LAPORAN MINGGUAN

PERIODE MINGGU KE- 1


( 22 November s/d 26 November 2024 )

PEKERJAAN :
PERAWATAN RUMAH RUSUN KELUARGA TNI/POLRI (POLRES MERAUKE)

LOKASI PEKERJAAN :
JL. RAYA MERDEKA KAB. MERAUKE, POV. PAPUA (POLRES MERAUKE)
PROVINSI PAPUA

PENYEDIA JASA KONSTRUKSI :

KONSULTAN PENGAWAS :

CV. MEGA DALLES ENGINEERING

TAHUN ANGGARAN :

2023
PEKERJAAN : PERAWATAN RUMAH RUSUN KELUARGA TNI/POLRI (POLRES MERAUKE)
TIPE PROTOTYPE : RUMAH SUSUN T-36 KDS-D
JUMLAH LANTAI : 3 LANTAI
LOKASI PEKERJAAN : JL. RAYA MERDEKA KAB. MERAUKE, POV. PAPUA (POLRES MERAUKE)
PENYEDIA JASA KONSTRUKSI : CV. DUNSADA ENGINEERING
TAHUN ANGGARAN : 2023
LAPORAN KEMAJUAN PEKERJAAN MINGGU KE - 1
( 22 November s/d 26 November 2024 )

Progres Mingguan

NO. URAIAN PEKERJAAN s/d Minggu Lalu MINGGU INI s/d MINGGU INI PERSENTASE
JUMLAH BOBOT
BOBOT BOBOT BOBOT TERHADAP ITEM
HARGA (%)
(%) ( %) (%) PEKERJAAN ( % )

I. PEKERJAAN PERSIAPAN STANDAR DAN PEKERJAAN RK3K KONSTRUKSI


I.A PEKERJAAN PERSIAPAN STANDAR 13.797.790,00 1,96 - - 0,00%

I.B. PEKERJAAN RK3K KONSTRUKSI 89.321.000,00 12,69 - - 0,00%

II. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


II. A PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDART
A.1 LANTAI 1 102.688.436,98 14,59 - - 0,00%

A.2 LANTAI 2 79.218.185,09 11,25 - - 0,00%

A.3. LANTAI 3 84.058.610,47 11,94 - - 0,00%

A.4. LANTAI ATAP 14.894.868,14 2,12 - - 0,00%

A.5. PEKERJAAN UTILITAS 60.076.664,26 8,53 - - 0,00%

A.6. PEKERJAAN SISTEM PENTANAHAN 30.051.173,75 4,27 - - 0,00%

B. PEKERJAAN MEKANIKAL & ELEKTRIKAL NON STANDART


B.1. PEKERJAAN PEMADAM KEBAKARAN 4.375.336,75 0,62 - - 0,00%

B.2 PEKERJAAN VENTILASI UDARA 80.788.812,00 11,48 - - 0,00%

B.3. PEKERJAAN INSTALASI ELEKTRONIK 118.109.962,70 16,78 - - 0,00%

B.4. PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN)


I PEKERJAAN INSTALASI PLAMBING 22.330.857,48 3,17 - - 0,00%

II. PENYAMBUNGAN DAYA PLN - - -

III PEKERJAAN INSTALASI KABEL FEEDER 4.286.610,56 0,61 - - 0,00%

JUMLAH TOTAL 703.998.308,18 100,00 - - 0,00%


PPN 11% 77.439.813,90
JUMLAH TOTAL (TERMASUK PPN) 781.438.122,08
PEMBULATAN 781.438.000,00

Merauke, 26 November 2023


Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :
Pejabat Pembuat Komitmen KONSULTAN PENGAWAS PENYEDIA JASA KONSTRUKSI
Rumah Susun dan Rumah Khusus CV. MEGA DALLES ENGINEERING CV. DUNSADA ENGINEERING
Paket Perawatan Rumah Susun Polres Marauke

