REKAPITULASI HARGA

PEKERJAAN PEMBANGUNAN MASJID


TASNIM

NO. PEKERJAAN JUMLAH HARGA


a b c
A PEKERJAAN PENDAHULUAN 3.443.082,15
B PEKERJAAN TANAH 24.177.959,81
C PEKERJAAN STRUKTUR BETON 184.188.639,06
D PEKERJAAN DINDING 101.853.595,19
E PEKERJAAN LANTAI & KERAMIK 79.216.973,24
F PEKERJAAN PLAFOND & ATAP 292.039.627,49
G PEKERJAAN KUSEN PINTU & JENDELA 42.068.755,42
H PEKERJAAN LISTRIK 16.927.514,62
I PEKERJAAN SANITASI 32.421.444,35
J PEKERJAAN FINISHING 47.520.452,70
JUMLAH TOTAL HARGA (Rp.) = 823.858.044,02
DIBULATKAN ( Rp. ) = 823.850.000,00
Terbilang : "Delapan Ratus Dua Puluh Tiga Juta Delapan Ratus Lima Puluh Ribu Rupiah"
RENCANA ANGGARAN & BIAYA ( RAB )
PEKERJAAN PEMBANGUNAN MASJID
TASNIM

NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA


a b c d e f=cxe
A PEKERJAAN PENDAHULUAN
1 Pembersihan Lokasi 144,00 M2 15.638,25 2.251.907,90
2 Pemasangan Bouplank 12,00 Ttk 99.264,52 1.191.174,25
3.443.082,15
B PEKERJAAN TANAH
1 Pek. Galian Tanah Pondasi Pile Cap (PC1 = 120x120x30) 18,43 M3 64.358,27 1.186.251,61
Pek. Galian Tanah Pondasi Pile Cap (PC2 = 80x80x30) 4,10 M3 64.358,27 263.611,47
2 Pek. Galian Tanah Sloof (S1) 4,96 M3 64.358,27 319.217,01
3 Pek. Galian Tanah Sloof (S2) 12,32 M3 64.358,27 792.893,87
Pek. Galian Tanah Batu Kali (S3) 9,60 M3 64.358,27 617.839,38
4 Pek. Bor Strouss dia.30cm (1 Titik = 6 Meter) 4,00 Ttk 164.550,00 658.200,00
5 Pek. Cor Strouss 1,70 M3 2.287.932,91 3.882.164,55
6 Pek. Alas Pasir tb.5cm Pondasi Pile Cap 1,41 M3 238.143,31 335.305,78
7 Pek. Alas Pasir tb.5cm (Sloof) 2,16 M3 238.143,31 514.389,55
8 Pek. Urugan Tanah Sirtu Peninggian Lantai 57,60 M3 270.973,73 15.608.086,59
24.177.959,81
C PEKERJAAN STRUKTUR BETON
1 Pek. Lantai Rabat Beton 5cm Pondasi Pile Cap 1,15 M3 714.294,54 822.867,30
2 Pek. Lantai Rabat Beton 5cm Sloof 2,16 M3 714.294,54 1.542.876,20
3 Pek. Pondasi Pile Cap (PC1) 120 x 120 x 30 6,91 M3 3.644.659,42 25.191.885,93
Pek. Pondasi Pile Cap (PC2) 80 x 80 x 30 1,54 M3 3.644.659,42 5.598.196,87
4 Pek. Sloof S1, 25/50 3,88 M3 3.438.071,86 13.322.528,47
5 Pek. Sloof S2, 20/30 4,62 M3 3.438.071,86 15.883.892,00
6 Pek. Sloof S3, 15/20 0,60 M3 3.438.071,86 2.062.843,12
7 Pek. Kolom K1, 40/40 4,48 M3 3.678.818,10 16.481.105,08
Pek. Kolom K2, 30/30 5,62 M3 3.678.818,10 20.660.242,44
8 Pek. Kolom K3, 15/30 1,94 M3 3.678.818,10 7.118.513,02
1 Pek. Balok B1, 25/60 (+6,00) 4,65 M3 3.438.071,86 15.987.034,16
2 Pek. Balok B2, 20/35 (+3,50) 2,73 M3 3.438.071,86 9.385.936,18
3 Pek. Balok B3, 15/25 (+3,50) 0,58 M3 3.438.071,86 1.998.379,27
4 Pek. Balok B4, 10/20 (+3,50) 0,08 M3 3.438.071,86 275.045,75
5 Pek. Balok Kantilever 1, 20/35~15 (+3,50) 0,72 M3 3.438.071,86 2.475.411,74
Pek. Balok Kantilever 2, 20/50~15 (+3,50) 0,26 M3 3.438.071,86 893.898,68
7 Pek. Lantai Dak Beton 12 cm (+3,50) 4,14 M3 3.909.492,81 16.194.683,03
1 Pek. Balok B3, 15/25 (+6,00) 0,72 M3 3.438.071,86 2.462.518,97
2 Pek. Balok B4, 10/20 (+6,00) 0,42 M3 3.438.071,86 1.443.990,18
4 Pek. Lantai Dak Beton 12 cm (+6,00) 6,24 M3 3.909.492,81 24.386.790,65
184.188.639,06
D PEKERJAAN DINDING
1 Pek. Dinding Pas. 1/2 Bata Merah (Top Elv. +3.50) 241,26 M2 116.476,51 28.100.540,42
Pek. Dinding Pas. 1/2 Bata Merah (Elv. +3.50 ~ +6.00) 145,20 M2 116.476,51 16.912.389,25
