OPNAM PEKERJAAN WIDODO

FINAL COUNT
AREA : ENTERTAIN & CONECTION

NO JENIS PEKERJAAN Volume Sat Pencapaian Sat Persentase (%) Keterangan


1 ENTERTAIN Lt.01
PEKEJAAN DINDING
1 Plesteran Lt.01 122,84 m² 122,84 m² 100,00%
2 Acian Lt.01 94,94 m² 94,94 m² 100,00%
3 Benangan Lt.01 68,30 m' 68,30 m' 100,00%
4 Cat Interior 57,73 m² 57,73 m² 100,00%

PEKEJAAN LANTAI
1 Keramik Lt.01 162,49 m² 160,49 m² 88,62%
2 Keramik lantai Conection 84,25 m² 84,25 m² 100,00%
3 Keramik Lantai KM Lt.01 1,95 m² 1,95 m² 100,00%
4 Badukan 53,35 m' 53,35 m' 100,00%
5 Rabat beton Conection belakang 1,10 m³ 1,10 m³ 100,00%
6 Pekerjaan Lantai KalsiDeck 48,95 m² 48,95 m² 100,00%
7 Rabat Lantai Taman Entertain Lt.01 20,40 m² 20,40 m² 100,00%

PEKEJAAN ATAP DAK


1 EXPOSE DAK BETON Lt.01 114,62 m² 114,62 m² 100,00%
-Plester 12,00 m² 12,00 m² 100,00%
2 Janggutan 15,20 m' 15,20 m' 100,00%
3 Cat Natural (clear doff) 117,23 m² 117,23 m² 100,00%

2 ENTERTAIN Lt.02
PEKEJAAN DINDING
1 Plesteran Lt.02 462,68 m² 462,68 m² 100,00%
2 Acian Lt.02 386,08 m² 386,08 m² 100,00%
3 Benangan Lt.02 125,00 m' 125,00 m' 100,00%
4 Pekerjaan cat Interior 103,36 m² 103,36 m² 100,00%
5 Cat Natural Interior 98,56 m² 98,56 m² 100,00%
6 Pasangan Bata ringan 2,93 m² 2,93 m² 100,00%

PEKEJAAN LANTAI
1 -Keramik Ruangan Lt.02 120,58 m² 120,58 m² 100,00%
2 -Keramik Lantai kamar mandi Lt.02 13,48 m² 13,48 m² 100,00%
3 -Keramik Lantai Kamar mandi conection Lt.02 1,63 m² 1,63 m² 100,00%
4 FINISH LANTAI CONECTION Lt.02
-Waterproof Sika top 107 151,54 m² 151,54 m² 100,00%
-Sekrit plesteran Lantai 5,85 m³ 5,85 m³ 100,00%

PEKEJAAN ATAP DAK


1 EXPOSE DAK BETON Lt.02 13,40 m² 13,40 m² 100,00%
2 Waterproof SikaDeck seal 13,40 m² 13,40 m² 100,00%

3 PEKERJAAN TAMBAHAN ENTERTAIN


1 Bongkar dinding Jendela 1,95 m² 1,95 m² 100,00%
2 Plester,Aci 63,85 m² 63,85 m² 100,00%
3 Benangan 383,33 m' 383,33 m' 100,00%
5 Tali air 29,50 m' 29,50 m' 100,00%
6 Pasangan Dinding Bata 18,34 m² 18,34 m² 100,00%
7 Bongkar Kolom Praktis Opening jendela KM Entertain Lt.02 1,80 m' 1,80 m' 100,00%
8 Cor badukan 43,75 m' 43,75 m' 100,00%
6 Pembuatan Rem conection ke entertain Lt.02
-Urugan Puing-Puing 1,50 m³ 1,50 m³ 100,00%
-Rabatan 4,73 m³ 4,73 m³ 100,00%
13 Tambahan opening jendela lt.02 4,37 m² 4,37 m² 100,00%
16 Pemadatan Pasir Entertain (Sirtu) 264,21 m² 264,21 m² 100,00%
19 Trap anak tangga Conection Lantai 2
- Pasangan Bata merah 0,53 m³ 0,53 m³ 100,00%
- Plesteran 4,60 m² 4,60 m² 100,00%
21 Rabat Lantai Taman Entertain Lt.01 20,40 m² 20,40 m² 100,00%
22 Perubahan Elevasi Keramik Lt.02 2,55 m² 2,55 m² 100,00%