I Pekerjaan Persiapan
1 pembersihan area kerja 52.5 m2 25,000.00 1,312,500.00
2 Bongkar benteng sebelah timur 8.7 m 50,000.00 435,000.00
3 levelling area 52.55 m2 25,000.00 1,313,750.00
II Pek. Tanah dan Pondasi -
1 Galian pondasi Kolom 100.100.150cm 35.72 m3 30,000.00 1,071,600.00
2 Pemasangan Lantai kerja Kolom t.5cm 35.72 m3 50,000.00 1,786,000.00
3 Galian pondasi 18 m3 50,000.00 900,000.00
5 Urugan tanah kembali 35.72 m3 20,000.00 714,400.00
JUMLAH 38,676,250.00
PROGRES PROGRES
INPUT
Bobot MINGGU INI SAMPAI MINGGU
DATA
(%) INI (%)
I Pekerjaan Persiapan
1 pembersihan area kerja 8.70 m2 15,000.00 130,500.00
2 Bongkar benteng sebelah timur 8.70 m 50,000.00 435,000.00
3 levelling area 6.00 m2 500,000.00 3,000,000.00
II Pek. Tanah dan Pondasi -
1 Galian pondasi Kolom 100.100.150cm 43.20 m3 69,575.00 3,005,640.00
2 Pemasangan Lantai kerja Kolom t.5cm 2.16 m3 148,718.00 321,230.88
3 Galian pondasi 6.48 m3 461,414.73 2,989,967.45
4 #REF! 29.70 m3 800,000.00 23,760,000.00
5 Urugan tanah kembali 4.86 m3 30,000.00 145,800.00
6 Urug pasir lantai kerja t.5cm 2.31 m3 148,718.00 343,910.38
III Pek. Struktur -
1 Pek. Bekesting sloof 27.00 m2 200,000.00 5,400,000.00
2 Pek. Bekesting kolom 31.68 m2 250,000.00 7,920,000.00
3 Pek. Bekesting balok 29.29 m2 225,000.00 6,590,155.89
4 Pek. Pembesian sloof 127.28 kg 15,000.00 1,909,170.00
5 Pek. Pembesian kolom 199.83 kg 15,000.00 2,997,456.00
6 Pek. Pembesian balok 138.07 kg 15,000.00 2,071,066.33
7 Pek. Pengecoran sloof 2.03 m3 850,000.00 1,721,250.00
8 Pek. Pengecoran kolom 1.19 m3 850,000.00 1,009,800.00
9 Pek. Pengecoran balok 2.20 m3 850,000.00 1,867,210.84
JUMLAH 65,618,157.76
PROGRES PROGRES PROGRES
INPUT
Bobot MINGGU MINGGU INI SAMPAI MINGGU
DATA
LALU (%) (%) INI (%)
I Pek. Persiapan
1 Pembersihan lahan 77 m2 15,180.00 1,168,860.00 1.77%
2 Bongkar benteng sebelah timur 32 m 92,593.40 2,962,988.80 4.49%
3 levelling area 6 m2 500,000.00 3,000,000.00 4.54%
II Pek. Tanah dan Pondasi -
1 Galian pondasi Kolom 100.100.150cm 43.2 m3 69,575.00 3,005,640.00 4.55%
2 Pemasangan Lantai kerja Kolom t.5cm 2.16 m3 148,718.00 321,230.88 0.49%
3 Galian pondasi 6.48 m3 461,414.73 2,989,967.45 4.53%
4 #REF! 29.7 m3 800,000.00 23,760,000.00 35.99%
5 Urugan tanah kembali 4.86 m3 30,000.00 145,800.00 0.22%
6 Urug pasir lantai kerja t.5cm 2.3125 m3 148,718.00 343,910.38 0.52%
III Pek. Struktur -
1 Pek. Bekesting sloof 44.66 m1 50,000.00 2,233,000.00 3.38%
2 Pek. Bekesting kolom 31.68 m2 250,000.00 7,920,000.00 12.00%
3 Pek. Bekesting balok 29.2896 m2 225,000.00 6,590,155.89 9.98%
4 Pek. Pembesian sloof 127.278 kg 15,000.00 1,909,170.00 2.89%
5 Pek. Pembesian kolom 199.83 kg 15,000.00 2,997,456.00 4.54%
6 Pek. Pembesian balok 138.071 kg 15,000.00 2,071,066.33 3.14%
7 Pek. Pengecoran sloof 2.025 m3 850,000.00 1,721,250.00 2.61%
8 Pek. Pengecoran kolom 1.188 m3 850,000.00 1,009,800.00 1.53%
9 Pek. Pengecoran balok 2.19672 m3 850,000.00 1,867,210.84 2.83%
JUMLAH 66,017,506.56 100.00%
PROGRES PROGRES PROGRES
INPUT
MINGGU MINGGU INI SAMPAI MINGGU
DATA
LALU (%) (%) INI (%)
100%
80%
60%
40%
20%
0%
1 2 3 4
10 minggu
minggu KE-
0 1 2 3 4 5 6 7 8 9 10
1.75%
14.50%
4.50%
4.51%
0.48%
4.49%
11.88% 11.88% 11.88%
0.22%
0.52%
4.05% 4.05%
3.96% 3.96% 3.96%
4.94% 4.94%
2.86%
2.25% 2.25%
3.11%
2.58%
0.76% 0.76%
2.80%
0% 20.75% 9.48% 11.88% 11.88% 15.93% 7.65% 11.15% 16.84% 4.72% 3.56%
0% 20.75% 30.23% 42.11% 53.99% 69.93% 77.58% 88.73% 105.57% 110.29% 113.85%
0% 1.42% 12.07% 26.35%
0% 1.42% 13.49% 39.84%
2 3 4 5 6 7 8 9 10 11
RAB
4.51%
0.48%
80% 4.49%
11.88% 11.88% 11.88%
0.22%
60% 0.52%
4.05% 4.05%
40% 3.96% 3.96% 3.96%
4.94% 4.94%
2.86%
20% 2.25% 2.25%
3.11%
2.58%
0.76% 0.76%
0%
1 2 3 4 5 6 7 8 9 10 11 2.80%
0% 20.75% 9.48% 11.88% 11.88% 15.93% 7.65% 11.15% 16.84% 4.72% 3.56%
0% 20.75% 30.23% 42.11% 53.99% 69.93% 77.58% 88.73% 105.57% 110.29% 113.85%
0% 1.42% 12.07% 26.35%
0% 1.42% 13.49% 39.84%