Anda di halaman 1dari 7

KEGIATAN : PEMBANGUNAN RUMAH KOST

PEKERJAAN : RUMAH KOST 3 LANTAI


LOKASI : JL. MUGAS BARAT VI NO 6 SEMARANG
NILAI KONTRAK : Rp. 2.293.478.562,00
PENYEDIA JASA : BP. HENOUG SATYOBUDHI
OWNER : BP. MARULI PAKPAHAN
KONSULTAN PENGAWAS : BP. DWI RESPONO ADHI
MINGGU : 52
PERIODE TANGGAL : 31 JANUARI 2022 - 5 FEBRUARI 2022

LAPORAN MINGGUAN

VOLUME 100% VOLUME TERPASANG VOLUME DIKERJAKAN VOLUME SISA


NO NAMA PEKERJAAN
VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT%

I PEK. PERSIAPAN
1 Ukur dan bowplank 93.20 m' 0.107% 93.20 m' 0.107% m' 0.000% m' 0.000%
2 Pembersihan lokasi 352.80 m² 0.054% 266.60 m² 0.041% m² 0.000% 86.20 m² 0.013%
3 Barak kerja 1.00 ls 0.327% 1.00 ls 0.327% ls 0.000% ls 0.000%
4 Air kerja dan listrik 1.00 ls 0.218% 0.93 ls 0.203% 0.03 ls 0.007% 0.04 ls 0.009%
5 Keamanan 1.00 ls 0.218% 0.93 ls 0.203% 0.03 ls 0.007% 0.04 ls 0.009%
6 Alat kerja 1.00 ls 0.436% 0.93 ls 0.405% 0.03 ls 0.013% 0.04 ls 0.017%
7 Mob & Demobilisasi 1.00 ls 0.545% 0.70 ls 0.382% ls 0.000% 0.30 ls 0.164%

II PEK. TANAH
1 Galian tanah footplat 186.59 m³ 0.814% 186.59 m³ 0.814% m³ 0.000% m³ 0.000%
2 Pemadatan tanah footplat dan pondasi 167.22 m² 0.109% 167.22 m² 0.109% m² 0.000% m² 0.000%
3 Pemadatan tanah bangunan 194.00 m² 0.127% 189.01 m² 0.124% 4.25 m² 0.003% 0.74 m² 0.000%
4 Galian tanah pipa air kotor 57.20 m' 0.087% 57.20 m' 0.087% m' 0.000% m' 0.000%
5 Galian tanah pondasi 134.00 m³ 0.584% 134.00 m³ 0.584% m³ 0.000% m³ 0.000%
6 Galian sumuran 18.00 m' 0.235% 18.00 m' 0.235% m' 0.000% m' 0.000%
7 Urugan tanah kembali 179.00 m³ 0.624% 179.00 m³ 0.624% m³ 0.000% m³ 0.000%
8 Perataan tanah kembali 162.00 m³ 0.565% 162.00 m³ 0.565% m³ 0.000% m³ 0.000%
Urugan tanah bangunan ( area dalam bangunan 60 cm
9 0.00 m³ 0.000% m³ 0.000% m³ 0.000% m³ 0.000%
+ halaman)
10 Urugan pasir bawah footplat 5 cm 4.28 m³ 0.084% 4.28 m³ 0.084% m³ 0.000% m³ 0.000%
11 Urugan pasir bawah pondasi 5 cm 6.10 m³ 0.120% 6.10 m³ 0.120% m³ 0.000% m³ 0.000%
12 Urugan pasir bawah lantai 5 cm lantai 1 8.85 m³ 0.174% 8.33 m³ 0.163% 0.52 m³ 0.010% m³ 0.000%
13 Urugan pasir bawah lantai 5 cm lantai 2 8.60 m³ 0.169% 8.60 m³ 0.169% m³ 0.000% m³ 0.000%
14 Urugan pasir bawah lantai 5 cm lantai 3 7.43 m³ 0.146% 7.43 m³ 0.146% m³ 0.000% m³ 0.000%

III PEK. BETON


1 Lantai kerja 1 : 3 : 5 footplat 5 cm 78.30 m² 0.202% 78.30 m² 0.202% m² 0.000% m² 0.000%
2 Lantai kerja 1 : 3 : 5 pondasi 5 cm 94.90 m² 0.244% 94.90 m² 0.244% m² 0.000% m² 0.000%
3 Cor lantai area parkir dan ruangan 8 cm ( O6-20)
- cor beton 132.00 m² 0.593% 124.36 m² 0.559% 7.64 m² 0.034% m² 0.000%
- pembesian 132.00 m² 0.181% 124.36 m² 0.171% 7.64 m² 0.010% m² 0.000%
4 Sumuran
- cor beton 18.00 m' 0.995% 18.00 m' 0.995% m' 0.000% m' 0.000%
- pembesian 18.00 m' 0.074% 18.00 m' 0.074% m' 0.000% m' 0.000%
5 Cor footplat
- cor beton 23.80 m³ 1.401% 23.80 m³ 1.401% m³ 0.000% m³ 0.000%
- pembesian 23.80 m³ 1.641% 23.80 m³ 1.641% m³ 0.000% m³ 0.000%
- bekisting 23.80 m³ 0.322% 23.80 m³ 0.322% m³ 0.000% m³ 0.000%
6 Cor kolom struktur K1 35/40
- cor beton 2.73 m³ 0.161% 2.73 m³ 0.161% m³ 0.000% m³ 0.000%
- pembesian 2.73 m³ 0.178% 2.73 m³ 0.178% m³ 0.000% m³ 0.000%
- bekisting 2.73 m³ 0.208% 2.73 m³ 0.208% m³ 0.000% m³ 0.000%
7 Cor kolom struktur K2 35/40
- cor beton 6.83 m³ 0.402% 6.83 m³ 0.402% m³ 0.000% m³ 0.000%
- pembesian 6.83 m³ 0.487% 6.83 m³ 0.487% m³ 0.000% m³ 0.000%
- bekisting 6.83 m³ 0.522% 6.83 m³ 0.522% m³ 0.000% m³ 0.000%
8 Cor kolom struktur K3 35/40
- cor beton 2.73 m³ 0.161% 2.73 m³ 0.161% m³ 0.000% m³ 0.000%
- pembesian 2.73 m³ 0.225% 2.73 m³ 0.225% m³ 0.000% m³ 0.000%
- bekisting 2.73 m³ 0.208% 2.73 m³ 0.208% m³ 0.000% m³ 0.000%
9 Cor kolom struktur K4 25/25
- cor beton 1.22 m³ 0.072% 1.22 m³ 0.072% m³ 0.000% m³ 0.000%
- pembesian 1.22 m³ 0.175% 1.22 m³ 0.175% m³ 0.000% m³ 0.000%
- bekisting 1.22 m³ 0.082% 1.22 m³ 0.082% m³ 0.000% m³ 0.000%
10 Cor kolom struktur K5 25/25
- cor beton 1.22 m³ 0.072% 1.22 m³ 0.072% m³ 0.000% m³ 0.000%
- pembesian 1.22 m³ 0.138% 1.22 m³ 0.138% m³ 0.000% m³ 0.000%
- bekisting 1.22 m³ 0.082% 1.22 m³ 0.082% m³ 0.000% m³ 0.000%
11 Cor kolom struktur K6 25/25
- cor beton 1.22 m³ 0.072% 1.22 m³ 0.072% m³ 0.000% m³ 0.000%
- pembesian 1.22 m³ 0.121% 1.22 m³ 0.121% m³ 0.000% m³ 0.000%
- bekisting 1.22 m³ 0.082% 1.22 m³ 0.082% m³ 0.000% m³ 0.000%
LAPORAN MINGGUAN

