Anda di halaman 1dari 7

PEKERJAAN STRUKTUR

PEMBANGUNAN RUMAH SUSUN KEJAKSAAN TINGGI SULAWESI


PEKERJAAN :
UTARA
SATUAN KERJA PENYEDIAAN PERUMAHAN PROVINSI SULAWESI
PEMBERI TUGAS :
UTARA
LOKASI : MANADO, SULAWESI UTARA
TAHUN : 2023

HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)

A PEKERJAAN STRUKTUR NON STANDAR 6,363,560,773.30

STRUKTUR BAWAH (SUB-STRUCTURE)

1 PEKERJAAN BORED PILE 2,304,484,078.80


Pekerjaan mobilisasi dan demobilisasi Ls 1.00 29,700,000.00 29,700,000.00
Pekerjaan pondasi bored pile dia.40cm
1
- Pengeboran pondasi bored pile dia.40cm m 2,109.13 340,500.00 718,158,913.04
- Beton K-300 m3 304.64 1,611,714.00 490,997,065.76
- Besi beton kg 46,500.00 21,191.20 985,390,800.00
Pekerjaan pembuangan lumpur/tanah pengeboran rit 181.00 443,300.00 80,237,300.00

2 PEKERJAAN RAFT 3,245,940,526.86

3
Pekerjaan Galian tanah m 1,212.28 128,287.50 155,519,857.35
3
Pekerjaan urugan pasir tebal 10cm m 121.23 368,115.00 44,625,697.97
Pekerjaan lantai kerja tebal 5cm m3 60.61 1,275,500.00 77,312,901.90

Pekerjaan RAFT
3
- Beton K-300 m 1,212.28 1,611,714.00 1,953,842,201.06
- Besi beton kg 45,735.59 21,191.20 969,191,984.85
- Bekisting m2 151.94 123,435.33 18,754,764.55

Urugan tanah kembali bekas galian m3 92.41 45,787.50 4,231,039.73


3
Pemadatan tanah CBR> 6% m 92.41 91,575.00 8,462,079.45
Pekerjaan PDA Test tiang titik 2.00 7,000,000.00 14,000,000.00

3 PEKERJAAN GWT , RUANG POMPA & STP 813,136,167.64

PEKERJAAN STRUKTUR GWT

1 Pekerjaan pondasi bored pile dia.40cm


- Pengeboran pondasi bored pile dia.40cm m1 132.00 340,500.00 44,946,000.00
- Beton K-300 m3 16.59 1,611,714.00 26,744,782.12
- Besi beton kg 2,279.53 21,191.20 48,306,039.71
-
Pekerjaan pembuangan lumpur/tanah rit 2.00 443,300.00 886,600.00
-
3 Pekerjaan PC-1 (GWT) -
- Beton K-300 m3 1.62 1,611,714.00 2,610,976.68
- Besi beton kg 347.37 21,191.20 7,361,187.14
- Bekisting m2 107.22 123,435.33 13,234,119.26
-
3 Pekerjaan Tie beam/sloof TB1 (GWT) -
- Beton K-300 m3 2.27 1,611,714.00 3,658,590.78
- Besi beton kg 458.60 21,191.20 9,718,284.32
- Bekisting m2 23.21 228,867.67 5,312,018.54
-
4 Pekerjaan Galian tanah: -
Pile cap tipe P-1 (GWT) m3 2.03 128,287.50 260,423.63
3
Tie Beam/sloof TB-1 m 4.24 128,287.50 543,939.00

5 Pekerjaan urugan pasir tebal 10cm


3
Pile cap tipe P-1 (GWT) m 0.27 368,115.00 99,391.05
Tie Beam/sloof TB-1 m3 0.50 368,115.00 184,057.50

6 Pekerjaan lantai kerja tebal 5cm


3
Pile cap tipe P-1 (GWT) m 0.70 1,275,500.00 892,850.00

3
7 Urugan kembali bekas galian m 4.72 45,787.50 216,117.00

8 Pekerjaan lantai dasar (GWT)


- Beton K-300 m3 16.91 1,611,714.00 27,254,083.74
- Besi beton kg 795.34 21,191.20 16,854,103.05
- Bekisting m2 9.27 228,867.67 2,121,603.27

