BIAYA KONSTRUKSI BANGUNAN RUMAH MAKAN MANJABAL

A/n. Gartiwa - Gunung Cupu Ciamis

No DESKRIPSI PEKERJAAN Jenis Vol SATUAN HARGA SATUAN JUMLAH (Rp)


A TANAH M2
B BANGUNAN
I Pekerjaan Awal
1 Pembersihan 659 M2 2,000 1,318,000
2 Pengukuran & Bouwplank 100 M2 75,000 7,500,000
3 Handling Material 3 Bln 800,000 2,400,000
4 Transport, Mobilisasi 3 Bln 550,000 1,650,000
Sub Total 12,868,000

II PEKERJAAN
PONDASI
1 Galian tanah, pondasi & Sloof 150 M3 40,000 6,000,000
2 Buang Tanah 1,500,000
3 Urugan tanah kembali 150 M3 30,000 4,500,000
4 Urugan tanah kembali (dari luar) 100 M3 50,000 5,000,000
5 Pondasi batu kali 50 M3 400,000 20,000,000
6 Pekejaan pondasi setempat 30 M3 1,800,000 54,000,000
7 Sloof beton 10 M3 3,000,000 30,000,000
8 Kolom beton struktur 10 M3 3,000,000 30,000,000
9 Tangga beton 1 M3 2,800,000 2,800,000
Sub Total 153,800,000

III PEKERJAAN
DINDING DAN LANTAI
1 Pasang batubata dan ring 200 M3 70,000 14,000,000
2 Plesteran dan aci 1:5 300 M3 50,000 15,000,000
3 Plesteran & acian (tekstur) 100 M3 75,000 7,500,000
4 Tali air kusen 200 M1 10,000 2,000,000
9 Pekerjaan waterproofing 0
- Toilet 20 M2 50,000 1,000,000
- Dak atap 55 M3 80,000 4,400,000
Sub Total 43,900,000

IV PEKERJAAN ATAP
1 Rangka Baja 70 M2 150,000 10,500,000
2 Atap Genteng keramik 60 M2 95,000 5,700,000
3 Nok Genteng Keramik 10 M2 80,000 800,000
4 Listplank ujung atap 10 M2 50,000 500,000
5 Atap carport&area service Solartuff 8 M2 180,000 1,440,000
Sub Total 18,940,000
No URAIAN PEKERJAAN SPESIFIKASI VOLUME SATUAN HARGA SATUAN JUMLAH (Rp)
V PEKERJAAN PLAFOND
1 Plafond Gypsum dan rangka Ex. Jayaboard 250 M2 75,000 18,750,000
2 List Plafond 280 M2 20,000 5,600,000
Sub Total 24,350,000

VI PEKERJAAN PINTU JENDELA


1 Kusen pintu dan jendela Alumunium 80 M1 95,000 7,600,000
2 Daun pintu kaca parameter Alumunium 50 M2 125,000 6,250,000
bangunan, incl. engsel,handel 0
3 Daun pintu kaca parameter Alumunium 50 M2 105,000 5,250,000
bangunan, incl. engsel,handel 0
4 Kusen pintu jendela Alumunium 100 M1 105,000 10,500,000
Sub Total 29,600,000

VII PEKERJAAN PENGECATAN


1 Cat dinding luar ICI Weathershie 250 M2 20,000 5,000,000
2 Cat dinding dalam Ex.ICI Catylac 300 M2 25,000 7,500,000
3 Cat plafond Ex.ICI Catylac 250 M2 15,000 3,750,000
Cat list plafond Ex.ICI Catylac 200 M1 15,000 3,000,000
4 Cat Plituran 0
- kusen pintu/jendela 100 M2 50,000 5,000,000
- daun pintu panel 25 M2 85,000 2,125,000
- daun jendela 15 M2 85,000 1,275,000
Sub Total 27,650,000

VIII PEKERJAAN ALAT SANITASI


Kran dobel 3 Unit 200,000 600,000
Kran tembok 2 Unit 150,000 300,000

Sub Total 900,000

IX PEKERJAAN SALURAN AIR


1 Instalasi air bersih
- Pipa PVC 1 ½" AW Ex. Wavin 85 10,000 850,000
- Pipa PVC 1 ¾" AW Ex. Wavin 70 10,000 700,000
- Pipa PVC 1/2" AW Ex. Wavin 50 10,000 500,000
- Fitting 1 175,000 175,000
2 Instalasi Air Kotor 0
-Pipa PVC 4" D Ex. Wavin 20 25,000 500,000
-Pipa PVC 2" D Ex. Wavin 8 25,000 200,000
- Fitting 1 180,000 180,000
3 Instalasi Air Bekas 0
- Pipa PVC 3" D Ex. Wavin 80 25,000 2,000,000
- Pipa PVC 2" D Ex. Wavin 8 25,000 200,000
- Pipa PVC 1¼" D Ex. Wavin 7 20,000 140,000
- Fitting 2 367,500 735,000
No DESKRIPSI PEKERJAAN JENIS VOLUME SATUAN HARGA SATUAN JUMLAH (Rp)
4 Instalasi Air Hujan
-Pipa PVC 4" D Ex. Wavin 60 55,000 3,300,000
-Pipa PVC 2" D Ex. Wavin 8 25,000 200,000
- Roof dram Ex. Antasan 8 135,000 1,080,000
- Fitting 2 300,000 600,000
5 Bak Kontrol 5 85,000 425,000
6 Septic Tank 1 1,500,000 1,500,000
7 Rembesan air 2 1,300,000 2,600,000
Sub Total 15,885,000

X PEKERJAAN INSTALASI LISTRIK


1 Instalasi titik lampu Plafond 15 Ttk. 150,000 2,250,000
3 Instalasi stop kontak standar 15 Ttk. 150,000 2,250,000
4 Instalasi stop kontak AC 4 Ttk. 150,000 600,000
5 Instalasi saklar Seri 8 Ttk. 85,000 680,000
6 Instalasi saklar tunggal 6 Ttk. 85,000 510,000
8 Instalasi TV 4 Ttk. 100,000 400,000
9 Stop kontak Ex. Broco 0
- Standar 8 Ttk. 35,000 280,000
10 Saklar seri Ex. Broco 6 Ttk. 50,000 300,000
11 Saklar tunggal 2 Ttk. 50,000 100,000
12 Downlight + PLE 8W 2 Ttk. 50,000 100,000
13 Lampu TL 2x 36W TKJL 028 8 Ttk. 80,000 640,000
14 Lampu TL 1 x 8W 4 Ttk. 120,000 480,000
16 Panel listrik & Box 2 Ttk. 450,000 900,000
17 Penangkal petir dan Grounding 1 Ttk. 950,000 950,000
Sub Total 10,440,000

No URAIAN PEKERJAAN Jumlah Harga Bobot Termin


% RP
A TANAH
B BANGUNAN
1 Pekerjaan awal 12,868,000
2 Pek. Pondasi 153,800,000
3 Pek Dinding lantai 43,900,000
4 Pekerjaan Atap 18,940,000
5 Pekerjaan Platfond 24,350,000
6 Pekerjaan Pintu Jendela 29,600,000 70 236,833,100
7 Pekerjaan Pengecatan 27,650,000
8 Pekerjaan Alat Sanitasi 900,000
9 Pekerjaan Saluran Air 15,885,000
10 Pekerjaan Instalasi Listrik 10,440,000 40 135,333,200
TOTAL 338,333,000