Anda di halaman 1dari 8

HARGA PERHITUNGAN SENDIRI

PENGADAAN POMPA

HARGA SATUAN JUMLAH HARGA


NO URAIAN VOLUME
(Rp) (Rp)
1 PEKERJAAN PERSIAPAN
1 Administrasi dan Dokumentasi Proyek 1.00 Ls 1,000,000 1,000,000

2 PENGADAAN POMPA
1 Pengadaan Pompa Intake (Submersible) 2 bh 250,000,000 500,000,000
Kapasitas 100 l/detik, head 35 m, power 25,5 Kw
termasuk panel pompa
2 Pengadaan Pompa Dosing (Diaphragm) 2 bh 25,000,000 50,000,000
Kapasitas 115 l/detik, head 10 m, power 0,09 Kw
termasuk panel pompa
3 Pengadaan Pompa Distribusi (Sentrifugal) 2 bh 200,000,000 400,000,000
Kapasitas 10 l/detik, head min 19 m termasuk panel
pompa

Jumlah 951,000,000
HARGA PERHITUNGAN SENDIRI

PEKERJAAN PEMBANGUNAN INTAKE TOWER

HARGA SATUAN JUMLAH HARGA


NO URAIAN VOLUME
(Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran dan Bouwplank. 1.00 Ls 1,000,000 1,000,000

II PEKERJAAN TANAH
1 Galian tanah 13.50 M3 39,555 533,993
2 Urugan tanah kembali 10.80 M3 13,170 142,236

III PEKERJAAN BETON


1 Lantai kerja 1 : 3 : 5 3.50 M3 651,986 2,281,951
2 Beton K.225 67.00 M3 850,602 56,990,353

IV PENGADAAN DAN PEMASANGAN AKSESORIES


INLET
1 AF. Wall Pipe CI DN. 500 mm - 60 cm 3.00 Bh 3,293,500 9,880,500
2 AF. Bend CI DN. 500 mm - 900 3.00 Bh 5,117,800 15,353,400
3 AF Pipe GI DN. 500 mm - 3 m 3.00 Bh 14,000,000 42,000,000
4 F. Spigot CI DN. 500 mm - 70 cm 3.00 Bh 2,000,000 6,000,000
5 Giboult Joint CI DN. 500 mm 1.00 Bh 2,173,900 2,173,900

OUTLET
1 AF. Wall Pipe CI DN. 500 mm - 60 cm 2.00 Bh 3,293,500 6,587,000
2 A.F Gate Valve DN. 500 mm 1.00 Bh 25,000,000 25,000,000
3 Strainer CI DN. 500 1.00 Bh 5,434,800 5,434,800
4 Giboult Joint CI DN. 500 mm 1.00 Bh 2,173,900 2,173,900
5 street box DN. 500 mm termasuk selubung 1.00 Unit 300,000 300,000

PEKERJAAN PENUNJANG
1 Jembatan Pipa 1.00 Unit 20,000,000 20,000,000
2 Manhole 1 x 1 m 4.00 Unit 1,500,000 6,000,000

V PEKERJAAN LAIN-LAIN
1 Pembersihan dan perapihan lapangan 1.00 Ls 1,500,000 1,500,000

JUMLAH 203,352,032
HARGA PERHITUNGAN SENDIRI

PEKERJAAN PEMBANGUNAN KANTOR

HARGA SATUAN JUMLAH HARGA


NO URAIAN VOLUME
(Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran dan Bouwplank. 1.00 Ls 1,000,000 1,000,000

II PEKERJAAN TANAH
1 Galian tanah Sedalam 1m 280.00 M3 Rp 38,637.00 10,818,360
3 Urugan Pasir 56.00 M3 134,255 7,518,280

III PEKERJAAN PASANGAN DAN BETON


1 Lantai kerja 1 : 3 : 5 1,000.00 M3 651,986 651,986,000
2 Pemasangan Pondasi Batu Belah 1 : 3 280.00 M3 681,395 190,790,600
3 Pemasangan dinding bata 280.00 M2 226,820 63,509,600
4 Plesteran termasuk acian 1 : 4 280.00 M2 50,369 14,103,320
5 Pekerjaan Pemasangan Atap 1,200.00 M2 63,723 76,467,600
6 Pengecatan tembok Baru 3,840.00 M2 15,034 57,730,560
7 Lantai Keramik 30 x 30 cm 3,000.00 M 103,822 311,466,000