9 Pekerjaan Dinding (GWT)


- Beton K-300 m3 72.63 1,611,714.00 117,058,787.82
- Besi beton kg 4,145.28 21,191.20 87,843,457.54
- Bekisting m2 290.50 206,145.00 59,885,122.50

3. RAB STRUKTUR Page 1


HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)

10 Pekerjaan Plat penutup (GWT)


- Beton K-300 m3 8.16 1,611,714.00 13,151,586.24
- Besi beton kg 900.00 21,191.20 19,072,080.00
- Bekisting m2 59.10 228,867.67 13,526,079.10

4 PEKERJAAN STRUKTUR RUANG POMPA

Pekerjaan pondasi bored pile dia.40cm


1
- Pengeboran pondasi bored pile dia.40cm m 88.00 340,500.00 29,964,000.00
3
- Beton K-300 m 11.06 1,611,714.00 17,830,391.98
- Besi beton kg 1,500.69 21,191.20 31,801,400.74
-
Pekerjaan pembuangan lumpur/tanah rit 3.00 443,300.00 1,329,900.00
-
Pekerjaan PC-1 (R.Pompa) -
3
- Beton K-300 m 0.72 1,611,714.00 1,160,434.08
- Besi beton kg 153.39 21,191.20 3,250,518.17
- Bekisting m2 214.43 123,435.33 26,468,238.53
-
Pekerjaan galian tanah : -
3
Pile cap tipe PC-1 (R.pompa) m 0.90 128,287.50 115,458.75
-
Pekerjaan urugan pasir tebal 10 cm: -
3
Pile cap tipe PC-1 (R.pompa) m 0.12 368,115.00 44,173.80
-
Pekerjaan lantai kerja tebal 5 cm: -
Pile cap tipe PC-1 (R.pompa) m3 0.06 1,275,500.00 76,530.00
-
3
Urugan tanah kembali bekas galian m 0.72 45,787.50 32,967.00
-
Pekerjaan lantai dasar ruang pompa -
- Beton K-300 m3 9.04 1,611,714.00 14,569,894.56
- Besi beton kg 743.00 21,191.20 15,745,061.60
- Bekisting m2 4.06 228,867.67 929,202.73
-
Pekerjaan pelat dak ruang pompa -
- Beton K-300 m3 5.39 1,611,714.00 8,687,138.46
- Besi beton kg 596.56 21,191.20 12,641,822.27
2
- Bekisting m 32.22 228,867.67 7,374,116.22
-
Kolom K3A (R.pompa) -
3
- Beton K-300 m 0.88 1,611,714.00 1,418,308.32
- Besi beton kg 172.10 21,191.20 3,647,005.52
- Bekisting m2 14.00 204,961.00 2,869,454.00
-
Balok B1 (R.pompa) -
- Beton K-300 m3 0.72 1,611,714.00 1,160,434.08
- Besi beton kg 344.73 21,191.20 7,305,242.38
- Bekisting m2 18.34 212,588.33 3,898,870.03
-
Tie beam dasar pelat (R.pompa) -
- Beton K-300 m3 2.28 1,611,714.00 3,674,707.92
- Besi beton kg 110.83 21,191.20 2,348,620.70
- Bekisting m2 18.50 228,867.67 4,234,051.83
-
Lantai ramp (R.pompa) -
- Beton K-300 m3 0.32 1,611,714.00 515,748.48
- Besi beton kg 36.64 21,191.20 776,445.57
- Bekisting m2 1.38 228,867.67 315,837.38
-
5 PEKERJAAN STRUKTUR STP -
-
Pekerjaan galian tanah : m3 60.00 128,287.50 7,697,250.00
Pasir urug diatas tanah urug t=10 + pasir pengisi m3 4.80 368,115.00 1,766,952.00
Cor beton lantai kerja t=5 cm m3 0.58 1,275,500.00 739,790.00
Pekerjaan urugan tanah kembali bekas galian m3 51.02 45,787.50 2,336,078.25
Pelat bawah t=15 cm -
- Beton K-300 m3 3.60 1,611,714.00 5,802,170.40
- Besi beton kg 249.60 21,191.20 5,289,323.52
2
- Bekisting m 4.80 228,867.67 1,098,564.80
Pelat penutup atap t=15 -
3
- Beton K-300 m 3.12 1,611,714.00 5,028,547.68
- Besi beton kg 757.44 21,191.20 16,051,062.53
- Bekisting m2 18.08 228,867.67 4,137,927.41
Cor dinding beton STP t=15 cm -
3
- Beton K-300 m 11.60 1,611,714.00 18,695,882.40
- Besi beton kg 513.64 21,191.20 10,884,647.97
- Bekisting m2 20.88 206,145.00 4,304,307.60
Pasangan bata bak kontrol + tutup plat besi 3 mm (lengkap terpasang) unit 4.00 237,400.00 949,600.00

