Anda di halaman 1dari 1

LAPORAN KEMAJUAN PEKERJAAN MINGGUAN

PT. PLN (PERSERO)


UNIT INDUK TRANSMISI JAWA BAGIAN BARAT
UNIT PELAKSANA TRANSMISI CILEGON PT. GEMPAR SILIWANGI BERKARYA

PEKERJAAN : PENGGANTIAN PAGAR PANEL PERIODE : THN 2022


PELAKSANA : PT. GEMPAR SILIWANGI BERKARYA MINGGU KE : 5 ( LIMA )
NOMOR KONTRAK : 0096.SPK/DAN.01.03/E34030000/2022 MULAI : 09 DES-2022

PROGRESS
NO NAMA BARANG / PEKERJAAN JASA VOL SAT BOBOT TOTAL S/D MINGGU LALU MINGGU INI
Vol % Bobot Vol % Bobot
A PEKERJAAN PERSIAPAN 6 7 8 9
1 Survey dan Dokumentasi 1.00 ls 0.726 1.00 100.00% 0.726% 1.00 100.00% 0.726%
2 Mobilisasi dan demobilisasi (alat, tenaga dan material) 1.00 ls 3.029 0.90 90.00% 2.726% 1.00 100.00% 3.029%
3 pagar temporary (rangka bambu + seng gelombang kecil tinggi 1.8 meter) 107.89 m' 15.936 107.89 100.00% 15.936% 107.89 100.00% 15.936%
B PEKERJAAN PELAKSANAAN
1 Pembersihan area pekerjaan 103.89 m2 1.293 83.11 80.00% 1.034% 103.89 100.00% 1.293%
2 Pengukuran ulang dan bowplank 51.95 m2 1.509 51.95 100.00% 1.509% 51.95 100.00% 1.509%
3 Pembongkaran pasangan pagar panel miring berikut tiang 192.78 m2 4.079 192.78 100.00% 4.079% 192.78 100.00% 4.079%
4 Galian tanah pondasi 47.48 m3 1.871 47.48 100.00% 1.871% 47.48 100.00% 1.871%
5 Urugan pasir tebal 5cm bawah pedestal 0.65 m3 0.123 0.65 100.00% 0.123% 0.65 100.00% 0.123%
6 Lantai kerja ad.1:3:5 tebal 3cm bawah pedestal 0.39 m3 0.146 0.39 100.00% 0.146% 0.39 100.00% 0.146%
7 Pondasi batu belah ad.1:3 25.08 m3 7.312 25.08 100.00% 7.312% 25.08 100.00% 7.312%
8 Cor beton bertulang pedestal uk.500x500 tebal 15cm + kolom pedestal 250x250, ad.1:2:3 + bekisting 3.61 m3 7.703 3.43 95.00% 7.318% 3.61 100.00% 7.703%
9 Cor beton bertulang pedestal uk.500x500 tebal 15cm + kolom pedestal 150x250, ad.1:2:3 + bekisting 1.31 m3 2.789 1.18 90.00% 2.510% 1.31 100.00% 2.789%
10 Urug kembali galian tanah pondasi 16.44 m3 2.183 16.44 100.00% 2.183% 16.44 100.00% 2.183%
11 Cor beton bertulang sloof uk.150x200 ad.1:2:3 + bekisting 3.12 m3 0.665 3.12 100.00% 0.665% 3.12 100.00% 0.665%
12 Cor beton bertulang kolom utama uk.250x250 ad.1:2:3 + bekisting 6.78 m3 12.627 6.78 100.00% 12.627% 6.78 100.00% 12.627%
13 Cor beton bertulang kolom diagonal uk.150x250 ad.1:2:3 + bekisting 1.94 m3 3.858 1.32 68.00% 2.623% 1.94 100.00% 3.858%
14 Pasang dinding 1/2 batako tebal 10cm ad.1:4 228.48 m2 11.154 228.48 100.00% 11.154% 228.48 100.00% 11.154%
15 Cor beton bertulang ring balk uk.150x250 ad.1:2:3 + bekisting (tengah dan atas) 6.24 m3 11.085 5.93 95.00% 10.531% 6.24 100.00% 11.085%
16 Plesteran dan acian (u/ kolom, diagonal, balk dan sloof) 267.51 m2 10.877 214.01 80.00% 8.701% 267.51 100.00% 10.877%
C PEKERJAAN LAIN-LAIN DAN FINISHING
1 Finishing dan perapihan eks. Pekerjaan berikut merapihkan panel block ekisting 1.00 ls 1.037 0.00 0.00% 0.000% 1.00 100.00% 1.037%
100.00 HASIL PROGRESS MINGGU INI : 100.00%

Disetujui Team Pengawas Labuan, 12 Desember 2022


PT. PLN (Persero) UPT. Cilegon PT. GEMPAR SILIWANGI BERKARYA
MULTG RANGKAS

Tedy Firmanudin
NOPI RIYANSYAH
(DIREKSI LAPANGAN)