REKAPITULASI ANGGARAN BIAYA

PEKERJAAN : WORKSHOP BILLIARD


LOKASI : KOTA KENDARI

JUMLAH
NO URAIAN DAN JENIS PEKERJAAN
HARGA
I. PEKERJAAN STRUKTUR 460,931,534.34
II. PEKERJAAN ARSITEKTUR 540,117,827.98
III. PEKERJAAN MEP 101,624,995.00
IV. PENGADAAN BARANG 1,255,200,000.00
A REAL COST 2,357,874,357.33
C TOTAL Rp 2,357,850,000.00

Terbilang : DUA MILIAR TIGA RATUS LIMA PULUH TUJUH JUTA DELAPAN RATUS LIMAH PULUH RIBU RUPIAH
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : WORKSHOP BILLIARD


LOKASI : KOTA KENDARI

HARGA SATUAN JUMLAH HARGA


NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
I. PEKERJAAN STRUKTUR
A. Pekerjaan Tanah dan Pondasi
1 Pek. Galian Pondasi Menerus M3 225.00 116,500.00 26,212,500.00
2 Pek. Galian Pondasi Menerus M3 3.00 116,500.00 349,500.00
3 Pek. Urugan Tanah Kembali M3 75.00 38,800.00 2,910,000.00
4 Pek. Batu Kosong (Aanstamping) M3 45.00 699,000.00 31,455,000.00
5 Pek. Pondasi Batu Belah M3 126.00 1,188,100.00 149,700,600.00
6 Pek. Pasangan Sloof 20/35
- Pek. Beton Mutu K-175 M3 9.00 1,297,700.00 11,679,300.00
- Pek. Pembesian KG 2,468.37 32,666.00 80,631,774.42
- Pek. Bekisting M2 39.38 48,120.00 1,894,725.00
7 Pek. Pondasi Poer Plat Beton Bertulang
- Pek. Beton Mutu K-175 M3 0.13 1,297,700.00 168,701.00
- Pek. Pembesian KG 455.69 32,666.00 14,885,717.19
- Pek. Bekisting M2 1.14 48,120.00 54,856.80
- Pek. Rabat Beton Lantai tebal 5 cm M3 0.10 1,142,400.00 111,955.20
- Pek. Urugan pasir bawa pondasi M3 0.10 262,600.00 25,734.80
Jumlah 320,080,364.41
B. Pekerjaan Dinding dan Rangka Bangunan
1 Pek. Pasangan Kolom 25/25
- Pek. Beton Mutu K-175 M3 3.92 1,297,700.00 5,080,495.50
- Pek. Pembesian KG 880.88 32,666.00 28,774,662.75
- Pek. Bekisting untuk 5x Pakai M2 43.50 72,800.00 3,166,800.00
2 Pek. Pasangan Kolom Teras 20/20
- Pek. Beton Mutu K-175 M3 1.14 1,297,700.00 1,479,378.00
- Pek. Pembesian KG 97.11 32,666.00 3,172,121.22
- Pek. Bekisting untuk 5x Pakai M2 4.05 72,800.00 295,082.67
3 Pek. Pasangan Balok Latei 13/13
- Pek. Beton Mutu K-175 M3 0.82 1,297,700.00 1,065,852.92
- Pek. Pembesian KG 166.98 32,666.00 5,454,485.38
- Pek. Bekisting untuk 5x Pakai M2 6.32 48,120.00 304,022.16
4 Pek. Pasangan Balok Latei 15/15
- Pek. Beton Mutu K-175 M3 0.47 1,297,700.00 603,819.81
- Pek. Pembesian KG 44.84 32,666.00 1,464,757.94
- Pek. Bekisting untuk 5x Pakai M2 3.10 48,120.00 149,268.24
5 Pek. Pasangan Ringbalok 15/20
- Pek. Beton Mutu K-175 M3 3.38 1,297,700.00 4,379,737.50
- Pek. Pembesian KG 309.62 32,666.00 10,113,981.59
- Pek. Bekisting untuk 5x Pakai M2 7.50 48,120.00 360,900.00
6 Pek. Pasangan Kanopi keliling Tebal 12 cm
- Pek. Beton Mutu K-175 M3 1.33 1,297,700.00 1,730,093.64
- Pek. Pembesian KG 44.40 32,666.00 1,450,225.36
- Pek. Bekisting untuk 5x Pakai M2 4.44 48,120.00 213,845.28
7 Pek. Pasangan Kanopi keliling Tebal 22 cm
- Pek. Beton Mutu K-175 M3 2.44 1,297,700.00 3,171,838.34
- Pek. Pembesian KG 64.13 32,666.00 2,094,769.97
- Pek. Bekisting untuk 5x Pakai M2 7.41 48,120.00 356,408.80
8 Pek. Pasangan Kanopi Teras
- Pek. Beton Mutu K-175 M3 0.92 1,297,700.00 1,193,884.00
- Pek. Pembesian KG 19.40 32,666.00 633,811.86
- Pek. Bekisting untuk 5x Pakai M2 4.60 48,120.00 221,352.00
9 Pek. Pasangan Bata Merah Camp. 1 : 4 M2 442.35 144,500.00 63,919,575.00
Jumlah 140,851,169.93
Total Sub-Pekerjaan Struktur 460,931,534.34
HARGA SATUAN JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6

II. PEKERJAAN ARSITEKTUR


A. Pekerjaan Lantai
1 Pek. Rabat Beton Lantai tebal 5 cm M3 8.40 1,142,400.00 9,596,160.00
2 Pek. Urugan Pasir Bawah Lantai M3 8.40 262,600.00 2,205,840.00
3 Pek. Urugan Tanah Bawah Lantai M3 33.60 137,500.00 4,620,000.00
4 Pek. Lantai Keramik 80 x 80 M2 145.00 807,200.00 117,044,000.00
5 Pek. Lantai Keramik 40 x 40 M2 26.36 584,100.00 15,396,876.00
6 Pek. Plint Lantai Keramik 10 x 60 M1 98.75 63,100.00 6,231,125.00
7 Pek. Keramik 20x20 untuk KM M2 5.93 218,400.00 1,295,112.00
8 Pek. Keramik 20x20 untuk dinding KM M2 27.27 289,000.00 7,881,030.00
Jumlah 164,270,143.00
B. Pekerjaan Plesteran
1 Pek. Plesteran Dinding Camp. 1 : 5 tebal 1,5 cm M2 799.60 52,800.00 42,218,880.00
2 Pekerjaan Acian Dinding M2 799.60 57,100.00 45,657,160.00
Jumlah 87,876,040.00
C. Pekerjaan Plafond dan Atap
1 Pek. Rangka Baja ringan M2 366.30 193,842.50 71,004,578.75
2 Pek. Atap Spandek M2 366.30 127,300.00 46,630,036.63
3 Pek. Nok dan Jurai Atap Metal M1 80.36 109,000.00 8,759,240.00
4 Pek. Listplank 1x20 cm M1 300.00 83,800.00 25,140,000.00
5 Pek. Rangka Plafond Besi Hollow Modul 60 x 60 cm M2 154.45 244,100.00 37,701,245.00
6 Pek. Plafond Gypsum t= 9 mm M2 154.45 165,200.00 25,515,140.00
7 Pas. List Plafond Gipsum M1 132.80 24,600.00 3,266,880.00
Jumlah 218,017,120.38
D. Pekerjaan Kusen dan Aksesoris
1 Pek. Pengadaan dan Pemasangan Pintu Kayu(P01)
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.06 9,628,000.00 577,680.00
2. Pembuatan dan Pemasangan Daun Pintu Kayu Kelas II M3 0.06 1,188,000.00 68,904.00
3. Pek. Pemasangan Handle Pintu dan Kunci Tanam BH 2.00 268,500.00 537,000.00
4. Pek. Pemasangan Kaca pintu 3mm M2 0.27 131,300.00 35,451.00
5. Pek. Pemasangan Engsel Pintu BH 6.00 66,500.00 399,000.00
2 Pek. Pengadaan dan Pemasangan Pintu Kayu(P02) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.18 9,628,000.00 1,684,900.00
2. Pembuatan dan Pemasangan Daun Pintu Kayu Kelas II M3 0.20 1,188,000.00 237,600.00
3. Pek. Pemasangan Handle Pintu dan Kunci Tanam BH 5.00 268,500.00 1,342,500.00
4. Pek. Pemasangan Engsel Pintu BH 15.00 66,500.00 997,500.00
3 Pek. Pemasangan Pintu WC BH 2.00 920,000.00 1,840,000.00
4 Pek. Pengadaan dan Pemasangan Pintu Jendela Aluminium(PJ01) -
1. Pembuatan dan Pemasangan Kusen Aluminium M1 13.00 126,300.00 1,641,900.00
2. Pembuatan dan Pemasangan Daun Pintu Aluminium M2 3.34 1,039,400.00 3,475,753.60
3. Pek. Pemasangan Handle Pintu dan Kunci Tanam BH 2.00 268,500.00 537,000.00
4. Pek. Rel sliding door SET 2.00 300,000.00 600,000.00
5. Pek. Pemasangan Kaca pintu 3mm M2 5.14 131,300.00 674,882.00
5 Pek. Pengadaan dan Pemasangan Jendela Kayu(J01) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.10 9,628,000.00 914,660.00
2. Pembuatan dan Pemasangan Daun Jendela Kayu Kelas II M3 0.32 1,188,000.00 380,160.00
3. Pek. Pasangan Engsel Jendela BH 8.00 54,300.00 434,400.00
4. Pek. Pasangan Grendel Daun Jendela BH 4.00 47,500.00 190,000.00
5. Pek. Pemasangan Kaca Jendela 3mm M2 2.32 131,300.00 304,616.00
6.Pek. Pasangan Kait Daun Jendela Standar BH 8.00 36,500.00 292,000.00
HARGA SATUAN JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
6 Pek. Pengadaan dan Pemasangan Jendela Kayu(J02) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.25 9,628,000.00 2,407,000.00
2. Pembuatan dan Pemasangan Daun Jendela Kayu Kelas II M3 0.80 1,188,000.00 950,400.00
3. Pek. Pasangan Engsel Jendela BH 20.00 54,300.00 1,086,000.00
4. Pek. Pasangan Grendel Daun Jendela BH 10.00 47,500.00 475,000.00
5. Pek. Pemasangan Kaca Jendela 3mm M2 5.20 131,300.00 682,760.00
6.Pek. Pasangan Kait Daun Jendela Standar BH 20.00 36,500.00 730,000.00
7 Pek. Pengadaan dan Pemasangan Jendela Kayu(J03) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.06 9,628,000.00 577,680.00
2. Pembuatan dan Pemasangan Daun Jendela Kayu Kelas II M3 0.12 1,188,000.00 142,560.00
3. Pek. Pasangan Engsel Jendela BH 4.00 54,300.00 217,200.00
4. Pek. Pasangan Grendel Daun Jendela BH 4.00 47,500.00 190,000.00
5. Pek. Pemasangan Kaca Jendela 3mm M2 0.78 131,300.00 102,414.00
6.Pek. Pasangan Kait Daun Jendela Standar BH 4.00 36,500.00 146,000.00
8 Pek. Pengadaan dan Pemasangan Jendela Kayu(J04) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.05 9,628,000.00 433,260.00
2. Pembuatan dan Pemasangan Daun Jendela Kayu Kelas II M3 0.01 1,188,000.00 16,632.00
3. Pek. Pasangan Grendel Daun Jendela BH 2.00 47,500.00 95,000.00
4. Pek. Pemasangan Kaca Jendela 3mm M2 0.92 131,300.00 120,796.00
5.Pek. Rel sliding BH 2.00 300,000.00 600,000.00
9 Pek. Pengadaan dan Pemasangan Jendela Kayu(J05) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.07 9,628,000.00 673,960.00
2. Pembuatan dan Pemasangan Daun Jendela Kayu Kelas II M3 0.21 1,188,000.00 249,480.00
3. Pek. Pasangan Engsel Jendela BH 6.00 54,300.00 325,800.00
4. Pek. Pasangan Grendel Daun Jendela BH 3.00 47,500.00 142,500.00
5. Pek. Pemasangan Kaca Jendela 3mm M2 1.44 131,300.00 189,072.00
6.Pek. Pasangan Kait Daun Jendela Standar BH 6.00 36,500.00 219,000.00
10 Pek. Pengadaan dan Pemasangan Ventilasi Kayu(VWC) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.04 9,628,000.00 385,120.00
2. Pek. Pemasangan Kaca Jendela 3mm M2 0.48 131,300.00 63,024.00
11 Pek. Pengadaan dan Pemasangan Ventilasi Kayu(VJ1) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.04 9,628,000.00 404,376.00
2. Pek. Pemasangan Kaca Jendela 3mm M2 0.44 131,300.00 57,772.00
12 Pek. Pengadaan dan Pemasangan Ventilasi Kayu(VP1) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.02 9,628,000.00 192,560.00
2. Pek. Pemasangan Kaca Jendela 3mm M2 0.30 131,300.00 39,390.00
13 Pek. Pengadaan dan Pemasangan Ventilasi Kayu(VP2) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.03 9,628,000.00 308,096.00
2. Pek. Pemasangan Kaca Jendela 3mm M2 0.36 131,300.00 47,268.00
14 Pek. Pengadaan dan Pemasangan Ventilasi Kayu(VJ5) -
1. Pembuatan dan Pemasangan Kusen Kayu Kelas II M3 0.03 9,628,000.00 250,328.00
2. Pek. Pemasangan Kaca Jendela 3mm M2 0.35 131,300.00 45,955.00
15 Pek. Pemasangan Lubang Udara Roster Block BH 18.00 35,000.00 630,000.00
Jumlah 30,362,309.60
HARGA SATUAN JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
E. Pekerjaan Pengecetan
1 Pek. Pengecetan Tembok Baru (Cat Dasar, Cat Penutup) M2 799.60 34,500.00 27,586,200.00
2 Pek. Pengecetan Plafond Gypsum (Plamur, Cat Penutup) M2 182.87 34,500.00 6,309,015.00
3 Pek. PengecetanPengecatan Kalsiplank 3 x sapu Cat Minyak M2 90.00 63,300.00 5,697,000.00
Jumlah 39,592,215.00
Total Sub-Pekerjaan Arsitektur 540,117,827.98

III. PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING


A. Pekerjaan Instalasi Listrik
1 Pek. Pasangan Instalasi Penerangan TITIK 100.00 331,200.00 33,120,000.00
2 Pek. Pas. Lampu HIAS LED BH 8.00 2,300,000.00 18,400,000.00
3 Pek. Pas. Lampu LED 11 Watt Setara Philips BH 60.00 199,900.00 11,994,000.00
4 Pek. Pas. Lampu LED 5 Watt BH 20.00 174,000.00 3,480,000.00
5 Pek. Pasangan Stop Kontak Tanam BH 30.00 90,100.00 2,703,000.00
6 Pek. Pasang Saklar Ganda Tanam BH 20.00 108,800.00 2,176,000.00
7 Pek. Pasang Saklar Tunggal Tanam BH 20.00 98,800.00 1,976,000.00
Jumlah 73,849,000.00
B. Pekerjaan Jaringan Air
1 Pek. Pemasangan Floor Drain BH 6.00 80,000.00 480,000.00
2 Pek. Pemasangan Closet Duduk BH 3.00 1,341,300.00 4,023,900.00
3 Pek. Pemasangan Closet Jongkok BH 3.00 541,300.00 1,623,900.00
4 Pek. Pemasangan Kran Air 1/2" BH 10.00 138,500.00 1,385,000.00
5 Pek. Pemasangan Pipa PVC dia. 1/2" M1 101.65 26,300.00 2,673,395.00
6 Pek. Pemasangan Pipa PVC dia. 3" M1 42.00 121,900.00 5,119,800.00
7 Pek. Pemasangan Pipa PVC dia. 4" M1 50.00 149,400.00 7,470,000.00
8 Pek. Pembuatan Septic Tank + Resapan LS 2.00 2,500,000.00 5,000,000.00
Jumlah 27,775,995.00
Total Sub-Pekerjaan Mekanikal Elektrikal Plumbing 101,624,995.00
RENCANA ANGGARAN BIAYA PENGADAAN BARANG (RABPB)

PEKERJAAN : WORKSHOP BILLIARD


LOKASI : KOTA KENDARI

HARGA SATUAN JUMLAH HARGA


NO. URAIAN DAN JENIS BARANG SAT VOLUME
(Rp) (Rp)
1 2 4 5 6

1 Meja Billiard Bh 20 35,250,000.00 705,000,000.00


2 Stik Billiard Bh 120 425,000.00 51,000,000.00
3 Rak Stick Billiard Bh 20 900,000.00 18,000,000.00
4 Kursi Tunggu bench 3 Sheet Bh 40 2,600,000.00 104,000,000.00
5 Coffe Table Bh 20 1,400,000.00 28,000,000.00
6 Sound System Entertaint Bh 12 1,000,000.00 12,000,000.00
7 TV 43 Inch Bh 8 7,500,000.00 60,000,000.00
8 Kursi Duduk/makan Single Bh 34 1,200,000.00 40,800,000.00
9 Meja Makan 4 seat 80 x 150 Bh 6 7,200,000.00 43,200,000.00
10 Meja Kasir Bh 1 49,500,000.00 49,500,000.00
11 Mesin Kasir Bh 1 7,000,000.00 7,000,000.00
12 Floor Standing AC 5 Pk Bh 2 25,500,000.00 51,000,000.00
13 AC 2 Pk Bh 8 6,500,000.00 52,000,000.00
14 Kursi Soffa 2 Seat Bh 4 6,250,000.00 25,000,000.00
15 Kursi Soffa 3 Seat Bh 1 8,700,000.00 8,700,000.00
-
Jumlah 1,255,200,000.00
REKAPITULASI ANGGARAN BIAYA BAHAN

PEKERJAAN : RUMAH TINGGAL


LOKASI : KOTA KENDARI
OWNER : MRS. S

JUMLAH
NO URAIAN DAN JENIS PEKERJAAN
HARGA
I. PEKERJAAN STRUKTUR 334,805,959.13
II. PEKERJAAN ARSITEKTUR 277,733,455.93
III. PEKERJAAN MEP 74,962,366.90
A REAL COST 687,501,781.96
B TOTAL Rp 687,500,000.00

Terbilang : TIGA RATUS ENAM PULUH DELAPAN JUTA SEMBILAN RATUS LIMA PULUH RIBU RUPIAH
BACKUP DATA

SKETSA/ GAMBAR PERHITUNGAN VOLUME

PEKERJAAN PERSIAPAN A PEKERJAAN PERSIAPAN


1 Pembersihan Lokasi = 1.00 Ls
2 Pek. Pengukuran Pem,asangan Bouwplank = 1.00 M'
3 Penyediaan Air Kerja / P3K = 1.00 Ls

PEKERJAAN TANAH DAN PASIR 1 PEKERJAAN TANAH DAN PASIR


CARPORT 1 Pek. Penggalian 1 m3 tanah biasa sedalam 1 m Pondasi Batu gunung
Panjang 18.00 Panjang 225.00
Lebar 0.8 Lebar 1
Tinggi 0.80 Tinggi 1.00

VOL. = PANJANG X LEBAR X TINGGI

= 225.00 X 1.00 X 1.00

= 225.00 M3

2 Pek. Penggalian Pondasi Poerplat


Panjang 1.00
Lebar 1
Tinggi 1.50

VOL. = PANJANG X LEBAR X TINGGI

= 1.00 X 1.00 X 1.50

= 3.00 M3

3 Pek. Urugan Kembali Alur Pondasi Batu Gunung

= 1/3 X Volume Galian VOL. = 1/3 X Volume Galian

= 1/3 X 18.00 = 1/3 X 225.00

= 6.00 M3 = 75.00 M3

4 Pek. Urugan Pasir Alas Pondasi


PANJANG = 225.00
LEBAR = 1.00
TINGGI = 0.07
VOL. = PANJANG X LEBAR X TINGGI
VOL. = PANJANG X LEBAR X TINGGI
= 18.00 X 1.00 X 0.07
= 225.00 X 1.00 X 0.07
= 1.26 M3
= 15.75 M3

5 Pek. Urugan Tanah Alas Lantai


Urugan dalam bangunan :
LUAS 164.14
Tinggi 0.30

VOL. = LUAS X TINGGI

= 164.14 X 0.30

= 49.24 M3

TOTAL VOLUME URUGAN = 49.24 M3

6 Pek. Urugan Pasir Bawah Lantai


Pasir dalam bangunan :
LUAS = 164.14
Tinggi = 0.05

VOL. = LUAS X TINGGI

= 164.14 X 0.05

= 8.21 M3

TOTAL VOLUME URUGAN = 8.21 M3

PEKERJAAN FONDASI PEKERJAAN FONDASI

1 Pek. Pas. Batu Kosong Bawah Pondasi


Panjang 225.00
lebar 1
Tinggi 0.20

VOL. = PANJANG X LEBAR X TINGGI VOL. = PANJANG X LEBAR X TINGGI

= 18.00 X 1 X 0.20 = 225.00 X 1 X 0.20

= 3.60 M3 = 45.00 M3

2 Pek. Pas. Pondasi BT. Gunung 1 : 3


Lebar atas 0.40
Lebar Bawah 1
Tinggi 0.8
Panjang 225.00

VOL. = (LA+LB)/2 X TINGGI X PANJANG VOL. = (LA+LB)/2 X TINGGI X PANJANG

= 0.70 X 0.8 X 18.00 = 0.70 X 0.8 X 225

= 10.08 M3 = 126.00 M3
PEKERJAAN BETON PEKERJAAN BETON
1 Pek. Membuat 1 m3 Lantai Kerja (Rabat Beton)
rabat beton dalam bangunan :
LUAS = 164.14
TINGGI = 0.10

VOL. = LUAS X TINGGI

= 164.14 X 0.10

= 16.41 M3

TOTAL VOLUME RABAT = 16.41 M3

2 Pek. Sloof Uk. 20 X 35 cm


- Pek. Bekisting
PANJANG = 225.00
SISI BEKISTING = 0.70

VOL. = PANJANG X SISI BEKISTING VOL. = PANJANG X SISI BEKISTING

= 18.00 X 0.7 = 225.00 X 0.7

= 3.15 M2 = 39.38 M2

- Pek. Pembesian
Pembesian Tulangan DIA 12 :
Panjang = 225.00
Jumlah Tulangan = 8
Massa Jenis = 0.888

VOL. = PANJANG X JUMLAH X MASSA JENIS VOL. = PANJANG X JUMLAH X MASSA JENIS

= 18.00 X 8 X 0.888 = 225.00 X 8 X 0.888

= 127.87 KG = 1598.40 KG 12
= 10.656
Pembesian Begel DIA 10 :
Jumlah Begel = 1500.00 = 266400
Panjang Begel = 0.94 = 60419520
Massa Jenis = 0.617

VOL. = JUMLAH X PANJANG X MASSA JENIS VOL. = JUMLAH X PANJANG X MASSA JENIS

= 90.00 X 0.94 X 0.617 = 1500.00 X 0.94 X 0.617

= 52.20 KG = 869.97 KG
= 12
TOTAL = 180.07 KG TOTAL = 2468.37 KG = 7.404
= 185100
- Pek. Beton Mutu f'c = 19.3 MPa (K.175) = 35671523.06962
Panjang = 225.00 96091043.06962
Lebar = 0.2
Tinggi = 0.2

VOL. = PANJANG X LEBAR X TINGGI VOL. = PANJANG X LEBAR X TINGGI

= 18.00 X 0.2 X 0.2 = 225.00 X 0.2 X 0.2

TOTAL = 0.72 M3 TOTAL = 9.00 M3

2.A PEK.PONDASI POERPLAT

BETON = 0.13 M3

BEKISTING = 1.14 M2

BESI POER = 1.56 X 46.66666666667 X 10 X 0.617


= 449.18 KG

BESI PEDESTAL
TULANGAN UTAMA = 8.00 X 0.9 X 0.617
= 4.44 KG

BEUGEL BESI 8 = 0.73 X 7.2 X 0.395


= 2.08 KG
BESI 10 = 453.62
TOTAL = 455.69

3 Pek. Kolom Utama Uk. 25 x 25 cm


- Pek. Bekisting
TINGGI = 4.5
LEBAR = 0.25
JUMLAH SISI = 4.00

VOL. = TINGGI X LEBAR X JUMLAH SISI X JUMLAH

= 4.50 X 0.25 X 4.00 X 29

= 43.50 M2

- Pek. Pembesian
Pembesian Tulangan DIA 12 :
TINGGI = 4.5
Jumlah Tulangan = 6
Massa Jenis = 0.888
jumlah = 29

VOL. = TINGGI X JUMLAH X MASSA JENIS X JUMLAH

= 4.50 X 6 X 0.888 X 29

= 695.30 KG

- Pembesian Begel DIA 8 :


Jumlah Begel = 30.00
Panjang Begel = 0.54
Massa Jenis = 0.395

VOL. = JUMLAH X PANJANG X MASSA JENIS X JUMLAH

= 30.00 X 0.54 X 0.395 X 29


= 185.57 KG

TOTAL = 880.88 KG

- Pek. Beton Mutu f'c = 19.3 MPa (K.175)


PANJANG = 0.15
Lebar = 0.2
Tinggi = 4.5
jumlah = 29

VOL. = PANJANG X LEBAR X TINGGI X JUMLAH

= 0.15 X 0.2 X 4.5 X 29

TOTAL = 3.92 M3
4 Pek. Kolom Teras
- Pek. Bekisting
TINGGI = 3.8
LEBAR = 0.8
JUMLAH SISI = 2.00

VOL. = TINGGI X LEBAR X JUMLAH SISI X JUMLAH

= 3.80 X 0.8 X 2.00 X 2

= 4.05 M2

- Pek. Pembesian
Pembesian Tulangan DIA 10 :
TINGGI = 3.8
Jumlah Tulangan = 10
Massa Jenis = 0.888
jumlah = 2

VOL. = TINGGI X JUMLAH X MASSA JENIS X JUMLAH

= 3.80 X 10 X 0.888 X 2

= 67.49 KG

- Pembesian Begel DIA 8 :


Jumlah Begel = 25.33
Panjang Begel = 1.48
Massa Jenis = 0.395

VOL. = JUMLAH X PANJANG X MASSA JENIS X JUMLAH

= 25.33 X 1.48 X 0.395 X 2

= 29.62 KG

TOTAL = 97.11 KG

- Pek. Beton Mutu f'c = 19.3 MPa (K.175)


PANJANG = 0.50
Lebar = 0.3
Tinggi = 3.8
jumlah = 2

VOL. = PANJANG X LEBAR X TINGGI X JUMLAH

= 0.50 X 0.3 X 3.8 X 2

TOTAL = 1.14 M3

5 Pek. Kolom Parkiran


- Pek. Bekisting
TINGGI = 3.3
LEBAR = 0.2
JUMLAH SISI = 4.00

VOL. = TINGGI X LEBAR X JUMLAH SISI X JUMLAH

= 3.30 X 0.2 X 4.00 X 10

= 8.80 M2

- Pek. Pembesian
Pembesian Tulangan DIA 10 :
TINGGI = 3.3
Jumlah Tulangan = 10
Massa Jenis = 0.888
jumlah = 10

VOL. = TINGGI X JUMLAH X MASSA JENIS X JUMLAH

= 3.30 X 10 X 0.888 X 10

= 293.04 KG

- Pembesian Begel DIA 8 :


Jumlah Begel = 18.33
Panjang Begel = 0.68
Massa Jenis = 0.395

VOL. = JUMLAH X PANJANG X MASSA JENIS X JUMLAH

= 18.33 X 0.68 X 0.395 X 10

= 49.24 KG

TOTAL = 342.28 KG

- Pek. Beton Mutu f'c = 19.3 MPa (K.175)


PANJANG = 0.20
Lebar = 0.2
Tinggi = 3.3
jumlah = 10

VOL. = PANJANG X LEBAR X TINGGI X JUMLAH

= 0.20 X 0.2 X 3.3 X 10

TOTAL = 1.32 M3

5 Pek. Balok Latei (13 x 13) Cm = 48.60 M1

bekisting = 6.32
beton = 0.82
pembesian =
tulangan utama = 4.00 x 48.60 x 0.617
= 119.94 kg

beugel = 0.49 x 243 x 0.395


= 47.03 kg
TOTAL BERAT = 166.98 KG

4 Pek. Balok Latei (15 x 15) Cm = 20.68 M1

bekisting = 3.10
beton = 0.47
pembesian =
tulangan utama = 4.00 x 20.68 x 0.395
= 32.67 kg

beugel = 0.53 x 103.4 x 0.222


= 12.17 kg

TOTAL BERAT = 44.84 KG

48.58 5 Pek. Ringbalk (15 x 20) Cm = 112.50 M1

= 9.72 bekisting = 22.50


= 1.09 beton = 3.38
= pembesian =
tulangan utama = 4.00 x 48.58 x 0.617 tulangan utama = 4.00 x 112.50 x 0.617
= 119.90 kg = 277.65 kg

beugel = 0.26 x 242.9 x 0.222 beugel = 0.26 x 562.5 x 0.222


= 13.80 kg = 31.97 kg

TOTAL BERAT = 133.70 KG TOTAL BERAT = 309.62 KG

6 Pek. Plat Atap Tebal 15 cm


- Pek. Bekisting :
Luas = 20.87
sisi Bekisting = 1
= 20.87 m2

- Pek. Pembesian
Pembesian Plat Lantai Vertikal = 7.26 0.15
= 48.40 1.75
= 84.70 2
= 169.40

Plat Lantai horizontal = 11.75 0.15


= 78.33 0.65
= 50.92 2
= 101.83

jumlah panjang tulangan = 271.23

VOL. = PANJANG X MASSA JENIS

= 271.23 X 0.40

= 27.14 KG

- Pek. Beton Mutu f'c = 19.3 MPa (K.175)