3. RAB STRUKTUR Page 2


HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)
Pipa PVC AW 3 inch + galian (terpasang) M 4.00 86,636.00 346,544.00
Pipa Vent PVC AW 3 inch unit 4.00 519,816.00 2,079,264.00

A PEKERJAAN STRUKTUR STANDART 5,541,375,808.17

STRUKTUR BAWAH (SUB-STRUCTURE) 258,790,187.05

2
Pekerjaan rollag bata pas 1 bata (dibawah dinding bata) m 108.54 170,200.00 18,472,657.00
2
Pekerjaan rollag bata (sisi luar) m 60.92 170,200.00 10,368,584.00
Besi doweel Ø 10-100 kg 360.28 21,191.20 7,634,850.30

PEKERJAAN TIE BEAM


Pekerjaan TB1
- Beton K-300 m3 17.74 1,611,714.00 28,591,806.36
- Besi beton kg 8,108.31 21,191.20 171,824,861.25
- Bekisting m2 177.40 123,435.33 21,897,428.13

STRUKTUR ATAS (UPPER STRUCTURE) 5,282,585,621.12

PEKERJAAN LANTAI 1 1,098,413,252.11

1 Pekerjaan Kolom K1
- Beton K-300 m3 4.99 1,611,714.00 8,045,676.29
- Besi beton kg 1,333.61 21,191.20 28,260,707.23
- Bekisting m2 37.44 204,961.00 7,673,739.84
2 Pekerjaan Kolom K2
3
- Beton K-300 m 43.06 1,611,714.00 69,393,957.98
- Besi beton kg 12,174.27 21,191.20 257,987,427.11
- Bekisting m2 358.80 204,961.00 73,540,006.80
3 Pekerjaan Kolom K3
- Beton K-300 m3 0.78 1,611,714.00 1,257,136.92
- Besi beton kg 204.92 21,191.20 4,342,450.75
- Bekisting m2 7.02 204,961.00 1,438,826.22
3 Pekerjaan Kolom K4
- Beton K-300 m3 4.21 1,611,714.00 6,788,539.37
- Besi beton kg 1,425.90 21,191.20 30,216,590.23
2
- Bekisting m 46.80 204,961.00 9,592,174.80
4 Pekerjaan Kolom K5
3
- Beton K-300 m 0.70 1,611,714.00 1,131,423.23
- Besi beton kg 144.02 21,191.20 3,051,965.69
- Bekisting m2 9.36 204,961.00 1,918,434.96
5 Pelat Lantai T= 120 mm
- Beton K-300 m3 83.25 1,611,714.00 134,180,992.67
- Wiremesh M6-150 m2 693.78 188,500.00 130,777,530.00
- Bondek m2 693.78 186,800.00 129,598,104.00
5 Tangga darurat lantai 1
3
- Beton K-300 m 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
2
- Bekisting m 46.91 187,201.33 8,780,996.78
6 Tangga Utama lantai 1
- Beton K-300 m3 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
- Bekisting m2 46.91 187,201.33 8,780,996.78
7 Plat beton kanopi jendela tebal 10cm
3
- Beton K-300 m 2.03 1,611,714.00 3,277,452.65
- Besi beton kg 209.11 21,191.20 4,431,367.21
2
- Bekisting m 33.24 228,867.67 7,606,645.77
8 Pekerjaan luar bangunan -
- Tanah urug peninggian lantai T=45cm (dalam bangunan) +
m3 89.51 137,362.50 12,295,248.69
pemadatan
3
- Pasir urug diatas tanah urug t=10 cm (dalam bangunan) m 19.89 368,115.00 7,322,175.47
3
- lantai kerja t=5cm (dalam bangunan) m 9.95 1,275,500.00 12,685,485.25
9 Pekerjaan dalam bangunan -
- Tanah urug peninggian lantai T=45cm (dalam bangunan) +
