RENCANA ANGGARAN BIAYA

Pekerjaan : Perluasan Jaringan TM,TR,Gardu Distribusi dan APP Pelanggan


Sasaran :
Lokasi : Jl.Pasa Dama Parit Malintang

HARGA SATUAN (Rp) NT


No Uraian Material / Kegiatan VOL STN JASA
MATERIAL JASA MATERIAL
T

I PEMASANGAN GARDU DISTRIBUSI


1 Pemasangan Gardu Distribusi 160 kvA 1 lot 92,346,300 3,835,100 T 92,346,300 3,835,100
-
II PEKERJAAN PEMASANGAN JTM -
1 Pemasangan Tiang besi 12 m 200 daN 45 btg 5,798,900 243,000 T 260,950,500 10,935,000
3 Penarikan Kawat A3CS 70 mm 3690 mtr 21,800 2,100 T 80,442,000 7,749,000
4 Pasang Kontruksi - -
TM-1 18 set 920,100 78,800 T 16,561,800 1,418,400
TM-2 17 set 2,057,300 122,600 T 34,974,100 2,084,200
TM-3 11 set 3,438,800 281,100 T 37,826,800 3,092,100

5 Pasang treck schoor (E-1) 7 set 291,400 90,100 T 2,039,800 630,700


6 Pengecatan Tiang 12 m 45 btg 83,550 94,500 T 3,759,750 4,252,500
7 Beton manchet tiang 12 m 45 btg 56,600 T 2,547,000 -
8 Pemasangan Joint Sleeve 70 mm 17 bh 24,900 15,600 423,300 265,200
- -
III PEKERJAAN PEMASANGAN JTR -
1 Penarikan LVTC 3x70+1x50 mm 1550 mtr 46,500 4,200 T 72,075,000 6,510,000
2 Pemasangan Kontruksi - -
TR-1 4 set 88,920 17,000 T 355,680 68,000
TR-2 7 set 113,820 23,000 T 796,740 161,000
TR-3 10 set 404,740 98,900 T 4,047,400 989,000
TR-4 9 set 94,320 20,600 T 848,880 185,400
- -
V PEKERJAAN SR - -
1 Jasa pemasangan SR dan APP Pelanggan 195 plg 69,700 T - 13,591,500
- -
VI TRANSPORTASI 1 lot 10,000,000 T - 10,000,000

Sub. Jumlah I… 517,648,750 61,932,000


PPN 10 % ….. 51,764,875 6,193,200
JUMLAH 569,413,625 68,125,200
TOTAL 637,538,825
Dibulatkan …………… 637,538,800