Luas 20.87
Tebal 0.15

VOL. = Luas X Tebal

= 20.87 X 0.15

= 3.13 m3

7 Pek. Kanopi beton 1


- Pek. Bekisting :
Luas = 55.55
sisi Bekisting = 2
= 22.22 m2

panjang jarak
- Pek. Pembesian = 55.55 / 0.25

= 222.20 x 0.45
= 199.98
berat besi
= 199.98 x 0.22
= 44.40 kg

- Pek. Beton = 55.55 x 0.12


= 1.33 m3

8 Pek. Kanopi beton 2


- Pek. Bekisting :
Luas = 55.55
sisi Bekisting = 2
= 22.22 m2

panjang jarak
- Pek. Pembesian = 55.55 / 0.25

= 222.20 x 0.65
= 288.86
berat besi
= 288.86 x 0.22
= 64.13 kg

- Pek. Beton = 55.55 x 0.22


= 2.44 m3
9 Pek. Kanopi beton 3
- Pek. Bekisting :
Luas = 11.5
sisi Bekisting = 2
= 23 m2

panjang jarak
- Pek. Pembesian = 11.50 / 0.25

= 46.00 x 0.95
= 87.40
berat besi
= 87.40 x 0.22
= 19.40 kg

- Pek. Beton = 11.50 x 0.40


= 0.92 m3

PEKERJAAN PASANGAN DINDING DAN PLESTERAN PEKERJAAN PASANG DINDING


1 Pek. Dinding Batu Bata Biasa Campuran 1 Pc : 5 Psr

= 18 x 3 LUAS DINDING = 442.35


= 54
- Bukaan Kusen
P1 = 2.73
P2 = 9.45
PWC = 2.82
PJ 1 = 6.3
J1 = 3.78
J2 = 8.45
J3 = 1.5
J4 = 1.44
J5 = 2.4
VWC = 0.56
VJ1 = 0.63
VP1 = 0.39
VP2 = 0.54
VJ5 = 0.48
ROSTER BLOCK = 1.08
42.55

LUAS DINDING - BUKAAN


= 442.35 42.55
VOL = 399.80 M2

3 Pek. Plesteran Dinding Biasa Campuran 1 Pc : 5 Psr

VOL. = VOL. =

= =

= 81.00 M2 = 799.60 M2

5 Pek. Acian

= 799.60 M2

PEKERJAAN KUSEN PINTU/JENDELA, DAUN PINTU/JENDELA, KUNCI DAN KACA PEKERJAAN KUSEN PINTU/JENDELA, DAUN PINTU/JENDELA, KUNCI DAN KACA

1 PINTU 1 (P1)
- Pek. Pembuatan dan pemasangan 1 m3 kusen pintu Kayu Kelas I 4.95

= 0.06 M3

- Pek. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I


= 0.06 m2

- Pek. pemasangan 1 m2 Kaca 3 mm


= 0.27 m2

- HANDLE PINTU = 2 BH

- KUNCI PINTU = 1 BH

- ENGSEL = 6 BH

2 PINTU 2 (P2)
- Pek. Pembuatan dan pemasangan 1 m3 kusen pintu Kayu Kelas I

= 0.18 M3

- Pek. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I


= 0.20 m2

- HANDLE PINTU = 5 BH
- KUNCI PINTU = 5 BH

- ENGSEL = 15 BH

4 PINTUJ1 (PJ1)
- Pek. Pembuatan dan pemasangan 1 m kusen aluminium

= 13.00 M1

- Pek. Pembuatan dan pemasangan 1 m2 Bingkai jendela aluminium


= 3.34 m2

- HANDLE PINTU = 5 BH

- KUNCI PINTU = 5 BH

- ENGSEL = 30 BH

- KACA = 5.14 M2

5 JENDELA 1 (J1)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.10 M3

- Pek. Pembuatan dan pemasangan 1 m2 daun Jendela, kayu kelas II


= 0.32 m2

- ENGSEL JENDELA = 8 BH

- KUNCI = 4 BH

- KAITANGIN = 8 BH

- KACA = 2.32 M2

6 JENDELA 2 (J2)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.25 M3

- Pek. Pembuatan dan pemasangan 1 m2 daun Jendela, kayu kelas II


= 0.80 m2

- ENGSEL JENDELA = 20 BH

- KUNCI = 10 BH

- KAITANGIN = 20 BH

- KACA = 5.2 M2

7 JENDELA 3 (J3)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.06 M3

- Pek. Pembuatan dan pemasangan 1 m2 daun Jendela, kayu kelas II


= 0.12 m2

- ENGSEL JENDELA = 4 BH

- KUNCI = 4 BH

- KAITANGIN = 4 BH

- KACA = 0.78 M2

8 JENDELA 4 (J4)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.05 M3

- Pek. Pembuatan dan pemasangan 1 m2 daun Jendela, kayu kelas II


= 0.01 m2

- ENGSEL JENDELA = 0 BH

- KUNCI = 2 BH

- KAITANGIN = 0 BH

- KACA = 0.92 M2

9 JENDELA 5 (J5)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.07 M3

- Pek. Pembuatan dan pemasangan 1 m2 daun Jendela, kayu kelas II


= 0.21 m2

- ENGSEL JENDELA = 6 BH

- KUNCI = 3 BH

- KAITANGIN = 6 BH

- KACA = 1.44 M2
10 VENTILASI WC (VWC)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.04 M3

- KACA = 0.48 M2

11 VENTILASI WC (VJI)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.04 M3

- KACA = 0.44 M2

12 VENTILASI (VP1)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.02 M3

- KACA = 0.3 M2

13 VENTILASI (VP2)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.03 M3

- KACA = 0.36 M2

14 VENTILASI (VJ5)
- Pek. Pembuatan dan pemasangan 1 m3 kusen Jendela kayu kelas II

= 0.03 M3

- KACA = 0.35 M2

15 KUSEN CARPORT
- Pek. Pembuatan dan pemasangan 1 m Kusen aluminium

= 66.00 M1

- FIBER GLASS = 28.08 M2

PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING


KERAMIK 80X80 = 145.00 M2

KERAMIK 40X40 = 26.36 M2

Pek. Dinding Keramik uk.20 x 20 cm (Lavatory & Km/Wc) Lantai 1 = 27.27 M2


LANTAI 5.93 M2

CONWOOD LANTAI 2.25 M2

CONWOOD ORNAMEN 30.70 M2

PLINT LANTAI 98.75 M2

PASIR BAWA LANTAI 8.40 M2

URUGAN TANAH BAWA LANTAI 33.60 M2

RABAT BAWA LANTAI 8.40 M2

6 Pek. Pasangan Atap Spandek


LUAS = 300.00
C0S 30 = 0.819

VOL. = LUAS : COS 30

= 300.00 : 0.819

= 366.30 M2

7 Pek. Pasangan Nok Spandek = 80.36 M1

8 Pek. Listplank 2 x 2/20 Kayu Kelas II = 300 M1

PEKERJAAN PENGECETAN PEKERJAAN PENGECETAN


1 Pek. Pengecetan bidang kayu baru ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup )
Kusen:
panjang = 5.00
lebar = 0.15

VOL. = panjang X lebar X sisi

= 5.00 X 0.15 X 2

= 1.50 M2

daun pintu
Luas = 0.06

VOL. = luas X sisi

= 0.06 X 2

= 0.12 M2
= 1.62 M2

2 Pek. Pengecatan 1 m2 tembok baru ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup )
luas = 0.00
sisi = 2.00

VOL. = luas X sisi

= 0.00 X 2.00

= 0.00 M2

PEKERJAAN SANITASI DAN PLUMBING PEKERJAAN SANITASI DAN PLUMBING


1 Pemasangan 1 buah closet Jongkok = 3.00 Bh
Pemasangan 1 buah floor drain = 3.00 Bh
Pemasangan 1 buah kran diameter ½” atau ¾ ” = 3.00 Bh
Pemasangan 1 m’ pipa PVC tipe AW diameter ½ ” = 52.00 M'
Pemasangan 1 m’ pipa PVC tipe AW diameter 2” = 46.00 M'
Pemasangan 1 m’ pipa PVC tipe AW diameter 4” = 30.00 M'
Pemasangan Septictank dan Peresapan = 1.00 Bh
Pemasangan Pompa AIR = 1.00 Bh
Pemasangan Tower Air 1200 Liter = 3.00 Bh

PEKERJAAN MEKANIKAL ELEKTRIKAL


1 Lampu philips 18 watt = 12.00 Bh
2 Lampu philips 9 watt = 3.00 Bh
2 Pemasangan. 1 Bh MCB = 3.00 Bh
3 Pemasangan. 1 Bh KWH = 3.00 Bh
4 Pek. 1 Bh Stop Kontak = 9.00 Bh
5 Pek. Saklar tunggal = 3.00 Bh
6 Pek. Saklar Ganda = 3.00 Bh
7 Pemasangan 1 Set Penangkal Petir = 0.00 Bh

PEKERJAAN FINISHING PEKERJAAN FINISHING


1 Pembersihan akhir pekerjaan = 1.00 Ls
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN
(PERMEN PUPR NOMOR 1 TAHUN 2022)

I. PEKERJAAN TANAH
1 1.7.1.a. Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m Untuk Volume s.d 200 m3 Dalam Satu Lokasi
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.750 112,500.00
2 Mandor Org/Hari 160,000.00 0.025 4,000.00
Jumlah A 116,500.00
B BAHAN

Jumlah B -
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 116,500.00

F Harga Satuan D + E 116,500.00

2 1.7.2.a Pengurugan Kembali 1 m3 Galian Tanah


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2500 37,500.00
2 Mandor Org/Hari 160,000.00 0.0083 1,333.33
Jumlah A 38,833.33
B BAHAN

Jumlah B
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 38,833.33

F Harga Satuan D + E 38,800.00

3 1.7.2.d Pengurugan 1 m3 dengan Pasir Urug


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.3000 45,000.00
2 Mandor Org/Hari 160,000.00 0.0100 1,600.00
Jumlah A 46,600.00
B BAHAN
1 Pasir Urug M3 180,000.00 1.2000 216,000.00
Jumlah B 216,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 262,600.00

F Harga Satuan D + E 262,600.00

17
4 1.7.2.e Pengurugan dan Pemadatan 1 m3 Sirtu
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2500 37,500.00
2 Mandor Org/Hari 160,000.00 0.0250 4,000.00
Jumlah A 41,500.00
B BAHAN
1 Sirtu M3 80,000.00 1.2000 96,000.00
Jumlah B 96,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 137,500.00

F Harga Satuan D + E 137,500.00

II. PEKERJAAN PONDASI


1 2.1.1.b Memasang 1 m3 Pondasi Batu Belah Tipe N (5,2 Mpa)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.5000 225,000.00
2 Tukang Batu Org/Hari 180,000.00 0.7500 135,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0750 15,000.00
4 Mandor Org/Hari 160,000.00 0.0750 12,000.00
Jumlah A 387,000.00
B BAHAN
1 Batu Gunung M3 350,000.00 1.20 420,000.00
2 Semen Portland Kg 1,700.00 163.00 277,100.00
3 Pasir Pasang M3 200,000.00 0.520 104,000.00
Jumlah B 801,100.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,188,100.00

F Harga Satuan D + E 1,188,100.00

2 1.5.1.1.b.(a) Pemasangan 1 m3 batu kosong (anstamping)


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.780 117,000.00
2 Tukang Batu Org/Hari 180,000.00 0.390 70,200.00
3 Kepala Tukang Org/Hari 200,000.00 0.039 7,800.00
4 Mandor Org/Hari 160,000.00 0.039 6,240.00
Jumlah A 201,240.00
B BAHAN
1 Batu belah 15 cm/20 cm M3 350,000.00 1.20 420,000.00
2 Pasir Urug M3 180,000.00 0.432 77,760.00
Jumlah B 497,760.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 699,000.00

F Harga Satuan D + E 699,000.00

18
III. PEKERJAAN DINDING
1 4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 PC : 3 PP
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.300 45,000.00
2 Tukang Batu Org/Hari 180,000.00 0.100 18,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.010 2,000.00
4 Mandor Org/Hari 160,000.00 0.015 2,400.00
Jumlah A 67,400.00
B BAHAN
1 Batu bata Biji 700.00 70.000 49,000.00
2 Semen Kg 1,700.00 14.370 24,429.00
3 Pasir Pasang M3 200,000.00 0.040 8,000.00
Jumlah B 81,429.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 148,829.00

F Harga Satuan D + E 148,800.00

2 4.4.1.9 Pemasangan 1 m2 Dinding Bata Berah (5x11x22) cm Tebal 1/2 Batu Campuran 1 PC : 4 PP
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.3000 45,000.00
2 Tukang Batu Org/Hari 180,000.00 0.1000 18,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0100 2,000.00
4 Mandor Org/Hari 160,000.00 0.0150 2,400.00
Jumlah A 67,400.00
B BAHAN
1 Batu bata Biji 700.00 70.000 49,000.00
2 Semen Kg 1,700.00 11.500 19,550.00
3 Pasir Pasang M3 200,000.00 0.043 8,600.00
Jumlah B 77,150.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 144,550.00

F Harga Satuan D + E 144,500.00

19
3 4.4.1.9 Pemasangan 1 m2 dinding conblock HB15 campuran 1 PC : 4 PP
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.3200 48,000.00
2 Tukang Batu Org/Hari 180,000.00 0.1200 21,600.00
3 Kepala Tukang Org/Hari 200,000.00 0.0120 2,400.00
4 Mandor Org/Hari 160,000.00 0.0160 2,560.00
Jumlah A 74,560.00
B BAHAN
1 Batako HB-15 Bh 3,000.00 12.500 37,500.00
2 Semen Kg 1,700.00 18.200 30,940.00
3 Pasir Pasang M3 200,000.00 0.0582 11,640.00
4 Besi Angker dia. 8 Kg 13,500.00 0.280 3,780.00
Jumlah B 80,080.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 154,640.00

F Harga Satuan D + E 154,600.00

IV PEKERJAAN PLESTERAN
1 Anl. Pemasangan plesteran 1 m' tali air
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.0800 12,000.00
2 Tukang Batu Org/Hari 180,000.00 0.0040 720.00
3 Kepala Tukang Org/Hari 200,000.00 0.0080 1,600.00
4 Mandor Org/Hari 160,000.00 0.0040 640.00
Jumlah A 14,960.00
B BAHAN
1 Semen Kg 1,700.00 0.2500 425.00
2 Pasir Pasang M3 200,000.00 0.0080 1,600.00
Jumlah B 2,025.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 16,985.00

F Harga Satuan D + E 16,900.00

20
2 4.4.2.5 Pemasangan 1 m2 plesteran 1 PC : 5 PP tebal 15 mm
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.1500 22,500.00
2 Tukang Batu Org/Hari 180,000.00 0.0750 13,500.00
3 Kepala Tukang Org/Hari 200,000.00 0.0080 1,600.00
4 Mandor Org/Hari 160,000.00 0.0080 1,280.00
Jumlah A 38,880.00
B BAHAN
1 Semen Portlan (PC) Kg 1,700.00 5.184 8,812.80
2 Pasir Pasang (PP) M3 200,000.00 0.026 5,200.00
Jumlah B 14,012.80
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 52,892.80

F Harga Satuan D + E 52,800.00

3 4.4.2.27 Pemasangan 1 m2 acian


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2000 30,000.00
2 Tukang Batu Org/Hari 180,000.00 0.1000 18,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0100 2,000.00
4 Mandor Org/Hari 160,000.00 0.0100 1,600.00
Jumlah A 51,600.00
B BAHAN
1 Semen Kg 1,700.00 3.250 5,525.00
Jumlah B 5,525.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 57,125.00

F Harga Satuan D + E 57,100.00

V PEKERJAAN KAYU
1 4.6.1.21 Pemasangan 1 m' lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.1000 15,000.00
2 Tukang Kayu Org/Hari 180,000.00 0.2000 36,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0200 4,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 55,800.00
B BAHAN
1 Kayu Papan Klas II M3 4,200,000.00 0.0108 45,360.00
2 Paku 5 dan 7 cm Kg 20,000.00 0.100 2,000.00
Jumlah B 47,360.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 103,160.00

F Harga Satuan D + E 103,160.00

21
VI PEKERJAAN LANGIT-LANGIT (PLAFOND)
1 4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.1500 22,500.00
2 Tukang Kayu Org/Hari 180,000.00 0.0500 9,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.5000 100,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 132,300.00
B BAHAN
1 Gypsum Board Lembar 80,000.00 0.3640 29,120.00
2 Sekrup Gypsum Kg 35,000.00 0.1100 3,850.00
Jumlah B 32,970.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 165,270.00

F Harga Satuan D + E 165,200.00

2 4.5.1.9 Pemasangan 1 m' list langit-langit kayu profil


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.0500 7,500.00
2 Tukang Kayu Org/Hari 180,000.00 0.0500 9,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0050 1,000.00
4 Mandor Org/Hari 160,000.00 0.0030 480.00
Jumlah 17,980.00
B BAHAN
1 List Kayu Profil M' 6,331.25 1.0000 6,331.25
2 Paku Sekrup Kg 35,000.00 0.0100 350.00
Jumlah B 6,681.25
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 24,661.25

F Harga Satuan D + E 24,600.00

22
VII PEKERJAAN BESI DAN ALUMINIUM
1 4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 60 cm, untuk plafon
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.3500 52,500.00
2 Tukang Besi Org/Hari 180,000.00 0.3500 63,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0350 7,000.00
4 Mandor Org/Hari 160,000.00 0.0180 2,880.00
Jumlah A 125,380.00
B BAHAN
1 Rangka Besi Hollow 40.40.2 cm M' 22,000.00 4.0000 88,000.00
2 Assesoris (perkuatan, las dll) Ls 30,800.00 1.0000 30,800.00
Jumlah B 118,800.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 244,180.00

F Harga Satuan D + E 244,100.00

2 4.2.1.22 Pemasangan 1 m2 Atap Pelana Rangka Atap Baja Ringan (Canai Dingin) profil C75
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.7340 110,100.00
2 Tukang Besi Org/Hari 180,000.00 0.7340 132,120.00
3 Kepala Tukang Org/Hari 200,000.00 0.0730 14,600.00
4 Mandor Org/Hari 160,000.00 0.0370 5,920.00
Jumlah A 262,740.00
B BAHAN
1 Baja Ringan Canai C75 Btg 120,000.00 3.0650 367,800.00
2 Sekrup Bh 500.00 9.0000 4,500.00
Jumlah B 372,300.00
C PERALATAN
Peralatan % 10.0000 37,230.00
Jumlah C 37,230.00
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 672,270.00

F Harga Satuan D + E 672,200.00

23
3 4.2.1.24 Pemasangan 1 m' Kusen Aluminium
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.0430 6,450.00
2 Tukang Besi Org/Hari 180,000.00 0.0430 7,740.00
3 Kepala Tukang Org/Hari 200,000.00 0.0043 860.00
4 Mandor Org/Hari 160,000.00 0.0021 336.00
Jumlah A 15,386.00
B BAHAN
1 Profil Aluminium 4" M 100,000.00 1.100 110,000.00
2 Skrup Fixer Bh 500.00 2.000 1,000.00
3 Sealant Tube 66,000.00 0.060 3,960.00
Jumlah B 111,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 126,386.00

F Harga Satuan D + E 126,300.00

4 4.2.1.25 Pemasangan 1 m2 Pintu Aluminium Strip


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.0850 12,750.00
2 Tukang Besi Org/Hari 180,000.00 0.0850 15,300.00
3 Kepala Tukang Org/Hari 200,000.00 0.0085 1,700.00
4 Mandor Org/Hari 160,000.00 0.0042 672.00
Jumlah A 30,422.00
B BAHAN
1 Profil Aluminium M 80,000.00 4.400 352,000.00
2 Aluminium Strip M 45,000.00 14.600 657,000.00
Jumlah B 1,009,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,039,422.00

F Harga Satuan D + E 1,039,400.00

24
5 4.2.1.26 Pemasangan 1 m2 Daun Kaca Aluminium
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.0850 12,750.00
2 Tukang Besi Org/Hari 180,000.00 0.0850 15,300.00
3 Kepala Tukang Org/Hari 200,000.00 0.0090 1,800.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 30,650.00
B BAHAN
1 Pintu Aluminium M 180,000.00 4.400 792,000.00
2 Profil Kaca M 50,000.00 4.500 225,000.00
3 Sealant Tube 66,000.00 0.270 17,820.00
Jumlah B 1,017,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,047,650.00

F Harga Satuan D + E 1,047,600.00

VIII. PEKERJAAN BETON


1 2.2.6.1.d.(a) Pembesian kolom, balok, ring balk, dan sloof untuk besi beton < 12 mm (per - 1 Kg)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.6000 240,000.00
2 Tukang Besi Org/Hari 180,000.00 1.6000 288,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.1600 32,000.00
4 Mandor Org/Hari 160,000.00 0.1600 25,600.00
Jumlah A 585,600.00
B BAHAN
1 Besi Beton Polos Kg 25,000.00 105.0000 2,625,000.00
2 Kawat beton Kg 20,000.00 2.8000 56,000.00
Jumlah B 2,681,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 3,266,600.00

F Harga Satuan D + E 32,666.00

25
2 2.2.2.1.g Membuat 1 m3 Beton Mutu f'c = 7,4 Mpa (K-100), Lantai Kerja
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.6500 247,500.00
2 Tukang Besi Org/Hari 180,000.00 0.2750 49,500.00
3 Kepala Tukang Org/Hari 200,000.00 0.0275 5,500.00
4 Mandor Org/Hari 160,000.00 0.1650 26,400.00
Jumlah A 328,900.00
B BAHAN
1 Semen Portland (PC) Kg 1,700.00 227 385,900.00
2 Pasir Beton (PB) M3 189.29 869 164,489.29
3 Kerikil (Kr) M3 263.17 1,000 263,171.85
4 Air Liter 90.00 215 19,350.00
Jumlah B 813,561.14
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,142,461.14

F Harga Satuan D + E 1,142,400.00

3 2.2.2.1.g Membuat 1 m3 Beton Mutu f'c = 14,5 Mpa (K-175), Lantai, Kolom, Balok
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.6500 247,500.00
2 Tukang Besi Org/Hari 180,000.00 0.2750 49,500.00
3 Kepala Tukang Org/Hari 200,000.00 0.0275 5,500.00
4 Mandor Org/Hari 160,000.00 0.1650 26,400.00
Jumlah A 328,900.00
B BAHAN
1 Semen Portland (PC) Kg 1,700.00 326 554,200.00
2 Pasir Beton (PB) Kg 189.29 760 143,857.14
3 Kerikil (Kr) M3 263.17 1,029 270,803.84
4 Air Liter 90.00 215 19,350.00
Jumlah B 968,860.98
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,297,760.98

F Harga Satuan D + E 1,297,700.00

26
4 4.1.1.19 Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung (5x Pakai)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.5200 78,000.00
2 Tukang Kayu Org/Hari 180,000.00 0.2600 46,800.00
3 Kepala Tukang Org/Hari 200,000.00 0.0260 5,200.00
4 Mandor Org/Hari 160,000.00 0.0260 4,160.00
Jumlah A 134,160.00
B BAHAN
1 Kayu Kelas III M3 2,205,000.00 0.0450 99,225.00
2 Paku 5 cm - 10 cm Kg 20,000.00 0.3000 6,000.00
3 Minyak Bekisting Liter 12,500.00 0.1000 1,250.00
Jumlah B 106,475.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 240,635.00

F Harga Satuan D + E 48,120.00

5 4.1.1.22 Pemasangan 1 m² Bekisting untuk Kolom Beton Bangunan Gedung (5x Pakai)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.6600 99,000.00
2 Tukang Batu Org/Hari 180,000.00 0.3300 59,400.00
3 Kepala Tukang Org/Hari 200,000.00 0.0330 6,600.00
4 Mandor Org/Hari 160,000.00 0.0330 5,280.00
Jumlah A 170,280.00
B BAHAN
1 Kayu Papan kelas III m³ 2,205,000.00 0.0400 88,200.00
2 Paku 5 cm - 12 cm Kg 20,000.00 0.4000 8,000.00
3 Minyak bekisting Liter 12,500.00 0.2000 2,500.00
4 Balok Kayu kelas III m³ 2,205,000.00 0.0150 33,075.00
5 Multipleks tebal 9 mm Lbr 120,000.00 0.3500 42,000.00
6 Dolken kayu ø8-10 ) cm- panj 4 m Batang 10,000.00 2.0000 20,000.00
Jumlah B 193,775.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 364,055.00

F Harga Satuan D + E 72,800.00

27
6 4.1.1.22 Pemasangan 1 m² Bekisting untuk Plat Beton Bangunan Gedung
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.6600 99,000.00
2 Tukang Kayu Org/Hari 180,000.00 0.3300 59,400.00
3 Kepala Tukang Org/Hari 200,000.00 0.0330 6,600.00
4 Mandor Org/Hari 160,000.00 0.0330 5,280.00
Jumlah A 170,280.00
B BAHAN
1 Kayu Papan kelas IV (Bekisting) m³ 2,205,000.00 0.040 88,200.00
2 Paku 5 cm - 12 cm Kg 20,000.00 0.400 8,000.00
3 Minyak bekisting Liter 12,500.00 0.200 2,500.00
4 Balok Kayu kelas IV (Bekisting) m³ 2,205,000.00 0.015 33,075.00
5 Multipleks tebal 9 mm Lbr 120,000.00 0.350 42,000.00
6 Dolken kayu .. 8-10) cm- panj 4 m Batang 10,000.00 6.000 60,000.00
Jumlah B 233,775.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 404,055.00

F Harga Satuan D + E 80,800.00

IX PEKERJAAN PENUTUP LANTAI


1 4.4.3.9 Pemasangan 1 m2 lantai ubin granit ukuran 60 cm x 60 cm
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.240 36,000.00
2 Tukang Batu Org/Hari 180,000.00 0.120 21,600.00
3 Kepala Tukang Org/Hari 200,000.00 0.012 2,400.00
4 Mandor Org/Hari 160,000.00 0.012 1,920.00
Jumlah 61,920.00
B BAHAN
1 Tegel Keramik 60 x 60 cm Bh 50,000.00 3.100 155,000.00
2 Semen warna Kg 28,000.00 9.600 268,800.00
3 Semen portland Kg 1,700.00 1.500 2,550.00
4 Pasir Pasang M3 200,000.00 0.045 9,000.00
Jumlah 435,350.00
Harga Satuan A + B 497,270.00

F Harga Satuan D + E 497,200.00

1 4.4.3.9 Pemasangan 1 m2 lantai ubin granit ukuran 80 cm x 80 cm


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.240 36,000.00
2 Tukang Batu Org/Hari 180,000.00 0.120 21,600.00
3 Kepala Tukang Org/Hari 200,000.00 0.012 2,400.00
4 Mandor Org/Hari 160,000.00 0.012 1,920.00
Jumlah 61,920.00
B BAHAN
1 Tegel Keramik 80 x 80 cm Bh 150,000.00 3.100 465,000.00
2 Semen warna Kg 28,000.00 9.600 268,800.00
3 Semen portland Kg 1,700.00 1.500 2,550.00
4 Pasir Pasang M3 200,000.00 0.045 9,000.00
Jumlah 745,350.00
Harga Satuan A + B 807,270.00

F Harga Satuan D + E 807,200.00

28
2 4.4.3.6 Pemasangan 1 m2 lantai ubin warna ukuran 20 cm x 20 cm
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.1350 20,250.00
2 Tukang Batu Org/Hari 180,000.00 0.0140 2,520.00
3 Kepala Tukang Org/Hari 200,000.00 0.2700 54,000.00
4 Mandor Org/Hari 160,000.00 0.0140 2,240.00
Jumlah 79,010.00
B BAHAN
1 Tegel Anti slip 20 x 20 Cm Bh 3,200.00 26.5000 84,800.00
2 Semen warna Kg 28,000.00 1.0000 28,000.00
3 Semen portland Kg 1,700.00 10.4000 17,680.00
4 Pasir Pasang M3 200,000.00 0.0450 9,000.00
Jumlah 139,480.00
Harga Satuan A + B 218,490.00

F Harga Satuan D + E 218,400.00

2 4.4.3.6 Pemasangan 1 m2 lantai ubin warna ukuran 40 cm x 40 cm


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.1350 20,250.00
2 Tukang Batu Org/Hari 180,000.00 0.0140 2,520.00
3 Kepala Tukang Org/Hari 200,000.00 0.2700 54,000.00
4 Mandor Org/Hari 160,000.00 0.0140 2,240.00
Jumlah 79,010.00
B BAHAN
1 Tegel Warna 40 x 40 Cm Bh 17,000.00 26.5000 450,500.00
2 Semen warna Kg 28,000.00 1.0000 28,000.00
3 Semen portland Kg 1,700.00 10.4000 17,680.00
4 Pasir Pasang M3 200,000.00 0.0450 9,000.00
Jumlah 505,180.00
Harga Satuan A + B 584,190.00

F Harga Satuan D + E 584,100.00

3 4.4.3.24 Pemasangan 1 m' plint tegel granit ukuran 10 x 60 cm


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.0900 13,500.00
2 Tukang Batu Org/Hari 180,000.00 0.0900 16,200.00
3 Kepala Tukang Org/Hari 200,000.00 0.0090 1,800.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 32,300.00
B BAHAN
1 Tegel Plint Keramik 10 x 60 Cm Bh 15,000.00 1.700 25,500.00
2 Semen portland Kg 1,700.00 1.140 1,938.00
3 Pasir Pasang M3 200,000.00 0.003 600.00
4 Semen warna Kg 28,000.00 0.100 2,800.00
Jumlah B 30,838.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 63,138.00

F Harga Satuan D + E 63,100.00

29
4 4.4.3.54 Pemasangan 1 m2 dinding keramik 20 x 20 cm
No. Uraian Satuan Harga Jumlah
Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.600 90,000.00
2 Tukang Batu Org/Hari 180,000.00 0.450 81,000.00
3 Kapala Tukang Org/Hari 200,000.00 0.045 9,000.00
4 Mandor Org/Hari 160,000.00 0.030 4,800.00
Jumlah A 184,800.00
B BAHAN
1 Tegel Dinding Keramik 20 x20 Cm Bh 3,200.00 26.500 84,800.00
2 Semen portland Kg 1,700.00 9.300 15,810.00
3 Pasir Pasang M3 200,000.00 0.018 3,600.00
Jumlah B 104,210.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 289,010.00

F Harga Satuan D + E 289,000.00

5 4.4.3.63 Pemasangan 1 m2 Paving Block Natural tebal 6 cm


No. Uraian Satuan Harga Jumlah
Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2500 37,500.00
2 Tukang Batu Org/Hari 180,000.00 0.5000 90,000.00
3 Kapala Tukang Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0013 208.00
Jumlah A 137,708.00
B BAHAN
1 Paving Block M2 120,000.00 1.010 121,200.00
2 Pasir Beton M3 265,000.00 0.050 13,250.00
Jumlah B 134,450.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 272,158.00