m3 297.67 137,362.50 40,888,764.06
pemadatan
- Pasir urug diatas tanah urug t=10 cm (dalam bangunan) m3 66.15 368,115.00 24,350,439.14
- lantai kerja t=5cm (dalam bangunan) m3 33.07 1,275,500.00 42,186,524.75

PEKERJAAN LANTAI 2 1,166,651,209.57

1 Pekerjaan Kolom K1
- Beton K-300 m3 3.71 1,611,714.00 5,982,682.37
- Besi beton kg 1,033.65 21,191.20 21,904,268.34
2
- Bekisting m 27.84 204,961.00 5,706,114.24
2 Pekerjaan Kolom K2
- Beton K-300 m3 18.79 1,611,714.00 30,287,329.49
- Besi beton kg 5,532.17 21,191.20 117,233,385.11
- Bekisting m2 156.60 204,961.00 32,096,892.60
3 Pekerjaan Kolom K3

3. RAB STRUKTUR Page 3


HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)
3
- Beton K-300 m 11.02 1,611,714.00 17,761,088.28
- Besi beton kg 3,020.67 21,191.20 64,011,524.57
- Bekisting m2 99.18 204,961.00 20,328,031.98
4 Pekerjaan Kolom K4
- Beton K-300 m3 3.13 1,611,714.00 5,047,888.25
- Besi beton kg 1,101.24 21,191.20 23,336,668.42
- Bekisting m2 34.80 204,961.00 7,132,642.80
5 Pekerjaan Balok B1
- Beton K-300 m3 1.92 1,611,714.00 3,086,754.65
- Besi beton kg 394.44 21,191.20 8,358,709.82
2
- Bekisting m 15.96 212,588.33 3,392,909.80
6 Pekerjaan Balok B2
- Beton K-300 m3 4.50 1,611,714.00 7,256,581.11
- Besi beton kg 1,050.36 21,191.20 22,258,429.52
- Bekisting m2 41.81 212,588.33 8,887,893.04
7 Pekerjaan Balok B3
- Beton K-300 m3 14.95 1,611,714.00 24,087,710.42
- Besi beton kg 4,518.80 21,191.20 95,758,893.91
- Bekisting m2 182.67 212,588.33 38,832,660.50
8 Pekerjaan Balok B4
3
- Beton K-300 m 6.15 1,611,714.00 9,905,400.84
- Besi beton kg 3,207.37 21,191.20 67,968,047.97
- Bekisting m2 106.37 212,588.33 22,613,233.61
9 Pekerjaan Balok B5
- Beton K-300 m3 0.11 1,611,714.00 172,856.33
- Besi beton kg 115.51 21,191.20 2,447,836.07
- Bekisting m2 2.73 212,588.33 579,303.21
10 Pekerjaan Balok B6
- Beton K-300 m3 4.45 1,611,714.00 7,174,061.36
- Besi beton kg 2,180.02 21,191.20 46,197,221.69
- Bekisting m2 111.28 212,588.33 23,656,829.73
11 Pelat Lantai T= 120 mm
3
- Beton K-300 m 76.23 1,611,714.00 122,866,760.39
2
- Wiremesh M6-150 m 635.28 188,500.00 119,750,280.00
- Bondek m2 635.28 186,800.00 118,670,304.00
12 Tangga darurat lantai 2
- Beton K-300 m3 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
- Bekisting m2 46.91 187,201.33 8,780,996.78
13 Tangga Utama lantai 2
- Beton K-300 m3 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
2
- Bekisting m 46.91 187,201.33 8,780,996.78
14 Plat beton kanopi jendela tebal 10cm
- Beton K-300 m3 2.36 1,611,714.00 3,800,292.67
- Besi beton kg 220.24 21,191.20 4,667,187.12
- Bekisting m2 40.46 228,867.67 9,259,070.32

