RENCANA ANGGARAN BIAYA (RAB)

Proyek : TYPE 36 STANDARD


Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 2 3 4 5

KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS

A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100% 0.76%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100% 0.73%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100% 5.00%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100% 0.21%

SUB TOTAL BIAYA PEKERJAAN PONDASI

B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 100% 0.68%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 100% 1.33%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 100% 0.73%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%

SUB TOTAL BIAYA PEKERJAAN STRUKTUR

C PEKERJAAN PASANGAN DINDING


1 C1072 Pas.Bata Ringan Tebal 1/2 Batu T.7,5cm 1:4/m2 190.09 m2 10.25% 10% 1.02%
2 F1003 Plesteran Bata 1:5/m2 T.1,52cm 380.18 m2 16.34%
3 F1018 Acian Plesteran Tebal 23mm/m2 380.18 m2 12.73%

SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING

D PEKERJAAN RANGKA & PENUTUP ATAP

1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%

SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP

E PEKERJAAN PELAPIS DINDING


1 F1096 Pas.Keramik Dinding Lokal 20X20/m2 Mulia 8.01 m2 0.65%

SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING

F PEKERJAAN PENUTUP PLAFOND


1 G1005 Rangka Plafond Besi Hollow/m2 (Bawah Kap/Kudakuda) 38.79 m2 1.95%
2 G1012 Plafond Gypsum 9mm/m2 38.79 m2 1.33%

SUB TOTAL BIAYA PEKERJAAN PELAPIS PLAFOND

G PEKERJAAN PELAPIS LANTAI


3 H1129 Pas.Keramik Lantai Lokal 30X30/m2 Mulia 33.54 m2 2.18%
2 H1127 Pas.Keramik Lantai Lokal 20X20/m2 Mulia (wc) 1.72 m2 0.12%

SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI

H PEKERJAAN PINTU, JENDELA, KACA


1 K1017 Kusen Pintu, Jendela Alumunium 4" 30.20 m2 1.44%
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS
2 I1003 Pintu Full Panel Solid Bangkirai Kwalitet Politur/bh 5.00 bh 2.60%
3 I1003 Daun Pintu Kaca 4.00 bh 2.08%
4 I1106 Jendela Rangka Kaca Bangkirai Kwalitet Cat/m2 3.00 m2 0.59%

SUB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA

J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%

SUB TOTAL BIAYA PEKERJAAN PENGECATAN

K PEKERJAAN INSTALASI SANITASI & ACCESSORIES


Air Bersih
1 L1101 Pemipaan PVC AW dia 11/2"/m' (Dibawah Tanah) 10.00 m' 0.28%
2 L1103 Pemipaan PVC AW dia 1"/m' (Dibawah Tanah) 10.00 m' 0.27%

Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%

Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%

SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI

L PEKERJAAN INSTALASI LISTRIK

1 N1001 Titik Lampu Dalam/ttk Bawah Plafond 8.00 ttk 0.69%


2 N1004 Titik Stop Kontak Biasa/ttk 8.00 ttk 0.75%

SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK

M PEKERJAAN LUAR & HALAMAN


1 O1087 Carport 13.16 m2 1.66%
2 O1082 Plat Duiker Pintu Masuk L.0,75M/m' 4.00 m' 0.62%

SUB TOTAL BIAYA PEKERJAAN LUAR & HALAMAN

100.00% 10.47%
RENCANA ANGGARAN BIAYA (RAB)
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 2 (Dua)

KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE

A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100%

SUB TOTAL BIAYA PEKERJAAN PONDASI

B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 100%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 100%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 100%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%

SUB TOTAL BIAYA PEKERJAAN STRUKTUR

C PEKERJAAN PASANGAN DINDING


1 C1072 Pas.Bata Ringan Tebal 1/2 Batu T.7,5cm 1:4/m2 190.09 m2 10.25% 10%
2 F1003 Plesteran Bata 1:5/m2 T.1,52cm 380.18 m2 16.34%
3 F1018 Acian Plesteran Tebal 23mm/m2 380.18 m2 12.73%

SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING

D PEKERJAAN RANGKA & PENUTUP ATAP

1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%

SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP

E PEKERJAAN PELAPIS DINDING


1 F1096 Pas.Keramik Dinding Lokal 20X20/m2 Mulia 8.01 m2 0.65%

SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING

F PEKERJAAN PENUTUP PLAFOND


1 G1005 Rangka Plafond Besi Hollow/m2 (Bawah Kap/Kudakuda) 38.79 m2 1.95%
2 G1012 Plafond Gypsum 9mm/m2 38.79 m2 1.33%

SUB TOTAL BIAYA PEKERJAAN PELAPIS PLAFOND

G PEKERJAAN PELAPIS LANTAI


3 H1129 Pas.Keramik Lantai Lokal 30X30/m2 Mulia 33.54 m2 2.18%
2 H1127 Pas.Keramik Lantai Lokal 20X20/m2 Mulia (wc) 1.72 m2 0.12%
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE

SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI

H PEKERJAAN PINTU, JENDELA, KACA


1 K1017 Kusen Pintu, Jendela Alumunium 4" 30.20 m2 1.44%
2 I1003 Pintu Full Panel Solid Bangkirai Kwalitet Politur/bh 5.00 bh 2.60%
3 I1003 Daun Pintu Kaca 4.00 bh 2.08%
4 I1106 Jendela Rangka Kaca Bangkirai Kwalitet Cat/m2 3.00 m2 0.59%

SUB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA

J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%

SUB TOTAL BIAYA PEKERJAAN PENGECATAN

K PEKERJAAN INSTALASI SANITASI & ACCESSORIES


Air Bersih
1 L1101 Pemipaan PVC AW dia 11/2"/m' (Dibawah Tanah) 10.00 m' 0.28%
2 L1103 Pemipaan PVC AW dia 1"/m' (Dibawah Tanah) 10.00 m' 0.27%

Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%

Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%

SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI

L PEKERJAAN INSTALASI LISTRIK

1 N1001 Titik Lampu Dalam/ttk Bawah Plafond 8.00 ttk 0.69%


2 N1004 Titik Stop Kontak Biasa/ttk 8.00 ttk 0.75%

SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK

M PEKERJAAN LUAR & HALAMAN


1 O1087 Carport 13.16 m2 1.66%
2 O1082 Plat Duiker Pintu Masuk L.0,75M/m' 4.00 m' 0.62%

SUB TOTAL BIAYA PEKERJAAN LUAR & HALAMAN

100.00%
KEMAJUAN PEKERJAAN

PROGRESS

0.76%
0.73%
5.00%
0.21%

0.68%
1.33%
0.73%

1.02%
KEMAJUAN PEKERJAAN

PROGRESS

10.47%
RENCANA ANGGARAN BIAYA (RAB)
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 3 (Tiga)

KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume kontrak
Satuan Bobot %
PROSENTASE PROGRESS

A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100% 0.76%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100% 0.73%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100% 5.00%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100% 0.21%

SUB TOTAL BIAYA PEKERJAAN PONDASI

B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 100% 0.68%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 100% 1.33%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 100% 0.73%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%

SUB TOTAL BIAYA PEKERJAAN STRUKTUR

C PEKERJAAN PASANGAN DINDING


1 C1072 Pas.Bata Ringan Tebal 1/2 Batu T.7,5cm 1:4/m2 190.09 m2 10.25% 10% 1.02%
2 F1003 Plesteran Bata 1:5/m2 T.1,52cm 380.18 m2 16.34%
3 F1018 Acian Plesteran Tebal 23mm/m2 380.18 m2 12.73%

SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING

D PEKERJAAN RANGKA & PENUTUP ATAP

1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%

SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP

E PEKERJAAN PELAPIS DINDING


1 F1096 Pas.Keramik Dinding Lokal 20X20/m2 Mulia 8.01 m2 0.65%

SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING

F PEKERJAAN PENUTUP PLAFOND


1 G1005 Rangka Plafond Besi Hollow/m2 (Bawah Kap/Kudakuda) 38.79 m2 1.95%
2 G1012 Plafond Gypsum 9mm/m2 38.79 m2 1.33%

SUB TOTAL BIAYA PEKERJAAN PELAPIS PLAFOND

G PEKERJAAN PELAPIS LANTAI


3 H1129 Pas.Keramik Lantai Lokal 30X30/m2 Mulia 33.54 m2 2.18%
2 H1127 Pas.Keramik Lantai Lokal 20X20/m2 Mulia (wc) 1.72 m2 0.12%

SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI

H PEKERJAAN PINTU, JENDELA, KACA


1 K1017 Kusen Pintu, Jendela Alumunium 4" 30.20 m2 1.44%
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume kontrak
Satuan Bobot %
PROSENTASE PROGRESS
2 I1003 Pintu Full Panel Solid Bangkirai Kwalitet Politur/bh 5.00 bh 2.60%
3 I1003 Daun Pintu Kaca 4.00 bh 2.08%
4 I1106 Jendela Rangka Kaca Bangkirai Kwalitet Cat/m2 3.00 m2 0.59%

SUB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA

J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%

SUB TOTAL BIAYA PEKERJAAN PENGECATAN

K PEKERJAAN INSTALASI SANITASI & ACCESSORIES


Air Bersih
1 L1101 Pemipaan PVC AW dia 11/2"/m' (Dibawah Tanah) 10.00 m' 0.28%
2 L1103 Pemipaan PVC AW dia 1"/m' (Dibawah Tanah) 10.00 m' 0.27%

Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%

Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%

SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI

L PEKERJAAN INSTALASI LISTRIK

1 N1001 Titik Lampu Dalam/ttk Bawah Plafond 8.00 ttk 0.69%


2 N1004 Titik Stop Kontak Biasa/ttk 8.00 ttk 0.75%

SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK

M PEKERJAAN LUAR & HALAMAN


1 O1087 Carport 13.16 m2 1.66%
2 O1082 Plat Duiker Pintu Masuk L.0,75M/m' 4.00 m' 0.62%

SUB TOTAL BIAYA PEKERJAAN LUAR & HALAMAN

100.00% 10.47%
RENCANA ANGGARAN BIAYA (RAB)
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 4 (Empat)

KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE

A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100%

SUB TOTAL BIAYA PEKERJAAN PONDASI

B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 100%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 100%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 100%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%

SUB TOTAL BIAYA PEKERJAAN STRUKTUR

C PEKERJAAN PASANGAN DINDING


1 C1072 Pas.Bata Ringan Tebal 1/2 Batu T.7,5cm 1:4/m2 190.09 m2 10.25% 10%
2 F1003 Plesteran Bata 1:5/m2 T.1,52cm 380.18 m2 16.34%
3 F1018 Acian Plesteran Tebal 23mm/m2 380.18 m2 12.73%

SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING

D PEKERJAAN RANGKA & PENUTUP ATAP

1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%

SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP

E PEKERJAAN PELAPIS DINDING


1 F1096 Pas.Keramik Dinding Lokal 20X20/m2 Mulia 8.01 m2 0.65%

SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING

F PEKERJAAN PENUTUP PLAFOND


1 G1005 Rangka Plafond Besi Hollow/m2 (Bawah Kap/Kudakuda) 38.79 m2 1.95%
2 G1012 Plafond Gypsum 9mm/m2 38.79 m2 1.33%

SUB TOTAL BIAYA PEKERJAAN PELAPIS PLAFOND

G PEKERJAAN PELAPIS LANTAI


3 H1129 Pas.Keramik Lantai Lokal 30X30/m2 Mulia 33.54 m2 2.18%
2 H1127 Pas.Keramik Lantai Lokal 20X20/m2 Mulia (wc) 1.72 m2 0.12%
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE

SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI

H PEKERJAAN PINTU, JENDELA, KACA


1 K1017 Kusen Pintu, Jendela Alumunium 4" 30.20 m2 1.44%
2 I1003 Pintu Full Panel Solid Bangkirai Kwalitet Politur/bh 5.00 bh 2.60%
3 I1003 Daun Pintu Kaca 4.00 bh 2.08%
4 I1106 Jendela Rangka Kaca Bangkirai Kwalitet Cat/m2 3.00 m2 0.59%

SUB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA

J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%

SUB TOTAL BIAYA PEKERJAAN PENGECATAN

K PEKERJAAN INSTALASI SANITASI & ACCESSORIES


Air Bersih
1 L1101 Pemipaan PVC AW dia 11/2"/m' (Dibawah Tanah) 10.00 m' 0.28%
2 L1103 Pemipaan PVC AW dia 1"/m' (Dibawah Tanah) 10.00 m' 0.27%

Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%

Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%

SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI

L PEKERJAAN INSTALASI LISTRIK

1 N1001 Titik Lampu Dalam/ttk Bawah Plafond 8.00 ttk 0.69%


2 N1004 Titik Stop Kontak Biasa/ttk 8.00 ttk 0.75%

SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK

M PEKERJAAN LUAR & HALAMAN


1 O1087 Carport 13.16 m2 1.66%
2 O1082 Plat Duiker Pintu Masuk L.0,75M/m' 4.00 m' 0.62%

SUB TOTAL BIAYA PEKERJAAN LUAR & HALAMAN

100.00%
KEMAJUAN PEKERJAAN

PROGRESS

0.76%
0.73%
5.00%
0.21%

0.68%
1.33%
0.73%

1.02%
KEMAJUAN PEKERJAAN

PROGRESS

10.47%
RENCANA ANGGARAN BIAYA (RAB)
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 5 (lima)

KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS

A PEKERJAAN PONDASI
Pekerjaan Bowplank, Tanah & Pasangan Batu Kali
1 A1002 Pas.Bouwplank T.1,00M/m' 30.80 m' 0.76% 100% 0.76%
2 A1003 Galian Tanah Lunak Dalam Max 1,00M/m3 12.49 m3 0.73% 100% 0.73%
3 A1040 Pondasi Batu Kali 1:5/m3 12.42 m3 5.00% 100% 5.00%
4 A1040 Pondasi Rollag Bawah Sloof 0.53 m3 0.21% 100% 0.21%

SUB TOTAL BIAYA PEKERJAAN PONDASI

B PEKERJAAN STRUKTUR
PEK. SLOOF 15X20
1 A1025 Beton 1:2:3/m3,dgn Seplit 1.38 m3 0.68% 0.00%
2 A1054 Pembesian Ulir/kg 176.87 kg 1.33% 50% 0.66%
3 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 14.71 m2 0.73% 0.00%
PEK. KOLOM 15X20
4 A1025 Beton 1:2:3/m3,dgn Seplit 1.40 m3 0.69%
5 A1054 Pembesian Ulir/kg 195.65 kg 1.47%
6 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 18.67 m2 0.93%
PEK. RINGBALOK 15X20
7 A1025 Beton 1:2:3/m3,dgn Seplit 1.07 m3 0.53%
8 A1054 Pembesian Ulir/kg 175.66 kg 1.32%
9 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 35.67 m2 1.77%
PEK. PLAT DAK TORN T. 15 CM
10 A1025 Beton 1:2:3/m3,dgn Seplit 0.26 m3 0.13%
11 A1054 Pembesian Ulir/kg 2.15 kg 0.02%
12 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 8.33 m2 0.41%
PEK. CANTILEVER
17 A1025 Beton 1:2:3/m3,dgn Seplit 0.70 m3 0.35%
18 A1053 Pembesian Polos/kg 60.67 kg 0.49%
19 A1070 Bekisting Sloof/m2 2xpakai dgn Papan 2/20 7.00 m2 0.35%

SUB TOTAL BIAYA PEKERJAAN STRUKTUR

C PEKERJAAN PASANGAN DINDING


1 C1072 Pas.Bata Ringan Tebal 1/2 Batu T.7,5cm 1:4/m2 190.09 m2 10.25%
2 F1003 Plesteran Bata 1:5/m2 T.1,52cm 380.18 m2 16.34%
3 F1018 Acian Plesteran Tebal 23mm/m2 380.18 m2 12.73%

SUB TOTAL BIAYA PEKERJAAN PASANGAN DINDING

D PEKERJAAN RANGKA & PENUTUP ATAP

1 E1038 Pek. Atap Smartruss + Penutup Atap Genteng Beton Plat 54.85 m2 5.27%
2 E1128 Pemasangan 1m² Lisplang GRC (Uk. 3x20cm) 12.00 m' 0.45%

SUB TOTAL BIAYA PEKERJAAN RANGKA & PENUTUP ATAP

E PEKERJAAN PELAPIS DINDING


1 F1096 Pas.Keramik Dinding Lokal 20X20/m2 Mulia 8.01 m2 0.65%

SUB TOTAL BIAYA PEKERJAAN PELAPIS DINDING

F PEKERJAAN PENUTUP PLAFOND


1 G1005 Rangka Plafond Besi Hollow/m2 (Bawah Kap/Kudakuda) 38.79 m2 1.95%
2 G1012 Plafond Gypsum 9mm/m2 38.79 m2 1.33%

SUB TOTAL BIAYA PEKERJAAN PELAPIS PLAFOND

G PEKERJAAN PELAPIS LANTAI


3 H1129 Pas.Keramik Lantai Lokal 30X30/m2 Mulia 33.54 m2 2.18%
2 H1127 Pas.Keramik Lantai Lokal 20X20/m2 Mulia (wc) 1.72 m2 0.12%

