JADWAL PELAKSANAAN PENATAAN INTERIOR GEDUNG AMPHITEATER (BAMBU CREATIVE CENTER) KECAMATAN SELAAWI

Sep-21 Oktober - 2021


Minggu - 3 Minggu - 4 Minggu - 5 Minggu - 1 Minggu - 2 Minggu - 3 Minggu - 4
NO DESKRIPSI PEKERJAAN TOTAL BOBOT
S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

I Pelaksanaan Pekerjaan
A Pekerjaan Dinding
1 Kusen 2 Unit 750,000 1,500,000 1.23 % 1.235

2 Aksesoris 2 Unit 200,000 400,000 0.33 % 0.329

3 Semen 4 Sak 55,000 220,000 0.18 % 0.181

4 Pasir 1 Colt 300,000 300,000 0.25 % 0.247

5 Bahan Finishing 2 Set 100,000 200,000 0.16 % 0.165

2,620,000
Ongkos Kerja
2 Tukang 1 2 hari 120,000 240,000 0.20 % 0.198

3 Tukang 2 2 hari 120,000 240,000 0.20 % 0.198

480,000
Total Biaya Pekerjaan Dinding 3,100,000 2.55 %

B Pekerjaan Atap Plafond & Sekat GRC (Ruang Ganti)


