RENCANA ANGGARAN BIAYA - Dinding Batas Unit Batu Bata

PEMBANGUNAN RUMAH - Pondasi Menerus Cor Beton


TYPE : 40/96 - Stuktur Beton Bertulang
KAV. : 8,00M x 12,00M - Lantai Keramik 40x40
Lokasi : Kuala Bekala - Sumatera Utara - Atap Rangka Baja Ringan Genteng Metal
- Plafond Gypsum Rangka Furing
SA VOLUME HARGA JUMLAH HARGA
NO URAIAN PEKERJAAN TU SATUAN KOPEL
KOPEL TUNGGAL
AN ( Rp ) ( Rp )
1 2 3 4 5 6 7=4x6

I PEKERJAAN PERSIAPAN
1 Air Kerja Ls 1.00 1.00 30,000.00 30,000.00
2 Pengukuran, Pematokan & Pembersihan Ls 1.00 1.00 30,000.00 30,000.00
3 Pemasangan Bouwplank M' 25.25 29.00 11,075.00 279,643.75
4 Keamanan Ls 1.00 1.00 35,000.00 35,000.00
Sub. Jumlah I 374,643.75
II PEKERJAAN PONDASI
1 Galian Tanah Pondasi Menerus M3 8.49 8.82 44,000.00 373,488.50
2 Urugan Pemadatan Tanah Kembali Eks Galian M3 2.83 2.94 20,000.00 56,589.17

3 Urugan Tanah Bawah Lantai & Teras Dari Luar M3 8.29 8.29 148,000.00 1,226,402.00
4 Urugan Pasir Bawah Pondasi, Lantai & Teras M3 2.31 2.33 174,000.00 401,745.56
5 Pondasi Menerus Cor Beton 1:2:3 M3 6.48 6.73 698,150.00 4,524,230.17
6 Pondasi Teras Batu Bata 1:3 M' 6.68 6.68 15,774.40 105,294.12
Sub. Jumlah II 6,687,749.51
III PEKERJAAN DINDING
1 Dinding Batu Bata :
- Batu Bata 1:3 Trassram Tg.40 Cm M2 15.50 15.50 83,344.60 1,291,841.30
- Batu Bata 1:5 M2 120.93 120.93 78,872.00 9,537,785.26
2 Struktur Beton Bertulang Campuran 1PC:2PS:3KR
- Balok Sloof BS, 12x15 (4Ø10 & Ø8-20) M3 0.62 0.62 4,797,273.00 2,978,027.15
- Balok Kolom KP, 12x12 (4Ø10 & Ø8-20) M3 0.81 0.81 5,393,995.27 4,355,154.93
- Balok Ring RB, 12x15 (4Ø10 & Ø8-20) M3 0.62 0.62 4,797,273.00 2,978,027.15
- Balok Sopi BSi, 12x15 (4Ø10 & Ø8-20) M3 0.24 0.24 4,797,273.00 1,152,784.70
- Balok Dak, 12x15 (4Ø8 & Ø8-20) M3 0.04 0.04 3,616,125.20 130,180.51
- Pekerjaan Plat Leufel (4Ø8 & Ø6-20) M3 0.40 0.40 3,541,791.30 1,415,299.80
- Balok Plat Dapur M3 0.04 0.04 3,541,791.30 127,504.49
- Pekerjaan Plat Beton Dapur (4Ø10 & Ø8-15) M3 0.14 0.14 4,050,327.26 583,247.13

3 Pasangan Plesteran :
- Plesteran 1:3 Trassram Tg.40Cm M2 12.40 15.40 29,635.00 367,474.00
- Plesteran 1:5 M2 191.08 210.58 26,785.00 5,118,067.09
4 - Pasangan Dinding Keramik 20x25 KM/WC Tinggi 180Cm M2 10.50 10.50 92,525.00 971,697.55
5 Ornamen:
- Dinding Motif M2 3.50 3.50 29,635.00 103,722.50

6 Locis Kusen 1:2:3 Bh 10.00 10.00 844.10 8,440.95


Sub. Jumlah III 31,119,254.50
1 2 3 4 5 6 7=4x6

IV PEKERJAAN KUSEN, PINTU & JENDELA


1 Kusen Aluminium , Daun Pintu & Jendela:
- Type PJ Panil Kayu+Engsel+Kunci 8" + jendela Jungkit + Kaca 5mm Bh 1.00 1.00 1,659,533 1,659,532.98
- Type PJ1 Panil Kayu+Engsel+Kunci 8" + jendela Jungkit + Kaca 5mm Bh 1.00 1.00 1,535,146 1,535,145.98
- Type P1 Panil Multipleks 9mm+Engsel+Kunci 6" Bh 2.00 2.00 892,568 1,785,135.75
- Type J2 Jendela Jungkit+Kaca Tebal 5mm Bh 1.00 1.00 1,183,191 1,183,191.20
- Type J2A Jendela Jungkit+Kaca Tebal 5mm Bh 1.00 1.00 904,494 904,494.20
- Pintu Type P2 uPVC+Engsel+Kunci Alpha Bh 1.00 1.00 265,250 265,250.00
Sub. Jumlah IV 7,332,750.10
V PEKERJAAN RANGKA ATAP
1 Konstruksi Baja Ringan CX.75 0,75mm M2 63.10 63.10 141,598.00 8,934,833.80
2 Papan Listplank GRC 2/20 M' 20.00 20.00 16,598.36 331,967.21
3 Talang Air M' 4.00 4.00 39,600.00 158,400.00

