RENCANA ANGGARAN BIAYA

GEDUNG PKBM BUMDES 2023

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH

I BIAYA UMUM
1 Biaya Uitzet 2 LS 600,000 1,200,000.00
2 Insentif Petugas Penyusunan Desain Gambar dan RAB Fiskk. 1 PAKET 7,200,000 7,200,000.00
II PEKERJAAN PONDASI DAN BETON -
1 kolom beton bertulang -
­Beton 10.78 M3 1,813,506.80 19,549,603.30
­Pembesian Kolom Uk. 35x35cm 1,228.92 KG 17,328.00 21,294,725.76
­Bekisting Kolom Uk. 35x35cm 71.50 M2 220,260.00 15,748,590.00
2 Ring Balok beton bertulang dan Sopi Sopi
­Beton 12.51 M3 1,813,506.80 22,691,503.84
­Pembesian Balok Uk. 25x 35 cm 2,027.03 KG 17,328.00 35,124,289.20
­Bekisting BalokUk. 25x 35 cm 67.93 M2 335,150.00 22,765,063.75
-
3 Pek. Balok Pinggang Beton Bertulang Uk. 8/20 cm + bekisting -
­Beton 1.18 M3 1,728,915.20 2,047,035.60
­Pembesian Balok Pinggang Uk. 8/20 cm 198.91 KG 17,328.00 3,446,747.14
­Bekisting Balok Pinggang Uk. 8/20 cm 17.76 M2 335,150.00 5,952,264.00
-
III PEKERJAAN PASANGAN DAN PLESTERAN -
1 Pasangan Dinding Bata 1 PC : 4 PP LT 2 288.96 M2 Rp 167,652.30 48,444,540.36
-
IV PEKERJAAN ATAP -
1 Pasang rangka atap baja ringan 363.51 M2 Rp 226,634.00 82,382,761.49
2 Pek Atap Genteng Metal 363.51 M² Rp 205,400.00 74,664,080.46
-
JUMLAH BIAYA TERMASUK PAJAK 362,511,204.90
DIBULATKAN 362,511,000.00
RENCANA ANGGARAN BIAYA (RAB)

Bidang : Bidang Pelaksanaan Pembangunan Desa Program : Dana Desa


Kegiatan : GEDUNG PKBM BUMDES 2023 Jenis Kegiatan : Pemb Gedung Serbaguna
Waktu Pelaksana : 90 hari Volume : 1 Unit

Uraian Volume Satuan Harga Satuan (Rp) Jumlah Total (Rp)

I BIAYA UMUM
1 Biaya Uitzet 2 LS Rp 600,000 1,200,000.00
2 Insentif Petugas Penyusunan Desain Gambar 1 PAKET Rp 7,200,000 7,200,000.00
Sub Total 1) 8,400,000.00
1. BAHAN

Semen Portland 12,653.33 Kg Rp 1,740 Rp 22,019,317


Pasir Beton 17.02 M3 Rp 280,000 Rp 4,765,110
Kerikil (maks 30 mm) 25.42 M3 Rp 270,000 Rp 6,863,196
Air 5,262.45 Liter Rp 2,000 Rp 10,524,895
Besi Beton (Polos/Ulir) 3,439.63 Kg Rp 14,000 Rp 48,154,792
Kawat Beton 65.52 Kg Rp 21,000 Rp 1,375,851
Kayu Kelas III 6.64 M3 Rp 2,500,000 Rp 16,612,250
Paku 5-10 cm 128.43 Kg Rp 13,000 Rp 1,669,527
Minyak Bekisting 24.29 Liter Rp 9,000 Rp 218,583
Balok Kayu Kelas II 1.54 M3 Rp 3,700,000 Rp 5,706,621
Plywood tebal 9mm 29.99 Lbr Rp 68,200 Rp 2,045,301
Dolken Kayu Ø 8 -10/400 cm 171.37 Batang Rp 3,500 Rp 599,795
Bata Merah 20,227.09 Bh Rp 1,200 Rp 24,272,506
Pasir Pasang 12.43 m3 Rp 280,000 Rp 3,479,059
Pasang rangka atap baja ringan 363.51 M2 Rp 226,634 Rp 82,382,761
Genteng metal 370.78 Bh Rp 160,000 Rp 59,324,138

Sub Total 2) Rp 290,013,702


2. ALAT
2.1 Papan Nama Proyek 1 Ls Rp 400,000 Rp 400,000
2.3 Timba Cor 7 Bh Rp 20,000 Rp 140,000
2.4 Benang 10 Glg Rp 10,000 Rp 100,000
Sub Total 3) Rp 640,000
Uraian Volume Satuan Harga Satuan (Rp) Jumlah Total (Rp)

3. UPAH
3.1 Pekerja 321 OH Rp 120,000 Rp 38,537,502.05
3.2 Tukang 146 OH Rp 140,000 Rp 20,507,530.15
3.3 Kepala Tukang 14.66 OH Rp 160,000 Rp 2,345,675.85

Sub Total 4) Rp 61,390,708


Total Biaya Rp 360,444,410
Dibulatkan Rp 360,444,000
RENCANA ANGGARAN BIAYA (RAB)

Bidang : Bidang Pelaksanaan Pembangunan Desa Program : Dana Desa


Kegiatan : GEDUNG PKBM BUMDES 2023 Jenis Kegiatan : Pemb Gedung Serbaguna
Waktu Pelaksanaa: 90 hari Volume : 1 Unit

Kebutuhan Bahan,
Uraian Volume koefisien Satuan Harga Satuan (Rp) Jumlah Total (Rp)
Alat & Upah

I BIAYA UMUM
1 Biaya Uitzet 2 LS Rp 600,000.00 1,200,000.00
2 Insentif Petugas Penyusunan Desain Gambar dan RAB Fiskk 1 PAKET Rp 7,200,000.00 7,200,000.00
1. BAHAN
kolom beton bertulang 35x35cm + bekisting
Beton 10.78
Semen Portland 384.000 4,139.52 Kg Rp 1,740.20 7,203,592.70
Pasir Beton 0.692 7.46 M3 Rp 280,000.00 2,088,732.80
Kerikil (maks 30 mm) 1.039 11.20 M3 Rp 270,000.00 3,024,113.40
Air 215.000 2,317.70 Liter Rp 2,000.00 4,635,400.00
Pembesian Kolom Uk. 35x35cm 1,228.92
Besi Beton (Polos/Ulir) 1.050 1,290.37 Kg Rp 14,000.00 18,065,124.00
Kawat Beton 0.020 24.58 Kg Rp 21,000.00 516,146.40
Bekisting Kolom Uk. 35x35cm 71.50
Kayu Kelas III 0.045 3.22 M3 Rp 2,500,000.00 8,043,750.00
Paku 5-10 cm 0.300 21.45 Kg Rp 13,000.00 278,850.00
Minyak Bekisting 0.100 7.15 Liter Rp 9,000.00 64,350.00
-
Ring Balok beton bertulang 25x35cm + bekisting -
­Beton 12.51
Semen Portland 384.000 4,804.80 Kg Rp 1,740.20 8,361,312.96
Pasir Beton 0.692 8.66 M3 Rp 280,000.00 2,424,422.00
Kerikil (maks 30 mm) 1.039 13.00 M3 Rp 270,000.00 3,510,131.63
Air 215.000 2,690.19 Liter Rp 2,000.00 5,380,375.00
­Pembesian Balok Uk. 25x 35 cm 2,027.03
Besi Beton (Polos/Ulir) 1.050 2,128.38 Kg Rp 14,000.00 29,797,267.50
Kawat Beton 0.020 40.54 Kg Rp 21,000.00 851,350.50
­Bekisting BalokUk. 25x 35 cm 67.93
Kayu Kelas III 0.040 2.72 M3 Rp 2,500,000.00 6,792,500.00
Paku 5-10 cm 0.400 27.17 Kg Rp 13,000.00 353,210.00
Minyak Bekisting 0.200 13.59 Liter Rp 9,000.00 122,265.00
Balok Kayu Kelas II 0.018 1.22 M3 Rp 3,700,000.00 4,523,805.00
Plywood tebal 9mm 0.350 23.77 Lbr Rp 68,200.00 1,621,369.75
Dolken Kayu Ø 8 -10/400 cm 2.000 135.85 Batang Rp 3,500.00 475,475.00
-
Pek. Balok Pinggang Beton Bertulang Uk. 8/20 cm + bekisting -
­Beton 1.18
Semen Portland 326.000 385.98 Kg Rp 1,740.20 671,689.36
Pasir Beton 0.760 0.90 M3 Rp 280,000.00 251,955.20
Kerikil (maks 30 mm) 1.029 1.22 M3 Rp 270,000.00 328,950.72
Air 215.000 254.56 Liter Rp 2,000.00 509,120.00
Pembesian Balok Pinggang Uk. 8/20 cm 198.91
Besi Beton (Polos/Ulir) 1.050 20.89 Kg Rp 14,000.00 292,400.64
Kawat Beton 0.020 0.40 Kg Rp 21,000.00 8,354.30

Bekisting Balok Pinggang Uk. 8/20 cm 17.76


Kayu Kelas III 0.040 0.71 M3 Rp 2,500,000.00 1,776,000.00
Paku 5-10 cm 0.400 7.10 Kg Rp 13,000.00 92,352.00
Minyak Bekisting 0.200 3.55 Liter Rp 9,000.00 31,968.00
Balok Kayu Kelas II 0.018 0.32 M3 Rp 3,700,000.00 1,182,816.00
Plywood tebal 9mm 0.350 6.22 Lbr Rp 68,200.00 423,931.20
Dolken Kayu Ø 8 -10/400 cm 2.000 35.52 Batang Rp 3,500.00 124,320.00
-
PEKERJAAN PASANGAN DAN PLESTERAN -
Pasangan Dinding Bata 1 PC : 4 PP LT 2 288.96 -
Bata Merah 70.000 20,227.09 Bh Rp 1,200.00 24,272,505.60
Semen Portlan 11.500 3,323.02 Kg Rp 1,740.20 5,782,722.19
Pasir Pasang 0.043 12.43 m3 Rp 280,000.00 3,479,059.14
-
Pasang rangka atap baja ringan 363.51 363.51 m2 Rp 226,634.00 82,382,761.49
-
Pek Atap Genteng Metal 363.506 -
Genteng metal 1.02 370.776 Bh Rp 160,000.00 59,324,137.93
Paku 5-10 cm 0.20 72.701 Kg Rp 13,000.00 945,114.94

