A. PEKERJAAN PENDAHULUAN
1 Penyedian / Sewa Gudang Kerja 1.00 ls 0.71% 0.00 0.00% 0.00% 1.00 0.71% 100.00% 1.00 0.71% 100.00%
2 Pembuatan Papan Nama Proyek 1.00 unit 0.25% 0.00 0.00% 0.00% 1.00 0.25% 100.00% 1.00 0.25% 100.00%
3 Penyedian Air Kerja 1.00 ls 0.25% 0.00 0.00% 0.00% 1.00 0.25% 100.00% 1.00 0.25% 100.00%
4 Pembongkaran Atap & Plafond Lama 1.00 ls 1.43% 0.00 0.00% 0.00% 1.00 1.43% 100.00% 1.00 1.43% 100.00%
2.64% 0.00% 0.00% 2.64% 100.00% 2.64% 100.00%
B. PEKERJAAN KONTRUKSI
1 Pek. Lantai Keramik uk. 40 x 40 cm 112.26 m2 14.27% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
2 Pas. Conblock 37.00 m2 3.94% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
3 Pas. Plafond Kalsiboard + Rangka Hollow 117.45 m2 14.50% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
4 Pas. Lisplank Kalsiboard 60.62 m1 2.61% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
5 Pas. Rangka Atap Baja Ringan 204.71 m2 29.83% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
6 Pas. Atap Genteng Metal 215.48 m2 17.93% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
7 Pas. Tutup Bubungan Genteng Metal 34.56 m1 2.81% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
8 Pas. Talang Patahan Atap 7.36 m1 0.69% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
9 Pek. Cat Kayu Lama 112.44 m2 2.27% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
10 Pek. Cat Tembok Dinding Lama 519.24 m2 4.54% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
11 Pek. Cat Tembok Baru untuk Plafond Lisplank 132.61 m2 3.11% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
96.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
C. PEKERJAAN LAIN-LAIN
1 Biaya Adminstrasi 1.00 ls 0.39% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
2 Biaya Dokumentasi 1.00 ls 0.29% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
3 Biaya P3K 1.00 ls 0.19% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
0.87% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2.
Nip. .......................... ......................... ......................
LAPORAN FISIK PEKERJAAN MINGGUAN
A. PEKERJAAN PENDAHULUAN
1 Penyedian / Sewa Gudang Kerja 1.00 ls 0.71% 1.00 0.71% 100.00% 0.00 0.00% 0.00% 1.00 0.71% 100.00%
2 Pembuatan Papan Nama Proyek 1.00 unit 0.25% 1.00 0.25% 100.00% 0.00 0.00% 0.00% 1.00 0.25% 100.00%
3 Penyedian Air Kerja 1.00 ls 0.25% 1.00 0.25% 100.00% 0.00 0.00% 0.00% 1.00 0.25% 100.00%
4 Pembongkaran Atap & Plafond Lama 1.00 ls 1.43% 1.00 1.43% 100.00% 0.00 0.00% 0.00% 1.00 1.43% 100.00%
2.64% 2.64% 100.00% 0.00% 0.00% 2.64% 100.00%
B. PEKERJAAN KONTRUKSI
1 Pek. Lantai Keramik uk. 40 x 40 cm 112.26 m2 14.27% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
2 Pas. Conblock 37.00 m2 3.94% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
3 Pas. Plafond Kalsiboard + Rangka Hollow 117.45 m2 14.50% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
4 Pas. Lisplank Kalsiboard 60.62 m1 2.61% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
5 Pas. Rangka Atap Baja Ringan 204.71 m2 29.83% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
6 Pas. Atap Genteng Metal 215.48 m2 17.93% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
7 Pas. Tutup Bubungan Genteng Metal 34.56 m1 2.81% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
8 Pas. Talang Patahan Atap 7.36 m1 0.69% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
9 Pek. Cat Kayu Lama 112.44 m2 2.27% 0.00 0.00% 0.00% 110.00 2.22% 97.83% 110.00 2.22% 97.83%
10 Pek. Cat Tembok Dinding Lama 519.24 m2 4.54% 0.00 0.00% 0.00% 500.00 4.37% 96.29% 500.00 4.37% 96.29%
11 Pek. Cat Tembok Baru untuk Plafond Lisplank 132.61 m2 3.11% 0.00 0.00% 0.00% 132.00 3.10% 99.54% 132.00 3.10% 99.54%
96.49% 0.00% 0.00% 9.69% 10.04% 9.69% 10.04%
C. PEKERJAAN LAIN-LAIN
1 Biaya Adminstrasi 1.00 ls 0.39% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
2 Biaya Dokumentasi 1.00 ls 0.29% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
3 Biaya P3K 1.00 ls 0.19% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
0.87% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2.
