TIME SCHEDULE

PEKERJAAN : REVITALISASI GEDUNG


LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :1
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%
1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%
0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211%
70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65% 20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
10.00%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45%
Ralisasi Komulatif 0.45%
Prestasi -4.40%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :2
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%
1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%
0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211%
70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65% 20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
2 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
10.00%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
1 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 1.56% 1.11%
Ralisasi Komulatif 1.56% 2.67%
Prestasi -3.29% -10.14%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :3
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%
1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%
0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211%
70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65% 20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
10.00%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45% 1.11% 8.29%
Ralisasi Komulatif 0.45% 1.56% 9.84%
Prestasi -4.40% -11.25% -14.48%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :4
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%

1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%


0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211% 70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :5
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%

1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%


0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211% 70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65%
20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03% 10.00%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45% 1.11% 8.29% 9.86% 13.40%
Ralisasi Komulatif 0.45% 1.56% 9.84% 19.71% 33.11%
Prestasi -4.40% -11.25% -14.48% -19.07% -22.81%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :6
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%

1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%


0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211% 70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65%
20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03% 10.00%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45% 1.11% 8.29% 9.86% 13.40% 13.34%
Ralisasi Komulatif 0.45% 1.56% 9.84% 19.71% 33.11% 46.44%
Prestasi -4.40% -11.25% -14.48% -19.07% -22.81% -22.30%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :7
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%

1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%


0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211% 70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65%
20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03% 10.00%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45% 1.11% 8.29% 9.86% 13.40% 13.34% 12.13%
Ralisasi Komulatif 0.45% 1.56% 9.84% 19.71% 33.11% 46.44% 58.57%
Prestasi -4.40% -11.25% -14.48% -19.07% -22.81% -22.30% -20.72%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :8
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%

1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%


0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211% 70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65%
20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03% 10.00%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45% 1.11% 8.29% 9.86% 13.40% 13.34% 12.13% 16.07%
Ralisasi Komulatif 0.45% 1.56% 9.84% 19.71% 33.11% 46.44% 58.57% 74.64%
Prestasi -4.40% -11.25% -14.48% -19.07% -22.81% -22.30% -20.72% -14.22%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE :9
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%

1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%


0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211% 70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65%
20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03% 10.00%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45% 1.11% 8.29% 9.86% 13.40% 13.34% 12.13% 16.07% 14.66%
Ralisasi Komulatif 0.45% 1.56% 9.84% 19.71% 33.11% 46.44% 58.57% 74.64% 89.30%
Prestasi -4.40% -11.25% -14.48% -19.07% -22.81% -22.30% -20.72% -14.22% -6.36%
TIME SCHEDULE
PEKERJAAN : REVITALISASI GEDUNG
LOKASI : SMKS ISLAM AN-NUURU, KECAMATAN TIRTOYUDO, KABUPATEN MALANG
MINGGU KE : 10
JADWAL PELAKSANAAN
NO. URAIAN VOLUME BOBOT Okt Nopember Desember SKALA
28-2 3-9 10-16 17-23 24-30 1-7 8-14 15-21 22-28 29-31
I PEKERJAAN PERSIAPAN 100.00%

