KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS
A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100% 0.76%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100% 0.73%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100% 5.00%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100% 0.21%
B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 100% 0.68%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 100% 1.33%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 100% 0.73%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%
1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%
J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%
Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%
Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%
100.00% 10.47%
RENCANA ANGGARAN BIAYA (RAB)
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 3 (Tiga)
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS
A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100% 0.76%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100% 0.73%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100% 5.00%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100% 0.21%
B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 100% 0.68%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 100% 1.33%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 100% 0.73%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%
1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%
J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%
Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%
Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%
100.00% 10.47%
RENCANA ANGGARAN BIAYA (RAB)
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 4 (Empat)
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS
A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100% 0.76%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100% 0.73%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100% 5.00%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100% 0.21%
B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 100% 0.68%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 100% 1.33%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 100% 0.73%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%
1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%
J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%
Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%
Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%
100.00% 10.47%
RENCANA ANGGARAN BIAYA (RAB)
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 5 (lima)
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS
A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100% 0.76%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100% 0.73%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100% 5.00%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100% 0.21%
B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 0.00%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 50% 0.66%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 0.00%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%
1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%
J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%
Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%
Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%
100.00% 7.37%