PENGEMBALIAN MATERIAL
KERAMIK LANTAI 40 X 40 SETARA MULIA 2.203.428,53
KERAMIK LANTAI. KM/WC 20 X20 SETARA MULIA 136.394,39
KERAMIK DINDING KM 20 X 25 SETARA MULIA 579.500,12
KERAMIK 20 X 20 POLOS 228.977,25
KERAMIK LANTAI. KM/WC 25 X40 SETARA MULIA 528.822,25
PENGEMBALIAN BIAYA MATERIAL 3.677.123
2.044.076,07 2.044.076,07
B. PEKERJAAN PONDASI DAN BETON
1 1 M3 MEMBUAT PONDASI BANGUNAN BATU BELAH 1 PC 5 PSR 8,52 M3 4.327.228,80
2 1 M3 MEMBUAT PONDASI BATAS KAVLING BATU BELAH 1 PC 5 PSR 0,81 M3 411.355,26
3 1 M3 MEMBUAT SLOOF 10X15 BETON BERTULANG 0,85 M3 3.627.848,81
4 1 M MEMBUAT RING BALOK 10X10 BETON BERTULANG ATAS BATA 56,84 M1 3.961.748,00
5 1 M MEMBUAT KOLOM PRAKTIS 10X12 BETON BERTULANG 25,20 M1 1.913.032,80
6 1 M MEMBUAT KOLOM PRAKTIS 10X15 BETON BERTULANG 39,60 M1 3.908.084,40
7 1 M3 MEMBUAT RING BALOK 10X15 BETON BERTULANG ATAS BATA 0,66 M3 2.415.350,53
8 1 UNIT MEJA DAPUR PLAT BETON BERTULANG T=6 CM 1,00 UNIT 928.723,00
9 1 M3 MEMBUAT BALOK 15X15 STRUKTUR BETON BERTULANG 0,23 M3 917.198,33
10 1 M2 BONGKARAN BEKISTING 71,22 M2 561.348,16
11 1 M3 MEMBUAT PLAT DAK BETON BELAKANG T10 CM 0,10 M3 459.556,20
23.431.474,29 23.431.474,29
C. PEKERJAAN PASANGAN DAN PLESTERAN
1 1 M2 PASANGAN DINDING BANGUNAN BATA MERAH 178,84 M2 14.743.894,30
2 1 M2 PLESTERAN DINDING BANGUNAN 357,68 M2 10.610.911,15
3 1 M2 ACIAN DINDING BANGUNAN 357,68 M2 6.552.325,26
4 1 BH PASANGAN GLASSBLOCK 5,00 BH 133.745,00
5 1 M PASANGAN PLINT ATAU PROFIL PLESTERAN 61,05 M 1.549.937,40
33.590.813,12 33.590.813,12
D. PEKERJAAN LANTAI DAN DINDING
1 1 M2 PASANG KERAMIK LANTAI RUANGAN 40X40 CM 32,42 M2 3.624.480,10
2 1 M2 PASANG KERAMIK LANTAI TERAS DEPAN 40X40 CM 2,10 M2 234.782,10
3 1 M2 PASANG KERAMIK LANTAI TERAS BELAKANG 40X40 CM 4,16 M2 465.371,66
4 1 M2 PASANGAN KERAMIK LANTAI 20 CM X 20 CM KM WC 2,23 M2 288.859,97
5 1 M2 PASANGAN KERAMIK DINDING 20 CM X 25 CM KM WC 9,46 M2 1.365.191,46
6 1 M2 PASANGAN KERAMIK DINDING 25 CM X 40 CM KM WC 10,00 M2 1.180.820,00
7 1 M2 PASANGAN KERAMIK MEJA DAN DINDING DAPUR 20 CM X 20 CM 3,74 M2 472.788,72
8 1 M PASANGAN PLINT KERAMIK LANTAI 58,30 M 1.351.860,40
8.984.154,43 8.984.154,43
E. PEKERJAAN ATAP
1 1 M2 PASANGAN ATAP GENTENG BETON 65,36 M2 4.630.481,29