Sub Total 1)
Kebutuhan Bahan,
Uraian Volume koefisien Satuan Harga Satuan (Rp) Jumlah Total (Rp)
Alat & Upah

2. ALAT
2.1 Papan Nama Proyek 1 Ls Rp 400,000.00 Rp 400,000.00
2.3 Timba Cor 7 Bh Rp 20,000.00 Rp 140,000.00
2.4 Benang 10 Glg Rp 10,000.00 Rp 100,000.00
Sub Total 2) Rp 640,000.00
3. UPAH
kolom beton bertulang 35x35cm + bekisting 10.78
Beton
3.1 Pekerja 1.650 17.787 OH Rp 120,000.00 Rp 2,134,440.00
3.2 Tukang 0.275 2.965 OH Rp 140,000.00 Rp 415,030.00
3.3 Kepala Tukang 0.028 0.302 OH Rp 160,000.00 Rp 48,294.40

Pembesian Kolom Uk. 35x35cm 1,228.92


Pekerja 0.008 9.831 OH Rp 120,000.00 Rp 1,179,763.20
Tukang 0.008 9.831 OH Rp 140,000.00 Rp 1,376,390.40
Kepala Tukang 0.0008 0.983 OH Rp 160,000.00 Rp 157,301.76

Bekisting Kolom Uk. 35x35cm 71.50


Pekerja 0.520 37.180 OH Rp 120,000.00 Rp 4,461,600.00
Tukang 0.260 18.590 OH Rp 140,000.00 Rp 2,602,600.00
Kepala Tukang 0.026 1.859 OH Rp 160,000.00 Rp 297,440.00

Ring Balok beton bertulang 25x35cm + bekisting

­Beton 12.51
Pekerja 1.650 20.646 OH Rp 120,000.00 Rp 2,477,475.00
Tukang 0.275 3.441 OH Rp 140,000.00 Rp 481,731.25
Kepala Tukang 0.028 0.350 OH Rp 160,000.00 Rp 56,056.00

­Pembesian Balok Uk. 25x 35 cm 2,027.03


Pekerja 0.008 16.216 OH Rp 120,000.00 Rp 1,945,944.00
Tukang 0.008 16.216 OH Rp 140,000.00 Rp 2,270,268.00
Kepala Tukang 0.001 1.622 OH Rp 160,000.00 Rp 259,459.20

­Bekisting BalokUk. 25x 35 cm 67.93


Pekerja 0.660 44.831 OH Rp 120,000.00 Rp 5,379,660.00
Tukang 0.330 22.415 OH Rp 140,000.00 Rp 3,138,135.00
Kepala Tukang 0.033 2.242 OH Rp 160,000.00 Rp 358,644.00

Pek. Balok Pinggang Beton Bertulang Uk. 8/20 cm + bekisting


­Beton 1.18
Pekerja 1.650 1.954 OH Rp 120,000.00 Rp 234,432.00
Tukang 0.275 0.326 OH Rp 140,000.00 Rp 45,584.00
Kepala Tukang 0.028 0.033 OH Rp 160,000.00 Rp 5,304.32

Pembesian Balok Pinggang Uk. 8/20 cm 198.91


Pekerja 0.008 1.591 OH Rp 120,000.00 Rp 190,955.52
Tukang 0.008 1.591 OH Rp 140,000.00 Rp 222,781.44
Kepala Tukang 0.001 0.159 OH Rp 160,000.00 Rp 25,460.74

Bekisting Balok Pinggang Uk. 8/20 cm 17.76


Pekerja 0.660 11.722 OH Rp 120,000.00 Rp 1,406,592.00
Tukang 0.330 5.861 OH Rp 140,000.00 Rp 820,512.00
Kepala Tukang 0.033 0.586 OH Rp 160,000.00 Rp 93,772.80

PEKERJAAN PASANGAN DAN PLESTERAN


Pasangan Dinding Bata 1 PC : 4 PP LT 2 288.96
Pekerja 0.300 86.688 OH Rp 120,000.00 Rp 10,402,502.40
Tukang 0.100 28.896 OH Rp 140,000.00 Rp 4,045,417.60
Kepala Tukang 0.010 2.890 OH Rp 160,000.00 Rp 462,333.44

Pasang rangka atap baja ringan 363.51


Pek Atap Genteng Metal 363.51
Pekerja 0.200 72.701 OH Rp 120,000.00 Rp 8,724,137.93
Tukang 0.100 36.351 OH Rp 140,000.00 Rp 5,089,080.46
Kepala Tukang 0.010 3.635 OH Rp 160,000.00 Rp 581,609.20

Sub Total 3)
Total Biaya Rp 361,084,410
Dibulatkan Rp 361,084,410
RENCANA ANGGARAN BIAYA (RAB)

NAMA KEGIATAN PROGRAM DANA DESA


JENIS GEDUNG PKBM BUMDES 2023
VOLUME 1 Unit
LOKASI DUSUN SIMPATIG
DESA HAMPARAN PUGU
KECAMATAN AIR HANGAT BARAT
ANGGARAN Rp 163,882,000.00

Harga Satuan Jumlah Harga


No URAIAN Volume Sat
(Rp) (Rp)

I PEKERJAAN PENDAHULUAN
1 Biaya Uitzet 2.00 LS 600,000.00 1,200,000.00
Insentif Petugas Penyusun Desain Gambar dan
2 1.00 LS 7,200,000.00 7,200,000.00
RAB Fisik
Sub Jumlah I 8,400,000.00
II BAHAN
1 Tanah Urug 172.80 m3 135,600.00 23,431,680.00
2 Pasir Pasang 48.11 m3 280,000.00 13,469,568.00
3 Batu 107.14 m3 350,000.00 37,497,600.00
4 Semen porland 15,411.46 kg 1,740.20 26,819,015.73

Sub Jumlah II 101,217,863.73


III ALAT
1 Selang Timbang 10.00 m 4,000.00 40,000.00
2 Gerobak Dorong 2.00 bh 500,000.00 1,000,000.00
3 Benang 2.00 Roll 7,500.00 15,000.00
4 Cangkul 2.00 bh 60,000.00 120,000.00
5 Sekop 2.00 bh 60,000.00 120,000.00
6 Ember 10.00 bh 10,000.00 100,000.00
7 Kuas 4" 1.00 bh 25,000.00 25,000.00
8 Papan Nama 1.00 bh 400,000.00 400,000.00
Sub Jumlah III 1,820,000.00
IV UPAH
1 Pekerja 216.72 Oh 120,000.00 26,006,400.00
2 Tukang 79.56 Oh 140,000.00 11,138,400.00
3 Tenaga Langsir 153.00 Oh 100,000.00 15,300,000.00
Sub Jumlah IV 52,444,800.00
JUMLAH 163,882,663.73
DIBULATKAN 163,882,000.00
PPN
PPH PASAL 22
Operasional TPK
PAJAK GALIAN C
TOTAL ANGGARAN 163,882,663.73
DIBULATKAN 163,882,000.00

mengetahui : Hamparan Pugu, ..... - Februari - 2023


Kepala Desa Ketua Tim Penyusun RKP Desa

......................... .........................
RENCANA ANGGARAN BIAYA (RAB)
DESA : ……………….…………………………………..……………………...
KECAMATAN : …………………………………………...…… No.RAB : ……...……..………………
KABUPATEN : …………………………………………...…… Bidang : ……...……..………………
PROVINSI : …………………………..……………….. Kegiatan : ……...……..………………

Harga Satuan Jumlah Total


URAIAN Volume Satuan Jumlah
Rp Rp
a b c d e=bxd f
1. BAHAN
1.1
1.2
1.3
1.4
1….
Sub Total 1) Rp - Rp -
2. ALAT
2.1
2.2
2.3
2.4
2. …
Sub Total 2) Rp - Rp -
3. UPAH
3.1
3.2
3.3
3. …
Sub Total 3 ) Rp - Rp -
Total Biaya
Keterangan :

Kategori Biaya
I-a : Pembelian bahan hasil tenaga manusia
I-b : Pembelian bahan hasil industri
II-a : Pembelian alat tangan
II-b : Pembelian / penyewaan alat mesin
III-a : Pembayaran tenaga kerja untuk konstruksi
III-b : Pembayaran tenaga untuk pengumpulan bahan

mengetahui : Hamparan Pugu, ..... - Februari - 2023


Kepala Desa Ketua Tim Penyusun RKP Desa

......................... .........................
KABUPATEN JOMBANG
KECAMATAN AIR HANGAT BARAT
DESA HAMPARAN PUGU
KEGIATAN : PROGRAM DANA DESA
PEMBANGUNAN JALAN USAHA TANI
PEMBANGUNAN SALURAN IRIGASI
PEMBANGUNAN JALAN HOTMIX
LOKASI : DUSUN WISATA 120M'
DUSUN KEDUNGWESI 246 M'
556.50 X 2.50
DESA HAMPARAN PUGU 566 x 2,50
TAHUN ANGGARAN : 2017
KODE DESA #N/A
DANA FISIK : 95,870,000
KEPALA DESA : HJ. SRI WIJAYATI
KETUA BPD : Drs. SUGENG PRASETYO
KETUA LPMD : MUNAWAR. SPd
KETUA TPD : MUNAWAR. SPd
SEKRETARIS TPD : ACH. ZAINURI
KAUR PERENCANAAN : SUROTO
PENGADAAN BARANG : HADI SUCIPTO
PENERIMA BARANG : SUPARNO
PELAKSANA KEG : ACHMAD WAKID
KASIE KESEJAHTERAAN: AHMAD DANI
SEKRETARIS DESA MACPOET