Nip. .......................... ......................... ......................
LAPORAN FISIK PEKERJAAN MINGGUAN
A. PEKERJAAN PENDAHULUAN
1 Penyedian / Sewa Gudang Kerja 1.00 ls 0.71% 1.00 0.71% 100.00% 0.00 0.00% 0.00% 1.00 0.71% 100.00%
2 Pembuatan Papan Nama Proyek 1.00 unit 0.25% 1.00 0.25% 100.00% 0.00 0.00% 0.00% 1.00 0.25% 100.00%
3 Penyedian Air Kerja 1.00 ls 0.25% 1.00 0.25% 100.00% 0.00 0.00% 0.00% 1.00 0.25% 100.00%
4 Pembongkaran Atap & Plafond Lama 1.00 ls 1.43% 1.00 1.43% 100.00% 0.00 0.00% 0.00% 1.00 1.43% 100.00%
2.64% 2.64% 100.00% 0.00% 0.00% 2.64% 100.00%
B. PEKERJAAN KONTRUKSI
1 Pek. Lantai Keramik uk. 40 x 40 cm 112.26 m2 14.27% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
2 Pas. Conblock 37.00 m2 3.94% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
3 Pas. Plafond Kalsiboard + Rangka Hollow 117.45 m2 14.50% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
4 Pas. Lisplank Kalsiboard 60.62 m1 2.61% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
5 Pas. Rangka Atap Baja Ringan 204.71 m2 29.83% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
6 Pas. Atap Genteng Metal 215.48 m2 17.93% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
7 Pas. Tutup Bubungan Genteng Metal 34.56 m1 2.81% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
8 Pas. Talang Patahan Atap 7.36 m1 0.69% 0.00 0.00% 0.00% 0.00 0.00% 0.00% 0.00 0.00% 0.00%
9 Pek. Cat Kayu Lama 112.44 m2 2.27% 110.00 2.22% 97.83% 0.00 0.00% 0.00% 110.00 2.22% 97.83%
10 Pek. Cat Tembok Dinding Lama 519.24 m2 4.54% 500.00 4.37% 96.29% 0.00 0.00% 0.00% 500.00 4.37% 96.29%
11 Pek. Cat Tembok Baru untuk Plafond Lisplank 132.61 m2 3.11% 132.00 3.10% 99.54% 0.00 0.00% 0.00% 132.00 3.10% 99.54%
96.49% 9.69% 10.04% 0.00% 0.00% 9.69% 10.04%
C. PEKERJAAN LAIN-LAIN
1 Biaya Adminstrasi 1.00 ls 0.39% 0.00 0.00% 0.00% 1.00 0.39% 100.00% 1.00 0.39% 100.00%
2 Biaya Dokumentasi 1.00 ls 0.29% 0.00 0.00% 0.00% 1.00 0.29% 100.00% 1.00 0.29% 100.00%
3 Biaya P3K 1.00 ls 0.19% 0.00 0.00% 0.00% 1.00 0.19% 100.00% 1.00 0.19% 100.00%
0.87% 0.00% 0.00% 0.87% 100.00% 0.87% 100.00%
2.
Nip. .......................... ......................... ......................
REKAP LAPORAN FISIK PEKERJAAN MINGGUAN
Disetujui, Dibuat,
Kontraktor Pelaksana Konsultan Pengawas
CV. FADHLAN SEJAHTERA CV. SELFIRA KONSULTAN
- -
Direktur Supervisi Engineer
Mengetahui, Menyetujui,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan
Dinas PU Cipta Karya Kab. Ogan Ilir Dinas PU Cipta Karya Kab. Ogan Ilir
Disetujui, Dibuat,
Kontraktor Pelaksana Konsultan Pengawas
CV. FADHLAN SEJAHTERA CV. SELFIRA KONSULTAN
- -
Direktur Supervisi Engineer
Mengetahui, Menyetujui,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan
Dinas PU Cipta Karya Kab. Ogan Ilir Dinas PU Cipta Karya Kab. Ogan Ilir
Disetujui, Dibuat,
Kontraktor Pelaksana Konsultan Pengawas
CV. FADHLAN SEJAHTERA CV. SELFIRA KONSULTAN
- -
Direktur Supervisi Engineer
Mengetahui, Menyetujui,
Pejabat Pembuat Komitmen Pejabat Pelaksana Teknis Kegiatan
Dinas PU Cipta Karya Kab. Ogan Ilir Dinas PU Cipta Karya Kab. Ogan Ilir