VOLUME 100% VOLUME TERPASANG VOLUME DIKERJAKAN VOLUME SISA


NO NAMA PEKERJAAN
VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT%

12 Cor kolom struktur K7 15/40


- cor beton 2.43 m³ 0.143% 2.43 m³ 0.143% m³ 0.000% m³ 0.000%
- pembesian 2.43 m³ 0.265% 2.43 m³ 0.265% m³ 0.000% m³ 0.000%
- bekisting 2.43 m³ 0.123% 2.43 m³ 0.123% m³ 0.000% m³ 0.000%
13 Cor kolom struktur K8 30/30
- cor beton 2.60 m³ 0.153% 2.60 m³ 0.153% m³ 0.000% m³ 0.000%
- pembesian 2.60 m³ 0.213% 2.60 m³ 0.213% m³ 0.000% m³ 0.000%
- bekisting 2.60 m³ 0.174% 2.60 m³ 0.174% m³ 0.000% m³ 0.000%
14 Cor kolom struktur K9 15/40
- cor beton 9.26 m³ 0.545% 9.26 m³ 0.545% m³ 0.000% m³ 0.000%
- pembesian 9.26 m³ 0.820% 9.26 m³ 0.820% m³ 0.000% m³ 0.000%
- bekisting 9.26 m³ 0.470% 9.26 m³ 0.470% m³ 0.000% m³ 0.000%
15 Cor kolom struktur K10 15/25
- cor beton 0.68 m³ 0.040% 0.68 m³ 0.040% m³ 0.000% m³ 0.000%
- pembesian 0.68 m³ 0.059% 0.68 m³ 0.059% m³ 0.000% m³ 0.000%
- bekisting 0.68 m³ 0.035% 0.68 m³ 0.035% m³ 0.000% m³ 0.000%
16 Cor kolom praktis 15/15
- cor beton 10.44 m³ 0.586% 10.44 m³ 0.586% m³ 0.000% m³ 0.000%
- pembesian 10.44 m³ 0.602% 10.44 m³ 0.602% m³ 0.000% m³ 0.000%
- bekisting 10.44 m³ 0.453% 10.44 m³ 0.453% m³ 0.000% m³ 0.000%
17 Cor kolom ban-banan pilar 15/15
- cor beton 0.50 m³ 0.028% 0.50 m³ 0.028% m³ 0.000% m³ 0.000%
- pembesian 0.50 m³ 0.029% 0.50 m³ 0.029% m³ 0.000% m³ 0.000%
- bekisting 0.50 m³ 0.022% 0.50 m³ 0.022% m³ 0.000% m³ 0.000%
18 Cor sloof S1 20/40
- cor beton 7.44 m³ 0.438% 7.44 m³ 0.438% m³ 0.000% m³ 0.000%
- pembesian 7.44 m³ 0.785% 7.44 m³ 0.785% m³ 0.000% m³ 0.000%
- bekisting 7.44 m³ 0.323% 7.44 m³ 0.323% m³ 0.000% m³ 0.000%
19 Cor sloof S2 20/30
- cor beton 2.56 m³ 0.151% 2.56 m³ 0.151% m³ 0.000% m³ 0.000%
- pembesian 2.56 m³ 0.259% 2.56 m³ 0.259% m³ 0.000% m³ 0.000%
- bekisting 2.56 m³ 0.111% 2.56 m³ 0.111% m³ 0.000% m³ 0.000%
20 Cor sloof S3 15/20
- cor beton 1.05 m³ 0.062% 1.05 m³ 0.062% m³ 0.000% m³ 0.000%
- pembesian 1.05 m³ 0.106% 1.05 m³ 0.106% m³ 0.000% m³ 0.000%
- bekisting 1.05 m³ 0.053% 1.05 m³ 0.053% m³ 0.000% m³ 0.000%
21 Cor balok beton lantai 2 B1 20/50
- cor beton 5.98 m³ 0.273% 5.98 m³ 0.273% m³ 0.000% m³ 0.000%
- pembesian 5.98 m³ 0.594% 5.98 m³ 0.594% m³ 0.000% m³ 0.000%
- bekisting 5.98 m³ 0.353% 5.98 m³ 0.353% m³ 0.000% m³ 0.000%
22 Cor balok beton lantai 2 B2 20/50
- cor beton 5.50 m³ 0.251% 5.50 m³ 0.251% m³ 0.000% m³ 0.000%
- pembesian 5.50 m³ 0.619% 5.50 m³ 0.619% m³ 0.000% m³ 0.000%
- bekisting 5.50 m³ 0.311% 5.50 m³ 0.311% m³ 0.000% m³ 0.000%
23 Cor balok beton lantai 2 B3 20/30
- cor beton 5.88 m³ 0.228% 5.88 m³ 0.228% m³ 0.000% m³ 0.000%
- pembesian 5.88 m³ 0.597% 5.88 m³ 0.597% m³ 0.000% m³ 0.000%
- bekisting 5.88 m³ 0.306% 5.88 m³ 0.306% m³ 0.000% m³ 0.000%
24 Cor balok beton lantai 2 B4 20/30
- cor beton 0.84 m³ 0.033% 0.84 m³ 0.033% m³ 0.000% m³ 0.000%
- pembesian 0.84 m³ 0.099% 0.84 m³ 0.099% m³ 0.000% m³ 0.000%
- bekisting 0.84 m³ 0.044% 0.84 m³ 0.044% m³ 0.000% m³ 0.000%
25 Cor balok beton lantai 2 B5 20/45
- cor beton 1.80 m³ 0.080% 1.80 m³ 0.080% m³ 0.000% m³ 0.000%
- pembesian 1.80 m³ 0.179% 1.80 m³ 0.179% m³ 0.000% m³ 0.000%
- bekisting 1.80 m³ 0.102% 1.80 m³ 0.102% m³ 0.000% m³ 0.000%
26 Cor balok beton lantai 2 B6 20/25
- cor beton 3.51 m³ 0.124% 3.51 m³ 0.124% m³ 0.000% m³ 0.000%
- pembesian 3.51 m³ 0.415% 3.51 m³ 0.415% m³ 0.000% m³ 0.000%
- bekisting 3.51 m³ 0.192% 3.51 m³ 0.192% m³ 0.000% m³ 0.000%
27 Cor balok beton lantai 2 B7 20/20
- cor beton 2.90 m³ 0.087% 2.90 m³ 0.087% m³ 0.000% m³ 0.000%
- pembesian 2.90 m³ 0.274% 2.90 m³ 0.274% m³ 0.000% m³ 0.000%
- bekisting 2.90 m³ 0.153% 2.90 m³ 0.153% m³ 0.000% m³ 0.000%
28 Cor balok beton lantai 2 B8 15/50
- cor beton 2.78 m³ 0.127% 2.78 m³ 0.127% m³ 0.000% m³ 0.000%
- pembesian 2.78 m³ 0.178% 2.78 m³ 0.178% m³ 0.000% m³ 0.000%
- bekisting 2.78 m³ 0.179% 2.78 m³ 0.179% m³ 0.000% m³ 0.000%
29 Cor balok beton lantai 2 B9 20/30
- cor beton 0.81 m³ 0.031% 0.81 m³ 0.031% m³ 0.000% m³ 0.000%
- pembesian 0.81 m³ 0.055% 0.81 m³ 0.055% m³ 0.000% m³ 0.000%
- bekisting 0.81 m³ 0.042% 0.81 m³ 0.042% m³ 0.000% m³ 0.000%
LAPORAN MINGGUAN

