(%) S (%) A. PONDASI CONVEYOR CV 01, CV 02 & CV 03 1 CONVEYOR CV 01 a Lantai Kerja Tebal 5 cm + Bowplank 1.34 m3 10% 100% b Beton 73.44 m3 40% 100% c Pekerjaan Pembesian 6821.88 kg 30% 100% d Bekisting 82.49 m2 20% 100% TOTAL 100% 100% 2 CONVEYOR CV 02 a Lantai Kerja Tebal 5 cm + Bowplank 0.78 m3 10% 100.00% b Beton 39.47 m3 40% 100.00% c Pekerjaan Pembesian 6365.17 kg 30% 100.00% d Bekisting 55.27 m2 20% 100.00% TOTAL 100% 100% 3 CONVEYOR CV 03 a Lantai Kerja Tebal 5 cm + Bowplank 5.97 m3 10% 100.00% b Beton 109.01 m3 40% 100.00% c Pekerjaan Pembesian 14422.74 kg 30% 100.00% d Bekisting 573.21 m2 20% 100.00% TOTAL 100% 100%