PEKERJAAN LANTAI 3 1,165,244,557.32

1 Pekerjaan Kolom K2
- Beton K-300 m3 18.79 1,611,714.00 30,287,329.49
- Besi beton kg 5,532.17 21,191.20 117,233,385.11
- Bekisting m2 156.60 204,961.00 32,096,892.60
2 Pekerjaan Kolom K3 -
- Beton K-300 m3 12.18 1,611,714.00 19,630,676.52
- Besi beton kg 3,338.63 21,191.20 70,749,579.79
- Bekisting m2 109.62 204,961.00 22,467,824.82
3 Pekerjaan Kolom K4 -
3
- Beton K-300 m 4.31 1,611,714.00 6,940,846.34
- Besi beton kg 1,514.21 21,191.20 32,087,919.08
- Bekisting m2 47.85 204,961.00 9,807,383.85
4 Pekerjaan Balok B1 -
- Beton K-300 m3 1.92 1,611,714.00 3,086,754.65
- Besi beton kg 205.95 21,191.20 4,364,405.71
- Bekisting m2 15.96 204,961.00 3,271,177.56
5 Pekerjaan Balok B2 -
- Beton K-300 m3 4.50 1,611,714.00 7,256,581.11
- Besi beton kg 1,050.36 21,191.20 22,258,429.52
2
- Bekisting m 41.81 212,588.33 8,887,893.04
6 Pekerjaan Balok B3 -
- Beton K-300 m3 14.95 1,611,714.00 24,087,710.42
- Besi beton kg 4,518.80 21,191.20 95,758,893.91
- Bekisting m2 182.67 212,588.33 38,832,660.50
7 Pekerjaan Balok B4 -
3
- Beton K-300 m 5.94 1,611,714.00 9,578,545.24
- Besi beton kg 3,108.62 21,191.20 65,875,472.27
- Bekisting m2 102.86 212,588.33 21,867,048.56

3. RAB STRUKTUR Page 4


HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)
8 Pekerjaan Balok B5 -
3
- Beton K-300 m 0.20 1,611,714.00 314,284.23