VOLUME 100% VOLUME TERPASANG VOLUME DIKERJAKAN VOLUME SISA


NO NAMA PEKERJAAN
VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT%

30 Cor balok beton lantai 2 B10 15/25


- cor beton 0.58 m³ 0.020% 0.58 m³ 0.020% m³ 0.000% m³ 0.000%
- pembesian 0.58 m³ 0.058% 0.58 m³ 0.058% m³ 0.000% m³ 0.000%
- bekisting 0.58 m³ 0.034% 0.58 m³ 0.034% m³ 0.000% m³ 0.000%
31 Cor balok atap dan balok talang beton B11 15/30
- cor beton 6.36 m³ 0.246% 6.36 m³ 0.246% m³ 0.000% m³ 0.000%
- pembesian 6.36 m³ 0.548% 6.36 m³ 0.548% m³ 0.000% m³ 0.000%
- bekisting 6.36 m³ 0.377% 6.36 m³ 0.377% m³ 0.000% m³ 0.000%
32 Cor lisplank beton B12 10/50 (LT 3 TAP)
- cor beton 2.67 m³ 0.103% 2.67 m³ 0.103% m³ 0.000% m³ 0.000%
- pembesian 2.67 m³ 0.209% 2.67 m³ 0.209% m³ 0.000% m³ 0.000%
- bekisting 2.67 m³ 0.210% 2.67 m³ 0.210% m³ 0.000% m³ 0.000%
33 Cor balok tandon B3 20/30
- cor beton 0.60 m³ 0.023% 0.60 m³ 0.023% m³ 0.000% m³ 0.000%
- pembesian 0.60 m³ 0.061% 0.60 m³ 0.061% m³ 0.000% m³ 0.000%
- bekisting 0.60 m³ 0.031% 0.60 m³ 0.031% m³ 0.000% m³ 0.000%
34 Cor ring balok praktis R1 15/20 (LT 3 ATAP)
- cor beton 1.02 m³ 0.057% 1.02 m³ 0.057% m³ 0.000% m³ 0.000%
- pembesian 1.02 m³ 0.067% 1.02 m³ 0.067% m³ 0.000% m³ 0.000%
- bekisting 1.02 m³ 0.043% 1.02 m³ 0.043% m³ 0.000% m³ 0.000%
35 Cor ring balok latio 15/30
- cor beton 2.12 m³ 0.119% 2.12 m³ 0.119% m³ 0.000% m³ 0.000%
- pembesian 2.12 m³ 0.183% 2.12 m³ 0.183% m³ 0.000% m³ 0.000%
- bekisting 2.12 m³ 0.133% 2.12 m³ 0.133% m³ 0.000% m³ 0.000%
36 Cor ring balok rangka kusen 15/15
- cor beton 6.88 m³ 0.386% 6.88 m³ 0.386% m³ 0.000% m³ 0.000%
- pembesian 6.88 m³ 0.294% 6.88 m³ 0.294% m³ 0.000% m³ 0.000%
- bekisting 6.88 m³ 0.298% 6.88 m³ 0.298% m³ 0.000% m³ 0.000%
37 Cor janggutan balok 6.00 m' 0.039% 6.00 m' 0.039% m' 0.000% m' 0.000%
38 Cor plat dak lantai 2 tebal 12 cm (readymix)
- cor beton 19.98 m³ 1.220% 19.98 m³ 1.220% m³ 0.000% m³ 0.000%
- pembesian 19.98 m³ 0.778% 19.98 m³ 0.778% m³ 0.000% m³ 0.000%
- bekisting 19.98 m³ 1.138% 19.98 m³ 1.138% m³ 0.000% m³ 0.000%
39 Cor plat dak lantai 3 tebal 12 cm (readymix)
- cor beton 16.80 m³ 1.026% 16.80 m³ 1.026% m³ 0.000% m³ 0.000%
- pembesian 16.80 m³ 0.654% 16.80 m³ 0.654% m³ 0.000% m³ 0.000%
- bekisting 16.80 m³ 0.957% 16.80 m³ 0.957% m³ 0.000% m³ 0.000%
40 Cor plat dak atap lantai 3 tebal 12 cm (LT 3 ATAP)
- cor beton 1.80 m³ 0.101% 1.80 m³ 0.101% m³ 0.000% m³ 0.000%
- pembesian 1.80 m³ 0.070% 1.80 m³ 0.070% m³ 0.000% m³ 0.000%
- bekisting 1.80 m³ 0.092% 1.80 m³ 0.092% m³ 0.000% m³ 0.000%
41 Cor plat tandon tebal 12 cm
- cor beton 0.48 m³ 0.027% 0.48 m³ 0.027% m³ 0.000% m³ 0.000%
- pembesian 0.48 m³ 0.019% 0.48 m³ 0.019% m³ 0.000% m³ 0.000%
- bekisting 0.48 m³ 0.025% 0.48 m³ 0.025% m³ 0.000% m³ 0.000%
42 Cor plat talang beton lantai 3 tebal 12 cm
- cor beton 4.85 m³ 0.272% 4.85 m³ 0.272% m³ 0.000% m³ 0.000%
- pembesian 4.85 m³ 0.189% 4.85 m³ 0.189% m³ 0.000% m³ 0.000%
- bekisting 4.85 m³ 0.248% 4.85 m³ 0.248% m³ 0.000% m³ 0.000%
43 Plat luifel 12 cm
- cor beton 31.49 m² 0.177% 31.49 m² 0.177% m² 0.000% m² 0.000%
- pembesian 31.49 m² 0.176% 31.49 m² 0.176% m² 0.000% m² 0.000%
- bekisting 31.49 m² 0.293% 31.49 m² 0.293% m² 0.000% m² 0.000%
44 Plat tangga beton ke lantai 2 dan lantai 3
- cor beton 2.90 m³ 0.163% 2.90 m³ 0.163% m³ 0.000% m³ 0.000%
- pembesian 2.90 m³ 0.113% 2.90 m³ 0.113% m³ 0.000% m³ 0.000%
- bekisting 2.90 m³ 0.165% 2.90 m³ 0.165% m³ 0.000% m³ 0.000%
45 Cor meja dapur
- cor beton 6.50 m' 0.037% 6.50 m' 0.037% m' 0.000% m' 0.000%
- pembesian 6.50 m' 0.036% 6.50 m' 0.036% m' 0.000% m' 0.000%
- bekisting 6.50 m' 0.060% 6.50 m' 0.060% m' 0.000% m' 0.000%

