Terbilang : Satu Milyar Tujuh Ratus Tujuh Puluh Tujuh Juta Rupiah
TP Ø 13 mm 54 M
BERAT / M' 1.04 KG
BERAT PER UNIT 56.16 KG
B BETON
DIAMETER 0.3 M
TINGGI 5 M
JUMLAH PONDASI 102 BH
VOLUME / UNIT 0.35325 M3
TOTAL 36.0315 M3
1 PILE CAP
A BESI
JUMLAH BATANG 18
TP Ø 16 mm 35.1 M
BERAT / M' 1.578 KG
BERAT PER UNIT 55.3878 KG
JUMLAH PONDASI 35 BH
TOTAL 1938.573 KG
3 TIE BEAM
A BESI
SK Ø 8 mm #REF! BH #REF! M'
BERAT / M' 0.395 KG
BERAT TOTAL SK #REF! KG
TP BESI D 16 TP BESI D 13
JUMLAH PANJANG #REF! JUMLAH PANJANG #REF!
TP Ø 16 mm #REF! M TP Ø 16 mm #REF! M
BERAT / M' 1.578 KG BERAT / M' 1.04 KG
TOTAL #REF! KG TOTAL #REF! KG
PEKERJAAN ARSITEKTUR
NO JENIS PEKERJAAN VOLUME
ANALISA HARGA SAT. JUMLAH HARGA
1 2 3 ### 4 5
PEKERJAAN ARSITEKTUR
I PEKERJAAN PERSIAPAN
1 Peralatan, Air, Listrik kerja 1.00 ls 5,000,000 5,000,000.00
2 Peralatan Keselamatan Kerja 1.00 ls 2,500,000 2,500,000.00
TOTAL PEKERJAAN PERSIAPAN 7,500,000.00
II PEKERJAAN TANAH
1 Galian Tanah pondasi 3.00 m3
### 55,000 165,000.00
2 Urugan tanah 22.80 m3
### 55,000 1,254,000.00
3 Urugan Sirtu 9.30 m3
### 150,000 1,395,000.00
TOTAL PEKERJAAN TANAH 2,814,000.00
III PEKERJAAN PASANGAN
1 Lantai 1 (satu)
- Pas. Bata Merah 1/2 bata 1pc:8ps 159.00 m2
6.10 107,591 17,107,008.75
- Pas. Pondasi Batu Belah 1pc:8ps 8.75 m3
### 712,335 6,232,931.25
- Plesteran 15 mm 1pc:6ps 318.00 m2
### 52,280 16,624,893.72
- Acian 318.00 m2 17,500 5,565,000.00
- Pasangan Sekoneng 500.00 m' 20,000 10,000,000.00
- kolom praktis 12x12 1pc : 3ps : 5kr 75.00 m' 62,258 4,669,372.50
- Balok Anak 20 x 30 (300kg Besi + bekisting) 4.80 m3
### 5,830,208 27,984,998.40
- Pas. Roster terawang 20x20 20.00 m2 220,017 4,400,348.00
- Kolom 15 x 25 (300kg Besi + bekisting) 2.89 m3
### 7,331,320 21,169,186.50
113,753,739.12
2 Lantai 2 (dua)
- Pas. Bata Merah 1/2 bata 1pc:8ps 162.00 m2
### 107,591 17,429,782.50
- Plesteran 15 mm 1pc:6ps 324.00 m2
### 52,280 16,938,570.96
- Acian 324.00 m2 17,500 5,670,000.00
- Pasangan Sekoneng 800.00 m' 20,000 16,000,000.00
- kolom praktis 12x12 1pc : 3ps : 5kr 75.00 m' 62,258 4,669,372.50
- Balok Anak 20 x 30 (300kg Besi + bekisting) 4.80 m3
### 5,830,208 27,984,998.40
- Pas. Roster terawang 20x20 104.00 m2 220,017 22,881,809.60
- Kolom 15 x 25 (300kg Besi + bekisting) 2.36 m3
### 7,331,320 17,320,243.50
- Pas. Lapisan Waterproof Atap sistem torching ex SIKA 270.00 m2 95,000 25,650,000.00
154,544,777.46
3 Lantai 2 (Dua)
- Pas. Lantai marmer 60x120-abu-abu muda 270.00 m2
### 584,392 157,785,860.25
- Pas. Plint marmer 15x60 130.00 m'### 120,000 15,600,000.00
- Pas. Dinding interior marmer 60x120-lime stone 94.00 m2
### 661,076 62,141,172.67
- Pas. Dinding Tiang interior marmer 50x120-lime stone 9.00 m2
### 661,076 5,949,686.75
- Pas. Granit dinding luar 60x60-cream 82.60 m2
### 309,206 25,540,399.08
267,017,118.75
VI PEKERJAAN FINISHING
1 Lantai 1 (Satu)
- Cat Dinding Interior 159.00 m2
### 25,767 4,096,953.00
- Cat Dinding exterior 278.25 m2
### 50,445 14,036,321.25
18,133,274.25
2 Lantai 2 (Dua)
- Cat Dinding Interior 243.00 m2
### 25,767 6,261,381.00
- Cat Dinding exterior 425.25 m2
### 50,445 21,451,736.25
27,713,117.25
2 Lantai 2 (Dua)
- Balkon Tangga stainless T=90cm 21.29 m'### 600,000 12,774,000.00
- Tangga Monyet besi lebar 50 cm 22.00 m'### 350,000 7,700,000.00
20,474,000.00
Terbilang : Satu Milyar Tujuh Ratus Tujuh Puluh Tujuh Juta Rupiah
PEKERJAAN SIPIL
NO JENIS PEKERJAAN BOBOT MINGGU KE KETERANGAN
JUNI JULI AGUSTUS SEPTEMBER OKTOBER
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
I PEKERJAAN PENDAHULUAN #REF! #REF! #REF! #REF! #REF! 100 Masa
Pelaksanaan
II PEK. GALIAN DAN URUGAN TANAH #REF! #REF! 140 Hari
Kalender
III PEKERJAAN PASANGAN BATU #REF! #REF! #REF! #REF!
F F #REF! #REF!
IX PEKERJAAN ATAP #REF!
I I
T T
X PEKERJAAN LANTAI #REF! R R #REF! #REF!
I I 25
XI PEKERJAAN SANITASI #REF! #REF!
XIII PEKERJAAN LAIN-LAIN #REF! #REF! #REF! #REF! #REF! #REF! #REF! 0
RENCANA #REF! #REF! #REF! 0.000 0.000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
HARGA
NO. JENIS BAHAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
HARGA
NO. J E N I S B A H A N SATUAN MINIMUM MAKSIMUM KETERANGAN
(Rp) (Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 126,500 165,000
Bulat Belah m3 154,000 192,500
Pecah 10/15 m3 220,000 220,000
Pecah 5/7 m3 220,000 220,000
Pecah 3/5 m3 187,000 220,000
2 KERIKIL Timbun m3 140,800 170,400
Sawur / Koral m3 66,000 231,000
Beton 0,5/1 m3 198,000 220,000
Beton ,1/2 m3 187,000 220,000
Beton ,2/3 m3 176,000 220,000
Biasa m3 140,800 170,400
Tras Giling m3 157,300 190,300
3 BATU BATA ex lokal bh 650 750
(Rp) (Rp)
(Rp) (Rp)
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 14,300 25,300
BJLS 0,20 lebar 55 cm m' 15,400 24,200
BJLS 0,28 lebar 55 cm m' 18,700 18,700
BJLS 0,30 lebar 55 cm m' 16,500 26,400
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 39,600 46,200
BJLS 0,20 panjang 180 cm lbr 39,600 51,700
BJLS 0,30 panjang 180 cm lbr 40,700 64,350
BJLS 0,40 panjang 180 cm lbr 66,000 96,250
III . B A H A N K A Y U
1 JATI Papan m3 19,500,000 21,450,000
Balok/pesagen m3 19,500,000 21,450,000
(Rp) (Rp)
4 UBIN PORSELIN
Lokal 11 X 11 putih dos - -
11 X 11 warna dos - -
Lokal 15 X 15 putih dos - -
15 X 15 warna dos - -
5 MOZAIK PORSELIN
10 X 20 cm m2 - -
15 X 15 cm m2 - -
20 X 20 cm m2 44,000 44,000
20 X 25 cm m2 41,800 44,000
8 Batu Paros m2 - -
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 9,900 9,900
besi beton prestress kg 12,100 12,100
besi beton ulir kg 9,900 9,900
(Rp) (Rp)
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 15,400 23,100 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 17,600 28,400 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 22,000 35,750 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 176,200 176,200 panjang 6 m
Pipa PVC DN 63 ( 2" ) btg 33,000 99,000 panjang 6 m
Pipa PVC DN 90 ( 3" ) btg 46,200 181,200 panjang 6 m
Pipa PVC DN 110 ( 4" ) btg 62,700 264,600 panjang 6 m
Pipa PVC DN 160 ( 6" ) btg 552,700 552,700 panjang 6 m
Pipa PVC DN 200 ( 8" ) btg 857,600 857,600 panjang 6 m
Pipa PVC DN 250 ( 10" ) btg 1,223,400 1,223,400 panjang 6 m
Pipa PVC DN 315 ( 12" ) btg 1,745,200 1,745,200 panjang 6 m
(Rp) (Rp)
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 9,000 10,900
30 X 60 lbr 11,550 14,000
60 X 120 lbr - -
List Kayu Profil m' 3,850 11,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,500 60,500
3 HARD BOARD-uk: 4'X 8' lbr - -
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 55,000 60,500
. 120 X 240 X 3 mm lbr 56,100 56,100
. 90 X 210 X 4 mm lbr 80,300 97,200
. 90 X 210 X 9 mm lbr 95,700 115,800
. 90 X 210 X 12 mm lbr - -
. 90 X 210 X 15 mm lbr - -
. 90 X 210 X 18 mm lbr - -
Tripleks
. 120 X 240 X 3 mm lbr 44,000 49,500
. 120 X 240 X 4 mm lbr 55,000 64,900
. 120 X 240 X 6 mm lbr 64,900 74,800
Multipleks
. 120 X 240 X 9 mm lbr 99,000 148,500
. 120 X 240 X 12 mm lbr 154,000 176,000
. 120 X 240 X 15 mm lbr 184,250 220,000
. 120 X 240 X 18 mm lbr 200,200 242,000
Formika ukuran pintu lbr 55,000 55,000
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 13,200 22,000
Dempul plamur kg 16,500 49,500
Ambril/amplas lbr 1,650 8,800
Batu Apung kg 11,200 12,300
Cat dasar kg 14,300 95,700
. Emco kg 49,500 77,000
. Yunior 66 (nippon paint) kg - -
. Deculux kg 16,500 16,500
. Siralax ons 16,500 38,500
. Spiritus ltr 7,700 16,500
. Plitur jadi ltr 33,000 55,000
2 TEMBOK
Kalkarium kg 3,300 4,950
Kapur sirih kg 3,300 3,300
Plamur kg 7,700 49,500
Cat Tembok kg 16,500 79,200
Sintex 5 kg - -
Danabride 5 kg - -
(Rp) (Rp)
3 BESI
Menie kg 14,300 22,000
Cat mengkilat kg 38,500 47,300
Cat kg 11,000 47,300
Thinner A ltr 7,150 15,400
Minyak cat ltr 6,600 11,000
Thinner Super ltr 9,900 22,000
Residu (teer/aspal) drum 14,500 16,500
Fibre glass (tanki air)
X.BAHAN KACA
1 KABEL LISTRIK
N YA : . 1 X 1 1/2 mm2 m' 55,000 137,500
SPLN LMK 1 X 2 1/2 mm2 m' 82,500 165,000
. 1X4 mm2 m' -
1X6 mm2 m' -
NYY :. 2 X 1 1/2 mm2 m' -
PRIMA 2 X 2 1/2 mm2 m' 3,300 88,000
. 2X4 mm2 m'
2X6 mm2 m'
3 X 1 1/2 mm2 m'
3 X 2 1/2 mm2 m'
3X4 mm2 m'
3X6 mm2 m'
NYM :. 2 X 1 1/2 mm2 m' 2,750 6,600
PRIMA 2 X 2 1/2 mm2 m' 3,850 8,800
. 2X4 mm2 m'
3 X 1 1/2 mm2 m' 8,800 8,800
3 X 2 1/2 mm2 m' 9,900 9,900
3X4 mm2 m'
3X6 mm2 m'
(Rp) (Rp)
2 SKAKELAR
Out bauw . Seri bh 1,650 19,250
. Engkel bh 8,250 16,500
In bauw . Seri bh 1,650 19,250
. Engkel bh 12,100 19,800
(Rp) (Rp)
2 KLOSET JONGKOK
bh 104,500 137,500
3 WASTAFEL PEDESTAL
bh 80,300 330,000
12 LAIN - LAIN
Kran Air bh 5,500 38,500
Seal tape bh 1,100 9,700
Floor drain bh 4,400 19,250
Lem Pralon bh 8,250 9,350
Urinoir bh 615300 676800
XV . POMPA AIR.