3. RAB STRUKTUR Page 5


HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)
- Besi beton kg 285.87 21,191.20 6,057,864.55
2
- Bekisting m 6.08 212,588.33 1,292,537.07
9 Pekerjaan Balok B6 -
- Beton K-300 m3 4.45 1,611,714.00 7,174,061.36
- Besi beton kg 2,180.02 21,191.20 46,197,221.69
- Bekisting m2 111.28 212,588.33 23,656,829.73
9 Pelat Lantai T= 120 mm -
- Beton K-300 m3 76.23 1,611,714.00 122,866,760.39
2
- Wiremesh M6-150 m 635.28 188,500.00 119,750,280.00
- Bondek m2 635.28 186,800.00 118,670,304.00
9 Tangga darurat lantai 3
- Beton K-300 m3 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
- Bekisting m2 46.91 187,201.33 8,780,996.78
10 Tangga Utama lantai 3 -
- Beton K-300 m3 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
- Bekisting m2 46.91 187,201.33 8,780,996.78
11 Plat beton kanopi jendela tebal 10cm
- Beton K-300 m3 2.24 1,611,714.00 3,606,886.99
- Besi beton kg 220.24 21,191.20 4,667,187.12
- Bekisting m2 40.46 228,867.67 9,259,070.32

12 Pekerjaan Balok (planter box) uk.35x25 -


3
- Beton K-300 m 1.00 1,611,714.00 1,611,714.00
- Besi beton kg 54.48 21,191.20 1,154,455.27
- Bekisting m2 1.45 212,588.33 307,190.14
-
13 Pekerjaan balok kantilever (planter box) -
- Beton K-300 m3 1.00 1,611,714.00 1,611,714.00
- Besi beton kg 130.98 21,191.20 2,775,638.53
- Bekisting m2 2.16 212,588.33 459,190.80
-
13 Pekerjaan Plat lantai (planter box) -
- Beton K-300 m3 1.00 1,611,714.00 1,611,714.00
- Wiremesh M6-150 m2 4.26 188,500.00 803,010.00
- Bondek m2 4.26 186,800.00 795,768.00

PEKERJAAN LANTAI 4 994,767,181.95

1 Pekerjaan Kolom K3
- Beton K-300 m3 2.32 1,611,714.00 3,739,176.48
- Besi beton kg 635.93 21,191.20 13,476,110.44
2
- Bekisting m 20.88 204,961.00 4,279,585.68
2 Pekerjaan Kolom K4
- Beton K-300 m3 21.53 1,611,714.00 34,704,231.71
- Besi beton kg 7,571.05 21,191.20 160,439,595.40
- Bekisting m2 239.25 204,961.00 49,036,919.25
3 Pekerjaan Balok B1
3
- Beton K-300 m 1.92 1,611,714.00 3,086,754.65
- Besi beton kg 205.95 21,191.20 4,364,405.71
2
- Bekisting m 15.96 212,588.33 3,392,909.80
4 Pekerjaan Balok B2
3
- Beton K-300 m 6.13 1,611,714.00 9,874,004.65
- Besi beton kg 1,400.48 21,191.20 29,677,906.03
- Bekisting m2 56.89 212,588.33 12,093,725.11
5 Pekerjaan Balok B3
- Beton K-300 m3 8.06 1,611,714.00 12,993,960.61
- Besi beton kg 2,511.43 21,191.20 53,220,131.92
- Bekisting m2 98.54 212,588.33 20,948,029.19
6 Pekerjaan Balok B4

3. RAB STRUKTUR Page 6


HARGA
JUMLAH
NO JENIS PEKERJAAN KODE SATUAN QUANTITY SATUAN
(Rp) (Rp)
3
- Beton K-300 m 5.72 1,611,714.00 9,218,165.99
- Besi beton kg 2,983.33 21,191.20 63,220,384.18
- Bekisting m2 98.99 212,588.33 21,044,331.71
7 Pekerjaan Balok B5
- Beton K-300 m3 0.30 1,611,714.00 477,712.03
- Besi beton kg 285.87 21,191.20 6,057,864.55
- Bekisting m2 6.08 212,588.33 1,292,537.07
8 Pekerjaan Balok B6
- Beton K-300 m3 4.45 1,611,714.00 7,174,061.36
- Besi beton kg 2,180.02 21,191.20 46,197,221.69
2
- Bekisting m 111.28 212,588.33 23,656,829.73
8 Pelat Lantai T= 120 mm
- Beton K-300 m3 76.23 1,611,714.00 122,866,760.39
- Wiremesh M6-150 m2 635.28 188,500.00 119,750,280.00
2
- Bondek m 635.28 186,800.00 118,670,304.00
9 Tangga Utama lantai 4
3
- Beton K-300 m 6.17 1,611,714.00 9,939,770.64
- Besi beton kg 158.84 21,191.20 3,365,965.10
- Bekisting m2 46.91 187,201.33 8,780,996.78
10 Plat beton kanopi jendela tebal 10cm
- Beton K-300 m3 2.36 1,611,714.00 3,800,292.67
- Besi beton kg 220.24 21,191.20 4,667,187.12
- Bekisting m2 40.46 228,867.67 9,259,070.32
-