IV PEK. PASANGAN
1 Pasangan pondasi batu belah 1:6 47.50 m³ 1.826% 47.50 m³ 1.826% m³ 0.000% m³ 0.000%
2 Pasangan bata trassram 104.34 m² 0.529% 104.34 m² 0.529% m² 0.000% m² 0.000%
3 Pasangan bata 1 : 6 lantai 1 272.74 m² 1.403% 272.74 m² 1.403% m² 0.000% m² 0.000%
4 Pasangan bata 1 : 6 lantai 2 323.49 m² 1.664% 323.49 m² 1.664% m² 0.000% m² 0.000%
5 Pasangan bata 1 : 6 lantai 3 311.87 m² 1.604% 311.87 m² 1.604% m² 0.000% m² 0.000%
6 Sponengan 3,510.90 m' 1.531% 3281.00 m' 1.431% 206.30 m' 0.090% 23.60 m' 0.010%
7 Tali air 108.15 m' 0.047% 108.15 m' 0.047% m' 0.000% m' 0.000%
8 Plesteran trassram 1 : 4 208.68 m² 0.546% 208.68 m² 0.546% m² 0.000% m² 0.000%
9 Plesteran 1 : 6 lantai 1 545.48 m² 1.524% 545.48 m² 1.524% m² 0.000% m² 0.000%
LAPORAN MINGGUAN

VOLUME 100% VOLUME TERPASANG VOLUME DIKERJAKAN VOLUME SISA


NO NAMA PEKERJAAN
VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT%

10 Plesteran 1 : 6 lantai 2 646.97 m² 1.807% 646.97 m² 1.807% m² 0.000% m² 0.000%


11 Plesteran 1 : 6 lantai 3 623.73 m² 1.742% 623.73 m² 1.742% m² 0.000% m² 0.000%
12 Plesteran luifel dan canopy 67.52 m² 0.218% 67.52 m² 0.218% m² 0.000% m² 0.000%
13 Ban - banan jendela 102.20 m' 0.312% 102.20 m' 0.312% m' 0.000% m' 0.000%
14 Plesteran plat tangga naik 18.06 m² 0.070% 18.06 m² 0.070% m² 0.000% m² 0.000%
15 Plesteran kolom dan balok 102.56 m² 0.331% 102.56 m² 0.331% m² 0.000% m² 0.000%
16 Plesteran gawangan kusen 567.35 m' 0.742% 567.35 m' 0.742% m' 0.000% m' 0.000%
17 Plesteran dak talang beton dan atap beton 181.50 m² 0.705% 181.50 m² 0.705% m² 0.000% m² 0.000%
18 Plesteran ban banan jendela 102.20 m' 0.223% 102.20 m' 0.223% m' 0.000% m' 0.000%
19 Pasangan tembok berlubang 18.75 m² 0.266% 18.75 m² 0.266% m² 0.000% m² 0.000%
20 Trap tangga rollag bata 54.30 m' 0.083% 54.30 m' 0.083% m' 0.000% m' 0.000%
21 Rumah genset 1.00 unit 0.196% unit 0.000% unit 0.000% 1.00 unit 0.196%

V PEK. RAILING DAN BESI PAGAR KACA


1 Railling tangga besi hollow 13.80 m' 0.361% 13.80 m' 0.361% m' 0.000% m' 0.000%
2 Railling balkon teras (pas bata dan besi) 42.00 m' 0.797% 42.00 m' 0.797% m' 0.000% m' 0.000%
3 Tangga ke tandon dan railing tandon 1.00 unit 0.305% unit 0.000% 1.00 unit 0.305% unit 0.000%
4 Tangga putar besi sampai lantai 3 1.00 unit 0.305% unit 0.000% unit 0.000% 1.00 unit 0.305%