2 1 M PASANGAN NOK BUBUNG GENTENG BETON 7,00 M1 435.736,00
3 1 M PASANGAN AKSESORIES KI/KA GENTENG BETON 0,57 M1 28.066,23
4 1 M PASANGAN WOODPLANK 26,50 M1 2.110.115,50
7.204.399,02 7.204.399,02
FIX RAP NGRSRI B‐38 TYPE LMA 1LT TYPE 36 Menjadi 47 TERBARU (4‐4‐22) 1
F. PEKERJAAN KUSEN, PINTU DAN JENDELA
1 1 M PASANGAN KUSEN KAYU LT. DASAR 75,55 M1 4.376.838,15
4.376.838,15 4.376.838,15
G. PEKERJAAN PERLENGKAPAN PINTU DAN JENDELA
1 1 BH PASANGAN DAUN PINTU KAYU PANEL KUNCI DAN ENGSEL 5,00 BH 3.626.305,00
2 1 M2 PASANGAN DAUN JENDELA KAYU + ENGSEL, SLOT DAN HAK ANGIN 0,51 M2 228.143,77
3 1 BH PASANGAN DAUN PINTU DAN KUSEN PVC (FIBER) 1,00 BH 299.354,00
4 1 BH DAUN JENDELA 0,51 BH 68.004,47
5 1 M1 KUSEN KAYU 75,55 BH 3.823.207,75
6 1 M2 PASANGAN KACA POLOS 5 MM 9,47 M2 1.350.970,76
7 1 BH PASANGAN DAUN PINTU DALAM DOBLE TRIPLEK KUNCI DAN ENGSEL 3,00 BH 2.342.781,00
11.738.766,75 11.738.766,75
H. PEKERJAAN SANITAIR
1 1 BH PASANGAN KLOSET DUDUK DAN JET WASHER 1,00 BH 2.248.380,00
2 1 BH PASANGAN DOUBLE KRAN AIR 1/2 DAN SHOWER 1,00 BH 640.356,00
3 1 BH PASANGAN KRAN AIR 1/2 3,00 BH 120.540,00
4 1 BH PASANGAN FLOOR DRAIN KM WC 1,00 BH 24.493,00
5 1 BH PASANGAN KITCHEN ZINK MEJA DAPUR 1,00 BH 422.476,00
3.456.245,00 3.456.245,00
I. PASANGAN INSTALASI AIR
1 1 M PASANGAN PIPA PVC DIAMETER 1/2 INCI AIR PDAM 39,70 M1 633.810,50
2 1 M PASANGAN PIPA PVC DIAMETER 2,5 INCI AIR KOTOR 14,00 M1 191.506,00
3 1 M PASANGAN PIPA PVC DIAMETER 3 INCI AIR HUJAN DARI BELAKANG 23,31 M1 1.002.912,75
4 1 M PASANGAN PIPA PVC DIAMETER 2 INCI AIR HUJAN DARI DAK BETON 5,30 M1 87.222,10
1.915.451,35 1.915.451,35
J. PEKERJAAN INSTALSI LISTRIK
1 1 TTK PASANGAN PIPA LISTRIK 5/8 DAN DUS INBOW 14,00 TITIK 186.676,00
186.676,00 186.676,00
K. PEKERJAAN PENGECATAN
1 1 M2 PASANGAN WATER PROOFING DAK BETON 2,23 M2 129.607,09
129.607,09 129.607,09
L. PEKERJAAN PEMASANGAN WATER TORN
1 1 UNIT PEMASANGAN TORN TANDOM 1,00 UNIT 1.010.177,00
1.010.177,00 1.010.177,00
M. PEKERJAAN LAIN-LAIN
1 1 LS PEMBERESAN LAHAN SETELAH SELESAI PEKERJAAN 1,00 LS 457.859,00
457.859,00 457.859,00
FIX RAP NGRSRI B‐38 TYPE LMA 1LT TYPE 36 Menjadi 47 TERBARU (4‐4‐22) 2
PEKERJAAN KHUSUS FINISING
4.029.351,19 4.029.351,19