ADOLF LEONARD BATLOLONA, S.T MALIK ASO DEREK WAINYAMBE, SH


NIP. 19740111 200502 1 004 Direktur Direktur

Page 1
PEKERJAAN : PERAWATAN RUMAH RUSUN KELUARGA TNI/POLRI (POLRES MERAUKE)
TIPE PROTOTYPE : RUMAH SUSUN T-36 KDS-D
JUMLAH LANTAI : 3 LANTAI
LOKASI PEKERJAAN : JL. RAYA MERDEKA KAB. MERAUKE, POV. PAPUA (POLRES MERAUKE)
PENYEDIA JASA KONSTRUKSI : CV. DUNSADA ENGINEERING
TAHUN ANGGARAN : 2023

LAPORAN KEMAJUAN PEKERJAAN MINGGU KE - 1

( 22 November s/d 26 November 2024 )

KONTRAK PROGRES MINGGU INI


s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

I. PEKERJAAN PERSIAPAN STANDAR DAN PEKERJAAN RK3K KONSTRUKSI


I.A PEKERJAAN PERSIAPAN STANDAR 13.797.790,00 1,96
1, Papan Nama Proyek ls 1,00 1,00 500.000,00 500.000,00 0,07 - 1,00 0,07 1,00 0,07 100,00%
2, Foto Proyek Phase 3,00 1,00 350.000,00 1.050.000,00 0,15 - 1,00 0,05 1,00 0,05 33,33%
3, Air Kerja Ls 1,00 1,00 6.247.790,00 6.247.790,00 0,89 - 1,00 0,89 1,00 0,89 100,00%
4, Listrik Kerja Ls 1,00 1,00 6.000.000,00 6.000.000,00 0,85 - 1,00 0,85 1,00 0,85 100,00%

I.B. PEKERJAAN RK3K KONSTRUKSI 89.321.000,00 12,69


1, Penyiapan RK3K terdiri atas: LS 1,00 1,00 1.500.000,00 1.500.000,00 0,21 0,30 0,06 0,30 0,06 30,00%
a Pembuatan Manual, Prosedur, Instruksi Kerja, Ijin Kerja
b Pembuatan Kartu Identitas Pekerja (KIP);

2, Sosialisasi dan Promosi K3 terdiri atas:


a Induksi K3 (Safety Induction ); khusus untukpekerja baru Org 55,00 1,00 200.000,00 11.000.000,00 1,56 22,00 0,63 22,00 0,63 40,00%
b Pengarahan K3 (safety briefing) : Pertemuan Keselamatan (Safety Talk dan/atau Tool Box Meeting) ; setiap hari Org 55,00 1,00 200.000,00 11.000.000,00 1,56 22,00 0,63 22,00 0,63 40,00%
Pelatihan K3;
- Bekerja di Ketinggian
- K3 Peralatan Konstruksi & Penggunaan bahan Kimia (MSDS)
- Analysis Keselamatan Pekerjaan
- Perilaku Berbasis Keselamatan (Budaya K3)
- P3K
d Simulasi K3; Org 14,00 1,00 300.000,00 4.200.000,00 0,60 7,00 0,30 7,00 0,30 50,00%
e Spanduk (banner) ; Lb 5,00 1,00 500.000,00 2.500.000,00 0,36 3,00 0,21 3,00 0,21 60,00%
f Poster; Lb 3,00 1,00 500.000,00 1.500.000,00 0,21 1,00 0,07 1,00 0,07 33,33%
g Papan Informasi K3. Bh 1,00 1,00 600.000,00 600.000,00 0,09 - - - 0,00%

3, Alat Pelindung Kerja terdiri atas:


a Jaring Pengaman(Polynet/Safety Net);
b Tali Keselamatan (Life Line); Ls 2,00 1,00 750.000,00 1.500.000,00 0,21 - - - 0,00%
c Penahan Jatuh (Safety Deck); Ls 1,00 1,00 1.375.000,00 1.375.000,00 0,20 - - - 0,00%
d Pagar Pengaman (Guard Railling); Ls 1,00 1,00 5.460.000,00 5.460.000,00 0,78 - - - 0,00%
e Pembatas Area (Restricted Area ). Ls 1,00 1,00 569.000,00 569.000,00 0,08 - - - 0,00%

