I PEKERJAAN PENDAHULUAN
1 Pek. Bongkar Atap M2 1,210.50 12,760.00 15,445,980.00 1.427 1,210.500 1.427 - - -
2 Pek. Bongkar Plafond M2 965.35 12,012.00 11,595,784.20 1.071 965.350 1.071 - - -
3 Pek. Bongkar Lantai Keramik M2 839.14 18,810.00 15,784,223.40 1.458 839.140 1.458 - - -
-
II PEKERJAAN PONDASI -
1 Pek. Pengukuran dan Pas. Bouplank M1 52.00 54,450.55 2,831,428.60 0.262 52.000 0.262 - - -
2 Pek. Galian Tanah M3 48.16 69,025.00 3,324,244.00 0.307 48.160 0.307 - - -
3 Pek. Urugan Kembali Galian Tanah M3 12.04 23,008.33 277,020.29 0.026 12.040 0.026 - - -
4 Pek. Lantai Kerja Beton Cor K.100 M3 3.28 605,599.80 1,986,367.34 0.184 3.280 0.184 - - -
5 Pas. Aanstampang batu kali M3 10.16 389,839.00 3,960,764.24 0.366 10.160 0.366 - - -
6 Pondasi Batu Kali M3 17.60 747,263.00 13,151,828.80 1.215 17.600 1.215 - - -
7 Pas. Pondasi Batu Bata M2 8.05 104,218.65 838,960.13 0.078 8.050 0.078 - - -
8 Pas. Angkur Pondasi Pergola Unit 5.00 325,000.00 1,625,000.00 0.150 5.000 0.150 - - -
-
III PEKERJAAN BETON, DINDING DAN PLESTERAN -
A Pekerjaan Beton Bertulang -
1 Pek. Sloof Beton 15 x 20 cm M3 1.32 3,885,500.00 5,128,860.00 0.474 1.320 0.474 - - -
2 Pek. Sloof Beton 20 x 25 cm M3 0.53 3,651,800.00 1,935,454.00 0.179 0.530 0.179 - - -
3 Pek. Kolom Beton 13 x 13 cm M3 0.22 5,229,700.00 1,150,534.00 0.106 0.220 0.106 - - -
4 Pek. Kolom Beton 20 x 20 cm M3 1.82 5,132,800.00 9,341,696.00 0.863 1.820 0.863 - - -
5 Pek. Balok Beton 20 x 25 cm M3 1.58 3,651,800.00 5,769,844.00 0.533 1.580 0.533 0.240 0.081 876,432.000
6 Pek. Plat Beton M3 7.79 3,885,500.00 30,268,045.00 2.796 6.240 2.240 1.550 0.556 6,022,525.000
-
B Pekerjaan Dinding dan Plesteran -
1 Pas. Dinding Bata 1 : 4 1/2 bata M2 113.60 104,218.65 11,839,238.64 1.094 113.600 1.094 41.200 0.397 4,293,808.380
2 Pas. Dinding Bata 1 : 4 teb 20cm M2 24.32 208,437.30 5,069,195.14 0.468 24.320 0.468 - - -
3 Pek. Plesteran 1 : 4 Tebal 15 mm M2 227.20 47,907.05 10,884,481.76 1.006 227.200 1.006 - - -
4 Pek. Acian Pada Plesteran M2 227.20 30,814.59 7,001,074.85 0.647 227.200 0.647 82.400 0.235 2,539,122.216
5 Pek. Afwerking Pada Beton M2 4.80 110,560.34 530,689.63 0.049 4.800 0.049 4.800 0.049 530,689.632
6 Pas. Keramik motif Batu Alam Pada Dinding M2 119.37 98,262.00 11,729,534.94 1.084 119.370 1.084 - - -
7 Pas. Keramik motif Batu Alam Pada Kolom Entrance M2 34.32 98,262.00 3,372,351.84 0.312 34.320 0.312 - - -
8 Pekerjaan Kolom Pergola Kayu 15x15x2,62 Diketam Halus M3 0.29 2,853,000.00 827,370.00 0.076 0.290 0.076 - - -
9 Pekerjaan Balok Pergola Kayu 8x15 Diketam Halus M3 0.57 2,853,000.00 1,626,210.00 0.150 0.570 0.150 - - -
-
IV PEKERJAAN KOZEN DAN PINTU -
1 Pas. Pintu Panil 1 Unit 8.00 371,700.00 2,973,600.00 0.275 8.000 0.275 1.000 0.034 371,700.000
2 Pas. Pintu Panil 2 Unit 4.00 743,400.00 2,973,600.00 0.275 4.000 0.275 - - -
3 Penggantian Kozen Kayu yang Rusak M3 0.32 7,452,797.55 2,384,895.22 0.220 0.320 0.220 - - -