F Harga Satuan D + E 272,100.00

30
X PEKERJAAN PENUTUP ATAP
4 Anl 1 m2 Pek. Kuda-Kuda Rangka Atap Baja Ringan
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.3000 45,000.00
2 Tukang Org/Hari 180,000.00 0.1000 18,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0100 2,000.00
4 Mandor Org/Hari 160,000.00 0.0150 2,400.00
Jumlah A 67,400.00
B BAHAN
1 Main Trus C 75 - 75 m' 19,000.00 2.8000 53,200.00
2 Reef Botton / Reng R 33-0,45 m' 10,000.00 4.6000 46,000.00
3 Self drilling Screw dia 6 x 20 mm (Truss Screw) bh 500.00 17.0000 8,500.00
4 Self drilling Screw dia 4 x 16 mm (Roof Bottom bh 500.00 24.0000 12,000.00
5 Dynabolt 12 x 120 mm bh 5,500.00 1.0000 5,500.00
6 Alat bantu ls 35,500.00 0.0350 1,242.50
Jumlah B 126,442.50
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 193,842.50

F Harga Satuan D + E 193,842.50

Anl Pemasangan 1 m’ lisplank ukuran (1 x 30) cm, Wood plank


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.100 15,000.00
2 Tukang Org/Hari 180,000.00 0.200 36,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.020 4,000.00
4 Mandor Org/Hari 160,000.00 0.005 800.00
Jumlah A 55,800.00
B BAHAN
1 Wood Lbr 60,000.00 0.2500 15,000.00
Plank
2 Skrup Bh 500.00 26.0000 13,000.00
Jumlah B 28,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 83,800.00

F Harga Satuan D + E 83,800.00

4.5.2.41 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 180,000.00 0.200 36,000.00
2 Tukang kayu Org/Hari 200,000.00 0.100 20,000.00
3 Kepala Tukang Org/Hari 150,000.00 0.010 1,500.00
4 Mandor Org/Hari 160,000.00 0.001 160.00
Jumlah A 57,660.00
B BAHAN
1 Genteng Metal Lbr 49,000.00 1.300 63,700.00
2 Baut Spandek 4,5cm Bh 1,000.00 6.000 6,000.00
Jumlah B 69,700.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 127,360.00

F Harga Satuan D + E 127,300.00

31
4.5.2.37 Pemasangan 1 m' nok genteng metal
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 0.1500 27,000.00
2 Kepala Tukang Org/Hari 200,000.00 0.0150 3,000.00
3 Pekerja Org/Hari 150,000.00 0.2500 37,500.00
4 Mandor Org/Hari 160,000.00 0.0130 2,080.00
Jumlah A 69,580.00
B BAHAN
1 Nok Genteng Metal Lbr 35,000.00 1.1000 38,500.00
2 Paku Atap Kg 20,000.00 0.0500 1,000.00
Jumlah B 39,500.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 109,080.00

F Harga Satuan D + E 109,000.00

32
XI PEKERJAAN KUNCI DAN KACA
1 4.6.2.2 Pemasangan 1 buah kunci biasa
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.010 900.00
2 Tukang Kayu Org/Hari 120,000.00 0.500 60,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.050 7,000.00
4 Mandor Org/Hari 120,000.00 0.005 600.00
Jumlah A 68,500.00
B BAHAN
1 Kunci Tanam Pintu Bh 200,000.00 1.0000 200,000.00
Jumlah B 200,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 268,500.00

F Harga Satuan D + E 268,500.00

2 4.6.2.5 Pemasangan 1 buah engsel pintu


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.015 1,350.00
2 Tukang Kayu Org/Hari 120,000.00 0.150 18,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.015 2,100.00
4 Mandor Org/Hari 120,000.00 0.0008 96.00
Jumlah A 21,546.00
B BAHAN
1 Kunci Tanam Pintu Bh 45,000.00 1.0000 45,000.00
Jumlah B 45,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 66,546.00

F Harga Satuan D + E 66,500.00

33
3 4.6.2.6 Pemasangan 1 buah engsel jendela kupu-kupu
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.010 900.00
2 Tukang Kayu Org/Hari 120,000.00 0.100 12,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.010 1,400.00
4 Mandor Org/Hari 120,000.00 0.0005 60.00
Jumlah A 14,360.00
B BAHAN
1 Engsel Kupu-Kupu Bh 40,000.00 1.0000 40,000.00
Jumlah B 40,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 54,360.00

F Harga Satuan D + E 54,300.00

34
4 4.6.2.8 Pemasangan 1 buah spring knip
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.015 1,350.00
2 Tukang Kayu Org/Hari 120,000.00 0.150 18,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.015 2,100.00
4 Mandor Org/Hari 120,000.00 0.0008 96.00
Jumlah A 21,546.00
B BAHAN
1 Spring Knip Bh 26,000.00 1.0000 26,000.00
Jumlah B 26,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 47,546.00

F Harga Satuan D + E 47,500.00

5 4.6.2.9 Pemasangan 1 buah kait angin


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.015 1,350.00
2 Tukang Kayu Org/Hari 120,000.00 0.150 18,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.015 2,100.00
4 Mandor Org/Hari 120,000.00 0.0008 96.00
Jumlah A 21,546.00
B BAHAN
1 Kait Angin Bh 15,000.00 1.0000 15,000.00
Jumlah B 15,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 36,546.00

F Harga Satuan D + E 36,500.00

6 4.6.2.17 Pemasangan 1 m2 kaca tebal 3 mm


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 0.1500 27,000.00
2 Kepala tukang Org/Hari 200,000.00 0.0150 3,000.00
3 Pekerja Org/Hari 150,000.00 0.0150 2,250.00
4 Mandor Org/Hari 160,000.00 0.0008 128.00
Jumlah A 32,378.00
B BAHAN
1 Kaca Tebal 3 mm M2 90,000.00 1.1000 99,000.00
Jumlah B 99,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 131,378.00

F Harga Satuan D + E 131,300.00

35
XII PEKERJAAN PENGECATAN
1 4.7.1.10 Pengecetan 1 m2 tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.0200 3,000.00
2 Tukang Cat Org/Hari 180,000.00 0.0630 11,340.00
3 Kepala Tukang Org/Hari 200,000.00 0.0063 1,260.00
4 Mandor Org/Hari 160,000.00 0.0030 480.00
Jumlah A 16,080.00
B BAHAN
1 Plamir Kg 10,000.00 0.1000 1,000.00
2 Cat Dasar Kg 45,000.00 0.1000 4,500.00
3 Cat Penutup Kg 50,000.00 0.2600 13,000.00
Jumlah B 18,500.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 34,580.00

F Harga Satuan D + E 34,500.00

1 4.7.1.10 1 M2 PEKERJAAN PLAMIR, CAT DASAR, CAT KILAP KAYU 3 x


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.1050 15,750.00
2 Tukang Cat Org/Hari 180,000.00 0.0040 720.00
3 Kepala Tukang Org/Hari 200,000.00 0.0700 14,000.00
4 Mandor Org/Hari 160,000.00 0.0030 480.00
Jumlah A 30,950.00
B BAHAN
1 Cat meni Kg 25,000.00 0.2000 5,000.00
2 Plamir Kg 15,000.00 0.1500 2,250.00
3 Cat dasar Kg 45,000.00 0.1700 7,650.00
4 cat penutup/kilap 3 x Kg 50,000.00 0.3500 17,500.00
Jumlah B 32,400.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 63,350.00

F Harga Satuan D + E 63,300.00

XIII PEKERJAAN SANITASI


1 5.1.1.2 Memasang Closet duduk
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.070 10,500.00
2 Tukang Batu Org/Hari 180,000.00 0.100 18,000.00
3 Kapala Tukang Org/Hari 200,000.00 0.010 2,000.00
4 Mandor Org/Hari 160,000.00 0.004 640.00
Jumlah A 31,140.00
B BAHAN
1 Closed Duduk Buah 1,300,000.00 1.0000 1,300,000.00
2 Semen Portland Kg 1,700.00 6.0000 10,200.00
3 Pasir Pasang M3 200,000.00 0.0100 2,000.00
Jumlah B 1,310,200.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,341,340.00

F Harga Satuan D + E 1,341,300.00

36
2 5.1.1.2 Memasang Closet Jongkok
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.070 10,500.00
2 Tukang Batu Org/Hari 180,000.00 0.100 18,000.00
3 Kapala Tukang Org/Hari 200,000.00 0.010 2,000.00
4 Mandor Org/Hari 160,000.00 0.004 640.00
Jumlah A 31,140.00
B BAHAN
1 Closed Jongkok Buah 500,000.00 1.0000 500,000.00
2 Semen Portland Kg 1,700.00 6.0000 10,200.00
3 Pasir Pasang M3 200,000.00 0.0100 2,000.00
Jumlah B 510,200.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 541,340.00

F Harga Satuan D + E 541,300.00

37
2 5.1.1.14 Pemasangan 1 buah floor drain
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.010 1,500.00
2 Tukang Batu Org/Hari 180,000.00 0.100 18,000.00
3 Kapala Tukang Org/Hari 200,000.00 0.010 2,000.00
4 Mandor Org/Hari 160,000.00 0.005 800.00
Jumlah A 22,300.00
B BAHAN
1 Floor Drain Bh 80,000.00 1.000 80,000.00
Jumlah B 80,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 102,300.00

F Harga Satuan D + E 102,300.00

3 5.1.1.19 Pemasangan 1 buah kran diameter 1/2"


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.010 1,500.00
2 Tukang Batu Org/Hari 180,000.00 0.400 72,000.00
3 Kapala Tukang Org/Hari 200,000.00 0.040 8,000.00
4 Mandor Org/Hari 160,000.00 0.005 800.00
Jumlah A 82,300.00
B BAHAN
1 Kran air Bh 55,000.00 1.000 55,000.00
2 Seal tape Bh 5,000.00 0.250 1,250.00
Jumlah B 56,250.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 138,550.00

F Harga Satuan D + E 138,500.00

38
4 5.1.1.25 Pemasangan 1 m' pipa PVC tipe AW diameter 1/2"
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.036 5,400.00
2 Tukang Batu Org/Hari 180,000.00 0.060 10,800.00
3 Kapala Tukang Org/Hari 200,000.00 0.006 1,200.00
4 Mandor Org/Hari 160,000.00 0.002 320.00
Jumlah A 17,720.00
B BAHAN
1 Pipa PVC 1/2" m' 5,300.00 1.2000 6,360.00
2 Perlengkapan 35 % dari harga pipa % 2,226.00 1.0000 2,226.00
Jumlah B 8,586.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 26,306.00

F Harga Satuan D + E 26,300.00

5 5.1.1.26 Pemasangan 1 m' pipa PVC tipe AW diameter 3/4"


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.036 5,400.00
2 Tukang Batu Org/Hari 180,000.00 0.060 10,800.00
3 Kapala Tukang Org/Hari 200,000.00 0.006 1,200.00
4 Mandor Org/Hari 160,000.00 0.002 320.00
Jumlah A 17,720.00
B BAHAN
1 Pipa PVC 3/4" m' 7,200.00 1.2000 8,640.00
2 Perlengkapan 35 % dari harga pipa ls 2,520.00 1.0000 2,520.00
Jumlah B 11,160.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 28,880.00

F Harga Satuan D + E 28,800.00

39
6 5.1.1.31 Memasang 1 M' Pipa PVC AW Diameter 3"
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.081 12,150.00
2 Tukang Batu Org/Hari 180,000.00 0.135 24,300.00
3 Kapala Tukang Org/Hari 200,000.00 0.0135 2,700.00
4 Mandor Org/Hari 160,000.00 0.004 640.00
Jumlah A 39,790.00
B BAHAN
1 Pipa PVC 3" m' 53,000.00 1.2000 63,600.00
2 Perlengkapan 35 % dari harga pipa ls 18,550.00 1.0000 18,550.00
Jumlah B 82,150.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 121,940.00

F Harga Satuan D + E 121,900.00

40
7 5.1.1.32 Memasang 1 M' Pipa PVC AW Diameter 4"
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.036 5,400.00
2 Tukang Batu Org/Hari 180,000.00 0.060 10,800.00
3 Kapala Tukang Org/Hari 200,000.00 0.006 1,200.00
4 Mandor Org/Hari 160,000.00 0.002 320.00
Jumlah A 17,720.00
B BAHAN
1 Pipa PVC 4" m' 85,000.00 1.2000 102,000.00
2 Perlengkapan 35 % dari harga pipa ls 29,750.00 1.0000 29,750.00
Jumlah B 131,750.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 149,470.00

F Harga Satuan D + E 149,400.00

41
XIV PEKERJAAN INSTALASI LISTRIK
1 8.4.6.1 Pemasangan 1 buah titik lampu
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2000 30,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.3000 54,000.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0500 8,000.00
Jumlah A 102,000.00
B BAHAN
1 Kabel NYM 2 x 2,5 mm m' 10,000.00 5.000 50,000.00
2 Pipa Conduit m' 6,250.00 5.000 31,250.00
3 Fitting (Elbow, T-Dus, Mongkok) bh 20,000.00 3.000 60,000.00
4 Klem bh 10,000.00 4.000 40,000.00
5 Fisher dan skrup bh 7,000.00 4.000 28,000.00
7 Fitting Lampu bh 20,000.00 1.000 20,000.00

Jumlah B 229,250.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 331,250.00

F Harga Satuan D + E 331,200.00

2 8.4.6.1 1 Titik Pasang Instalasi Stop Kontak


No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2000 30,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.3000 54,000.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0500 8,000.00
Jumlah A 102,000.00
B BAHAN
1 Kabel NYM 3 x 2,5 mm m' 10,000.00 5.000 50,000.00
2 Pipa Conduit m' 6,250.00 5.000 31,250.00
3 Fitting (elbow, male, bust) bh 20,000.00 3.000 60,000.00
4 Sadle/klem bh 10,000.00 4.000 40,000.00
5 Fisher dan skrup bh 7,000.00 5.000 35,000.00
6 Tee dos bh 20,000.00 1.000 20,000.00
7 Stop kontak tanam bh 30,000.00 1.000 30,000.00
Jumlah B 266,250.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 368,250.00

F Harga Satuan D + E 368,200.00

42
1 Unit Pasang Stop Kontak
No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.1650 24,750.00
2 Tukang Listrik Org/Hari 180,000.00 0.0165 2,970.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0300 6,000.00
4 Mandor Org/Hari 160,000.00 0.0150 2,400.00
Jumlah A 36,120.00
B BAHAN
1 Stop Kontak BH 40,000.00 1.000 40,000.00
2 Perlengkapan % 40,000.00 0.350 14,000.00
Jumlah B 54,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 90,120.00

F Harga Satuan D + E 90,100.00

1 Unit Pasang Saklar Tunggal


No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2000 30,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.0200 3,600.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0500 8,000.00
Jumlah A 51,600.00
B BAHAN
1 Saklar Tunggal BH 35,000.00 1.000 35,000.00
2 Perlengkapan % 35,000.00 0.350 12,250.00
Jumlah B 47,250.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 98,850.00

F Harga Satuan D + E 98,800.00

1 Unit Pasang Saklar Ganda


No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2000 30,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.0600 10,800.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0250 4,000.00
Jumlah A 54,800.00
B BAHAN
1 Saklar Ganda BH 40,000.00 1.000 40,000.00
2 Perlengkapan % 40,000.00 0.350 14,000.00
Jumlah B 54,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 108,800.00

F Harga Satuan D + E 108,800.00

43
1 Unit Pasang Lampu SL 25 Watt + fitting downlight 5"
No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.4000 60,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.0850 15,300.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 86,100.00
B BAHAN
1 Lampu SL25 Watt Setara Philips BH 120,000.00 1.000 120,000.00
2 Lampu Hias Led BH 2,300,000.00 1.000 2,300,000.00
3 Perlengkapan % 2,420,000.00 0.035 84,700.00
Jumlah B 2,504,700.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 2,590,800.00

F Harga Satuan D + E 2,590,800.00

1 Unit Pasang Lampu SL 15 Watt + fitting standard


No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.4000 60,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.0850 15,300.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 86,100.00
B BAHAN
1 Lampu SL15 Watt Setara Philips BH 40,000.00 1.000 40,000.00
2 Fitting Standar BH 20,000.00 1.000 20,000.00
3 Perlengkapan % 60,000.00 0.035 2,100.00
Jumlah B 62,100.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 148,200.00

F Harga Satuan D + E 148,200.00

1 Unit Pasang Lampu Led 11 Watt + fitting downlight 5"


No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.4000 60,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.0850 15,300.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 86,100.00
B BAHAN
1 Lampu Led 11 Watt Philips BH 50,000.00 1.000 50,000.00
2 Downlight 5" BH 60,000.00 1.000 60,000.00
3 Perlengkapan % 110,000.00 0.035 3,850.00
Jumlah B 113,850.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 199,950.00

F Harga Satuan D + E 199,900.00

44
1 Unit Pasang Lampu Led 5 Watt + fitting downlight 5"
No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.4000 60,000.00
2 Tukang Listrik Org/Hari 180,000.00 0.0850 15,300.00
3 Kepala Tukang Listrik Org/Hari 200,000.00 0.0500 10,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 86,100.00
B BAHAN
1 Lampu Led 5 Watt Philips BH 25,000.00 1.000 25,000.00
2 Downlight 5" BH 60,000.00 1.000 60,000.00
3 Perlengkapan % 85,000.00 0.035 2,975.00
Jumlah B 87,975.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 174,075.00

F Harga Satuan D + E 174,000.00

4 Anl. Memasang 1 Buah Closed Duduk


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 pekerja Org/Hari 10,000.00 0.070 700.00
2 Tukang Batu Org/Hari 6,250.00 0.100 625.00
3 Kapala Tukang Org/Hari 20,000.00 0.010 200.00
4 Mandor Org/Hari 10,000.00 0.004 40.00
Jumlah A 1,565.00
B BAHAN
1 Closed Duduk m' 1,300,000.00 1.0000 1,300,000.00
2 Perlengkapan 35 % dari harga pipa ls 455,000.00 1.0000 455,000.00
Jumlah B 1,755,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,756,565.00

F Harga Satuan D + E 1,756,565.00

V PEKERJAAN KAYU
1 Anl 1 M3 PEK. KUSEN PINTU/JENDELA KAYU KLAS II
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 18.0000 3,240,000.00
2 Kepala Tukang Org/Hari 200,000.00 2.0000 400,000.00
3 Pekerja Org/Hari 150,000.00 6.0000 900,000.00
4 Mandor Org/Hari 160,000.00 0.3000 48,000.00
Jumlah A 4,588,000.00
B BAHAN
1 Kayu Klas II M3 4,200,000.00 1.2000 5,040,000.00
Jumlah B 5,040,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 9,628,000.00

F Harga Satuan D + E 9,628,000.00

45
2 Anl Pemasangan 1 m2 dinding pemisah Calsiboard rangkap, rangka kayu kelas II
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 0.6000 108,000.00
2 Kepala Tukang Org/Hari 200,000.00 0.0600 12,000.00
3 Pekerja Org/Hari 150,000.00 0.2000 30,000.00
4 Mandor Org/Hari 160,000.00 0.0100 1,600.00
Jumlah A 151,600.00
B BAHAN
1 Balok Kayu Klas II M3 4,200,000.00 0.0280 117,600.00
2 Paku 7 cm – 10 cm Kg 20,000.00 0.1500 3,000.00
3 Caslsiboard Lbr 70,000.00 0.8600 60,200.00
4 Lem Kayu Kg 20,000.00 0.5600 11,200.00
Jumlah B 192,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 343,600.00

F Harga Satuan D + E 343,600.00

2 Anl 1 M2 PEK. PASANG PINTU PANIL JATI


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 3.0000 540,000.00
2 Kepala Tukang Org/Hari 200,000.00 0.3000 60,000.00
3 Pekerja Org/Hari 150,000.00 1.0000 150,000.00
4 Mandor Org/Hari 160,000.00 0.0500 8,000.00
Jumlah A 758,000.00
B BAHAN
1 Papan Kayu Klas II M3 4,200,000.00 0.1000 420,000.00
2 Lem Kayu KG 20,000.00 0.5000 10,000.00
Jumlah B 430,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,188,000.00

F Harga Satuan D + E 1,188,000.00

46
3 Anl Memasang 1 m2 Panel Dinding Multipleks Finish HPL
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 0.6000 108,000.00
2 Kepala Tukang Org/Hari 200,000.00 0.0600 12,000.00
3 Pekerja Org/Hari 150,000.00 0.2000 30,000.00
4 Mandor Org/Hari 160,000.00 0.0100 1,600.00
Jumlah A 151,600.00
B BAHAN
1 Multipleks 12 mm Lbr 120,000.00 0.8600 103,200.00
2 HPL 1 mm Lbr 285,000.00 0.8600 245,100.00
4 Lem Fox Kg 20,000.00 0.5600 11,200.00
Jumlah B 359,500.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 511,100.00

F Harga Satuan D + E 511,100.00

4 Anl Memasang 1 m1 lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 0.2000 36,000.00
2 Kepala Tukang Org/Hari 200,000.00 0.0250 5,000.00
3 Pekerja Org/Hari 150,000.00 0.1000 15,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 56,800.00
B BAHAN
1 Kayu Papan Klas II M3 4,200,000.00 0.0108 45,360.00
2 Paku campur Kg 20,000.00 0.1000 2,000.00
Jumlah B 47,360.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 104,160.00

F Harga Satuan D + E 104,160.00

47
5 Anl Memasang 1 m’ list langit-langit kayu profil
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 0.0500 9,000.00
2 Kepala tukang Org/Hari 200,000.00 0.0050 1,000.00
3 Pekerja Org/Hari 150,000.00 0.0500 7,500.00
4 Mandor Org/Hari 160,000.00 0.0300 4,800.00
Jumlah 22,300.00
B BAHAN
1 Lis plafond kayu profil M1 5,000.00 1.0500 5,250.00
2 Paku Kg 20,000.00 0.0100 200.00
Jumlah B 5,450.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 27,750.00

F Harga Satuan D + E 27,750.00

6 Anl 1 M2 PEK. LANGIT-LANGIT CALSIBOARD


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 180,000.00 0.0500 9,000.00
2 Kepala tukang Org/Hari 200,000.00 0.0050 1,000.00
3 Pekerja Org/Hari 150,000.00 0.1000 15,000.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 25,800.00
B BAHAN
1 Calsiboar 3 mm Lbr 70,000.00 0.3640 25,480.00
2 Paku Calsiboard Kg 25,000.00 0.1100 2,750.00
Jumlah B 28,230.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 54,030.00

F Harga Satuan D + E 54,030.00

7 Anl Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm tebal 9 mm


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 180,000.00 0.1000 18,000.00
2 Tukang Org/Hari 200,000.00 0.0500 10,000.00
3 Kepala Tukang Org/Hari 150,000.00 0.0050 750.00
4 Mandor Org/Hari 160,000.00 0.0050 800.00
Jumlah A 29,550.00
B BAHAN
1 Gypsum board Lembar 80,000.00 0.3640 29,120.00
2 Skerup gypsum Kg 35,000.00 0.1100 3,850.00
Jumlah B 32,970.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 62,520.00

F Harga Satuan D + E 62,520.00

48
8 Anl Pemasangan 1 M1 list langit-langit gypsum board
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 180,000.00 0.0500 9,000.00
2 Tukang Org/Hari 200,000.00 0.0500 10,000.00
3 Kepala Tukang Org/Hari 150,000.00 0.0050 750.00
4 Mandor Org/Hari 160,000.00 0.0030 480.00
Jumlah 20,230.00
B BAHAN
1 List gypsum board M1 20,000.00 1.0000 20,000.00
2 Paku sekerup Kg 35,000.00 0.0100 350.00
Jumlah B 20,350.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 40,580.00

F Harga Satuan D + E 40,580.00

Anl Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 6.7000 1,005,000.00
2 Tukang Kayu Org/Hari 200,000.00 20.1000 4,020,000.00
3 Kepala Tukang Org/Hari 200,000.00 2.1000 420,000.00
4 Mandor Org/Hari 160,000.00 0.3350 53,600.00
Jumlah 5,498,600.00
B BAHAN
1 Kayu kelas II M3 4,200,000.00 1.2000 5,040,000.00
2 Besi Strip tebal 5mm Kg 28,000.00 15.0000 420,000.00
3 Paku 12mm Kg 20,000.00 5.6000 112,000.00
Jumlah B 5,572,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 11,070,600.00

F Harga Satuan D + E 11,070,600.00

Anl Pemasangan 1 m3 konstruksi gordeng kayu kelas II


No. Uraian Satuan Harga - Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 6.7000 1,005,000.00
2 Tukang Kayu Org/Hari 200,000.00 20.1000 4,020,000.00
3 Kepala Tukang Org/Hari 200,000.00 2.1000 420,000.00
4 Mandor Org/Hari 160,000.00 0.3350 53,600.00
Jumlah 5,498,600.00
B BAHAN
1 Kayu kelas II M3 4,200,000.00 1.1000 4,620,000.00
2 Besi Strip tebal 5mm Kg 28,000.00 15.0000 420,000.00
3 Paku 12mm Kg 20,000.00 3.0000 60,000.00
Jumlah B 5,100,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 10,598,600.00

