PEKERJAAN
PERENCANAAN TEMPAT PARKIR DAN GEDUNG FASILITAS PENUNJANG
KANTOR BANK INDONESIA
WILAYAH KALIMANTAN UTARA
LOKASI
Kota Tarakan Provinsi Kalimantan Utara
TIME SCHEDULE
Kegiatan : 0
Pekerjaan : 0
Lokasi Kegiatan : 0
DARI TANGGAL 23-Aug 30-Aug 6-Sep 13-Sep 20-Sep 27-Sep 4-Oct 11-Oct 18-Oct 25-Oct 1-Nov 8-Nov 15-Nov 22-Nov 29-Nov 6-Dec
SAMPAI DENGAN TANGGAL 29-Aug 5-Sep 12-Sep 19-Sep 26-Sep 3-Oct 10-Oct 17-Oct 24-Oct 31-Oct 7-Nov 14-Nov 21-Nov 28-Nov 5-Dec 12-Dec
A PEKERJAAN PENDAHULUAN
1 Pembersihan dan Persiapan Pekerjaan 0.014% 0.01%
B PEKERJAAN TANAH
1 Urugan Pasir Bawah Lantai t= 5cm 0.048%
C PEKERJAAN BETON
1 Cor Beton Bertulang Sloof bantu 10/20 0.317% 0.13% 0.19%
2 Kolom beton bertulang 20/20 1.480% 0.59% 0.43% 0.46%
3 Kolom Praktis 10/10 0.143% 0.04%
4 Cor beton Bertulang Balok 20/30 0.847% 0.08% 0.04% 0.13%
5 Cor beton Bertulang Balok 20/25 1.009% 0.20% 0.10%
6 Cor beton Bertulang Balok 18/20 0.167% 0.03% 0.02%
7 Cor Beton Bertulang Ringbalk 18/20 1.436%
8 Cor Beton Bertulang Balok Kantilever BK 20/25 0.405% 0.08% 0.02%
9 Cor Beton Sunscreen 15/30 0.321%
10 Plat Dag beton k-225 2.969% 0.59% 0.74%
11 List plank beton 1.141%
12 Cor Lantai rabat Finishing Acian 0.252%
F PEKERJAAN ATAP
1 Rangka Atap Baja Ringan 2.615%
2 Atap Multiroof 1.455%
3 Bubungan 0.418%
4 Jurai Dalam 0.046%
5 Listplank GRC 30 cm 0.151%
G PEKERJAAN KUSEN / P / J
1
Kusen Pintu & Jendela Aluminium 0.704%
2
Pintu Type P.1 0.654%
3
Pintu Type P.2 0.474%
4
Pintu Km/Wc (PVC) 0.208%
5
Bovenlicht BV 0.057%
6
Kunci Tanam 2 x Putar (Yale) 0.039%
7
Engsel pintu Kaca 0.015%
8
Kaca Polos / Bening 5mm 0.393%
H PEKERJAAN PLAFOND
1 Rangka Plafond Besi Holow 0.354%
2 Plafond Gypsum 0.119%
I PEKERJAAN LANTAI
1 Lantai Keramik toilet 30x30 0.216%
J PEKERJAAN CAT-CATAN
1 Cat dinding luar dalam 0.676%
2 Cat Plafound 0.068%
K PEKERJAAN FINISHING
1 Dinding keramik WC 30/30 0.398%
2 Pas. Pagar realing besi Holow 0.867%
3 Raling Tangga besi Holow 0.662%
4 Pas. Tangga besi dari lantai 1 kelantai 2 0.654% 0.00%
5 Pas. Exhouse Fan 0.077%
M PEKERJAAN PLUMBING
1 Instalasi pipa air bersih
- Pipa PVC AW Dia. 2' 0.026%
- Fitting material bantu 0.004%
2 Instalasi pipa air kotor, limbah & ventilasi
- Pipa PVC Kelas AW Dia. 3' 0.102%
- Pipa PVC Kelas AW Dia. 4' 0.051%
- Fitting material bantu 0.007%
PROGRESS REALISASI MINGGU INI 0.014% 0.719% 0.736% 1.414% 1.007% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000% 0.000%
30
PROGGRES REALISASI S.D MINGGU INI 0.014% 0.733% 1.469% 2.884% 3.891% 3.891% 3.891% 3.891% 3.891% 3.891% 3.891% 3.891% 3.891% 3.891% 3.891% 3.891%
