B PEKERJAAN LANDSCAPE
B.I. LANDSCAPE DI LOKASI BANGUNAN PENGOLAH LUMPUR ( PASANG BARU DAN PERBAIKAN KERUSAKAN )
1 Urugan kembali 91,200 m3 0,004 20% 1,000 1,000 1,000 1,000 1,000 1,000
2 Urugan pasir dibawah paving tebal 4 cm 60,800 m3 0,176 100% 1,000 1,000 1,000
3 Urugan sirtu tebal 20 cm padat 304,000 m3 0,642 100% 1,000 1,000 1,000 1,000
4 Pemadatan 304,000 m3 0,095 100% 1,000 1,000 1,000
5 Pasangan paving blok mutu K300 tebal 8 cm ( Volume baru 50%) 760,000 m2 0,941 100% 1,000 1,000 1,000 1,000
6 Pasangan batu kali 1 : 3 20,000 m3 0,173 100% 1,000 1,000 1,000 1,000
7 Saluran buis beton 30 cm 80,000 m 0,220 100% 1,000 1,000 1,000
8 Kansteen ukuran 20 x 30 x 50 696,400 m 0,656 100% 1,000 1,000 1,000
B.II. LANDSCAPE DI LOKASI INTAKE
1 Pagar pengaman (BRC tinggi 1,75 m @2,4 m) 60,000 m 0,167 100% 1,000 1,000 1,000 1,000
2 Pintu pagar BRC lebar 6,00 x 1,75 m berikut frame,grendel dan 1,000 1,000
1,000 ls 0,063 100%
kunci gembok
3 Pagar panel beton combinasi BRC tinggi 2,00 m1 batas area 1,000 1,000 1,000 1,000 1,000 1,000
52,000 m' 0,104 50%
dengan masjid
B.III. LANDSCAPE UMUM
1 Penanaman Pohon Palm tinggi 1.5 m 16,000 bh 0,031 100% 1,000 1,000 1,000
2 Gebalan rumput di area ex direksikeet dan gudang 1.000,000 m2 0,295 100% 1,000 1,000 1,000 1,000 1,000
- 16A, socket outlet 250 V, 2P + E, mounting height to suit with field 1,000
1,000 titik 0,006 100%
condition
3 Outdoor Lighting
- Pole outdoor lighting 4,000 unit 0,010 100% 1,000
4 Lightning Work & Grounding
- Lighting protection include air terminal, wiring and grounding 1,000 ls 0,280 100% 1,000 1,000 1,000
- Electrical grounding including grounding rod 2 Nos with BCC 1,000
1,000 ls 0,033 100%
16mm2 maximum
BOBOT PROGRESS SISA PEKERJAAN 7,262