(Rp) (Rp)
X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 38,500 38,500
Merah/hitam m2
2 HOLLAND Abu-abu m2 44,000 45,100
Merah/hitam m2 53,900 53,900
3 UNIDECOR Abu-abu m2 53,900 80,850
Merah/hitam m2
XVII. L A I N - L A I N
1 KREI 25 MM m2
2 Sliding Pintu J4 bh 165,000 165,000
3 Naco per Daun bh 11,000 27,500
4 Rolling door Besi m2 660,000 660,000
Rolling door Almunium m2
5 Awning Almunium m2
6 Kusen Almunium 4" Putih m' 90,000 110,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg
8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum
Hotmix Tebal = 4 Cm m2
Hotmix Tebal = 5 Cm m2
Hotmix Tebal = 6 Cm m2
Hotmix Tebal = 7 Cm m2
(Rp) (Rp)
13 LAIN-LAIN
Minyak Beton & bekisting ltr 24,200 24,200
Pintu Lipat Besi m2
Sunscreen Allumunim m2
Allumunium Foil m2 6,600 17,600
Soda api kg 2,750 27,500
Sabun kg
Air m3
Koas bh 16,500 16,500
Koas Alang-alang ikat
Solar (Industri) ltr 4,950 4,950
Premium (Industri) ltr 4,950 4,950
Pelumas ltr
Kawat Bu 16 ( Gantungan ) kg 19,800 19,800
Paku Biasa kg 15,400 15,400
Paku Bangkirai kg 17,600 17,600
Paku Beton Reng bh 330 330
Paku Beton Usuk bh 550 550
Plastik 90 x 20 m Tebal rol 8,800 126,500
14 AGREGAT
Sirtu m³ 170,500 206,300
(Rp) (Rp)
(Rp) (Rp)
Gerobak sampah -
1 Gerobak sampah Set 1,760,000 1,760,000
2 Ban luar gerobak sampah bh 206,300 206,300
3 Ban dalam gerobak sampah bh 41,300 41,300
4 Palek gerobak sampah bh 123,800 123,800
5 As gerobak sampah bh 99,000 99,000
6 Laker bh 123,800 123,800
Mesin Buldozer
1 Hydraulic Pump bh 17,980,700 17,980,700
2 Pump bh 23,243,400 23,243,400
3 Bearing ( AT 21140) bh 326,300 326,300
4 Bearing ( AT 21139) bh 932,800 932,800
5 Kit bh 4,197,600 4,197,600
6 Bearing ( AR 97517) bh 330,600 330,600
7 Intake Valve bh 376,600 376,600
8 Exhaust Valve bh 386,200 386,200
9 Kit bh 2,487,500 2,487,500
(Rp) (Rp)
Kompos
1 Bioactivator kompos botol 27,500 27,500
2 Karung goni lbr 22,000 22,000
3 Plastik pupuk ukuran 40 x 60 x 0.3 pak 55,000 55,000
4 Karung plastik lembar 5,500 5,500
-
Tempat Sampah / Tong sampah -
1 Tong sampah besi besar bh 71,500 71,500
2 Tiang penyangga tong sampah besi besar bh 38,500 38,500
3 Tong sampah besi kecil bh 44,000 44,000
4 Tiang penyangga tong sampah besi kecil bh 27,500 27,500
5 Tong sampah plastik besar bh 110,000 110,000
6 Tiang penyangga tong sampah plastik besar bh 38,500 38,500
7 Tong sampah plastik kecil bh 93,500 93,500
8 Tiang penyangga tong sampah plastik kecil bh 27,500 27,500
Tossa -
1 Ban luar depan tossa roda tiga bh 209,700 209,700
2 Ban dalam depan tossa roda tiga bh 37,900 37,900
3 Ban luar belakang tossa roda tiga bh 473,600 473,600
4 Ban dalam belakang tossa roda tiga bh 67,700 67,700
5 Rantai depan bh 77,800 77,800
6 Rantai belakang bh 128,500 128,500
7 Gear depan bh 20,300 20,300
8 Gear tengah bh 68,800 68,800
9 Gear belakang bh 108,200 108,200
10 Kampas rem depan bh 37,200 37,200
11 Kampas rem belakang bh 74,400 74,400
12 Accu bh 318,000 318,000
13 Kampas kopling bh 77,100 77,100
14 Rantai kampret bh 118,400 118,400
15 Busi bh 33,800 33,800
(Rp) (Rp)
Truck Sampah -
1 Stang seker bh 1,014,800 1,014,800
2 Ring seker set 1,758,900 1,758,900
3 Oli mesin ltr 27,000 27,000
4 Oli gardan ltr 33,900 33,900
5 Oli porseneling ltr 33,900 33,900
6 Oli hidrolig ltr 27,000 27,000
7 Kabel PTO bh 270,600 270,600
8 Kabel rem bh 203,000 203,000
9 Kabel gas bh 135,300 135,300
10 Stop lamp bh 54,100 54,100
11 Central kopling atas bh 169,100 169,100
12 Central kopling bawah bh 135,300 135,300
13 Filter solar bh 27,000 27,000
14 Filter oli mesin bh 94,700 94,700
15 Filter angin bh 67,700 67,700
16 Kampas kopling bh 947,100 947,100
17 Kampas rem depan set 169,100 169,100
18 Kampas rem belakang set 169,100 169,100
19 Baskom filter bh 67,700 67,700
20 Waterpom bh 405,900 405,900
21 Nosel bh 338,300 338,300
22 Baut roda bh 54,100 54,100
23 Palek roda truk bh 541,200 541,200
24 Shiver bh 20,300 20,300
25 Baut kopel bh 6,800 6,800
26 Dinamo stater bh 2,706,000 2,706,000
27 Dinamo amper bh 3,382,500 3,382,500
28 Tali kipas bh 40,600 40,600
29 Radiator bh 2,706,000 2,706,000
30 Minyak rem ltr 60,900 60,900
31 Minyak power ltr 60,900 60,900
32 Skring bh 1,400 1,400
33 Servo bh 2,029,500 2,029,500
15 Accu Ns 70 Amper bh 811,800 811,800
16 Accu N 50 Z bh 778,000 778,000
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
VII . B A H A N P I P A D A N A S E S S O R I S P E R P I P A A N -
-
I. BAHAN PI PA -
-
1. Pipa PVC " MASPION " Standard SNI. 06.0084-2002 -
a. S - 6.3 -
- Pipe - Mof -
Pipa PVC DN 16 ( 3/8" ) AW JIS m' 3,400 3,400
Pipa PVC DN 20 ( 1/2" ) AW JIS m' 5,300 5,300
Pipa PVC DN 25 ( 3/4" ) AW JIS m' 8,700 8,700
Pipa PVC DN 32 ( 1" ) AW JIS m' 14,100 14,100
Pipa PVC DN 40 ( 1 ¼" ) m' 21,700 21,700
Pipa PVC DN 50 ( 1 ½" ) m' 33,300 33,300
-
b. S-8 -
- Pipe - Mof -
Pipa PVC DN 25 ( 3/4" ) AW JIS m' 7,000 7,000
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
H Assesoris Perpipaan
Staner Keni ½'' bh 1,650 1,650
¾'' bh 2,200 2,200
1'' bh 2,750 2,750
1 ¼'' bh 3,850 3,850
1 ½'' bh 4,400 4,400
2'' bh 4,950 4,950
2 ½'' bh 6,050 6,050
3'' bh 7,150 7,150
4'' bh 13,750 13,750
-
shock ½'' bh 1,705 1,705
¾'' bh 2,200 2,200
1'' bh 2,750 2,750
1 ¼'' bh 3,300 3,300
1 ½'' bh 3,850 3,850
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
90 ̊ 3,265,713 3,265,713
45 ̊ 2,982,045 2,982,045
22,5 ̊ 2,489,245 2,489,245
11,25 ̊ 2,148,124 2,148,124
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
90 ̊ 1,598,806 1,598,806
45 ̊ 1,468,104 1,468,104
22,5 ̊ 1,251,833 1,251,833
11,25 ̊ 1,048,740 1,048,740
Bend PVC DN 280 mm -
Ukuran -
90 ̊ 2,110,449 2,110,449
45 ̊ 1,922,118 1,922,118
22,5 ̊ 1,606,077 1,606,077
11,25 ̊ 1,346,587 1,346,587
Bend PVC DN 315 ( 12" ) -
Ukuran -
90 ̊ 2,827,484 2,827,484
45 ̊ 2,413,477 2,413,477
22,5 ̊ 2,018,885 2,018,885
11,25 ̊ 1,652,420 1,652,420
Bend PVC DN 355 ( 14" ) -
Ukuran -
90 ̊ 8,122,301 8,122,301
45 ̊ 5,340,522 5,340,522
22,5 ̊ 4,879,182 4,879,182
11,25 ̊ 4,646,895 4,646,895
Bend PVC DN 400 ( 16" ) -
Ukuran -
90 ̊ 12,049,774 12,049,774
45 ̊ 9,625,011 9,625,011
22,5 ̊ 8,747,123 8,747,123
11,25 ̊ 8,330,597 8,330,597
Bend PVC DN 450 ( 18" ) -
Ukuran -
90 ̊ 18,000,290 18,000,290
45 ̊ 14,504,380 14,504,380
22,5 ̊ 11,365,519 11,365,519
11,25 ̊ 10,824,231 10,824,231
Bend PVC DN 500 ( 20" ) -
Ukuran -
90 ̊ 26,925,525 26,925,525
45 ̊ 20,679,956 20,679,956
22,5 ̊ 16,132,655 16,132,655
11,25 ̊ 15,364,492 15,364,492
Bend PVC DN 630 ( 24" ) -
Ukuran -
90 ̊ 55,487,817 55,487,817
45 ̊ 38,603,389 38,603,389
22,5 ̊ 27,521,582 27,521,582
11,25 ̊ 26,210,954 26,210,954
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
90 ̊ bh 974,424 974,424
45 ̊ bh 901,824 901,824
22,5 ̊ bh 754,688 754,688
11,25 ̊ bh 659,164 659,164
(Rp) (Rp)
Ukuran -
90 ̊ bh 50,578,671 50,578,671
45 ̊ bh 33,694,287 33,694,287
22,5 ̊ bh 22,611,600 22,611,600
11,25 ̊ bh 22,611,600 22,611,600
(Rp) (Rp)
- RRJ -
Ukuran -
63 x 63 bh 147,939 147,939
75 x 63 bh 225,929 225,929
75 x 75 bh 173,932 173,932
- RR - SC -
Ukuran -
63 x 16 bh 133,936 133,936
63 x 20 bh 133,936 133,936
63 x 25 bh 133,936 133,936
63 x 32 bh 133,936 133,936
63 x 40 bh 144,232 144,232
63 x 50 bh 144,232 144,232
75 x 16 bh 186,065 186,065
75 x 20 bh 186,065 186,065
75 x 25 bh 186,065 186,065
75 x 32 bh 241,747 241,747
75 x 50 bh 241,747 241,747
90 x 32 bh 255,387 255,387
90 x 40 bh 255,387 255,387
90 x 50 bh 255,387 255,387
- RR - Flange -
Ukuran -
63 x 63 bh 236,247 236,247
75 x 63 bh 246,862 246,862
75 x 75 bh 268,807 268,807
-
b. SOCKET / REDUCER ( Outside Diameter ) -
- SCJ -
Ukuran -
20 x 20 bh 1,375 1,375
25 x 20 bh 1,903 1,903
25 x 25 bh 1,375 1,375
32 x 20 bh 2,464 2,464
32 x 25 bh 2,354 2,354
32 x 32 bh 1,694 1,694
40 x 40 bh 6,754 6,754
40 x 25 bh 17,369 17,369
40 x 32 bh 3,619 3,619
40 x 40 bh 3,729 3,729
50 x 20 bh 10,285 10,285
50 x 25 bh 10,285 10,285
50 x 32 bh 7,557 7,557
50 x 40 bh 7,557 7,557
50 x 50 bh 5,115 5,115
63 x 20 bh 35,420 35,420
63 x 25 bh 35,420 35,420
63 x 32 bh 25,344 25,344
63 x 40 bh 31,680 31,680
63 x 50 bh 21,021 21,021
63 x 63 bh 19,833 19,833
(Rp) (Rp)
75 x 20 bh 105,556 105,556
75 x 25 bh 104,445 104,445
75 x 32 bh 133,771 133,771
75 x 50 bh 128,590 128,590
75 x 63 bh 89,023 89,023
75 x 75 bh 27,775 27,775
90 x 20 bh 79,486 79,486
90 x 25 bh 79,486 79,486
90 x 32 bh 75,031 75,031
90 x 40 bh 73,821 73,821
90 x 50 bh 75,031 75,031
- RRJ -