VI PEK. KERAMIK
LANTAI 1
1 Lantai ruangan,60x60 cm ex platinum 98.48 m² 0.779% 98.48 m² 0.779% m² 0.000% m² 0.000%
2 Lantai teras kamar 60x60 cm ex granite tile gelap 8.70 m² 0.097% 8.70 m² 0.097% m² 0.000% m² 0.000%
3 Lantai teras depan 60x60 ex granite tile gelap 2.82 m² 0.031% 2.82 m² 0.031% m² 0.000% m² 0.000%
4 Lantai parkir motor dan koridor 40x40 ex Platinum 45.15 m² 0.275% 33.77 m² 0.206% 11.38 m² 0.069% m² 0.000%
5 Lantai ruang jaga 40x40 ex Platinum 5.50 m² 0.034% m² 0.000% 5.50 m² 0.034% m² 0.000%
6 Lantai ruang genset 40 x 40 ex Platinum 2.00 m² 0.012% m² 0.000% 2.00 m² 0.012% m² 0.000%
7 Lantai keramik kamar mandi ex Platinum 40x40 14.28 m² 0.087% 14.28 m² 0.087% m² 0.000% m² 0.000%
8 Trap tangga naik ke lantai 2 ex granite tile gelap 11.20 m² 0.132% 11.20 m² 0.132% m² 0.000% m² 0.000%
9 Trap tangga teras depan ex granite tile gelap 2.40 m² 0.028% 2.40 m² 0.028% m² 0.000% m² 0.000%
10 Dinding keramik kamar mandi ex platinum 20x40 97.59 m² 0.794% 97.59 m² 0.794% m² 0.000% m² 0.000%
11 Meja dapur ex granite tile gelap 3.50 m² 0.041% 3.50 m² 0.041% m² 0.000% m² 0.000%
12 Dinding dapur ex granite tile gelap 4.44 m² 0.052% 4.44 m² 0.052% m² 0.000% m² 0.000%
13 Plin lantai ruangan 70.44 m' 0.154% 70.44 m' 0.154% m' 0.000% m' 0.000%
14 Plin trap lantai tangga naik ke lantai 2 12.50 m' 0.044% 12.50 m' 0.044% m' 0.000% m' 0.000%
15 Plin lantai dapur 8.54 m' 0.019% 8.54 m' 0.019% m' 0.000% m' 0.000%
16 Plin lantai teras depan dan teras kamar 15.60 m' 0.041% 15.60 m' 0.041% m' 0.000% m' 0.000%
17 Plin lantai ruang jaga dan parkir 37.25 m' 0.065% 11.60 m' 0.020% 15.80 m' 0.028% 9.85 m' 0.017%
18 Pingul meja dapur 5.00 m' 0.022% 5.00 m' 0.022% m' 0.000% m' 0.000%

LANTAI 2
1 Lantai ruangan,60x60 cm ex platinum 88.71 m² 0.702% 88.71 m² 0.702% m² 0.000% m² 0.000%

2 Lantai teras kamar 60x60 cm ex granite tile gelap 13.05 m² 0.145% 13.05 m² 0.145% m² 0.000% m² 0.000%

Lantai gudang dan cuci jemur, koridor 40x40 ex


3 22.25 m² 0.136% 22.25 m² 0.136% m² 0.000% m² 0.000%
Platinum
4 Lantai keramik kamar mandi ex Platinum 40x40 15.63 m² 0.095% 15.63 m² 0.095% m² 0.000% m² 0.000%
5 Trap tangga naik ke lantai 3 ex granite tile gelap 11.20 m² 0.132% 11.20 m² 0.132% m² 0.000% m² 0.000%
6 Dinding keramik kamar mandi ex platinum 20x40 107.69 m² 0.876% 107.69 m² 0.876% m² 0.000% m² 0.000%
7 Meja dapur ex granite tile gelap 1.40 m² 0.017% 1.40 m² 0.017% m² 0.000% m² 0.000%
8 Dinding dapur ex granite tile gelap 1.92 m² 0.023% 1.92 m² 0.023% m² 0.000% m² 0.000%
9 Plin lantai ruangan 88.35 m' 0.193% 88.35 m' 0.193% m' 0.000% m' 0.000%
10 Plin trap lantai tangga naik ke lantai 3 12.50 m' 0.044% 12.50 m' 0.044% m' 0.000% m' 0.000%
11 Plin lantai teras kamar 17.70 m' 0.046% 17.70 m' 0.046% m' 0.000% m' 0.000%
12 Plin lantai gudang dan cuci jemur, koridor 43.40 m' 0.076% 43.40 m' 0.076% m' 0.000% m' 0.000%
13 Pingul meja dapur 2.00 m' 0.009% 2.00 m' 0.009% m' 0.000% m' 0.000%

LANTAI 3
1 Lantai ruangan,60x60 cm ex platinum 88.71 m² 0.702% 88.71 m² 0.702% m² 0.000% m² 0.000%
2 Lantai teras kamar 60x60 cm ex granite tile gelap 13.05 m² 0.145% 13.05 m² 0.145% m² 0.000% m² 0.000%
3 Lantai koridor 40x40 ex Platinum 10.70 m² 0.065% 10.70 m² 0.065% m² 0.000% m² 0.000%
4 Lantai keramik kamar mandi ex Platinum 40x40 15.63 m² 0.095% 15.63 m² 0.095% m² 0.000% m² 0.000%
5 Dinding keramik kamar mandi ex platinum 20x40 99.60 m² 0.810% 99.60 m² 0.810% m² 0.000% m² 0.000%
6 Meja dapur ex granite tile gelap 1.40 m² 0.017% 1.40 m² 0.017% m² 0.000% m² 0.000%
7 Dinding dapur ex granite tile gelap 1.92 m² 0.023% 1.92 m² 0.023% m² 0.000% m² 0.000%
8 Plin lantai ruangan 88.35 m' 0.193% 88.35 m' 0.193% m' 0.000% m' 0.000%
9 Plin lantai teras kamar 17.70 m' 0.046% 17.70 m' 0.046% m' 0.000% m' 0.000%
10 Plin lantai koridor 24.50 m' 0.053% 24.50 m' 0.053% m' 0.000% m' 0.000%
11 Pingul meja dapur 2.00 m' 0.009% 2.00 m' 0.009% m' 0.000% m' 0.000%

VII PEK. SANITASI


1 Sal air kotor PVC 2" Maspion AW abu abu 66.00 m' 0.101% 66.00 m' 0.101% m' 0.000% m' 0.000%
2 Sal air kotor PVC 3" Maspion D abu abu 360.00 m' 1.177% 360.00 m' 1.177% m' 0.000% m' 0.000%
LAPORAN MINGGUAN