F Harga Satuan D + E 10,598,600.00

49
RENCANA ANGGARAN BIAYA BAHAN

PEKERJAAN : WORKSHOP BILLIARD


LOKASI : KOTA KENDARI
### : Err:509

HARGA JUMLAH HARGA


NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
I. PEKERJAAN STRUKTUR
A. Pekerjaan Tanah dan Pondasi
1 Pek. Galian Pondasi Menerus M3 225.00 116,500.00 26,212,500.00
2 Pek. Urugan Tanah Kembali M3 75.00 38,800.00 2,910,000.00
3 Pek. Batu Kosong (Aanstamping) M3 45.00
- Batu belah 15 cm/20 cm M3 54.00 350,000.00 18,900,000.00
- Pasir Urug M3 19.44 180,000.00 3,499,200.00
4 Pek. Pondasi Batu Belah M3 126.00
- Batu Gunung M3 151.20 350,000.00 52,920,000.00
- Semen Portland KG 20,538 1,700.00 34,914,600.00
- Pasir Pasang M3 65.52 200,000.00 13,104,000.00
5 Pek. Pasangan Sloof 15/20
A. Pek. Beton Mutu K-175 M3 9.00
- Semen Portland (PC) KG 2,934.00 1,700.00 4,987,800.00
- Pasir Beton (PB) M3 6,840.00 189.29 1,294,714.29
- Kerikil (Kr) M3 9,261.00 263.17 2,437,234.52
- Air LTR 1,935.00 90.00 174,150.00
B. Pek. Pembesian KG 2,468.37
- Besi Beton Polos KG 2,591.79 25,000.00 64,794,712.50
- Kawat beton KG 69.11 20,000.00 1,382,287.20
C. Pek. Bekisting M2 39.38
- Kayu Kelas III M3 1.77 2,205,000.00 3,906,984.37
- Paku 5 cm - 10 cm KG 11.81 20,000.00 236,250.00
- Minyak Bekisting LTR 3.94 12,500.00 49,218.75
Jumlah 231,723,651.63
B. Pekerjaan Dinding dan Rangka Bangunan
1 Pek. Pasangan Kolom 15/15
A. Pek. Beton Mutu K-175 M3 3.92
- Semen Portland (PC) KG 1,276 1,700.00 2,169,693.00
- Pasir Beton (PB) M3 2,975 189.29 563,200.71
- Kerikil (Kr) M3 4,029 263.17 1,060,197.02
- Air LTR 842 90.00 75,755.25
B. Pek. Pembesian KG 880.88
- Besi Beton Polos KG 924.92 25,000.00 23,122,968.75
- Kawat beton KG 24.66 20,000.00 493,290.00
C. Pek. Bekisting untuk 5x Pakai M2 43.50
- Kayu Papan kelas III M3 1.74 2,205,000.00 3,836,700.00
- Paku 5 cm - 12 cm KG 17.40 20,000.00 348,000.00
- Minyak bekisting LTR 8.70 12,500.00 108,750.00
- Balok Kayu kelas III M3 0.65 2,205,000.00 1,438,762.50
- Multipleks tebal 9 mm LBR 0.35 120,000.00 42,000.00
- Dolken kayu ø8-10 ) cm- panj 4 m BTG 87.00 10,000.00 870,000.00
2 Pek. Pasangan Kolom Teras 20/20
A. Pek. Beton Mutu K-175 M3 1.14
- Semen Portland (PC) KG 372 1,700.00 631,788.00
- Pasir Beton (PB) KG 866 189.29 163,997.14
- Kerikil (Kr) KG 1,173 263.17 308,716.37
- Air LTR 245 90.00 22,059.00
B. Pek. Pembesian KG 97.11
- Besi Beton Polos KG 101.96 25,000.00 2,549,078.00
- Kawat beton KG 2.72 20,000.00 54,380.33
C. Pek. Bekisting untuk 5x Pakai M2 4.05
- Kayu Papan kelas III M3 0.16 2,205,000.00 357,504.00
- Paku 5 cm - 12 cm KG 1.62 20,000.00 32,426.67
- Minyak bekisting LTR 0.81 12,500.00 10,133.33
- Balok Kayu kelas III M3 0.06 2,205,000.00 134,064.00
- Multipleks tebal 9 mm LBR 1.42 120,000.00 170,240.00
- Dolken kayu ø8-10 ) cm- panj 4 m BTG 8.11 10,000.00 81,066.67
HARGA JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
3 Pek. Pasangan Balok Latei 13/13
A. Pek. Beton Mutu K-175 M3 0.82
- Semen Portland (PC) KG 326.00 1,700.00 554,200.00
- Pasir Beton (PB) M3 624.22 189.29 118,155.63
- Kerikil (Kr) M3 845 263.17 222,422.02
- Air LTR 176.59 90.00 15,892.93
B. Pek. Pembesian KG 166.98
- Besi Beton Polos KG 175.33 25,000.00 4,383,158.06
- Kawat beton KG 4.68 20,000.00 93,507.37
C. Pek. Bekisting untuk 5x Pakai M2 6.32
- Kayu Kelas III M3 0.28 2,205,000.00 626,903.55
- Paku 5 cm - 10 cm KG 1.90 20,000.00 37,908.00
- Minyak Bekisting LTR 0.63 12,500.00 7,897.50
4 Pek. Pasangan Balok Latei 15/15
A. Pek. Beton Mutu K-175 M3 0.47
- Semen Portland (PC) KG 152 1,700.00 257,869.26
- Pasir Beton (PB) M3 354 189.29 66,936.73
- Kerikil (Kr) M3 479 263.17 126,005.02
- Air LTR 100 90.00 9,003.55
B. Pek. Pembesian KG 45
- Besi Beton Polos KG 47 25,000.00 1,177,061.66
- Kawat beton KG 1.26 20,000.00 25,110.65
C.Pek. Bekisting untuk 5x Pakai M2 3.10
- Kayu Kelas III M3 0.14 2,205,000.00 307,795.95
- Paku 5 cm - 10 cm KG 0.93 20,000.00 18,612.00
- Minyak Bekisting LTR 0.31 12,500.00 3,877.50
5 Pek. Pasangan Ringbalok 15/20
A. Pek. Beton Mutu K-175 M3 3.38
- Semen Portland (PC) KG 1,100.25 1,700.00 1,870,425.00
- Pasir Beton (PB) M3 2,565.00 189.29 485,517.86
- Kerikil (Kr) M3 3,472.88 263.17 913,962.95
- Air LTR 725.63 90.00 65,306.25
B. Pek. Pembesian KG 309.62
- Besi Beton Polos KG 325.10 25,000.00 8,127,472.50
- Kawat beton KG 8.67 20,000.00 173,386.08
C.Pek. Bekisting untuk 5x Pakai M2 7.50
- Kayu Kelas III M3 0.34 2,205,000.00 744,187.50
- Paku 5 cm - 10 cm KG 2.25 20,000.00 45,000.00
- Minyak Bekisting LTR 0.75 12,500.00 9,375.00
6 Pek. Pasangan Kanopi keliling Tebal 12 cm
A. Pek. Beton Mutu K-175 M3 1.33
- Semen Portland (PC) KG 434.62 1,700.00 738,859.44
- Pasir Beton (PB) M3 1,013.23 189.29 191,790.34
- Kerikil (Kr) M3 1,371.86 263.17 361,035.67
- Air LTR 286.64 90.00 25,797.42
B. Pek. Pembesian KG 44.40
- Besi Beton Polos KG 46.62 25,000.00 1,165,383.45
- Kawat beton KG 1.24 20,000.00 24,861.51
C.Pek. Bekisting untuk 5x Pakai M2 4.44
- Kayu Kelas III M3 0.20 2,205,000.00 440,955.90
- Paku 5 cm - 10 cm KG 1.33 20,000.00 26,664.00
- Minyak Bekisting LTR 0.44 12,500.00 5,555.00
7 Pek. Pasangan Kanopi keliling Tebal 22 cm
A. Pek. Beton Mutu K-175 M3 2.44
- Semen Portland (PC) KG 796.81 1,700.00 1,354,575.64
- Pasir Beton (PB) M3 1,857.59 189.29 351,615.63
- Kerikil (Kr) M3 2,515.08 263.17 661,898.73
- Air LTR 525.50 90.00 47,295.27
HARGA JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
B. Pek. Pembesian KG 64.13
- Besi Beton Polos KG 67.33 25,000.00 1,683,331.65
- Kawat beton KG 1.80 20,000.00 35,911.08
C.Pek. Bekisting untuk 5x Pakai M2 7.41
- Kayu Kelas III M3 0.33 2,205,000.00 734,926.50
- Paku 5 cm - 10 cm KG 2.22 20,000.00 44,440.00
- Minyak Bekisting LTR 0.74 12,500.00 9,258.33
8 Pek. Pasangan Kanopi Teras
A. Pek. Beton Mutu K-175 M3 0.92
- Semen Portland (PC) KG 299.92 1,700.00 509,864.00
- Pasir Beton (PB) M3 699.20 189.29 132,348.57
- Kerikil (Kr) M3 946.68 263.17 249,139.53
- Air LTR 197.80 90.00 17,802.00
B. Pek. Pembesian KG 19.40
- Besi Beton Polos KG 20.37 25,000.00 509,323.50
- Kawat beton KG 0.54 20,000.00 10,865.57
C.Pek. Bekisting untuk 5x Pakai M2 4.60
- Kayu Kelas III M3 0.21 2,205,000.00 456,435.00
- Paku 5 cm - 10 cm KG 1.38 20,000.00 27,600.00
- Minyak Bekisting LTR 0.46 12,500.00 5,750.00
10 Pek. Pasangan Bata Merah Camp. 1 : 4 M2 442.35
- Batu bata BIJI 30,964.50 700.00 21,675,150.00
- Semen KG 5,087.03 1,700.00 8,647,942.50
- Pasir Pasang M3 19.02 200,000.00 3,804,210.00
Jumlah 103,082,307.50
Total Sub-Pekerjaan Struktur 334,805,959.13
HARGA JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
II. PEKERJAAN ARSITEKTUR
A. Pekerjaan Lantai
1 Pek. Rabat Beton Lantai tebal 5 cm M3 8.40
- Semen Portland (PC) KG 1,907 1,700.00 3,241,560.00
- Pasir Beton (PB) M3 7,300 189.29 1,381,710.00
- Kerikil (Kr) M3 8,400 263.17 2,210,643.56
- Air LTR 1,806.00 90.00 162,540.00
2 Pek. Urugan Pasir Bawah Lantai M3 8.40
- Pasir Urug M3 10.08 180,000.00 1,814,400.00
3 Pek. Urugan Tanah Bawah Lantai M3 33.60
- Sirtu M3 40.32 80,000.00 3,225,600.00
4 Pek. Lantai Keramik 80 x 80 M2 145.00
- Tegel Keramik 80 x 80 cm BH 449.50 150,000.00 67,425,000.00
- Semen warna KG 139.20 28,000.00 3,897,600.00
- Semen portland KG 217.50 1,700.00 369,750.00
- Pasir Pasang M3 6.52 200,000.00 1,305,000.00
5 Pek. Lantai Keramik 40 x 40 M2 26.36
- Tegel Warna 40 x 40 Cm BH 698.54 17,000.00 11,875,180.00
- Semen warna KG 2.64 28,000.00 73,808.00
- Semen portland KG 274.14 1,700.00 466,044.80
- Pasir Pasang M3 1.19 200,000.00 237,240.00
6 Pek. Plint Lantai Keramik 10 x 60 M1 98.75
- Tegel Plint Keramik 10 x 60 Cm BH 167.88 15,000.00 2,518,125.00
- Semen portland KG 112.57 1,700.00 191,377.50
- Pasir Pasang KG 0.30 200,000.00 59,250.00
- Semen warna KG 9.88 28,000.00 276,500.00
7 Pek. Keramik 20x20 untuk KM M2 5.93
- Tegel Anti slip 20 x 20 Cm BH 157.14 3,200.00 502,864.00
- Semen warna KG 5.93 28,000.00 166,040.00
- Semen portland KG 61.67 1,700.00 104,842.40
- Pasir Pasang KG 0.27 200,000.00 53,370.00
8 Pek. Keramik 20x20 untuk dinding KM M2 27.27
- Tegel Dinding Keramik 20 x20 Cm BH 722.66 3,200.00 2,312,496.00
- Semen portland KG 253.61 1,700.00 431,138.70
- Pasir Pasang M3 0.49 200,000.00 98,172.00
Jumlah 104,400,251.96
B. Pekerjaan Plesteran
1 Pek. Plesteran Dinding Camp. 1 : 5 tebal 1,5 cm M2 799.60
- Semen Portlan (PC) KG 4,145.13 1,700.00 7,046,714.88
- Pasir Pasang (PP) M3 20.79 200,000.00 4,157,920.00
2 Pekerjaan Acian Dinding M2 799.60
- Semen KG 2,599 1,700.00 4,417,790.00
Jumlah 15,622,424.88
C. Pekerjaan Plafond dan Atap
1 Pek. Rangka Baja ringan M2 366.30
- Main Trus C 75 - 75 M1 1,025.64 19,000.00 19,487,179.49
- Reef Botton / Reng R 33-0,45 M1 1,684.98 10,000.00 16,849,816.85
- Self drilling Screw dia 6 x 20 mm (Truss Screw) BH 6,227.11 500.00 3,113,553.11
- Self drilling Screw dia 4 x 16 mm (Roof Bottom Screw) BH 8,791.21 500.00 4,395,604.40
- Dynabolt 12 x 120 mm BH 366.30 5,500.00 2,014,652.01
- Alat bantu LS 12.82 35,500.00 455,128.21
HARGA JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
2 Pek. Atap Spandek M2 366.30
- Genteng Metal LMBR 476.19 49,000.00 23,333,333.33
- Baut Spandek 4,5cm BH 2,198 1,000.00 2,197,802.20
3 Pek. Nok dan Jurai Atap Metal M1 80.36
- Nok Genteng Metal LMBR 88.40 35,000.00 3,093,860.00
- Paku Atap KG 4.02 20,000.00 80,360.00
4 Pek. Listplank 1x20 cm M1 300.00
Kayu Papan Klas II M3 3.24 4,200,000.00 13,608,000.00
Paku 5 dan 7 cm KG 30.00 20,000.00 600,000.00
5 Pek. Rangka Plafond Besi Hollow Modul 60 x 60 cm M2 154.45
- Rangka Besi Hollow 40.40.2 cm M1 617.80 22,000.00 13,591,600.00
- Assesoris (perkuatan, las dll) LS 154.45 30,800.00 4,757,060.00
6 Pek. Plafond Gypsum t= 9 mm M2 154.45
- Gypsum Board LMBR 56.22 80,000.00 4,497,584.00
- Sekrup Gypsum DUS 16.99 35,000.00 594,632.50
7 Pas. List Plafond Gipsum M1 132.80 20,000.00 2,656,000.00
115,326,166.10
D. Pekerjaan Kusen dan Aksesoris
1 Pembuatan dan Pemasangan Kusen Kayu Kelas II (Pintu,Jendela & Ventilasi) 0.92
- Kayu Klas II M3 1.10 4,200,000.00 4,611,600.00
2 Pembuatan dan Pemasangan Daun Pintu & Jendela Kayu Kelas II M3 1.72
- Papan Kayu Klas II M3 0.17 4,200,000.00 723,240.00
- Lem Kayu KG 0.86 20,000.00 17,220.00
3 Pek. Pemasangan Pintu WC BH 2.00 920,000.00 1,840,000.00
4 Pek. Pengadaan dan Pemasangan Pintu Jendela Aluminium
A. Pembuatan dan Pemasangan Kusen Aluminium M1 13.00
- Profil Aluminium 4" M1 14.30 100,000.00 1,430,000.00
- Skrup Fixer BH 26.00 500.00 13,000.00
- Sealant TUBE 0.78 66,000.00 51,480.00
B. Pembuatan dan Pemasangan Daun Pintu Aluminium M2 3.34
- Profil Aluminium M1 14.71 80,000.00 1,177,088.00
- Aluminium Strip M1 48.82 45,000.00 2,197,008.00
C. Pek. Pemasangan Handle Pintu dan Kunci Tanam BH 2.00 268,500.00 537,000.00
D. Pek. Rel sliding door SET 2.00 300,000.00 600,000.00
E. Pek. Pemasangan Kaca pintu 3mm M2 5.14 131,300.00 674,882.00
5 Pek. Pemasangan Handle Pintu dan Kunci Tanam BH 7.00 200,000.00 1,400,000.00
6 Pek. Pemasangan Engsel Pintu BH 21.00 45,000.00 945,000.00
7 Pek. Pemasangan Engsel Jendela BH 38.00 40,000.00 1,520,000.00
8 Pek. Pemasangan Rel sliding door SET 2.00 300,000.00 600,000.00
9 Pek. Pemasangan Kaca 3mm M2 12.86 90,000.00 1,157,400.00
10 Pek. Pasangan Grendel Daun Jendela BH 23.00 26,000.00 598,000.00
11 Pek. Pasangan Kait Daun Jendela Standar BH 38.00 15,000.00 570,000.00
12 Pek. Pemasangan Lubang Udara Roster Block BH 18.00 35,000.00 630,000.00
Jumlah 21,292,918.00
E. Pekerjaan Pengecetan
1 Pek. Pengecetan Tembok Baru (Cat Dasar, Cat Penutup) M2 799.60
- Plamir KG 79.96 10,000.00 799,600.00
- Cat Dasar KG 79.96 45,000.00 3,598,200.00
- Cat Penutup KG 207.90 50,000.00 10,394,800.00
2 Pek. Pengecetan Plafond Gypsum (Plamir, Cat Penutup) M2 182.87
- Plamir KG 18.29 10,000.00 182,870.00
- Cat Dasar KG 18.29 45,000.00 822,915.00
- Cat Penutup KG 47.55 50,000.00 2,377,310.00
3 Pek. PengecetanPengecatan Kalsiplank 3 x sapu Cat Minyak M2 90.00
- Cat meni KG 18.00 25,000.00 450,000.00
- Plamir KG 13.50 15,000.00 202,500.00
- Cat dasar KG 15.30 45,000.00 688,500.00
- cat penutup/kilap 3 x KG 31.50 50,000.00 1,575,000.00

Jumlah 21,091,695.00
Total Sub-Pekerjaan Arsitektur 277,733,455.93
HARGA JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6

III. PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING


A. Pekerjaan Instalasi Listrik
1 Pek. Pasangan Instalasi Penerangan TITIK 100.00
- Kabel NYM 2 x 2,5 mm M1 500.00 10,000.00 5,000,000.00
- Pipa Conduit M1 500.00 6,250.00 3,125,000.00
- Fitting (Elbow, T-Dus, Mongkok) BH 300.00 20,000.00 6,000,000.00
- Klem BH 400.00 10,000.00 4,000,000.00
- Fisher dan skrup BH 400.00 7,000.00 2,800,000.00
- Fitting Lampu BH 100.00 20,000.00 2,000,000.00
2 Pek. Pas. Lampu HIAS LED BH 8.00 2,300,000.00 18,400,000.00
3 Pek. Pas. Lampu LED 11 Watt Setara Philips BH 60.00
- Lampu Led 11 Watt Philips BH 60.00 50,000.00 3,000,000.00
- Downlight 5" BH 60.00 60,000.00 3,600,000.00
- Perlengkapan LS 2.10 110,000.00 231,000.00
4 Pek. Pas. Lampu LED 5 Watt BH 20.00
- Lampu Led 5 Watt Philips BH 20.00 25,000.00 500,000.00
- Downlight 5" BH 20.00 60,000.00 1,200,000.00
- Perlengkapan LS 0.70 85,000.00 59,500.00
5 Pek. Pasangan Stop Kontak Tanam BH 30.00
- Stop Kontak BH 30.00 40,000.00 1,200,000.00
- Perlengkapan LS 10.50 40,000.00 420,000.00
6 Pek. Pasang Saklar Ganda Tanam BH 20.00
- Saklar Ganda BH 20.00 40,000.00 800,000.00
- Perlengkapan LS 7.00 40,000.00 280,000.00
7 Pek. Pasang Saklar Tunggal Tanam BH 20.00
- Saklar Tunggal BH 20.00 35,000.00 700,000.00
- Perlengkapan LS 7.00 35,000.00 245,000.00
Jumlah 53,560,500.00
B. Pekerjaan Jaringan Air
1 Pek. Pemasangan Floor Drain BH 6.00 80,000.00 480,000.00
2 Pek. Pemasangan Closet Duduk BH 3.00
- Closed Duduk BH 3.00 1,300,000.00 3,900,000.00
- Semen Portland KG 18.00 1,700.00 30,600.00
- Pasir Pasang M3 0.03 200,000.00 6,000.00
3 Pek. Pemasangan Closet Jongkok BH 1.00
- Closed Jongkok BH 1.00 500,000.00 500,000.00
- Semen Portland KG 6.00 1,700.00 10,200.00
- Pasir Pasang M3 0.01 200,000.00 2,000.00
4 Pek. Pemasangan Kran Air 1/2" BH 10.00
- Kran air BH 10.00 55,000.00 550,000.00
- Seal tape BH 2.50 5,000.00 12,500.00
5 Pek. Pemasangan Pipa PVC dia. 1/2" M1 101.65
- Pipa PVC 1/2" M1 121.98 5,300.00 646,494.00
- Perlengkapan 35 % dari harga pipa LS 101.65 2,226.00 226,272.90
6 Pek. Pemasangan Pipa PVC dia. 3" M1 42.00
- Pipa PVC 3" M1 50.40 53,000.00 2,671,200.00
- Perlengkapan 35 % dari harga pipa LS 42.00 18,550.00 779,100.00
7 Pek. Pemasangan Pipa PVC dia. 4" M1 50.00
- Pipa PVC 4" M1 60.00 85,000.00 5,100,000.00
- Perlengkapan 35 % dari harga pipa LS 50.00 29,750.00 1,487,500.00
8 Pek. Pembuatan Septic Tank + Resapan LS 2.00 2,500,000.00 5,000,000.00
Jumlah 21,401,866.90
Total Sub-Pekerjaan Mekanikal Elektrikal Plumbing 74,962,366.90
KEBUTUHAN BAHAN BANGUNAN

PEKERJAAN : WORKSHOP BILLIARD


LOKASI : KOTA KENDARI
### : Err:509

HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
I. PEKERJAAN STRUKTUR
A. Pekerjaan Tanah dan Pondasi
1 Pek. Galian Pondasi Menerus M3 225 116,500.00 26,212,500.00
2 Pek. Urugan Tanah Kembali M3 75 38,800.00 2,910,000.00
3 Pek. Batu Kosong (Aanstamping) M3 45.0
- Batu belah 15 cm/20 cm RIT 8.3 2,275,000.00 18,900,000.00
- Pasir Urug RIT 3.0 1,170,000.00 3,499,200.00
4 Pek. Pondasi Batu Belah M3 126.0
- Batu Gunung RIT 23.3 2,275,000.00 52,920,000.00
- Semen Portland ZAK 411 85,000.00 34,914,600.00
- Pasir Pasang RIT 10.1 1,300,000.00 13,104,000.00
5 Pek. Pasangan Sloof 15/20
A. Pek. Beton Mutu K-175 M3 9.0
- Semen Portland (PC) ZAK 59 85,000.00 4,987,800.00
- Pasir Beton (PB) RIT 0.8 1,722,500.00 1,294,714.29
- Kerikil (Kr) RIT 1.1 2,309,333.00 2,437,234.52
- Air LITER 1935 90.00 174,150.00
B. Pek. Pembesian KG 2468.4
- Besi Beton Polos Ǿ 10 BATANG 227 185,000.00 41,958,000.00
- Besi Beton Polos Ǿ 8 BATANG 193 118,500.00 22,836,712.50
- Kawat beton KG 69 20,000.00 1,382,287.20
C. Pek. Bekisting M2 39.4
- Kayu Kelas III M3 1.8 2,205,000.00 3,906,984.37
- Paku 5 cm - 10 cm KG 11.8 20,000.00 236,250.00
- Minyak Bekisting LTR 3.9 12,500.00 49,218.75
Jumlah 231,723,651.63
B. Pekerjaan Dinding dan Rangka Bangunan
1 Pek. Pasangan Kolom 15/15
A. Pek. Beton Mutu K-175 M3 3.9
- Semen Portland (PC) ZAK 26 85,000.00 2,169,693.00
- Pasir Beton (PB) RIT 0.3 1,722,500.00 563,200.71
- Kerikil (Kr) RIT 0.5 2,309,333.00 1,060,197.02
- Air LITER 842 90.00 75,755.25
B. Pek. Pembesian KG 880.9
- Besi Beton Polos Ǿ 10 BATANG 99 185,000.00 18,251,730.00
- Besi Beton Polos Ǿ 8 BATANG 41 118,500.00 4,871,238.75
- Kawat beton KG 24.7 20,000.00 493,290.00
C. Pek. Bekisting untuk 5x Pakai M2 43.5
- Kayu Papan kelas III M3 1.7 2,205,000.00 3,836,700.00
- Paku 5 cm - 12 cm KG 17 20,000.00 348,000.00
- Minyak bekisting LTR 8.7 12,500.00 108,750.00
- Balok Kayu kelas III M3 0.7 2,205,000.00 1,438,762.50
- Multipleks tebal 9 mm LBR 0.4 120,000.00 42,000.00
- Dolken kayu ø8-10 ) cm- panj 4 m BTG 87 10,000.00 870,000.00
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
2 Pek. Pasangan Kolom Teras 20/20
A. Pek. Beton Mutu K-175 M3 1.1
- Semen Portland (PC) ZAK 7 85,000.00 631,788.00
- Pasir Beton (PB) RIT 0.1 1,722,500.00 163,997.14
- Kerikil (Kr) RIT 0.1 2,309,333.00 308,716.37
- Air LITER 245 90.00 22,059.00
B. Pek. Pembesian KG 97.1
- Besi Beton Polos Ǿ 10 BATANG 10 185,000.00 1,771,560.00
- Besi Beton Polos Ǿ 8 BATANG 7 118,500.00 777,518.00
- Kawat beton KG 2.7 20,000.00 54,380.33
C. Pek. Bekisting untuk 5x Pakai M2 4.1
- Kayu Papan kelas III M3 0.2 2,205,000.00 357,504.00
- Paku 5 cm - 12 cm KG 1.6 20,000.00 32,426.67
- Minyak bekisting LTR 0.8 12,500.00 10,133.33
- Balok Kayu kelas III M3 0.1 2,205,000.00 134,064.00
- Multipleks tebal 9 mm LBR 1.4 120,000.00 170,240.00
- Dolken kayu ø8-10 ) cm- panj 4 m BTG 8 10,000.00 81,066.67
3 Pek. Pasangan Balok Latei 13/13
A. Pek. Beton Mutu K-175 M3 0.8
- Semen Portland (PC) ZAK 6.5 85,000.00 554,200.00
- Pasir Beton (PB) RIT 0.1 1,722,500.00 118,155.63
- Kerikil (Kr) RIT 0.1 2,309,333.00 222,422.02
- Air LTR 177 90.00 15,892.93
B. Pek. Pembesian KG 167.0
- Besi Beton Polos Ǿ 6 BATANG 47 66,500.00 3,148,551.00
- Besi Beton Polos Ǿ 6 BATANG 19 66,500.00 1,234,607.06
- Kawat beton KG 5 20,000.00 93,507.37
C. Pek. Bekisting untuk 5x Pakai M2 6.3
- Kayu Kelas III M3 0.3 2,205,000.00 626,903.55
- Paku 5 cm - 10 cm KG 2 20,000.00 37,908.00
- Minyak Bekisting LTR 0.6 12,500.00 7,897.50
4 Pek. Pasangan Balok Latei 15/15
A. Pek. Beton Mutu K-175 M3 0.5
- Semen Portland (PC) ZAK 3.0 85,000.00 257,869.26
- Pasir Beton (PB) RIT 0.04 1,722,500.00 66,936.73
- Kerikil (Kr) RIT 0.1 2,309,333.00 126,005.02
- Air LTR 100 90.00 9,003.55
B. Pek. Pembesian KG 44.8
- Besi Beton Polos Ǿ 8 BATANG 7 118,500.00 857,703.00
- Besi Beton Polos Ǿ 6 BATANG 5 66,500.00 319,358.65
- Kawat beton KG 1.3 20,000.00 25,110.65
C.Pek. Bekisting untuk 5x Pakai M2 3.1
- Kayu Kelas III M3 0.1 2,205,000.00 307,795.95
- Paku 5 cm - 10 cm KG 1 20,000.00 18,612.00
- Minyak Bekisting LTR 0.3 12,500.00 3,877.50
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
5 Pek. Pasangan Ringbalok 15/20
A. Pek. Beton Mutu K-175 M3 3.4
- Semen Portland (PC) ZAK 22 85,000.00 1,870,425.00
- Pasir Beton (PB) RIT 0.3 1,722,500.00 485,517.86
- Kerikil (Kr) RIT 0.4 2,309,333.00 913,962.95
- Air LTR 726 90.00 65,306.25
B. Pek. Pembesian KG 309.6
- Besi Beton Polos Ǿ 10 BATANG 39 185,000.00 7,288,312.50
- Besi Beton Polos Ǿ 8 BATANG 7 118,500.00 839,160.00
- Kawat beton KG 9 20,000.00 173,386.08
C.Pek. Bekisting untuk 5x Pakai M2 7.5
- Kayu Kelas III M3 0.3 2,205,000.00 744,187.50
- Paku 5 cm - 10 cm KG 2.3 20,000.00 45,000.00
- Minyak Bekisting LTR 0.8 12,500.00 9,375.00
6 Pek. Pasangan Kanopi keliling Tebal 12 cm
A. Pek. Beton Mutu K-175 M3 1.3
- Semen Portland (PC) ZAK 9 85,000.00 738,859.44
- Pasir Beton (PB) RIT 0.1 1,722,500.00 191,790.34
- Kerikil (Kr) RIT 0.2 2,309,333.00 361,035.67
- Air LTR 287 90.00 25,797.42
B. Pek. Pembesian KG 44.4
- Besi Beton Polos Ǿ 6 BATANG 18 66,500.00 1,165,383.45
- Kawat beton KG 1.2 20,000.00 24,861.51
C.Pek. Bekisting untuk 5x Pakai M2 4.4
- Kayu Kelas III M3 0.2 2,205,000.00 440,955.90
- Paku 5 cm - 10 cm KG 1.3 20,000.00 26,664.00
- Minyak Bekisting LTR 0.4 12,500.00 5,555.00
7 Pek. Pasangan Kanopi keliling Tebal 22 cm
A. Pek. Beton Mutu K-175 M3 2.4
- Semen Portland (PC) ZAK 16 85,000.00 1,354,575.64
- Pasir Beton (PB) RIT 0.2 1,722,500.00 351,615.63
- Kerikil (Kr) RIT 0.3 2,309,333.00 661,898.73
- Air LTR 526 90.00 47,295.27
B. Pek. Pembesian KG 64.1
- Besi Beton Polos Ǿ 6 BATANG 25.3 66,500.00 1,683,331.65
- Kawat beton KG 1.8 20,000.00 35,911.08
C.Pek. Bekisting untuk 5x Pakai M2 7.4
- Kayu Kelas III M3 0.3 2,205,000.00 734,926.50
- Paku 5 cm - 10 cm KG 2.2 20,000.00 44,440.00
- Minyak Bekisting LTR 0.7 12,500.00 9,258.33
8 Pek. Pasangan Kanopi Teras
A. Pek. Beton Mutu K-175 M3 0.9
- Semen Portland (PC) ZAK 6.0 85,000.00 509,864.00
- Pasir Beton (PB) RIT 0.1 1,722,500.00 132,348.57
- Kerikil (Kr) RIT 0.1 2,309,333.00 249,139.53
- Air LTR 198 90.00 17,802.00
B. Pek. Pembesian KG 19.4
- Besi Beton Polos Ǿ 6 BATANG 7.7 66,500.00 509,323.50
- Kawat beton KG 0.5 20,000.00 10,865.57
C.Pek. Bekisting untuk 5x Pakai M2 4.6
- Kayu Kelas III M3 0.2 2,205,000.00 456,435.00
- Paku 5 cm - 10 cm KG 1.4 20,000.00 27,600.00
- Minyak Bekisting LTR 0.5 12,500.00 5,750.00
10 Pek. Pasangan Bata Merah Camp. 1 : 4 M2 442.3
- Batu bata BIJI 30964 700.00 21,675,150.00
- Semen ZAK 102 85,000.00 8,647,942.50
- Pasir Pasang RIT 2.9 1,300,000.00 3,804,210.00
Jumlah 103,082,307.50
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
II. PEKERJAAN ARSITEKTUR
A. Pekerjaan Lantai
1 Pek. Rabat Beton Lantai tebal 5 cm M3 8.4
- Semen Portland (PC) ZAK 38 85,000.00 3,241,560.00
- Pasir Beton (PB) RIT 0.8 1,722,500.00 1,381,710.00
- Kerikil (Kr) RIT 1.0 2,309,333.00 2,210,643.56
- Air LTR 1806 90.00 162,540.00
2 Pek. Urugan Pasir Bawah Lantai M3 8.4
- Pasir Urug RIT 1.6 1,170,000.00 1,814,400.00
3 Pek. Urugan Tanah Bawah Lantai M3 33.6
- Sirtu RIT 6.2 520,000.00 3,225,600.00
4 Pek. Lantai Keramik 80 x 80 M2 145.0
- Tegel Keramik 80 x 80 cm DUS 225 300,000.00 67,425,000.00
- Semen warna KG 139 28,000.00 3,897,600.00
- Semen portland ZAK 4.4 85,000.00 369,750.00
- Pasir Pasang RIT 1.0 1,300,000.00 1,305,000.00
5 Pek. Lantai Keramik 40 x 40 M2 26.4
- Tegel Warna 40 x 40 Cm DUS 140 85,000.00 11,875,180.00
- Semen warna KG 26 28,000.00 738,080.00
- Semen portland ZAK 5.5 85,000.00 466,044.80
- Pasir Pasang RIT 0.2 1,300,000.00 237,240.00
6 Pek. Plint Lantai Keramik 10 x 60 M1 98.8
- Tegel Plint Keramik 10 x 60 Cm DUS 28 90,000.00 2,518,125.00
- Semen portland ZAK 2.3 85,000.00 191,377.50
- Pasir Pasang RIT 0.05 1,300,000.00 59,250.00
- Semen warna KG 10 28,000.00 276,500.00
7 Pek. Keramik 20x20 untuk KM M2 5.9
- Tegel Anti slip 20 x 20 Cm DUS 6.3 80,000.00 502,864.00
- Semen warna KG 6 28,000.00 166,040.00
- Semen portland ZAK 1.2 85,000.00 104,842.40
- Pasir Pasang RIT 0.04 1,300,000.00 53,370.00
8 Pek. Keramik 20x20 untuk dinding KM M2 27.3
- Tegel Dinding Keramik 20 x20 Cm DUS 29 80,000.00 2,312,496.00
- Semen portland ZAK 5 85,000.00 431,138.70
- Pasir Pasang RIT 0.1 1,300,000.00 98,172.00
Jumlah 105,064,523.96
B. Pekerjaan Plesteran
1 Pek. Plesteran Dinding Camp. 1 : 5 tebal 1,5 cm M2 799.6
- Semen Portlan (PC) ZAK 83 85,000.00 7,046,714.88
- Pasir Pasang (PP) RIT 3.2 1,300,000.00 4,157,920.00
2 Pekerjaan Acian Dinding M2 799.6
- Semen ZAK 52 85,000.00 4,417,790.00
Jumlah 15,622,424.88
C. Pekerjaan Plafond dan Atap
1 Pek. Rangka Baja ringan M2 366.3
- Main Trus C 75 - 75 BATANG 171 114,000.00 19,487,179.49
- Reef Botton / Reng R 33-0,45 BATANG 281 60,000.00 16,849,816.85
- Self drilling Screw dia 6 x 20 mm (Truss Screw) DUS 12 250,000.00 3,113,553.11
- Self drilling Screw dia 4 x 16 mm (Roof Bottom Screw) DUS 18 250,000.00 4,395,604.40
- Dynabolt 12 x 120 mm DUS 7 302,500.00 2,014,652.01
- Alat bantu LS 12.8 35,500.00 455,128.21
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
2 Pek. Atap Spandek M2 366.3
- Genteng Metal LEMBAR 476 49,000.00 23,333,333.33
- Baut Spandek 4,5cm DUS 44 50,000.00 2,197,802.20
3 Pek. Nok dan Jurai Atap Metal M1 80.4
- Nok Genteng Metal LMBR 88 35,000.00 3,093,860.00
- Paku Atap KG 4 20,000.00 80,360.00
4 Pek. Listplank 1x20 cm M1 300.0
Kayu Papan Klas II M3 3.2 4,200,000.00 13,608,000.00
Paku 5 dan 7 cm KG 30.0 20,000.00 600,000.00
5 Pek. Rangka Plafond Besi Hollow Modul 60 x 60 cm M2 154.5
- Rangka Besi Hollow 40.40.2 cm BATANG 154 88,000.00 13,591,600.00
- Assesoris (perkuatan, las dll) LS 154 30,800.00 4,757,060.00
6 Pek. Plafond Gypsum t= 9 mm M2 154.5
- Gypsum Board LMBR 56 80,000.00 4,497,584.00
- Sekrup Gypsum DUS 17 35,000.00 594,632.50
7 Pas. List Plafond Gipsum BATANG 66 40,000.00 2,656,000.00
Jumlah 115,326,166.10
D. Pekerjaan Kusen dan Aksesoris
1 Pembuatan dan Pemasangan Kusen Kayu Kelas II (Pintu,Jendela & Ventilasi) 0.9
- Kayu Klas II M3 1.1 4,200,000.00 4,611,600.00
2 Pembuatan dan Pemasangan Daun Pintu & Jendela Kayu Kelas II M3 1.7
- Papan Kayu Klas II M3 0.2 4,200,000.00 723,240.00
- Lem Kayu KG 1 20,000.00 17,220.00
3 Pek. Pemasangan Pintu WC BH 2 920,000.00 1,840,000.00
4 Pek. Pengadaan dan Pemasangan Pintu Jendela Aluminium
A. Pembuatan dan Pemasangan Kusen Aluminium M1 13.0
- Profil Aluminium 4" M1 14 100,000.00 1,430,000.00
- Skrup Fixer BH 26 500.00 13,000.00
- Sealant BOTOL 1 66,000.00 51,480.00
B. Pembuatan dan Pemasangan Daun Pintu Aluminium M2 3.3
- Profil Aluminium M1 15 80,000.00 1,177,088.00
- Aluminium Strip M1 49 45,000.00 2,197,008.00
C. Pek. Pemasangan Handle Pintu dan Kunci Tanam BH 2 268,500.00 537,000.00
D. Pek. Rel sliding door SET 2 300,000.00 600,000.00
E. Pek. Pemasangan Kaca pintu 3mm M2 5 131,300.00 674,882.00
5 Pek. Pemasangan Handle Pintu dan Kunci Tanam BH 7 200,000.00 1,400,000.00
6 Pek. Pemasangan Engsel Pintu BH 21 45,000.00 945,000.00
7 Pek. Pemasangan Engsel Jendela BH 38 40,000.00 1,520,000.00
8 Pek. Pemasangan Rel sliding door SET 2 300,000.00 600,000.00
9 Pek. Pemasangan Kaca 3mm M2 13 90,000.00 1,157,400.00
10 Pek. Pasangan Grendel Daun Jendela BH 23 26,000.00 598,000.00
11 Pek. Pasangan Kait Daun Jendela Standar BH 38 15,000.00 570,000.00
12 Pek. Pemasangan Lubang Udara Roster Block BH 18 35,000.00 630,000.00
Jumlah 21,292,918.00
E. Pekerjaan Pengecetan
1 Pek. Pengecetan Tembok Baru (Cat Dasar, Cat Penutup) M2 799.6
- Plamir KG 80 10,000.00 799,600.00
- Cat Dasar KG 80 45,000.00 3,598,200.00
- Cat Penutup KG 208 50,000.00 10,394,800.00
2 Pek. Pengecetan Plafond Gypsum (Plamir, Cat Penutup) M2 182.9
- Plamir KG 18 10,000.00 182,870.00
- Cat Dasar KG 18 45,000.00 822,915.00
- Cat Penutup KG 48 50,000.00 2,377,310.00
3 Pek. PengecetanPengecatan Kalsiplank 3 x sapu Cat Minyak M2 90.0
- Cat meni KG 18 25,000.00 450,000.00
- Plamir KG 14 15,000.00 202,500.00
- Cat dasar KG 15.3 45,000.00 688,500.00
- cat penutup/kilap 3 x KG 31 50,000.00 1,575,000.00
Jumlah 21,091,695.00
HARGA JUMLAH
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 3 4 5 6
III. PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING
A. Pekerjaan Instalasi Listrik
1 Pek. Pasangan Instalasi Penerangan TITIK 100.0
- Kabel NYM 2 x 2,5 mm M1 500 10,000.00 5,000,000.00
- Pipa Conduit M1 500 6,250.00 3,125,000.00
- Fitting (Elbow, T-Dus, Mongkok) BH 300 20,000.00 6,000,000.00
- Klem BH 400 10,000.00 4,000,000.00
- Fisher dan skrup BH 400 7,000.00 2,800,000.00
- Fitting Lampu BH 100 20,000.00 2,000,000.00
2 Pek. Pas. Lampu HIAS LED BH 8 2,300,000.00 18,400,000.00
3 Pek. Pas. Lampu LED 11 Watt Setara Philips BH 60.0
- Lampu Led 11 Watt Philips BH 60 50,000.00 3,000,000.00
- Downlight 5" BH 60 60,000.00 3,600,000.00
- Perlengkapan LS 2 110,000.00 231,000.00
4 Pek. Pas. Lampu LED 5 Watt BH 20.0
- Lampu Led 5 Watt Philips BH 20 25,000.00 500,000.00
- Downlight 5" BH 20 60,000.00 1,200,000.00
- Perlengkapan LS 0.7 85,000.00 59,500.00
5 Pek. Pasangan Stop Kontak Tanam BH 30.0
- Stop Kontak BH 30 40,000.00 1,200,000.00
- Perlengkapan LS 11 40,000.00 420,000.00
6 Pek. Pasang Saklar Ganda Tanam BH 20.0
- Saklar Ganda BH 20.0 40,000.00 800,000.00
- Perlengkapan LS 7.0 40,000.00 280,000.00
7 Pek. Pasang Saklar Tunggal Tanam BH 20.0
- Saklar Tunggal BH 20 35,000.00 700,000.00
- Perlengkapan LS 7 35,000.00 245,000.00
Jumlah 53,560,500.00
B. Pekerjaan Jaringan Air
1 Pek. Pemasangan Floor Drain BH 6.0 80,000.00 480,000.00
2 Pek. Pemasangan Closet Duduk BH 3.0
- Closed Duduk BH 3.0 1,300,000.00 3,900,000.00
- Semen Portland KG 18.0 1,700.00 30,600.00
- Pasir Pasang M3 0.030 200,000.00 6,000.00
3 Pek. Pemasangan Closet Jongkok BH 1.0
- Closed Jongkok BH 1.0 500,000.00 500,000.00
- Semen Portland KG 6.0 1,700.00 10,200.00
- Pasir Pasang M3 0.010 200,000.00 2,000.00
4 Pek. Pemasangan Kran Air 1/2" BH 10.0
- Kran air BH 10 55,000.00 550,000.00
- Seal tape BH 2.5 5,000.00 12,500.00
5 Pek. Pemasangan Pipa PVC dia. 1/2" M1 101.7
- Pipa PVC 1/2" M1 122 5,300.00 646,494.00
- Perlengkapan 35 % dari harga pipa LS 102 2,226.00 226,272.90
6 Pek. Pemasangan Pipa PVC dia. 3" M1 42.0
- Pipa PVC 3" M1 50 53,000.00 2,671,200.00
- Perlengkapan 35 % dari harga pipa LS 42 18,550.00 779,100.00
7 Pek. Pemasangan Pipa PVC dia. 4" M1 50.0
- Pipa PVC 4" M1 60 85,000.00 5,100,000.00
- Perlengkapan 35 % dari harga pipa LS 50 29,750.00 1,487,500.00
8 Pek. Pembuatan Septic Tank + Resapan LS 2 2,500,000.00 5,000,000.00
Jumlah 21,401,866.90
KEBUTUHAN BAHAN BANGUNAN