DEVIASI -0.034% -1.246% -7.591% -13.259% -23.289% -34.326% -41.822% -50.461% -55.145% -63.537% -65.684% -71.902% -76.801% -84.815% -93.597% -96.109%
REKAPITULASI RENCANA ANGGARAN BIAYA
Kegiatan :
Pekerjaan :
Lokasi Kegiatan :
A PEKERJAAN PENDAHULUAN
B PEKERJAAN TANAH
D PEKERJAAN BETON
E PEKERJAAN PASANGAN DAN PLESTERAN
F PEKERJAAN KAYU DAN ATAP
G PEKERJAAN KUSEN / P / J
H PEKERJAAN PLAFOND
I PEKERJAAN LANTAI
J PEKERJAAN CAT-CATAN
K PEKERJAAN FINISHING
L PEKERJAAN JARINGAN SANITASI
M PEKERJAAN PLUMBING
N PEKERJAAN JARINGAN LISTRIK
JUMLAH
PPN 10 %
TOTAL JUMLAH + PPN 10 %
DIBULATKAN
TERBILANG :
DUA MILYAR ENAM RATUS SEMBILAN PULUH SATU JUTA DELAPAN RATUS SEMBILAN PULUH
Mengetahui,
Konsultan Sipil
YAYAN WARDANA
KAPITULASI RENCANA ANGGARAN BIAYA
JUMLAH ( Rp. )
350,000.00
14,766,115.00
658,743,839.54
427,239,938.90
782,744,000.00
63,759,414.05
117,303,377.26
106,930,360.65
33,632,299.41
158,006,601.60
27,929,947.65
4,657,500.00
51,110,000.00
2,447,173,394.06
244,717,339.41
2,691,890,733.47
2,691,890,000.00
US SEMBILAN PULUH SATU JUTA DELAPAN RATUS SEMBILAN PULUH RIBU RUPIAH
Mengetahui,
Konsultan Sipil
YAYAN WARDANA
RENCANA ANGGARAN BIAYA PEKERJAAN
Kegiatan :
Pekerjaan :
Lokasi Kegiatan :
No. Uraian Pekerjaan Satuan Volume Harga Satuan (Rp.) Jumlah Harga (Rp.)
A PEKERJAAN PENDAHULUAN
1 Pembersihan dan Persiapan Pekerjaan Ls 1.00 350,000.00 350,000.00
Sub Jumlah A 350,000.00
B PEKERJAAN TANAH
1 Urugan Pasir Bawah Lantai t= 5cm M³ 83.00 177,905.00 14,766,115.00
I PEKERJAAN PERSIAPAN
1. 1 m' pengukuran dan pemasangan bowplank
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
A Tenaga Kerja :
Pekerja OH 0.100 110,000.00 11,000.00
Tukang Kayu OH 0.100 145,000.00 14,500.00
Kepala Tukang OH 0.010 165,000.00 1,650.00
Mandor OH 0.005 170,000.00 850.00
Jumlah Tenaga Kerja 28,000.00
B Bahan :
Kayu Balok 5/7 m3 0.0120 4,400,000.00 52,800.00
Paku biasa 2 inci - 3 inci kg 0.0200 18,000.00 360.00
Kayu papan 3/20 m3 0.0070 2,500,000.00 17,500.00
Jumlah Harga Bahan 70,660.00
C Peralatan :
II PEKERJAAN TANAH
1. Menggali 1 m3 tanah biasa sedalam 1 meter
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
A Tenaga kerja :
pekerja L.01 OH 0.7500 110,000.00 82,500.00
Mandor L.02 OH 0.0250 170,000.00 4,250.00
Jumlah Tenaga Kerja 86,750.00
B Bahan :
Jumlah Harga Bahan
C Peralatan :
Jumlah Harga Alat
IV PEKERJAAN BETON
1. Membuat 1 m3 beton mutu f’c = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
A Tenaga Kerja :
Pekerja L.01 OH 1.6500 110,000.00 181,500.00
Tukang batu L.02 OH 0.2750 145,000.00 39,875.00
Kepala tukang L.03 OH 0.0280 165,000.00 4,620.00
Mandor L.04 OH 0.0830 170,000.00 14,110.00