VI PEKERJAAN LAIN-LAIN
1 Kusen Pintu Kayu lengkap 10.00 Bh 5,000,000 50,000,000
2 Sky Light kaca 10 mm ( 60 x 120 cm ) 20.00 Unit 850,000 17,000,000
3 Roster 20 x 20 10.00 M2 35,000 350,000
4 Titik lampu 30.00 titik 85,000 2,550,000

JUMLAH 1,455,290,320
HARGA PERHITUNGAN SENDIRI

PEKERJAAN PEMBANGUNAN RUMAH POMPA

HARGA SATUAN JUMLAH HARGA


NO URAIAN VOLUME
(Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran dan Bouwplank. 1.00 Ls 1,000,000 1,000,000

II PEKERJAAN TANAH
1 Galian tanah 33.64 M3 39,555 1,330,630
2 Urugan tanah kembali 16.82 M3 13,170 221,519
3 Urugan Pasir 2.93 M3 124,890 365,928

III PEKERJAAN PASANGAN DAN BETON


1 Lantai kerja 1 : 3 : 5 2.40 M3 651,986 1,564,766
2 Beton K.225 16.80 M3 850,602 14,290,118
3 Perancah 1.00 Unit 10,000,000 10,000,000
4 Plesteran termasuk acian 1 : 4 61.80 M2 30,090 1,859,562
5 Lantai Keramik 30 x 30 cm 24.00 M 100,349 2,408,375

VI PEKERJAAN LAIN-LAIN
1 Kusen Pintu alumunium (1.2 x 2.5 m) lengkap 1.00 Bh 5,000,000 5,000,000
2 Cat Dinding 2 x 61.80 M2 28,560 1,765,008
3 Sky Light kaca 10 mm ( 60 x 120 cm ) 1.00 Unit 850,000 850,000
4 Roster 20 x 20 3.00 M2 35,000 105,000
5 Titik lampu 2.00 titik 85,000 170,000

JUMLAH 40,930,907
HARGA PERHITUNGAN SENDIRI

PEKERJAAN PEMBANGUNAN IPA 200 L/DETIK

HARGA SATUAN JUMLAH HARGA


NO URAIAN VOLUME
(Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Sewa Direksikeet dan Gudang Proyek 1.00 Ls 6,000,000 6,000,000
2 Pematokan dan Pengukuran lahan 1.00 Ls 1,500,000 1,500,000
3 Administrasi dan dokumentasi 1.00 Ls 1,500,000 1,500,000
4 Papan Nama 1.00 Ls 500,000 500,000

II PEKERJAAN TANAH
1 Galian tanah 1,471.00 M3 39,555 58,185,405
2 Urugan tanah kembali 288.00 M3 13,170 3,792,960
3 Urugan Pasir 186.00 M3 124,890 23,229,540

III PEKERJAAN PASANGAN


1 Pasangan Batu belah 1 : 4 846.78 M3 542,913 459,727,447
2 Plesteran termasuk acian 1 : 4 444.00 M2 30,090 13,359,960
3 Siaran 1 : 2 850.00 M2 28,644 24,347,188

IV PEKERJAAN BETON
1 Lantai kerja 1 : 3 : 5 48.00 M3 651,986 31,295,328
2 Beton K.225 748.00 M3 850,602 636,250,505
3 Besi beton (150 / m3) 59,367.00 kg 15,000 890,505,000
4 Perancah 1.00 Unit 10,000,000 10,000,000
5 Water stop 81.00 M' 50,000 4,050,000