Dibuat pada tanggal : 4/28/2017

CAMAT SUMOBITO 2 Mei 2017

Drs. ANWAR MKp


NIP. 197104181992011004

KASI PMD KEC. SUMOBITO


SAMSUL HUDA
RENCANA ANGGARAN BIAYA (RAB)

NAMA KEGIATAN PROGRAM DANA DESA


JENIS PEMBANGUNAN JALAN USAHA TANI
VOLUME 120M'
LOKASI DUSUN WISATA
DESA HAMPARAN PUGU
KECAMATAN AIR HANGAT BARAT
ANGGARAN Rp 157,462,000

Volume Kebutuhan Bahan, Alat &


Harga Satuan Jumlah Harga
NO Jenis Pekerjaan Pekerjaan Koef. Analisa Upah
Jumlah Sat. Jumlah Sat. (Rp.) (Rp.)
I PEKERJAAN PENDAHULUAN
1. A T K 1.00 LS 1.00 LS 300,000.00 300,000.00
3 Biaya Uitzet 2.00 LS 2.00 kl 400,000.00 800,000.00
4 Insentif Petugas Penyusun RAB Fisik 1.00 LS 1.00 kl 2,000,000.00 2,000,000.00
5 Biayan Pelaporan dan Dokumentasi 1.00 LS 1.00 kl 300,000.00 300,000.00
6 Pemasangan Papan Kegiatan 1.00 LS 1.00 LS 400,000.00 400,000.00
Sub Jumlah I 3,800,000.00
II 1. BAHAN
1 Galian Tanah 28.80 m3
Tanah urug
2 Timbunan Tanah 144.00 m3
Tanah Urug 1.200 172.80 M3 135,600.00 23,431,680.00
3 Pasangan batu kali 1 PC : 4 Ps 89.28 m3
Batu 1.200 107.14 m3 350,000.00 37,497,600.00
Semen porland 163.000 14,552.64 kg 1,740.20 25,324,504.13
Pasir pasang 0.520 46.43 M3 280,000.00 12,999,168.00
4 Plester siaran 1 : 2 84.00 m2
Semen porland 10.224 858.82 kg 1,740.20 1,494,511.60
Pasir pasang 0.020 1.68 M3 280,000.00 470,400.00
Sub Jumlah II 101,217,863.73
II UPAH
1 Galian Tanah 28.80 M3
Pekerja 0.750 21.60 Org/hr 120,000.00 2,592,000.00

2 Timbunan Tanah 144.00 M3


Pekerja 0.250 36.00 Org/hr 120,000.00 4,320,000.00

3 Pasangan batu kali 1 PC : 4 Ps 89.28 M3


Pekerja 1.500 133.92 Org/hr 120,000.00 16,070,400.00
Tukang batu 0.750 66.96 Org/hr 140,000.00 9,374,400.00

4 Plester siaran 1 : 2 84.00 M2


Pekerja 0.300 25.20 Org/hr 120,000.00 3,024,000.00
Tukang batu 0.150 12.60 Org/hr 140,000.00 1,764,000.00
Tenaga Langsir 153.00 Org/hr 100,000.00 15,300,000.00

Sub Jumlah III 52,444,800.00

JUMLAH 157,462,663.73
DIBULATKAN 157,462,000.00
SUDAH TERMASUK PPN PPH

Hamparan Pugu, ..... - Februari - 2023


Diperiksa oleh : KAUR PERENCANAAN
KASIE KESEJAHTERAAN

….... …........

Menyetujui Mengetahui
SEKRETARIS DESA KEPALA DESA

….................. …..................................
LAMPIRAN: PERATURAN BUPATI KERINCI NOMOR 9 TA.HUN 2022 TENTANG TILNTANG STANDAR
HARGA BARANG/JASA BAG! PEMERINTAH DESA DALAM KABUPATEN KERINCI TAHUN 2022

NO URAIAN SATUAN BIAYA


A B C D

1 Honorarium Penanggungjawab Pengelolaan Keuangan Desa OB 250,000


2 Honorarium Pengelola Keuangan Desa
A. OB 200,000
B. OB 175,000
C. OB 150,000
3 Honorarium Tim Pelaksana Kegiatan
A. Penanggungjawab
Pagu Rp 10.000.000,- s/d 50.000.000,- OB 200,000
Pagu Rp 50.000.000,- s/d 100.000.000,- OB 250,000
Pagu Rp 100.000.000,- s/d 200.000.000,- OB 300,000
Pagu Rp 200.000.000,- keatas OB 350,000
B. Ketua
Pagu Rp 10.000.000,- s/d 50.000.000,- OB 100,000
Pagu Rp 50.000.000,- s/d 100.000.000,- OB 150,000
Pagu Rp 100.000.000,- s/d 200.000.000,- OB 200,000
Pagu Rp 200.000.000,- keatas OB 250,000
C. Sekretaris
Pagu Rp 10.000.000,- s/d 50.000.000,- OB 90,000
Pagu Rp 50.000.000,- s/d 100.000.000,- OB 100,000
Pagu Rp 100.000.000,- s/ci 200.000.000,- OB 150,000
Pagu Rp 200.000.000,- keatas OB 200,000
d. Anggota
Pagu Rp 10.000.000,- s/d 50.000.000,- OB 60,000
Pagu Rp 50.000.000,- s/d 100.000.000,- OB 85,000
Pagu Rp 100.000.000,- s/c1200.000.000,- OB 100,000
Pagu Rp 200.000.000,- keatas OB 150,000
Biaya Operasional Pemilihan Kepala Desa
4. (Honor Panitia, Cetak Surat Suara, Biaya Rapat, Paket 25,000,000
biaya pengamanan, dan keperluan lainnya)
5 Honorarium Operator Profil Desa dan Sipades OB 250,000
6 Honorarium Operator Siskeudes OB 350,000
7 Honorarium Pengurus Lembaga Desa
a. Lembaga Keagamaan
Ketua OB 100,000
Wakil Ketua OB 90,000
Sekretaris OB 80,000
Bendahara OB 70,000
b. Lembaga Kepemudaan
Ketua OB 100,000
Wakil Ketua OB 90,000
Sekretaris OB 80,000
Bendahara OB 70,000
c. Lembaga Adat
Ketua OB 100,000
Wakil Ketua OB 90,000
Sekretaris OB 80,000
Bendahara OB 70,000
d. Lembaga PKK Desa
Ketua OB 100,000
Wakil Ketua OB 90,000
Sekretaris OB 80,000
Bendahara OB 70,000
Ketua Pokja OB 60,000
Ketua Posyandu OB 60,000
8 Insentif Guru PAUD Desa OB 250,000
9 Honorarium Kader Pembangunan Manusia, OB 200,000
Honorarium Kader Teknis KEGIATAN 100,000
Honorarium Posyantekdes :
Ketua merangkap Anggota kegiatan 100,000
Anggota kegiatan 80,000
10 Insentif Guru Ngaji OB 250,000
Insentif Imam Masjid OB 250,000
11 Insentif Penceramah/Da'i OB 150,000
12 Insentif Gharim Masjid atau Bilal OB 150,000
13 BPJS Kesehatan Kepala Desa & Perangkat Desa OB 67,350
2 % dari pagu
14 Insentif Petugas Penyusun RAB Fisik PAKET kegiatan.
15 BPJS Ketenagakerjaan OB 13,100
Honorarium Narasumber untuk kegiatan sosialisasi,
16 pelatihan, dan kegiatan sejenisnya
a. Pejabat Eselon II/Kapolres/Dandim OJ 750,000
b. Pejabat Eselon III/Gol. IV/Kapolsek/Koramil OJ 650,000
c. Pejabat Eselon FV/Gol.
III/Babinsa/Babinkantibmas OJ 500,000
d. Pakar/Praktisi/Pembicara Khusus /Profesional OJ 700,000
e.Pejabat Pembuka Acara Tingkat Desa (Kepala
Dinas/Camat/Pejabat Lainnya dengan perrnintaan tertulis
dan i Kepala Desa) OK 500,000
Catatan : Narasumber kegiatan disesuaikan dengan kebutuhan kegiatan yang
dilaksanakan oleh Desa, dengan permintaan tertulisdari Kepala Desa
17 Makan dan snack kegiatan, pelatihan, sosialisasi, dan sebagainya :
a Makan bungkus 25,000
b Snack kotak 10,000
18 Pemeliharaan dan perawatan Kendaraan Operasional Desa
a. Servis unit/ tahun 1,000,000
b. Pajak Kendaraan unit! Tahun 300,000
19 Pengembangan dan pengelolaan Website Desa

a. Pendaftaran domain iclesa.iddi Kementerian Kominfo).