VOLUME 100% VOLUME TERPASANG VOLUME DIKERJAKAN VOLUME SISA


NO NAMA PEKERJAAN
VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT%

3 Sal air kotor PVC 4" Maspion D abu abu 324.00 m' 1.413% 324.00 m' 1.413% m' 0.000% m' 0.000%
4 Sal air kotor PVC 5" Maspion D abu abu 104.70 m' 0.571% 104.70 m' 0.571% m' 0.000% m' 0.000%
5 Sal air kotor AC PVC 3/4" Maspion D 126.00 m' 0.110% 126.00 m' 0.110% m' 0.000% m' 0.000%
6 Bak kontrol 40 x 40 cm 12.00 bh 0.183% 12.00 bh 0.183% bh 0.000% bh 0.000%
7 Saluran air panas 1/2" 48.00 m' 0.167% 48.00 m' 0.167% m' 0.000% m' 0.000%
8 Saluran air bersih PVC 3/4" 186.40 m' 0.163% 186.40 m' 0.163% m' 0.000% m' 0.000%
9 Saluran air bersih PVC 1" 241.50 m' 0.263% 241.50 m' 0.263% m' 0.000% m' 0.000%
10 Saluran air bersih PVC 1 1/2" 50.70 m' 0.062% 50.70 m' 0.062% m' 0.000% m' 0.000%
11 Septictank dan peresapan 1.00 unit 0.654% unit 0.000% unit 0.000% 1.00 unit 0.654%
12 Closet duduk ex American Standard 17.00 bh 1.408% 17.00 bh 1.408% bh 0.000% bh 0.000%
13 Closet jongkok ex INA 1.00 bh 0.031% 1.00 bh 0.031% bh 0.000% bh 0.000%
14 Wastafel ex CINA 16.00 bh 0.384% 16.00 bh 0.384% bh 0.000% bh 0.000%
15 Wastafel ex American Standard 1.00 bh 0.041% 1.00 bh 0.041% bh 0.000% bh 0.000%
16 Kran wastafel ex Wasser 17.00 bh 0.241% 17.00 bh 0.241% bh 0.000% bh 0.000%
17 Kran dinding T kamar mandi ex Onda 17.00 bh 0.148% bh 0.000% 17.00 bh 0.148% bh 0.000%
18 Kran dinding ex Onda 7.00 bh 0.046% bh 0.000% bh 0.000% 7.00 bh 0.046%
19 Shower spray dan kran air panas dingin ex Wasser 16.00 bh 0.802% 16.00 bh 0.802% bh 0.000% bh 0.000%
20 Jet washer ex Wasser 18.00 bh 0.184% 18.00 bh 0.184% bh 0.000% bh 0.000%
21 Kitchen zink dapur ex Royal 3.00 bh 0.059% 3.00 bh 0.059% bh 0.000% bh 0.000%
22 Kran kitchen zink dapur ex Onda 3.00 bh 0.039% 1.00 bh 0.013% 2.00 bh 0.026% bh 0.000%
23 Floordrain ex SAN EI 33.00 bh 0.360% 30.00 bh 0.327% 3.00 bh 0.033% bh 0.000%
24 Roof drain ex SAN EI 4" 4.00 bh 0.052% bh 0.000% 4.00 bh 0.052% bh 0.000%
25 Radar air 1.00 bh 0.003% bh 0.000% bh 0.000% 1.00 bh 0.003%
26 Stop kran tandon ex KITZ 1" 4.00 bh 0.061% bh 0.000% 4.00 bh 0.061% bh 0.000%
27 Tandon bawah tanah 2,5x2x2 m
- cor beton 1.00 bh 0.246% 1.00 bh 0.246% bh 0.000% bh 0.000%
- pembesian 1.00 bh 0.150% 1.00 bh 0.150% bh 0.000% bh 0.000%
- bekisting 1.00 bh 0.201% 1.00 bh 0.201% bh 0.000% bh 0.000%
- galian dan perataan 1.00 bh 0.110% 1.00 bh 0.110% bh 0.000% bh 0.000%
- tutup plat 1.00 bh 0.065% 1.00 bh 0.065% bh 0.000% bh 0.000%
28 Tandon atas (upah pasang) 1.00 bh 0.022% 1.00 bh 0.022% bh 0.000% bh 0.000%
29 Pompa air jet pump 1.00 unit 0.087% unit 0.000% unit 0.000% 1.00 unit 0.087%
30 Pompa pendorong 1.00 unit 0.035% unit 0.000% unit 0.000% 1.00 unit 0.035%

VII
PEK. KUSEN PINTU DAN JENDELA
I
LANTAI 1
1 Kusen Upvc dan pintu P1 19.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%

2 Kusen dan pintu aluminium rangka kaca P2 ( by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%

3 Kusen dan puntu P3 Upvc 17.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
4 Kusen Upvc dan pintu P4 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
5 Kusen Upvc dan pintu P5 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
6 Kusen dan pintu P6 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
7 Kusen dan jendela kaca aluminium J1 ( by owner ) 3.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
8 Kusen dan jendela kaca aluminium J2 ( by owner ) 18.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
9 Kusen dan kaca aluminium J3 ( by owner ) 18.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
10 Kusen dan jendela kaca aluminium J4 ( by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
11 Kusen dan kaca aluminium J5 ( by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
12 Kusen dan kaca aluminium J6 ( by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
13 Kusen dan kaca aluminium J7 ( by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
14 Kusen dan jendela kaca aluminium J8 ( by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
Kusen dan pintu aluminium rangka kaca PJ1 ( by owner
15 16.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%
)
16 Kusen dan pintu aluminium rangka kaca PJ2 (by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%

17 Kusen dan jendela kaca aluminium BV1 ( by owner ) 1.00 unit 0.000% unit 0.000% unit 0.000% unit 0.000%

18 Kusen dan pintu PB 1.00 unit 0.065% unit 0.000% unit 0.000% 1.00 unit 0.065%

IX PEK. PLAFOND
1 Plafond gypsum rangka hollow 419.16 m² 2.376% 413.66 m² 2.345% 5.50 m² 0.031% m² 0.000%
2 Plafond luar kalsiboard rangka hollow 32.59 m² 0.213% 32.59 m² 0.213% m² 0.000% m² 0.000%
3 Plafond gypsum drop ceiling 33.80 m' 0.192% 33.80 m' 0.192% m' 0.000% m' 0.000%
4 List plafond gypsum 636.96 m' 0.555% 636.96 m' 0.555% m' 0.000% m' 0.000%

X PEK. LISTRIK
1 Instalasi titik lampu,kabel NYM 2x1,5mm eterna 131.00 ttk 1.199% 131.00 ttk 1.199% ttk 0.000% ttk 0.000%
2 Instalasi stop kontak ,kabel NYM 2x2,5mm eterna 48.00 ttk 0.492% 48.00 ttk 0.492% ttk 0.000% ttk 0.000%

3 Instalasi titik lampu taman ,kabel NYY 2x1,5mm eterna 3.00 ttk 0.034% 3.00 ttk 0.034% ttk 0.000% ttk 0.000%

4 Instalasi stop kontak pompa 3.00 ttk 0.031% 3.00 ttk 0.031% ttk 0.000% ttk 0.000%
5 Instalasi stop kontak water heater 16.00 ttk 0.164% 16.00 ttk 0.164% ttk 0.000% ttk 0.000%
6 Instalasi stop kontak filter air 1.00 ttk 0.010% 1.00 ttk 0.010% ttk 0.000% ttk 0.000%
LAPORAN MINGGUAN