Ukuran -
63 x 63 bh 62,832 62,832
75 x 63 bh 140,734 140,734
75 x 75 bh 71,192 71,192
- RR - Spigot -
Ukuran -
75 x 63 1,107,260 1,107,260
- RR - SC -
Ukuran -
63 x 20 bh 74,041 74,041
63 x 25 bh 74,041 74,041
63 x 32 bh 71,192 71,192
63 x 40 bh 46,761 46,761
63 x 50 bh 67,837 67,837
75 x 50 bh 198,396 198,396
75 x 63 bh 123,398 123,398
90 x 32 bh 151,151 151,151
90 x 40 bh 147,741 147,741
90 x 50 bh 147,741 147,741
(Rp) (Rp)
90 x 25 bh 73,117 73,117
90 x 32 bh 71,247 71,247
90 x 40 bh 80,212 80,212
90 x 50 bh 85,459 85,459
(Rp) (Rp)
(Rp) (Rp)
- SCJ
Ukuran
90 x 63 bh 64,020 64,020
90 x 75 bh 60,280 60,280
90 x 90 bh 36,498 36,498
110 x 32 bh 109,483 109,483
110 x 50 bh 109,483 109,483
110 x 63 bh 96,591 96,591
110 x 75 bh 108,031 108,031
110 x 90 bh 111,496 111,496
110 x 110 bh 49,434 49,434
160 x 75 bh 243,111 243,111
160 x 90 bh 213,664 213,664
160 x 110 bh 231,990 231,990
160 x 160 bh 133,276 133,276
200 x 160 bh 454,487 454,487
200 x 200 bh 337,777 337,777
250 x 160 bh 779,427 779,427
250 x 200 bh 952,567 952,567
- RRJ
Ukuran
90 x 63 bh 126,236 126,236
90 x 75 bh 116,809 116,809
90 x 90 bh 94,655 94,655
110 x 63 bh 184,294 184,294
110 x 75 bh 193,303 193,303
110 x 90 bh 202,829 202,829
110 x 110 bh 165,616 165,616
160 x 63 bh 430,903 430,903
160 x 75 bh 475,145 475,145
160 x 90 bh 326,601 326,601
160 x 110 bh 370,810 370,810
160 x 160 bh 253,374 253,374
200 x 90 bh 945,175 945,175
200 x 110 bh 976,437 976,437
200 x 160 bh 675,213 675,213
200 x 200 bh 501,710 501,710
250 x 63 bh 1,280,213 1,280,213
250 x 90 bh 1,266,859 1,266,859
250 x 110 bh 14,455,276 14,455,276
250 x 160 bh 1,003,684 1,003,684
250 x 200 bh 1,240,987 1,240,987
250 x 250 bh 720,104 720,104
- RR - Spigot
Ukuran
90 x 63 bh 96,030 96,030
90 x 75 bh 92,675 92,675
110 x 63 bh 144,177 144,177
110 x 75 bh 153,197 153,197
110 x 90 bh 162,514 162,514
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
Fitting PVC Solvent Cement Join SCJ. DN ( 3/4" x 1/2" ) 1,012 1,012
l. LEM/ LUBRICAN -
- TUBE 7,854 7,854
- KALENG -
ukuran -
500 gram 62,425 62,425
1,000 ml 124,377 124,377
ᴓ
7. PVC FERRULE -
-
a. SISTEM SAMBUNGAN ULIR -
BSP ( 1 '' ), bsp ( 1/2 '' ), I ( 84 mm ) 104,885 104,885
BSP ( 1 1/4 '' ), bsp ( 3/4 '' ), I ( 101 mm ) 135,047 135,047
-
b. SISTEM SAMBUNGAN ULIR -
BSP ( 1 '' ), bsp ( 3/4 '' ), I ( 101 mm ) 130,636 130,636
-
c. SISTEM SAMBUNGAN LEM -
D ( 32 mm ), d ( 20 mm ), L ( 84 mm ) 104,885 104,885
D ( 40 mm ), d ( 25 mm ), L ( 101 mm ) 135,047 135,047
-
8. FITTING PVC SNI UNILON -
-
a. PVC Reducer Socket RR Joint -
Ø 90 x 63 mm bh 99,000 99,000
Ø 110 x 90 mm bh 158,400 158,400
Ø 110 x 63 mm bh 141,900 141,900
Ø 160 x 110 mm bh 277,200 277,200
Ø 160 x 90 mm bh 240,900 240,900
(Rp) (Rp)
Ø 90 x 90 mm bh 1,963,500 1,963,500
Ø 110 x 110 mm bh 2,587,200 2,587,200
Ø 160 x 160 mm bh 9,521,600 9,521,600
e. ELBOW 90 ̊ SCJ -
Ø 20 mm bh 39,600 39,600
Ø 25 mm bh 60,060 60,060
Ø 32 mm bh 85,140 85,140
Ø 40 mm bh 164,340 164,340
Ø 50 mm bh 270,600 270,600
Ø 63 mm bh 498,300 498,300
Ø 75 mm bh 1,056,000 1,056,000
Ø 90 mm bh 1,963,500 1,963,500
Ø 110 mm bh 2,587,200 2,587,200
Ø 160 mm bh 9,521,600 9,521,600
f. ELBOW 45 ̊ SCJ -
Ø 20 mm bh 39,600 39,600
Ø 25 mm bh 60,060 60,060
Ø 32 mm bh 85,140 85,140
Ø 40 mm bh 164,340 164,340
(Rp) (Rp)
Ø 50 mm bh 270,600 270,600
Ø 63 mm bh 498,300 498,300
Ø 75 mm bh 1,056,000 1,056,000
Ø 90 mm bh 1,963,500 1,963,500
Ø 110 mm bh 2,587,200 2,587,200
Ø 160 mm bh 9,521,600 9,521,600
-
9. FITTING PVC SNI UNILON -
-
a. Long Bend Socket / Spigot RR - Joint -
Ø 63 mm -
90 ̊ bh 62,700 62,700
45 ̊ bh 51,480 51,480
22,5 ̊ bh 48,840 48,840
11,25 ̊ bh 46,200 46,200
Ø 75 mm -
90 ̊ bh 109,560 109,560
45 ̊ bh 93,720 93,720
22,5 ̊ bh 91,740 91,740
11,25 ̊ bh 85,140 85,140
Ø 90 mm -
90 ̊ bh 129,580 129,580
45 ̊ bh 112,860 112,860
22,5 ̊ bh 98,340 98,340
11,25 ̊ bh 93,060 93,060
Ø 110 mm -
90 ̊ bh 196,900 196,900
45 ̊ bh 167,200 167,200
22,5 ̊ bh 165,000 165,000
11,25 ̊ bh 151,800 151,800
Ø 140 mm -
90 ̊ bh 419,100 419,100
45 ̊ bh 330,660 330,660
22,5 ̊ bh 270,600 270,600
11,25 ̊ bh 237,600 237,600
Ø 160 mm -
90 ̊ bh 447,480 447,480
45 ̊ bh 389,400 389,400
22,5 ̊ bh 331,980 331,980
11,25 ̊ bh 295,020 295,020
Ø 200 mm -
90 ̊ bh 805,200 805,200
45 ̊ bh 693,000 693,000
22,5 ̊ bh 577,500 577,500
11,25 ̊ bh 504,240 504,240
Ø 250 mm -
90 ̊ bh 1,413,720 1,413,720
(Rp) (Rp)
45 ̊ bh 1,294,920 1,294,920
22,5 ̊ bh 1,069,200 1,069,200
11,25 ̊ bh 898,920 898,920
Ø 315 mm -
90 ̊ bh 2,455,200 2,455,200
45 ̊ bh 2,003,100 2,003,100
22,5 ̊ bh 1,782,000 1,782,000
11,25 ̊ bh 1,487,860 1,487,860
Ø 355 mm -
90 ̊ bh 6,091,800 6,091,800
45 ̊ bh 3,762,000 3,762,000
22,5 ̊ bh 3,366,000 3,366,000
11,25 ̊ bh 3,366,000 3,366,000
Ø 400 mm -
90 ̊ bh 9,108,000 9,108,000
45 ̊ bh 7,067,500 7,067,500
22,5 ̊ bh 6,329,400 6,329,400
11,25 ̊ bh 6,329,400 6,329,400
Ø 450 mm -
90 ̊ bh 13,840,200 13,840,200
45 ̊ bh 10,916,400 10,916,400
22,5 ̊ bh 8,335,800 8,335,800
11,25 ̊ bh 8,269,800 8,269,800
Ø 500 mm -
90 ̊ bh 20,526,000 20,526,000
45 ̊ bh 15,259,200 15,259,200
22,5 ̊ bh 11,418,000 11,418,000
11,25 ̊ bh 11,418,000 11,418,000
Ø 630 mm -
90 ̊ bh 42,570,000 42,570,000
45 ̊ bh 28,380,000 28,380,000
22,5 ̊ bh 19,047,600 19,047,600
11,25 ̊ bh 19,047,600 19,047,600
(Rp) (Rp)
Ø 400 mm -
90 ̊ bh 10,164,000 10,164,000
45 ̊ bh 8,118,000 8,118,000
22,5 ̊ bh 7,365,600 7,365,600
11,25 ̊ bh 7,365,600 7,365,600
Ø 450 mm -
90 ̊ bh 15,180,000 15,180,000
45 ̊ bh 12,216,600 12,216,600
22,5 ̊ bh 9,570,000 9,570,000
11,25 ̊ bh 9,570,000 9,570,000
Ø 500 mm -
90 ̊ bh 22,770,000 22,770,000
45 ̊ bh 17,424,000 17,424,000
(Rp) (Rp)
Ø 75 mm -
90 ̊ bh 72,600 72,600
45 ̊ bh 59,400 59,400
22,5 ̊ bh 52,800 52,800
11,25 ̊ bh 45,540 45,540
Ø 90 mm -
90 ̊ bh 80,520 80,520
45 ̊ bh 65,340 65,340
22,5 ̊ bh 57,420 57,420
11,25 ̊ bh 48,180 48,180
Ø 110 mm -
(Rp) (Rp)
90 ̊ bh 164,340 164,340
45 ̊ bh 115,500 115,500
22,5 ̊ bh 92,400 92,400
11,25 ̊ bh 79,200 79,200
Ø 140 mm -
90 ̊ bh 363,000 363,000
45 ̊ bh 310,200 310,200
22,5 ̊ bh 257,400 257,400
11,25 ̊ bh 217,800 217,800
Ø 160 mm -
90 ̊ bh 402,600 402,600
45 ̊ bh 343,200 343,200
22,5 ̊ bh 277,200 277,200
11,25 ̊ bh 237,600 237,600
Ø 200 mm -
90 ̊ bh 63,910 63,910
45 ̊ bh 621,720 621,720
22,5 ̊ bh 521,400 521,400
11,25 ̊ bh 455,400 455,400
Ø 250 mm -
90 ̊ bh 1,273,800 1,273,800
45 ̊ bh 1,168,200 1,168,200
22,5 ̊ bh 960,300 960,300
11,25 ̊ bh 811,800 811,800
Ø 315 mm -
90 ̊ bh 2,211,000 2,211,000
45 ̊ bh 1,805,100 1,805,100
22,5 ̊ bh 1,603,800 1,603,800
11,25 ̊ bh 1,349,700 1,349,700
Ø 355 mm -
90 ̊ bh 5,484,600 5,484,600
45 ̊ bh 3,385,800 3,385,800
22,5 ̊ bh 3,029,400 3,029,400
11,25 ̊ bh 3,029,400 3,029,400
Ø 400 mm -
90 ̊ bh 8,197,200 8,197,200
45 ̊ bh 6,369,000 6,369,000
22,5 ̊ bh 5,695,800 5,695,800
11,25 ̊ bh 5,695,800 5,695,800
Ø 450 mm -
90 ̊ bh 12,454,200 12,454,200
45 ̊ bh 9,820,800 9,820,800
22,5 ̊ bh 7,444,800 7,444,800
11,25 ̊ bh 7,444,800 7,444,800
Ø 500 mm -
90 ̊ bh 18,473,400 18,473,400
45 ̊ bh 13,734,600 13,734,600
22,5 ̊ bh 10,276,200 10,276,200
(Rp) (Rp)
-
10. FITTING PVC SNI UNILON -
a. PVC Tee All Socket RRJ ( INJ ) -
Ø 63 x 63 mm bh 142,560 142,560
Ø 90 x 90 mm bh 237,600 237,600
Ø 90 x 63 mm bh 205,920 205,920
Ø 110 x 110 mm bh 396,000 396,000
Ø 110 x 90 mm bh 356,400 356,400
Ø 110 x 63 mm bh 316,800 316,800
Ø 160 x 160 mm bh 732,600 732,600
Ø 160 x 110 mm bh 633,600 633,600
Ø 160 x 90 mm bh 574,200 574,200
Ø 160 x 63 mm bh 495,000 495,000
b. PVC Tee All Socket RRJ ( INJ + HP ) -
Ø 200 x 200 mm bh 1,801,800 1,801,800
Ø 200 x 160 mm bh 1,622,500 1,622,500
Ø 200 x 110 mm bh 1,366,200 1,366,200
Ø 200 x 90 mm bh 1,335,400 1,335,400
Ø 200 x 63 mm bh 1,424,500 1,424,500
Ø 250 x 250 mm bh 3,940,200 3,940,200
Ø 250 x 200 mm bh 3,564,000 3,564,000
Ø 250 x 160 mm bh 3,366,000 3,366,000
Ø 250 x 110 mm bh 3,358,300 3,358,300
Ø 250 x 90 mm bh 3,346,200 3,346,200
c. PVC Tee All Socket RRJ ( INJ + HP ) -
Ø 315 x 315 mm bh 4,048,000 4,048,000
Ø 315 x 250 mm bh 3,940,200 3,940,200
Ø 315 x 200 mm bh 3,762,000 3,762,000
Ø 315 x 160 mm bh 3,564,000 3,564,000
Ø 315 x 110 mm bh 3,355,000 3,355,000
Ø 355 x 355 mm bh 5,346,000 5,346,000
Ø 355 x 315 mm bh 5,148,000 5,148,000
Ø 355 x 250 mm bh 4,950,000 4,950,000
Ø 400 x 400 mm bh 7,722,000 7,722,000
Ø 400 x 355 mm bh 7,524,000 7,524,000
Ø 400 x 315 mm bh 7,306,200 7,306,200
(Rp) (Rp)
(Rp) (Rp)
VIII . B A H A N C A T.