PEKERJAAN : CARPORT
LOKASI : KOTA KENDARI
OWNER : MRS. S

HARGA JUMLAH HARGA


NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
I. PEKERJAAN STRUKTUR
A. Pekerjaan Tanah dan Pondasi
1 Pek. Galian Pondasi Menerus M3 18.00 116,500.00 2,097,000.00
2 Pek. Galian Pondasi Poerplat M3 3.00 116,500.00 349,500.00
3 Pek. Urugan Tanah Kembali M3 6.00 38,800.00 232,800.00
4 Pek. Batu Kosong (Aanstamping) M3 3.60
- Batu belah 15 cm/20 cm RIT 0.66 2,275,000.00 1,512,000.00
- Pasir Urug RIT 1.56 1,170,000.00 1,819,584.00
5 Pek. Pondasi Batu Belah M3 10.08
- Batu Gunung RIT 1.86 2,275,000.00 4,233,600.00
- Semen Portland ZAK 33 85,000.00 2,793,168.00
- Pasir Pasang RIT 0.81 1,300,000.00 1,048,320.00
6 Pek. Pasangan Sloof 15/20
A. Pek. Beton Mutu K-175 M3 0.72
- Semen Portland (PC) ZAK 4.69 85,000.00 399,024.00
- Pasir Beton (PB) RIT 0.06 1,722,500.00 103,577.14
- Kerikil (Kr) RIT 0.08 2,309,333.00 194,978.76
- Air LTR 154.80 90.00 13,932.00
B. Pek. Pembesian KG 180.07
- Besi Beton Polos Ǿ 10 BATANG 18.14 185,000.00 3,356,640.00
- Besi Beton Polos Ǿ 8 BATANG 11.56 118,500.00 1,370,202.75
- Kawat beton KG 5.04 20,000.00 100,839.31
C. Pek. Bekisting M2 3.15
- Kayu Kelas III M3 0.05 2,205,000.00 99,225.00
- Paku 5 cm - 10 cm KG 0.95 20,000.00 18,900.00
- Minyak Bekisting LTR 0.32 12,500.00 3,937.50
7 Pek. Pondasi Poer Plat Beton Bertulang
A. Pek. Beton Mutu K-175 M3 0.13
- Semen Portland (PC) ZAK 1 85,000.00 72,046.00
- Pasir Beton (PB) RIT 0.01 1,722,500.00 18,701.43
- Kerikil (Kr) RIT 0.02 2,309,333.00 35,204.50
- Air LTR 27.95 90.00 2,515.50
B. Pek. Pembesian KG 455.69
- Besi Beton Polos Ǿ 10 BATANG 64.4 185,000.00 11,907,483.00
- Besi Beton Polos Ǿ 8 BATANG 0.5 118,500.00 54,498.15
- Kawat beton KG 12.76 20,000.00 255,188.93
C. Pek. Bekisting M2 1.14
- Kayu Kelas III M3 0.05 2,205,000.00 113,116.50
- Paku 5 cm - 10 cm KG 0.34 20,000.00 6,840.00
- Minyak Bekisting LTR 0.11 12,500.00 1,425.00
D. Rabat Beton M3 0.10
- Semen Portland (PC) ZAK 0.44 85,000.00 37,818.20
- Pasir Beton (PB) RIT 0.01 1,722,500.00 16,119.95
- Kerikil (Kr) RIT 0.01 2,309,333.00 25,790.84
- Air LTR 21.07 90.00 1,896.30
E. Urugan Pasir Bawah Pondasi M3 0.10 262,600.00 25,734.80
Jumlah 32,321,607.57
HARGA JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
B. Pekerjaan Dinding dan Rangka Bangunan
1 Pek. Pasangan Kolom Carport 20/20
A. Pek. Beton Mutu K-175 M3 1.32
- Semen Portland (PC) ZAK 9 85,000.00 731,544.00
- Pasir Beton (PB) RIT 0.11 1,722,500.00 189,891.43
- Kerikil (Kr) RIT 0.15 2,309,333.00 357,461.06
- Air LTR 284 90.00 25,542.00
B. Pek. Pembesian KG 293.04
- Besi Beton Polos Ǿ 10 BATANG 10 185,000.00 1,771,560.00
- Besi Beton Polos Ǿ 8 BATANG 7 118,500.00 777,518.00
- Kawat beton KG 8 20,000.00 164,102.40
C. Pek. Bekisting untuk 5x Pakai M2 2.93
- Kayu Papan kelas III M3 0.12 2,205,000.00 258,720.00
- Paku 5 cm - 12 cm KG 1.17 20,000.00 23,466.67
- Minyak bekisting LTR 0.59 12,500.00 7,333.33
- Balok Kayu kelas III M3 0.04 2,205,000.00 97,020.00
- Multipleks tebal 9 mm LBR 1.03 120,000.00 123,200.00
- Dolken kayu ø8-10 ) cm- panj 4 m BTG 5.87 10,000.00 58,666.67
2 Pek. Pasangan Ringbalok 15/20
A. Pek. Beton Mutu K-175 M3 1.09
- Semen Portland (PC) ZAK 7.13 85,000.00 605,768.31
- Pasir Beton (PB) RIT 0.1 1,722,500.00 157,243.05
- Kerikil (Kr) RIT 0.13 2,309,333.00 296,002.13
- Air LTR 235.01 90.00 21,150.52
B. Pek. Pembesian KG 133.70
- Besi Beton Polos Ǿ 8 BATANG 27 118,500.00 3,147,255.30
- Besi Beton Polos Ǿ 6 BATANG 5 66,500.00 362,367.94
- Kawat beton KG 3.74 20,000.00 74,871.96
C.Pek. Bekisting untuk 5x Pakai M2 3.24
- Kayu Kelas III M3 0.15 2,205,000.00 321,356.70
- Paku 5 cm - 10 cm KG 0.97 20,000.00 19,432.00
- Minyak Bekisting LTR 0.32 12,500.00 4,048.33
3 Pek. Pasangan Atap Beton Carport
A. Pek. Beton Mutu K-175 M3 3.13
- Semen Portland (PC) ZAK 20 85,000.00 1,734,923.10
- Pasir Beton (PB) RIT 0.3 1,722,500.00 450,344.79
- Kerikil (Kr) RIT 0.4 2,309,333.00 847,751.41
- Air LTR 673 90.00 60,575.18
B. Pek. Pembesian KG 27.14
- Besi Beton Polos Ǿ 8 BATANG 6 118,500.00 712,350.63
- Kawat beton KG 0.8 20,000.00 15,196.81
C.Pek. Bekisting untuk 5x Pakai M2 20.87
- Kayu Papan kelas IV (Bekisting) M3 0.83 2,205,000.00 1,840,734.00
- Paku 5 cm - 12 cm KG 8.35 20,000.00 166,960.00
- Minyak bekisting LTR 4.17 12,500.00 52,175.00
- Balok Kayu kelas IV (Bekisting) M3 0.31 2,205,000.00 690,275.25
- Multipleks tebal 9 mm LBR 7.30 120,000.00 876,540.00
- Dolken kayu .. 8-10) cm- panj 4 m BTG 41.74 10,000.00 417,400.00
4 Pek. Pasangan Bata Merah Camp. 1 : 4 M2 54.00
- Batu bata BIJI 3,780.00 700.00 2,646,000.00
- Semen ZAK 12 85,000.00 1,055,700.00
- Pasir Pasang RIT 0.4 1,300,000.00 464,400.00
Jumlah 21,626,847.96
Total Sub-Pekerjaan Struktur 53,948,455.52
HARGA JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
II. PEKERJAAN ARSITEKTUR
A. Pekerjaan Lantai
1 Pek. Rabat Beton Lantai tebal 5 cm M3 1.95
- Semen Portland (PC) ZAK 9 85,000.00 752,505.00
- Pasir Beton (PB) RIT 0.2 1,722,500.00 320,754.11
- Kerikil (Kr) RIT 0.2 2,309,333.00 513,185.11
- Air LTR 419.25 90.00 37,732.50
Jumlah 1,624,176.72
B. Pekerjaan Plesteran
1 Pek. Plesteran Dinding Camp. 1 : 5 tebal 1,5 cm M2 81.00
- Semen Portlan (PC) ZAK 8.40 85,000.00 713,836.80
- Pasir Pasang (PP) RIT 0.32 1,300,000.00 421,200.00
2 Pekerjaan Acian Dinding M2 81.00
- Semen ZAK 5 85,000.00 447,525.00
Jumlah 1,582,561.80
C. Pekerjaan Kusen dan Aksesoris
1 Pek. Pengadaan dan Pemasangan Pintu Jendela Aluminium
A. Pembuatan dan Pemasangan Kusen Aluminium M1 66.00
- Profil Aluminium 4" M1 72.60 100,000.00 7,260,000.00
- Skrup Fixer BH 132.00 500.00 66,000.00
- Sealant BOTOL 3.96 66,000.00 261,360.00
B. Pek. Pemasangan Fiber glass 3mm M2 28.08 480,000.00 13,478,400.00
Jumlah 21,065,760.00
D. Pekerjaan Pengecetan
1 Pek. Pengecetan Tembok Baru (Cat Dasar, Cat Penutup) M2 54.00
- Plamir KG 5.40 10,000.00 54,000.00
- Cat Dasar KG 5.40 45,000.00 243,000.00
- Cat Penutup KG 14.04 50,000.00 702,000.00
Jumlah 999,000.00
Total Sub-Pekerjaan Arsitektur 25,271,498.52

III. PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING


A. Pekerjaan Instalasi Listrik
1 Pek. Pasangan Instalasi Penerangan TITIK 3.00
- Kabel NYM 2 x 2,5 mm M1 15.00 10,000.00 150,000.00
- Pipa Conduit M1 15.00 6,250.00 93,750.00
- Fitting (Elbow, T-Dus, Mongkok) BH 9.00 20,000.00 180,000.00
- Klem BH 12.00 10,000.00 120,000.00
- Fisher dan skrup BH 12.00 7,000.00 84,000.00
- Fitting Lampu BH 3.00 20,000.00 60,000.00
3 Pek. Pas. Lampu LED 11 Watt Setara Philips BH 3.00
- Lampu Led 11 Watt Philips BH 3.00 50,000.00 150,000.00
- Downlight 5" BH 3.00 60,000.00 180,000.00
- Perlengkapan LS 0.11 110,000.00 11,550.00
Jumlah 1,029,300.00
B. Pekerjaan Jaringan Air
1 Pek. Pemasangan Pipa PVC dia. 3" M1 24.50
- Pipa PVC 3" M1 29.40 53,000.00 1,558,200.00
- Perlengkapan 35 % dari harga pipa LS 24.50 18,550.00 454,475.00
Jumlah 2,012,675.00
Total Sub-Pekerjaan Mekanikal Elektrikal Plumbing 3,041,975.00
DAFTAR HARGA BAHAN DAN UPAH KERJA

.
HARGA
NO. URAIAN JENIS TENAGA / BAHAN SATUAN
('Rp.)
1 2 3 4
I UPAH TENAGA KERJA :
1 Pekerja Hari 150,000.00
2 Mandor Hari 160,000.00
3 Tukang Batu Hari 180,000.00
4 Tukang Kayu Hari 180,000.00
5 Tukang Besi, Aluminium Hari 180,000.00
6 Tukang Cat Hari 180,000.00
7 Kepala Tukang Batu, Kayu, Besi, Cat Hari 200,000.00

II HARGA BAHAN
1 Tanah Timbunan (didatangkan) M3 80,000.00
2 Pasir Urug M3 180,000.00
3 Pasir Pasangan M3 200,000.00
4 Pasir Beton M3 265,000.00
Pasir Beton Kg 189.29
5 Kerikil M3 355,282.00
Krikil (Maks 30 mm) Kg 263.17
6 Batu Pecah/Suplit 1-2 cm M3 449,263.00
Batu Pecah/Suplit Kg 309.84
7 Batu Gunung M3 350,000.00
8 Air Ltr 90.00
9 Batu bata Bh 700.00
10 Paving Blok M2 120,000.00
11 Portland Cemen ( PC ) Kg 1,700.00
12 Portland Cemen ( PC ) Zak 85,000.00
13 Semen Warna Kg 28,000.00
14 Semen Nat Kg 28,000.00
15 Papan Kayu Jati M3 6,279,000.00
16 Balok Kayu Klas I M3 6,279,000.00
17 Balok Kayu Klas II M3 4,200,000.00
18 Balok Kayu Klas III M3 3,360,000.00
18 Papan Kayu Kelas I M3 6,279,000.00
19 Papan Kayu Kelas II M3 4,200,000.00
20 Kaso 5/7 Kls II M3 4,200,000.00
21 Reng 3/4 M3 4,200,000.00
20 Papan Kayu Kelas IV ( Bekesting ) M3 2,205,000.00
21 Kayu dolken diameter 8 cm btg 10,000.00
22 Lem Kayu Merk Fox Kg 20,000.00
23 List plafond kayu profil M1 5,000.00
24 List Gypsum M1 20,000.00
25 Lis kaca 1x 1 cm M1 3,500.00
26 Pintu/Jendela Aluminum M1 180,000.00
27 Profil Kaca M1 50,000.00
28 Kusen Aluminium Profil 4" M1 100,000.00
29 Profil Alumunium M1 80,000.00
30 Aluminium Strip M1 45,000.00
31 Bajar Ringan C 75 Btg 120,000.00
32 Besi Hollow t= 4.0 x 4.0 cm M1 22,000.00
33 Besi Hollow t= 4.0 x 2.0 cm M1 15,000.00
34 Besi Hollow t= 4.0 x 6.0 cm M1 36,666.67
35 Main Truss C 75 - 75 M1 19,000.00
36 Reef Botton / Reng R 33-0,45 M1 10,000.00
37 Besi Plat Baja Kg 28,000.00
38 Besi Polos Kg 25,000.00
39 Besi Ulir Kg 28,000.00
40 Baut (Srew driver) Bh 700.00
41 Selft drilling screw dia 6 x 20 mm(truss screw) Bh 500.00

65
HARGA
NO. URAIAN JENIS TENAGA / BAHAN SATUAN
('Rp.)
1 2 3 4
42 Selft drilling screw dia 4 x 16 mm (roof botton screw) Bh 500.00
43 Dynabolt 12 x 120 mm Bh 5,500.00
44 Insulasi ISOFLEX M2 50,000.00
44 Sekrup Bh 500.00
45 Sekrup Gypsum Kg 35,000.00
46 Sealant Tube 66,000.00
46 Tegel Geranit 80 x 80 Cm (motif) Bh 150,000.00
47 Tegel Geranit 60 x 60 Cm (motif) Bh 90,000.00
48 Tegel Keramik 60 x 60 Cm Anti Sliip Bh 50,000.00
49 Tegel Plint Geranit 10 x 60 Cm (motif) Bh 15,000.00
50 Tegel Keramik 50 x 50 Cm (motif) Bh 25,000.00
51 Tegel Keramik 50 x 50 Cm Anti Sliip Bh 25,000.00
52 Tegel Plint Keramik 10 x 50 Cm (motif) Bh 5,000.00
53 Tegel Keramik 40 x 40 Cm Bh 17,000.00
54 Tegel Plint Keramik 10 x 40 Cm Bh 4,250.00
55 Tegel Keramik 30 x 30 Cm Polos Bh 6,363.64
56 Tegel Plint Keramik 10 x 30 Cm (motif) Bh 6,363.64
57 Tegel Keramik 30 x 30 Cm (polos) Bh 6,363.64
58 Tegel Plint Keramik 10 x 30 Cm (polos) Bh 3,181.82
59 Tegel Keramik anti slip KM 20 x 20 Cm Bh 3,200.00
Tegel Keramik 20 x 20 Cm (Polos) Bh 2,500.00
60 Tegel Keramik Dinding 20 x 25 Cm Bh 3,200.00
61 Keramik Batu Alam M2 200,000.00
62 Nok Seng 40 CM M' 30,000.00
63 Atap Genteng Metal Soka Jempol Lbr 75,000.00
64 Atap Metal Spandek aspal Lbr 49,000.00
65 Nok Genteng Metal Soka Jempol Lbr 35,000.00
66 Baut Spandek 4,5cm Bh 1,000.00
67 Calsiboard 3 mm Lbr 70,000.00
68 Gypsum board Lbr 80,000.00
69 Wood Plank Lbr 60,000.00
70 Plywood 9 mm Lbr 80,000.00
71 Multipleks 9 mm Lbr 120,000.00
72 HPL 1 mm Lbr 285,000.00
73 Besi Beton Kg 21,000.00
74 Kawat Bindrat Kg 20,000.00
75 Kawat Las Kg 20,000.00
76 Paku Campur Kg 20,000.00
77 Paku Tripleks Kg 25,000.00
78 Paku seng Kg 25,000.00
79 Paku Genteng Metal Kg 20,000.00
80 Saklar Ganda Kg 40,000.00
81 Saklar Tunggal Bh 35,000.00
82 Stop Kontak Bh 40,000.00
83 Fitting Standar Bh 20,000.00
84 Lampu Led 11 Watt Philips Bh 50,000.00
85 Lampu Led 5 Watt Philips Bh 25,000.00
86 Lampu SL15 Watt Setara Philips Bh 40,000.00
87 Lampu SL25 Watt Setara Philips Bh 120,000.00
88 Lampu Hias Led Bh 2,300,000.00
89 Downlight 5" Bh 60,000.00
90 Kabel NYM 2 x 2,5 mm m' 10,000.00
91 Pipa Conduit m' 6,250.00
92 Fitting (elbow, male, bust) bh 20,000.00
93 Sadle/klem bh 10,000.00
94 Fisher dan skrup bh 7,000.00
95 Flexible Conduit PVC 20 mm m' 500.00
96 Tee dos bh 2,500.00
97 Mini Circuit Breaker ( MCB ) Bh 200,000.00
98 Kunci Tanam Anchor 693 LD 2 x putar pintu tunggal Bh 170,000.00
99 Kunci Tanam Anchor 693 LD 2 x putar pintu doble Bh 200,000.00
100 Kunci Pintu Kaca Bh 250,000.00
101 Rel sliding door Bh 300,000.00

66
HARGA
NO. URAIAN JENIS TENAGA / BAHAN SATUAN
('Rp.)
1 2 3 4
102 Patch Fitting Bh 500,000.00
103 Patch Lock Bh 1,000,000.00
104 Floor Hinge Bh 700,000.00
105 Engsel Pintu Type H Psg 45,000.00
106 Engsel Pintu Kaca Psg 50,000.00
107 Engsel Pintu Type Kupu Kupu Psg 45,000.00
108 Engsel Jendela Type Kupu Kupu Psg 40,000.00
109 Grendel Pintu Panjang Bh 25,000.00
110 Grendel Jendela Bh 10,000.00
111 Pegangan Pintu Steenlis Bh 600,000.00
112 Kait-kait Angin Bh 15,000.00
113 Kaca Ryben 5 mm M2 150,000.00
114 Kaca Tempered 12 mm M2 2,500,000.00
115 Fiber glass bening 3 mm M2 480,000.00
116 Spring Knip Bh 26,000.00
117 Cat Duco Kg 50,000.00
118 Cat Meny Seng/Besi Kg 25,000.00
119 Meny kayu Kg 25,000.00
120 Meny Besi Kg 25,000.00
121 Minyak cat Ltr 9,000.00
122 Minyak bekisting Ltr 12,500.00
123 Kuas Bh 20,000.00
124 Cat Dasar Kg 45,000.00
125 Cat Aviteks Kg 50,000.00
126 Cat Tembok Setara Metroligh Kg 40,000.00
127 Cat Atap / setara AGA Kg 45,000.00
128 Cat Kilap Kayu / setara glotex Kg 50,000.00
129 Cat Vernis Kayu Kg 50,000.00
130 Plamir Kayu Kg 15,000.00
131 Plamir Tembok Jadi Kg 10,000.00
132 Amplas Kayu Lbr 10,000.00
133 Dempul Kayu Kg 25,000.00
134 Lem Kayu Merk Fox Kg 18,000.00
135 Besi Beugel/baut/Angker Kuda-kuda Kg 27,000.00
136 Baut dia 12 Bh 27,000.00
115 Pipa Pvc 1/2" Wavin/Maspion M' 5,300.00
116 Pipa Pvc 3/4" Wavin/Maspion M' 7,200.00
117 Pipa Pvc 2" Wavin/Maspion M' 27,000.00
118 Pipa Pvc 3" Wavin/Maspion M' 53,000.00
119 Pipa Pvc 4" Wavin/Maspion M' 85,000.00
120 Klosed Jongkok Bh 500,000.00
121 Klosed Duduk Siram Bh 1,300,000.00
122 Bak Air Fiber Glas Bh 450,000.00
123 Wastafel Bh 1,000,000.00
124 Kran Air Bh 55,000.00
125 Floor Drain Bh 80,000.00
126 Seal Tape Bh 5,000.00
127 Pintu PVC Km/Wc Bh 920,000.00
128 Pengelasan Pipa cm 2,000.00
129 Rumput Gajah Mini M2 85,000.00
119 Kawat Duri M1 2,000.00
120 Beton Roster Bh 35,000.00
121 Jendela Boven Bh 215,000.00
122 Kaca tebal 5 mm M2 160,000.00
122 Kaca tebal 3mm M2 90,000.00

