HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)
3
Pekerjaan Galian tanah m 1,212.28 128,287.50 155,519,857.35
3
Pekerjaan urugan pasir tebal 10cm m 121.23 368,115.00 44,625,697.97
Pekerjaan lantai kerja tebal 5cm m3 60.61 1,275,500.00 77,312,901.90
Pekerjaan RAFT
3
- Beton K-300 m 1,212.28 1,611,714.00 1,953,842,201.06
- Besi beton kg 45,735.59 21,191.20 969,191,984.85
- Bekisting m2 151.94 123,435.33 18,754,764.55
3
7 Urugan kembali bekas galian m 4.72 45,787.50 216,117.00
2
Pekerjaan rollag bata pas 1 bata (dibawah dinding bata) m 108.54 170,200.00 18,472,657.00
2
Pekerjaan rollag bata (sisi luar) m 60.92 170,200.00 10,368,584.00
Besi doweel Ø 10-100 kg 360.28 21,191.20 7,634,850.30
1 Pekerjaan Kolom K1
- Beton K-300 m3 4.99 1,611,714.00 8,045,676.29
- Besi beton kg 1,333.61 21,191.20 28,260,707.23
- Bekisting m2 37.44 204,961.00 7,673,739.84
2 Pekerjaan Kolom K2
3
- Beton K-300 m 43.06 1,611,714.00 69,393,957.98
- Besi beton kg 12,174.27 21,191.20 257,987,427.11
- Bekisting m2 358.80 204,961.00 73,540,006.80
3 Pekerjaan Kolom K3
- Beton K-300 m3 0.78 1,611,714.00 1,257,136.92
- Besi beton kg 204.92 21,191.20 4,342,450.75
- Bekisting m2 7.02 204,961.00 1,438,826.22
3 Pekerjaan Kolom K4
- Beton K-300 m3 4.21 1,611,714.00 6,788,539.37
- Besi beton kg 1,425.90 21,191.20 30,216,590.23
2
- Bekisting m 46.80 204,961.00 9,592,174.80
4 Pekerjaan Kolom K5
3
- Beton K-300 m 0.70 1,611,714.00 1,131,423.23
- Besi beton kg 144.02 21,191.20 3,051,965.69
- Bekisting m2 9.36 204,961.00 1,918,434.96
5 Pelat Lantai T= 120 mm
- Beton K-300 m3 83.25 1,611,714.00 134,180,992.67
- Wiremesh M6-150 m2 693.78 188,500.00 130,777,530.00
- Bondek m2 693.78 186,800.00 129,598,104.00
5 Tangga darurat lantai 1
3
- Beton K-300 m 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
2
- Bekisting m 46.91 187,201.33 8,780,996.78
6 Tangga Utama lantai 1
- Beton K-300 m3 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
- Bekisting m2 46.91 187,201.33 8,780,996.78
7 Plat beton kanopi jendela tebal 10cm
3
- Beton K-300 m 2.03 1,611,714.00 3,277,452.65
- Besi beton kg 209.11 21,191.20 4,431,367.21
2
- Bekisting m 33.24 228,867.67 7,606,645.77
8 Pekerjaan luar bangunan -
- Tanah urug peninggian lantai T=45cm (dalam bangunan) +
m3 89.51 137,362.50 12,295,248.69
pemadatan
3
- Pasir urug diatas tanah urug t=10 cm (dalam bangunan) m 19.89 368,115.00 7,322,175.47
3
- lantai kerja t=5cm (dalam bangunan) m 9.95 1,275,500.00 12,685,485.25
9 Pekerjaan dalam bangunan -
- Tanah urug peninggian lantai T=45cm (dalam bangunan) +
m3 297.67 137,362.50 40,888,764.06
pemadatan
- Pasir urug diatas tanah urug t=10 cm (dalam bangunan) m3 66.15 368,115.00 24,350,439.14
- lantai kerja t=5cm (dalam bangunan) m3 33.07 1,275,500.00 42,186,524.75
1 Pekerjaan Kolom K1
- Beton K-300 m3 3.71 1,611,714.00 5,982,682.37
- Besi beton kg 1,033.65 21,191.20 21,904,268.34
2
- Bekisting m 27.84 204,961.00 5,706,114.24
2 Pekerjaan Kolom K2
- Beton K-300 m3 18.79 1,611,714.00 30,287,329.49
- Besi beton kg 5,532.17 21,191.20 117,233,385.11
- Bekisting m2 156.60 204,961.00 32,096,892.60
3 Pekerjaan Kolom K3
1 Pekerjaan Kolom K2
- Beton K-300 m3 18.79 1,611,714.00 30,287,329.49
- Besi beton kg 5,532.17 21,191.20 117,233,385.11
- Bekisting m2 156.60 204,961.00 32,096,892.60
2 Pekerjaan Kolom K3 -
- Beton K-300 m3 12.18 1,611,714.00 19,630,676.52
- Besi beton kg 3,338.63 21,191.20 70,749,579.79
- Bekisting m2 109.62 204,961.00 22,467,824.82
3 Pekerjaan Kolom K4 -
3