A . MEREK
(Rp) (Rp)
Ukuran
25 cc
50 cc
100 cc
200 cc
250 cc
270 cc set
300 cc
350 gram
350 gram set
725 gram
0.7 kilo gram
1 kilo gram
1.7 kilo gram set
2.5 kilo gram set
4 kilo gram
4 kilo gram set
4.5 kilo gram
5 kilo gram
18 kilo gram
20 kilo gram
21 kilo gram
25 kilo gram
40 kilo gram
Lain - lain
(Rp) (Rp)
(Rp) (Rp)
- Starlight / Sparkle -
Ukuran -
300 cc 26,730 26,730
(Rp) (Rp)
- Flourescent -
Ukuran -
300 cc 25,520 25,520
2. Tan -
- Standard / Candytone / Metalic -
Ukuran -
300 cc 19,140 19,140
-
D. CAT MOBIL / INDUSTRI ( AUTOMOTIF / INDUSTRIAL LACQUER ) -
-
1. Suzuka -
- Cat Duco Warna-warna -
Ukuran -
1 kilo gram 56,430 56,430
200 cc 15,070 15,070
20 kilo gram 1,055,560 1,055,560
- Candytone / Metalic / Tembaga -
Ukuran -
1 kilo gram 73,260 73,260
200 cc 18,810 18,810
20 kilo gram 1,368,400 1,368,400
- Starlight / Sparkle / Flourescent -
Ukuran -
1 kilo gram 94,600 94,600
200 cc 22,110 22,110
20 kilo gram 1,659,680 1,659,680
- Clear Coat Anti Gores Terdiri dari 2 komponen -
Ukuran -
1 kilo gram 116,270 116,270
200 cc 32,670 32,670
- Rubberized Undercoat -
Ukuran -
1 kilo gram 38,610 38,610
- Clear - 222 -
Ukuran -
1 kilo gram 40,480 40,480
200 cc 12,320 12,320
20 kilo gram 748,330 748,330
- Primer 260 - 270 -
Ukuran -
1 kilo gram 40,480 40,480
200 cc 12,320 12,320
20 kilo gram 748,330 748,330
2. Suzuka -
- Epoxy Filler Terdiri dari 2 komponen -
Ukuran -
1 liter set 46,310 46,310
270 cc set 13,420 13,420
- Epoxy Filler -
Ukuran -
1 kilo gram 29,700 29,700
(Rp) (Rp)
2. Djarum ( Aluminium ) -
Ukuran -
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
50 cc 51,480 51,480
100 cc 84,700 84,700
200 cc 156,530 156,530
0.45 liter 26,620 26,620
0.90 liter 48,620 48,620
3,78 liter 198,770 198,770
- Matt / Flat Enamel -
Ukuran -
0.90 liter 48,620 48,620
- Vernis -
Ukuran -
0.45 liter 21,230 21,230
0.90 liter 33,330 33,330
- Bron Emas Terdiri dari 2 komponen -
Ukuran -
100 cc 173,470 173,470
2. Djarum ( High Gloss Enamel ) -
Ukuran -
0.80 liter 36,630 36,630
3. Yoko ( High Gloss Enamel ) -
Ukuran -
0.70 liter 30,910 30,910
3,78 liter 150,480 150,480
VIII . B A H A N C A T. -
-
I. PRODUCT NIPPON PAINT ( CAT DEKORATIF ) -
Per 1 Mei 2012 -
-
A. CAT TEMBOK WATER - BASED ( WALL PAINT ) -
UNTUK EXTERIOR & INTERIOR : -
1. Nippon Weatherbond ( Brilliant White ) -
Ukuran -
1 liter 99,330 99,330
2.5 liter 219,780 219,780
20 liter 1,530,100 1,530,100
2. Nippon Spot-less ( Brilliant White ) -
Ukuran -
1 liter 87,670 87,670
2.5 liter 176,880 176,880
20 liter 1,229,800 1,229,800
3. Super Vinilex -
Ukuran -
1 kilo gram 92,827 92,827
5 kilo gram 121,550 121,550
25 kilo gram 600,050 600,050
4. Vinilex -
Ukuran -
1 kilo gram 27,830 27,830
5 kilo gram 103,950 103,950
25 kilo gram 512,050 512,050
(Rp) (Rp)
(Rp) (Rp)
-
C. PLAMIR TEMBOK ( WALL FILLER ) -
1. Matex Putty -
Ukuran -
1 kilo gram 13,860 13,860
4 kilo gram 38,500 38,500
14 kilo gram 13,028 13,028
20 kilo gram 187,000 187,000
37 kilo gram 36,190 36,190
D. CAT PELAPIS ANTI BOCOR ( WATER - PROOFING ) -
1. Nippon Elastex Water Proof -
Ukuran -
1 kilo gram 43,230 43,230
4 kilo gram 160,820 160,820
20 kilo gram 754,600 754,600
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
4. MOWILEX WEATHERCOAT -
Kategori Produk ( Water Base ) -
Ukuran -
2.5 liter 205,920 205,920
20 liter 1,537,030 1,537,030
5. MOWILEX ROOF PAINT -
Kategori Produk ( Water Base ) -
Ukuran -
2.5 liter 156,090 156,090
5 liter 290,950 290,950
20 liter 1,118,040 1,118,040
6. MOWILEX ELASTOMERIC WALL COATING -
Kategori Produk ( Water Base ) -
Ukuran -
2.5 liter 209,110 209,110
20 liter 1,572,340 1,572,340
7. MOWILEX VINYL SILK Kategori Produk ( Water Base ) -
Ukuran -
2.5 liter 165,275 165,275
20 liter 1,246,960 1,246,960
(Rp) (Rp)
(Rp) (Rp)
(Rp) (Rp)
V. PRODUCT PAR -
Per 23 April 2012 -
-
1. A917 PAR Emulsion -
Ukuran -
5 kilo gram 35,200 35,200
20 kilo gram 140,250 140,250
(Rp) (Rp)
Rp 157,000.00
Rp 205,000.00
Rp 500.00
Rp 108,000.00
Rp 137,000.00
Rp 230,000.00
Rp 37,000.00
Rp 31,000.00
Rp 234,000.00
Rp 9,100.00
Wrning
0.09
0.72
8
72,000
90,000
Rp 10,150.00
80,920
92,480
104,040
Tenaga
1.000 m3 galian Tanah #REF! #REF!
36.000 oh Tukang 90,000.00 100,000.00
6.000 oh Kepala Tukang 90,000.00 100,000.00
3.000 oh Mandor 80,000.00 90,000.00
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 5,850.00 6,675.00
1 m' Urugan Tanah Kembali 2,730.00 3,115.00
1 m' Ongkos Pemasangan 66,137.50 73,937.50
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 3,120.00 3,560.00
1 m' Urugan Tanah Kembali 1,170.00 1,335.00
1 m' Ongkos Pemasangan 34,391.50 38,447.50
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 2,535.00 2,892.50
1 m' Urugan Tanah Kembali 780.00 890.00
1 m' Ongkos Pemasangan 26,455.00 29,575.00
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 2,340.00 2,670.00
1 m' Urugan Tanah Kembali 585.00 667.50
1 m' Ongkos Pemasangan 21,164.00 23,660.00
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 1,950.00 2,225.00
1 m' Urugan Tanah Kembali 390.00 445.00
1 m' Ongkos Pemasangan 13,227.50 14,787.50
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 3,900.00 4,450.00
1 m' Urugan Tanah Kembali 1,560.00 1,780.00
1 m' Ongkos Pemasangan 20,610.00 23,250.00
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 3,120.00 3,560.00
1 m' Urugan Tanah Kembali 1,170.00 1,335.00
1 m' Ongkos Pemasangan 13,396.50 15,112.50
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 1,950.00 2,225.00
1 m' Urugan Tanah Kembali 390.00 445.00
1 m' Ongkos Pemasangan 5,152.50 5,812.50
1 m' Pengetesan Pipa #REF! #REF!
Tenaga
1 m' Galian Tanah #REF! #REF!
1 m' Urugan Pasir 1,950.00 2,225.00
1 m' Urugan Tanah Kembali 390.00 445.00
1 m' Ongkos Pemasangan 5,152.50 5,812.50
1 m' Pengetesan Pipa #REF! #REF!
2,730.00 3,115.00
1,560.00 1,780.00
1,170.00 1,335.00
780.00 890.00
585.00 667.50
390.00 445.00
5,850.00 6,675.00
3,900.00 4,450.00
3,120.00 3,560.00
2,535.00 2,892.50
2,340.00 2,670.00
1,950.00 2,225.00
30,915.00 34,875.00
20,610.00 23,250.00
13,396.50 15,112.50
10,305.00 11,625.00
8,244.00 9,300.00
5,152.50 5,812.50
52,910.00 59,150.00
9,100.00 10,400.00
35,100.00 39,000.00
3,510.00 3,900.00
5,200.00 5,850.00
66,137.50 73,937.50
52,910.00 59,150.00
34,391.50 38,447.50
26,455.00 29,575.00
21,164.00 23,660.00
13,227.50 14,787.50
#REF! #REF!
#REF! #REF!
379,665.00 417,630.00
- -
379,665.00 417,630.00
#REF! #REF!
#REF! #REF!
3,240,000.00 3,600,000.00
540,000.00 600,000.00
240,000.00 270,000.00
45,000.00 45,000.00
#REF! #REF!
880,000.00 962,500.00
880,000.00 962,500.00
#REF! #REF!
#REF! #REF!
5,850.00 6,675.00
2,730.00 3,115.00
66,137.50 73,937.50
#REF! #REF!
#REF! #REF!
511,500.00 550,000.00
511,500.00 550,000.00
#REF! #REF!
#REF! #REF!
396,000.00 423,500.00
396,000.00 423,500.00
#REF! #REF!
#REF! #REF!
3,120.00 3,560.00
1,170.00 1,335.00
34,391.50 38,447.50
#REF! #REF!
#REF! #REF!
261,250.00 286,000.00
261,250.00 286,000.00
#REF! #REF!
#REF! #REF!
2,535.00 2,892.50
780.00 890.00
26,455.00 29,575.00
#REF! #REF!
#REF! #REF!
184,250.00 211,750.00
184,250.00 211,750.00
#REF! #REF!