4, Alat Pelindung Diri terdiri atas:


a Topi Pelindung (Safety Helmet) ; Bh 55,00 1,00 175.000,00 9.625.000,00 1,37 - - - 0,00%
b Pelindung Mata (Goggles, Spectacles); Psg 17,00 1,00 70.000,00 1.190.000,00 0,17 - - - 0,00%
c Tameng Muka (Face Shield); Bh 14,00 1,00 45.000,00 630.000,00 0,09 - - - 0,00%
d Masker Selam (Breathing Apparatus); Bh 1,00 160.000,00 -
e Pelindung Telinga (Ear Plug, Ear Muff); Psg 17,00 1,00 87.000,00 1.479.000,00 0,21 - - - 0,00%
f Pelindung Pernafasan Dan Mulut (Masker); Bh 55,00 1,00 50.000,00 2.750.000,00 0,39 - - - 0,00%
g Sarung Tangan (Safety Gloves); Psg 17,00 1,00 28.000,00 476.000,00 0,07 - - - 0,00%
h Sepatu Keselamatan (Safety Shoes); untuk Staf Psg 17,00 1,00 250.000,00 4.250.000,00 0,60 - - - 0,00%
h Sepatu Keselamatan (Rubber Safety Shoes and toe cap) Psg 55,00 1,00 173.000,00 9.515.000,00 1,35 - - - 0,00%
i Penunjang Seluruh Tubuh (Full Body Harness); Bh 5,00 1,00 222.000,00 1.110.000,00 0,16 - - - 0,00%

Page 2
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

j Jaket Pelampung (Life Vest); -


k Rompi Keselamatan (Safety Vest); Bh 55,00 1,00 57.000,00 3.135.000,00 0,45 - - - 0,00%
l Celemek (Apron/Coveralls); Bh -
m Pelindung Jatuh (Fall Arrester); Bh 5,00 1,00 459.000,00 2.295.000,00 0,33 - - - 0,00%

7, P3K
a Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban, dll) Ls 1,00 1,00 1.000.000,00 1.000.000,00 0,14 1,00 0,14 1,00 0,14 100,00%
b Ruang P3K (Tempat Tidur Pasien, Stetoskop, Timbangan Berat Badan, Tensi Meter, dll); Ls 1,00 1,00 1.000.000,00 1.000.000,00 0,14 1,00 0,14 1,00 0,14 100,00%

8, Rambu-rambu : LS 1,00 1,00 2.650.000,00


a Rambu Petunjuk; - - - 0,00%
b Rambu Larangan; - - - 0,00%
c Rambu Peringatan; - - - 0,00%
d Rambu Kewajiban; - - - 0,00%
e Rambu Informasi; - - - 0,00%
f Rambu Pekerjaan Sementara; - - - 0,00%
g Tongkat Pengatur Lalu Lintas (Warning Lights Stick) ; - - - 0,00%
h Kerucut Lalu Lintas (Traffic Cone) ; - - - 0,00%
i Lampu Putar (Rotary Lamp ); - - - 0,00%
j Lampu Selang Lalu Lintas. - - - 0,00%

9, Lain- Lain Terkait Pengendalian Risiko K3


Alat Pemadam Api Ringan (APAR); 10Kg Bh 2,00 1,00 781.000,00 1.562.000,00 0,22 - - - 0,00%
Sirine; Bh 4,00 1,00 1.000.000,00 4.000.000,00 0,57 - - - 0,00%
Bendera K3; Bh 2,00 1,00 300.000,00 600.000,00 0,09 - - - 0,00%
Jalur Evakuasi (Escape Route ); Ls 1,00 1,00 500.000,00 500.000,00 0,07 - - - 0,00%
Lampu Darurat (Emergency Lamp ); Bh 2,00 1,00 500.000,00 1.000.000,00 0,14 - - - 0,00%
Program Inspeksi Dan Audit Internal; Org 2,00 1,00 1.000.000,00 2.000.000,00 0,28 - - - 0,00%
Pelaporan dan Penyelidikan Insiden. Ls 1,00 1,00 1.000.000,00

II. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


II. A PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDART
A.1 LANTAI 1
1, PEMIPAAN AIR BERSIH 3.732.418,69 0,53
Pipa PVC AW (Incl. Fitting & Accessories)
- PVC AW dia. 15 m 314,00 42.307,65 - - - 0,00%
- PVC AW dia. 20 m 57,00 - 44.475,75 2.535.117,75 0,36 - - - 0,00%
- PVC AW dia. 25 m 4,00 48.780,90 195.123,60 0,03 - - - 0,00%
- PVC AW dia. 40 m 110,00 74.333,70 - - - 0,00%
- PVC AW dia. 50 (Riser dari Tangki Air Atas) m 16,00 80.661,49 - - - 0,00%
Peralatan Katup-katup
(Ball Valve & Gate Valve)
- dia. 25 bh 2,00 314.755,04 629.510,08 0,09 - - - 0,00%
- dia. 40 bh 1,00 372.667,26 372.667,26 0,05 - - - 0,00%
- Meter Air c/w BV dia. 20 bh 12,00 378.183,76 - - - 0,00%

2, PEMIPAAN AIR KOTOR & AIR BEKAS 4.617.116,90 0,66


Pipa PVC AW (Incl. Fitting & Accessories)
- dia. 150 ( horisontal pipa air kotor ) m 108,00 405.530,10 - - - 0,00%
- dia. 150 ( horisontal pipa air bekas) m 105,00 405.530,10 - - - 0,00%
- dia. 150 ( riser pipa air kotor ) m 53,00 405.530,10 - - - 0,00%
- dia. 100 ( riser pipa air bekas ) m 51,00 166.308,75 - - - 0,00%
- dia. 100 m 51,00 166.308,75 - - - 0,00%
- dia. 80 m 48,00 104.526,11 - - - 0,00%
- dia. 50 m 49,00 80.661,49 - - - 0,00%
- dia. 20 ( pipa drain ac + isolasi ) m 36,00 66.713,63 2.401.690,50 0,34 - - - 0,00%
Clean Out (CO) - - - 0,00%
- CO, dia. 150 bh 6,00 237.309,80 1.423.858,80 0,20 - - - 0,00%
- CO, dia. 100 bh 4,00 197.891,90 791.567,60 0,11 - - - 0,00%
- Portable Grease Trap bh 12,00 597.055,81 - - - 0,00%

3, PEMIPAAN AIR HUJAN 7.714.463,85 1,10


Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- dia. 150 ( pipa horisontal ) M 104,00 405.530,10 - - - 0,00%

Page 3
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- dia. 100 ( pipa tegak ) M 16,00 166.308,75 2.660.940,00 0,38 - - - 0,00%


- dia. 80 ( riser pipa cucian ) M 36,00 104.526,11 3.762.940,05 0,53 - - - 0,00%
- dia. 50 M 16,00 80.661,49 1.290.583,80 0,18 - - - 0,00%

4, PEMIPAAN VENT 5.029.808,40 0,71


Pipa PVC Kelas D (Incl. Fitting & Accessories)
- Dia. 80 ( pipa riser ) M 48,00 104.787,68 5.029.808,40 0,71 - - - 0,00%
- Dia. 32 M 144,00 70.934,74 - - - 0,00%

