Anda di halaman 1dari 1

SCHEDULE SISA PEKERJAAN

BANGUNAN SLUDGE POND


Bobot Progress M 47 M 48 M 49 M 50 M 51 M 52 M 53
No. Uraian Pekerjaan Volume Sat Sisa Sisa 18/07 20/07 22/07 25/07 27/07 29/07 01/08 03/08 05/08 08/08 10/08 12/08 15/08 17/08 19/08 22/08 24/08 26/08 29/08 31/08
Bobot Progres 19/07 21/07 24/07 26/07 28/07 31/07 02/08 04/08 07/08 09/08 11/08 14/08 16/08 18/08 21/08 23/08 25/08 28/08 30/08 Done
II. PEKERJAAN SIPIL - BANGUNAN KOLAM LUMPUR/SLUDGE POND
A PEKERJAAN PERSIAPAN
1 Dokumentasi dan pelaporan 1,000 ls 0,003 25% 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000 1,000
2 Pembuatan As Built Drawing 1,000 ls 0,009 45% 1,000 1,000 1,000

B PEKERJAAN LANDSCAPE
B.I. LANDSCAPE DI LOKASI BANGUNAN PENGOLAH LUMPUR ( PASANG BARU DAN PERBAIKAN KERUSAKAN )
1 Urugan kembali 91,200 m3 0,004 20% 1,000 1,000 1,000 1,000 1,000 1,000
2 Urugan pasir dibawah paving tebal 4 cm 60,800 m3 0,176 100% 1,000 1,000 1,000
3 Urugan sirtu tebal 20 cm padat 304,000 m3 0,642 100% 1,000 1,000 1,000 1,000
4 Pemadatan 304,000 m3 0,095 100% 1,000 1,000 1,000
5 Pasangan paving blok mutu K300 tebal 8 cm ( Volume baru 50%) 760,000 m2 0,941 100% 1,000 1,000 1,000 1,000
6 Pasangan batu kali 1 : 3 20,000 m3 0,173 100% 1,000 1,000 1,000 1,000
7 Saluran buis beton 30 cm 80,000 m 0,220 100% 1,000 1,000 1,000
8 Kansteen ukuran 20 x 30 x 50 696,400 m 0,656 100% 1,000 1,000 1,000
B.II. LANDSCAPE DI LOKASI INTAKE
1 Pagar pengaman (BRC tinggi 1,75 m @2,4 m) 60,000 m 0,167 100% 1,000 1,000 1,000 1,000
2 Pintu pagar BRC lebar 6,00 x 1,75 m berikut frame,grendel dan 1,000 1,000
1,000 ls 0,063 100%
kunci gembok
3 Pagar panel beton combinasi BRC tinggi 2,00 m1 batas area 1,000 1,000 1,000 1,000 1,000 1,000
52,000 m' 0,104 50%
dengan masjid
B.III. LANDSCAPE UMUM
1 Penanaman Pohon Palm tinggi 1.5 m 16,000 bh 0,031 100% 1,000 1,000 1,000
2 Gebalan rumput di area ex direksikeet dan gudang 1.000,000 m2 0,295 100% 1,000 1,000 1,000 1,000 1,000

C PEKERJAAN KONSTRUKSI KOLAM LUMPUR / SLUDGE POND


C.I. PEKERJAAN TANAH DAN PONDASI
1 Pembuatan saluran pengganti karena terkena bangunan kolam :
- Pekerjaan Manhole ukuran L 1,5 m , P 2,0 m dan T 1,75 m 2,000 unit 0,249 100% 1,000 1,000 1,000 1,000
C.II. PEKERJAAN BETON BERTULANG
( SUDAH TERPROGRESS 100% )
C.III. PEKERJAAN LAIN LAIN
1 Pekerjaan dinding dan pintu
- Pengecatan dinding 65,270 m2 0,019 100% 1,000 1,000 1,000
2 Pengadaan & Pemasangan Pintu Air CHS SS 316, lengkap dengan 1,000 1,000
4,000 unit 2,468 70%
spindle &
3 Tangga Vertikal (tangga monyet) 27,000 m' 0,089 100% 1,000 1,000 1,000
4 Beton K-225 kemiringan dasar pompa 5,000 m3 0,043 100% 1,000
5 Beton K-225 rabat t=10 cm 9,768 m3 0,085 100% 1,000
6 Paving block termasuk bedding 180,000 m2 0,176 100% 1,000 1,000 1,000 1,000
C.IV. PEKERJAAN ELECTRICAL
1 Lighting Fixtures
- Flood Light luminaire composed 50W LED 4,000 bh 0,053 100% 1,000
- Lighting Pole 9 M for flood light with mirroring industrial reflector
4,000 bh 0,169 100%
BVP150 (type G)
2 Small Power Accessories
1,000
- 16A, socket outlet 250 V, 2P + E, mounting above floor 0,3 meter 1,000 titik 0,004 100%

- 16A, socket outlet 250 V, 2P + E, mounting height to suit with field 1,000
1,000 titik 0,006 100%
condition
3 Outdoor Lighting
- Pole outdoor lighting 4,000 unit 0,010 100% 1,000
4 Lightning Work & Grounding
- Lighting protection include air terminal, wiring and grounding 1,000 ls 0,280 100% 1,000 1,000 1,000
- Electrical grounding including grounding rod 2 Nos with BCC 1,000
1,000 ls 0,033 100%
16mm2 maximum
BOBOT PROGRESS SISA PEKERJAAN 7,262