4 Penggantian Kozen dan Pintu Toilet Unit 7.00 1,856,000.00 12,992,000.00 1.200 7.000 1.200 - - -
5 Pas. Kozen Kayu Penghubung Dapur - Ruang Makan M3 0.08 7,452,797.55 596,223.80 0.055 0.080 0.055 - - -
6 Pas. Pintu Panil l = 90 cm Penghubung Dapur - Ruang Makan M2 1.89 537,533.15 1,015,937.65 0.094 1.890 0.094 - - -
7 Rehab Daun Jendela menjadi Pintu Panil di Ruang Makan Unit 1.00 850,000.00 850,000.00 0.079 1.000 0.079 - - -
8 Rehab Arah Bukaan Kozen dan Pintu Double Ruang Makan Unit 1.00 350,000.00 350,000.00 0.032 1.000 0.032 - - -
9 Rehab. Kaca Naco Unit 28.00 185,000.00 5,180,000.00 0.479 28.000 0.479 - - -
-
V PEKERJAAN KAP / ATAP -
1 Mengganti Kuda-kuda dan Gording yang Rusak M3 2.40 3,820,454.00 9,169,089.60 0.847 2.400 0.847 - - -
2 Pas. Angkur + Mour Baut Kg 8.24 28,000.00 230,720.00 0.021 8.240 0.021 - - -
3 Pas. Lisplank GRC Double tbl. 8 mm M1 - 52,552.50 - - - - -
4 Penggantian Lisplank Papan tbl. 4 cm M3 0.95 2,361,046.26 2,242,993.95 0.207 0.950 0.207 - - -
5 Pekerjaan Papan Pergola Kayu 2,5x20 Diketam Halus M3 0.60 2,853,000.00 1,711,800.00 0.158 0.600 0.158 - - -
6 Pekerjaan Kuda-kuda Kanopi Selasar 6/12 M3 0.27 2,853,000.00 770,310.00 0.071 0.270 0.071 - - -
7 Pekerjaan Rangka Kuda-kuda Kanopi Selasar 5/10 M3 0.05 2,853,000.00 142,650.00 0.013 0.050 0.013 - - -
8 Pas. Atap Spandek 0,4 M2 - 147,121.70 - - - - -
9 Pas. Atap Spandek 0,3 M2 1,210.50 121,971.30 147,646,258.65 13.640 1,210.500 13.640 - - -
10 Pas Bola-bola/Nok Samping Atap M1 135.22 55,943.25 7,564,646.27 0.699 135.220 0.699 - - -
11 Pas Perabung Atap M1 93.00 63,203.25 5,877,902.25 0.543 93.000 0.543 - - -
12 Pas. Atap Polycarbonate Pergola M2 42.80 325,000.00 13,910,000.00 1.285 42.800 1.285 - - -
13 Pas. Atap Polycarbonate Selasar M2 30.00 325,000.00 9,750,000.00 0.901 30.000 0.901 - - -
-
VI PEKERJAAN PLAFON -
1 Pas. Rangka Besi Hollow 20 x 40 x 0,4 mm M2 904.50 60,989.50 55,165,002.75 5.096 904.500 5.096 - - -
2 Pas. Gipsum Board tebal 9 mm M2 1,310.10 47,515.33 62,249,833.83 5.751 1,310.100 5.751 - - -
3 Pas. Les Gipsum tebal 9 mm M2 67.90 47,515.33 3,226,290.91 0.298 67.900 0.298 - - -
4 Rehab dan droping up Rangka Plafon M2 16.80 60,989.50 1,024,623.60 0.095 16.800 0.095 - - -
-
VII PEKERJAAN LANTAI -
1 Pas. Keramik Lantai 60 x 60 cm Polished M2 637.90 112,002.75 71,446,554.23 6.600 637.900 6.600 - - -
2 Pas. Keramik Lantai 60 x 60 cm Unpolished M2 235.74 112,002.75 26,403,528.29 2.439 235.740 2.439 - - -
3 Pas. Keramik Dinding 20x40 di Toilet M2 258.46 98,262.00 25,396,796.52 2.346 258.460 2.346 - - -
4 Pas. Keramik Lantai 40x40 M2 205.47 98,262.00 20,189,893.14 1.865 205.470 1.865 - - -
5 Pas. Keramik lantai motif Batu Alam M3 115.70 98,262.00 11,368,913.40 1.050 115.700 1.050 - - -
-
VIII PEKERJAAN PENGECATAN -
1 Pek. Cat Dinding Tembok/Beton (Cat Air) M2 1,221.20 18,922.20 23,107,790.64 2.135 1,221.200 2.135 - - -
2 Pek. Cat Plafon Gipsum + Les (Cat Air) M2 1,310.10 18,922.20 24,789,974.22 2.290 1,310.100 2.290 - - -