5, INSTALASI PANEL 7.637.995,45 1,08


Pengadaan dan pemasangan PP-LT.1 unit 1,00 7.637.995,45 7.637.995,45 1,08 - - - 0,00%
dengan komponen panel, sbb : - - - 0,00%
- MCCB 3P, 75 A - - - 0,00%
- MCB 1P, 6 A - - - 0,00%
- Ampere-meter 50/5 A - - - 0,00%
- Volt-meter 0-500 Volt - - - 0,00%
- Volt Selector Switch - - - 0,00%
- Fuse 2 A - - - 0,00%
- Indicator Lamp - - - 0,00%
- Rel MCB 3P - - - 0,00%
- Cu Bar 5 x 63 A - - - 0,00%
- Accessories & Termination - - - 0,00%
- Box Panel - - - 0,00%
- KW-meter/1ph/6A bh 12,00 380.610,92 - - - 0,00%
Pengadaan dan pemasangan P-UNIT , dengan komponen panel sbb : unit 12,00 770.855,65 - - - 0,00%
- MCB 1P, 6 A : 1 bh - - - 0,00%
- MCB 1P, 6 A : 2 bh - - - 0,00%
- Box Hanger : 1 bh - - - 0,00%

6, INSTALASI KABEL FEEDER 19.591.270,65 2,78


a. Kabel Distribusi Daya dari MDP :
- NYY 4 x 10 mm2 + E-NYA 6 mm2 ke PP-LT.1 m1 10,00 181.747,51 1.817.475,12 0,26 - - - 0,00%

b. Kabel Distribusi Daya dari PP-LT.1 ke :


- NYM 3 x 4 mm2 ke P-Unit/1 m1 34,15 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/2 m1 28,95 66.803,71 1.933.967,45 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/3 m1 18,95 66.803,71 1.265.930,34 0,18 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/4 m1 29,45 66.803,71 1.967.369,31 0,28 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/5 m1 35,95 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/6 m1 43,95 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/7 m1 34,35 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/8 m1 29,11 66.803,71 1.944.656,05 0,28 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/9 m1 19,25 66.803,71 1.285.971,45 0,18 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/10 m1 22,00 66.803,71 1.469.681,66 0,21 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/11 m1 25,00 66.803,71 1.670.092,79 0,24 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/12 m1 28,00 66.803,71 1.870.503,93 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Serbaguna m1 16,45 66.803,71 1.098.921,06 0,16 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Pengelola m1 22,95 66.803,71 1.533.145,18 0,22 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Mushola m1 25,95 66.803,71 1.733.556,32 0,25 - - - 0,00%

7, INSTALASI KABEL TRAY -


- Kabel Tray W600 x H100 m' 16,00 628.192,14 - - - 0,00%
- Kabel Tray W200 x H100 m' 56,00 280.540,50 - - - 0,00%

Fitting-Fitting :
- Elbow W200 x H100 bh 1,00 184.703,85 - - - 0,00%
- Material bantu ( mur, baut, hanger rod, supporting, dll ) lot 1,00 - - - - 0,00%

8, INSTALASI ARMATUR LAMPU, SAKLAR & STOP KONTAK 16.716.086,67 2,37


- Lampu LED 9 Watt bh 16,00 166.317,46 2.661.079,36 0,38 - - - 0,00%
- Lampu LED 9 Watt, c/w battery charger (Selasar) bh 4,00 197.911,96 791.647,84 0,11 - - - 0,00%
- Lampu LED 7 Watt bh 16,00 99.969,01 1.599.504,16 0,23 - - - 0,00%
- Lampu Baret isi TL Bulat-20 watt c/w battery charger bh 1,00 758.844,73 758.844,73 0,11 - - - 0,00%
- Exit Lamp-18 watt c/w battery charger bh 2,00 1.035.925,98 2.071.851,97 0,29 - - - 0,00%

Page 4
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- Lampu TL 1 x 36 watt, Balk bh 2,00 673.905,67 1.347.811,34 0,19 - - - 0,00%


- Stop Kontak 1P, 220 Volt, 10A, Wall Type bh 29,00 52.533,53 1.523.472,35 0,22 - - - 0,00%
- Stop Kontak AC 1P, 220 Volt, 16A, Wall Type bh 24,00 83.074,88 1.993.797,10 0,28 - - - 0,00%
- Saklar 1 gang bh 45,00 42.002,03 1.890.091,31 0,27 - - - 0,00%
- Saklar 2 gang bh 30,00 63.065,03 1.891.950,88 0,27 - - - 0,00%
- Saklar Hotel 1 gang bh 1,00 40.948,88 40.948,88 0,01 - - - 0,00%
- Saklar Hotel 2 gang bh 2,00 72.543,38 145.086,76 0,02 - - - 0,00%