V PEKERJAAN UNIT SEDIMENTASI


1 Tube Setler Dn.2" termasuk penyangga 288.00 M2 1,300,000 374,400,000

2 Lateral pipa PVC Dn.200 mm - 3 m' dengan lobang 6.00 800,000 4,800,000
orifice unit

3 Guter Stainlees steel 6 mm ( t = 20; lbr = 30 cm ) L = 2.00 10,000,000 20,000,000


8,5 m' Unit

4 Guter Stainlees steel 6 mm ( t = 40; lbr = 50 cm ) L = 7 2.00 15,000,000 30,000,000


m' Unit

VI PENGADAAN DAN PEMASANGAN AKSESORIES


UNIT FLOKULASI
1 AF. Wall Pipe CI DN. 500 mm - 60 cm 1.00 Bh 2,500,000 2,500,000
2 AF. Wall Pipe CI DN. 500 mm - 60 cm 5.00 Bh 1,858,700 9,293,500
3 AF Pipe GI DN. 500 mm - 3 m 1.00 Bh 8,000,000 8,000,000
4 AF Pipe GI DN. 500 mm - 17 m 1.00 Bh 40,000,000 40,000,000
5 AF Pipe GI DN. 500 mm - 6 m 1.00 Bh 15,000,000 15,000,000
6 AF Pipe GI DN. 500 mm - 1 m 1.00 Bh 3,000,000 3,000,000
7 A.F Gate Valve DN. 500 mm 1.00 Bh 18,650,000 18,650,000
8 AF. Bend CI DN. 500 mm - 900 4.00 Bh 2,038,000 8,152,000
9 AF. Bend CI DN. 500 mm - 900 1.00 Bh 1,087,000 1,087,000
10 Belmount DN. 350 mm 1.00 Bh 1,260,900 1,260,900
11 Besi beton penutup DN. 12 cm lebar DN. 160 cm 6.00 Bh 1,500,000 9,000,000

UNIT SEDIMENTASI

1 Pipa manifold PVC DN. 500 mm - 6 m termasuk 1.00 Bh 4,500,000 4,500,000


lubang orifice DN. 2.54 cm

2 Pipa lateral PVC DN. 200 mm - 3 m termasuk lubang 6.00 Bh 900,000 5,400,000
orifice DN. 25 mm
3 AF. Wall Pipe CI DN. 500 mm - 60 cm 1.00 Bh 2,500,000 2,500,000
4 AF. Wall Pipe CI DN. 250 mm - 60 cm 4.00 Bh 1,440,200 5,760,800
5 Dop PVC DN. 500 1.00 Bh 400,000 400,000
6 Dop PVC DN. 500 6.00 Bh 250,000 1,500,000
7 Supot penguat pipa manifol dan lateral 1.00 Bh 7,500,000 7,500,000
8 AF Pipe PVC DN. 200 mm - 4 m 1.00 Bh 1,200,000 1,200,000
9 A.F Gate Valve DN. 200 mm 1.00 Bh 4,150,000 4,150,000
10 Giboult Joint DN. 200 mm 1.00 Bh 610,500 610,500
11 Flange soket PVC DN. 200 mm 1.00 Bh 691,950 691,950
12 street box DN. 150 mm termasuk selubung 1.00 Bh 300,000 300,000

UNIT FILTRASI
1 AF. Wall Pipe CI DN. 250 mm - 60 cm 4.00 Bh 1,858,700 7,434,800
2 A.F Gate Valve DN. 250 mm 16.00 Bh 6,250,000 100,000,000
3 AF Pipe GI DN. 250 mm - 3 m 4.00 Bh 8,000,000 32,000,000
4 AF Pipe GI DN. 250 mm - 1 m 4.00 Bh 3,000,000 12,000,000
5 AF. Bend CI DN. 250 mm - 900 16.00 Bh 1,087,000 17,392,000
6 F. Spigot DN. 250 mm - 60 cm 4.00 Bh 760,900 3,043,600
7 Clamp penguat pipa 4.00 Bh 250,000 1,000,000
8 Pipa header GI DN. 450 mm - 21 m 1.00 Bh 84,000,000 84,000,000
9 Dop Steel DN. 450 mm 1.00 Bh 1,500,000 1,500,000

10 Guter Stainlees steel 6 mm ( t = 30; lbr = 35 cm ) L = 3 4.00 unit 6,000,000 24,000,000


m'

VII PEKERJAAN MEDIA FILTRASI


1 Nozzel 392.00 Bh 40,000 15,680,000
2 Plat dudukan pasir PVC tebal 2 cm 18.00 M2 4,000,000 72,000,000
3 Kerikil 13,500.00 kg 2,500 33,750,000
4 Pasir 2,700.00 kg 2,500 6,750,000

VIII PEKERJAAN LAIN-LAIN


1 Saluran drainase MD 30 77.66 M' 750,000 58,245,000
2 Rangka atap IWF 200 x 100 x 0,5 1,919.70 kg 22,000 42,233,400
3 Gording besi C 125 x 20 x 2 mm 832.50 kg 22,000 18,315,000
4 Genteng galvalum tebal 1 mm termasuk krepusan 203.50 m2 250,000 50,875,000
5 Bak kontrol pasangan batu belah 2.00 unit 2,500,000 5,000,000
6 Uji Coba dan Comissioning 24.00 jam 10,000,000 240,000,000