SUB TOTAL BIAYA PEKERJAAN PELAPIS LANTAI

H PEKERJAAN PINTU, JENDELA, KACA


1 K1017 Kusen Pintu, Jendela Alumunium 4" 30.20 m2 1.44%
KEMAJUAN PEKERJAAN
No No ID Pekerjaan Volume Satuan Bobot %
PROSENTASE PROGRESS
2 I1003 Pintu Full Panel Solid Bangkirai Kwalitet Politur/bh 5.00 bh 2.60%
3 I1003 Daun Pintu Kaca 4.00 bh 2.08%
4 I1106 Jendela Rangka Kaca Bangkirai Kwalitet Cat/m2 3.00 m2 0.59%

SUB TOTAL BIAYA PEKERJAAN PINTU, JENDELA, KACA

J PEKERJAAN PENGECATAN
1 K1061 Cat Tembok Dalam/m2 380.18 m2 14.26%
2 K1062 Cat Plafond /m2 38.79 m2 1.48%

SUB TOTAL BIAYA PEKERJAAN PENGECATAN

K PEKERJAAN INSTALASI SANITASI & ACCESSORIES


Air Bersih
1 L1101 Pemipaan PVC AW dia 11/2"/m' (Dibawah Tanah) 10.00 m' 0.28%
2 L1103 Pemipaan PVC AW dia 1"/m' (Dibawah Tanah) 10.00 m' 0.27%

Air Kotor
3 L1222 Pemipaan PVC AW dia 1,5"/m' (Bawah Wastafel/K'Zink) 10.00 m' 0.24%
4 L1223 Pemipaan PVC AW dia 2"/m' (Bawah Lantai) 10.00 m' 0.36%

Accessories
5 M1150 Closet Duduk Lokal Lengkap 1.00 bh 1.45%
6 M1235 Kran Taman Lokal /bh Type3 4.00 bh 0.44%
7 M1021 Bath Shower Lokal/bh Type3 1.00 bh 1.63%

SUB TOTAL BIAYA PEKERJAAN INSTALASI SANITASI

L PEKERJAAN INSTALASI LISTRIK

1 N1001 Titik Lampu Dalam/ttk Bawah Plafond 8.00 ttk 0.69%


2 N1004 Titik Stop Kontak Biasa/ttk 8.00 ttk 0.75%

SUB TOTAL BIAYA PEKERJAAN INSTALASI LISTRIK

M PEKERJAAN LUAR & HALAMAN


1 O1087 Carport 13.16 m2 1.66%
2 O1082 Plat Duiker Pintu Masuk L.0,75M/m' 4.00 m' 0.62%

SUB TOTAL BIAYA PEKERJAAN LUAR & HALAMAN

100.00% 7.37%
REKAPITULASI PROGRESS
Proyek : TYPE 36 STANDARD
Lokasi : PESONA GREEN CIBINONG
KAVLING NO. : No. 2 3 4 5

KEMAJUAN PEKERJAAN
No PEKERJAAN
KAVLING NO. 2 KAVLING NO. 3 KAVLING NO. 4 KAVLING NO. 5

A PEKERJAAN PONDASI 6.70% 6.70% 6.70% 6.70%

B PEKERJAAN STRUKTUR 2.74% 2.74% 2.74% 0.66%

C PEKERJAAN PASANGAN DINDING 1.02% 1.02% 1.02% 0.00%

D PEKERJAAN RANGKA & PENUTUP ATAP

E PEKERJAAN PELAPIS DINDING

F PEKERJAAN PENUTUP PLAFOND

G PEKERJAAN PELAPIS LANTAI

H PEKERJAAN PINTU, JENDELA, KACA

J PEKERJAAN PENGECATAN

K PEKERJAAN INSTALASI SANITASI & ACCESSORIES

L PEKERJAAN INSTALASI LISTRIK

M PEKERJAAN LUAR & HALAMAN

10.47% 10.47% 10.47% 7.37%

PROGRESS RATA2 9.69%