9, INSTALASI PENERANGAN & STOP KONTAK 37.649.276,37 5,35


- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Lampu ttk 41,00 316.579,90 12.979.775,86 1,84 - - - 0,00%
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak ttk 29,00 409.412,44 11.872.960,72 1,69 - - - 0,00%
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak AC ttk 24,00 533.189,16 12.796.539,80 1,82 - - - 0,00%

A.2 LANTAI 2
1, PEMIPAAN AIR BERSIH 4.509.699,06 0,64
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- PVC AW dia. 15 m 352,00 42.307,65 - - - 0,00%
- PVC AW dia. 20 m 64,00 44.475,75 2.846.448,00 0,40 - - - 0,00%
- PVC AW dia. 40 m 110,00 74.333,70 - - - 0,00%
- PVC AW dia. 50 (Riser dari Tangki Air Atas) m 16,00 80.661,49 1.290.583,80 0,18 - - - 0,00%
Peralatan Katup-katup - - - 0,00%
(Ball Valve & Gate Valve) - - - 0,00%
- dia. 40 bh 1,00 372.667,26 372.667,26 0,05 - - - 0,00%
- Meter Air c/w BV dia. 20 bh 16,00 378.183,76 - - - 0,00%

2, PEMIPAAN AIR KOTOR & AIR BEKAS 12.880.414,80 1,83


Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- dia. 150 ( riser pipa air kotor ) m 64,00 405.530,10 - - - 0,00%
- dia. 100 ( riser pipa air bekas ) m 64,00 166.308,75 - - - 0,00%
- dia. 100 m 24,00 166.308,75 3.991.410,00 0,57 - - - 0,00%
- dia. 80 m 48,00 104.526,11 5.017.253,40 0,71 - - - 0,00%
- dia. 50 m 48,00 80.661,49 3.871.751,40 0,55 - - - 0,00%
- dia. 20 ( pipa drain ac + isolasi ) m 192,00 66.713,63 - - - 0,00%
- Dop, dia. 80 bh 32,00 253.056,90 - - - 0,00%
- Portable Grease Trap bh 16,00 597.055,81 - - - 0,00%

3, PEMIPAAN AIR HUJAN 4.542.410,03 0,65


Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- dia. 100 ( pipa tegak ) m 16,00 166.308,75 2.660.940,00 0,38 - - - 0,00%
- dia. 80 ( riser pipa cucian ) m 18,00 104.526,11 1.881.470,03 0,27 - - - 0,00%

4, PEMIPAAN VENT 1.676.602,80 0,24


Pipa PVC Kelas D (Incl. Fitting & Accessories)
- Dia. 80 ( pipa riser ) m 16,00 104.787,68 1.676.602,80 0,24 - - - 0,00%
- Dia. 32 m 192,00 70.934,74 - - - 0,00%

5, INSTALASI PANEL
Pengadaan dan pemasangan PP-LT.2 unit 1,00 7.637.995,45 - - - 0,00%
dengan komponen panel, sbb :
- MCCB 3P, 63 A
- MCB 1P, 6 A
- Ampere-meter 50/5 A
- Volt-meter 0-500 Volt
- Volt Selector Switch
- Fuse 2 A
- Indicator Lamp
- Rel MCB 3P
- Cu Bar 5 x 63 A
- Accessories & Termination
- Box Panel
- KW-meter/1ph/6A bh 16,00 380.610,92 - - - 0,00%
Pengadaan dan pemasangan P-UNIT , dengan komponen panel sbb : unit 16,00 770.855,65 - - - 0,00%
- MCB 1P, 6 A : 1 bh
- MCB 1P, 6 A : 2 bh

Page 5
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- Box Hanger : 1 bh

6, INSTALASI KABEL FEEDER 20.447.942,73 2,90


a Kabel Distribusi Daya dari MDP : m' 16,00 181.747,51 2.907.960,19 0,41 - - - 0,00%
- NYY 4 x 10 mm2 + E-NYA 6 mm2 ke PP-LT.2

b Kabel Distribusi Daya dari PP-LT.2 ke :