- Beton K-300 m 4.31 1,611,714.00 6,940,846.34
- Besi beton kg 1,514.21 21,191.20 32,087,919.08
- Bekisting m2 47.85 204,961.00 9,807,383.85
4 Pekerjaan Balok B1 -
- Beton K-300 m3 1.92 1,611,714.00 3,086,754.65
- Besi beton kg 205.95 21,191.20 4,364,405.71
- Bekisting m2 15.96 204,961.00 3,271,177.56
5 Pekerjaan Balok B2 -
- Beton K-300 m3 4.50 1,611,714.00 7,256,581.11
- Besi beton kg 1,050.36 21,191.20 22,258,429.52
2
- Bekisting m 41.81 212,588.33 8,887,893.04
6 Pekerjaan Balok B3 -
- Beton K-300 m3 14.95 1,611,714.00 24,087,710.42
- Besi beton kg 4,518.80 21,191.20 95,758,893.91
- Bekisting m2 182.67 212,588.33 38,832,660.50
7 Pekerjaan Balok B4 -
3
- Beton K-300 m 5.94 1,611,714.00 9,578,545.24
- Besi beton kg 3,108.62 21,191.20 65,875,472.27
- Bekisting m2 102.86 212,588.33 21,867,048.56
1 Pekerjaan Kolom K3
- Beton K-300 m3 2.32 1,611,714.00 3,739,176.48
- Besi beton kg 635.93 21,191.20 13,476,110.44
2
- Bekisting m 20.88 204,961.00 4,279,585.68
2 Pekerjaan Kolom K4
- Beton K-300 m3 21.53 1,611,714.00 34,704,231.71
- Besi beton kg 7,571.05 21,191.20 160,439,595.40
- Bekisting m2 239.25 204,961.00 49,036,919.25
3 Pekerjaan Balok B1
3
- Beton K-300 m 1.92 1,611,714.00 3,086,754.65
- Besi beton kg 205.95 21,191.20 4,364,405.71
2
- Bekisting m 15.96 212,588.33 3,392,909.80
4 Pekerjaan Balok B2
3
- Beton K-300 m 6.13 1,611,714.00 9,874,004.65
- Besi beton kg 1,400.48 21,191.20 29,677,906.03
- Bekisting m2 56.89 212,588.33 12,093,725.11
5 Pekerjaan Balok B3
- Beton K-300 m3 8.06 1,611,714.00 12,993,960.61
- Besi beton kg 2,511.43 21,191.20 53,220,131.92
- Bekisting m2 98.54 212,588.33 20,948,029.19
6 Pekerjaan Balok B4
1 Pekerjaan Kolom K3
3
- Beton K-300 m 2.32 1,611,714.00 3,739,176.48
- Besi beton kg 635.93 21,191.20 13,476,110.44
- Bekisting m2 20.88 204,961.00 4,279,585.68
2 Pekerjaan Kolom K4 -
- Beton K-300 m3 10.18 1,611,714.00 16,405,636.81
- Besi beton kg 3,579.04 21,191.20 75,844,172.37
- Bekisting m2 113.10 204,961.00 23,181,089.10
3 Pekerjaan Kolom K5 -
- Beton K-300 m3 2.61 1,611,714.00 4,206,573.54
- Besi beton kg 554.13 21,191.20 11,742,644.95
2
- Bekisting m 34.80 204,961.00 7,132,642.80
4 Pekerjaan Balok B2 -
- Beton K-300 m3 1.60 1,611,714.00 2,572,295.54
- Besi beton kg 350.12 21,191.20 7,419,476.51
- Bekisting m2 14.82 212,588.33 3,150,559.10
5 Pekerjaan Balok B3 -
3
- Beton K-300 m 9.52 1,611,714.00 15,339,488.00
- Besi beton kg 2,826.35 21,191.20 59,893,725.77
2
- Bekisting m 116.33 212,588.33 24,729,337.88
6 Pekerjaan Balok B4 -
- Beton K-300 m3 5.79 1,611,714.00 9,335,498.77
- Besi beton kg 2,983.33 21,191.20 63,220,384.18
- Bekisting m2 100.25 212,588.33 21,312,193.01
7 Pekerjaan Balok B5 -
- Beton K-300 m3 0.30 1,611,714.00 477,712.03
- Besi beton kg 285.87 21,191.20 6,057,864.55
- Bekisting m2 6.08 212,588.33 1,292,537.07
8 Pekerjaan Balok B6 -
- Beton K-300 m3 4.45 1,611,714.00 7,174,061.36
- Besi beton kg 2,180.02 21,191.20 46,197,221.69
- Bekisting m2 111.28 212,588.33 23,656,829.73
8 Pelat Lantai T= 120 mm -
3
- Beton K-300 m 76.23 1,611,714.00 122,866,760.39
- Wiremesh M6-150 m2 635.28 188,500.00 119,750,280.00
- Bondek m2 635.28 186,800.00 118,670,304.00
1 Pekerjaan Balok B4
3
- Beton K-300 m 1.59 1,611,714.00 2,568,749.77
- Besi beton kg 830.81 21,191.20 17,605,814.26
- Bekisting m2 27.59 212,588.33 5,864,249.18
-
2 Pelat Lantai T= 120 mm -
3
- Beton K-300 m 3.87 1,611,714.00 6,239,267.24
- Wiremesh M6-150 m2 32.26 188,500.00 6,081,010.00
2
- Bondek m 32.26 186,800.00 6,026,168.00