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,020
0,100
0,100

Pasang LBS
- Mandor
- Tukang
- Pekerja

HO
HO
HO

1,000
6,000
4,000

HARGA
SATUAN
(Rp.)

JUMLAH
HARGA
(Rp.)

ANALISA HARGA SATUAN UPAH PEMASANGAN SUTR


NAMA PAKET
LOKASI
DOKUMEN PENGADAAN

No.

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

:
:
:

PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU


DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO
No. DP.018.J/APBN-DM/LISDES-J/2012

URAIAN PEKERJAAN

STN

VOLUME

Plastic Strap / (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,010
0,010

Stoping Buckle/ (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,010
0,010

Stainless Steel Strip @ 0,75 mtr / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,010
0,010

Suspension Clamp / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,013
0,039
0,039

Suspension Clamp Bracket / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,013
0,039
0,039

Strain Clamp / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,013
0,039
0,039

Tension Bracket / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,013
0,039
0,039

Turn Buckle / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,005
0,020
0,020

Dead End Tubes / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,008
0,008

Link / Buah
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,010
0,010

PVC 2" = 50 cm / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,016
0,050
0,050

Tap Connector TC / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,005
0,016
0,016

Earthing Rod 16 mm + Clamp / Btg


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,020
0,070
0,070

Kawat Arde AAAC 70 mm / Mtr


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,018
0,018

Kabel Schoen Bimetal Connector 70mm/Bh


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,007
0,025
0,025

HARGA
SATUAN
(Rp.)

JUMLAH
HARGA
(Rp.)

No.
16.

17.

17.

18.

19.

20.

21.

22.

23.

24.

25.

26.

27.

URAIAN PEKERJAAN

STN

VOLUME

Baut M.12 x 45 mm / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,009
0,009

Pipa Galvanis 3/4" @ 3 Mtr / Btg


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,020
0,020
0,020

Galvanis Stell Wire 22 mm / Mtr


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,004
0,020
0,010

Patok Schoor UNP 8 Rod Stay / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,020
0,150
0,070

Thimble / Buah
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,002
0,011
0,006

Wire Clip / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,004
0,020
0,015

Spanschroef / Turn Bucle 1 / 2" / Buah


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,006
0,034
0,017

Bridle for Heavy Guy / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,008
0,045
0,022

Double Guy Wire Band / Set


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,008
0,045
0,022

LVTC 3 X 70 + 1 X 50 mm2
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,005
0,020
0,030

LVTC 3 X 35 + 1 X 25 mm2
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,003
0,010
0,015

HO
HO
HO

0,003
0,010
0,015

HO
HO
HO

0,023
0,077
0,077

LVTC 3 X 25 + 1 X 25 mm2
- Mandor
- Tukang
- Pekerja
Joint Compresion / Buah
- Mandor
- Tukang
- Pekerja

/ Mtr

HARGA
SATUAN
(Rp.)

JUMLAH
HARGA
(Rp.)

ANALISA HARGA SATUAN UPAH PEMASANGAN GARDU


NAMA PAKET
: PEKERJAAN PEMBANGUNAN JARINGAN DISTRIBUSI SUTM, SUTR DAN GARDU
LOKASI
: DESA TANJUNG AUR KECAMATAN SERAI SERUMPUN - KABUPATEN TEBO
DOKUMEN PENGADAAN : No. DP.018.J/APBN-DM/LISDES-J/2012

No.

I.
1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

URAIAN PEKERJAAN

STN

VOLUME

Pasang Trafo 25 - 50 KVA/ 20 KV / (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

1,000
3,000
3,000

Pasang Trafo 50 - 100 KVA/20 KV / (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

1,000
6,000
4,000

Pasang Trafo 160 - 250 KVA/ 20 KV / (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

1,000
8,000
5,000

Lingtning Arrester 20 KV / (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,067
0,200
0,200

Cut Out 20 KV + Fuse Link / (Set)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,067
0,200
0,200

Line Tap Connector All Size / (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,010
0,040
0,040

Cross Arm Type 2500 UNP.8 Cut Out / (Set)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,042
0,125
0,250

Single/Double Arm Band / (Set)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,030
0,120
0,120

Rangka Dudukan Trafo Cantol / (Set)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,250
0,750
0,750

Rangka Dudukan Trafo Portal / (Set)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

1,000
1,000
3,000

LV Panel 400/630 A / (Set)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

1,000
3,000
4,000

HARGA
SATUAN
(Rp.)