Jumlah Tenaga Kerja 240,105.00
B Bahan :
Portland Cement kg 276.0000 1,300.00 358,800.00
Pasir Beton kg 828.0000 78.57 65,057.14
Kerikil ( maksimum 30 mm ) kg 1,012.0000 344.83 348,965.52
Air Liter 215.0000 45.00 9,675.00
Jumlah Harga Bahan 782,497.66
C Peralatan :
3. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
A Tenaga Kerja :
Pekerja L.01 OH 1.6500 110,000.00 181,500.00
Tukang batu L.02 OH 0.2750 145,000.00 39,875.00
Kepala tukang L.03 OH 0.0280 165,000.00 4,620.00
Mandor L.04 OH 0.0830 170,000.00 14,110.00
Jumlah Tenaga Kerja 240,105.00
B Bahan :
Portland Cement kg 326.000 1,300.00 423,800.00
Pasir Beton kg 760.000 78.57 59,714.29
Kerikil ( maksimum 30 mm ) kg 1,029.000 344.83 354,827.59
Air Liter 215.000 45.00 9,675.00
Jumlah Harga Bahan 848,016.87
C Peralatan :
5. Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
A Tenaga Kerja :
Pekerja L.01 OH 1.6500 110,000.00 181,500.00
Tukang batu L.02 OH 0.2750 145,000.00 39,875.00
Kepala tukang L.03 OH 0.0280 165,000.00 4,620.00
Mandor L.04 OH 0.0830 170,000.00 14,110.00
Jumlah Tenaga Kerja 240,105.00
B Bahan :
Portland Cement kg 384.000 1,300.00 499,200.00
Pasir Beton kg 692.000 78.57 54,371.43
Kerikil ( maksimum 30 mm ) kg 1,039.000 344.83 358,275.86
Air Liter 215.000 45.00 9,675.00
Jumlah Harga Bahan 921,522.29
C Peralatan :
6. Membuat 1 m3 beton mutu f’c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
A Tenaga Kerja :
Pekerja L.01 OH 1.6500 110,000.00 181,500.00
Tukang batu L.02 OH 0.2750 145,000.00 39,875.00
Kepala tukang L.03 OH 0.0280 165,000.00 4,620.00
Mandor L.04 OH 0.0830 170,000.00 14,110.00
Jumlah Tenaga Kerja 240,105.00
B Bahan :
Portland Cement kg 413.000 1,300.00 536,900.00
Pasir Beton kg 681.000 78.57 53,507.14
Kerikil ( maksimum 30 mm ) kg 1,021.000 344.83 352,068.97
Air Liter 215.000 45.00 9,675.00
Jumlah Harga Bahan 952,151.11
C Peralatan :
1. Memasang 1 m2 dinding bata merah ukuran (9 x 9 x 18) cm tebal 1/2 bata, Campuran Spesi 1 PC : 4 PP
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
A Tenaga Kerja :
Pekerja L.01 OH 0.3000 110,000.00 33,000.00
Tukang batu L.02 OH 0.1000 145,000.00 14,500.00
Kepala tukang L.03 OH 0.0100 165,000.00 1,650.00
Mandor L.04 OH 0.0150 170,000.00 2,550.00
Jumlah Tenaga Kerja 51,700.00
B Bahan :
Bata merah Bh 55.000 3,000.00 165,000.00
Portland Cement kg 11.500 1,300.00 14,950.00
Pasir Pasang m3 0.0430 110,000.00 4,730.00
Jumlah Harga Bahan 184,680.00
C Peralatan :
1. 1 m2 Pengecatan Tembok baru ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
Harga sat. Jumlah Harga
No Uraian Jenis Pekerjaan Kode Sat. Koeff.