Catatan: Domain harus didaftarkan langsung oleh Desa ke
layaan Kementerian. Kominfo sesuai ketentuan perundang-
undangan yang berlaku. ls 100,000
b. Server dan Hosting (sesuai rekomendasi dari Kementerian
Komunikasi dan Informatika RI) per tahun 4,500,000
c. Security Maintance dan Domain Name System Security
Extensions (sesuai rekomendasi dari Kementerian
Komunikasi dan Informatika) per tahun 5,200,000
d. Honorarium Pengelola Website Desa
Penanggungjawab (Kepala Desa) OB 300,000
Operator Website Desa ((Sesuai SK dan i Kepala Desa) OB 250,000
e. Pengadaan Smartphone, minimal RAM 3 GB unit 2,000,000
f. Paket internet OB 100,000

Catatan : 1. Menyediakan menu profil, berita, pengumuman


clan layanan online khusus untuk warga desa seperti
layanan Surat Perpanjangan KTP, surat Keterangan
Pembuatan KTP Bagi Pemula, Surat Keterangan Pindah,
Surat Keterangan Datang, Surat Keterangan Lahir, Surat
Keterangan Kematian, Perubahan. Data KK, Surat
Keterangan Domisili, Surat Keterangan Riwayat Tan.ah, dan
sebagainya yang dapat diakses secara online oleh seluruh
warga desa.
2. Website harus memiliki database warga
3. Menyediakan data statistik kependudukan, data geografis
desa, dan sebagainya
yang dapat diinput oleh operator desa
4. Pihak pengembang web bertanggungjawab penuh
terhadap keamanan web desa
(web security)
20 Pengadaan kendaraan dinas roda 2 (dua) unit 31,000,000
II. STANDAR UPAH
Kecamatan Air Hangat Barat
Pekeria Hok Rp120,000.00
Tukang Hok Rp140,000.00
Kepala Tukang Hok Rp160,000.00
Catatan : Upah Langsir dapat dianggarkan apdbila lokasi pelaksanaan kegiatan
pembangunan tidak terjangkau oleh kendaraan
I. HARGA SATUAN DASAR BAHAN DAN MATERIAL
GAMBAR DESAIN KEGIATAN JALAN USAHA TANI

GAMBAR RENCANA

KABUPATEN
KERINCI
0,25 Plesteran tebal 1,5 cm, 1Pc : 3Ps KECAMATAN

0,10
0,00 ±
AIR HANGAT BARAT
DESA
HAMPARAN PUGU
JENIS PRASARANA
JALAN USAHA TANI
Pas. Batu kali 1Pc : 4Ps, Siar 1Pc : 2Ps LOKASI
DUSUN WISATA
0,60 – JUDUL GAMBAR
GAMBAR DESAIN
Urugan psir Digambar Oleh
0.90-

1.00-
Pelaksana Kegiatan
(Kader Teknik)
0,40
Diperiksa dan Disetujui oleh :
Dinas/Instansi terkait dan/atau
Tenaga Profesional
(jika tersedia)

Lembar…..Dari…..Lembar
Catatan : Gambar dibuat secara manual
PERHITUNGAN VOLUME PEKERJAAN

KEGIATAN : PROGRAM DANA DESA VOL : 7mx2m


PROGRAM DANA DESA VOL : 630 m'
LOKASI : DUSUN WISATA
DESA HAMPARAN PUGU
KECAMATAN AIR HANGAT BARAT
TAHUN ANGGARAN : 2017

NO SKETSA / GAMBAR PERHITUNGAN VOLUME PEKERJAAN VOLUME SAT.


I PROGRAM DANA DESA
1,20 0,25 7,00 0,25 1,20
A JEMBATAN
0,40 1,20 0,40 0,40 1,40 1,40 1,40 1,40 1,40 0,40
1. Galian tanah
0,80 +
2 x (2,20 x 1,19 x 0,90) 4.71 m3
0,00 ±
0,20 –
0,60 –
2. Urugan pasir pasang
0,80 –
2 x (2,20 x 1,19 x 0,10) 0.52 m3
1,70 – 3. Pasangan batu kali, 1Pc : 4Ps
2,50 –
2,60 –
2 x ((2,20x1,99x0,80)) + (1,64/2x1,70x2) - (0,25x0,80x2)) 9.39 m3
0,99
2,20 4. Siaran, 1Pc : 2Ps
"Pipa Galvanis Ø 3
Kolom 15/20 1,19
2 x (2 x 0,90) 3.60 m2
Plat lantai
Gelagar 20/40 5. Tulangan
Balok tumpu 20/25
Pas. Batu kali 1Pc:4Ps, Siar 1Pc:2Ps
- Balok tumpu 20/25 :
Urugan pasir pasang Beugle Ø 8 = 2x0,90x((200/15)+1)x8^2x0,006165 10.18 kg
Tul pokok Ø 12 = 2x6x2,00x12^2x0,006165 21.31 kg
2,00
- Balok gelagar 20/40 :
Beugle Ø 8 = 2x1,20x((750/15)+1)x8^2x0,006165 48.29 kg
Tul pokok D 16 = 2x6x7,50x16^2x0,006165 142.04 kg
Tul kuda² D 16 = 2x1x7,90x16^2x0,006165 24.94 kg
D16-200
D16-200 - Plat Lantai jembatan :
D16-200
Tul bagi D 12 = 2x7,50x((200/10)+1)x12^2x0,006165 279.64 kg
D12-100
D12-100

Tul pokok D 16 = 2x2,00x((750/20)+1)x16^2x0,006165 243.05 kg


8,30

7,50

Tul kuda² D 16 = 2x2,20x((750/20)+1)x16^2x0,006165 267.35 kg


A A 6. Acuan Untuk Beton Struktur
- Acuan untuk Balok tumpu 20/25 :
2 x (2,00 x 0,20) 0.80 m2
- Acuan untuk Balok gelagar 20/40 :
2 x ((7,00 x 0,40 x 2)+(7,00 x 0,20)) 14.00 m2
- Acuan untuk Plat Lantai jembatan :
Acuan bag. bawah = 2,00 x 7,00 14.00 m2
DENAH
Acuan bag. samping = 2 x (7,50 x 0,20) 3.00 m2
Total 31.80 m2
0,40 7. Spesi beton 1:2:3
2,00 - Balok tumpu 20/25 :
D16 - 200 2 x (2,00 x 0,20 x 0,25) 0.20 m3
D16 - 100 D16 - 100
- Balok gelagar 20/40 :

0,2
0
2 x (7,50 x 0,20 x 0,40) 1.20 m3
D12 - 100 D16 - 100 D16 - 200
- Plat Lantai jembatan :
DETAIL PENULANGAN PLAT LANTAI 2,00 x 7,50 x 0,20 3.00 m3
Total 4.40 m3
B LEUNENG
1,50 1. Pasangan batu kali, 1Pc : 4Ps
7,50 0,20 4 x (0,40 X 1,20 X 0,80) 1.54 m3
Tul kuda -kuda D16 2. Siaran, 1Pc : 2Ps
4 x (1,00 x 0,60 x 2) 4.80 m2

0,40
Tul pokok 6 D16
3. Plesteran, 1Pc : 3Ps
Beugle Ø 8 - 150 4 x ((0,40 x 2,80)+(0,10 x 3,60 x 2)) 7.36 m2
DETAIL PENULANGAN GELAGAR 20/40 4. Tulangan
- Kolom 15/20 :
Beugle Ø 8 = 12x0,70x((80/15)+1)x8^2x0,006165 20.99 kg
0,20 0,15 Tul pokok Ø 12 = 12x4x0,80x12^2x0,006165 34.09 kg
Total 55.08 kg
5. Acuan Untuk Beton Struktur
0,25

Tul pokok 4Ø12 6.72 m2

0,2
Tul pokok 4Ø12 12 x (0,80 x 0,70)

0
Beugle Ø 8 - 150 Beugle Ø 8 - 150 7. Spesi beton 1:2:3
DETAIL PENULANGAN BALOK TUMPU 20/25 DETAIL PENULANGAN KOLOM 15/20 - Kolom 15/20 :
12 x (0,80 x 0,15 x 0,20) 0.29 m3
8. Pasang pipa besi galvanis D = 3"
4 x 7,00 28.00 m'
PERHITUNGAN VOLUME PEKERJAAN

II PEMBANGUNAN TEMBOK PENAHAN JALAN (TPJ)


PANJANG = 120 M'
1. Galian Tanah
(0,20 x 0,60 x 120)*2 28.80 m3
2. Timbunan Tanah
2 x 0,60 x 120 144.00 m3
3. Pasangan batu kali 1 PC : 4 Ps 89.28 M3
0,30 Plesteran tebal 1,5 cm, 1Pc : 3Ps Pondasi (0,60x0,20x120)x2 28.80

0,10
Tembok ((0,60+0,25)/2x0.60x120)x2 60.48
0,00 ± 4 Plester siaran 1 : 2
(0,35x120)x2 84.00 m2
5 Plesteran ban-banan ! : 2
(030+.10)x250 100.00 m2

Pas. Batu kali 1Pc : 4Ps, Siar 1Pc : 2Ps

0.70 –

Urugan psir
0.90
1.00-

0,40

Jombang, Maret 2019


Diperiksa oleh : Mengetahui KAUR PERENCANAAN
KASIE KESEJAHTERAAN KEPALA DESA
AHMAD DANI HJ. SRI WIJAYATI SUROTO
PERHITUNGAN VOLUME PEKERJAAN

II PEMBANGUNAN SALURAN IRIGASI

1. Galian Tanah
(0,30 x 0,40 x 246)*2 59.04 m3
2. Urugan pasir bawah pondasi
(0,10 x 0,40 x 246)X2 19.68 m3
3. Pasangan batu kali 1 PC : 4 Ps 167.28 M3
Pondasi (0,40x0,20x246)X2 39.36
0,25
Tembok ((0,40+0,25)/2x0.80x246)X2 127.92
0,00 4 Plester siaran 1 : 2
(0,70x246)X2 344.40 m2
5 Plesteran ban-banan ! : 2
((025+.10)x246)X2 172.20 m2

