BOBOT
NO URAIAN VOL. SAT. BOBOT PROGRESS TERLAKSANA
A PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1 ls 0.32% 100.00% 0.32%
3 Pengukuran dan Pasangan Bouwplank 253.29 m2 0.38% 100.00% 0.38%
4 Pekerjaan Bongkaran Atap 110.843 m2 1.43% 100.00% 1.43%
5 Pekerjaan Bongkaran lain-lain 1 ls 1.07% 100.00% 1.07%
LANTAI 1
B PEKERJAAN GALIAN DAN URUGAN
1 Galian Pondasi 0.512 m3 0.01% 100.00% 0.01%
2 Galian Carport 16 m3 0.29% 25.00% 0.07%
LANTAI II
P PEKERJAAN PENGECATAN
1 Cat Interior Mowilex Cendana, White 172.73 m2 1.76% 0.00% 0.00%
2 Cat Eksterior Mowilex Eksterior 103.06 m2 1.16% 0.00% 0.00%
3 Cat Plafond Vinilex Ceiling 80.68 m2 0.87% 100.00% 0.87%
Q PEKERJAAN PLUMBING
1 Instalasi Pipa Air Closet 4" 12 m' 0.48% 100.00% 0.48%
2 Instalasi Pipa Air Kotor 3" 32 m' 0.86% 100.00% 0.86%
3 Instalasi Pipa Air Bersih 1/2" 28 m' 0.27% 100.00% 0.27%
4 Instalasi Pipa Air Panas 10 m' 0.32% 100.00% 0.32%
S PEKERJAAN PENGELASAN
Railing Tangga Besi Galvanis Finish Duco + Acrylic
1 5mm + Handle Kayu 12.19 m' 0.00%
2.82% 0.00%
Railing Balkon Besi Galvanis Finish Duco + Acrylic
2 5mm + Handle Besi 4.5 m' 0.00%
1.02% 0.00%
3 Kanopi Solar Flat Teras Belakang 18.83 m2 3.54% 0.00% 0.00%
Pagar Besi Galvanis + Perforated Metal + Dinding
4 Finish Batu Alam 1 ls 0.00%
2.58% 0.00%
T PEKERJAAN FAÇADE
1 Dinding Batu Alam 14 m2 0.86% 0.00% 0.00%
2 Topian Beton 0.13 m3 0.11% 100.00% 0.11%
3 Pasangan Batu Andesit Carport 65.4 m2 3.79% 0.00% 0.00%
4 Pasangan Lantai Custom Taman 10.35 m2 0.33% 0.00% 0.00%
5 Pas. Dinding Roster R. Service Area 5.15 m2 0.45% 100.00% 0.45%
TOTAL HARGA
OVERHEAD 2% 1.93% 100.00% 1.93%
TOTAL HARGA PEKERJAAN 100.00% 70.10%
DIBULATKAN