- NYM 3 x 4 mm2 ke P-Unit/1 m' 34,15 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/2 m' 28,95 66.803,71 1.933.967,45 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/3 m' 16,45 66.803,71 1.098.921,06 0,16 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/4 m' 18,95 66.803,71 1.265.930,34 0,18 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/5 m' 29,45 66.803,71 1.967.369,31 0,28 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/6 m' 35,95 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/7 m' 43,95 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/8 m' 34,35 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/9 m' 29,11 66.803,71 1.944.656,05 0,28 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/10 m' 19,25 66.803,71 1.285.971,45 0,18 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/11 m' 16,45 66.803,71 1.098.921,06 0,16 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/12 m' 28,95 66.803,71 1.933.967,45 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/13 m' 22,00 66.803,71 1.469.681,66 0,21 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/14 m' 25,00 66.803,71 1.670.092,79 0,24 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/15 m' 28,00 66.803,71 1.870.503,93 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/16 m' 32,00 66.803,71 - - - 0,00%

7, INSTALASI KABEL TRAY 188.397,93 0,03


- Kabel Tray W200 x H100 m' 56,00 280.540,50 - - - 0,00%
Fitting-Fitting :
- Elbow W200 x H100 bh 1,00 184.703,85 184.703,85 0,03 - - - 0,00%
- Material bantu ( mur, baut, hanger rod, supporting, dll ) lot 1,00 3.694,08 3.694,08 0,00 - - - 0,00%

8, INSTALASI ARMATUR LAMPU, SAKLAR & STOP KONTAK 18.748.549,32 2,66


- Lampu LED 9 Watt bh 20,00 166.317,46 3.326.349,20 0,47 - - - 0,00%
- Lampu LED 9 Watt, c/w battery charger (Selasar) bh 3,00 197.911,96 593.735,88 0,08 - - - 0,00%
- Lampu LED 7 Watt bh 12,00 99.969,01 1.199.628,12 0,17 - - - 0,00%
- Lampu Baret isi TL Bulat-32 watt c/w battery charger bh 3,00 758.844,73 2.276.534,18 0,32 - - - 0,00%
- Exit Lamp-18 watt c/w battery charger bh 3,00 1.035.925,98 3.107.777,95 0,44 - - - 0,00%
- Lampu TL 1 x 36 watt, Balk bh 3,00 673.905,67 2.021.717,01 0,29 - - - 0,00%
- Stop Kontak 1P, 220 Volt, 10A, Wall Type bh 24,00 52.533,53 1.260.804,70 0,18 - - - 0,00%
- Stop Kontak AC 1P, 220 Volt, 16A, Wall Type bh 12,00 83.074,88 996.898,55 0,14 - - - 0,00%
- Saklar 1 gang bh 64,00 42.002,03 2.688.129,87 0,38 - - - 0,00%
- Saklar 2 gang bh 16,00 63.065,03 1.009.040,47 0,14 - - - 0,00%
- Saklar Hotel 1 gang bh 3,00 40.948,88 122.846,64 0,02 - - - 0,00%
- Saklar Hotel 2 gang bh 2,00 72.543,38 145.086,76 0,02 - - - 0,00%

9, INSTALASI PENERANGAN & STOP KONTAK 16.224.168,42 2,30


- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Lampu ttk 44,00 316.579,90 - - - 0,00%
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak ttk 24,00 409.412,44 9.825.898,53 1,40 - - - 0,00%
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak AC ttk 12,00 533.189,16 6.398.269,90 0,91 - - - 0,00%