3 Pek. Cat Lisplank GRC (Cat Minyak) M2 117.69 35,363.90 4,161,977.39 0.384 117.690 0.384 - - -
4 Pek Cat. Kayu Kozen, Pintu dan Jendela M2 124.21 35,363.90 4,392,550.02 0.406 124.210 0.406 - - -
5 Pek. Cat Kayu Pergola dengan Cat Melamic 4x jalan M2 25.95 65,300.00 1,694,535.00 0.157 25.950 0.157 - - -
-
IX PEKERJAAN PERLENGKAPAN DAN INTERIOR -
1 Pas. Instalasi Titik Lampu + Fitting Ttk 56.00 145,000.00 8,120,000.00 0.750 56.000 0.750 - - -
2 Pas. Sakelar Bh 41.00 36,250.00 1,486,250.00 0.137 41.000 0.137 - - -
3 Pas. Stop Kontak Bh 35.00 36,250.00 1,268,750.00 0.117 35.000 0.117 - - -
4 Pas. Downlight 3" + Lampu SL 18 Wat Bh 56.00 79,750.00 4,466,000.00 0.413 56.000 0.413 - - -
5 Pas. Washtafel Set Unit 11.00 1,584,125.00 17,425,375.00 1.610 11.000 1.610 - - -
6 Pas. Closet Duduk Komplit Unit 2.00 1,667,500.00 3,335,000.00 0.308 2.000 0.308 - - -
7 Pas. Jet Washer Unit 6.00 90,625.00 543,750.00 0.050 6.000 0.050 - - -
8 Pas. Kaca Cermin Set Unit 6.00 543,750.00 3,262,500.00 0.301 6.000 0.301 - - -
9 Pek. Interior Bahan dan Rangka Multiplek Fin. HPL M2 147.26 1,341,250.00 197,512,475.00 18.247 147.260 18.247 - - -
10 Pas. Wallpaper Dinding M2 311.60 87,725.00 27,335,110.00 2.525 311.600 2.525 - - -
11 Instalasi Stop Kontak Ttk 2.00 145,000.00 290,000.00 0.027 2.000 0.027 - - -
12 Instalasi Air Panas Selang Pipa Flexibel 1/2" + Acc M1 28.00 78,000.00 2,184,000.00 0.202 28.000 0.202 - - -
13 Instalasi Air Bersih PVC 3/4" + Acc M1 65.00 39,909.10 2,594,091.50 0.240 65.000 0.240 - - -
14 Instalasi Pipa PVC 3" + Acc M1 32.00 79,949.10 2,558,371.20 0.236 32.000 0.236 - - -
15 Instalasi Pipa PVC 4" + Acc M1 28.00 110,133.10 3,083,726.80 0.285 28.000 0.285 - - -
16 Penggantian Kran Air Stainless Steel Unit 22.00 67,808.13 1,491,778.86 0.138 22.000 0.138 - - -
17 Pas. Kran Air Dingin/Panas Stainless Steel Unit 4.00 438,508.13 1,754,032.52 0.162 4.000 0.162 - - -
18 Pemindahan Kitchen Zink + Perbaikan kembali Unit 3.00 455,000.00 1,365,000.00 0.126 3.000 0.126 - - -
19 Meja Beton Dapur M1 5.60 245,000.00 1,372,000.00 0.127 5.600 0.127 - - -
20 Pembuatan Pintu Meja Dapur Rangka Multiplek Fin, HPL M2 6.94 1,341,250.00 9,308,275.00 0.860 6.940 0.860 - - -
21 Pas. Top table Granit Marmer untuk meja Dapur M2 12.60 1,350,000.00 17,010,000.00 1.571 12.600 1.571 - - -
22 Pas. Kran Zink Stainless Steel Unit 3.00 218,508.13 655,524.39 0.061 3.000 0.061 - - -
23 Pas. Closet Jongkok Unit 7.00 700,221.77 4,901,552.39 0.453 7.000 0.453 - - -
24 Pas. Closet Duduk Type A Untuk Ruang Kelas I dan II Unit 4.00 3,576,892.00 14,307,568.00 1.322 4.000 1.322 - - -
25 Pas. Floor Drain Stainless Steel Bh 22.00 78,705.00 1,731,510.00 0.160 22.000 0.160 - - -
26 Pas. Bak Air ex walrus/setara Bh 11.00 485,000.00 5,335,000.00 0.493 11.000 0.493 - - -
27 Pas Unit Septicktank Unit 1.00 7,500,000.00 7,500,000.00 0.693 1.000 0.693 - - -

Jumlah Bobot Pekerjaan : ### 100.000 99.444% 1.352% 14,634,277