#REF! #REF!
2,340.00 2,670.00
585.00 667.50
21,164.00 23,660.00
#REF! #REF!
#REF! #REF!
99,000.00 137,500.00
99,000.00 137,500.00
#REF! #REF!
#REF! #REF!
1,950.00 2,225.00
390.00 445.00
13,227.50 14,787.50
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!
3,900.00 4,450.00
1,560.00 1,780.00
20,610.00 23,250.00
#REF! #REF!
#REF! #REF!
#REF! #REF!
3,120.00 3,560.00
1,170.00 1,335.00
13,396.50 15,112.50
#REF! #REF!
#REF! #REF!
22,000.00 35,750.00
22,000.00 35,750.00
#REF! #REF!
#REF! #REF!
1,950.00 2,225.00
390.00 445.00
5,152.50 5,812.50
#REF! #REF!
#REF! #REF!
17,600.00 28,400.00
17,600.00 28,400.00
#REF! #REF!
#REF! #REF!
1,950.00 2,225.00
390.00 445.00
5,152.50 5,812.50
#REF! #REF!
0.1089
1
9.1827364555
48000 55488
50000 57800
50000 57800
6.29 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) m3 3,606,184.00 3,806,253.00
6.30 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) m3 6,588,980.00 7,331,320.00
6.31 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) m3 5,020,104.00 5,830,208.00
6.32 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) m3 4,750,869.00 5,424,863.00
6.33 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) m3 4,782,103.00 5,504,091.00
6.34 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) m3 4,824,840.00 5,383,925.00
6.35 Membuat Kolom Penguat Beton Bertulang (11 x 11) cm m' 58,441.90 62,258.30
6.36 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 81,096.35 87,156.45
X 6 PEKERJAAN SANITASI
6.1 Memasang Closet Duduk / Mono Blok Unit 1,217,390.00 1,263,000.00
6.2 Memasang Closet Jongkok Porselen Unit 466,562.00 542,240.00
6.4 Memasang Urinoir Unit 804,367.00 891,855.00
6.5 Memasang Wastafel Unit 350,617.00 480,555.00
6.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,169,310.00 1,354,050.00
6.14 Memasang Pipa Beton, Ø 15 cm - 20 cm m' 74,365.60 104,861.20
6.15 Memasang Pipa Beton, Ø 30 cm - 100 cm m' 407,905.45 454,408.25
6.20 Memasang Pipa Galvanis Ø ¾" m' 40,425.00 52,170.83
6.23 Memasang Pipa Galvanis Ø 3" m' 128,112.00 138,330.17
6.24 Memasang Pipa Galvanis Ø 4" m' 164,406.50 178,245.33
6.25 Memasang Pipa PVC type AW Ø ½" m' 14,571.50 18,593.25
6.29 Memasang Pipa PVC type AW Ø 2" m' 64,056.00 167,913.00
6.31 Memasang Pipa PVC type AW Ø 3" m' 90,973.00 302,424.00
6.33 Memasang Bak Cuci Piring Stainles Steel Buah 161,170.00 304,835.00
6.35 Memasang Kran Ø ¾" atau ½" Buah 16,527.50 50,892.50
6.36 Memasang Floor Drain Buah 15,400.00 31,500.00
6.2 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 514,115.45 650,949.85
6.2.1 Bahan 464,715.45 595,149.85
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 23,100.00 28,000.00 28,875.00 35,000.00
2.5 Kg Portalnd Semen 1,292.50 1,402.50 3,231.25 3,506.25
1.2 Lbr Seng Gelombang 3" - 5" 40,700.00 64,350.00 48,840.00 77,220.00
0.005 m3 Pasir Beton 310,000.00 340,000.00 1,550.00 1,700.00
0.009 m3 Koral Beton 140,800.00 170,400.00 1,267.20 1,533.60
0.072 m3 Kayu 5/7X4m Kayu Kruing 5,280,000.00 6,600,000.00 380,160.00 475,200.00
0.06 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 792.00 990.00
0.45 Kg Meni Besi 14,300.00 22,000.00 6,435.00 9,900.00
6.35.2
6.36.2
0.03
33.3
6.15 1 m3 Mengurug Sirtu Padat untuk Peninggian Lantai Bangunan 98,700.00 299,450.00
6.15.1 Bahan 79,200.00 277,200.00
1.2 m3 Sirtu 66,000.00 231,000.00 79,200.00 277,200.00
6.6 1m3 Memasang Pondasi Batu Kali 1Kp : 1Sm : 2Pp 422,410.00 549,458.00
6.6.1 Bahan 237,160.00 340,208.00
1.2 m3 Batu Belah 15/20 154,000.00 192,500.00 184,800.00 231,000.00
0.17 m3 Kapur Pasang (KP) 6,600.00 257,400.00 1,122.00 43,758.00
0.17 Kg Semen Merah (SM) - - - -
0.340 m3 Pasir Pasang 150,700.00 192,500.00 51,238.00 65,450.00
6.10 1 m3 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah 2,111,043.00 2,233,585.00
6.10.1 Bahan 1,776,893.00 1,854,585.00
0.480 m3 Batu Belah 15/20 cm 154,000.00 192,500.00 73,920.00 92,400.00
126 Kg Besi Beton 9,900.00 9,900.00 1,247,400.00 1,247,400.00
194 Kg Portland Semen 1,292.50 1,402.50 250,745.00 272,085.00
0.312 m3 Pasir Beton 310,000.00 340,000.00 96,720.00 106,080.00
0.468 m3 Koral Beton 176,000.00 220,000.00 82,368.00 102,960.00
1.8 Kg Kawat Beton 14,300.00 18,700.00 25,740.00 33,660.00
6.1 1 m2
Memasang Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1Pc : 2Pp 223,479.75 254,108.75
6.1.1 Bahan 159,279.75 181,408.75
140 Buah Bata Merah 650.00 750.00 91,000.00 105,000.00
43.5 Kg Portland Semen (PC) 1,292.50 1,402.50 56,223.75 61,008.75
0.08 m3 Pasir Pasang (PP) 150,700.00 192,500.00 12,056.00 15,400.00
6.2 1 m2Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 3PP 211,501.58 241,429.88
6.2.1 Bahan 147,301.58 168,729.88
140 Buah Bata Merah 650.00 750.00 91,000.00 105,000.00
32.95 Kg Portland Semen (PC) 1,292.50 1,402.50 42,587.88 46,212.38
0.091 m3 Pasir Pasang (PP) 150,700.00 192,500.00 13,713.70 17,517.50
6.3 1 m2Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 4PP 203,530.98 232,838.88
6.3.1 Bahan 139,330.98 160,138.88
140 Buah Bata Merah 650.00 750.00 91,000.00 105,000.00
26.55 Kg Portland Semen (PC) 1,292.50 1,402.50 34,315.88 37,236.38
0.093 m3 Pasir Pasang (PP) 150,700.00 192,500.00 14,015.10 17,902.50
6.4 1 m2Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 5PP 199,264.90 228,470.50
6.4.1 Bahan 135,064.90 155,770.50
140 Buah Bata Merah 650.00 750.00 91,000.00 105,000.00
22.2 Kg Portland Semen (PC) 1,292.50 1,402.50 28,693.50 31,135.50
0.102 m3 Pasir Pasang (PP) 150,700.00 192,500.00 15,371.40 19,635.00
6.5 1 m2Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 6PP 197,496.65 227,131.25
6.5.1 Bahan 133,296.65 154,431.25
140 Buah Bata Merah 650.00 750.00 91,000.00 105,000.00
18.5 Kg Portland Semen (PC) 1,292.50 1,402.50 23,911.25 25,946.25
0.122 m3 Pasir Pasang (PP) 150,700.00 192,500.00 18,385.40 23,485.00
6.6 1 m2Memasang Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1Pc : 3 KP :10PP 182,349.65 216,721.95
6.6.1 Bahan 118,149.65 144,021.95
140 Buah Bata Merah 650.00 750.00 91,000.00 105,000.00
10.08 Kg Portland Semen (PC) 1,292.50 1,402.50 13,028.40 14,137.20
0.0925 m3 Pasir Pasang (PP) 150,700.00 192,500.00 13,939.75 17,806.25
0.0275 m3 Kapur Pasang (KP) 6,600.00 257,400.00 181.50 7,078.50
6.7 1 m2
Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 2PP 107,819.48 122,742.38
6.7.1 Bahan 75,719.48 86,392.38
70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
18.95 Kg Portland Semen 1,292.50 1,402.50 24,492.88 26,577.38
0.038 m3 Pasir Pasang 150,700.00 192,500.00 5,726.60 7,315.00
#REF! 6.8 1 m2
Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 3PP 102,201.23 116,703.93
6.8.1 Bahan 70,101.23 80,353.93
#REF! 70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
#REF! 14.37 Kg Portland Semen 1,292.50 1,402.50 18,573.23 20,153.93
#REF! 0.04 m3 Pasir Pasang 150,700.00 192,500.00 6,028.00 7,700.00
6.9 1 m2
Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 4PP 98,943.85 113,256.25
6.9.1 Bahan 66,843.85 76,906.25
70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
11.50 Kg Portland Semen 1,292.50 1,402.50 14,863.75 16,128.75
0.043 m3 Pasir Pasang 150,700.00 192,500.00 6,480.10 8,277.50
6.10 1 m2
Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 5PP 96,892.90 111,088.70
Bahan 64,792.90 74,738.70
6.10.1 70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
9.68 Kg Portland Semen 1,292.50 1,402.50 12,511.40 13,576.20
0.045 m3 Pasir Pasang 150,700.00 192,500.00 6,781.50 8,662.50
#REF! 6.11 1 m2
Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 6PP 95,737.90 109,951.30
6.11.1 Bahan 63,637.90 73,601.30
#REF! 70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
#REF! 8.32 Kg Portland Semen 1,292.50 1,402.50 10,753.60 11,668.80
#REF! 0.049 m3 Pasir Pasang 150,700.00 192,500.00 7,384.30 9,432.50
6.12 1 m2
Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 8PP 93,536.25 107,591.25
6.12.1 Bahan 61,436.25 71,241.25
70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
6.50 Kg Portland Semen 1,292.50 1,402.50 8,401.25 9,116.25
0.05 m3 Pasir Pasang 150,700.00 192,500.00 7,535.00 9,625.00
6.13 1 m2
Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 3KP : 10PP 91,050.25 108,647.25
6.13.1 Bahan 58,950.25 72,297.25
70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
4.5 Kg Portland Semen 1,292.50 1,402.50 5,816.25 6,311.25
0.05 m3 Pasir Pasang 150,700.00 192,500.00 7,535.00 9,625.00
0.015 m3 Kapur Padam 6,600.00 257,400.00 99.00 3,861.00
6.14 1 m2Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1Pc : 1SM : 1PP 80,431.40 96,948.20
6.14.1 Bahan 48,331.40 60,598.20
70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
0.018 m3 Semen Merah - - - -
0.018 m3 Pasir Pasang 150,700.00 192,500.00 2,712.60 3,465.00
0.018 m3 Kapur Padam 6,600.00 257,400.00 118.80 4,633.20
6.15 1 m2Memasang Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP 81,912.00 97,843.60
6.15.1 Bahan 49,812.00 61,493.60
70 Buah Bata Merah 5 x 11 x 22 650.00 750.00 45,500.00 52,500.00
0.014 m3 Semen Merah - - - -
0.028 m3 Pasir Pasang 150,700.00 192,500.00 4,219.60 5,390.00
0.014 m3 Kapur Padam 6,600.00 257,400.00 92.40 3,603.60
6.20 1 m2 Memasang Dinding HB/CB 10, speci camp. 1PC : 3PP 150,571.10 171,703.90
6.20.1 Bahan 118,471.10 135,353.90
12.500 buah Batako 3,300.00 3,300.00 41,250.00 41,250.00
15.160 kg PC 1,292.50 1,402.50 19,594.30 21,261.90
0.364 m3 Pasir Pasang 150,700.00 192,500.00 54,854.80 70,070.00