1 GRC 4 mm 40 lbr 50,000 2,000,000 1.65 % 1.646

2 Rangka Baja Ringan 12 btg 80,000 960,000 0.79 % 0.79

3 Rangka Hollow Galvanis 20 btg 25,000 500,000 0.41 % 0.412

4 Rangka Hollow 3x6 5 btg 120,000 600,000 0.49 % 0.494

5 Sekrup Gypsum 10 dus 40,000 400,000 0.33 % 0.329

6 Baut dynabolt 10 dus 27,000 270,000 0.22 % 0.222

4,730,000
Ongkos Kerja
1 Paket 64.5 M³ 25,000 1,612,500 1.33 % 1.327

1,612,500
Total Biaya Pekerjaan Plafond 6,342,500 5.22 %

C Pekerjaan Installasi Listrik


- Installasi 10 titik 10 titik 200,000 2,000,000 1.65 % 1.646

2,000,000
Total Biaya Pekerjaan Installasi Listrik 2,000,000 1.65 %

D Pekerjaan Pengecatan Dinding & Atap Plafond


1 Cat Asian Paint @25 kg 4 pcs 400,000 1,600,000 1.32 % 1.317

2 Roll Cat + Baki 2 Set 150,000 300,000 0.25 % 0.247

1,900,000
Ongkos Kerja
1 Tukang 1 2 hari 120,000 240,000 0.20 % 0.198

2 Tukang 2 2 hari 120,000 240,000 0.20 % 0.198

480,000
Total Biaya Pekerjaan Pengecatan 2,380,000 1.96 %

E Pekerjaan Sub Kang Utang


1 Partisi Bambu Ruang Ganti 1 Paket 11,800,000 11,800,000 9.71 % 9.712

2 Partisi Bambu Ruang Tengah 1 Paket 2,600,000 2,600,000 2.14 % 2.14

3 Sekat Toren 2 Paket 400,000 800,000 0.66 % 0.658

4 Lampu Hias Besar Custom 1 Unit 1,000,000 1,000,000 0.82 % 0.823

6 Pemasangan Atap Amphiteater 1 Paket 5,500,000 5,500,000 4.53 % 4.527

7 Partisi Bambu Dinding Luar 6 M² 400,000 2,400,000 1.98 % 1.975

Total Biaya Pekerjaan Sub Kang Utang 24,100,000 19.83 %

F Pekerjaan Panggung
1 Bambu Utuh dia.7 cm 175 btg 12,000 2,100,000 1.73 % 1.728

2 Bahan Pengawet (borax) 10 kg 50,000 500,000 0.41 % 0.412

3 Multiplek 9mm 10 lmbr 150,000 1,500,000 1.23 % 1.235

4 Besi Hollow 20 btg 120,000 2,400,000 1.98 % 1.975

5 Baut+Mur M6 1 dus 150,000 150,000 0.12 % 0.123

6 Lem 1 Paket 500,000 500,000 0.41 % 0.412

7 Bahan Finishing 1 Paket 1,000,000 1,000,000 0.82 % 0.823

8 Letter Sign 1 Set 3,000,000 3,000,000 2.47 % 2.469

9 Lighting 1 Set 1,000,000 1,000,000 0.82 % 0.823

12,150,000
Ongkos Kerja
1 Paket 1 Paket 3,000,000 3,000,000 2.47 % 2.469

3,000,000
Total Biaya Pekerjaan Panggung 15,150,000 12.47 %

G Pekerjaan Furnitur
1 Bambu Laminasi (Tebal 20,25,30) 1 M³ 35,000,000 35,000,000 28.81 % 28.81

2 Bantal sofa 1 Set 5,000,000 5,000,000 4.12 % 4.12

3 Besi Hollow 10 btg 150,000 1,500,000 1.23 % 1.23

4 Rel Pintu 2 Set 250,000 500,000 0.41 % 0.41

5 Kunci Pintu 2 Set 150,000 300,000 0.25 % 0.25

6 Cermin Meja Rias 2 pcs 200,000 400,000 0.33 % 0.33

7 Cermin Vertikal 2 pcs 500,000 1,000,000 0.82 % 0.82

8 Gorden 2 lmbr 300,000 600,000 0.49 % 0.49

9 Bahan Baku Finishing 1 Paket 2,550,000 2,550,000 2.10 % 2.10

10 Paku 1 Paket 500,000 500,000 0.41 % 0.41

11 Sekrup 5 dus 50,000 250,000 0.21 % 0.21

12 Lem 1 Paket 1,000,000 1,000,000 0.82 % 0.82

13 Thinner 6 klng 30,000 180,000 0.15 % 0.15

14 Kain Ball 2 lmbr 100,000 200,000 0.16 % 0.16

15 Kuas 4 dus 50,000 200,000 0.16 % 0.16

16 Amplas (80, 100, 150, 240) 1 Paket 1,000,000 1,000,000 0.82 % 0.82

50,180,000
Ongkos Kerja
1 Furnitur 1 Paket 13,000,000 13,000,000 10.70 % 10.70

13,000,000
Pengeluaran Akomodasi&Transportasi Bambu Laminasi
1 Ongkir 1 Paket 3,000,000 3,000,000 2.47 % 2.47

2 Pengiriman Furnitur 1 Paket 750,000 750,000 0.62 % 0.62

3 Transport&Akomodasi Bondowoso 1 Paket 1,500,000 1,500,000 1.23 % 1.23

5,250,000
Total Biaya Pekerjaan Furnitur 68,430,000 56.32 %

Estimasi Total Keseluruhan Pengeluaran 121,502,500 100.00 %


0 0 1.23 39 12.2 0 0 0 0 1.56 0 24.5 0 0 0 0 0 0 0 0 0 0 0 0 0 21.4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
BOBOT PERMINGGU 52.5 26.1 0.0 21.4 0 0 0
AKUMULASI BOBOT PERMINGGU 52.5 78.6 78.6 100 0 0 0
JUMLAH PENGELUARAN PERMINGGU 63,730,000 31,722,500 - 26,050,000 - - -
AKUMULASI PENGELUARAN 63,730,000 95,452,500 95,452,500 121,502,500 26,050,000 26,050,000 -

III Finishing/Checking

IV Serah Terima Pekerjaan

ANGGARAN 179,776,000
PPN+PPH 11.5 20,674,240
ASURANSI+ASOSIASI 7,500,000
REAL ANGGARAN 151,601,760
MARGIN 30,099,260

: Jadwal Yang Harus Diselesaikan