0,80

1,00
1,10

0.40
0,40 1,20

Jombang, Maret 2019


Diperiksa oleh : Mengetahui KAUR PERENCANAAN
KASIE KESEJAHTERAAN KEPALA DESA
AHMAD DANI HJ. SRI WIJAYATI SUROTO
ANALISA HARGA SNI 2008
1 1 m3 Galian Untuk Tanah Biasa sedalam 1 m
Upah An. SNI ( Revisi ) 6.1.1
0.750 Oh Pekerja @ Rp. 120,000.00 = Rp. 90,000.00
0.025 Oh Mandor @ Rp. = Rp. -
Jumlah = Rp. 90,000.00
2 1 m3 Urugan kembali
Upah An. SNI ( Revisi ) 6.9.1
0.192 Oh Pekerja @ Rp. 120,000.00 = Rp. 23,040.00
0.019 Oh Mandor @ Rp. - = Rp. -
Jumlah = Rp. 23,040.00
3 1 m3 Urugan Tanah
Bahan An. SNI ( Revisi ) 6.15
1.200 m3 Tanah Urug @ Rp. 135,600.00 = Rp. 162,720.00
Jumlah = 162,720.00
Upah An. SNI ( Revisi ) 6.11.2
0.250 Oh Pekerja @ Rp. 120,000.00 = Rp. 30,000.00
0.0250 Oh Mandor @ Rp. - = Rp. -
= Rp. 30,000.00
Total Upah dan Bahan = Rp. 192,720.00
4 1 m3 Urugan pasir dengan penyiraman
Bahan An. SNI ( Revisi ) 6.11.1
1.200 m3 Pasir urug @ Rp. 158,200.00 = Rp. 189,840.00
Jumlah = 189,840.00
Upah An. SNI ( Revisi ) 6.11.2
0.300 Oh Pekerja @ Rp. 120,000.00 = Rp. 36,000.00
0.0100 Oh Mandor @ Rp. - = Rp. -
= Rp. 36,000.00
Total Upah dan Bahan = Rp. 225,840.00
5 1 m3 Urug Pasir
Bahan An. SNI ( Revisi ) 6.15.1
1.200 m3 Sirtu @ Rp. 158,200.00 = Rp. 189,840.00
Jumlah = Rp. 189,840.00
Upah An. SNI ( Revisi ) 6.15.2
0.250 Oh Pekerja @ Rp. 120,000.00 = Rp. 30,000.00
0.025 Oh Mandor @ Rp. - = Rp. -
= Rp. 30,000.00
Total Upah dan Bahan = Rp. 219,840.00
6 1 m3 Pasang pondasi batu kosong
Bahan An. SNI ( Revisi ) 6.14.1
1.200 m3 Batu belah ( 15/20 ) @ Rp. 350,000.00 = Rp. 420,000.000
Jumlah = Rp. 420,000.000
Upah An. SNI ( Revisi ) 6.14.2
0.780 Oh Pekerja @ Rp. 120,000.00 = Rp. 93,600.000
0.390 Oh Tukang batu @ Rp. 140,000.00 = Rp. 54,600.000
0.039 Oh Kepala tukang @ Rp. - = Rp. -
0.039 Oh Mandor @ Rp. - = Rp. -
Jumlah = Rp. 148,200.000
Total harga = Rp. 568,200.000
7 1 m3 Pasang pondasi batu kali 1 Pc : 4 Ps
Bahan An. SNI ( Revisi ) 6.7.1
1.200 m3 Batu @ Rp. 350,000.00 = Rp. 420,000.000
163.000 Kg Semen porland @ Rp. 1,740.20 = Rp. 283,652.600
0.520 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 145,600.000
Jumlah = Rp. 849,252.600

Upah An. SNI ( Revisi ) 6.7.2


1.500 Oh Pekerja @ Rp. 120,000.00 = Rp. 180,000.000
0.750 Oh Tukang batu @ Rp. 140,000.00 = Rp. 105,000.000
0.075 Oh Kepala tukang @ Rp. - = Rp. -
0.075 Oh Mandor @ Rp. - = Rp. -
Jumlah = Rp. 285,000.000
Total harga = Rp. 1,134,252.600
8 1m3 Membuat beton tumbuk mutu K 125
Bahan An. SNI ( Revisi ) 6.4.1
276.000 Kg Semen portland @ Rp. 1,740.20 = Rp. 480,295.200
0.828 m3 Pasir beton @ Rp. 280,000.00 = Rp. 231,840.000
1.012 m3 Koral beton @ Rp. 250,000.00 = Rp. 253,000.000
= Rp. 965,135.200
Upah An. SNI ( Revisi ) 6.4.2
1.650 Oh Pekerja @ Rp. 120,000.00 = Rp. 198,000.000
0.275 Oh Tukang batu @ Rp. 140,000.00 = Rp. 38,500.000
0.028 Oh Kepala tukang @ Rp. - = Rp. -
0.080 Oh Mandor @ Rp. - = Rp. -
Jumlah = Rp. 236,500.000
Total harga = Rp. 1,201,635.200
9 1 m2 Plesteran, 1 Pc : 4 Ps, tebal 15 mm
Bahan An. SNI ( Revisi ) 6.4.1
6.240 Kg Semen portland @ Rp. 1,740.20 = Rp. 10,858.848
0.024 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 6,720.000
Jumlah = Rp. 17,578.848
Upah An. SNI ( Revisi ) 6.4.2
0.300 Oh Pekerja @ Rp. 120,000.00 = Rp. 36,000.000
0.150 Oh Tukang batu @ Rp. 140,000.00 = Rp. 21,000.000
0.015 Oh Kepala tukang @ Rp. - = Rp. -
0.010 Oh Mandor @ Rp. - = Rp. -
Jumlah = Rp. 57,000.000
Total harga = Rp. 74,578.848
10 1 m2 Plesteran, 1 Pc : 8 Ps, tebal 15 mm
Bahan An. SNI ( Revisi ) 6.7.1
3.456 Kg Semen portland @ Rp. 1,740.20 = Rp. 6,014.131
0.029 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 8,120.000
= Rp. 14,134.131
Upah An. SNI ( Revisi ) 6.7.2
0.300 Oh Pekerja @ Rp. 120,000.00 = Rp. 36,000.000
0.150 Oh Tukang batu @ Rp. 140,000.00 = Rp. 21,000.000
0.015 Oh Kepala tukang @ Rp. - = Rp. -
0.010 Oh Mandor @ Rp. - = Rp. -
= Rp. 57,000.000
Total harga = Rp. 71,134.131
11 1 m2 Plesteran, siaran adukan 1 : 2
Bahan An. SNI ( Revisi ) 6.35.1
10.224 Kg Semen portland @ Rp. 1,740.20 = Rp. 17,791.805
0.020 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 5,600.000
Jumlah = Rp. 23,391.805
Upah An. SNI ( Revisi ) 6.35.2
0.300 Oh Pekerja @ Rp. 120,000.00 = Rp. 36,000.000
0.150 Oh Tukang batu @ Rp. 140,000.00 = Rp. 21,000.000
0.015 Oh Kepala tukang @ Rp. = Rp. -
0.015 Oh Mandor @ Rp. = Rp. -
= Rp. 57,000.000
Total harga = Rp. 80,391.805

12 1 m2 Pasang Paving Stone dengan Penebaran pasir pasang pengunci


Bahan An. SNI ( Revisi ) 6.3.1 + 6.11.1
1.000 m2 Paving stone @ Rp. 71,500.00 = Rp. 71,500.000
0.010 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 2,800.000
Jumlah = Rp. 74,300.000
Upah An. SNI ( Revisi ) 6.35.2
0.135 Oh Pekerja @ Rp. 120,000.00 = Rp. 16,200.000
0.065 Oh Tukang batu @ Rp. 140,000.00 = Rp. 9,100.000
0.015 Oh Kepala tukang @ Rp. - = Rp. -
0.015 Oh Mandor @ Rp. - = Rp. -
= Rp. 25,300.000
Total harga = Rp. 99,600.000
13 1 m' Pasang Kanstin beton interlocking dan galian tanah kanstin
Bahan An. SNI ( Revisi ) 6.4.1
2.500 bj Kanstin beton Interlocking @ Rp. 33,000.00 = Rp. 82,500.000
0.001 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 280.000
Jumlah = Rp. 82,780.000
Upah An. SNI ( Revisi ) 6.35.2
0.050 Oh Pekerja @ Rp. 120,000.00 = Rp. 6,000.000
0.050 Oh Tukang batu @ Rp. 140,000.00 = Rp. 7,000.000
0.015 Oh Kepala tukang @ Rp. - = Rp. -
0.015 Oh Mandor @ Rp. - = Rp. -
= Rp. 13,000.000
Total harga = Rp. 95,780.000
14 1 m3 Urug pasir pasang bawah paving
Bahan An. SNI ( Revisi ) 6.11
1.200 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 336,000.000
Jumlah = Rp. 336,000.000
Upah An. SNI ( Revisi ) 6.35.2
0.300 Oh Pekerja @ Rp. 120,000.00 = Rp. 36,000.000
0.000 Oh Tukang batu @ Rp. 140,000.00 = Rp. -
0.015 Oh Kepala tukang @ Rp. - = Rp. -
0.015 Oh Mandor @ Rp. - = Rp. -
= Rp. 36,000.000
Total harga = Rp. 372,000.000
14 1 m' Pasang Uskup block
Bahan An. SNI ( Revisi ) 6.4.1
3.340 bj Uskup @ Rp. 9,350.00 = Rp. 31,229.000
0.001 m3 Pasir pasang @ Rp. 280,000.00 = Rp. 280.000
Jumlah = Rp. 31,509.000
Upah An. SNI ( Revisi ) 6.35.2
0.050 Oh Pekerja @ Rp. 120,000.00 = Rp. 6,000.000
0.050 Oh Tukang batu @ Rp. 140,000.00 = Rp. 7,000.000
0.015 Oh Kepala tukang @ Rp. - = Rp. -
0.015 Oh Mandor @ Rp. - = Rp. -
= Rp. 13,000.000
Total harga = Rp. 44,509.000
HARGA
TOTAL
NO URAIAN PEKERJAAN KODE VOLUME SATUAN SATUAN
(Rp.)
(Rp.)
I BIAYA UMUM
1 Biaya Uitzet 2 LS 600,000.00 1,200,000.00
2 Insentif Petugas Penyusun RAB Fisik 1 PAKET 2,000,000.00 2,000,000.00
3 Pemasangan Papan Kegiatan 1 LS 300,000.00 300,000.00
Sub Jumlah I 3,500,000.00
II PEMBANGUNAN JALAN USAHA TANI
1 Galian Tanah SNI 28.80 m3 90,000.00 2,592,000.00
2 Timbunan Tanah SNI 144.00 m3 192,720.00 27,751,680.00
3 Pasangan batu kali 1 PC : 4 Ps SNI 89.28 m3 1,134,252.60 101,266,072.13
4 Plester siaran 1 : 2 SNI 84.00 m2 80,391.80 6,752,911.60
Sub Jumlah II 138,362,663.73
JUMLAH 141,862,663.73
DIBULATKAN (Rp.) 141,862,000.00

SUDAH TERMASUK PAJAK


RENCANA ANGGARAN BIAYA

Propinsi : Jawa Timur No. RAB :