VOLUME 100% VOLUME TERPASANG VOLUME DIKERJAKAN VOLUME SISA


NO NAMA PEKERJAAN
VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT%

7 Instalasi AC, kabel 3x2,5mm 20.00 ttk 0.314% 20.00 ttk 0.314% ttk 0.000% ttk 0.000%
8 Instalasi telpon 1.00 ttk 0.010% ttk 0.000% ttk 0.000% 1.00 ttk 0.010%
9 Instalasi televisi 18.00 ttk 0.184% 18.00 ttk 0.184% ttk 0.000% ttk 0.000%
10 Instalasi bell pintu 1.00 ttk 0.016% ttk 0.000% 1.00 ttk 0.016% ttk 0.000%
11 Penangkal petir 1.00 unit 0.349% 1.00 unit 0.349% unit 0.000% unit 0.000%
12 Stop kontak ex Broco 68.00 bh 0.059% 68.00 bh 0.059% bh 0.000% bh 0.000%
13 Saklar tunggal ex Broco 15.00 bh 0.013% 15.00 bh 0.013% bh 0.000% bh 0.000%
14 Saklar ganda ex Broco 49.00 bh 0.053% 49.00 bh 0.053% bh 0.000% bh 0.000%
15 Stop kontak AC ex Broco 20.00 bh 0.061% 20.00 bh 0.061% bh 0.000% bh 0.000%
16 MCB ex Broco 18.00 pas 0.078% 18.00 pas 0.078% pas 0.000% pas 0.000%
17 Box MCB 18.00 bh 0.157% 18.00 bh 0.157% bh 0.000% bh 0.000%
18 Downlight ex Sunlie [Panasonic] 79.00 bh 0.148% 79.00 bh 0.148% bh 0.000% bh 0.000%
19 Fitting ex Broco [Panasonic] 42.00 bh 0.029% 42.00 bh 0.029% bh 0.000% bh 0.000%
20 Lampu paralel/strip ruangan 22.38 m' 0.073% 22.38 m' 0.073% m' 0.000% m' 0.000%
21 Lampu baret bulat 2.00 bh 0.031% 2.00 bh 0.031% bh 0.000% bh 0.000%
22 Lampu baret kotak 2.00 bh 0.031% 2.00 bh 0.031% bh 0.000% bh 0.000%
23 Lampu dinding 5.00 bh 0.076% 2.00 bh 0.031% bh 0.000% 3.00 bh 0.046%
24 Lampu LED Hannoch 9W 126.00 bh 0.220% 126.00 bh 0.220% bh 0.000% bh 0.000%
25 Kabel oper spanning 1.00 ls 0.654% 1.00 ls 0.654% ls 0.000% ls 0.000%
26 Arde tanah 1.00 unit 0.011% 1.00 unit 0.011% unit 0.000% unit 0.000%
27 Stop kontak genset dan handle genset 1.00 unit 0.109% unit 0.000% unit 0.000% 1.00 unit 0.109%

XI PEK. FINISHING
1 Cat dinding dalam ex Dulux 1,054.86 m² 1.426% 811.67 m² 1.097% 96.09 m² 0.130% 147.11 m² 0.199%
2 Cat dinding luar ex Dulux 601.73 m² 1.115% 246.07 m² 0.456% 49.54 m² 0.092% 306.13 m² 0.567%
3 Sealer dinding 1,656.59 m² 0.542% 1621.29 m² 0.530% 35.30 m² 0.012% m² 0.000%
4 Cat luifel ex Dulux 67.52 m² 0.125% 24.00 m² 0.044% 43.52 m² 0.081% m² 0.000%
5 Cat ban - banan ex Dulux 130.66 m' 0.100% 36.57 m' 0.028% 94.09 m' 0.072% m' 0.000%
6 Aquaproof dak lantai 2 dan lantai 3 102.00 m² 0.111% 102.00 m² 0.111% m² 0.000% m² 0.000%
7 Aquaproof dak talang dan atap 77.75 m² 0.085% 77.75 m² 0.085% m² 0.000% m² 0.000%
8 Aquaproof nok 38.70 m' 0.042% 38.70 m' 0.042% m' 0.000% m' 0.000%
9 Cat lisplank 51.60 m' 0.045% 51.60 m' 0.045% m' 0.000% m' 0.000%
10 Cat genteng beton 183.42 m² 0.240% 183.42 m² 0.240% m² 0.000% m² 0.000%

XII PEK. ATAP


1 Kuda - kuda atap baja ringan ex Bukit 175.83 m² 1.495% 175.83 m² 1.495% m² 0.000% m² 0.000%
2 Genteng beton flat 175.83 m² 1.150% 175.83 m² 1.150% m² 0.000% m² 0.000%
3 Galvalum plat bawah genteng 175.83 m² 0.307% 175.83 m² 0.307% m² 0.000% m² 0.000%
4 Nok genteng keramik 38.70 m' 0.270% 38.70 m' 0.270% m' 0.000% m' 0.000%
5 Lisplank kalsiplank double 20 cm 51.60 m' 0.225% 51.60 m' 0.225% m' 0.000% m' 0.000%
6 Atap drying court lantai 2 20.10 m² 0.679% 20.10 m² 0.679% m² 0.000% m² 0.000%

PEKERJAAN : PAGAR (t = 3 m), CARPORT DAN


PAGAR DAN HALAMAN DEPAN
I PEK. TANAH
1 Galian tanah pondasi 33.50 m³ 0.146% 33.50 m³ 0.146% m³ 0.000% m³ 0.000%
2 Galian tanah footplat pagar 12.00 m³ 0.052% 12.00 m³ 0.052% m³ 0.000% m³ 0.000%
3 Galian tanah pondasi depan 5.04 m³ 0.022% 5.04 m³ 0.022% m³ 0.000% m³ 0.000%
4 Urugan tanah kembali 20.78 m³ 0.072% 20.78 m³ 0.072% m³ 0.000% m³ 0.000%
5 Perataan tanah kembali 29.76 m³ 0.104% 21.79 m³ 0.076% m³ 0.000% 7.97 m³ 0.028%
6 Pemadatan halaman 157.00 m³ 0.103% 109.90 m³ 0.072% m³ 0.000% 47.10 m³ 0.031%
7 Urugan pasir bawah pondasi 5 cm 2.16 m³ 0.042% 2.16 m³ 0.042% m³ 0.000% m³ 0.000%
8 Urugan pasir bawah footplat 5 cm 0.40 m³ 0.008% 0.40 m³ 0.008% m³ 0.000% m³ 0.000%
9 Urugan pasir bawah paving 10 cm 15.70 m³ 0.308% 11.80 m³ 0.232% m³ 0.000% 3.90 m³ 0.077%