67
1,722,500.00
265,000.00
2,309,333.00
355,282.00

2,275,000.00

980,000.00

88,000.00
60,000.00

114,000.00
60,000.00

250,000.00

68
300,000.00

90,000.00

85,000.00

80,000.00

50,000.00

69
REKAPITULASI ANGGARAN BIAYA
PEKERJAAN : CARPORT
LOKASI : KOTA KENDARI
OWNER : MRS. S

JUMLAH
NO URAIAN DAN JENIS PEKERJAAN
HARGA
I. PEKERJAAN STRUKTUR 71,265,709.62
II. PEKERJAAN ARSITEKTUR 34,806,780.00
III. PEKERJAAN MEP 4,579,850.00
A REAL COST 110,652,339.62
C TOTAL Rp 110,650,000.00

Terbilang : TUJUH PULUH TIGA JUTA TIGA RATUS RIBU RUPIAH


REKAPITULASI ANGGARAN BIAYA BAHAN
PEKERJAAN : CARPORT
LOKASI : KOTA KENDARI
OWNER : MRS. S

JUMLAH
NO URAIAN DAN JENIS PEKERJAAN
HARGA
I. PEKERJAAN STRUKTUR 53,948,455.52
II. PEKERJAAN ARSITEKTUR 34,806,780.00
III. PEKERJAAN MEP 3,041,975.00
A REAL COST 91,797,210.52
C TOTAL Rp 91,750,000.00

Terbilang : ENAM PULUH LIMA JUTA DUA RATUS LIMA PULUH RIBU RUPIAH
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : CARPORT
LOKASI : KOTA KENDARI
OWNER : MRS. S

HARGA SATUAN JUMLAH HARGA


NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6
I. PEKERJAAN STRUKTUR
A. Pekerjaan Tanah dan Pondasi
1 Pek. Galian Pondasi Menerus M3 18.00 116,500.00 2,097,000.00
2 Pek. Galian Pondasi Poerplat M3 3.00 116,500.00 349,500.00
3 Pek. Urugan Tanah Kembali M3 6.00 38,800.00 232,800.00
4 Pek. Batu Kosong (Aanstamping) M3 3.60 699,000.00 2,516,400.00
5 Pek. Pondasi Batu Belah M3 10.08 1,188,100.00 11,976,048.00
6 Pek. Pasangan Sloof 15/20
- Pek. Beton Mutu K-175 M3 0.72 1,297,700.00 934,344.00
- Pek. Pembesian KG 180.07 32,666.00 5,882,173.15
- Pek. Bekisting M2 3.15 48,120.00 151,578.00
7 Pek. Pondasi Poer Plat Beton Bertulang
- Pek. Beton Mutu K-175 M3 0.13 1,297,700.00 168,701.00
- Pek. Pembesian KG 455.69 32,666.00 14,885,717.19
- Pek. Bekisting M2 1.14 48,120.00 54,856.80
- Pek. Rabat Beton Lantai tebal 5 cm M3 0.10 1,142,400.00 111,955.20
- Pek. Urugan pasir bawa pondasi M3 0.10 262,600.00 25,734.80
Jumlah 39,386,808.14
B. Pekerjaan Dinding dan Rangka Bangunan
1 Pek. Pasangan Kolom Carport 20/20
- Pek. Beton Mutu K-175 M3 1.32 1,297,700.00 1,712,964.00
- Pek. Pembesian KG 293.04 32,666.00 9,572,444.64
- Pek. Bekisting untuk 5x Pakai M2 2.93 72,800.00 213,546.67
2 Pek. Pasangan Ringbalok 15/20
- Pek. Beton Mutu K-175 M3 1.09 1,297,700.00 1,418,450.98
- Pek. Pembesian KG 133.70 32,666.00 4,367,442.00
- Pek. Bekisting untuk 5x Pakai M2 3.24 48,120.00 155,844.64
3 Pek. Pasangan Atap Beton Carport
- Pek. Beton Mutu K-175 M3 3.13 1,297,700.00 4,062,449.85
- Pek. Pembesian KG 27.14 32,666.00 886,462.69
- Pek. Bekisting untuk 5x Pakai M2 20.87 80,800.00 1,686,296.00
4 Pek. Pasangan Bata Merah Camp. 1 : 4 M2 54.00 144,500.00 7,803,000.00
Jumlah 31,878,901.47
Total Sub-Pekerjaan Struktur 71,265,709.62
HARGA SATUAN JUMLAH HARGA
NO. URAIAN DAN JENIS PEKERJAAN SAT VOLUME
(Rp) (Rp)
1 2 4 5 6

II. PEKERJAAN ARSITEKTUR


A. Pekerjaan Lantai
1 Pek. Rabat Beton tebal 5 cm M3 1.95 1,142,400.00 2,227,680.00
Jumlah 2,227,680.00
B. Pekerjaan Plesteran
1 Pek. Plesteran Dinding Camp. 1 : 5 tebal 1,5 cm M2 81.00 52,800.00 4,276,800.00
2 Pekerjaan Acian Dinding M2 81.00 57,100.00 4,625,100.00
Jumlah 8,901,900.00
C. Pekerjaan Kusen dan Aksesoris
1 Pek. Pemasangan Kusen Aluminium Skylight Carpot
1. Pembuatan dan Pemasangan Kusen Aluminium M1 66.00 126,300.00 8,335,800.00
2. Pek. Pemasangan Fiber glass 3mm M2 28.08 480,000.00 13,478,400.00
Jumlah 21,814,200.00
D. Pekerjaan Pengecetan
1 Pek. Pengecetan Tembok Baru (Cat Dasar, Cat Penutup) M2 54.00 34,500.00 1,863,000.00
Jumlah 1,863,000.00
Total Sub-Pekerjaan Arsitektur 34,806,780.00

III. PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING


A. Pekerjaan Instalasi Listrik
1 Pek. Pasangan Instalasi Penerangan TITIK 3.00 331,200.00 993,600.00
2 Pek. Pas. Lampu LED 11 Watt Setara Philips BH 3.00 199,900.00 599,700.00
Jumlah 1,593,300.00
B. Pekerjaan Jaringan Air
1 Pek. Pemasangan Pipa PVC dia. 3" M1 24.50 121,900.00 2,986,550.00
Jumlah 2,986,550.00
Total Sub-Pekerjaan Mekanikal Elektrikal Plumbing 4,579,850.00
ANALISA HARGA SATUAN

A.2.3.1. HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.2 Penggalian 1 m3 Tanah Biasa Sedalam 2 m
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
1 Pekerja L.01 OH 0.900 100,000.00 90,000.00
2 Mandor L.04 OH 0.0450 110,000.00 4,950.00
JUMLAH TENAGA KERJA 94,950.00
B BAHAN
- - -
Jumlah JUMLAH HARGA BAHAN -
C PERALATAN
- - -
Jumlah JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 94,950.00
E Overhead + Profit 15 % x D 0.15 14,242.50
F Harga Satuan Pekerjaan (D + E) 109,192.50

A.4.1.1. HARGA SATUAN PEKERJAAN BETON


A.4.1.1.9 Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 1.650 100,000.00 165,000.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 214,080.00
B BAHAN
Semen Portland Kg 384.000 1,460.00 560,640.00
Pasir Beton Kg 692.000 160.71 111,214.29
Batu Pecah/Suplit Kg 1,039.000 210.54 218,750.34
Air Ltr 215.000 70.00 15,050.00
JUMLAH HARGA BAHAN 905,654.63
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,119,734.63
E Overhead + Profit 15 % x D 0.15 167,960.19
F Harga Satuan Pekerjaan (D + E) 1,287,694.82

A.4.1.1.9 1m3 Pembuatan Beton Mutu fc 14,5 Mpa (K175), slump (12±2) cm, w/c= 0,66
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 1.650 100,000.00 165,000.00
Tukang Batu L.02 OH 0.275 130,000.00 35,750.00
Kepala Tukang L.03 OH 0.028 150,000.00 4,200.00
Mandor L.04 OH 0.083 110,000.00 9,130.00
JUMLAH TENAGA KERJA 214,080.00
B BAHAN
Semen Portland Kg 326.000 1,460.00 475,960.00
Pasir Beton Kg 760.000 160.71 122,142.86
Batu Pecah/Suplit Kg 1,029.000 210.54 216,644.95
Air Liter 215.000 70.00 15,050.00
JUMLAH HARGA BAHAN 829,797.81
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 1,043,877.81
E Overhead + Profit 15 % x D 0.15 156,581.67
F Harga Satuan Pekerjaan (D + E) 1,200,459.48

74
A.4.1.1.9 Pemasangan 1 BH Buis Beton Dia. Luar 80 cm, Tbl. 6 cm, Tinggi 60 cm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.250 100,000.00 25,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.010 150,000.00 1,500.00
Mandor L.04 OH 0.005 110,000.00 550.00
JUMLAH TENAGA KERJA 46,550.00
B BAHAN
Beton Mutu 1 K175 M3 0.080 1,043,877.81 83,510.22
JUMLAH HARGA BAHAN 83,510.22
C PERALATAN
Sewa Mal. Pracetak Ls 1.0000 20,000.00 20,000.00
JUMLAH HARGA ALAT 20,000.00
D Jumlah (A+B+C) 150,060.22
E Overhead + Profit 15 % x D 0.15 22,509.03
F Harga Satuan Pekerjaan (D + E) 172,569.26

A.4.1.1.17 Pembesian 1 Kg dengan besi polos atau besi ulir


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.007 100,000.00 700.00
Tukang Besi L.02 OH 0.007 130,000.00 910.00
Kepala Tukang L.03 OH 0.001 150,000.00 105.00
Mandor L.04 OH 0.000 110,000.00 44.00
JUMLAH TENAGA KERJA 1,759.00
B BAHAN
Besi Beton (polos/ulir) Kg 1.050 15,000.00 15,750.00
Kawat Beton Kg 0.015 26,000.00 390.00
JUMLAH HARGA BAHAN 16,140.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 17,899.00
E Overhead + Profit 15 % x D 0.15 2,684.85
F Harga Satuan Pekerjaan (D + E) 20,583.85

A.4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi (2x Pakai)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
1 Pekerja L.01 OH 0.520 100,000.00 52,000.00
Tukang Kayu L.02 OH 0.260 130,000.00 33,800.00
Kepala Tukang L.03 OH 0.026 150,000.00 3,900.00
2 Mandor L.04 OH 0.026 110,000.00 2,860.00
JUMLAH TENAGA KERJA 92,560.00
B BAHAN
Kayu Kelas III M3 0.020 1,600,000.00 32,000.00
Paku 5-10cm Kg 0.300 18,000.00 5,400.00
Minyak Bekisting Ltr 0.100 9,000.00 900.00
JUMLAH HARGA BAHAN 38,300.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 130,860.00
E Overhead + Profit 15 % x D 0.15 19,629.00
F Harga Satuan Pekerjaan (D + E) 150,489.00

75
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk Balok (2x Pakai)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.330 100,000.00 33,000.00
Tukang Kayu L.02 OH 0.165 130,000.00 21,450.00
Kepala Tukang L.03 OH 0.017 150,000.00 2,475.00
Mandor L.04 OH 0.017 110,000.00 1,815.00
JUMLAH TENAGA KERJA 58,740.00
B BAHAN
Kayu Papan kelas III (Bekisting) m³ 0.020 1,600,000.00 32,000.00
Paku 5 cm - 12 cm Kg 0.200 18,000.00 3,600.00
Minyak bekisting Liter 0.100 9,000.00 900.00
Balok Kayu kelas III (Bekisting) m³ 0.009 1,600,000.00 14,400.00
Multipleks tebal 9 mm Lbr 0.175 120,000.00 21,000.00
Dolken kayu .. 8-10) cm- panj 4 m Batang 1.000 9,000.00 9,000.00
JUMLAH HARGA BAHAN 80,900.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 139,640.00
E Overhead + Profit 15 % x D 0.15 20,946.00
F Harga Satuan Pekerjaan (D + E) 160,586.00

A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom (3x Pakai)


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.660 100,000.00 66,000.00
Tukang Kayu L.02 OH 0.330 130,000.00 42,900.00
Kepala Tukang L.03 OH 0.033 150,000.00 4,950.00
Mandor L.04 OH 0.033 110,000.00 3,630.00
JUMLAH TENAGA KERJA 117,480.00
B BAHAN
Kayu Kelas III M3 0.013 1,600,000.00 21,333.33
Paku 5-10cm Kg 0.400 18,000.00 7,200.00
Minyak Bekisting Ltr 0.200 9,000.00 1,800.00
Balok Kayu Kelas II M3 0.005 2,600,000.00 13,000.00
Tripleks 6mm Lbr 0.117 85,000.00 9,916.67
Dolken Kayu Ø8-10cm panjang 4m Btng 0.667 9,000.00 6,000.00
JUMLAH HARGA BAHAN 59,250.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 176,730.00
E Overhead + Profit 15 % x D 0.15 26,509.50
F Harga Satuan Pekerjaan (D + E) 203,239.50

A.4.4.2. HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.2 Pemasangan 1 m2 plesteran 1SP:2PP tebal 15mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.300 100,000.00 30,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 53,400.00
B BAHAN
Semen Portland Kg 10.224 1,460.00 14,927.04
Pasir pasang M3 0.020 225,000.00 4,500.00
JUMLAH HARGA BAHAN 19,427.04
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 72,827.04
E Overhead + Profit 15 % x D 0.15 10,924.06
F Harga Satuan Pekerjaan (D + E) 83,751.10

76
A.4.4.2.3 Pemasangan 1 m2 plesteran 1SP:3PP tebal 15mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.300 100,000.00 30,000.00
Tukang Batu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.015 110,000.00 1,650.00
JUMLAH TENAGA KERJA 53,400.00
B BAHAN
Semen Portland Kg 7.776 1,460.00 11,352.96
Pasir pasang M3 0.023 225,000.00 5,175.00
JUMLAH HARGA BAHAN 16,527.96
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 69,927.96
E Overhead + Profit 15 % x D 0.15 10,489.19
F Harga Satuan Pekerjaan (D + E) 80,417.15

A.4.5.2. HARGA SATUAN PEKERJAAN PENUTUP ATAP


Anl Pemasangan 1 m2 Atap Spandek
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.120 100,000.00 12,000.00
Tukang L.02 OH 0.060 130,000.00 7,800.00
Kepala Tukang L.03 OH 0.006 150,000.00 900.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 21,360.00
B BAHAN
Spandek dan Sejenis T.0,3 mm M1 1.250 45,000.00 56,250.00
Paku Payung/Seng Kg 0.020 25,000.00 500.00
JUMLAH HARGA BAHAN 56,750.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 78,110.00
E Overhead + Profit 15 % x D 0.15 11,716.50
F Harga Satuan Pekerjaan (D + E) 89,826.50

Anl Pemasangan 1 M' Nok Atap Spandek


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.150 100,000.00 15,000.00
Tukang L.02 OH 0.070 130,000.00 9,100.00
Kepala Tukang L.03 OH 0.007 150,000.00 1,050.00
Mandor L.04 OH 0.006 110,000.00 660.00
JUMLAH TENAGA KERJA 25,810.00
B BAHAN
Nok Spandek Lbr 1.000 30,000.00 30,000.00
Papan Kayu Klas II M3 0.007 2,600,000.00 18,055.56
Paku Payung/Seng Kg 0.050 25,000.00 1,250.00
JUMLAH HARGA BAHAN 49,305.56
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 75,115.56
E Overhead + Profit 15 % x D 0.15 11,267.33
F Harga Satuan Pekerjaan (D + E) 86,382.89

77
A.4.6.1. HARGA SATUAN PEKERJAAN KAYU
A.4.6.1.13 Pemasangan 1 m3 konstruksi kuda-kuda expose, kayu kelas II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 6.7000 100,000.00 670,000.00
Tukang kayu L.02 OH 20.1000 130,000.00 2,613,000.00
Kepala Tukang L.03 OH 2.0100 150,000.00 301,500.00
Mandor L.04 OH 0.3350 110,000.00 36,850.00
JUMLAH TENAGA KERJA 3,621,350.00
B BAHAN
Kayu Kls.II M3 1.2000 2,600,000.00 3,120,000.00
Besi Strip tebal 5mm Kg 15.0000 20,000.00 300,000.00
Paku 12 cm Kg 5.6000 18,000.00 100,800.00
JUMLAH HARGA BAHAN 3,520,800.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 7,142,150.00
E Overhead + Profit 15 % x D 0.15 1,071,322.50
F Harga Satuan Pekerjaan (D + E) 8,213,472.50

A.4.6.1.15 Pemasangan 1 m3 konstruksi gordeng kayu kelas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 6.7000 100,000.00 670,000.00
Tukang kayu L.02 OH 20.1000 130,000.00 2,613,000.00
Kepala Tukang L.03 OH 2.0100 150,000.00 301,500.00
Mandor L.04 OH 0.3350 110,000.00 36,850.00
JUMLAH TENAGA KERJA 3,621,350.00
B BAHAN
Kayu Kls.II M3 1.1000 2,600,000.00 2,860,000.00
Besi Strip tebal 5mm Kg 15.0000 20,000.00 300,000.00
Paku 12 cm Kg 3.0000 18,000.00 54,000.00
JUMLAH HARGA BAHAN 3,214,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 6,835,350.00
E Overhead + Profit 15 % x D 0.15 1,025,302.50
F Harga Satuan Pekerjaan (D + E) 7,860,652.50

A.4.6.1.21 Pemasangan 1 m1 listplank ukuran (3x20) cm, kayu kelas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang kayu L.02 OH 0.2000 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.0200 150,000.00 3,000.00
Mandor L.04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 39,550.00
B BAHAN
Papan kayu M3 0.0108 2,600,000.00 28,080.00
Paku 5 dan 10 cm Kg 0.1000 18,000.00 1,800.00
JUMLAH HARGA BAHAN 29,880.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 69,430.00
E Overhead + Profit 15 % x D 0.15 10,414.50
F Harga Satuan Pekerjaan (D + E) 79,844.50

78
A.4.6.1.22 Pemasangan 1 m’ lisplank ukuran (1 x 20) cm, Wood plank
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang kayu L.02 OH 0.2000 130,000.00 26,000.00
Kepala Tukang L.03 OH 0.0200 150,000.00 3,000.00
Mandor L.04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 39,550.00
B BAHAN
Wood Plank Lbr 0.2500 60,000.00 15,000.00
Skrup Bh 26.0000 500.00 13,000.00
JUMLAH HARGA BAHAN 28,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 67,550.00
E Overhead + Profit 15 % x D 0.15 10,132.50
F Harga Satuan Pekerjaan (D + E) 77,682.50

A.4.6.1.13B Pemasangan 1 m2 lantai papan 3x20 kayu kelas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.0800 100,000.00 8,000.00
Tukang kayu L.02 OH 0.0500 130,000.00 6,500.00
Kepala Tukang L.03 OH 0.0050 150,000.00 750.00
Mandor L.04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 15,800.00
B BAHAN
Papan kayu Klas II M3 0.0240 2,600,000.00 62,400.00
Paku 5 dan 10 cm Kg 0.0120 18,000.00 216.00
JUMLAH HARGA BAHAN 62,616.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 78,416.00
E Overhead + Profit 15 % x D 0.15 11,762.40
F Harga Satuan Pekerjaan (D + E) 90,178.40

A.4.6.1.13B Pemasangan 1 m2 Papan 3x20 kayu kelas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.1000 100,000.00 10,000.00
Tukang kayu L.02 OH 0.0500 130,000.00 6,500.00
Kepala Tukang L.03 OH 0.0050 150,000.00 750.00
Mandor L.04 OH 0.0050 110,000.00 550.00
JUMLAH TENAGA KERJA 17,800.00
B BAHAN
Papan kayu Klas II M3 0.0240 2,600,000.00 62,400.00
Paku 5 dan 10 cm Kg 0.0120 18,000.00 216.00
JUMLAH HARGA BAHAN 62,616.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 80,416.00
E Overhead + Profit 15 % x D 0.15 12,062.40
F Harga Satuan Pekerjaan (D + E) 92,478.40

79
A.4.6.1.13B Pemasangan 1 m3 Balok Expose kayu kelas II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 2.5000 100,000.00 250,000.00
Tukang kayu L.02 OH 8.0000 130,000.00 1,040,000.00
Kepala Tukang L.03 OH 1.0000 150,000.00 150,000.00
Mandor L.04 OH 0.2000 110,000.00 22,000.00
JUMLAH TENAGA KERJA 1,462,000.00
B BAHAN
Balok kayu Klas II M3 1.1000 2,600,000.00 2,860,000.00
Paku 5 dan 10 cm Kg 2.8000 18,000.00 50,400.00
JUMLAH HARGA BAHAN 2,910,400.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,372,400.00
E Overhead + Profit 15 % x D 0.15 655,860.00
F Harga Satuan Pekerjaan (D + E) 5,028,260.00

A.4.6.1.13B Membuat 1 m2 Pekerjaan Pagar Kayu Klas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.2000 100,000.00 20,000.00
Tukang kayu L.02 OH 0.7500 130,000.00 97,500.00
Kepala Tukang L.03 OH 0.0750 150,000.00 11,250.00
Mandor L.04 OH 0.0200 110,000.00 2,200.00
JUMLAH TENAGA KERJA 130,950.00
B BAHAN
Balok kayu Klas II M3 0.0120 2,600,000.00 31,200.00
Paku 5 dan 10 cm Kg 0.0100 18,000.00 180.00
JUMLAH HARGA BAHAN 31,380.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 162,330.00
E Overhead + Profit 15 % x D 0.15 24,349.50
F Harga Satuan Pekerjaan (D + E) 186,679.50

A.4.6.1.13B Membuat 1 m3 Tiang Sandaran Kayu Klas II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 5.0000 100,000.00 500,000.00
Tukang kayu L.02 OH 7.5000 130,000.00 975,000.00
Kepala Tukang L.03 OH 0.7500 150,000.00 112,500.00
Mandor L.04 OH 0.2500 110,000.00 27,500.00
JUMLAH TENAGA KERJA 1,615,000.00
B BAHAN
Balok kayu Klas II M3 1.1000 2,600,000.00 2,860,000.00
Paku 5 dan 10 cm Kg 0.4000 18,000.00 7,200.00
JUMLAH HARGA BAHAN 2,867,200.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 4,482,200.00
E Overhead + Profit 15 % x D 0.15 672,330.00
F Harga Satuan Pekerjaan (D + E) 5,154,530.00

80
A.4.6.1.13B 1 M3 PEK. KUSEN PINTU/JENDELA KAYU KLAS II
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 6.0000 100,000.00 600,000.00
Tukang kayu L.02 OH 18.0000 130,000.00 2,340,000.00
Kepala Tukang L.03 OH 2.0000 150,000.00 300,000.00
Mandor L.04 OH 0.3000 110,000.00 33,000.00
JUMLAH TENAGA KERJA 3,273,000.00
B BAHAN
Balok kayu Klas II M3 1.2000 2,600,000.00 3,120,000.00
JUMLAH HARGA BAHAN 3,120,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 6,393,000.00
E Overhead + Profit 15 % x D 0.15 958,950.00
F Harga Satuan Pekerjaan (D + E) 7,351,950.00

A.4.6.1.13B 1 M2 PEK. PASANG BINGKAI JENDELA KACA KAYU KLAS II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.8000 100,000.00 80,000.00
Tukang kayu L.02 OH 2.0000 130,000.00 260,000.00
Kepala Tukang L.03 OH 0.2000 150,000.00 30,000.00
Mandor L.04 OH 0.0400 110,000.00 4,400.00
JUMLAH TENAGA KERJA 374,400.00
B BAHAN
Papan Kayu Klas II M3 0.0350 2,600,000.00 91,000.00
JUMLAH HARGA BAHAN 91,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 465,400.00
E Overhead + Profit 15 % x D 0.15 69,810.00
F Harga Satuan Pekerjaan (D + E) 535,210.00

A.4.6.1.13B 1 M2 PEK. PASANG PINTU PANIL KAYU KLAS II


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 1.0000 100,000.00 100,000.00
Tukang kayu L.02 OH 3.0000 130,000.00 390,000.00
Kepala Tukang L.03 OH 0.3000 150,000.00 45,000.00
Mandor L.04 OH 0.0500 110,000.00 5,500.00
JUMLAH TENAGA KERJA 540,500.00
B BAHAN
Papan Kayu Klas II M3 0.0350 2,600,000.00 91,000.00
Lem Kayu Kg 0.5000 20,000.00 10,000.00
JUMLAH HARGA BAHAN 101,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 641,500.00
E Overhead + Profit 15 % x D 0.15 96,225.00
F Harga Satuan Pekerjaan (D + E) 737,725.00

81
A.4.6.1.13B 1 M2 PEK. PAS. KACA Bening 5 mm
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.0150 100,000.00 1,500.00
Tukang kayu L.02 OH 0.1500 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.0150 150,000.00 2,250.00
Mandor L.04 OH 0.0008 110,000.00 82.50
JUMLAH TENAGA KERJA 23,332.50
B BAHAN
Kaca Bening M3 1.1000 150,000.00 165,000.00
JUMLAH HARGA BAHAN 165,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 188,332.50
E Overhead + Profit 15 % x D 0.15 28,249.88
F Harga Satuan Pekerjaan (D + E) 216,582.38

A.4.6.2. HARGA SATUAN PEKERJAAN PENGGANTUNG DAN PENGUNCI


A.4.6.2.5 Pemasangan 1 buah engsel pintu
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.015 100,000.00 1,500.00
Tukang kayu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 23,338.00
B BAHAN
Engsel pintu Bh 1.000 20,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 43,338.00
E Overhead + Profit 15 % x D 0.15 6,500.70
F Harga Satuan Pekerjaan (D + E) 49,838.70

A.4.6.2.5.a Pemasangan 1 buah grendel pintu


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.015 100,000.00 1,500.00
Tukang kayu L.02 OH 0.150 130,000.00 19,500.00
Kepala Tukang L.03 OH 0.015 150,000.00 2,250.00
Mandor L.04 OH 0.001 110,000.00 88.00
JUMLAH TENAGA KERJA 23,338.00
B BAHAN
Grendel pintu Bh 1.000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 15,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 38,338.00
E Overhead + Profit 15 % x D 0.15 5,750.70
F Harga Satuan Pekerjaan (D + E) 44,088.70

82
A.4.7.1. HARGA SATUAN PEKERJAAN PENGECETAN
A.4.7.1.4 Pengecetan 1 m2 Pengecetan Bidang Kayu Baru
( 1 Lapis Plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.020 100,000.00 2,000.00
Tukang cat L.02 OH 0.063 130,000.00 8,190.00
Kepala Tukang L.03 OH 0.006 150,000.00 945.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 11,465.00
B BAHAN
Cat meni kayu Kg 0.200 25,000.00 5,000.00
Plamur Kayu Kg 0.150 19,200.00 2,880.00
Cat Dasar Kg 0.170 30,000.00 5,100.00
Cat Penutup Kg 0.260 30,000.00 7,800.00
Kuas 3'' Bh 0.010 15,000.00 150.00
Pengencer Kg 0.030 25,000.00 750.00
Amplas Lbr 0.200 10,000.00 2,000.00
JUMLAH HARGA BAHAN 23,680.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 35,145.00
E Overhead + Profit 15 % x D 0.15 5,271.75
F Harga Satuan Pekerjaan (D + E) 40,416.75

A.4.7.1.9 Pelaburan 1 M2 bidang kayu baru dengan vernis


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.1600 100,000.00 16,000.00
Tukang cat L.02 OH 0.1600 130,000.00 20,800.00
Kepala Tukang L.03 OH 0.0160 150,000.00 2,400.00
Mandor L.04 OH 0.0030 110,000.00 330.00
JUMLAH TENAGA KERJA 39,530.00
B BAHAN
Vernis Ltr 0.1500 20,000.00 3,000.00
Dempul Kg 0.0050 20,000.00 100.00
Amplas Lbr 0.1000 10,000.00 1,000.00
JUMLAH HARGA BAHAN 4,100.00
C PERALATAN
Kuas Rol Bh 0.010 25,000.0000 250.00
JUMLAH HARGA ALAT 250.00
D Jumlah (A+B+C) 43,880.00
E Overhead + Profit 15 % x D 0.15 6,582.00
F Harga Satuan Pekerjaan (D + E) 50,462.00

A.4.7.1.10 Pengecetan 1 m2 tembok baru ( 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.020 100,000.00 2,000.00
Tukang cat L.02 OH 0.063 130,000.00 8,190.00
Kepala Tukang L.03 OH 0.006 150,000.00 945.00
Mandor L.04 OH 0.003 110,000.00 330.00
JUMLAH TENAGA KERJA 11,465.00
B BAHAN
Plamur Tembok Kg 0.100 15,000.00 1,500.00
Cat tembok dasar Kg 0.100 15,000.00 1,500.00
Cat tembok penutup Kg 0.260 15,000.00 3,900.00
JUMLAH HARGA BAHAN 6,900.00
C PERALATAN
Kuas Rol Bh 0.010 15,000.0000 150.00
JUMLAH HARGA ALAT 150.00
D Jumlah (A+B+C) 18,515.00
E Overhead + Profit 15 % x D 0.15 2,777.25
F Harga Satuan Pekerjaan (D + E) 21,292.25

83
A.5.1.1. HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG
A.8.4.1.11 Pemasangan 1 m1 pipa PVC tipe AW diameter 6"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.081 100,000.00 8,100.00
Tukang pipa L.02 OH 0.130 130,000.00 16,900.00
Kepala Tukang L.03 OH 0.014 150,000.00 2,025.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 27,465.00
B BAHAN
Pipa PVC diameter 6" M1 1.000 137,500.00 137,500.00
Perlengkapan % - 0.00 -
JUMLAH HARGA BAHAN 137,500.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 164,965.00
E Overhead + Profit 15 % x D 0.15 24,744.75
F Harga Satuan Pekerjaan (D + E) 189,709.75

A.8.4.1.11 Pemasangan 1 m1 pipa PVC tipe AW diameter 8"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.081 100,000.00 8,100.00
Tukang pipa L.02 OH 0.130 130,000.00 16,900.00
Kepala Tukang L.03 OH 0.014 150,000.00 2,025.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 27,465.00
B BAHAN
Pipa PVC diameter 8" M1 1.000 200,000.00 200,000.00
Perlengkapan % - 0.00 -
JUMLAH HARGA BAHAN 200,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 227,465.00
E Overhead + Profit 15 % x D 0.15 34,119.75
F Harga Satuan Pekerjaan (D + E) 261,584.75