Kabupaten : Malang Program : P3MD Kemendesa PDTT
Kecamatan : Tajinan Kegiatan : TPT RT. 08 (TPS Sawah)
Desa : Tajinan Volume : 65 m

Volume Harga Total Jumlah


Jumlah Pajak
Uraian Swada Dana Satuan Satuan Swdya+.. Dana Desa
Total (Rp)
ya Desa (Rp) (Rp) (Rp)
BAHAN
1 Batu Gunung 36.0 36.0 m3 250,000 941,000 9,000,000
2 Batu Pecah 2/3 1.0 1.0 m3 250,000 0 250,000
3 Batako 588.0 588.0 bh 4,000 246,000 2,352,000
4 Pasir Pasang 21.0 21.0 m3 165,000 362,300 3,465,000
5 Semen (40 Kg) 134.0 134.0 zak 65,000 910,700 8,710,000
6 Besi Ø6 27.0 27.0 btg 29,000 0 783,000
7 Besi Ø8 56.0 56.0 btg 49,000 287,000 2,744,000
8 Kawat bendrat 6.0 6.0 kg 47,000 0 282,000
Sub Total 1) 0 2,747,000 27,586,000
PERALATAN
1 Selang Timbang 20.0 20.0 m 3,500 70,000
2 Kereta Dorong 1.0 1.0 bh 500,000 500,000
3 Benang 2.0 2.0 Roll 7,500 15,000
4 Ganco 1.0 1.0 bh 75,000 75,000
5 Cangkul 2.0 2.0 bh 60,000 120,000
6 Sekop 2.0 2.0 bh 60,000 120,000
7 Ember 10.0 10.0 bh 10,000 100,000
8 Kuas 4" 1.0 1.0 bh 25,000 25,000
9 Prasasti 1.0 1.0 Ls 350,000 350,000
10 Papan Proyek 1.0 1.0 Ls 150,000 150,000
Sub Total 2) 0 0 1,525,000
UPAH
1 Pekerja 78.0 78.0 OH 65,000 5,070,000
2 Tukang 33.0 33.0 OH 80,000 2,640,000
0 0 7,710,000
OPERASIONAL PK
1 Transport TPK 3.0 0.0 3.0 Org 250,000 750,000
2 Transport Pengawas 1.0 0.0 1.0 Org 250,000 250,000
3 FC + Penggandaan 1.0 0.0 1.0 Ls 73,700 73,700
Sub Total 4) 0 0 1,073,700
TOTAL BIAYA 0 2,747,000 37,894,700

Biaya 37,894,700
Sumber Dana dari Dana Desa Biaya Pajak 2,747,000
Total Biaya (Dana Desa + Pajak) 40,641,700

Tajinan, 2018

Mengetahui / Menyetujui : Dibuat Oleh :


KEPALA DESA Tim Penyusun RKP Desa
Ketua

H. I S B A N D I NGATENO
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Timur No. RAB
Kabupaten : Malang Program
Kecamatan : Tajinan Kegiatan
Desa : Tajinan Volume
VOLUME Satua Harga Satuan Jumlah
URAIAN DPP PPN PPH Psl 22
Total Swadya DD n (Rp) (Rp)
BAHAN
1 Batu Gunung 36.00 36.00 m3 250,000 9,000,000 8,181,800 818,200 122,800
2 Batu Pecah 2/3 1.00 1.00 m3 250,000 250,000 227,200 - -
3 Batako 588.00 588.00 bh 4,000 2,352,000 2,138,100 213,900 32,100
4 Pasir Pasang 21.00 21.00 m3 165,000 3,465,000 3,150,000 315,000 47,300
5 Semen (40 Kg) 134.00 134.00 zak 65,000 8,710,000 7,918,100 791,900 118,800
6 Besi Ø6 27.00 27.00 btg 29,000 783,000 711,800 - -
7 Besi Ø8 56.00 56.00 btg 49,000 2,744,000 2,494,500 249,500 37,500
8 Kawat bendrat 6.00 6.00 kg 47,000 282,000 256,300 - -
Sub Total 1) 27,586,000 25,077,800 2,388,500 358,500
ALAT
1 Selang Timbang 20.00 20.00 m 3,500 70,000 63,600 - -
2 Kereta Dorong 1.00 1.00 bh 500,000 500,000 454,500 - -
3 Benang 2.00 2.00 Roll 7,500 15,000 13,600 - -
4 Ganco 1.00 1.00 bh 75,000 75,000 68,100 - -
5 Cangkul 2.00 2.00 bh 60,000 120,000 109,000 - -
6 Sekop 2.00 2.00 bh 60,000 120,000 109,000 - -
7 Ember 10.00 10.00 bh 10,000 100,000 90,900 - -
8 Kuas 4" 1.00 1.00 bh 25,000 25,000 22,700 - -
9 Prasasti 1.00 1.00 Ls 350,000 350,000 318,100 - -
10 Papan Proyek 1.00 1.00 Ls 150,000 150,000 136,300 - -
Sub Total 2) 1,525,000 1,385,800 - -
UPAH
1 Pekerja 78.00 OH 65,000 5,070,000 - - -
2 Tukang 33.00 OH 80,000 2,640,000 - - -
Sub Total 3) 7,710,000 - - -
OPERASIONAL PK
1 Transport TPK 3.00 Org 250,000 750,000 - - -
2 Transport Pengawas 1.00 Org 250,000 250,000 - - -
3 FC + Penggandaan 1.00 Ls 73,700 73,700 - - -
Sub Total 4) 1,073,700 - - -
JUMLAH TOTAL 37,894,700 26,463,600 2,388,500 358,500

Mengetahui / Menyetujui :
KEPALA DESA

H. I S B A N D I
ANGGARAN BIAYA
:
: P3MD Kemendesa PDTT
: TPT RT. 08 (TPS Sawah)
: 65 m

PPH psl 23 JUMLAH TOTAL

9,941,000 941,000
250,000 -
2,598,000 246,000
3,827,300 362,300
9,620,700 910,700
783,000 -
3,031,000 287,000
282,000 -
0 30,333,000 2,747,000

70,000 -
500,000 -
15,000 -
75,000 -
120,000 -
120,000 -
100,000 -
25,000 -
350,000 -
150,000 -
- 1,525,000 -

5,070,000 -
2,640,000 -
- 7,710,000 -

750,000 -
250,000 -
73,700 -
- 1,073,700 -
- 40,641,700 2,747,000

Tajinan, 2018
Dibuat Oleh :
Tim Penyusun RKP Desa
Ketua

NGATENO
PROGRAM DANA DESA
PEMBANGUNAN JALAN
USAHA TANI
DUSUN WISATA
DESA HAMPARAN PUGU
0,25
KECAMATAN AIR HANGAT
Plesteran tebal 1,5 cm, 1Pc : 3Ps

0,10
BARAT
Dibuat Oleh :
0,00 ±
KAUR PERENCANAAN

SUROTO
Diperiksa Oleh :
Pas. Batu kali 1Pc : 4Ps, Siar 1Pc : 2Ps
KASIE KESEJAHTERAAN

0,60 –

AHMAD DANI
0.90-
Urugan psir Disetujui
1.00-
SEKRETARIS DESA

0,40
MACPOET
Mengethahui
KEPALA DESA

HJ. SRI WIJAYATI


Diverifikasi
Tim Verifikasi Desa

HADI MUKIYO
PROGRAM DANA DESA
PEMBANGUNAN SALURAN
IRIGASI
DUSUN KEDUNGWESI
DESA HAMPARAN PUGU
KECAMATAN AIR HANGAT
0.25 BARAT
0.00 Dibuat Oleh :
Ketua Tim Pembangunan

MUNAWAR. SPd
Diperiksa Oleh :
SEKRETARIS DESA

0.80 MACPOET
Disetujui
KETUA BPD
1.00
1.10

Drs. SUGENG PRASETYO


0.40 1.20 0.40 Mengethahui
KEPALA DESA

HJ. SRI WIJAYATI


Diverifikasi
Tim Tekinis Kab. Jombang

Ir. AHMAD SAIAN


NIP. 196106021986081002
PEMERINTAH KABUPATEN JOMBANG

KECAMATAN AIR HANGAT BARAT


DESA HAMPARAN PUGU

KEPUTUSAN KEPALA DESA HAMPARAN PUGU


NOMOR : 188 / /NaN/2018

TENTANG
PATOKAN HARGA SATUAN PEKERJAAN PER KEGIATAN DAN
STANDAR HARGA SATUAN BAHAN BANGUNAN SERTA
UPAH PEKERJA DI DESA HAMPARAN PUGU
TAHUN ANGGARAN 2017

KEPALA DESA HAMPARAN PUGU,

Menimbang : bahwa guna mempersiapkan pedoman kegiatan dalam rangka penyusunan dan
pelaksanaan kegiatan pembangunan, maka dipandang perlu menetapkan Patokan
Harga Satuan Pekerjaan Per Kegiatan dan Standar Harga Satuan Bahan Bangunan
serta Upah Pekerja Tahun Anggaran 2017 dalam Keputusan Kepala Desa;

Mengingat : 1. 1. Undang-Undang Nomor 17 Tahun 2003 tentang Keuangan Negara;


2. Undang-Undang Nomor 32 Tahun 2004 tentang Pemerintahan Daerah
sebagaimana telah diubah terakhir dengan Undang-Undang Nomor 12 Tahun
2008 (Lembaran Negara tahun 2008 Nomor 59, Tambahan Lembaran Negara
Nomor 4844) ;
3. Peraturan Pemerintah Nomor 58 Tahun 2005 tentang Pengelolaan Keuangan
Daerah ;
4. Peraturan Presiden Republik Indonesia Nomor 54 Tahun 2010 tentang
Pengadaan Barang/Jasa Pemerintah sebagaimana telah diubah kedua kali
dengan Peraturan Presiden Republik Indonesia Nomor 70 Tahun 2012 ;
5. Peraturan Menteri Dalam NegeriNomor 13 Tahun 2006 tentang Pedoman
Pengelolaan Keuangan Daerah sebagaimana telah diubah terakhir dengan
Peraturan Menteri Dalam Negeri Nomor 21 Tahun 2011.
6. Peraturan Bupati Jombang Nomor 1A Tahun 2010 tentang Pedoman
Pengelolaan Alokasi Dana Desa sebagaimana telah diubah dengan Peraturan
Bupati Jombang Nomor 3 Tahun 2011;

MEMUTUSKAN:
Menetapka :
n
KESATU : Penetapan Patokan Harga Satuan Pekerjaan Per Kegiatan dan Standar Harga Satuan
Bahan Bangunan serta Upah Pekerja di Desa Hamparan Pugu Kecamatan Air
Hangat Barat Kabupaten Jombang Tahun Anggaran 2017 sebagaimana tercantum
pada Lampiran yang merupakan bagian yang tidak terpisahkan dari Keputusan ini.

