RINCIAN MATERIAL KEMAJUAN PHISIK PEKERJAAN
PEKERJAAN : PEMASANGAN JARINGAN SUTR
: TC 3 X 70 + 1 X 50 mm
: TERSEBAR PT. PLN ( Persero ) Area Malang
Surat Perjanjian Pihak Pertama No. : 0250.Pj/613/AREA - MLG/2013
Surat Perjanjian Pihak Kedua No. : 0013/SPK/ML - MLG/viI/2013 VOLUME : 3000 Ms
SUMBER DANA : SKKI 01 / SAR / MAL / I / 2013 LOKASI : TERSEBAR PT. PLN ( Persero ) Area Malang
VOLUME VOLUME
NO. URAIAN PEKERJAAN SAT. REALISASI
KONTRAK K.TMB K.KRG KENDALA KETERANGAN
I SUTR 3000 3160
Perencanaan tidak sesuai
dengan realisasi, Realisasi
sesuai kebutuhan lokasi
II TIANG BETTON
1 Tiang betton 9 - 200 daN + E 24 18 6
2 Tiang betton 9 - 200 daN 42 50 8
3 Tiang betton 7 - 100 daN 8 1 7
III POLE ACCESSORIES
GROUNDING DALAM 24 18 6
1 Ground Rod 1.5 mtr + Clamp 24 18 6
2 AAAC 70 sqmm 48 36 12
3 Line Tap Connector 50 - 70 mm type G 24 18 6
4 Terminal Lug 70 mm - AI / CU 48 0 48
5 Terminal Lug 70 mm - AI / CU 0 36 36
6 Bolt M.12 + Washer 48 36 12
IV POLE SUPPORTER
1 Pemasangan Guy Wire Murni 30 34 4
3 Pemasangan Strut Pole 8 2 6
V MATERIAL POLE SUPPORTER
1 Preformed Termination 35 mm 60 68 8
2 Galvanized Steel Wire 35 mm 300 340 40
3 Beton Block 40 X 40 X 10 30 34 4
4 U - Bolt + Steel Plate 30 34 4
5 Guy Wire Rod 5/8 " ( 15 mm ) - 1.800 mm 30 34 4
6 Square Washer 16 8 12
7 Single Guy Wire Band 62 34 28
8 Strut Tie 1200 - Pipe 2" 8 2 6
9 Pipa Pelindung 3/4 " - 2000 30 34 4
10 Single Arm Band 8 2 6
11 Guy Wire Timble 30 34 4
12 Turn Buckle TM ( 5/8" ) 30 34 4
13 Wire Clip 30 34 4
14 Bolt & Nut M. 16 X 50 148 79 69
15 Strut Arm TR 8 2 6
VI POLE TOP ARRANGMENT
1 Pemasangan TR - 1 24 30 6
2 Pemasangan TR - 2 14 26 12
3 Pemasangan TR - 3 24 14 10
4 Pemasangan TR - 6 5 2 3
5 Pemasangan TR - 7 20 16 4
VII MATERIAL POLE TOP ARRANGMENT
1 Small Angle Assembly ( SAA ) 29 31 2
2 Large Angle Assembly ( LAA ) 14 26 12
3 Dead End Assembly ( DEA ) 49 32 17
4 Bundled End Assembly ( BEA ) 24 14 10
5 Crmpresion Connector for Allmunium 70 75 51 24
6 Crmpresion Connector for Allmunium 50 25 17 8
VII CONDUCTOR ACCESORIIES
1 TC 3 X 70 + 1 X 50 sqmm 3060 3160 100
2 Pondasi Type A 10 7 3
3 Stanless Steel Strip 197 176 21
PENGANGKUTAN MATERIAL Ton/m3 9.448 9.532 0.084
Mengetahui/Diperiksa :
PT. PLN (PERSERO) AREA MALANG CV. MULIA
PENGAWAS
BAMBANG SISWANTO MUHLIS FANANI
A T PENYAMBUNGAN Direktur
RENCANA KERJA / S - CURVE
NO. NOTA DINAS : 0013/SPK/ML - MLG/vii/2013
NO.KONTRAK : 0250.Pj/613/AREA - MLG/2013
PEKERJAAN : PEMASANGAN JARINGAN SUTR
: TC 3 X 70 + 1 X 50 mm
LOKASI : TERSEBAR PT. PLN ( Persero ) Area Malang
PELAKSANA : CV. MULIA
Prosentase
NO URAIAN SAT. VOL Rupiah
(%)
A PERSIAPAN
1 Pemesanan Bahan / Pabrikan & Galvanized LS
2 Perijinan LS
3 Asuransi ( Tenaga kerja / Material ) LS
4 Pemeriksaan Kwalitas Barang LS
5 Persetujuan Pelaksanaan Pekerjaan LS
6 Pelaporan Pekerjaan LS
B PELAKSANAAN
I SUTR
1 Tiang betton 9 - 200 daN + E B 18 51,165,360 21.0%
2 Tiang betton 9 - 200 daN B 50 138,236,200 58.0%
