RENCANA PEMBUATAN TEMPAT BUDIDAYA UDANG (JANUARI 2022 - JUNI 2022

NO URAIAN BIAYA BOBOT


M1
1 DESAIN 1,500,000 3.2% 3.2%

2 PEMBELIAN BAHAN 18,000,000 38.7%

3 PENGADAAN PERALATAN K3 3,000,000 6.5%

4 PENGUKURAN KAYU 1,000,000 2.2%

5 PEMOTONGAN KAYU 4,000,000 8.6%

6 PELUBANGAN KAYU 1,000,000 2.2%

7 PEMASANGAN KERANGKA 6,000,000 12.9%

8 PEMASANGAN PELAMPUNG 3,000,000 6.5%

9 PEMASANGAN PAPAN 6,000,000 12.9%

10 PEMASANGAN JARING 3,000,000 6.5%


46,500,000 100.0%
RENCANA PROGES MINGGUAN 3.2%
AKUMULASI PROGES 3.2%
REALISASI PROGRES MINGGUAN 22.58%
AKUMULASI REALISASI PROGRES 22.58%
DEVIASI 19.35%

RENCANA DAN REALISASI


12.0%

10.0%

8.0%

6.0% RENCANA

4.0%

2.0%

0.0%
22.58% 11.61% 7.74% 2.58%
2.0%

0.0%
22.58% 11.61% 7.74% 2.58%

PROGRES MINGGU 1 SAMPAI MINGGU 4


RENCANA REALISASI
25.2% 44.52%
DEVIASI -22.58%
PENCAPAIAN PEKERJAAN
1.) DATA PROGRES REALISASI BULAN JANUARI BERDASARKAN M4 TANGGAL 29 FEBUARI
2.) PROGRES PEKEJAAN SAMPAI PENGADAAN PERALATAN K3

PEMENUHAN REALISASI TERHADAP RENCANA

2022
M1 M2 M3
RENCANA 22.58% 34.19% 41.94%
REALISASI 22.58% 11.61% 7.74%

DOKUMENTASI
M2 M3 M4 M5 M6 M7 M8 M9 M10 M11

7.7% 7.7% 7.7% 7.7% 7.7%

2.2% 2.2% 2.2%

1.1% 1.1%

2.9% 2.9% 2.9%

1.1% 1.1%

2.6% 2.6%

2.2% 9.9% 9.9% 11.7% 11.7% 10.6% 1.1% 1.1% 2.6% 2.6%
5.4% 15.3% 25.2% 36.8% 48.5% 59.1% 60.2% 61.3% 63.9% 66.5%
11.61% 7.74% 2.58%
34.19% 41.94% 44.52%
6.24% -7.53% -22.58%
M4 TANGGAL 29 FEBUARI 2022

PROBLEM IDENTIFIKASI DAN LANGKAH TINDAK LANJUT

1.) ADA KENDALA PADA PEMBELIAN BAHAN DAN ALAT K3 KARENA TERJADI KETERLAMBATAN DARI SUPP
M4 2.) MENAMBAH SUPLLAYER
44.52%
2.58%
M12 M13 M14 M15 M16 M17 M18 M19 M20 M21

2.6% 2.6% 2.6%

2.2% 2.2% 2.2%

4.3% 4.3% 4.3%

1.6%

2.6% 2.6% 2.6% 2.2% 2.2% 2.2% 4.3% 4.3% 4.3% 1.6%
69.0% 71.6% 74.2% 76.3% 78.5% 80.6% 84.9% 89.2% 93.5% 95.2%
TERLAMBATAN DARI SUPPLYER
M22 M23 M24

1.6% 1.6% 1.6%

1.6% 1.6% 1.6%


96.8% 98.4% 100.0%
PROGRES STATUS
Membangun Tempat Bdidaya Udang

MINGGU : M1

NO URAIAN BIAYA BOBOT


1 DESAIN 1,500,000 3.2%
2 PEMBELIAN BAHAN 18,000,000 38.7%
3 PENGADAAN PERALATAN K3 3,000,000 6.5%
4 PENGUKURAN KAYU 1,000,000 2.2%
5 PEMOTONGAN KAYU 4,000,000 8.6%
6 PELUBANGAN KAYU 1,000,000 2.2%
7 PEMASANGAN KERANGKA 6,000,000 12.9%
8 PEMASANGAN PELAMPUNG 3,000,000 6.5%
9 PEMASANGAN PAPAN 6,000,000 12.9%
10 PEMASANGAN JARING 3,000,000 6.5%

46,500,000 100.0%
PROGRES PERSENTASI PEKERJAAN
100 3.23%
50 19.35%
0 0
0
0
0
0
0
0
0
PRESTASI 22.58%
Membangun Tempat Bdidaya Udang

MINGGU : M2

NO URAIAN BIAYA BOBOT


1 DESAIN 1,500,000 3.2%
2 PEMBELIAN BAHAN 18,000,000 38.7%
3 PENGADAAN PERALATAN K3 3,000,000 6.5%
4 PENGUKURAN KAYU 1,000,000 2.2%
5 PEMOTONGAN KAYU 4,000,000 8.6%
6 PELUBANGAN KAYU 1,000,000 2.2%
7 PEMASANGAN KERANGKA 6,000,000 12.9%
8 PEMASANGAN PELAMPUNG 3,000,000 6.5%
9 PEMASANGAN PAPAN 6,000,000 12.9%
10 PEMASANGAN JARING 3,000,000 6.5%

46,500,000 100.0%
PROGRES PERSENTASI PEKERJAAN
100 3.23%
80 30.97%
0 0
0
0
0
0
0
0
0
PRESTASI 34.19%
Membangun Tempat Bdidaya Udang

MINGGU : M3

NO URAIAN BIAYA BOBOT PROGRES


1 DESAIN 1,500,000 3.2% 100
2 PEMBELIAN BAHAN 18,000,000 38.7% 100
3 PENGADAAN PERALATAN K3 3,000,000 6.5% 7
4 PENGUKURAN KAYU 1,000,000 2.2% 0
5 PEMOTONGAN KAYU 4,000,000 8.6% 0
6 PELUBANGAN KAYU 1,000,000 2.2% 0
7 PEMASANGAN KERANGKA 6,000,000 12.9% 0
8 PEMASANGAN PELAMPUNG 3,000,000 6.5% 0
9 PEMASANGAN PAPAN 6,000,000 12.9% 0
10 PEMASANGAN JARING 3,000,000 6.5% 0
PRESTASI

46,500,000 100.0%
PERSENTASI PEKERJAAN
3.23%
38.71%
0.45%

41.94%
Membangun Tempat Bdidaya Udang

MINGGU : M4

NO URAIAN BIAYA BOBOT PROGRES


1 DESAIN 1,500,000 3.2% 100
2 PEMBELIAN BAHAN 18,000,000 38.7% 100
3 PENGADAAN PERALATAN K3 3,000,000 6.5% 40
4 PENGUKURAN KAYU 1,000,000 2.2% 0
5 PEMOTONGAN KAYU 4,000,000 8.6% 0
6 PELUBANGAN KAYU 1,000,000 2.2% 0
7 PEMASANGAN KERANGKA 6,000,000 12.9% 0
8 PEMASANGAN PELAMPUNG 3,000,000 6.5% 0
9 PEMASANGAN PAPAN 6,000,000 12.9% 0
10 PEMASANGAN JARING 3,000,000 6.5% 0
PRESTASI

46,500,000 100.0%
PERSENTASI PEKERJAAN
3.23%
38.71%
2.58%

44.52%