KEDUA : Patokan Harga sebagaimana dimaksud dalam Diktum KESATU digunakan sebagai
pedoman untuk penyusunan Rencana Kerja Anggaran Desa Hamparan Pugu Tahun
Anggaran 2017.
KETIGA : Patokan harga sebagaimana dimaksud dalam Diktum KESATU merupakan salah
satu acuan yang dapat dipergunakan sebagai pedoman pelaksanaan Anggaran
Pendapatan dan Belanja Desa Tahun Anggaran 2017 disamping perkembangan
harga pasar yang berlaku maupun ketentuan-ketentuan dalam peraturan perundang-
undangan yang berlaku.

KEEMPAT : Patokan harga sebagaimana dimaksud dalam Diktum KESATU meliputi harga
material, biaya menaikkan, mengangkut dan menurunkan material yang diangkut ke
lokasi pekerjaan.
KELIMA : Patokan harga sebagaimana dimaksud dalam Diktum KESATU merupakan harga
tertinggi.
KEENAM : Patokan harga sebagaimana dimaksud dalam Diktum KESATU belum termasuk
Pajak Pertambahan Nilai.
KETUJUH : Keputusan ini berlaku sejak tanggal ditetapkan.

Ditetapkan di Desa Hamparan Pugu


pada tanggal
KEPALA DESA HAMPARAN PUGU,

HJ. SRI WIJAYATI

SALINAN Keputusan ini disampaikan kepada:


Yth. 1. Sdr. Bupati Jombang;
2. Sdr. Camat Air Hangat Barat;
3. Sdr. Ketua BPD Hamparan Pugu;
4. Sdr. Anggota Tim Pembangunan Desa.
LAMPIRAN I : KEPUTUSAN KEPALA DESA HAMPARAN PUGU
NOMOR : 188 / /NaN/2018
TANGGAL :

DAFTAR PATOKAN HARGA SATUAN PEKERJAAN PER KEGIATAN (HSPK)


DI DESA HAMPARAN PUGU
TAHUN ANGGARAN 2017

HARGA
NO MACAM PEKERJAAN SATUAN SATUAN
(Rp)
1 2 3 4

1 Galian tanah m3 72,162.50


2 Urugan pasir urug m3 222,065.00
3 Tulangan besi beton polos 10 Kg 146,079.00
4 Tulangan besi beton ulir Kg 146,079.00
5 Acuan Untuk Beton Struktur m2 #N/A
6 Spesi beton 1:2:3 m3 1,075,000.00
7 Pas. Batu kali, 1:4 m3 902,520.00
8 Siaran 1:2 m2 53,615.00
9 Plesteran 1:3 m2 65,596.00
10 Pasang pipa besi galvanis D = 3" m' -

KEPALA DESA HAMPARAN PUGU,

HJ. SRI WIJAYATI


DAFTAR STANDAR HARGA SATUAN BAHAN BANGUNAN DAN UPAH PEKERJA
DI DESA HAMPARAN PUGU
TAHUN ANGGARAN 2017

HARGA PPN 10% HARGA +


NO JENIS BAHAN SATUAN
(Rp) PPN 10%
BAHAN BANGUNAN :

1 Pasir pasang / beton m3 280,000.00 280,000.00


2 Tanah Urug m3 120,000.00 15,600.00 135,600.00
3 Pasir Urug m3 140,000.00 18,200.00 158,200.00
4 Batu kali M3 350,000.00 350,000.00
5 Semen (40 kg) Zak 77,000.00 10,010.00 87,010.00
6 Tulangan besi beton polos kg 10,500.00 1,050.00 11,550.00
7 Tulangan besi beton ulir kg 11,000.00 1,100.00 12,100.00
8 Paku kg 15,000.00 1,500.00 16,500.00
9 Kayu acuan m3 3,000,000.00 300,000.00 3,300,000.00
10 Pipa pcv 2" Ljr 115,000.00 11,500.00 126,500.00
11 Batu Pecah 2/3 m3 250,000.00 25,000.00 275,000.00
12 Paving Stone K 300 T=6 cm m2 65,000.00 6,500.00 71,500.00
13 Paving topi uskup K 300 T=6 cm Bh 8,500.00 850.00 9,350.00
14 Kanstien Bh 30,000.00 3,000.00 33,000.00
15 Kayu terentang /papan radu lbr 15,000.00 1,500.00 16,500.00
16 Paku biasa 2" - 5" Kg 15,000.00 1,500.00 16,500.00
-
PERALATAN : -
1 Molen Unit/hr 150,000.00 150,000.00
2 Keranjang Bh 20,000.00 20,000.00
3 Ember Bh 10,000.00 10,000.00
4 Kotak adukan Bh 110,000.00 110,000.00
5 Cetok Bh 15,000.00 15,000.00
6 Kuas Bh 18,000.00 18,000.00
7 Alat bantu (set @ 3 alat) set 75,000.00 75,000.00
8 Kasut kayu Bh 22,500.00 22,500.00
9 Gergaji Bh 100,000.00 100,000.00
UPAH : -
1 Buruh tak terampil/pekerja Org/hari 120,000.00 120,000.00
2 Buruh terampil Org/hari 120,000.00 120,000.00
3 Tukang batu/kayu/besi Org/hari 140,000.00 140,000.00
4 Kepala Tukang Org/hari 0.00 -
5 Mandor Org/hari 0.00 -

KEPALA DESA HAMPARAN PUGU,

HJ. SRI WIJAYATI


TIME SCHEDULE / KURVA S

NAMA KEGIATAN PROGRAM DANA DESA


JENIS PEMBANGUNAN JALAN USAHA TANI
VOLUME 120M'
LOKASI DUSUN WISATA
DESA HAMPARAN PUGU
KECAMATAN AIR HANGAT BARAT
ANGGARAN Rp 95,870,000

Jumlah Harga Bobot Bulan I Bulan II Bulan III


No Uraian Pekerjaan Volume Sat Grafik Keterangan
( Rp ) (% ) M1 M2 M3 M4 M1 M2 M3 M4 M1 M2 M3 M4
100
1 Err:509 Err:509 Err:509 300,000 0.31% 0.156% 0.156%
2 Err:509 Err:509 Err:509 600,000 0.63% 0.313% 0.313% 90
3 Biaya Uitzet 2 Err:509 500,000 0.52% 0.261% 0.261% 80
4 Insentif Petugas Penyusun Desain Gam 1 LS 2,000,000 2.09% 2.086% 70
5 Biayan Pelaporan dan Dokumentasi 1 0 250,000 0.26% 0.261%
60
6 0 3 0 - 0.00% 0.000%
7 Pemasangan Papan Kegiatan 1 LS 300,000 0.31% 0.313% 50
8 Galian Tanah 14.4 m3 1,296,000 1.35% 0.338% 0.338% 0.338% 0.338% 40
9 Timbunan Tanah 144 m3 33,302,016 34.74% 11.579% 11.579% 11.579% 30
10 Pasangan batu kali 1 PC : 4 Ps 89.28 m3 53,915,326 56.24% 11.248% 11.248% 11.248% 11.248% 11.248%
20
11 Plester siaran 1 : 2 42 m2 3,407,032 3.55% 0.888% 0.888% 0.888% 0.888%
12 0 0 m2 - 0.00% 0.000% 0.000% 0.000% 0.000%
10
0
Jumlah 95,870,374 100% 0% 1% 3% 12% 23% 23% 12% 12% 12% 1% 0% 0%
Rencana 0.00% 0.16% 0.73% 3.47% 15.38% 38.55% 61.87% 74.01% 86.14% 98.54% 100.00% 100.00% 100.00%

Jombang, Maret 2019


Mengetahui : Diperiksa oleh : Mengetahui KAUR PERENCANAAN
SEKRETARIS DESA KASIE KESEJAHTERAAN KEPALA DESA

MACPOET AHMAD DANI HJ. SRI WIJAYATI SUROTO


TIME SCHEDULE / KURVA S

NAMA KEGIATAN PROGRAM DANA DESA


JENIS PEMBANGUNAN SALURAN IRIGASI
VOLUME 246 M'
LOKASI DUSUN KEDUNGWESI
DESA HAMPARAN PUGU
KECAMATAN AIR HANGAT BARAT
ANGGARAN Rp 193,700,000