A.8.4.1.11 Pemasangan 1 m1 pipa PVC tipe AW diameter 10"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.081 100,000.00 8,100.00
Tukang pipa L.02 OH 0.130 130,000.00 16,900.00
Kepala Tukang L.03 OH 0.014 150,000.00 2,025.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 27,465.00
B BAHAN
Pipa PVC diameter 10" M1 1.000 300,000.00 300,000.00
Perlengkapan % - 0.00 -
JUMLAH HARGA BAHAN 300,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 327,465.00
E Overhead + Profit 15 % x D 0.15 49,119.75
F Harga Satuan Pekerjaan (D + E) 376,584.75

84
A.8.4.1.11 Pemasangan 1 m1 pipa PVC tipe AW diameter 4"
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.081 100,000.00 8,100.00
Tukang pipa L.02 OH 0.130 130,000.00 16,900.00
Kepala Tukang L.03 OH 0.014 150,000.00 2,025.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 27,465.00
B BAHAN
Pipa PVC diameter 4" M1 1.000 62,500.00 62,500.00
Perlengkapan % - 0.00 -
JUMLAH HARGA BAHAN 62,500.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 89,965.00
E Overhead + Profit 15 % x D 0.15 13,494.75
F Harga Satuan Pekerjaan (D + E) 103,459.75

A.8.4.1.11 Pemasangan 1 m1 pipa PVC tipe AW diameter 3"


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.081 100,000.00 8,100.00
Tukang pipa L.02 OH 0.130 130,000.00 16,900.00
Kepala Tukang L.03 OH 0.014 150,000.00 2,025.00
Mandor L.04 OH 0.004 110,000.00 440.00
JUMLAH TENAGA KERJA 27,465.00
B BAHAN
Pipa PVC diameter 3" M1 1.000 45,000.00 45,000.00
Perlengkapan % - 0.00 -
JUMLAH HARGA BAHAN 45,000.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 72,465.00
E Overhead + Profit 15 % x D 0.15 10,869.75
F Harga Satuan Pekerjaan (D + E) 83,334.75

A.4.6.2. HARGA SATUAN PEKERJAAN KUDA KUDA BAJA RINGAN


A.4.6.1.13 1 m2 Pek. Kuda-Kuda Rangka Atap Baja Ringan
Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.3000 100,000.00 30,000.00
Tukang Baja Ringan L.02 OH 0.1000 130,000.00 13,000.00
Kepala Tukang L.03 OH 0.0100 150,000.00 1,500.00
Mandor L.04 OH 0.0150 110,000.00 1,650.00
JUMLAH TENAGA KERJA 46,150.00
B BAHAN
Main Trus C 75 - 75 m' 2.8000 15,000.00 42,000.00
Reef Botton / Reng R 33-0,45 m' 4.6000 7,000.00 32,200.00
Self drilling Screw dia 6 x 20 mm (Truss Screw) bh 17.0000 500.00 8,500.00
Self drilling Screw dia 4 x 16 mm (Roof Bottom Screw) bh 24.0000 500.00 12,000.00
Dynabolt 12 x 120 mm bh 1.0000 3,000.00 3,000.00
Alat bantu ls 0.0350 1,000.00 35.00
JUMLAH HARGA BAHAN 97,735.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 143,885.00
E Overhead + Profit 15 % x D 0.15 21,582.75
F Harga Satuan Pekerjaan (D + E) 165,467.75

A.4.6.1.13 Membuat 1 M2 Pagar Reling Baja Ringan


Harga Satuan Jumlah Harga
No. Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA KERJA
Pekerja L.01 OH 0.1080 100,000.00 10,800.00
Tukang Baja Ringan L.02 OH 0.1800 130,000.00 23,400.00
Kepala Tukang L.03 OH 0.0180 150,000.00 2,700.00
Mandor L.04 OH 0.0540 110,000.00 5,940.00
JUMLAH TENAGA KERJA 42,840.00
B BAHAN
Main Trus C 75 - 75 m' 4.6000 15,000.00 69,000.00
Self drilling Screw dia 6 x 20 mm (Truss Screw) m' 17.0000 500.00 8,500.00
Dynabolt 12 x 120 mm bh 1.0000 3,000.00 3,000.00
Alat bantu bh 0.0350 1,000.00 35.00
JUMLAH HARGA BAHAN 80,535.00
C PERALATAN
- - -
JUMLAH HARGA ALAT -

85
D Jumlah (A+B+C) 123,375.00
E Overhead + Profit 15 % x D 0.15 18,506.25
F Harga Satuan Pekerjaan (D + E) 141,881.25

86
ANALISIS HARGA SATUAN PEKERJAAN BERDASARKAN
(PERMEN PUPR NOMOR 1 TAHUN 2022)

I. PEKERJAAN TANAH
1 1.7.1.a. Penggalian 1 m3 Tanah Biasa Sedalam s.d 1 m Untuk Volume s.d 200 m3 Dalam Satu Lokasi
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.750 112,500.00
2 Mandor Org/Hari 160,000.00 0.025 4,000.00
Jumlah A 116,500.00
B BAHAN

Jumlah B -
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 116,500.00
E Overhead 10% 11,650.00
F Harga Satuan D + E 128,100.00

2 1.7.2.a Pengurugan Kembali 1 m3 Galian Tanah


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2500 37,500.00
2 Mandor Org/Hari 160,000.00 0.0083 1,333.33
Jumlah A 38,833.33
B BAHAN

Jumlah B
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 38,833.33
E Overhead 10% 3,883.33
F Harga Satuan D + E 42,700.00

87
3 1.7.2.d Pengurugan 1 m3 dengan Pasir Urug
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.3000 45,000.00
2 Mandor Org/Hari 160,000.00 0.0100 1,600.00
Jumlah A 46,600.00
B BAHAN
1 Pasir Urug M3 180,000.00 1.2000 216,000.00
Jumlah B 216,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 262,600.00
E Overhead 10% 26,260.00
F Harga Satuan D + E 288,800.00

4 1.7.2.e Pengurugan dan Pemadatan 1 m3 Sirtu


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.2500 37,500.00
2 Mandor Org/Hari 160,000.00 0.0250 4,000.00
Jumlah A 41,500.00
B BAHAN
1 Sirtu M3 80,000.00 1.2000 96,000.00
Jumlah B 96,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 137,500.00
E Overhead 10% 13,750.00
F Harga Satuan D + E 151,200.00

II. PEKERJAAN PONDASI


1 2.1.1.b Memasang 1 m3 Pondasi Batu Belah Tipe N (5,2 Mpa)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.5000 225,000.00
2 Tukang Batu Org/Hari 180,000.00 0.7500 135,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.0750 15,000.00
4 Mandor Org/Hari 160,000.00 0.0750 12,000.00
Jumlah A 387,000.00
B BAHAN
1 Batu Gunung M3 320,000.00 1.20 384,000.00
2 Semen Portland Kg 1,550.00 163.00 252,650.00
3 Pasir Pasang M3 130,000.00 0.520 67,600.00
Jumlah B 704,250.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,091,250.00
E Overhead 10% 109,125.00
F Harga Satuan D + E 1,200,300.00

88
2 1.5.1.1.b.(a) Pemasangan 1 m3 batu kosong (anstamping)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.780 117,000.00
2 Tukang Batu Org/Hari 180,000.00 0.390 70,200.00
3 Kepala Tukang Org/Hari 200,000.00 0.039 7,800.00
4 Mandor Org/Hari 160,000.00 0.039 6,240.00
Jumlah A 201,240.00
B BAHAN
1 Batu belah 15 cm/20 cm M3 350,000.00 1.20 420,000.00
2 Pasir Urug M3 180,000.00 0.432 77,760.00
Jumlah B 497,760.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 699,000.00
E Overhead 10% 69,900.00
F Harga Satuan D + E 768,900.00

III. PEKERJAAN DINDING


1 4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 PC : 3 PP
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 120,000.00 0.1000 12,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.0100 1,400.00
3 Pekerja Org/Hari 90,000.00 0.3000 27,000.00
4 Mandor Org/Hari 120,000.00 0.0150 1,800.00
Jumlah A 42,200.00
B BAHAN
1 Batu bata Biji 500.00 70.00 35,000.00
2 Semen Kg 1,550.00 14.37 22,273.50
3 Pasir Pasang M3 130,000.00 0.04 5,200.00
Jumlah B 62,473.50
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 104,673.50
E Overhead 10% 10,467.35
F Harga Satuan D + E 115,100.00

89
2 4.4.1.10 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1 PC : 5 PP
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 120,000.00 0.1000 12,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.0100 1,400.00
3 Pekerja Org/Hari 90,000.00 0.3000 27,000.00
4 Mandor Org/Hari 120,000.00 0.0150 1,800.00
Jumlah A 42,200.00
B BAHAN
1 Batu bata Biji 500.00 70.000 35,000.00
2 Semen Kg 1,550.00 9.680 15,004.00
3 Pasir Pasang M3 130,000.00 0.045 5,850.00
Jumlah B 55,854.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 98,054.00
E Overhead 10% 9,805.40
F Harga Satuan D + E 107,800.00

3 4.4.1.9 Pemasangan 1 m2 dinding conblock HB15 campuran 1 PC : 4 PP


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.3200 28,800.00
2 Tukang Batu Org/Hari 120,000.00 0.1200 14,400.00
3 Kepala Tukang Org/Hari 140,000.00 0.0120 1,680.00
4 Mandor Org/Hari 120,000.00 0.0160 1,920.00
Jumlah A 46,800.00
B BAHAN
1 Batako HB-15 Bh 3,000.00 12.500 37,500.00
2 Semen Kg 1,550.00 18.200 28,210.00
3 Pasir Pasang M3 130,000.00 0.0582 7,566.00
4 Besi Angker dia. 8 Kg 13,500.00 0.280 3,780.00
Jumlah B 73,276.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 120,076.00
E Overhead 10% 12,007.60
F Harga Satuan D + E 132,000.00

90
IV PEKERJAAN PLESTERAN
1 Anl. Pemasangan plesteran 1 m' tali air
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 120,000.00 0.0800 9,600.00
2 Kepala Tukang Org/Hari 140,000.00 0.0040 560.00
3 Pekerja Org/Hari 90,000.00 0.0080 720.00
4 Mandor Org/Hari 120,000.00 0.0040 480.00
Jumlah A 11,360.00
B BAHAN
1 Semen Kg 1,550.00 0.2500 387.50
2 Pasir Pasang M3 130,000.00 0.0080 1,040.00
Jumlah B 1,427.50
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 12,787.50
E Overhead 10% 1,278.75
F Harga Satuan D + E 14,000.00

2 4.4.2.5 Pemasangan 1 m2 plesteran 1 PC : 5 PP tebal 15 mm


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 120,000.00 0.1500 18,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.0150 2,100.00
3 Pekerja Org/Hari 90,000.00 0.3000 27,000.00
4 Mandor Org/Hari 120,000.00 0.0150 1,800.00
Jumlah A 48,900.00
B BAHAN
1 Semen Kg 1,550.00 5.184 8,035.20
2 Pasir Pasang M3 130,000.00 0.026 3,380.00
Jumlah B 11,415.20
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 60,315.20
E Overhead 10% 6,031.52
F Harga Satuan D + E 66,300.00

91
3 4.4.2.27 Pemasangan 1 m2 acian
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 120,000.00 0.2000 24,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.1000 14,000.00
3 Pekerja Org/Hari 90,000.00 0.0100 900.00
4 Mandor Org/Hari 120,000.00 0.0100 1,200.00
Jumlah A 40,100.00
B BAHAN
1 Semen Kg 1,550.00 3.250 5,037.50
Jumlah B 5,037.50
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 45,137.50
E Overhead 10% 4,513.75
F Harga Satuan D + E 49,600.00

V PEKERJAAN KAYU
1 4.6.1.2 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II atau III
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 120,000.00 18.00 2,160,000.00
2 Kepala Tukang Org/Hari 140,000.00 1.80 252,000.00
3 Pekerja Org/Hari 90,000.00 6.00 540,000.00
4 Mandor Org/Hari 120,000.00 0.30 36,000.00
Jumlah A 2,988,000.00
B BAHAN
1 Kayu Klas II M3 4,200,000.00 1.2000 5,040,000.00
2 Paku 10 cm Kg 15,500.00 1.2500 19,375.00
3 Lem kayu Kg 91,400.00 1.0000 91,400.00
Jumlah B 5,150,775.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 8,138,775.00
E Overhead 10% 813,877.50
F Harga Satuan D + E 8,952,652.50

92
2 4.6.1.5 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I atau II
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 120,000.00 3.0000 360,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.3000 42,000.00
3 Pekerja Org/Hari 90,000.00 1.0000 90,000.00
4 Mandor Org/Hari 120,000.00 0.0500 6,000.00
Jumlah A 498,000.00
B BAHAN
1 Kayu Papan Kelas II M3 4,200,000.00 0.0400 168,000.00
2 Lem Kayu Kg 91,400.00 0.5000 45,700.00
Jumlah B 213,700.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 711,700.00
E Overhead 10% 71,170.00
F Harga Satuan D + E 782,870.00

3 4.6.1.6 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I atau II
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 120,000.00 2.4000 288,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.2400 33,600.00
3 Pekerja Org/Hari 90,000.00 0.8000 72,000.00
4 Mandor Org/Hari 120,000.00 0.0400 4,800.00
Jumlah A 398,400.00
B BAHAN
1 Kayu Papan Kelas II M3 4,200,000.00 0.0240 100,800.00
2 Lem Kayu Kg 91,400.00 0.3000 27,420.00
Jumlah B 128,220.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 526,620.00
E Overhead 10% 52,662.00
F Harga Satuan D + E 579,282.00

4 4.6.1.21 Pemasangan 1 m' lisplank ukuran (3 x 20) cm, kayu kelas I atau kelas II
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 120,000.00 0.2000 24,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.0250 3,500.00
3 Pekerja Org/Hari 90,000.00 0.1000 9,000.00
4 Mandor Org/Hari 120,000.00 0.0050 600.00
Jumlah A 37,100.00
B BAHAN
1 Kayu Papan Klas II M3 4,200,000.00 0.0108 45,360.00
2 Paku campur Kg 15,500.00 0.100 1,550.00
Jumlah B 46,910.00
C PERALATAN

93
Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 84,010.00
E Overhead 10% 8,401.00
F Harga Satuan D + E 92,411.00

94
VI PEKERJAAN LANGIT-LANGIT (PLAFOND)
1 4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.1000 9,000.00
2 Tukang Kayu Org/Hari 120,000.00 0.0500 6,000.00
3 Kepala Tukang Org/Hari 140,000.00 0.0050 700.00
4 Mandor Org/Hari 120,000.00 0.0050 600.00
Jumlah A 16,300.00
B BAHAN
1 Gypsum Board Lembar 99,250.00 0.3640 36,127.00
2 Sekrup Gypsum Kg 35,000.00 0.1100 3,850.00
Jumlah B 39,977.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 56,277.00
E Overhead 10% 5,627.70
F Harga Satuan D + E 61,900.00

2 4.5.1.9 Pemasangan 1 m' list langit-langit kayu profil


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.0500 4,500.00
2 Tukang Kayu Org/Hari 120,000.00 0.0500 6,000.00
3 Kepala Tukang Org/Hari 140,000.00 0.0050 700.00
4 Mandor Org/Hari 120,000.00 0.0030 360.00
Jumlah 11,560.00
B BAHAN
1 List Kayu Profil M' 6,331.25 1.0000 6,331.25
2 Paku Sekrup Kg 35,000.00 0.0100 350.00
Jumlah B 6,681.25
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 18,241.25
E Overhead 10% 1,824.13
F Harga Satuan D + E 20,000.00

95
VII PEKERJAAN BESI DAN ALUMINIUM
1 4.2.1.21 Pemasangan 1 m2 rangka besi hollow 1x40.40.2 mm, modul 60 x 60 cm, untuk plafon
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.3500 31,500.00
2 Tukang Besi Org/Hari 120,000.00 0.3500 42,000.00
3 Kepala Tukang Org/Hari 140,000.00 0.0350 4,900.00
4 Mandor Org/Hari 120,000.00 0.0180 2,160.00
Jumlah A 80,560.00
B BAHAN
1 Rangka Besi Hollow 40.40.2 cm M' 6,750.00 4.0000 27,000.00
2 Assesoris (perkuatan, las dll) Ls 9,450.00 1.0000 9,450.00
Jumlah B 36,450.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 117,010.00
E Overhead 10% 11,701.00
F Harga Satuan D + E 128,700.00

2 4.2.1.22 Pemasangan 1 m2 atap pelana rangka atap baja canai dingin profil C75
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.7340 66,060.00
2 Tukang Besi Org/Hari 120,000.00 0.7340 88,080.00
3 Kepala Tukang Org/Hari 140,000.00 0.0730 10,220.00
4 Mandor Org/Hari 120,000.00 0.0370 4,440.00
Jumlah A 168,800.00
B BAHAN
1 Baja Ringan Canai C75 Kg 17,500.00 3.0650 53,637.50
2 Sekrup Bh 400.00 9.0000 3,600.00
Jumlah B 57,237.50
C PERALATAN
Peralatan % 10.0000 5,723.75
Jumlah C 5,723.75
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 231,761.25
E Overhead 10% 23,176.13
F Harga Satuan D + E 254,900.00

96
VIII. PEKERJAAN BETON
1 2.2.6.1.d.(a) Pembesian kolom, balok, ring balk, dan sloof untuk besi beton < 12 mm (per - 1 Kg)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.6000 240,000.00
2 Tukang Besi Org/Hari 180,000.00 1.6000 288,000.00
3 Kepala Tukang Org/Hari 200,000.00 0.1600 32,000.00
4 Mandor Org/Hari 160,000.00 0.1600 25,600.00
Jumlah A 585,600.00
B BAHAN
1 Besi Beton Polos Kg 25,000.00 105.0000 2,625,000.00
2 Kawat beton Kg 20,000.00 2.8000 56,000.00
Jumlah B 2,681,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 3,266,600.00
E Overhead 10% 326,660.00
F Harga Satuan D + E 35,932.00

2 2.2.2.1.g Membuat 1 m3 Beton Mutu f'c = 7,4 Mpa (K-100), Lantai Kerja
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.6500 247,500.00
2 Tukang Besi Org/Hari 180,000.00 0.2750 49,500.00
3 Kepala Tukang Org/Hari 200,000.00 0.0275 5,500.00
4 Mandor Org/Hari 160,000.00 0.1650 26,400.00
Jumlah A 328,900.00
B BAHAN
1 Semen Portland (PC) Kg 1,700.00 227 385,900.00
2 Pasir Beton (PB) M3 189.29 869 164,489.29
3 Kerikil (Kr) M3 263.17 1,000 263,171.85
4 Air Liter 90.00 215 19,350.00
Jumlah B 813,561.14
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,142,461.14
E Overhead 10% 114,246.11
F Harga Satuan D + E 1,256,700.00

97
3 2.2.2.1.g Membuat 1 m3 Beton Mutu f'c = 14,5 Mpa (K-175), Lantai, Kolom, Balok
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 1.6500 247,500.00
2 Tukang Besi Org/Hari 180,000.00 0.2750 49,500.00
3 Kepala Tukang Org/Hari 200,000.00 0.0275 5,500.00
4 Mandor Org/Hari 160,000.00 0.1650 26,400.00
Jumlah A 328,900.00
B BAHAN
1 Semen Portland (PC) Kg 1,700.00 326 554,200.00
2 Pasir Beton (PB) Kg 189.29 760 143,857.14
3 Kerikil (Kr) Kg 263.17 1,029 270,803.84
4 Air Liter 90.00 215 19,350.00
Jumlah B 968,860.98
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 1,297,760.98
E Overhead 10% 129,776.10
F Harga Satuan D + E 1,427,500.00

4 4.1.1.19 Pemasangan 1 m2 Bekisting untuk Sloof Beton Bangunan Gedung


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 150,000.00 0.5200 78,000.00
2 Tukang Kayu Org/Hari 180,000.00 0.2600 46,800.00
3 Kepala Tukang Org/Hari 200,000.00 0.0260 5,200.00
4 Mandor Org/Hari 160,000.00 0.0260 4,160.00
Jumlah A 134,160.00
B BAHAN
1 Kayu Kelas III M3 2,205,000.00 0.0450 99,225.00
2 Paku 5 cm - 10 cm Kg 20,000.00 0.3000 6,000.00
3 Minyak Bekisting Liter 12,500.00 0.1000 1,250.00
Jumlah B 106,475.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 240,635.00
E Overhead 10% 24,063.50
F Harga Satuan D + E 264,600.00

98
5 4.1.1.22 Pemasangan 1 m² bekisting untuk kolom
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.6600 59,400.00
2 Tukang Batu Org/Hari 120,000.00 0.3300 39,600.00
3 Kepala Tukang Org/Hari 140,000.00 0.0330 4,620.00
4 Mandor Org/Hari 120,000.00 0.0330 3,960.00
Jumlah A 107,580.00
B BAHAN
1 Kayu Papan kelas IV (Bekisting) m³ 2,205,000.00 0.0400 88,200.00
2 Paku 5 cm - 12 cm Kg 20,000.00 0.4000 8,000.00
3 Minyak bekisting Liter 12,500.00 0.2000 2,500.00
4 Balok Kayu kelas IV (Bekisting) m³ 2,205,000.00 0.0150 33,075.00
5 Multipleks tebal 9 mm Lbr 167,000.00 0.3500 58,450.00
6 Dolken kayu .. 8-10 ) cm- panj 4 m Batang 13,600.00 2.0000 27,200.00
Jumlah B 217,425.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 325,005.00
E Overhead 10% 32,500.50
F Harga Satuan D + E 357,500.00

6 4.1.1.23 Pemasangan 1 m² bekisting untuk balok


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.6600 59,400.00
2 Tukang Kayu Org/Hari 120,000.00 0.3300 39,600.00
3 Kepala Tukang Org/Hari 140,000.00 0.0330 4,620.00
4 Mandor Org/Hari 120,000.00 0.0330 3,960.00
Jumlah A 107,580.00
B BAHAN
1 Kayu Papan kelas IV (Bekisting) m³ 2,205,000.00 0.0400 88,200.00
2 Paku 5 cm - 12 cm Kg 20,000.00 0.4000 8,000.00
3 Minyak bekisting Liter 12,500.00 0.2000 2,500.00
4 Balok Kayu kelas IV (Bekisting) m³ 2,205,000.00 0.0180 39,690.00
5 Multipleks tebal 9 mm Lbr 167,000.00 0.3500 58,450.00
6 Dolken kayu .. 8-10) cm- panj 4 m Batang 13,600.00 2.0000 27,200.00
Jumlah B 224,040.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 331,620.00
E Overhead 10% 33,162.00
F Harga Satuan D + E 364,700.00

99
IX PEKERJAAN PENUTUP LANTAI
1 4.4.3.9 Pemasangan 1 m2 lantai ubin granit ukuran 40 cm x 40 cm
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 90,000.00 0.4500 40,500.00
2 Kepala Tukang Org/Hari 120,000.00 0.0450 5,400.00
3 Pekerja Org/Hari 140,000.00 0.6000 84,000.00
4 Mandor Org/Hari 120,000.00 0.0300 3,600.00
Jumlah 133,500.00
B BAHAN
1 Tegel Keramik 40 x 40 Cm Bh 15,000.00 6.6300 99,450.00
2 Semen warna Kg 5,350.00 1.3000 6,955.00
3 Semen portland Kg 1,550.00 9.8000 15,190.00
4 Pasir Pasang M3 130,000.00 0.0450 5,850.00
Jumlah 127,445.00
Harga Satuan A + B 260,945.00
E Overhead 10% 26,094.50
F Harga Satuan D + E 287,000.00

2 4.4.3.6 Pemasangan 1 m2 lantai ubin warna ukuran 20 cm x 20 cm


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 90,000.00 0.1350 12,150.00
2 Kepala Tukang Org/Hari 120,000.00 0.0140 1,680.00
3 Pekerja Org/Hari 140,000.00 0.2700 37,800.00
4 Mandor Org/Hari 120,000.00 0.0140 1,680.00
Jumlah 53,310.00
B BAHAN
1 Tegel Warna 20 x 20 Cm Bh 3,040.00 26.5000 80,560.00
2 Semen warna Kg 5,350.00 1.0000 5,350.00
3 Semen portland Kg 1,550.00 10.4000 16,120.00
4 Pasir Pasang M3 130,000.00 0.0450 5,850.00
Jumlah 107,880.00
Harga Satuan A + B 161,190.00
E Overhead 10% 16,119.00
F Harga Satuan D + E 177,300.00

100
3 4.4.3.24 Pemasangan 1 m' plint tegel granit ukuran 10 x 40 cm
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Tukang Batu Org/Hari 90,000.00 0.0900 8,100.00
2 Kepala Tukang Org/Hari 120,000.00 0.0090 1,080.00
3 Pekerja Org/Hari 140,000.00 0.0900 12,600.00
4 Mandor Org/Hari 120,000.00 0.0050 600.00
Jumlah A 22,380.00
B BAHAN
1 Tegel Plint Keramik 10 x 40 Cm Bh 3,750.00 2.6500 9,937.50
2 Semen portland Kg 1,550.00 1.1400 1,767.00
3 Pasir Pasang M3 130,000.00 0.0030 390.00
4 Semen warna Kg 5,350.00 0.1000 535.00
Jumlah B 12,629.50
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 35,009.50
E Overhead 10% 3,500.95
F Harga Satuan D + E 38,500.00

4 4.4.3.54 Pemasangan 1 m2 dinding keramik 20 x 20 cm


No. Uraian Satuan Harga Jumlah
Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.600 54,000.00
2 Tukang Batu Org/Hari 120,000.00 0.450 54,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.045 6,300.00
4 Mandor Org/Hari 120,000.00 0.030 3,600.00
Jumlah A 117,900.00
B BAHAN
1 Tegel Dinding Keramik 20 x20 Cm Bh 3,040.00 26.500 80,560.00
2 Semen portland Kg 1,550.00 9.300 14,415.00
3 Pasir Pasang M3 130,000.00 0.018 2,340.00
Jumlah B 97,315.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 215,215.00
E Overhead 10% 21,521.50
F Harga Satuan D + E 236,700.00

101
X PEKERJAAN PENUTUP ATAP
1 4.5.2.41 Pemasangan 1 m2 genteng metal ukuran 80 x 100 atap pelana
No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.200 18,000.00
2 Tukang kayu Org/Hari 120,000.00 0.100 12,000.00
3 Kepala Tukang Org/Hari 140,000.00 0.010 1,400.00
4 Mandor Org/Hari 120,000.00 0.001 120.00
Jumlah A 31,520.00
B BAHAN
1 Genteng Metal Lbr 25,116.67 1.300 32,651.67
2 Baut Spandek 4,5cm Bh 10,000.00 6.000 60,000.00
Jumlah B 92,651.67
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 124,171.67
E Overhead 10% 12,417.17
F Harga Satuan D + E 136,500.00

2 4.5.2.37 Pemasangan 1 m' nok genteng metal


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 120,000.00 0.1500 18,000.00
2 Kepala Tukang Org/Hari 140,000.00 0.0150 2,100.00
3 Pekerja Org/Hari 90,000.00 0.2500 22,500.00
4 Mandor Org/Hari 120,000.00 0.0130 1,560.00
Jumlah A 44,160.00
B BAHAN
1 Nok Genteng Metal Lbr 51,000.00 1.1000 56,100.00
2 Paku Atap Kg 15,500.00 0.0500 775.00
Jumlah B 56,875.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 101,035.00
E Overhead 10% 10,103.50
F Harga Satuan D + E 111,100.00

102
XI PEKERJAAN KUNCI DAN KACA
1 4.6.2.2 Pemasangan 1 buah kunci biasa
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.010 900.00
2 Tukang Kayu Org/Hari 120,000.00 0.500 60,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.050 7,000.00
4 Mandor Org/Hari 120,000.00 0.005 600.00
Jumlah A 68,500.00
B BAHAN
1 Kunci Tanam Pintu Bh 220,000.00 1.0000 220,000.00
Jumlah B 220,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 288,500.00
E Overhead 10% 28,850.00
F Harga Satuan D + E 317,300.00

2 4.6.2.5 Pemasangan 1 buah engsel pintu


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.015 1,350.00
2 Tukang Kayu Org/Hari 120,000.00 0.150 18,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.015 2,100.00
4 Mandor Org/Hari 120,000.00 0.0008 96.00
Jumlah A 21,546.00
B BAHAN
1 Kunci Tanam Pintu Bh 32,400.00 1.0000 32,400.00
Jumlah B 32,400.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 53,946.00
E Overhead 10% 5,394.60
F Harga Satuan D + E 59,300.00

3 4.6.2.6 Pemasangan 1 buah engsel jendela kupu-kupu


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.010 900.00
2 Tukang Kayu Org/Hari 120,000.00 0.100 12,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.010 1,400.00
4 Mandor Org/Hari 120,000.00 0.0005 60.00
Jumlah A 14,360.00
B BAHAN
1 Engsel Kupu-Kupu Bh 30,200.00 1.0000 30,200.00
Jumlah B 30,200.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 44,560.00

103
E Overhead 10% 4,456.00
F Harga Satuan D + E 49,000.00

104
4 4.6.2.8 Pemasangan 1 buah spring knip
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.015 1,350.00
2 Tukang Kayu Org/Hari 120,000.00 0.150 18,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.015 2,100.00
4 Mandor Org/Hari 120,000.00 0.0008 96.00
Jumlah A 21,546.00
B BAHAN
1 Spring Knip Bh 26,000.00 1.0000 26,000.00
Jumlah B 26,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 47,546.00
E Overhead 10% 4,754.60
F Harga Satuan D + E 52,300.00

5 4.6.2.9 Pemasangan 1 buah kait angin


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.015 1,350.00
2 Tukang Kayu Org/Hari 120,000.00 0.150 18,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.015 2,100.00
4 Mandor Org/Hari 120,000.00 0.0008 96.00
Jumlah A 21,546.00
B BAHAN
1 Kait Angin Bh 22,500.00 1.0000 22,500.00
Jumlah B 22,500.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 44,046.00
E Overhead 10% 4,404.60
F Harga Satuan D + E 48,400.00