B. PEKERJAAN PENGECATAN KAYU
1 1 M2 PENGECATAN DAUN PINTU PANEL CAT KAYU 27,39 M2 1.114.196,99
2 1 M1 PENGECATAN KUSEN PINTU DAN JENDELA CAT KAYU 75,55 M1 1.720.953,45
3 1 M1 PENGECATAN DAUN JENDELA CAT KAYU 6,55 M1 81.069,35
2.916.219,79 2.916.219,79
C. PEKERJAAN PENGECATAN MELAMIK
1 1 M2 PENGECATAN MELAMIK KUSEN PINTU DAN JENDELA 18,89 M2 2.953.759,46
2 1 M2 PENGECATAN MELAMIK DAUN PINTU PANEL 27,39 M2 4.283.752,70
3 1 M2 PENGECATAN MELAMIK DAUN JENDELA 1,44 M2 225.353,67
7.462.865,83 7.462.865,83
D. PEKERJAAN INSTALSI LISTRIK
1 1 TTK PASANG 1 TITIK STOP KONTAK 8,00 TITIK 829.376,00
2 1 TTK PASANG SAKLAR GANDA 2 TITIK LAMPU 3,00 TITIK 317.091,00
3 1 TTK PASANG SAKLAR TUNGGAL 1 TITIK LAMPU 2,00 TITIK 180.018,00
4 1 TTK PASANG 1 BUAH PANEL DAN GROUNDING 1,00 TITIK 172.406,00
5 1 TTK PASANG FITING LAMPU 4,00 TITIK 318.952,00
6 1 TTK PASANG DOWNLIGHT 7,00 TITIK 728.994,00
7 1 TTK PASANG 1 BUAH TITIK ANTENA 1,00 TITIK 259.941,00
2.806.778,00 2.806.778,00
E. PEKERJAAN PLAFOND
1 1 M2 LANGIT LANGIT GYPSUM BOARD 9 MM + RANGKA BESI HOLLOW 34,52 M2 3.536.336,67
2 1 M PASANGAN PROFIL GYPSUM 12 CM 52,50 M1 801.570,00
4.337.906,67 4.337.906,67
F. PEKERJAAN BAJA RINGAN
1 1 M2 PASANGAN RANGKA ATAP BAJA RINGAN 65,36 M2 8.790.712,01
2 1 M1 PASANGAN TALANG DATAR 18,00 M1 857.970,00
9.648.682,01 9.648.682,01
FIX RAP NGRSRI B‐38 TYPE LMA 1LT TYPE 36 Menjadi 47 TERBARU (4‐4‐22) 3
PEKERJAAN DILUAR BANGUNAN
A. PEKERJAAN RABAT BETON DAN PLAT DUICKER CARFORT
1 1 M3 MEMBUAT PLAT DUICKER CARFORT 0,73 M3 1.539.552,06
2 1 M3 MEMBUAT RABAT BETON CARFORT 2,10 M3 1.232.611,18
2.772.163,25 2.772.163,25
B. PEKERJAAN DINDING BATAS TAMAN DAN RUMPUT TAMAN
1 1 M2 PASANGAN DINDING BATA MERAH BATAS TAMAN 5,58 M2 460.356,13
2 1 M2 PLESTERAN DINDING BATAS TAMAN 11,17 M2 331.309,89
3 1 M2 ACIAN DINDING BATAS TAMAN 11,17 M2 204.586,59
4 1 M2 PASANGAN RUMPUT TAMAN DAN TANAH 17,24 M2 980.835,32
1.977.087,93 1.977.087,93
C. PEKERJAAN LAIN - LAIN
1 1 BH PEKERJAAN SEPTIC TANK DAN REMBESAN 1,00 BH 2.088.354,00
2.088.354,00 2.088.354,00
10 Januari 2023
Diperiksa Dibuat :
……………………………….. ……………………………….
Supervisor Teknik Staff Teknik
FIX RAP NGRSRI B‐38 TYPE LMA 1LT TYPE 36 Menjadi 47 TERBARU (4‐4‐22) 4