JUMLAH
HARGA
(Rp.)

No.

12.

13.

14.

15.

16.

URAIAN PEKERJAAN

STN

VOLUME

LV Panel Trafo 25 / 50 kVA / ( Set)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

1,000
2,000
2,000

Conductor NYY/NYA 50/70/150 mm / (m')


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,011
0,044
0,048

Terminal Lug 50 - 150 mm / (Buah)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,010
0,040
0,040

Pipa Galvanis 2", 3" u/ Jurusan / (Btg)


- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,167
0,167
0,333

GROUNDING
Pentanahan / (Set)
- Mandor
- Tukang
- Pekerja

HO
HO
HO

0,157
0,600
0,600

HARGA
SATUAN
(Rp.)

JUMLAH
HARGA
(Rp.)

ANALISA HARGA MATERIAL TIANG TOWER MONOPOLE


No.

1.

U R AIAN

PEMASANGAN BOUWPLANK / M'


- Kayu 5/7
- Paku biasa 2" - 5"
- Kayu papan 3/20

STN

VOLUME

M3
Btg
Kg

0,005
0,250
0,020

HRG SATUAN
( Rp. )

Jumlah
Pembulatan
2.

A.18. PEK. URUGAN PASIR DIBAWAH LANTAI DAN PONDASI / M3


- Pasir Urug

M3

1,200
Jumlah
Pembulatan

3.

G.41. PEK. BETON CAMPURAN 1:2:3 / M3


- Semen ( PC ).
- Kerikil Beton
- Pasir Pasangan.

Zak
M3
M3

8,300
0,830
0,540
Jumlah
Pembulatan

4.

G.41.b. PEK. BETON CAMPURAN 1:3:5 / M3


- Semen ( PC ).
- Kerikil Beton
- Pasir Pasangan.

Zak
M3
M3

5,625
0,910
0,540
Jumlah
Pembulatan

5.

F.8.a. BEKESTING BETON TIDAK BERTINGKAT BETON BERTULANG / M3


- Papan Kayu
M3
- Paku
Kg

0,400
4,000
Jumlah
Pembulatan

6.

I.2. PEK. BESI BETON BERTULANG 100 Kg/ M3


- Besi beton
- Kawat beton

Kg
Kg

110,000
2,000
Jumlah
Pembulatan

7.

I.2. PEK. BESI BETON BERTULANG 225 Kg / M3


- PEK. BESI BETON BERTULANG / M3

Kg

2,250
Jumlah
Pembulatan

8.

SUPL Vi. BETON BERTULANG (1:2:3 BESI 225 Kg) BERTINGKAT/M3


- I.2. PEK. BESI BETON BERTULANG 225 Kg / M3
M3
- G.41. PEK. BETON CAMPURAN 1:2:3 / M3
M3
- F.8.a. BEKESTING BETON TIDAK BERTINGKAT BETON BERTULANG /M3
M3

1,000
1,000
1,000
Jumlah
Pembulatan

9.

GUY WIRE (Tower Monopole)


- Galvanis Steel Wire 35 mm
- Patok Schoor UNP 8 Rod Stay
- Guy Isolator
- Spanschroef / Turn Bucle 5 / 8"
- Wire Clip
- Double Guy Wire Band

Mtr
Set
Bh
Bh
Bh
Set

72,000
1,000
1,000
1,000
4,000
1,000
Jumlah
Pembulatan

10.