(Rp. ) (Rp. )
Tenaga Kerja:
Pekerja L.01 OH 0.020 110,000.00 2,200.00
Tukang cat L.02 OH 0.063 145,000.00 9,135.00
Kepala Tukang L.03 OH 0.006 165,000.00 1,039.50
Mandor L.04 OH 0.003 170,000.00 510.00
Jumlah Tenaga Kerja 12,884.50
B Bahan :
Plamuur Kg 0.100 39,600.00 3,960.00
Cat dasar Kg 0.100 31,500.00 3,150.00
Cat penutup Kg 0.260 39,600.00 10,296.00
Jumlah Harga Bahan 17,406.00
C Peralatan :
Kegiatan : 0
Pekerjaan : 0
Lokasi Kegiatan : 0
1 2 3 4
A. UPAH
1 Pekerja Orang / Hari 110,000.00
2 Tukang Cat Orang / Hari 145,000.00
3 Tukang Kayu Orang / Hari 145,000.00
4 Tukang Batu Orang / Hari 145,000.00
5 Tukang Besi Orang / Hari 145,000.00
6 Kepala Tukang Cat Orang / Hari 165,000.00
7 Kepala Tukang Kayu Orang / Hari 165,000.00
8 Kepala Tukang Batu Orang / Hari 165,000.00
9 Kepala Tukang Besi Orang / Hari 165,000.00
10 Mandor Orang / Hari 170,000.00
11 Pekerja Orang / Jam Efektif 15,714.29
12 Mandor Orang / Jam Efektif 24,285.71
B. BAHAN
1 Semen PC 50 Kg Zak 65,000.00
kg 1,300.00
2 Semen Putih Zak 137,500.00
3 Semen warna kg 20,000.00
4 Semen Mortar Prime MU-380 Kg 2,250.00
5 Batu Gunung M3 560,000.00
6 Batu Batako Buah 3,000.00
7 Batu Bata Ringan Buah 20,481.93
8 Roster (B) Buah 33,000.00
9 Roster (K) Buah 22,000.00
10 Paving Block Segienam (K) Buah 3,520.00
11 Glass Box Buah 33,000.00
12 Batu Pecah 1/1 - 5/7 cm M3 500,000.00
kg 344.83
13 Batu Kerikil sungai M3 350,000.00
14 Pasir Urug M3 100,000.00
15 Pasir Pasangan / Beton M3 110,000.00
kg 78.57
16 Bahan Tanah Urug Biasa M3 50,400.00
17 Bahan Tanah Urug Pilihan M3 57,600.00
18 Besi Beton Polos Kg 13,000.00
19 Besi Beton Ulir Kg 15,000.00
19 Kawat Beton / Bendrat Kg 25,000.00
20 Besi Pelat 5 mm Kg 24,500.00
21 Kayu Perancah M 3
2,500,000.00
22 Kayu Meranti M3 2,500,000.00
HARGA SATUAN DASAR
NO. URAIAN SATUAN
(Rp.)
1 2 3 4
23 Kayu Bengkirai / Lembasung M 3
4,400,000.00
24 Kusen kayu Lembasung M3 4,400,000.00
25 Kayu ulin (balok) M3 7,000,000.00
26 Kayu Laut Dia. 8-10 cm Btg 35,000.00
27 Plywood 4 mm Lbr 85,800.00
28 Plywood 9 mm Lbr 135,000.00
29 Pipa PVC 2" M1 21,015.00
30 Seng Gelombang BJLS 30 Lembar 58,500.00
31 Seng Gelombang BJLS 20 Lembar 49,500.00
32 Seng Pelat BJLS 30 Lembar 84,600.00
33 Seng Pelat BJLS 20 Lembar 79,200.00
34 Closet Jongkok (toto) non polos Buah 315,000.00
35 Closet Duduk Buah 2,178,000.00
36 Tempat sabun Toto S11N Buah 81,000.00
37 Floor drain Toto Buah 67,500.00
38 Kran dinding Buah 22,500.00
39 Kran Shower Cabang euro Buah 405,000.00
40 Kitchen sink Royal 1 lubang Buah 495,000.00
41 Kran dapur Toto Buah 157,500.00
42 Washtafel Toto Buah 990,000.00
43 Urinoir Toto U57M Buah 2,425,500.00
44 Cermin Buah 135,000.00
45 Kaca polos 8 mm M2 362,000.00
46 Kunci Tanam 2 x Putar (Yale) Buah 158,400.00
47 Kunci Tanam 2 x putar (Union) Buah 272,250.00
48 Engsel pintu 4" (Axaxi) tiap daun pintu 3 bh Buah 29,700.00
49 Engsel jendela 4"(Axaxi) tiap daun 2 bh Buah 29,700.00
50 Grendel putar pintu dua daun Buah 24,750.00
51 Grendel jendela (lamskar) Buah 24,750.00
52 Handel jendela (lamskar) Buah 18,450.00
53 Hak angin jendela 10 " (lamskar) Buah 21,150.00
54 Gypsum Board Lembar 84,150.00
55 Gypsum BRC Boar 6 mm Lembar 121,500.00
56 Les Plafond 4/4 M1 16,200.00
57 Liastplank GRC Board 30 cm M' 22,500.00
58 Genteng Metal Multi Color Lembar 84,150.00
59 Bubungan Genteng Metal Multi Color Lembar 64,350.00
60 Paku Biasa Kg 18,000.00
61 Paku Ulin Kg 22,500.00
62 Paku Seng Kg 22,500.00
63 Paku Genteng Metal Multi Color Buah 217.80
64 Tegel Keramik (20/20) M 2
89,100.00
HARGA SATUAN DASAR
NO. URAIAN SATUAN
(Rp.)