0.280 kg Besi Angkur Ø 8 mm 9,900.00 9,900.00 2,772.00 2,772.00
6.21 1 m2 Memasang Dinding HB/CB 10, speci camp. 1PC : 4PP 150,271.63 172,074.33
6.21.1 Bahan 118,171.63 135,724.33
12.500 buah Batako 3,300.00 3,300.00 41,250.00 41,250.00
12.130 kg PC 1,292.50 1,402.50 15,678.03 17,012.33
0.388 m3 Pasir Pasang 150,700.00 192,500.00 58,471.60 74,690.00
0.280 kg Besi Angkur Ø 8 mm 9,900.00 9,900.00 2,772.00 2,772.00
6.22 1 m2Memasang Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1Pc : 2PP 220,017.40 293,145.00
6.22.1 Bahan 187,917.40 256,795.00
30 Buah Terawang / Roster 5,500.00 7,700.00 165,000.00 231,000.00
14 kg Portland Semen 1,292.50 1,402.50 18,095.00 19,635.00
0.032 m3 Pasir Pasang 150,700.00 192,500.00 4,822.40 6,160.00
6.23 1 m2Memasang Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1Pc : 4PP 216,592.00 289,515.00
6.23.1 Bahan 184,492.00 253,165.00
30 Buah Terawang / Roster 5,500.00 7,700.00 165,000.00 231,000.00
11 kg Portland Semen 1,292.50 1,402.50 14,217.50 15,427.50
0.035 m3 Pasir Pasang 150,700.00 192,500.00 5,274.50 6,737.50
6.24 1 m2 Memasang Finishing Siar Pasangan Dinding Bata Merah (=20 m') 22,627.09 25,378.97
6.24.1 Bahan 4,017.09 4,358.97
3.108 Kg Portland Semen 1,292.50 1,402.50 4,017.09 4,358.97
6.25 1 m2 Memasang Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') 10,798.00 12,104.00
6.25.1 Bahan 2,068.00 2,244.00
1.600 Kg Portland Semen 1,292.50 1,402.50 2,068.00 2,244.00
6.26 1 m2 Memasang Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp 47,052.85 53,051.85
6.26.1 Bahan 10,002.85 11,201.85
6.34 Kg Pc 1,292.50 1,402.50 8,194.45 8,891.85
0.012 m3 PP 150,700.00 192,500.00 1,808.40 2,310.00
6.2 1 m3 Membuat Kosen Pintu & Jendela Kayu klas II atau III 9,113,100.00 9,410,125.00
6.2.1 Bahan 6,887,100.00 6,923,125.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 5,720,000.00 5,720,000.00 6,864,000.00 6,864,000.00
1.25 kg Paku Biasa 2" - 5 " 13,200.00 16,500.00 16,500.00 20,625.00
1 kg Lem Kayu 6,600.00 38,500.00 6,600.00 38,500.00
6.2.2 Tenaga 2,226,000.00 2,487,000.00
6.00 OH Pekerja 70,000.00 80,000.00 420,000.00 480,000.00
18.00 OH Tukang Kayu 90,000.00 100,000.00 1,620,000.00 1,800,000.00
1.80 OH Kepala Tukang 90,000.00 100,000.00 162,000.00 180,000.00
0.30 OH Mandor 80,000.00 90,000.00 24,000.00 27,000.00
6.3 1 m2 Membuat Pintu KlampStandard Kayu Klas II (Kayu Kamfer) 376,950.00 392,345.00
6.3.1 Bahan 247,060.00 247,225.00
0.040 m3 Kayu Klas II (Kamfer), papan 6,160,000.00 6,160,000.00 246,400.00 246,400.00
0.05 Kg Paku Biasa 2" - 5 " 13,200.00 16,500.00 660.00 825.00
6.5 1 m2 Membuat Daun Pintu Panel Kayu Klas I atau II 617,730.00 662,825.00
6.5.1 Bahan 246,730.00 248,325.00
0.04 m3 Kayu Klas II (Kamfer), papan 6,160,000.00 6,160,000.00 246,400.00 246,400.00
0.050 kg Lem Kayu 6,600.00 38,500.00 330.00 1,925.00
6.5.2 Tenaga 371,000.00 414,500.00
1 OH Pekerja 70,000.00 80,000.00 70,000.00 80,000.00
3.0 OH Tukang Kayu 90,000.00 100,000.00 270,000.00 300,000.00
0.30 OH Kepala Tukang 90,000.00 100,000.00 27,000.00 30,000.00
0.05 OH Mandor 80,000.00 90,000.00 4,000.00 4,500.00
6.6 1 m2 Membuat Pintu & Jendela Kaca Kayu Klas I atau II 446,620.00 490,990.00
6.6.1 Bahan 149,820.00 159,390.00
0.024 m3 Kayu Klas II (Kamfer), papan 6,160,000.00 6,160,000.00 147,840.00 147,840.00
0.300 kg Lem Kayu 6,600.00 38,500.00 1,980.00 11,550.00
6.6.2 Tenaga 296,800.00 331,600.00
0.800 OH Pekerja 70,000.00 80,000.00 56,000.00 64,000.00
2.400 OH Tukang Kayu 90,000.00 100,000.00 216,000.00 240,000.00
0.240 OH Kepala Tukang 90,000.00 100,000.00 21,600.00 24,000.00
0.040 OH Mandor 80,000.00 90,000.00 3,200.00 3,600.00
6.7 1 m2 Membuat Pintu & Jendela Jalusi Kayu Klas I atau II 1,622,300.00 1,806,550.00
6.7.1 Bahan 1,251,300.00 1,392,050.00
0.064 m3 Kayu Klas I (Jati), papan 19,500,000.00 21,450,000.00 1,248,000.00 1,372,800.00
0.5 kg Lem Kayu 6,600.00 38,500.00 3,300.00 19,250.00
6.7.2 Tenaga 371,000.00 414,500.00
1 OH Pekerja 70,000.00 80,000.00 70,000.00 80,000.00
3 OH Tukang Kayu 90,000.00 100,000.00 270,000.00 300,000.00
0.3 OH Kepala Tukang 90,000.00 100,000.00 27,000.00 30,000.00
0.05 OH Mandor 80,000.00 90,000.00 4,000.00 4,500.00
6.8 1 m2 Membuat Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm) 497,696.00 561,095.00
6.8.1 Bahan 237,996.00 270,945.00
0.025 m3 Kayu Klas II (Kamfer), papan 6,160,000.00 6,160,000.00 154,000.00 154,000.00
0.030 Kg Paku Biasa 1/2" - 1" 13,200.00 16,500.00 396.00 495.00
0.500 Ltr Lem Kayu 6,600.00 38,500.00 3,300.00 19,250.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 80,300.00 97,200.00 80,300.00 97,200.00
6.9 1 m2 Membuat Pintu Plywood rangkap, rangka expose kayu klas I atau II 538,492.00 606,241.00
6.9.1 Bahan 241,692.00 274,641.00
0.0256 m3 Kayu Klas II (Kamfer), papan 6,160,000.00 6,160,000.00 157,696.00 157,696.00
0.03 Kg Paku Biasa 1/2" - 1" 13,200.00 16,500.00 396.00 495.00
0.5 Ltr Lem Kayu 6,600.00 38,500.00 3,300.00 19,250.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 80,300.00 97,200.00 80,300.00 97,200.00
6.9.2 Tenaga 296,800.00 331,600.00
0.800 OH Pekerja 70,000.00 80,000.00 56,000.00 64,000.00
2.400 OH Tukang Kayu 90,000.00 100,000.00 216,000.00 240,000.00
0.240 OH Kepala Tukang 90,000.00 100,000.00 21,600.00 24,000.00
0.040 OH Mandor 80,000.00 90,000.00 3,200.00 3,600.00
6.10 1 m2 Membuat Jalusi mati Kosen Kayu Klas I atau II 1,443,680.00 1,593,225.00
6.10.1 Bahan 1,171,980.00 1,289,475.00
0.06 m3 Kayu Klas I (Jati), papan 19,500,000.00 21,450,000.00 1,170,000.00 1,287,000.00
0.15 Kg Paku Biasa 1/2" - 1" 13,200.00 16,500.00 1,980.00 2,475.00
6.11 1 m2 Membuat Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I 866,976.00 977,095.00
6.11.1 Bahan 570,176.00 645,495.00
0.025 m3 Kayu Klas I (Jati), papan 19,500,000.00 21,450,000.00 487,500.00 536,250.00
0.03 Kg Paku Biasa 1/2" - 1" 13,200.00 16,500.00 396.00 495.00
0.3 kg Lem Kayu 6,600.00 38,500.00 1,980.00 11,550.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 80,300.00 97,200.00 80,300.00 97,200.00
6.12 1 m2 Membuat Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II 578,114.00 634,645.00
6.12.1 Bahan 262,724.00 282,275.00
0.025 m3 Kayu Klas II (Kamfer), papan 6,160,000.00 6,160,000.00 154,000.00 154,000.00
0.03 Kg Paku Biasa 1/2" - 1" 13,200.00 16,500.00 396.00 495.00
0.08 kg Lem Kayu 6,600.00 38,500.00 528.00 3,080.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 80,300.00 97,200.00 80,300.00 97,200.00
0.5 Lbr Formika 55,000.00 55,000.00 27,500.00 27,500.00
6.12.2 Tenaga 315,390.00 352,370.00
0.850 OH Pekerja 70,000.00 80,000.00 59,500.00 68,000.00
2.550 OH Tukang Kayu 90,000.00 100,000.00 229,500.00 255,000.00
0.255 OH Kepala Tukang 90,000.00 100,000.00 22,950.00 25,500.00
0.043 OH Mandor 80,000.00 90,000.00 3,440.00 3,870.00
6.13 1 m3 Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter 7,909,670.00 8,291,900.00
6.13.1 Bahan 6,423,670.00 6,631,900.00
1.1 m3 Kayu Kamfer, balok 5,720,000.00 5,720,000.00 6,292,000.00 6,292,000.00
15 Kg Besi Strip 3,850.00 16,500.00 57,750.00 247,500.00
5.6 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 73,920.00 92,400.00
#REF! 6.16 1 m2 Memasang Rangka Atap asbes, Kayu Klas II 121,272.00 124,247.00
6.16.1 Bahan 103,972.00 104,797.00
#REF! 0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 5,720,000.00 5,720,000.00 80,080.00 80,080.00
#REF! 0.0036 m3 Reng (2x3) cm 5,720,000.00 5,720,000.00 20,592.00 20,592.00
#REF! 0.25 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 3,300.00 4,125.00
6.17 1 m2 Memasang Rangka Atap Genteng Beton, Kayu Klas II 141,864.00 144,839.00
6.17.1 Bahan 124,564.00 125,389.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 5,720,000.00 5,720,000.00 80,080.00 80,080.00
0.0072 m3 Reng (2x3) cm 5,720,000.00 5,720,000.00 41,184.00 41,184.00
0.25 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 3,300.00 4,125.00
6.19 1 m2 Memasang Rangka Langit-langit (1,00x1,00) m, kayu Klas II atau III 136,928.00 143,138.00
6.19.1 Bahan 90,728.00 91,388.00
0.0154 m3 Kayu Klas II (Kamfer), balok 5,720,000.00 5,720,000.00 88,088.00 88,088.00
0.2 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 2,640.00 3,300.00
6.20 1 m2 Memasang Rangka Langit-langit (60x60) cm, kayu Klas II atau III 141,036.00 147,261.00
6.20.1 Bahan 96,536.00 97,361.00
0.0163 m3 Kayu Klas II (Kamfer), balok 5,720,000.00 5,720,000.00 93,236.00 93,236.00
0.25 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 3,300.00 4,125.00
6.21 1 m' Memasang Listplank Uk. (3x20)cm Kayu klas I atau II 239,120.00 263,760.00
6.21.1 Bahan 211,920.00 233,310.00
0.0108 m3 Kayu klas I (Jati), papan 19,500,000.00 21,450,000.00 210,600.00 231,660.00
0.10 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 1,320.00 1,650.00
6.22 1 m' Memasang Listplank Uk. (3x30)cm Kayu klas I atau klas II 95,620.00 99,035.00
6.22.1 Bahan 68,420.00 68,585.00
0.011 m3 Kayu klas II (Kamfer), papan 6,160,000.00 6,160,000.00 67,760.00 67,760.00
0.05 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 660.00 825.00
6.23 1 m2 Memasang Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III 217,830.00 224,855.00
6.23.1 Bahan 162,140.00 162,635.00
0.028 m3 Kayu klas II (Kamfer), balok 5,720,000.00 5,720,000.00 160,160.00 160,160.00
0.15 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 1,980.00 2,475.00
6.24 1 m2 Memasang Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II 290,584.00 330,007.00
6.24.1 Bahan 234,894.00 267,787.00