BOR PILE DIA 250MM / M'


- Beton K-225
- Baja Tulangan
- Casing
- Bore Pile
- Alat Bantu

M3
Kg
M2
Jam
Ls

0,106
0,189
1,247
0,007
1,000
Jumlah
Pembulatan

10.

TIANG MONOPOLE / KG
- Besi Pipa / Plat
- Biaya Galvanis

Kg
Kg

1,000
1,000
Jumlah
Pembulatan

JUMLAH
( Rp.)

ANALISA HARGA UPAH PASANG TIANG TOWER MONOPOLE


No.

1.

U R AIAN

A.1. PEK. GALIAN TANAH/M3


- Pekerja
- Mandor

STN

VOLUME

Org
Org

0,750
0,025

HRG SATUAN
( Rp. )

Jumlah
Pembulatan
2.

PEMASANGAN BOUWPLANK / M'


- Tukang
- Kepala Tukang

Org
Org

0,100
0,010
Jumlah
Pembulatan

3.

A.18. PEK. URUGAN PASIR DIBAWAH LANTAI DAN PONDASI / M3


- Pekerja
Mandor

Org
Org

0,250
0,010
Jumlah
Pembulatan

4.

G.41. PEK. BETON CAMPURAN 1:2:3 / M3


- Kepala Tukang
- Tukang
- Mandor
- Pekerja

Org
Org
Org
Org

0,100
1,000
0,300
6,000
Jumlah
Pembulatan

5.

G.41.b. PEK. BETON CAMPURAN 1:3:5 / M3


- Kepala Tukang
- Tukang
- Mandor
- Pekerja

Org
Org
Org
Org

0,050
0,500
0,300
6,000
Jumlah
Pembulatan

6.

F.8.a. BEKESTING BETON TIDAK BERTINGKAT BETON BERTULANG / M3


- Kepala Tukang
Org
- Tukang
Org
- Mandor
Org
- Pekerja
Org

0,330
3,300
0,200
4,000
Jumlah
Pembulatan

7.

I.2. PEK. BESI BETON BERTULANG 100 Kg / M3


- Kepala Tukang
- Tukang
- Pekerja

Org
Org
Org

3,000
9,000
9,000
Jumlah
Pembulatan

8.

I.2. PEK. BESI BETON BERTULANG 225 Kg / M3


- PEK. BESI BETON BERTULANG / M3

Kg

2,250
Jumlah
Pembulatan

9.

Membuat Beton Mutu K 225 + Besi 100 Kg + Bekisting / M3


- I.2. PEK. BESI BETON BERTULANG 225 Kg / M3
M3
- G.41. PEK. BETON CAMPURAN 1:2:3 / M3
M3
- F.8.a. BEKESTING BETON TIDAK BERTINGKAT BETON BERTULANG /M3
M3

1,000
1,000
1,000
Jumlah
Pembulatan

10.

GUY WIRE (Tower Monopole)


- Galvanis Steel Wire 35 mm
- Patok Schoor UNP 8 Rod Stay
- Guy Isolator
- Spanschroef / Turn Bucle 5 / 8"
- Wire Clip
- Double Guy Wire Band

Mtr
Set
Bh
Bh
Bh
Set

72,000
1,000
1,000
1,000
4,000
1,000
Jumlah
Pembulatan

JUMLAH
( Rp.)

ANALISA HARGA UPAH PASANG TIANG TOWER MONOPOLE


No.

11.

U R AIAN

BOR PILE DIA 250MM / M'


- Mandor
- Tukang
- Pekerja

STN

VOLUME

Org
Org
Org

0,0099
0,0050
0,0017

HRG SATUAN
( Rp. )

Jumlah
Pembulatan
12.

PASANG TIANG MONOPOLE / KG


- Kepala Tukang
- Tukang
- Mandor
- Pekerja

Org
Org
Org
Org

0,0060
0,0600
0,0040
0,0600
Jumlah
Pembulatan

JUMLAH
( Rp.)