Sub. Jumlah V 9,425,201.01


VI PEKERJAAN PENUTUP ATAP & PLAFOND
1 Penutup Atap Genteng Metal Tebal 0,3 M2 63.10 63.10 81,030.00 5,112,993.00
2 Nok Atap Genteng Metal T.0,3 M' 13.00 13.00 23,790.54 309,276.98
3 Rangka Furing+Plafond Gypsum 9mm :
- Bagian Dalam M2 39.25 39.25 70,000.00 2,747,500.00
- Bagian Luar M2 14.90 14.90 75,000.00 1,117,500.00
4 List Plafond Profil Kayu :
- Bagian Dalam M' 50.60 50.60 5,650.00 285,890.00
Sub. Jumlah VI 9,573,159.98
VII PEKERJAAN INSTALASI LISTRIK (In Bow)
1 Titik Lampu Ttk 10.00 10.00 113,100.00 1,131,000.00
2 Titik Stop Kontak Ttk 4.00 4.00 97,100.00 388,400.00
3 Box Sekering MCB Lengkap Arde Ttk 1.00 1.00 225,300.00 225,300.00
Sub. Jumlah VII 1,744,700.00
1 2 3 4 5 6 7=4x6

VIII PEKERJAAN LANTAI


1 Lantai Ruangan Keramik 40x40 M2 36.55 36.55 94,037.50 3,437,070.63
2 Lantai KM/WC Keramik Grid 20x20 M2 2.70 2.70 86,575.00 233,752.50
3 Lantai Teras Keramik 40x40 M2 4.96 4.96 94,037.50 466,426.00
Sub. Jumlah VIII 4,137,249.13
IX PEKERJAAN SANITAIR
1 Pipa PVC :
- Air Bersih PVC ؽ" M' 26.23 26.23 18,065.83 473,866.81
- Air Kotor Pipa PVC Ø3" M' 21.80 21.80 23,700.00 516,731.10
- Air Tinja Pipa PVC Ø4" M' 6.00 6.00 24,200.00 145,200.00
2 Saringan Air Kotor KM/WC Bh 1.00 1.00 20,000.00 20,000.00
3 Bak Mandi Fibre Glass 60x60 Bh 1.00 1.00 225,000.00 225,000.00
4 Kran Air ؽ" Bh 3.00 3.00 12,500.00 37,500.00
5 Kitchen Zink Single Bh 1.00 1.00 1,260,483.35 1,260,483.35
6 Septictank Lengkap pas batu bata Bh 1.00 1.00 900,000.00 900,000.00
7 Closet duduk Amerika Standart +Dudukan batu bata M' 1.00 1.00 983,008.92 983,008.92
Sub. Jumlah IX 4,561,790.18
X PEKERJAAN PENGECATAN
1 Cat Tembok Variasi M2 203.48 225.98 22,530.00 4,584,395.39
2 Cat Plafond M2 54.15 54.15 22,530.00 1,219,999.50
Sub. Jumlah X 5,804,394.89
XI PEKERJAAN LAIN-LAIN
1 Carpot Cor Beton M2 13.05 13.05 52,104.00 679,957.20
2 Pembersihan Akhir Unit 1.00 1.00 50,000.00 50,000.00
3 Plat Jembatan S1/ S2 Bh 1.00 1.00 784,502.91 784,502.91
4 Rumput Depan Rumah M2 18.00 18.00 33,000.00 594,000.00
5 Pekerjaan Pagar Batubata Batas unit & saluran : 21.35 21.35 -
- Pondasi Roolag BatuBata M' 21.35 21.35 15,774.40 336,783.44
- Batu Bata 1:3 Tinggi 40 Cm Batas Unit m2 8.54 8.54 83,344.60 711,762.88
- Batu Bata 1:3 Tinggi 40 Cm dinding saluran m2 3.20 3.20 83,344.60 266,702.72
- Batu Bata 1:3 Tinggi 20 Cm dari atas saluran m2 1.60 1.60 83,344.60 133,351.36
- Plesteran 1:3 Tinggi 40 cm m2 10.14 10.14 26,785.00 271,599.90
- Cat Tembok m2 10.14 10.14 28,385.00 287,823.90

Sub. Jumlah X 4,116,484.31