SCHEDULE "S" CURVE

PEMBONGKARAN DAN RENOVASI BOTTOM AREA


Desember 2021 Januari 2022 Februari 2022 Maret 2022
No. Description Bobot Notes
1 2 3 4 5 6 7 8 9 10 11 12 13
I Persiapan, MOB & DEMOB Start Pekerjaan 15 Desember 2021 Finish Pekerjaan 15 Maret 2021 100%

100.000%
A Pekerjaan Pembongkaran Partisi Area Office Ex GM Chemical 15.3662% 0.561% 0.561% 2.561% 2.561% 2.561% 6.561%
B Pekerjaan Renovasi Layout Ruang Commers Stockfit 95.663%
1 Pekerjaan Partisi 3.3070% 1.102% 1.102% 1.102%
2 Pekerjaan Plafond 0.687% 0.687% 91.326%
1.3731%
3 Plint lantai GRC 10cm finishing cat hitam 0.6042% 0.302% 0.302%
4 Pekerjaan Kusen, pintu dan Jendela Aluminium 1.0906% 0.545% 0.545% 84.988%
5 Pekerjaan Cat 0.8448% 0.845%

78.651%
C Pekerjaan Renovasi Ruang Planning
1 Bongkar dan Pasang Pintu Existing 0.8389% 0.419% 0.419%
2 Pekerjaan Pasang Dinding bata 1.6483% 0.824% 0.824%
3 Pekerjaan Partisi 1.4564% 0.728% 0.728% 69.182%

4 Pekerjaan Plester & Aci 0.6040% 0.302% 0.302%


5 Pekerjaan Plafond 3.2885% 1.096% 1.096% 1.096%
6 Pekerjaan Cat 1.8266% 0.913% 0.913%
59.100%

D Pekerjaan Pembuatan Ruangan Regrind


1 Pekerjaan Pasang Dinding bata 10.2742% 2.569% 2.569% 2.569% 2.569%
2 Pekerjaan Plester & Aci 13.6810% 2.736% 2.736% 2.736% 2.736% 2.736%
3 Pindah Pintu 0.4195% 0.419%
47.037%
4 Pekerjaan Exhausfan 1.4362% 1.436%
5 Pekerjaan Cat 3.7002% 1.850% 1.850%

E Pekerjaan Pembuatan Cutting Dies


1 Pekerjaan Pasang Dinding bata 2.7228% 1.361% 1.361%
2 Pekerjaan Plester & Aci 1.5100% 31.551% 0.755% 0.755%
3 Pekerjaan Cat 0.3691% 0.369%
4 Pekerjaan Pintu swing besi 1.1186% 1.119%
5 Pekerjaan Pasang wiemesh galvanish + cat minyak 5.8304% 1.943% 1.943% 1.943%
6 Pekerjaan Exhausfan 0.3591% 0.359%
18.576%

F Pekerjaan Rangka besi & Atap Regrind dan Cutting Dies 21.6860% 0.337% 6.337% 6.337% 4.337% 4.337%

G Pekerjaan Pembongkaran Area Cutting Dies Existing


8.405%
1 Pekerjaan Pembongkaran Area Cutting Dies Existing 1.6107% 1.611%
2 Pengurugan dan Pemadatan lantai 6 x 4 x 0,3 m 1.6912% 1.691%
2.224%
3 Screed Lantai + cat lantai 1.3423% 1.342%
0.561%
0%
100.00%
Progress Rencana 0.561% 1.663% 6.180% 10.171% 12.976% 15.486% 12.063% 10.082% 9.469% 6.337% 6.337% 4.337% 4.337%
Progress Rencana Komulatif 0.561% 2.224% 8.405% 18.576% 31.551% 47.037% 59.100% 69.182% 78.651% 84.988% 91.326% 95.663% 100.000%