Jumlah Harga Bobot Bulan I Bulan II Bulan III


No Uraian Pekerjaan Volume Sat Grafik Keterangan
( Rp ) (% ) M1 M2 M3 M4 M1 M2 M3 M4 M1 M2 M3 M4
100
1 Err:509 1 kl 350,000 0.18% 0.090% 0.090%
90
2 Err:509 2 kl 700,000 0.36% 0.181% 0.181%
3 Biaya Uitzet 2 kl 500,000 0.26% 0.129% 0.129% 80
4 Insentif Petugas Penyusun Desain Gam 1 kl 900,000 0.46% 0.465% 70
5 Biayan Pelaporan dan Dokumentasi 1 kl 400,000 0.21% 0.206%
60
6 0 3 kl - 0.00% 0.000% 0.206%
50
7 Pemasangan Papan Kegiatan 1 kl 500,000 0.26% 0.258%
8 Galian Tanah 59.04 m3 - 0.00% 0.000% 0.000% 0.000% 0.000% 40
9 Timbunan Tanah 19.68 m3 3,202,330 1.65% 11.579% 11.579% 11.579% 30
10 Pasangan batu kali 1 PC : 4 Ps 167.28 m3 171,627,139 88.60% 17.719% 17.719% 17.719% 17.719% 17.719%
20
11 Plester siaran 1 : 2 344.4 m2 15,539,261 8.02% 0.888% 0.888% 0.888% 0.888%
10
12 0 172.2 m2 - 0.00% 0.000% 0.000% 0.000% 0.000%
0
Jumlah 193,718,729 100% 0% 0% 1% 12% 29% 29% 19% 19% 19% 1% 0% 0%
Rencana 0.00% 0.09% 0.40% 1.12% 12.70% 42.00% 71.39% 90.00% 108.60% 127.34% 128.82% 128.82% 128.82%

Jombang, Maret 2019


Mengetahui : Diperiksa oleh : Mengetahui KAUR PERENCANAAN
SEKRETARIS DESA KASIE KESEJAHTERAAN KEPALA DESA

MACPOET AHMAD DANI HJ. SRI WIJAYATI SUROTO


TIME SCHEDULE / KURVA S

NAMA KEGIATAN PROGRAM DANA DESA


JENIS PEMBANGUNAN JALAN HOTMIX
VOLUME 556.50 X 2.50
LOKASI DUSUN WISATA
DESA HAMPARAN PUGU
KECAMATAN AIR HANGAT BARAT
ANGGARAN Rp -

Jumlah Harga Bobot Bulan I Bulan II Bulan III


No Uraian Pekerjaan Volume Sat Grafik Keterangan
( Rp ) (% ) M1 M2 M3 M4 M1 M2 M3 M4 M1 M2 M3 M4
100
1 0 1 kl 140,000 0.07% 0.036% 0.036%
90
2 Err:509 2 kl - 0.00% 0.000% 0.000%
3 Err:509 2 kl 24,496,800 12.65% 6.323% 6.323% 80
4 Biaya Uitzet 1 kl - 0.00% 0.000% 70
5 Insentif Petugas Penyusun Desain Gam 1 kl 193,718,729 100.00% 100.000%
60
6 Biayan Pelaporan dan Dokumentasi 3 kl 400,000 0.21% 0.206% 100.000%
50
7 0 1 kl - 0.00% 0.000%
8 Pemasangan Papan Kegiatan 0 m3 - 0.00% 0.000% 0.000% 0.000% 0.000% 40
9 Galian Tanah 0 m3 - 0.00% 11.579% 11.579% 11.579% 30
10 Timbunan Tanah 0 m3 - 0.00% 0.000% 0.000% 0.000% 0.000% 0.000%
20
11 Pasangan batu kali 1 PC : 4 Ps 0 m2 - 0.00% 0.888% 0.888% 0.888% 0.888%
10
12 Plester siaran 1 : 2 0 m2 #VALUE! #VALUE! 0.000% 0.000% 0.000% 0.000%
0
Jumlah #VALUE! #VALUE! 0% 6% 0% 12% 12% 12% 1% 1% 7% 201% 0% 0%
Rencana 0.00% 0.04% 6.36% 6.57% 18.14% 29.72% 41.34% 42.23% 43.11% 50.33% 251.21% 251.21% 251.21%

0
Mengetahui : 0.00% 0.00% Jombang, Maret 2019
Mengetahui : Diperiksa oleh : Mengetahui

0 0 0 -
FOTO 0%
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 08 ( TPS Sawah )

Sketsa Perhitungan
0.1
balok 0.1
Catatan: Talud Pasangan Batu, Panjang 65 M
Batako 0.75 1.00 Tiap jarak 3 meter
Sloof 0.15 diberi kolom uk. 10 x 15 cm Perhitungan volume Pas. Batu
0.08 = 65 / 3 V1 = (1) x ( 0.30 + 0.40 ) / 2 x 1.00 x 65.0
0.30 = 22 + 1 1 x 0.35 x 1.00 x 65 = 22.8 m3
1.00 = 23 kolom
V2 = (1) x ( 0.40 x 0.40 ) x 65.0
0.1 0.1 1 x 0.40 x 0.40 x 65 = 10.4 m3
VT = ( V1 + V2 )
0.15 0.10
0.40 22.8 + 10.4 = 33.2 m3
Kolom & sloof balok Perhitungan Volume Plesteran
0.40 A = (1) x ( 0.08 + 0.20 + 0.00 ) x 65.0
Jarak antar begel = 0.20 m 1 x 0.38 x 65.0 = 24.7 m2
Jumlah begel kolom & sloof = 440 bh besi
Volume Galian Tanah
Jumlah begel balok = 325 bh pokok Ø8 V = 0.40 x 0.40 x 65 = 10.40 m3
panjang 1 begel kolom & sloof = 0.46 m Perhitungan Strikan / Siaran
panjang 1 begel balok = 0.36 m besi begel A = 1/4 x ( 1.00 - 0.08 ) x 65.0
Panjang total begel = 319 m Ø6 0.25 x 0.92 x 65.0 = 15.0 m2
Sketsa Perhitungan Batako
U PETA LOKASI A batako = 65 x 0.75 = 48.8 m2
Lokasi TPT A kolom = 0.1 x 0.75 x 23.00 = 1.73 m2
Jl. Garuda

RT.08 A total = 47.0 m2


Perhitungan Cor Beton
RT .08 RT.04
V sloof = 0.10 x 0.15 x 65.00 = 0.98 m3
ke Gading V balok = 0.10 x 0.10 x 65.00 = 0.65 m3
ke Purwosekar

V Kolom = 0.10 x 0.15 x 1.00 x 23 = 0.35 m3


Lapangan

sawah Rumah Warga


Perhitungan Besi
Besi begel Ø6 = 319 m = 26.62 ≈ 27.00 btg
RT.07 = 319 x 0.222 = 70.91 kg
Besi pokok Ø8 = 666 m = 55.50 ≈ 56.00 btg
= 666 x 0.395 = 263.1 kg

An. SNI 6.6.1 Pekerjaan Pasangan Batu Belah 15/20 (1 : 5)


An. SNI 024 Batu 15/20 1.100 x 33.2 x 1.0 = 36.5 m3
Pasir Pasang 0.544 x 33.2 x 1.0 = 18.0 m3
Semen (40 Kg) 3.400 x 33.2 x 1.0 = 112.7 zak
Pekerja 1.500 x 33.2 x 1.0 = 49.7 OH
Tukang 0.600 x 33.2 x 1.0 = 19.9 OH
An. SNI 6.5.1 Pekerjaan Plesteran tebal 1,5 cm (1 : 5)
An. SNI 028 Pasir Pasang 0.022 x 24.7 x 1.0 = 0.5 m3
Semen (40 Kg) 0.108 x 24.7 x 1.0 = 2.7 zak
Pekerja 0.200 x 24.7 x 1.0 = 4.9 OH
Tukang 0.150 x 24.7 x 1.0 = 3.7 OH
An. SNI 6.5.1 Pekerjaan Setrikan (1 : 5)
An. SNI 028 Pasir Pasang 0.022 x 15.0 x 1.0 = 0.3 m3
Semen (40Kg) 0.108 x 15.0 x 1.0 = 1.6 zak
Pekerja 0.200 x 15.0 x 1.0 = 3.0 OH
Tukang 0.150 x 15.0 x 1.0 = 2.2 OH
An. SNI 6.1.1 Pekerjaan Galian Tanah( Analisa SNI )
An. SNI 010 Pekerja 0.400 x 10.4 = 4.2 OH
An. SNI 6.20.1 1 m2 Batako 1/2 Bata uk. 10 x 20 x 40
Batako 12.500 x 47.0 x 1.0 = 587.8 bh
Semen (40Kg) 0.188 x 47.0 x 1.0 = 8.8 zak
Pasir Pasang 0.027 x 47.0 x 1.0 = 1.3 m3
Pekerja 0.320 x 47.0 x 1.0 = 15.0 OH
Tukang 0.100 x 47.0 x 1.0 = 4.7 OH
An. SNI 6.5.1 Pekerjaan Beton Bertulang (1 : 2 : 3)
An. SNI 028 Pasir Pasang 0.520 x 1.32 x 1.0 = 0.69 m3
Semen (40 Kg) 5.800 x 1.32 x 1.0 = 7.66 zak
Batu Pecah 2/3 0.870 x 1.32 x 1.0 = 1.15 m3
Pekerja 1.650 x 1.32 x 1.0 = 2.18 OH
Tukang 0.250 x 1.32 x 1.0 = 0.33 OH
An. SNI 6.25.1 Pembesian
Besi Ø6 mm 1.000 x 27.00 x 1.0 = 27.00 btg
Besi Ø8 mm 1.000 x 56.00 x 1.0 = 56.00 btg
Kawat bendrat 0.015 x 333.98 x 1.0 = 5.01 kg
Pekerja 0.007 x 333.98 x 1.0 = 2.34 OH
Tukang 0.007 x 333.98 x 1.0 = 2.34 OH
Rekapitulasi kebutuhan bahan dan tenaga kerja
Batu Gunung = 36.47 ≈ 36.00 m3 selisih → 0.47
Batu Pecah 2/3 = 1.15 ≈ 1.00 m3 selisih → 0.15
Batako = 587.81 ≈ 588.00 bh selisih → (0.19)
Pasir Pasang = 20.86 ≈ 21.00 m3 selisih → (0.14)
Semen (40 Kg) = 133.47 ≈ 134.00 zak selisih → (0.53)
Besi Ø6 = 27.00 ≈ 27.00 btg selisih → -
Besi Ø8 = 56.00 ≈ 56.00 btg selisih → -
Kawat bendrat = 5.01 ≈ 6.00 kg selisih → (0.99)
Pekerja = 78.39 ≈ 78.00 OH selisih → 0.39
Tukang = 33.21 ≈ 33.00 OH selisih → 0.21