PEKERJAAN LANTAI ROOFTOP 813,124,161.72

1 Pekerjaan Kolom K3
3
- Beton K-300 m 2.32 1,611,714.00 3,739,176.48
- Besi beton kg 635.93 21,191.20 13,476,110.44
- Bekisting m2 20.88 204,961.00 4,279,585.68
2 Pekerjaan Kolom K4 -
- Beton K-300 m3 10.18 1,611,714.00 16,405,636.81
- Besi beton kg 3,579.04 21,191.20 75,844,172.37
- Bekisting m2 113.10 204,961.00 23,181,089.10
3 Pekerjaan Kolom K5 -
- Beton K-300 m3 2.61 1,611,714.00 4,206,573.54
- Besi beton kg 554.13 21,191.20 11,742,644.95
2
- Bekisting m 34.80 204,961.00 7,132,642.80
4 Pekerjaan Balok B2 -
- Beton K-300 m3 1.60 1,611,714.00 2,572,295.54
- Besi beton kg 350.12 21,191.20 7,419,476.51
- Bekisting m2 14.82 212,588.33 3,150,559.10
5 Pekerjaan Balok B3 -
3
- Beton K-300 m 9.52 1,611,714.00 15,339,488.00
- Besi beton kg 2,826.35 21,191.20 59,893,725.77
2
- Bekisting m 116.33 212,588.33 24,729,337.88
6 Pekerjaan Balok B4 -
- Beton K-300 m3 5.79 1,611,714.00 9,335,498.77
- Besi beton kg 2,983.33 21,191.20 63,220,384.18
- Bekisting m2 100.25 212,588.33 21,312,193.01
7 Pekerjaan Balok B5 -
- Beton K-300 m3 0.30 1,611,714.00 477,712.03
- Besi beton kg 285.87 21,191.20 6,057,864.55
- Bekisting m2 6.08 212,588.33 1,292,537.07
8 Pekerjaan Balok B6 -
- Beton K-300 m3 4.45 1,611,714.00 7,174,061.36
- Besi beton kg 2,180.02 21,191.20 46,197,221.69
- Bekisting m2 111.28 212,588.33 23,656,829.73
8 Pelat Lantai T= 120 mm -
3
- Beton K-300 m 76.23 1,611,714.00 122,866,760.39
- Wiremesh M6-150 m2 635.28 188,500.00 119,750,280.00
- Bondek m2 635.28 186,800.00 118,670,304.00

PEKERJAAN LANTAI ATAP 44,385,258.44

1 Pekerjaan Balok B4
3
- Beton K-300 m 1.59 1,611,714.00 2,568,749.77
- Besi beton kg 830.81 21,191.20 17,605,814.26
- Bekisting m2 27.59 212,588.33 5,864,249.18
-
2 Pelat Lantai T= 120 mm -
3
- Beton K-300 m 3.87 1,611,714.00 6,239,267.24
- Wiremesh M6-150 m2 32.26 188,500.00 6,081,010.00
2
- Bondek m 32.26 186,800.00 6,026,168.00

3. RAB STRUKTUR Page 7

Anda mungkin juga menyukai