II PEK. BETON
1 Lantai kerja 1 : 3 : 5 50.48 m² 0.130% 50.48 m² 0.130% m² 0.000% m² 0.000%
2 Cor footplat pagar 60 x 60 cm
0.72 m³ 0.042% 0.72 m³ 0.042% m³ 0.000% m³ 0.000%
0.72 m³ 0.050% 0.72 m³ 0.050% m³ 0.000% m³ 0.000%
0.72 m³ 0.010% 0.72 m³ 0.010% m³ 0.000% m³ 0.000%
3 Cor jembatan pintu masuk 15 cm
9.00 m² 0.101% m² 0.000% m² 0.000% 9.00 m² 0.101%
9.00 m² 0.058% m² 0.000% m² 0.000% 9.00 m² 0.058%
9.00 m² 0.053% m² 0.000% m² 0.000% 9.00 m² 0.053%
4 Sloof 15/20
1.20 m³ 0.071% 1.20 m³ 0.071% m³ 0.000% m³ 0.000%
1.20 m³ 0.121% 1.20 m³ 0.121% m³ 0.000% m³ 0.000%
1.20 m³ 0.061% 1.20 m³ 0.061% m³ 0.000% m³ 0.000%
5 Kolom praktis 15/15
0.47 m³ 0.026% 0.47 m³ 0.026% m³ 0.000% m³ 0.000%
0.47 m³ 0.027% 0.47 m³ 0.027% m³ 0.000% m³ 0.000%
LAPORAN MINGGUAN

VOLUME 100% VOLUME TERPASANG VOLUME DIKERJAKAN VOLUME SISA


NO NAMA PEKERJAAN
VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT% VOLUME SAT BOBOT%

0.47 m³ 0.020% 0.47 m³ 0.020% m³ 0.000% m³ 0.000%


6 Kolom K11 15/30
1.62 m³ 0.102% 1.62 m³ 0.102% m³ 0.000% m³ 0.000%
1.62 m³ 0.160% 1.62 m³ 0.160% m³ 0.000% m³ 0.000%
1.62 m³ 0.082% 1.62 m³ 0.082% m³ 0.000% m³ 0.000%
7 Ring praktis 15/15
0.88 m³ 0.049% 0.88 m³ 0.049% m³ 0.000% m³ 0.000%
0.88 m³ 0.051% 0.88 m³ 0.051% m³ 0.000% m³ 0.000%
0.88 m³ 0.038% 0.88 m³ 0.038% m³ 0.000% m³ 0.000%

III PEK. PASANGAN


1 Pasangan pondasi batu belah 1:6 13.72 m³ 0.527% 13.72 m³ 0.527% m³ 0.000% m³ 0.000%
2 Pasangan pondasi batu belah 1:6 (depan) 4.73 m³ 0.182% 1.48 m³ 0.057% m³ 0.000% 3.25 m³ 0.125%
3 Pasangan bata 1 : 6 117.60 m² 0.605% 117.60 m² 0.605% m² 0.000% m² 0.000%
4 Plesteran 1 : 6 235.20 m² 0.657% 235.20 m² 0.657% m² 0.000% m² 0.000%
5 Plesteran balok dan kolom 6.78 m² 0.022% 6.78 m² 0.022% m² 0.000% m² 0.000%
6 Tali air 110.00 m' 0.048% 110.00 m' 0.048% m' 0.000% m' 0.000%
7 Sponengan 93.40 m' 0.041% 93.40 m' 0.041% m' 0.000% m' 0.000%
8 Pasangan paving block 157.00 m² 0.890% 118.00 m² 0.669% m² 0.000% 39.00 m² 0.221%
9 Kansteen taman 9.50 m' 0.083% m' 0.000% 9.50 m' 0.083% m' 0.000%

IV PEK. FINISHING
1 Cat dinding luar ex Dulux 124.40 m² 0.231% m² 0.000% 61.98 m² 0.115% 62.42 m² 0.116%
2 Sealer dinding 124.40 m² 0.041% 124.40 m² 0.041% m² 0.000% m² 0.000%

PEKERJAAN : VOLUME TAMBAH


I PEK. PERSIAPAN
1 Pembersihan lokasi 180.00 m² 0.027% m² 0.000% m² 0.000% 180.00 m² 0.027%
2 Pasang pagar pengaman 28.00 m' 0.183% 28.00 m' 0.183% m' 0.000% m' 0.000%

II PEK. TANAH
1 Bongkar pondasi lama area footplat 25.86 m³ 0.451% 25.86 m³ 0.451% m³ 0.000% m³ 0.000%
2 Bongkar lantai lama area footplat 58.70 m² 0.064% 58.70 m² 0.064% m² 0.000% m² 0.000%
3 Bongkar pondasi lama area pondasi 2.24 m³ 0.039% 2.24 m³ 0.039% m³ 0.000% m³ 0.000%
4 Kuras air 104.20 m³ 0.182% 104.20 m³ 0.182% m³ 0.000% m³ 0.000%
5 Buang galian (1) 1.00 ls 0.975% 1.00 ls 0.975% ls 0.000% ls 0.000%
6 Buang galian (2) 12.00 rit 0.209% 12.00 rit 0.209% rit 0.000% rit 0.000%

III PEK. KONSTRUKSI


1 Pemasangan pipa kamar mandi + kran 16.00 unit 0.195% 16.00 unit 0.195% unit 0.000% unit 0.000%
2 List Keramik Kamar Mandi 94.40 m' 0.206% 94.40 m' 0.206% m' 0.000% m' 0.000%
3 Pemasangan Kusen KM/ WC 18.00 unit 0.118% 18.00 unit 0.118% unit 0.000% unit 0.000%
4 Sticker Stepnosing Tangga 39.60 m' 0.016% m' 0.000% m' 0.000% 39.60 m' 0.016%
5 Tangga akses ke tandon 5.02 m' 0.055% 5.02 m' 0.055% m' 0.000% m' 0.000%
6 Tempat Sabun KM/ WC 18.00 unit 0.047% 18.00 unit 0.047% unit 0.000% unit 0.000%
7 Pembongkaran Dinding untuk Jendela 4.40 m² 0.023% 4.40 m² 0.023% m² 0.000% m² 0.000%
8 Buang galian (3) 15.00 rit 0.262% 15.00 rit 0.262% rit 0.000% rit 0.000%
9 Cantolan Terpal 6.00 titik 0.021% 6.00 titik 0.021% titik 0.000% titik 0.000%

TOTAL KUMULATIF 100.00% 95.01% 1.57% 3.41%


PROGRESS RENCANA MC-100 100.00%
PROGRESS REALISASI 96.59%
DEVIASI -3.41% TERLAMBAT

Semarang, 5 Februari 2022 CATATAN : 05/02/2022


Konsultan Pengawas PERKIRAAN PEKERJAAN SELESAI = 15 HARI.
PADA TANGGAL = 20/02/2022

BP. DWI RESPONO ADHI