0.028 m3 Kayu klas II (Kamfer), balok 5,720,000.00 5,720,000.00 160,160.00 160,160.00
0.15 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 1,980.00 2,475.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 80,300.00 97,200.00 69,058.00 83,592.00
0.56 Ltr Lem 6,600.00 38,500.00 3,696.00 21,560.00
6.27 1 m2 Memasang Dinding Lambriziring dari Plywood ukuran (120x240) cm 42,080.00 50,095.00
6.27.1 Bahan 32,780.00 39,705.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 80,300.00 97,200.00 32,120.00 38,880.00
0.05 Kg Paku Biasa 1/2" - 1" 13,200.00 16,500.00 660.00 825.00
6.28 1 m2 Memasang Dinding Bilik, Rangka Kayu Klas III atau IV 100,469.95 105,881.00
6.28.1 Bahan 88,119.95 91,931.00
1.500 m2 Bilik Bambu 15,000.00 17,500.00 22,500.00 26,250.00
0.014 m3 Kayu Klas III (Meranti) 4,675,000.00 4,675,000.00 65,450.00 65,450.00
0.012 Kg Paku Biasa 1/2" - 1" 13,200.00 16,500.00 158.40 198.00
0.003 m' List Kayu 2/4 3,850.00 11,000.00 11.55 33.00
6.2 1 m3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 821,417.67 922,864.23
6.2.1 Bahan 672,007.67 753,094.23
276 Kg Portland Semen 1,292.50 1,402.50 356,730.00 387,090.00
828 kg Pasir Beton 221.43 242.86 183,342.86 201,085.71
1,012 kg Kerikil (maksimum 30 mm) 130.37 162.96 131,934.81 164,918.52
215 ltr Air 0.00 0.00 - -
#REF! 6.4 1 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 733,181.08 825,349.39
6.4.1 Bahan 628,901.08 706,809.39
#REF! 230 Kg Portland Semen 1,292.50 1,402.50 297,275.00 322,575.00
#REF! 893 kg Pasir Beton 221.43 242.86 197,735.71 216,871.43
#REF! 1,027 kg Kerikil (maksimum 30 mm) 130.37 162.96 133,890.37 167,362.96
#REF! 200 ltr Air 0.00 0.00 - -
6.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 873,201.83 979,245.32
6.5.1 Bahan 723,791.83 809,475.32
326 Kg Portland Semen 1,292.50 1,402.50 421,355.00 457,215.00
760 Kg Pasir Beton 221.43 242.86 168,285.71 184,571.43
1,029 Kg Kerikil (maksimum 30 mm) 130.37 162.96 134,151.11 167,688.89
215 ltr Air 0.00 0.00 - -
6.6 1 m3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61 900,646.14 1,008,993.39
6.6.1 Bahan 751,236.14 839,223.39
352 Kg Portland Semen 1,292.50 1,402.50 454,960.00 493,680.00
731 Kg Pasir Beton 221.43 242.86 161,864.29 177,528.57
1,031 Kg Kerikil (maksimum 30 mm) 130.37 162.96 134,411.85 168,014.81
215 ltr Air 0.00 0.00 - -
6.7 1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 919,982.42 1,030,234.01
6.7.1 Bahan 770,572.42 860,464.01
371 Kg Portland Semen 1,292.50 1,402.50 479,517.50 520,327.50
698 Kg Pasir Beton 221.43 242.86 154,557.14 169,514.29
1,047 Kg Kerikil (maksimum 30 mm) 130.37 162.96 136,497.78 170,622.22
215 ltr Air 0.00 0.00 - -
6.8 1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 934,413.39 1,045,705.66
6.8.1 Bahan 785,003.39 875,935.66
384 Kg Portland Semen 1,292.50 1,402.50 496,320.00 538,560.00
692 Kg Pasir Beton 221.43 242.86 153,228.57 168,057.14
1,039 Kg Kerikil (maksimum 30 mm) 130.37 162.96 135,454.81 169,318.52
215 ltr Air 0.00 0.00 - -
6.9 1 m3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 959,382.14 1,072,499.29
6.9.1 Bahan 809,972.14 902,729.29
406 Kg Portland Semen 1,292.50 1,402.50 524,755.00 569,415.00
684 kg Pasir Beton 221.43 242.86 151,457.14 166,114.29
1,026 kg Kerikil (maksimum 30 mm) 130.37 162.96 133,760.00 167,200.00
215 ltr Air 0.00 0.00 - -
6.10 1 m3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 967,113.51 1,080,773.40
6.10.1 Bahan 817,703.51 911,003.40
413 Kg Portland Semen 1,292.50 1,402.50 533,802.50 579,232.50
681 Kg Pasir Beton 221.43 242.86 150,792.86 165,385.71
1,021 Kg Kerikil (maksimum 30 mm) 130.37 162.96 133,108.15 166,385.19
215 ltr Air 0.00 0.00 - -
6.11 1 m3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49 1,036,967.24 1,158,302.53
6.11.1 Bahan 846,917.24 942,352.53
439 Kg Portland Semen 1,292.50 1,402.50 567,407.50 615,697.50
670 Kg Pasir Beton 221.43 242.86 148,357.14 162,714.29
1,006 Kg Kerikil (maksimum 30 mm) 130.37 162.96 131,152.59 163,940.74
215 ltr Air 0.00 0.00 - -
6.12 1 m3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48 1,047,153.23 1,169,218.68
6.12.1 Bahan 857,103.23 953,268.68
448 Kg Portland Semen 1,292.50 1,402.50 579,040.00 628,320.00
667 Kg Pasir Beton 221.43 242.86 147,692.86 161,985.71
1,000 Kg Kerikil (maksimum 30 mm) 130.37 162.96 130,370.37 162,962.96
215 ltr Air 0.00 0.00 - -
6.28 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 2,981,635.00 3,166,475.00
6.28.1 Bahan 2,374,385.00 2,479,975.00
0.2 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 9,240.00 11,180.00
1.5 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 19,800.00 24,750.00
0.4 Ltr Minyak Bekisting 24,200.00 24,200.00 9,680.00 9,680.00
157.5 Kg Besi Beton Polos 9,900.00 9,900.00 1,559,250.00 1,559,250.00
2.25 Kg Kawat Beton 14,300.00 18,700.00 32,175.00 42,075.00
336 Kg Portland Semen 1,292.50 1,402.50 434,280.00 471,240.00
0.54 m3 Pasir Beton 310,000.00 340,000.00 167,400.00 183,600.00
0.81 m3 Kerikil Beton 176,000.00 220,000.00 142,560.00 178,200.00
#REF! 6.29 1 m3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 3,606,184.00 3,806,253.00
6.29.1 Bahan 2,919,534.00 3,030,753.00
#REF! 0.27 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 12,474.00 15,093.00
#REF! 2 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 26,400.00 33,000.00
#REF! 0.6 Ltr Minyak Bekisting 24,200.00 24,200.00 14,520.00 14,520.00
#REF! 210 Kg Besi Beton Polos 9,900.00 9,900.00 2,079,000.00 2,079,000.00
#REF! 3 Kg Kawat Beton 14,300.00 18,700.00 42,900.00 56,100.00
#REF! 336 Kg Portland Semen 1,292.50 1,402.50 434,280.00 471,240.00
#REF! 0.54 m3 Pasir Beton 310,000.00 340,000.00 167,400.00 183,600.00
#REF! 0.81 m3 Kerikil Beton 176,000.00 220,000.00 142,560.00 178,200.00
6.30 1 m3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 6,588,980.00 7,331,320.00
6.30.1 Bahan 5,668,720.00 6,292,750.00
0.4 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 18,480.00 22,360.00
4 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 52,800.00 66,000.00
2 Ltr Minyak Bekisting 24,200.00 24,200.00 48,400.00 48,400.00
315 kg Besi Beton Polos 9,900.00 9,900.00 3,118,500.00 3,118,500.00
4.5 kg Kawat Beton 14,300.00 18,700.00 64,350.00 84,150.00
336 Kg Portland Semen 1,292.50 1,402.50 434,280.00 471,240.00
0.54 m3 Pasir Beton 310,000.00 340,000.00 167,400.00 183,600.00
0.81 m3 Kerikil Beton 176,000.00 220,000.00 142,560.00 178,200.00
0.15 m3 Kayu Klas II Balok 5,500,000.00 7,700,000.00 825,000.00 1,155,000.00
3.5 Lbr Plywood 9 mm 95,700.00 115,800.00 334,950.00 405,300.00
20 Btg Dolken diameter 8 / 4rm 23,100.00 28,000.00 462,000.00 560,000.00
6.31 1 m3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 5,020,104.00 5,830,208.00
6.31.1 Bahan 4,369,444.00 4,927,788.00
0.32 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 14,784.00 17,888.00
3.2 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 42,240.00 52,800.00
1.6 Ltr Minyak Bekisting 24,200.00 24,200.00 38,720.00 38,720.00
210 Kg Besi Beton Polos 9,900.00 9,900.00 2,079,000.00 2,079,000.00
3 Kg Kawat Beton 14,300.00 18,700.00 42,900.00 56,100.00
336 Kg Portland Semen 1,292.50 1,402.50 434,280.00 471,240.00
0.54 m3 Pasir Beton 310,000.00 340,000.00 167,400.00 183,600.00
0.81 m3 Kerikil Beton 176,000.00 220,000.00 142,560.00 178,200.00
0.14 m3 Kayu Klas II Balok 5,500,000.00 7,700,000.00 770,000.00 1,078,000.00
2.8 Lbr Plywood 9 mm 95,700.00 115,800.00 267,960.00 324,240.00
16 Btg Dolken diameter 8 / 4rm 23,100.00 28,000.00 369,600.00 448,000.00
6.32 1 m3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 4,750,869.00 5,424,863.00
6.32.1 Bahan 4,098,569.00 4,688,013.00
0.32 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 14,784.00 17,888.00
3.2 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 42,240.00 52,800.00
1.6 Ltr Minyak Bekisting 24,200.00 24,200.00 38,720.00 38,720.00
157.5 Kg Besi Beton Polos 9,900.00 9,900.00 1,559,250.00 1,559,250.00
2.25 Kg Kawat Beton 14,300.00 18,700.00 32,175.00 42,075.00
336 Kg Portland Semen 1,292.50 1,402.50 434,280.00 471,240.00
0.54 m3 Pasir Beton 310,000.00 340,000.00 167,400.00 183,600.00
0.81 m3 Kerikil Beton 176,000.00 220,000.00 142,560.00 178,200.00
0.12 m3 Kayu Klas II Balok 5,500,000.00 7,700,000.00 660,000.00 924,000.00
2.8 Lbr Plywood 9 mm 95,700.00 115,800.00 267,960.00 324,240.00
32 Btg Dolken diameter 8 / 4rm 23,100.00 28,000.00 739,200.00 896,000.00
6.32.2 Tenaga 652,300.00 736,850.00
5.3 OH Pekerja 70,000.00 80,000.00 371,000.00 424,000.00
0.275 OH Tukang batu 90,000.00 100,000.00 24,750.00 27,500.00
1.3 OH Tukang Kayu 90,000.00 100,000.00 117,000.00 130,000.00
1.05 OH Tukang Besi 90,000.00 100,000.00 94,500.00 105,000.00
0.265 OH Kepala Tukang 90,000.00 100,000.00 23,850.00 26,500.00
0.265 OH Mandor 80,000.00 90,000.00 21,200.00 23,850.00
6.33 1 m3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) 4,782,103.00 5,504,091.00
6.33.1 Bahan 4,130,073.00 4,767,541.00
0.24 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 11,088.00 13,416.00
3.2 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 42,240.00 52,800.00
1.6 Ltr Minyak Bekisting 24,200.00 24,200.00 38,720.00 38,720.00
157.5 Kg Besi Beton Polos 9,900.00 9,900.00 1,559,250.00 1,559,250.00
2.25 Kg Kawat Beton 14,300.00 18,700.00 32,175.00 42,075.00
336 Kg Portland Semen 1,292.50 1,402.50 434,280.00 471,240.00
0.54 m3 Pasir Beton 310,000.00 340,000.00 167,400.00 183,600.00
