JADWAL PELAKSANAAN PENATAAN INTERIOR GEDUNG AMPHITEATER (BAMBU CREATIVE CENTER) KECAMATAN SELAAWI

September - 2021 Oktober - 2021


Minggu - 1 Minggu - 2 Minggu - 3 Minggu - 4 Minggu - 5 Minggu - 1 Minggu - 2 Minggu - 3 Minggu - 4
No Deskripsi Kegiatan
S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M S S R K J S M
30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

I Pelaksanaan Pekerjaan
A Pekerjaan Dinding
- Pembongkaran Dinding
- Pembongkaran Pintu
- Pemasangan Dinding+Bambu Utuh
- Finishing Pintu
- Pemasangan Pintu
- Pembelanjaan Bahan &Alat
1 Kusen 2 Unit 500,000 1,000,000
2 Aksesoris 2 Unit 100,000 200,000
3 Bambu Utuh 6 M² 500,000 3,000,000
4 Semen 4 Sak 55,000 220,000
5 Pasir 1 Colt 300,000 300,000
6 Bahan Finishing 2 Set 100,000 200,000
4,920,000
Ongkos Kerja
1 Mandor 4 hari 150,000 600,000
2 Tukang 1 4 hari 120,000 480,000
3 Tukang 2 4 hari 120,000 480,000
1,560,000
Total Biaya Pekerjaan Dinding 6,480,000

B Pekerjaan Atap Plafond


- Pemasangan Rangka
- Pemasangan GRC
- Pembelanjaan Bahan &Alat
1 GRC 4 mm 40 lbr 50,000 2,000,000
2 Rangka Baja Ringan 12 btg 75,000 900,000
3 Rangka Hollow Galvanis 20 btg 25,000 500,000
4 Rangka Hollow 3x6 6 btg 120,000 720,000
5 Sekrup Gypsum 10 dus 40,000 400,000
6 Baut dynabolt 10 dus 27,000 270,000
4,790,000
Ongkos Kerja
1 Mandor 6 hari 150,000 900,000
2 Tukang 1 6 hari 120,000 720,000
3 Tukang 2 6 hari 120,000 720,000
2,340,000
Total Biaya Pekerjaan Atap Plafond 7,130,000

C Pekerjaan Installasi Listrik


- Installasi 25 titik 25 titik 200,000 5,000,000
5,000,000
Total Biaya Pekerjaan Installasi Listrik 5,000,000

D Pekerjaan Pengecatan Dinding & Atap Plafond


- Pengecatan Atap Plafond
- Pengecatan Dinding
Pembelanjaan Bahan &Alat
1 Cat Asian Paint @25 kg 6 pcs 400,000 2,400,000
2 Roll Cat + Baki 2 Set 150,000 300,000
2,700,000
Ongkos Kerja
1 Tukang 1 2 hari 120,000 240,000
2 Tukang 2 2 hari 120,000 240,000
480,000
Total Biaya Pekerjaan Pengecatan 3,180,000

E Pekerjaan Sub Kang Utang


1 Partisi Bambu Ruang Ganti 1 Paket 14,750,000 14,750,000
2 Partisi Bambu Ruang Tengah 1 Paket 3,250,000 3,250,000
3 Sekat Toren 2 Paket 500,000 1,000,000
4 Lampu Hias Besar Custom 1 Unit 3,000,000 3,000,000
5 Lampu Hias Kecil Custom 20 Unit 250,000 5,000,000
6 Pemasangan Atap Amphiteater 1 Paket 5,500,000 5,500,000
Total Biaya Pekerjaan Sub Kang Utang 32,500,000
- Pembelian Bahan
- Pemotongan Bambu
- Pengawetan Bambu
- Pemasangan Atap Amphiteater
- Pemasangan Dinding Bambu Pintu Luar
- Pemasangan Partisi Bambu, Sekat Toren, Lampu Hias

F Pekerjaan Panggung
- Pembelian Bahan Bambu
- Pemotongan Bilah Bambu
- Pengawetan Bilah Bambu
- Setting Dekorasi Bambu
- Pengeleman Dekorasi Bambu
- Setting Dekorasi Bambu
Pembelanjaan Bahan &Alat
1 Letter Sign 1 Set 3,000,000 3,000,000
2 Bambu Utuh dia.7 cm 200 btg 15,000 3,000,000
3 Multiplek 9mm 10 lmbr 150,000 1,500,000
4 Lighting 1 Set 1,000,000 1,000,000
5 Bahan Pengawet (borax) 10 kg 50,000 500,000
6 Besi Hollow 20 btg 120,000 2,400,000
7 Baut+Mur M6 1 dus 150,000 150,000
8 Lem 1 Paket 500,000 500,000
12,050,000
Ongkos Kerja
1 Paket 1 Paket 3,000,000 3,000,000
3,000,000
Total Biaya Pekerjaan Panggung 15,050,000

G Pekerjaan Furnitur
Pembelanjaan Bahan &Alat
1 Bambu Laminasi (Tebal 20,25,30) 1.3 M³ 35,000,000 45,500,000
2 Besi Hollow 10 btg 150,000 1,500,000
3 Rel Pintu 2 Set 250,000 500,000
4 Kunci Pintu 2 Set 150,000 300,000
5 Cermin Meja Rias 2 pcs 200,000 400,000
6 Cermin Vertikal 2 pcs 500,000 1,000,000
7 Gorden 2 lmbr 300,000 600,000
8 Bahan Baku Finishing 1 Paket 2,550,000 2,550,000
9 Paku 1 Paket 500,000 500,000
10 Sekrup 5 dus 50,000 250,000
11 Lem 1 Paket 1,000,000 1,000,000
12 Thinner 6 klng 30,000 180,000
13 Kain Ball 2 lmbr 100,000 200,000
14 Kuas 4 dus 50,000 200,000
15 Amplas (80, 100, 150, 240) 1 Paket 1,000,000 1,000,000
55,680,000
Ongkos Kerja
1 Furnitur 1 Paket 17,650,000 17,650,000
17,650,000
Total Biaya Pekerjaan Pengecatan 73,330,000

II Pengaturan LayOut Interior


1 Delivery Furnitur
a. Sewa Kendaraan 1 hari 500,000 500,000
b. Pengiriman Barang
2 Pengaturan Layout Furnitur
500,000
Total Biaya Pengiriman Barang 500,000

Total Keseluruhan Pengeluaran 143,170,000 #

III Finishing/Checking

IV Serah Terima Pekerjaan

: Jadwal Yang Harus Diselesaikan


: Hari Libur
# Setelah ada penyesuaian dengan kebutuhan tambahan Camat
Atap Amphiteater, Dinding Bambu Pintu Luar