3 Tiang betton 7 - 100 daN B 1 1,501,272 11.0% 90.0%
III POLE ACCESSORIES
GROUNDING DALAM S 18
1 Ground Rod 1.5 mtr + Clamp S 18 2,155,662 0.9%
2 AAAC 70 sqmm M 36 452,304 0.8%
3 Line Tap Connector 50 - 70 mm type G B 18 52,200 1.2%
4 Terminal Lug 70 mm - AI / CU B 0
5 Terminal Lug 70 mm - AI / CU B 36 1,900,656 0.8%
6 Bolt M.12 + Washer B 36 183,024 0.2%
3.90%
IV POLE SUPPORTER
1 Pemasangan Guy Wire Murni S 34 18,351,092 0.5% 0.5%
3 Pemasangan Strut Pole S 2 810,798 0.4% 0.4%
VI POLE TOP ARRANGMENT
1 Pemasangan TR - 1 S 30 2,217,900 0.9%
2 Pemasangan TR - 2 S 26 2,158,702 0.9%
3 Pemasangan TR - 3 S 14 2,553,320 0.10%
4 Pemasangan TR - 6 S 2 388,876 0.3%
5 Pemasangan TR - 7 S 16 1,980,640 0.8%
3%
VII CONDUCTOR ACCESORIIES
1 TC 3 X 70 + 1 X 50 sqmm mtr 3160 2,970,400 0.15%
2 Pondasi Type A mtr 7 7,589,295 0.30%
3 Stanless Steel Strip mtr 176 2,722,720 0.70%
1.15%
FINISHING
1 PENGANGKUTAN MATERIAL Ton/m3 9.532 2,685,106 1.0% 1.0%
JUMLAH 240,075,527 100%
PPN 10 % 24,007,552
JUMLAH 264,083,079
Dibulatkan 264,083,079
RENCANA KERJA / S - CURVE
NO. NOTA DINAS : 1075/041/MA-MLG/2013 Tgl. 1 Oktober 2013
NO.KONTRAK : 309.Pj/631/AREA-MLG/2013 Tgl. 23 September 2013
PEKERJAAN : PEMASANGAN SUTM & GTT KHUSUS 2 TIANG
LOKASI : PENGGILINGAN BATU SINAR JAYA JL. BARAN PAGEDANGAN GONDANGLEGI
PELAKSANA : CV. TOMAH JAYA
Bulan Oktober Nopember
Prosentase
Tgl. Mulai 1 8 15 22 1 8 15 22
NO URAIAN SAT. VOL Rupiah Jumlah KETERANGAN
Tgl. Akhir 7 14 21 31 7 14 21 30
(%)
Minggu ke I II III IV I II III IV
A PERSIAPAN
1 Pemesanan Bahan / Pabrikan & Galvanized LS
2 Perijinan LS
3 Asuransi ( Tenaga kerja / Material ) LS
4 Pemeriksaan Kwalitas Barang LS
5 Persetujuan Pelaksanaan Pekerjaan LS
6 Pelaporan Pekerjaan LS
B PELAKSANAAN
I SUTM
1 Tiang Beton BH 1 5,868,650 11.54 % 11.54
2 Pole Suporter SET - 100%
3 Pole Top Arrangement SET 2 5,506,114 10.83 % 10.83
4 Konstruksi Grounding untu GW Clamp SET -
5 Anti Clambing + Danger Plate SET 1 57,708 0.11 % 0.11
6 Conduktor Acsesories KMS 0.06 -
7 AAAC-S 150 sqmm ( SPLN ) MS 184 250,240 0.49 % 11,682,712 75% 0.49
22.97 % 22.97 %
II GTT
1 Transformator UNIT 1 10,153,083 19.97 % 8.07 11.90
2 Tiang Beton BH 2 14,675,754 28.86 % 28.86
3 Pole Top Arrangement SET 2 5,506,114 10.83 % 50% 10.83
4 Conduktor & Acsesories Gardu Cantol SET 1 1,083,509 2.13% 2.13
5 Grounding Dalam SET 2 709,270 1.39 % 1.39
6 Rangka Dudukan Trafo & APP Type Khusus SET 1 5,049,000 9.93 % 9.93
7 Kabel M 34 920,380 1.81 % 1.81
8 Pondasi GTT SET 1 635,250 1.25 % 38,732,360 25% 1.25
76.17 % 76.17 %
FINISHING
1 PENGANGKUTAN MATERIAL Ton/m 1.418 432,446 0.85 % 0.85 % 0.45 0.40
JUMLAH 50,415,072 100% 100% 0%
0.00 0.00 11.54 28.86 40.26 17.69 1.65
PPN 10 % 5,041,507 SASARAN MINGGUAN
0.00 0.00 11.54 40.40 80.66 98.35 11.54
JUMLAH 55,456,579 KOMULATIVE
Dibulatkan 43,463,000
Mengetahui, PELAKSANA
PENGAWAS PEKERJAAN CV. TOMAH JAYA
TRIKORO BUDI PRANYOTO NARKHOLIS S.