RANCANGAN ANGGARAN BIAYA

PEKERJAAN : PERENCANAAN PEMASANGAN TM,TR, DAN GARDU DISTRIBUSI


SASARAN :
LOKASI :

No
Uraian Material / Kegiatan VOL SATUAN HARGA SATUAN

I PEMASANGAN GARDU DISTRIBUSI


Pemasangan Gardu Distribusi 160 kvA 1 lot 92,346,300
II PEKERJAAN PEMASANGAN JTM
Pemasangan Tiang beton 9/ 200 daN 9 btg 2,552,400
Pemasangan Tiang beton 11/ 200 daN 13 btg 4,788,400
Pemasangan Tiang beton 13/ 350 daN 1 btg 9,425,600
Penarikan Kawat A3CS 70 mm2 2360 mtr 21,800
Pasang Kontruksi
TM-1 9 set 446,700
TM-2 3 set 2,057,300
TM-3 1 set 3,438,800
TM-4 1 set 1,077,900
Pasang treck schoor (E-1) 4 btg 291,400
III PEKERJAAN PEMASANGAN JTR
Penarikan TC AL 3x70+1x50 mm 1320 mtr 46,500
Pemasangan Kontruksi
TR-1 5 set 88,920
TR-2 2 set 136,820
TR-3 2 set 114,920
TR-9 1 set 404,740
Pasang treck schoor (E-1) 5 btg 270,700
GROUNDING 2 set 123,225
SUB JUMLAH
PPN 10%
JUMLAH
DAN GARDU DISTRIBUSI

JUMLAH

92,346,300

22,971,600
62,249,200
9,425,600
51,448,000

4,020,300
6,171,900
3,438,800
1,077,900
1,165,600

61,380,000

444,600
273,640
229,840
404,740
1,353,500
246,450
Rp 318,647,970
Rp 31,864,797
Rp 350,512,767