REKAP VOLUME RITASE DT BENDUNGAN KEMPO

Ritase Batu DT Bendungan Kempo

No Hari Tanggal Volume Satuan


1 Selasa 3/1/2023 - Rit
2 Rabu 3/2/2023 - Rit
3 Kamis 3/3/2023 - Rit
4 Jumat 3/4/2023 3 Rit
5 Sabtu 3/5/2023 - Rit
6 Minggu 3/6/2023 2 Rit
7 Senin 3/7/2023 3 Rit
8 Selasa 3/8/2023 7 Rit
9 Rabu 3/9/2023 - Rit
10 Kamis 3/10/2023 4 Rit
11 Jumat 3/11/2023 8 Rit
12 Sabtu 3/12/2023 Rit
13 Minggu 3/13/2023 Rit
14 Senin 3/14/2023 Rit
15 Selasa 3/15/2023 Rit
16 Rabu 3/16/2023 Rit
27

SOM

Andri Wirawan
REKAP ITEM PEKERJAAN SWAKELOLA KEMPO
Periode 2/17/2023 - 3/3/2023

No Item Pekerjaan Volume Sat Harsat Jumlah


1 Ritase angkutan batu rip-rap 49 Rit 380,000 18,620,000
2 Biaya Pekerjaan Riprap (Est 80% dari total) 646 m3 115,000 74,336,000
3 Biaya keamanan harian 1 /2mggu 700,000 700,000
4 Checker 14 /Hari 115,000 1,610,000

95,266,000
Rencana Pembayaran 3/7/2023

SCARM SOM

Septian Rizki Pramono Andri Wirawan


REKAP ITEM PEKERJAAN SWAKELOLA KEMPO
Periode 2/17/2023 - 3/3/2023

No Item Pekerjaan Volume Sat Harsat Jumlah


1 Ritase angkutan batu rip-rap 27.0 Rit 380,000 10,260,000
2 Biaya Pekerjaan Riprap (Est 80% dari total) 241.0 m3 115,000 27,715,000
3 Biaya keamanan harian 1.0 /2mggu 700,000 700,000
4 Checker 9.0 /Hari 115,000 1,035,000

39,710,000
Rencana Pembayaran 3/14/2023

SCARM SOM

Septian Rizki Pramono Andri Wirawan