6 4.6.2.17 Pemasangan 1 m2 kaca tebal 5 mm


No. Uraian Satuan Harga Koefisien Jumlah
Satuan Harga
A TENAGA KERJA
1 Tukang Kayu Org/Hari 120,000.00 0.1500 18,000.00
2 Kepala tukang Org/Hari 140,000.00 0.0150 2,100.00
3 Pekerja Org/Hari 90,000.00 0.0150 1,350.00
4 Mandor Org/Hari 120,000.00 0.0008 96.00
Jumlah A 21,546.00
B BAHAN
1 Kaca Tebal 5 mm M2 172,500.00 1.1000 189,750.00
Jumlah B 189,750.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 211,296.00
E Overhead 10% 21,129.60

105
F Harga Satuan D + E 232,400.00

106
XII PEKERJAAN PENGECATAN
1 4.7.1.10 Pengecetan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.0200 1,800.00
2 Tukang Cat Org/Hari 120,000.00 0.0630 7,560.00
3 Kepala Tukang Org/Hari 140,000.00 0.0063 882.00
4 Mandor Org/Hari 120,000.00 0.0030 360.00
Jumlah A 10,602.00
B BAHAN
1 Plamuur Kg 22,168.75 0.1000 2,216.88
2 Cat Dasar Kg 28,000.00 0.1000 2,800.00
3 Cat Penutup Kg 30,000.00 0.2600 7,800.00
Jumlah B 12,816.88
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 23,418.88
E Overhead 10% 2,341.89
F Harga Satuan D + E 25,700.00

XIII PEKERJAAN SANITASI


1 5.1.1.2 Memasang 1 buah closet jongkok porselen
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.070 6,300.00
2 Tukang Batu Org/Hari 120,000.00 0.100 12,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.010 1,400.00
4 Mandor Org/Hari 120,000.00 0.004 480.00
Jumlah A 20,180.00
B BAHAN
1 Closed Jongkok Buah 240,000.00 1.0000 240,000.00
2 Semen Portland Kg 1,550.00 6.0000 9,300.00
3 Pasir Pasang M3 130,000.00 0.0100 1,300.00
Jumlah B 249,300.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 269,480.00
E Overhead 10% 26,948.00
F Harga Satuan D + E 296,400.00

2 5.1.1.14 Pemasangan 1 buah floor drain


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.010 900.00
2 Tukang Batu Org/Hari 120,000.00 0.100 12,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.010 1,400.00
4 Mandor Org/Hari 120,000.00 0.005 600.00
Jumlah A 14,900.00
B BAHAN
1 Floor Drain Bh 75,000.00 1.000 75,000.00

107
Jumlah B 75,000.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 89,900.00
E Overhead 10% 8,990.00
F Harga Satuan D + E 98,800.00

108
3 5.1.1.19 Pemasangan 1 buah kran diameter 1/2"
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.010 900.00
2 Tukang Batu Org/Hari 120,000.00 0.400 48,000.00
3 Kapala Tukang Org/Hari 140,000.00 0.040 5,600.00
4 Mandor Org/Hari 120,000.00 0.005 600.00
Jumlah A 55,100.00
B BAHAN
1 Kran air Bh 19,800.00 1.000 19,800.00
2 Seal tape Bh 10,000.00 0.250 2,500.00
Jumlah B 22,300.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 77,400.00
E Overhead 10% 7,740.00
F Harga Satuan D + E 85,100.00

4 5.1.1.25 Pemasangan 1 m' pipa PVC tipe AW diameter 1/2"


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.036 3,240.00
2 Tukang Batu Org/Hari 120,000.00 0.060 7,200.00
3 Kapala Tukang Org/Hari 140,000.00 0.006 840.00
4 Mandor Org/Hari 120,000.00 0.002 240.00
Jumlah A 11,520.00
B BAHAN
1 Pipa PVC 1/2" m' 8,500.00 1.2000 10,200.00
2 Perlengkapan 35 % dari harga pipa % 3,570.00 1.0000 3,570.00
Jumlah B 13,770.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 25,290.00
E Overhead 10% 2,529.00
F Harga Satuan D + E 27,800.00

109
5 5.1.1.26 Pemasangan 1 m' pipa PVC tipe AW diameter 3/4"
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.036 3,240.00
2 Tukang Batu Org/Hari 120,000.00 0.060 7,200.00
3 Kapala Tukang Org/Hari 140,000.00 0.006 840.00
4 Mandor Org/Hari 120,000.00 0.002 240.00
Jumlah A 11,520.00
B BAHAN
1 Pipa PVC 3/4" m' 9,775.00 1.2000 11,730.00
2 Perlengkapan 35 % dari harga pipa ls 3,421.25 1.0000 3,421.25
Jumlah B 15,151.25
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 26,671.25
E Overhead 10% 2,667.13
F Harga Satuan D + E 29,300.00

6 5.1.1.31 Memasang 1 M' Pipa PVC AW Diameter 3"


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.081 7,290.00
2 Tukang Batu Org/Hari 120,000.00 0.135 16,200.00
3 Kapala Tukang Org/Hari 140,000.00 0.0135 1,890.00
4 Mandor Org/Hari 120,000.00 0.004 480.00
Jumlah A 25,860.00
B BAHAN
1 Pipa PVC 3" m' 65,000.00 1.2000 78,000.00
2 Perlengkapan 35 % dari harga pipa ls 22,750.00 1.0000 22,750.00
Jumlah B 100,750.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 126,610.00
E Overhead 10% 12,661.00
F Harga Satuan D + E 139,200.00

7 5.1.1.32 Memasang 1 M' Pipa PVC AW Diameter 4"


Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.036 3,240.00
2 Tukang Batu Org/Hari 120,000.00 0.060 7,200.00
3 Kapala Tukang Org/Hari 140,000.00 0.006 840.00
4 Mandor Org/Hari 120,000.00 0.002 240.00
Jumlah A 11,520.00
B BAHAN
1 Pipa PVC 4" m' 112,500.00 1.2000 135,000.00
2 Perlengkapan 35 % dari harga pipa ls 39,375.00 1.0000 39,375.00
Jumlah B 174,375.00
C PERALATAN

110
Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 185,895.00
E Overhead 10% 18,589.50
F Harga Satuan D + E 204,400.00

111
XIV PEKERJAAN INSTALASI LISTRIK
1 8.4.6.1 Pemasangan 1 buah titik lampu
Harga Jumlah
No. Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.2000 18,000.00
2 Tukang Listrik Org/Hari 120,000.00 0.3000 36,000.00
3 Kepala Tukang Listrik Org/Hari 140,000.00 0.0500 7,000.00
4 Mandor Org/Hari 120,000.00 0.0500 6,000.00
Jumlah A 67,000.00
B BAHAN
1 Kabel NYM 2 x 2,5 mm m' 9,775.00 5.000 48,875.00
2 Pipa Conduit m' 8,500.00 5.000 42,500.00
3 Fitting (Elbow, T-Dus, Mongkok) bh 12,000.00 3.000 36,000.00
4 Klem bh 3,000.00 4.000 12,000.00
5 Fisher dan skrup bh 500.00 4.000 2,000.00
7 Fitting Lampu bh 20,000.00 1.000 20,000.00

Jumlah B 161,375.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 228,375.00
E Overhead 10% 22,837.50
F Harga Satuan D + E 251,200.00

2 8.4.6.1 1 Titik Pasang Instalasi Stop Kontak


No. Harga Jumlah
Uraian Satuan Koefisien
Satuan Harga
A TENAGA KERJA
1 Pekerja Org/Hari 90,000.00 0.2000 18,000.00
2 Tukang Listrik Org/Hari 120,000.00 0.3000 36,000.00
3 Kepala Tukang Listrik Org/Hari 140,000.00 0.0500 7,000.00
4 Mandor Org/Hari 120,000.00 0.0500 6,000.00
Jumlah A 67,000.00
B BAHAN
1 Kabel NYM 3 x 2,5 mm m' 9,775.00 5.000 48,875.00
2 Pipa Conduit m' 8,500.00 5.000 42,500.00
3 Fitting (elbow, male, bust) bh 12,000.00 3.000 36,000.00
4 Sadle/klem bh 3,000.00 4.000 12,000.00
5 Fisher dan skrup bh 500.00 5.000 2,500.00
6 Tee dos bh 20,000.00 1.000 20,000.00
7 Stop kontak tanam bh 30,000.00 1.000 30,000.00
Jumlah B 191,875.00
C PERALATAN

Jumlah C -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 258,875.00
E Overhead 10% 25,887.50
F Harga Satuan D + E 284,700.00

112
TABEL BESI ILMUSIPIL.COM

BESI BETON POLOS & ULIR

UKURAN BERAT
(mm) (Kg) Beton Rasio
6 0.222 0 -
8 0.395 4.74 1 Kg/m3
9 0.500 2 Kg/m3
10 0.617 7.404 3 Kg/m3
12 0.888 10.656 4 Kg/m3
13 1.040 5 Kg/m3
16 1.578 18.936 6 Kg/m3
16 1.578 7 Kg/m3
19 2.223 8 Kg/m3
22 2.985 9 Kg/m3
25 3.853 10 Kg/m3
28 4.830 11 Kg/m3
29 5.185 -
32 6.313
36 7.990
6p 0.22 10.656 23.40
8p 0.4
9p 0.5
10p 0.62
12p 0.89 Besi 12 1 Btg
13p 1.04
16p 1.57
16p 1.58
19p 2.23
22p 2.98 Besi 16 1 Btg
25p 3.85
28p 4.83
29p 5.19
32p 6.31
36p 7.99

HARGA BESI 12 100,000,000 BTG

HARGA BESI 14 160,000,000 BTG


1x1 10 M1 = 3.95 Kg
4x1 40 M1 = 15.8 Kg
15,800

25,000.00 9,875.00

22,200.00 = 4000 15,800

4000 15,800

30,060.30 76,102.03 11.5 2,613.94

91,487,869.57
2.19594595 Btg

77,800.00

7,301.05

127,872.00 1.64
145,000.00
50,072.00
7,657.37

227,232.00

82,232.00
DATA PERHITUNGAN (BACK UP DATA)
No
SKET GAMBAR TAKE OF SHEET
I PEKERJAAN PERSIAPAN
1. Pembersihan Lapangan dan Perataan = 1.00 Ls

2. Pas Bouwplank = 14.00 Unit

3. Air Listrik Kerja = 1.00 Ls

II PEKERJAAN STRUKTUR STANDAR


A. Pekerjaan Galian Tanah dan Pondasi 1. Galian Tanah
Pondasi Menerus 1
V= T x L x P
0.55 x 0.60 x 132.00 = 43.56 M3

Pondasi Menerus 2
V= T x L x P
0.3 x 0.25 x 6.50 = 0.49 M3

V. Total = = 44.05 M3

2. Urugan Tanah
V= 1/3 Volume Galian = 14.68 M3

3. Urugan Pasir Alas Pondasi t = 5cm


Urugan Pasir 1
V= T x L x P
0.05 x 0.60 x 132.00 = 3.96 M3

V= T x L x P
0.3 x 0.25 x 6.50 = 0.49 M3

V. Total = = 4.45 M3

4. Pasangan Batu Kosong


V= T x L x P
0.15 x 0.60 x 132 = 11.88 M3

V. Total = = 11.88 M3

5. Pasangan Batu Gunung


Pas. Batu 1
V= T x L x P
0.6 x 0.45 x 132 = 35.64 M3

Pas. Batu 2
V= T x L x P
0.3 x 0.30 x 6.50 = 0.59 M3

V. Total = = 36.22 M3
6. Sloof Beton 15/20 cm
Camp. Beton
V= T x L x P
0.2 x 0.15 x 138.50 = 4.16 M3

V. Total = = 4.16 M3

Pembesian
Tulangan pokok
V= P x Jml
138.50 x 4 = 554.00 M'

Berat besi x P
0.62 x 554.00 = 341.82 kg

Beugel
P / Jrk x L
138.50 / 0.15 x 0.54 = 498.60 M'

Berat besi x P
0.395 x 498.60 = 196.95 kg

Berat A + Berat B
341.82 + 196.95 = 538.77 kg

V. Total = = 538.77 kg

Bekisting
V= P x T x Banyak
138.50 x 0.2 x 2.00 = 55.40 M2

V. Total = = 13.85 M2

B. Pekerjaan Dinding dan Rangka Bangunan 1. Kolom Beton 15/15 cm


Camp. Beton
V= T x PxL x Banyak
3.8 x 0.02 x 50.00 = 4.27 M3

V. Total = = 4.27 M3

Pembesian
Tulangan pokok
V= T. P x Jml
157.50 x 4 = 630.00 M'

Berat besi x P
0.62 x 630.00 = 388.71 kg

Beugel
P / Jrk x L
157.50 / 0.15 x 0.44 = 462.00 M'

Berat besi x P
0.395 x 462.00 = 182.49 kg

Berat A + Berat B
388.71 + 182.49 = 571.20 kg

V. Total = = 571.20 M3
Bekisting
V= P x L x Banyak
157.50 x 0.15 x 4.00 = 94.50 M2

V. Total = = 23.63 M3

2. Pas. Bata Camp 1 : 4


V= T x P - Bukaan
3.8 x 141.75 - 72.11 = 466.54 M2

Tambahan 2 x 25.00 = 50.00 M2

V. Total = = 516.54 M3

3. Balok Latei 11/11 cm


V= T x L x P
0.11 x 0.11 x 82.18 = 0.99 M3

V. Total = = 0.99 M3

Pembesian
V= P x Jml
82.18 x 4 = 328.72 M'

Berat besi x P
0.40 x 328.72 = 129.84 kg

P / Jrk x L
82.18 / 0.2 x 0.36 = 147.92 M'

Berat besi x P
0.22 x 147.92 = 32.84 kg

Berat A + Berat B
129.84 + 32.84 = 162.68 kg

V. Total = = 162.68 kg

Bekisting
V= P x T x Banyak
82.18 x 0.11 x 2.00 = 18.08 M2

V. Total = = 4.52 M3

4. Ring Balk 15/20 cm


Camp. Beton
V= T x L x P
0.15 x 0.2 x 141.75 = 4.25 M3

V. Total = = 4.25 M3
Pembesian
V= P x Jml
141.75 x 4 = 567.00 M'

Berat besi x P
0.62 x 567.00 = 349.84 kg

P / Jrk x L
141.75 / 0.15 x 0.52 = 491.40 M'

Berat besi x P
0.40 x 491.40 = 194.10 kg

Berat A + Berat B
349.84 + 194.10 = 543.94 kg

V. Total = = 543.94 Kg

Bekisting
V= P x T x Banyak
141.75 x 0.2 x 2.00 = 56.70 M2

V. Total = = 14.18 M2

5. Plat Kanopi
Plat Talang air keliling
V= T x L x P
V= 0.1 x 2.00 x 65.00 = 13.00 M3

pembesian
V= P / Jrk x L
65.00 / 0.20 x 2.00 = 650.00 M'

Berat besi x P
0.395 x 650.00 = 256.75 Kg

Dak beton Belakang


V= T x L x P
V= 0.1 x 2.28 x 2.13 = 0.48 M3

pembesian
V= P / Jrk x L
2.13 / 0.20 x 2.28 = 24.17 M'

Berat besi x P
0.40 x 24.17 = 9.55 Kg

V. Beton = 13.48 x 0.48 = 6.52 M3

V. Besi = 266.30 x 9.55 = 275.85 Kg

III PEKERJAAN ARSITEKTUR STANDAR


A. Pekerjaan Lantai 1. Timbunan Tanah Bawah Lantai
V= Luas Lantai x T
189.62 x 0.40 = 75.85 M3

V. Total = = 75.85 M3
2. Timbunan Pasir Bawah Lantai
V= Luas Lantai x T
189.62 x 0.05 = 9.48 M3

V. Total = = 9.48 M3

3. Rabat Beton Tumbuk di Bawah Lantai Keramik


V= Luas Lantai x T
V= 189.62 x 0.05 = 9.48 M3

V. Total = = 9.48 M3

4. Lantai Keramik 60x60


V= Luas Lantai yang di Maksud = 177.95 M2

V. Total = = 177.95 M2

5 Plint Lantai 10x60


V= Keliling Ruangan = 152.72 M'

V. Total = = 152.72 M'

5. Lantai Keramik 20x20


V= Luas Lantai yang di Maksud = 11.68 M2

V. Total = = 11.68 M2

6. Dinding Keramik 20x20


V= Luas Lantai yang di Maksud = 25.43 M2

V. Total = = 25.43 M2

B. Pekerjaan Plesteran
1. Plasteran
V= V. Pas. Bata x J. Sisi
466.54 x 2 = 933.08 M2

V. Total = = 933.08 M2

2. Acian
V= V. Plasteran - D. Keramik
V= 933.08 - 25.43 = 907.65 M2

V. Total = = 907.65 M2
C. Pekerjaan Plafond dan Atap
1. Luasan Bidang Atap 1

= 6.93 M2

Luasan Bidang Atap 2

= 6.29 M2

Luasan Bidang Atap 3

= 35.45 M2

Luasan Bidang Atap 4

= 59.09 M2

Luasan Bidang Atap 5

= 56.20 M2

Luasan Bidang Atap 6

= 6.15 M2

Luasan Bidang Atap 7

= 6.15 M2
Luasan Bidang Atap 8

= 32.02 M2

Luasan Bidang Atap 9

= 2.86 M2

Luasan Bidang Atap 10

= 1.43 M2

Luas bidang x cos 30


V. Total = 212.57 x 0.86 = 182.81 M2

2. Luasan Penutup Atap


V= V. Luasan = 182.81 M2

V. Total = = 182.81 M2

3. Kuda-kuda kayu

Gording
V= P x Penampang
V= 208.50 x 0.01 = 1.50 M3

Balok Nok/bubungan
V= P x Penampang
V= 47.70 x 0.01 = 0.34 M3

Kuda-kuda
V= P x Penampang x Jumlah
V= 130.60 x 0.01 x = 0.94 M3

4. Lisplank
V= P x Qty
V= 62.00 x 1.00 = 62.00 M'

5. Rangka Plafond
V= Luas Plafond = 124.50 M2

V. Total = = 124.50 M2
6. Penutup Plafond Gypsum
V= Luas Plafond = 124.50 M2

V. Total = = 124.50 M2

7. List Plafond Gypsum


V= Panjang List = 142.42 M'

V. Total = = 142.42 M'

8. Err:509

V. Total = = 56.00

D. Pekerjaan Kusen dan Aksesoris


1. Pintu kayu D01
V= Banyak Pintu = 5.00 Bh

Kusen
V= P x Penampang
6.5 x 0.01 = 0.05 M3

V. Total = 0.05 x 5.00 = 0.26 M3

Daun Pintu
V= P x L x TEBAL
2.25 x 0.8 x 0.03 = 0.05 M3

V. Total = 0.05 x 5.00 = 0.27 M3

Relling Pintu
V= Banyak Pintu = 5.00 Bh

V. Total = 5.00 x 1.00 = 5.00 Bh

Handle Pintu
V= Banyak Pintu = 5.00 Bh

V. Total = 5.00 x 1.00 = 5.00 Bh

2. Pintu kayu D02


V= Banyak Pintu = 4.00 Bh

Kusen
V= P x Penampang
6.5 x 0.01 = 0.03 M3

V. Total = 0.03 x 4.00 = 0.13 M3

Daun Pintu
V= P x L x TEBAL
2.2 x 0.7 x 0.03 = 0.05 M3

V. Total = 0.05 x 4.00 = 0.18 M3

Engsel Pintu
V= Banyak Pintu = 4.00 Bh

V. Total = 4.00 x 3.00 = 12.00 Bh

Handle Pintu
V= Banyak Pintu = 4.00 Bh

V. Total = 4.00 x 1.00 = 4.00 Bh

3. Pintu kayu D03


V= Banyak Pintu = 1.00 Bh

Kusen
V= P x Penampang
7.16 x 0.01 = 0.05 M3
V. Total = 0.05 x 1.00 = 0.05 M3

Bingkai Pintu
V= P x L x TEBAL
4.74 x 0.08 x 0.03 = 0.14 M3

V. Total = 0.14 x 4.00 = 0.56 M3

Stik frame 10x10 mm


V= vertikal horizontal
6.42 + 2.60 = 9.02 M1

V. Total = 9.02 x 4.00 = 36.08 M1


Kaca Buram 5 mm
V= P x L
2.16 x 0.56 = 1.21 M2

V. Total = 1.21 x 4.00 = 4.84 M2

Sliding rell
V= Banyak Pintu = 4.00 Bh

V. Total = 4.00 x 1.00 = 4.00 Bh

4. Jendela W01
V= Banyak Jendela = 3.00 Bh

Kusen
V= P x Penampang
9.40 x 0.01 = 0.07 M3

V. Total = 0.07 x 3.00 = 0.21 M3

Daun Jendela
V= P x L x Penampang
3.30 x 2.70 X 0.00 = 0.03 M3

V. Total = 0.03 x 3.00 = 0.08 M3

Kaca Jendela 5 mm
V= P x L
1.25 x 1.53 = 1.91 M2

V. Total = 1.91 x 3.00 = 5.74 M2

Engsel Jendela
V= Banyak Jendela = 3.00 Bh

V. Total = 3.00 x 2.00 = 6.00 Bh

Pengunci Jendela
V= Banyak Pintu = 2.00 Bh

V. Total = = 2.00 Bh

Stik frame 10x10 mm


V= vertikal horizontal
4.59 + 4.80 = 9.39 M1

V. Total = 9.39 x 3.00 = 28.17 M1

5. Jendela W02
V= Banyak Jendela = 2.00 Bh

Kusen
V= P x Penampang
6.8 x 0.01 = 0.05 M3

V. Total = 0.05 x 2.00 = 0.10 M3

Daun Jendela
V= P x L x Penampang
3.30 x 2.70 X 0.00 = 0.03 M3

V. Total = 0.03 x 2.00 = 0.05 M3

Kaca Jendela 5 mm
V= P x L
2.29 x 0.7 = 1.60 M2

V. Total = 1.60 x 2.00 = 3.21 M2

Engsel Jendela
V= Banyak Jendela = 2.00 Bh
V. Total = = 4.00 Bh

Pengunci Jendela
V= Banyak Jendela = 2.00 Bh

V. Total = = 2.00 Bh

Stik frame 10x10 mm


V= vertikal horizontal
6.81 + 3.35 = 10.16 M1

V. Total = 10.16 x 2.00 = 20.32 M1

6. Jendela W03
V= Banyak Jendela = 2.00 Bh

Kusen
V= P x Penampang
4.80 x 0.01 = 0.04 M3

V. Total = 0.04 x 2.00 = 0.07 M3

Daun Jendela
V= P x L x Penampang
3.20 x 1.20 X 0.00 = 0.01 M3

V. Total = 0.01 x 2.00 = 0.02 M3

Kaca Jendela 5 mm
V= P x L
1.58 x 0.6 = 0.95 M2

V. Total = 0.95 x 2.00 = 1.90 M2

Engsel Jendela
V= Banyak Jendela = 2.00 Bh

V. Total = = 4.00 Bh

Pengunci Jendela
V= Banyak Jendela = 2.00 Bh

V. Total = = 2.00 Bh

7. Jendela W04
V= Banyak Pintu = 1.00 Bh

Kusen
V= P x Penampang
2.40 x 0.01 = 0.02 M3

V. Total = 0.02 x 1.00 = 0.02 M3

Daun Jendela
V= P x L x Penampang
1.00 x 1.00 X 0.01 = 0.01 M3

V. Total = 0.01 x 1.00 = 0.01 M3

Kaca Jendela 5 mm
V= P x L
0.52 x 0.52 = 0.27 M2

V. Total = 0.27 x 1.00 = 0.27 M2

Engsel Jendela
V= Banyak Jendela = 1.00 Bh

V. Total = = 2.00 Bh
Pengunci Jendela
V= Banyak Jendela = 1.00 Bh

V. Total = = 1.00 Bh

8. Jendela W05

Kaca Jendela 5 mm
V= P x L
2.90 x 0.25 = 0.73 M2

V. Total = 0.73 x 3.00 = 2.18 M2

9. Jendela W06

Kaca Jendela 5 mm
V= P x L
1.75 x 2.35 = 4.11 M2

V. Total = 4.11 x 1.00 = 4.11 M2

10. Jendela W07


V= Banyak Jendela = 1.00 Bh

Kusen
V= P x Penampang
6.6 x 0.01 = 0.05 M3

V. Total = 0.05 x 1.00 = 0.05 M3

Daun Jendela
V= P x L x Penampang
4.80 x 1.42 X 0.00 = 0.02 M3

V. Total = 0.02 x 1.00 = 0.02 M3

Kaca Jendela 5 mm
V= P x L
2.27 x 0.582 = 1.32 M2

V. Total = 1.32 x 1.00 = 1.32 M2

Engsel Jendela
V= Banyak Jendela = 1.00 Bh

V. Total = = 2.00 Bh

Pengunci Jendela
V= Banyak Jendela = 1.00 Bh

V. Total = = 1.00 Bh

Stik frame 10x10 mm


V= vertikal horizontal
6.81 + 2.85 = 9.66 M1

V. Total = 9.66 x 1.00 = 9.66 M1

11. PJ 01
V= JUMLAH = 1.00 Bh

Kusen
V= P x Penampang
13.2 x 0.01 = 0.10 M3

PILAR KAYU
V= P x Penampang
6.6 x 0.04 = 0.26 M3

V. Total = 0.10 x 1.00 = 0.36 M3

Daun Jendela
V= P x L x Penampang
4.82 x 1.42 X 0.00 = 0.04 M3

Daun Pintu
V= P x L x Penampang
5.00 x 2.00 X 0.00 = 0.06 M3

V. Total = = 0.10 M3

Kaca Jendela 5 mm
V= P x L
2.34 x 0.582 = 2.72 M2

Kaca Pintu 5 mm
V= P x L
2.34 x 0.8 = 3.74 M2

V. Total = = 6.47 M2

Engsel Jendela
V= Banyak Jendela = 2.00 Bh

V. Total = = 4.00 Bh

Relling Pintu
V= Banyak Pintu = 2.00 Bh

Handle Pintu
V= Banyak Pintu = 2.00 Bh

Pengunci Jendela
V= Banyak Jendela = 2.00 Bh
V. Total = = 2.00 Bh

Stik frame 10x10 mm


V= vertikal horizontal
27.24 + 12.00 = 39.24 M1

V. Total = 39.24 x 1.00 = 39.24 M1

12. PJ 02

V= Banyak Pintu = 1.00 Bh

Kusen
V= P x Penampang
10.8 x 0.01 = 0.08 M3

V. Total = 0.08 x 1.00 = 0.08 M3

Daun Pintu
V= P x L x TEBAL
5.7 x 0.1 x 0.04 = 0.02 M3

V. Total = 0.02 x 1.00 = 0.02 M3

Engsel Pintu
V= Banyak Pintu = 1.00 Bh

V. Total = 1.00 x 3.00 = 3.00 Bh

Handle Pintu
V= Banyak Pintu = 1.00 Bh

V. Total = 1.00 x 1.00 = 1.00 Bh

Kaca Jendela 5 mm
V= P x L
2.42 x 1.352 = 6.54 M2

Kaca Pintu 5 mm
V= P x L
1.96 x 0.72 = 2.82 M2

13. PJ 03
V= Banyak Pintu = 1.00 Bh

Kusen
V= P x 0
7.16 x 0.01 = 0.05 M3

V. Total = 0.05 x 1.00 = 0.05 M3

Bingkai Pintu
V= P x L x TEBAL
4.74 x 0.08 x 0.03 = 0.01 M3

V. Total = 0.01 x 4.00 = 0.05 M3

Stik frame 10x10 mm


V= vertikal horizontal
6.42 + 2.60 = 9.02 M1

V. Total = 9.02 x 4.00 = 36.08 M1

Kaca Buram 5 mm
V= P x L
2.16 x 0.56 = 1.21 M2

V. Total = 1.21 x 4.00 = 4.84 M2

Sliding rell
V= Banyak Pintu = 4.00 Bh

V. Total = 4.00 x 1.00 = 4.00 Bh

14. PJ 04
V= Banyak Pintu = 1.00 Bh

Kusen
V= P x 0.08
6.85 x 0.01 = 0.05 M3

V. Total = 0.05 x 1.00 = 0.05 M3

Bingkai Pintu
V= P x L x TEBAL
4.74 x 0.08 x 0.03 = 0.01 M3

V. Total = 0.01 x 3.00 = 0.03 M3

Stik frame 10x10 mm


V= vertikal horizontal
6.42 + 2.60 = 9.02 M1

V. Total = 9.02 x 3.00 = 27.06 M1

Kaca Buram 5 mm
V= P x L
2.16 x 0.56 = 1.21 M2

V. Total = 1.21 x 3.00 = 3.63 M2

Sliding rell
V= Banyak Pintu = 3.00 Bh

V. Total = 3.00 x 1.00 = 3.00 Bh

E. Pekerjaan Pengecatan
1. Pengecatan Dinding
V= V. Acian
V= 907.65 = 907.65 M2

2. V. Total = 907.65 x 0.00 = 0.00 M2

Pengecatan Plafond
V = V. Penutup Plafond
V= 124.50 = 124.50 M2

V. Total = 124.50 x 0.00 = 0.00 M2


V PEKERJAAN MEP
A. Pekerjaan Elektrikal
1. Titik lampu = 30.00

= 0.00 Buah

2. Stop Kontak = 16.00 Buah

= 16.00 Buah

3. MCB Box = 1.00 Buah

= 1.00 Buah

4. Meteran = 1.00 Buah

= 1.00 Buah

5. Saklar Ganda = 4.00 Buah

= 4.00 Buah

6. Saklar Tunggal = 12.00 Buah

= 12.00 Buah
7. Lampu LED 11 watt (Downlight) = 23.00 Buah

= 23.00 Buah

8. Lampu LED 5 watt = 7.00 Buah

= 7.00 Buah

Buah
B. Pekerjaan Sanitasi Air Bersih dan Kotor
1. Floordrain = 3.00

= 3.00 Buah

2. Kloset Duduk = 3.00 Buah

= 3.00 Buah

3. Kran Air = 4.00 Buah

= 4.00 Buah

4. Wastafel = 3.00 Buah

= 3.00 Buah

5. Shower Spray = 3.00 Buah

= 3.00 Buah

4. Pipa PVC 3 inch = 35.80 Buah

= 35.80 M'

5. Pipa PVC 4 inch = 29.00 M'

= 29.00 M'

6. Pipa PVC 1/2 inch = 35.90 M'

= 35.90 M'

7. Septictank = 1.00 M'

= 1.00 Buah