2 Pek. Plesteran Dinding (1pc : 5psr) 772,91 M2 42.213,77 32.627.443,42
3 Pek. Acian Dinding 772,91 M2 31.327,35 24.213.222,09
101.853.595,19
E PEKERJAAN LANTAI & KERAMIK
1 Pek. Alas Pasir Lantai tb.5cm 7,20 M3 238.143,31 1.714.631,82
2 Pek. Lantai Rabat Beton tb.5cm 7,20 M3 714.294,54 5.142.920,65
3 Pek. Lantai Granit 60x60 127,50 M2 357.616,81 45.596.143,28
4 Pek. Lantai Keramik 25x25 (Toilet) 16,00 M2 176.775,85 2.828.413,60
5 Pek. Dinding Keramik 30x60 (Toilet) 86,63 M2 207.062,01 17.936.746,18
1 Pek. Pengecatan Water Proofing (Lantai Dak Beton) 115,42 M2 51.967,75 5.998.117,71
79.216.973,24
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
a b c d e f=cxe
F PEKERJAAN PLAFOND & ATAP
1 Pek. Plafond Gypsumboard 9mm + Rk. Hollow 88,13 M2 103.201,86 9.094.663,62
2 Pek. Plafond Calciboard 3mm + Rk. Hollow 55,20 M2 207.138,88 11.434.066,40
3 Pek. Plamur Expose Dak Beton 36,51 M2 21.480,05 784.236,63
4 Pek. Rangka Atap Galvalum 64,34 M2 171.876,00 11.058.501,84
Pek. Pasang Atap Genteng Beton 122,50 M2 163.450,00 20.022.625,00
Pek. Profil Lisplank GRC 52,20 M' 105.470,00 5.505.534,00
5 Pasang Kubah Flanel Besar (Luas lingkaran 31,5 m2 + Tinggi 3,5 m) 110,32 M2 2.000.000,00 220.640.000,00
6 Pasang Kubah Flanel Kecil (Luas lingkaran 4,5 m2 + Tinggi 1,5 m) 6,75 M2 2.000.000,00 13.500.000,00
292.039.627,49
G PEKERJAAN KUSEN PINTU & JENDELA
Kusen Type PU 1,00 Unit 3.198.626,17 3.198.626,17
Kusen Type PJ 2,00 Unit 4.261.116,88 8.522.233,76
Kusen Type P1 2,00 Unit 2.180.386,71 4.360.773,41
Kusen Type P2 (PVC) 4,00 Unit 700.000,00 2.800.000,00
Kusen Type J1 4,00 Unit 2.955.233,31 11.820.933,22
Kusen Type J2a 2,00 Unit 2.075.088,69 4.150.177,38
Kusen Type J2b 6,00 Unit 1.202.668,58 7.216.011,47
42.068.755,42
H PEKERJAAN LISTRIK
1 Pek. Instalasi Titik Lampu 46,00 Ttk 218.162,11 10.035.456,88
2 Pek. Instalasi Titik Stop Kontak 12,00 Ttk 235.529,92 2.826.359,00
3 Pas. Saklar Lampu Ganda 8,00 Bh 78.229,92 625.839,33
4 Pas. Saklar Lampu Tunggal 6,00 Bh 56.329,92 337.979,50
5 Pas. MCB 1,00 Bh 111.879,92 111.879,92
6 Pas. Lampu PL 46,00 Bh 65.000,00 2.990.000,00
16.927.514,62
I PEKERJAAN SANITASI
1 Pas. Kran Air 10 Bh 85.394,68 853.946,77
2 Pas. Kloset Duduk 4 Bh 2.650.000,00 10.600.000,00
5 Pas. Floor Drain 32 Bh 81.663,91 2.613.244,99
6 Pek. Pipa Air Bersih PVC 3/4" 49 M' 25.277,43 1.238.594,19
Pek. Pipa Air Hujan PVC 2" 39 M' 35.148,78 1.370.802,48
7 Pek. Pipa Air Kotor (Pembuangan) PVC 3" 144 M' 51.933,90 7.478.481,53
8 Pek. Pipa Air Kloset PVC 4" 16 M' 60.398,40 966.374,39
9 Pek. Pompa Air 1 Unit 800.000,00 800.000,00
10 Pek. Ground Watertank 1 Unit 2.500.000,00 2.500.000,00
11 Pek. Septictank + Resapan 1 Unit 4.000.000,00 4.000.000,00
32.421.444,35
J PEKERJAAN FINISHING
2 Pek. Ornamen Fasad GRC Krawangan 10,60 M2 700.000,00 7.420.000,00
Pek. Ornamen Lis Beton 12,65 M' 250.000,00 3.162.500,00
Pek. Ornamen Dinding Motif "Bata Expose" 66,86 M2 151.499,50 10.129.256,57
Pek. Ornamen Dinding Conwood 29,00 M2 160.000,00 4.640.000,00
3 Pek. Pengecatan Dinding 772,91 M2 25.292,75 19.549.021,13
4 Pek. Pengecatan Plafon & Lisplank GRC 174,65 M2 15.000,00 2.619.675,00
47.520.452,70
JUMLAH TOTAL HARGA ( Rp. ) = 823.858.044,02