7 Hand riil stainless steel (4 x 4 cm) t=2 mm,tinggi 100 53.71 M' 800,000 42,968,000
cm

JUMLAH 3,612,086,783
HARGA PERHITUNGAN SENDIRI

PEKERJAAN PEMBANGUNAN RESERVOIR 4800 M

HARGA SATUAN JUMLAH HARGA


NO URAIAN VOLUME
(Rp) (Rp)

I PEKERJAAN PERSIAPAN
1 Pengukuran dan Bouwplank. 1.00 Ls 1,000,000 1,000,000

II PEKERJAAN TANAH
1 Galian tanah 9,430.00 M3 39,555 373,003,650
2 Urugan tanah kembali 590.00 M3 13,170 7,770,300
3 Urugan Pasir 460.00 M3 124,890 57,449,400

III PEKERJAAN BETON


1 Lantai kerja 1 : 3 : 5 115.00 M3 651,986 74,978,390
2 Beton K.225 1,416.00 M3 850,602 1,204,452,828

IV PENGADAAN DAN PEMASANGAN AKSESORIES


INLET
1 AF. Wall Pipe CI DN. 500 mm - 60 cm 1.00 Bh 3,293,500 3,293,500
2 AF. Bend CI DN. 500 mm - 900 1.00 Bh 5,117,800 5,117,800
3 AF Pipe GI DN. 500 mm - 3 m 1.00 Bh 14,000,000 14,000,000
4 F. Spigot CI DN. 500 mm - 70 cm 1.00 Bh 2,000,000 2,000,000
5 Giboult Joint CI DN. 500 mm 1.00 Bh 2,173,900 2,173,900

OUTLET
1 AF. Wall Pipe CI DN. 500 mm - 60 cm 2.00 Bh 3,293,500 6,587,000
2 A.F Gate Valve DN. 500 mm 1.00 Bh 25,000,000 25,000,000
3 Strainer CI DN. 500 1.00 Bh 5,434,800 5,434,800
4 Giboult Joint CI DN. 500 mm 1.00 Bh 2,173,900 2,173,900
5 street box DN. 500 mm termasuk selubung 1.00 Unit 300,000 300,000

WASH OUT DAN OVER FLOW


1 AF. Wall Pipe CI DN. 450 mm - 60 cm 1.00 Bh 3,293,500 3,293,500
2 AF. Bend CI DN. 450 mm - 900 1.00 Bh 5,117,800 5,117,800
3 A.F Gate Valve DN. 450 mm 1.00 Bh 25,000,000 25,000,000
4 AF Tee CI DN. 450-450 mm 1.00 Bh 8,416,700 8,416,700
5 AF Pipe GI DN. 450 mm - 3 m 1.00 Bh 14,000,000 14,000,000
6 AF Pipe GI DN. 450 mm - 1 m 1.00 Bh 4,000,000 4,000,000
7 AF Pipe GI DN. 450 mm - 0.5 m 1.00 Bh 2,000,000 2,000,000
8 street box DN. 150 mm termasuk selubung 1.00 Unit 300,000 300,000

PEKERJAAN PENUNJANG
1 Tangga Besi 1.00 Unit 2,000,000 2,000,000
2 Manhole 1 x 1 m 4.00 Unit 1,500,000 6,000,000
3 Air Vent Dn. 40 mm 4.00 Unit 500,000 2,000,000

V PEKERJAAN LAIN-LAIN
1 Pembersihan dan perapihan lapangan 1.00 Ls 1,500,000 1,500,000

JUMLAH 1,858,363,468
REKAPITULASI HARGA PERHITUNGAN SENDIRI

JUMLAH HARGA
NO URAIAN
(Rp)

I PEKERJAAN PEMBANGUNAN IPA 200 L/DETIK 3,612,086,783


II PEKERJAAN PEMBANGUNAN RESERVOIR 4800 M 1,858,363,468
III PEKERJAAN PEMBANGUNAN RUMAH POMPA 40,930,907
IV KANTOR 1,455,290,320
V PEKERJAAN PEMBANGUNAN INTAKE DAN BAK PENGUMPUL 203,352,032
VI PENGADAAN POMPA 951,000,000
JALAN AKSES 865,350,000
LAMPU PENERANGAN 1,350,000,000
RUMAH JAGA 241,502,700
METER INDUK 51,286,832
JUMLAH 10,629,163,042
Dibulatkan 10,629,163,042