II PEKERJAAN
PONDASI
1 Galian tanah, pondasi & Sloof 150 M3 40,000 6,000,000
2 Buang Tanah 1,500,000
3 Urugan tanah kembali 150 M3 30,000 4,500,000
4 Urugan tanah kembali (dari luar) 100 M3 50,000 5,000,000
5 Pondasi batu kali 50 M3 400,000 20,000,000
6 Pekejaan pondasi setempat 30 M3 1,800,000 54,000,000
7 Sloof beton 10 M3 3,000,000 30,000,000
8 Kolom beton struktur 10 M3 3,000,000 30,000,000
9 Tangga beton 1 M3 2,800,000 2,800,000
Sub Total 153,800,000
III PEKERJAAN
DINDING DAN LANTAI
1 Pasang batubata dan ring 200 M3 70,000 14,000,000
2 Plesteran dan aci 1:5 300 M3 50,000 15,000,000
3 Plesteran & acian (tekstur) 100 M3 75,000 7,500,000
4 Tali air kusen 200 M1 10,000 2,000,000
9 Pekerjaan waterproofing 0
- Toilet 20 M2 50,000 1,000,000
- Dak atap 55 M3 80,000 4,400,000
Sub Total 43,900,000
IV PEKERJAAN ATAP
1 Rangka Baja 70 M2 150,000 10,500,000
2 Atap Genteng keramik 60 M2 95,000 5,700,000
3 Nok Genteng Keramik 10 M2 80,000 800,000
4 Listplank ujung atap 10 M2 50,000 500,000
5 Atap carport&area service Solartuff 8 M2 180,000 1,440,000
Sub Total 18,940,000
No URAIAN PEKERJAAN SPESIFIKASI VOLUME SATUAN HARGA SATUAN JUMLAH (Rp)
V PEKERJAAN PLAFOND
1 Plafond Gypsum dan rangka Ex. Jayaboard 250 M2 75,000 18,750,000
2 List Plafond 280 M2 20,000 5,600,000
Sub Total 24,350,000