1 2 3 4
Bh 3,564.00
65 Tegel Keramik (20/25) M2 89,100.00
Bh 4,455.00
66 Tegel Keramik (30/30) M2 92,070.00
Bh 8,370.00
67 Tegel Keramik (40/40) M 2
94,050.00
Bh 15,675.00
68 Tegel Granito (60/60) M2 297,000.00
Bh 148,500.00
69 Plint Keramik M2 94,050.00
3,617.31
70 Batu Alam M 2
346,500.00
71 Dempul/ Plamir Kg 39,600.00
72 Cat Minyak Avian Kg 54,450.00
73 Cat meni Kg 29,700.00
74 Cat dasar kg 31,500.00
75 cat air dulux Kg 39,600.00
76 Cat air Paragon Kg 29,700.00
77 Minyak Cat Thiner Ltr 24,750.00
78 Minyak Begisting Ltr 7,200.00
79 Amplas Lbr 59,400.00
80 Kuas cat Bh 13,500.00
81 Grass Block Bh 27,000.00
82 Air m3 45,000.00
kg 45.00
Besi Holow 40.40.3 mm m' 9,652.50
83 Galvalume C-75, 0,8 m' 16,500.00
84 Galvalume C-75, 0,6 m' 15,000.00
85 Baut ( Sre Driver) Bh 315.00
86 Dynabolt Bh 15,750.00
87 Reng 0,45 m' 8,250.00
88 Bak Air Fiber Bh 855,000.00
89 Lem perekat Kg 36,000.00
90 Sealent Tube 67,500.00
91 Profil Aluminium Coklat m' 135,000.00
92 Skrup fixer Bh 270.00
93 Karpet m2 11,250.00
94 Pagar besi holow + pengecatan m2 675,000.00
95 Pas. Pipa PVC Dia. 2" m' 21,375.00
96 Pas. Pipa PVC Dia. 3" m' 38,250.00
97 Pas. Pipa PVC Dia. 4" m' 45,000.00
98 Pas. Dinding Partisi PVC + Rangka m2 616,500.00
99 Exhouse Fan Bh 469,980.00
C V . R AIHAN M AHAR AN I S EJAHT ER A
G ENE RAL C O NTR AC TO R & SUPP LIER
J L. AGATH IS RT. 0 5 KAR ANG HAR APAN TARAKAN
H p : 0 8 12 5 8 95 2 73
A PEKERJAAN PENDAHULUAN
1 Pembersihan dan Persiapan Pekerjaan Ls 1.00 350,000.00 350,000.00
Sub Jumlah A 350,000.00
B PEKERJAAN TANAH
1 Urugan Pasir Bawah Lantai t= 5cm M³ #REF! 177,905 #REF!
Sub Jumlah H -
I PEKERJAAN LANTAI
1 Lantai Keramik toilet 30x30 M² #REF! #REF!
Sub Jumlah L -
M PEKERJAAN PLUMBING
1 Instalasi pipa air bersih
- Pipa PVC AW Dia. 2' M¹ 30.00 -
- Fitting material bantu Ls 1.00 -
2 Instalasi pipa air kotor, limbah & ventilasi
- Pipa PVC Kelas AW Dia. 3' M¹ 65.00 -
- Pipa PVC Kelas AW Dia. 4' M¹ 28.00 -
- Fitting material bantu Ls 1.00 -
Sub Jumlah M -
N PEKERJAAN JARINGAN LISTRIK
1 Lampu down light 15 Watt Buah 98.00 -
2 Saklar tunggal Buah 2.00 -
3 Saklar ganda Buah 6.00 -
4 Stop kontak Buah 6.00 -
5 Stop kontak AC Buah 4.00 -
6 Titik lampu + instalasi Titik 98.00 -
7 Titik stop kontak + instalasi Titik 10.00 -
8 Box Sekring Buah 1.00 -
Sub Jumlah N -