1 Membersihkan lapangan dan peralatan 324.00 m2 0.094% 0.05% 0.05%


0.094%
II PEKERJAAN PASANGAN
1 Pasangan Bata hebel 1 Pc : 6 Ps 529.30 m2 3.870% 1.29% 1.29% 1.29%
2 Plesteran 1 Pc : 6 Ps tebal 15 mm 1,058.60 m2 3.003% 1.00% 1.00% 1.00%
90.00%
3 Acian 1,058.60 m2 2.316% 1.16% 1.16%
4 Benangan 297.60 m1 0.395% 0.20% 0.20%
9.584%
III PEKERJAAN BETON
1 Membuat kolom beton bertulang 25/35 15.02 m3 7.220% 3.61% 3.61%
2 Membuat kolom dan ring beton bertulang 15/15 4.41 m3 2.369% 1.18% 1.18% 80.00%
3 Membuat balok beton bertulang 20/60 7.84 m3 3.216% 1.07% 1.07% 1.07%
4 Membuat balok beton bertulang 20/40 10.22 m3 4.194% 2.10% 2.10%
5 Membuat balok beton bertulang 15/20 0.39 m3 0.160% 0.16%
6 Membuat plat dag beton bertulang 54.69 m3 25.051% 8.35% 8.35% 8.35%
42.211% 70.00%
IV PEKERJAAN ATAP DAN PLAFOND
1 Pasang rangka atap galvalume 152.00 m2 1.655% 0.83% 0.83%
2 Pasang atap galvalum 152.00 m2 0.822% 0.82%
3 Pasang bubung multiroof 15.20 m1 0.118% 0.12%
4 Pasang rangka plafon 121.60 m2 0.766% 0.38% 0.38%
5 Pasang penutup plafon 121.60 m2 0.644% 0.64% 60.00%
4.004%
V PEKERJAAN KUSEN DAN PENGUNCI
1 Pasang kusen pintu dan jendela beton 7.29 m3 1.753% 0.88% 0.88%
2 Pasang daun pintu aluminium 21.12 m2 1.328% 1.33%
3 Pasang daun jendela kaca aluminium 27.60 m2 0.969% 0.97%
50.00%
4 Pasang engsel pintu 12.00 bh 0.095% 0.05% 0.05%
5 Pasang engsel jendela 23.00 bh 0.060% 0.03% 0.03%
6 Pasang grendel jendela 23.00 bh 0.053% 0.03% 0.03%
7 Pasang kait angin 23.00 bh 0.072% 0.04% 0.04%
8 Pasang kunci pintu 8.00 bh 0.106% 0.05% 0.05%
4.436% 40.00%
VI PEKERJAAN LANTAI
1 Pasang Lantai Keramik 30x30 594.00 m2 5.668% 1.89% 1.89% 1.89%
5.668%
VII PEKERJAAN LISTRIK
1 Memasang lampu pijar SL 18 watt dan instalasi 48.00 m1 0.833% 0.28% 0.28% 0.28%
30.00%
2 Memasang Saklar ganda 20.00 m1 0.507% 0.17% 0.17% 0.17%
3 Memasang Saklar tunggal 4.00 bh 0.098% 0.03% 0.03% 0.03%
4 Memasang Stop Kontak 20.00 bh 0.482% 0.16% 0.16% 0.16%
1.920%
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 529.30 m2 1.959% 0.65% 0.65% 0.65%
20.00%
2 Pengecatan plafon 594.00 m2 2.199% 1.10% 1.10%
4.158%
VIII PEKERJAAN INTERIOR DAN MEBELAIR
1 Interior RPS MM
- Mini theater 1.00 ls 3.094% 1.55% 1.55%
- Ruang rekaman dan ruang kontrol 1.00 ls 3.094% 1.03% 1.03% 1.03% 10.00%
- Studio foto dan vidio 1.00 ls 3.094% 0.77% 0.77% 0.77% 0.77%
- Laboratorium komputer 1.00 ls 2.321% 0.77% 0.77% 0.77%
2 Interior RPS DPIB 1.00 ls 5.492% 1.83% 1.83% 1.83%
3 Mebelair RPS DPIB 1.00 ls 10.829% 2.71% 2.71% 2.71% 2.71%
27.925% 0.00%
1 2 3 4 5 6 7 8 9 10
Rencana Tiap minggu 4.84% 7.96% 11.52% 14.46% 17.14% 12.82% 10.55% 9.57% 6.80% 4.34%
Rencana Komulatif 4.84% 12.81% 24.33% 38.78% 55.92% 68.74% 79.29% 88.86% 95.66% 100.0%
Relisasi Tiap Minggu 0.45% 1.11% 8.29% 9.86% 13.40% 13.34% 12.13% 16.07% 14.66% 10.70%
Ralisasi Komulatif 0.45% 1.56% 9.84% 19.71% 33.11% 46.44% 58.57% 74.64% 89.30% 100.0%
Prestasi -4.40% -11.25% -14.48% -19.07% -22.81% -22.30% -20.72% -14.22% -6.36% 0.00%