BOBOT PROGRE

NO. DESKRIPSI PEKERJAAN VOLUME SATUAN


(%) S (%)
A. PONDASI CONVEYOR CV 01, CV 02 & CV 03
1 CONVEYOR CV 01
a Lantai Kerja Tebal 5 cm + Bowplank 1.34 m3 10% 100%
b Beton 73.44 m3 40% 100%
c Pekerjaan Pembesian 6821.88 kg 30% 100%
d Bekisting 82.49 m2 20% 100%
TOTAL 100% 100%
2 CONVEYOR CV 02
a Lantai Kerja Tebal 5 cm + Bowplank 0.78 m3 10% 100.00%
b Beton 39.47 m3 40% 100.00%
c Pekerjaan Pembesian 6365.17 kg 30% 100.00%
d Bekisting 55.27 m2 20% 100.00%
TOTAL 100% 100%
3 CONVEYOR CV 03
a Lantai Kerja Tebal 5 cm + Bowplank 5.97 m3 10% 100.00%
b Beton 109.01 m3 40% 100.00%
c Pekerjaan Pembesian 14422.74 kg 30% 100.00%
d Bekisting 573.21 m2 20% 100.00%
TOTAL 100% 100%

B. PEKERJAAN RETAINING WALL


1 Lantai Kerja Tebal 5 cm + Bowplank 1.94 m3 5% 95%
2 Beton 441 m3 35% 95%
3 Lantai Hopper 120 m3 15% 95%
4 Pekerjaan Pembesian 60964.57 kg 30% 95%
5 Bekisting 1387 m2 15% 95%
TOTAL 100% 95%

C. PEKERJAAN MCC ROOM


1 Pekerjaan Galian 14.18 m3 0.19% 100%
2 Pekerjaan Pondasi Minipile 48 m 7.44% 100%
3 Pekerjaan Sloof 2.23 m3 6.61% 100%
4 Pekerjaan Pelat Lantai 5.37 m3 6.29% 95%
5 Pekerjaan Pelat Gutter 6.04 m3 7.28% 100%
6 Pekerjaan Kolom 15 cm x 25 cm 1.14 m3 3.59% 100%
7 Pekerjaan Kolom 15 cm x 15 cm 0.55 m3 1.93% 100%
8 Pekerjaan Balok 15 cm x 25 cm 0.82 m3 2.32% 100%
9 Pekerjaan Balok 15 cm x 20 cm 3.87 m3 10.94% 100%
10 Pekerjaan Dinding 157.89 m2 30.25% 90%
11 Pekerjaan Dak Aap 15.76 m3 17.23% 90%
12 Pekerjaan Dak Lantai Luar 4.6 m3 3.41% 90%
13 Pekerjaan Kanopi 2.2 m3 1.55% 90%
14 Pekerjaan Pintu 3 pcs 0.97% 90%
TOTAL 100% 96%

D. PEKERJAAN CONTROL ROOM


1 Pekerjaan Pondasi 0.5 m3 5.26% 100%
2 Pekerjaan Sloof 1.37 m3 5.75% 100%
3 Pekerjaan Pelat Lantai 1 5.07 m3 6.52% 100%
4 Pekerjaan Pelat Lantai 2 4.95 m3 6.37% 100%
5 Pekerjaan Kolom 15 cm x 25 cm 1.05 m3 4.67% 100%
6 Pekerjaan Kolom 15 cm x 15 cm 0.79 m3 3.94% 100%
7 Pekerjaan Balok Lantai 2 1.7 m3 5.91% 100%
8 Pekerjaan Balok Ring 1.76 m3 9.73% 100%
9 Pekerjaan Dinding 140 m2 37.91% 100%
10 Pekerjaan Dak Aap 5.81 m3 9.67% 100%
11 Pekerjaan Tangga 1 unit 1.02% 40%
12 Pekerjaan Jendela 15 pcs 2.33% 100%
13 Pekerjaan Pintu 2 pcs 0.91% 100%
TOTAL 100% 95%