0.81 m3 Kerikil Beton 176,000.00 220,000.00 142,560.00 178,200.00
0.16 m3 Kayu Klas II Balok 5,500,000.00 7,700,000.00 880,000.00 1,232,000.00
2.8 Lbr Plywood 9 mm 95,700.00 115,800.00 267,960.00 324,240.00
24 Btg Dolken diameter 8 / 4rm 23,100.00 28,000.00 554,400.00 672,000.00
6.33.2 Tenaga 652,030.00 736,550.00
5.3 OH Pekerja 70,000.00 80,000.00 371,000.00 424,000.00
0.275 OH Tukang batu 90,000.00 100,000.00 24,750.00 27,500.00
1.3 OH Tukang Kayu 90,000.00 100,000.00 117,000.00 130,000.00
6.34 1 m3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 4,824,840.00 5,383,925.00
6.34.1 Bahan 4,086,480.00 4,550,655.00
0.25 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 11,550.00 13,975.00
3 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 39,600.00 49,500.00
1.2 Ltr Minyak Bekisting 24,200.00 24,200.00 29,040.00 29,040.00
210 Kg Besi Beton Polos 9,900.00 9,900.00 2,079,000.00 2,079,000.00
3 Kg Kawat Beton 14,300.00 18,700.00 42,900.00 56,100.00
336 Kg Portland Semen 1,292.50 1,402.50 434,280.00 471,240.00
0.54 m3 Pasir Beton 310,000.00 340,000.00 167,400.00 183,600.00
0.81 m3 Kerikil Beton 176,000.00 220,000.00 142,560.00 178,200.00
0.105 m3 Kayu Klas II Balok 5,500,000.00 7,700,000.00 577,500.00 808,500.00
2.5 Lbr Plywood 9 mm 95,700.00 115,800.00 239,250.00 289,500.00
14 Btg Dolken diameter 8 / 4rm 23,100.00 28,000.00 323,400.00 392,000.00
6.34.2 Tenaga 738,360.00 833,270.00
5.65 OH Pekerja 70,000.00 80,000.00 395,500.00 452,000.00
0.275 OH Tukang batu 90,000.00 100,000.00 24,750.00 27,500.00
1.56 OH Tukang Kayu 90,000.00 100,000.00 140,400.00 156,000.00
1.4 OH Tukang Besi 90,000.00 100,000.00 126,000.00 140,000.00
0.323 OH Kepala Tukang 90,000.00 100,000.00 29,070.00 32,300.00
0.283 OH Mandor 80,000.00 90,000.00 22,640.00 25,470.00
#REF! 6.35 1 m' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm 58,441.90 62,258.30
6.35.1 Bahan 39,181.90 40,448.30
#REF! 0.002 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 92.40 111.80
#REF! 0.01 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 132.00 165.00
#REF! 3 Ltr Besi Beton Polos 9,900.00 9,900.00 29,700.00 29,700.00
#REF! 0.045 Kg Kawat Beton 14,300.00 18,700.00 643.50 841.50
#REF! 4 Kg Portland Semen 1,292.50 1,402.50 5,170.00 5,610.00
#REF! 0.006 m3 Pasir Beton 310,000.00 340,000.00 1,860.00 2,040.00
#REF! 0.009 m3 Kerikil Beton 176,000.00 220,000.00 1,584.00 1,980.00
6.35.2 Tenaga 19,260.00 21,810.00
#REF! 0.18 OH Pekerja 70,000.00 80,000.00 12,600.00 14,400.00
#REF! 0.02 OH Tukang batu 90,000.00 100,000.00 1,800.00 2,000.00
#REF! 0.02 OH Tukang Kayu 90,000.00 100,000.00 1,800.00 2,000.00
#REF! 0.02 OH Tukang Besi 90,000.00 100,000.00 1,800.00 2,000.00
#REF! 0.006 OH Kepala Tukang 90,000.00 100,000.00 540.00 600.00
#REF! 0.009 OH Mandor 80,000.00 90,000.00 720.00 810.00
#REF! 6.36 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 81,096.35 87,156.45
6.36.1 Bahan 49,296.35 51,146.45
#REF! 0.003 m3 Kayu Klas III (Terentang) 46,200.00 55,900.00 138.60 167.70
#REF! 0.02 Kg Paku Biasa 2" - 5" 13,200.00 16,500.00 264.00 330.00
#REF! 3.6 Ltr Besi Beton Polos 9,900.00 9,900.00 35,640.00 35,640.00
#REF! 0.05 Kg Kawat Beton 14,300.00 18,700.00 715.00 935.00
#REF! 5.5 Kg Portland Semen 1,292.50 1,402.50 7,108.75 7,713.75
#REF! 0.009 m3 Pasir Beton 310,000.00 340,000.00 2,790.00 3,060.00
#REF! 0.015 m3 Kerikil Beton 176,000.00 220,000.00 2,640.00 3,300.00
6.6 1 m'
Pasang Genteng Bubung Plentong Besar 76,322.40 84,760.00
6.6.1 Bahan 28,362.40 30,580.00
4 Buah Genteng Bubung Plentong Besar 3,300.00 3,300.00 13,200.00 13,200.00
8 Kg Portland Semen 1,292.50 1,402.50 10,340.00 11,220.00
0.032 m3 Pasir Pasang 150,700.00 192,500.00 4,822.40 6,160.00
6.6.2 Tenaga 47,960.00 54,180.00
0.4 OH Pekerja 70,000.00 80,000.00 28,000.00 32,000.00
0.2 OH Tukang Kayu 90,000.00 100,000.00 18,000.00 20,000.00
0.02 OH Kepala Tukang 90,000.00 100,000.00 1,800.00 2,000.00
0.002 OH Mandor 80,000.00 90,000.00 160.00 180.00
6.1 1 m2 Memasang Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm 30,052.00 32,405.00
6.1.1 Bahan 20,702.00 21,945.00
1.1 Lbr Plat Asbes 18,700.00 19,800.00 20,570.00 21,780.00
0.01 Kg Paku 13,200.00 16,500.00 132.00 165.00
6.5 1 m2 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm 47,808.50 56,395.00
6.5.1 Bahan 30,508.50 36,945.00
0.375 Lbr Tripleks (4 mm) 80,300.00 97,200.00 30,112.50 36,450.00
0.03 Kg Paku Tripleks 13,200.00 16,500.00 396.00 495.00
#REF! 6.7 1 m2 Memasng Langit-langit Gypsu Board, Uk (120x240) tebal 9 mm 34,856.00 45,652.00
6.7.1 Bahan 22,506.00 31,702.00
#REF! 0.364 Lbr Gypsum Board 60,500.00 60,500.00 22,022.00 22,022.00
#REF! 0.11 Kg Paku Sekrup 4,400.00 88,000.00 484.00 9,680.00
6.9 1 m2 Memasang Langit-langit Akuatik Uk (60x120) cm & Rangka Allumunium 122,650.00 135,800.00
6.9.1 Bahan 36,150.00 38,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 0.00 0.00 - -
X PEKERJAAN SANITASI
6.1 1 Unit Memasang Closet Duduk / Mono Blok 1,217,390.00 1,263,000.00
6.1.1 Bahan 874,500.00 874,500.00
1 Buah Kloset Duduk / Monoblok 825,000.00 825,000.00 825,000.00 825,000.00
0.06 Kelengkapan 6% dari harga Kloset 825,000.00 825,000.00 49,500.00 49,500.00
6.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,169,310.00 1,354,050.00
6.8.1 Bahan 428,310.00 517,050.00
0.4 m3 Batu Bata 487,500.00 562,500.00 195,000.00 225,000.00
120 Kg Portland Semen 1,292.50 1,402.50 155,100.00 168,300.00
0.3 m3 Pasir Pasang 150,700.00 192,500.00 45,210.00 57,750.00
360 buah Porselen 11 x 11 cm 0.00 0.00 - -
6 Kg Semen Nat 5,500.00 11,000.00 33,000.00 66,000.00
6.33 1 Buah Memasang Bak Cuci Piring Stainles Steel 161,170.00 304,835.00
6.33.1 Bahan 129,250.00 269,300.00
1 Buah Bak Cuci Stainles Steel 110,000.00 192,500.00 110,000.00 192,500.00
1 Set Water Drain & assesories 19,250.00 76,800.00 19,250.00 76,800.00
6.33.2 Tenaga 31,920.00 35,535.00
0.03 OH Pekerja 70,000.00 80,000.00 2,100.00 2,400.00
0.3 OH Tukang Ledeng 90,000.00 100,000.00 27,000.00 30,000.00
0.03 OH Kepala Tukang 90,000.00 100,000.00 2,700.00 3,000.00
0.0015 OH Mandor 80,000.00 90,000.00 120.00 135.00
6.18 1 m' Memasang Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 161,708.00 168,107.50
6.18.1 Bahan 108,658.00 108,707.50
1.05 Lbr Seng Plaat 18,700.00 18,700.00 19,635.00 19,635.00
0.015 Kg Paku Biasa 1 - 2,5 cm 13,200.00 16,500.00 198.00 247.50
0.019 m3 Kayu Papan Klas II atau III 4,675,000.00 4,675,000.00 88,825.00 88,825.00
6.19 1 m' Memasang Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm 63,247.00 78,555.00
6.19.1 Bahan 22,407.00 32,835.00
1.05 Lbr Seng Plaat 16,500.00 26,400.00 17,325.00 27,720.00
0.01 Kg Paku Biasa 1 - 2,5 cm 13,200.00 16,500.00 132.00 165.00
0.5 Kg Besi strip 9,900.00 9,900.00 4,950.00 4,950.00
6.57 1 m2 Memasang Dinding Batu Paros / Batu Tempel Hitam 106,911.38 120,866.88
6.57.1 Bahan 20,461.38 23,216.88
1.10 m2 Batu Paros 0.00 0.00 - -
11.75 Kg Portland Semen 1,292.50 1,402.50 15,186.88 16,479.38
0.035 m3 Pasir Pasang 150,700.00 192,500.00 5,274.50 6,737.50
6.63 1 m' Memasang Plint Kayu Klas II Ukuran 2x10 cm 39,245.00 41,825.50
6.63.1 Bahan 18,485.00 18,485.50
0.003 m3 Papan Kayu Klas II 6,160,000.00 6,160,000.00 18,480.00 18,480.00
0.05 kg Paku Sekrup 5 cm 100.00 110.00 5.00 5.50
6.2 1 m2 Mencuci Bidang Permukaan Tembok yang Pernah dicat 10,700.00 12,225.00
6.2.1 Bahan - -
0.05 Kg Sabun 0.00 0.00 - -
6.3 1 m2 Mengerok Karat Cat Lama permukaan Baja dg cara manual 10,700.00 12,225.00
6.3.1 Bahan - -
0.05 Kg Sabun 0.00 0.00 - -
6.12 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 7,733.75 8,828.75
6.12.1 Bahan 253.75 288.75
0.35 Ltr Residu atau Ter 725.00 825.00 253.75 288.75
#REF! 6.14 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 25,767.00 50,445.00
2 lap. Cat Penutup)
6.14.1 Bahan 17,930.00 41,690.00
#REF! 0.1 Kg Plamir 7,700.00 49,500.00 770.00 4,950.00
#REF! 0.1 Kg Cat Dasar 14,300.00 95,700.00 1,430.00 9,570.00
#REF! 0.26 Kg Cat Penutup 2 kali 60,500.00 104,500.00 15,730.00 27,170.00
6.14.2 Tenaga 7,837.00 8,755.00
#REF! 0.02 OH Pekerja 70,000.00 80,000.00 1,400.00 1,600.00
#REF! 0.063 OH Tukang Cat 90,000.00 100,000.00 5,670.00 6,300.00
#REF! 0.0063 OH Kepala Tukang 90,000.00 100,000.00 567.00 630.00
#REF! 0.0025 OH Mandor 80,000.00 90,000.00 200.00 225.00
6.15 1 m2 Pengecat Tembok Lama (1lap.Plamir, 2lap Cat Penutup) 10,718.00 30,911.00
6.15.1 Bahan 4,400.00 23,826.00
0.1 Kg Cat Dasar 14,300.00 95,700.00 1,430.00 9,570.00
0.18 Kg Cat Penutup 2 kali 16,500.00 79,200.00 2,970.00 14,256.00
6.21 1 m2 Pengecatan Permukaan Baja dg Meni Besi & Perancah 41,963.40 48,176.80
6.21.1 Bahan 1,588.40 2,751.80
0.1 Kg Meni Besi 14,300.00 22,000.00 1,430.00 2,200.00
0.01 Kg Perekat / Lem 6,600.00 44,000.00 66.00 440.00
0.002 m3 Perancah Kayu 46,200.00 55,900.00 92.40 111.80
6.24 1 m2 Pengecatan Permukaan Baja lapis Seng (Galvanis) secara 156,160.00 185,028.00
Manual sistem 3 lap. Cat Konvensional dg Tebal 200 μm
6.24.1 Bahan 6,160.00 17,028.00
0.11 Kg Cat dasar 11,000.00 47,300.00 1,210.00 5,203.00
0.17 Kg Cat Antara 11,000.00 47,300.00 1,870.00 8,041.00
0.08 Kg Cat Penutup 38,500.00 47,300.00 3,080.00 3,784.00
6.24.2 Tenaga 150,000.00 168,000.00
0.50 OH Pekerja 70,000.00 80,000.00 35,000.00 40,000.00
0.80 OH Tukang Cat 90,000.00 100,000.00 72,000.00 80,000.00
0.30 OH Kepala Tukang 90,000.00 100,000.00 27,000.00 30,000.00
0.20 OH Mandor 80,000.00 90,000.00 16,000.00 18,000.00