E. PEKERJAAN POWER HOUSE


1 Pekerjaan Persiapan 344 m2 0.95% 100%
2 Pekerjaan Tanah 344 m3 2.27% 100%
3 Pekerjaan Pondasi 17.16 m3 9.62% 100%
4 Pekerjaan U-ditch 104 m 12.51% 100%
5 Pekerjaan Sloof 10.32 m3 9.62% 100%
6 Pekerjaan Kolom 9.36 m3 9.62% 100%
7 Pekerjaan Pelat 46.08 m3 9.62% 100%
8 Pekerjaan Balok 10.32 m3 9.62% 100%
9 Pekerjaan Dinding 63 m3 16.38% 100%
10 Pekerjaan Penutup Atap & Plafon 344 m2 13.78% 100%
11 Pekerjaan Pengecatan 420 m2 0.10% 0%
12 Pekerjaan Pintu & Jendela 7 pcs 5.88% 0%
TOTAL 100.00% 93.99%
BOBOT PROGRES
NO. DESKRIPSI PEKERJAAN VOLUME SATUAN
(%) (%)
1 Pekerjaan Persiapan 344 m2 0.95% 100%
2 Pekerjaan Tanah 344 m3 2.27% 100%
3 Pekerjaan Pondasi 17.16 m3 9.62% 100%
4 Pekerjaan U-ditch 104 m 12.51% 100%
5 Pekerjaan Sloof 10.32 m3 9.62% 100%
6 Pekerjaan Kolom 9.36 m3 9.62% 90% 8.66%
7 Pekerjaan Pelat 46.08 m3 9.62% 95% 9.14%
8 Pekerjaan Balok 10.32 m3 9.62% 90% 8.66%
9 Pekerjaan Dinding 63 m3 16.38% 70% 11.47%
10 Pekerjaan Penutup Atap & Plafon 344 m2 13.78% 30% 4.13%
11 Pekerjaan Pengecatan 420 m2 0.10% 0%
12 Pekerjaan Pintu & Jendela 7 pcs 5.88% 0%
TOTAL 100.00% 77.03%
BOBOT PROGRES
NO. DESKRIPSI PEKERJAAN VOLUME SATUAN
(%) (%)
1 Pekerjaan Pondasi 17.16 m3 9.62% 100%
2 Pekerjaan Sloof 10.32 m3 9.62% 100%
3 Pekerjaan Kolom 9.36 m3 9.62% 90%
4 Pekerjaan Pelat Lantai 46.08 m3 9.62% 95%
5 Pekerjaan Balok 10.32 m3 9.62% 90%
6 Pekerjaan Dinding 63 m3 16.38% 70%
7 Pekerjaan Dak Atap 420 m2 0.10% 0%
8 Pekerjaan Tangga 7 pcs 5.88% 0%
TOTAL 100.00%
BOBOT PROGRES
NO. DESKRIPSI PEKERJAAN VOLUME SATUAN
(%) (%)
1 Pekerjaan Tanah 344 m3 2.27% 100%
2 Pekerjaan Pondasi 17.16 m3 9.62% 100%
3 Pekerjaan Pelat Gutter 104 m 12.51% 100%
4 Pekerjaan Sloof 10.32 m3 9.62% 100%
5 Pekerjaan Kolom 9.36 m3 9.62% 90% 8.66%
6 Pekerjaan Pelat Lantai 46.08 m3 9.62% 95% 9.14%
7 Pekerjaan Balok 10.32 m3 9.62% 90% 8.66%
8 Pekerjaan Dinding 63 m3 16.38% 70% 11.47%
9 Pekerjaan Dak Atap 344 m2 13.78% 30% 4.13%
10 Pekerjaan Kanopi 420 m2 0.10% 0%
TOTAL 100.00% #REF!