A.3. LANTAI 3
1, PEMIPAAN AIR BERSIH 8.232.772,26 1,17
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- PVC AW dia. 15 m 88,00 42.307,65 3.723.073,20 0,53 - - - 0,00%
- PVC AW dia. 20 m 64,00 44.475,75 2.846.448,00 0,40 - - - 0,00%
- PVC AW dia. 40 m 110,00 74.333,70 - - - 0,00%
- PVC AW dia. 50 (Riser dari Tangki Air Atas) m 16,00 80.661,49 1.290.583,80 0,18 - - - 0,00%
Peralatan Katup-katup - - - 0,00%
(Ball Valve & Gate Valve) - - - 0,00%
- dia. 40 bh 1,00 372.667,26 372.667,26 0,05 - - - 0,00%
- Meter Air c/w BV dia. 20 bh 16,00 378.183,76 - - - 0,00%

2, PEMIPAAN AIR KOTOR & AIR BEKAS 9.825.097,50 1,40


Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- dia. 150 ( riser pipa air kotor ) m 64,00 405.530,10 - - - 0,00%

Page 6
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- dia. 100 ( riser pipa air bekas ) m 64,00 166.308,75 - - - 0,00%


- dia. 100 m 9,00 166.308,75 1.496.778,75 0,21 - - - 0,00%
- dia. 80 m 12,00 104.526,11 1.254.313,35 0,18 - - - 0,00%
- dia. 50 m 48,00 80.661,49 3.871.751,40 0,55 - - - 0,00%
- dia. 20 ( pipa drain ac + isolasi ) m 48,00 66.713,63 3.202.254,00 0,45 - - - 0,00%
- Dop, dia. 80 bh 32,00 253.056,90 - - - 0,00%
- Portable Grease Trap bh 16,00 597.055,81 - - - 0,00%

3, PEMIPAAN AIR HUJAN 4.333.357,80 0,62


Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- dia. 100 ( pipa tegak ) m 16,00 166.308,75 2.660.940,00 0,38 - - - 0,00%
- dia. 80 ( riser pipa cucian ) m 16,00 104.526,11 1.672.417,80 0,24 - - - 0,00%

4, PEMIPAAN VENT - -
Pipa PVC Kelas D (Incl. Fitting & Accessories)
- Dia. 80 ( pipa riser ) m 64,00 104.787,68 - - - 0,00%
- Dia. 32 m 192,00 70.934,74 - - - 0,00%

5, INSTALASI PANEL - -
Pengadaan dan pemasangan PP-LT.3 unit 1,00 7.637.995,45 - - - 0,00%
dengan komponen panel, sbb :
- MCCB 3P, 63 A
- MCB 1P, 6 A
- Ampere-meter 50/5 A
- Volt-meter 0-500 Volt
- Volt Selector Switch
- Fuse 2 A
- Indicator Lamp
- Rel MCB 3P
- Cu Bar 5 x 63 A
- Accessories & Termination
- Box Panel
- KW-meter/1ph/6A bh 16,00 380.610,92 - - - 0,00%
Pengadaan dan pemasangan P-UNIT , dengan komponen panel sbb : unit 16,00 770.855,65 - - - 0,00%
- MCB 1P, 6 A : 1 bh
- MCB 1P, 6 A : 2 bh
- Box Hanger : 1 bh

6, INSTALASI KABEL FEEDER 21.538.427,80 3,06


a Kabel Distribusi Daya dari MDP :
- NYY 4 x 10 mm2 + E-NYA 6 mm2 ke PP-LT.3 m 22,00 181.747,51 3.998.445,26 0,57 - - - 0,00%
-
b Kabel Distribusi Daya dari PP-LT.3 ke :
- NYM 3 x 4 mm2 ke P-Unit/1 m' 34,15 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/2 m' 28,95 66.803,71 1.933.967,45 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/3 m' 16,45 66.803,71 1.098.921,06 0,16 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/4 m' 18,95 66.803,71 1.265.930,34 0,18 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/5 m' 29,45 66.803,71 1.967.369,31 0,28 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/6 m' 35,95 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/7 m' 43,95 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/8 m' 34,35 66.803,71 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/9 m' 29,11 66.803,71 1.944.656,05 0,28 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/10 m' 19,25 66.803,71 1.285.971,45 0,18 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/11 m' 16,45 66.803,71 1.098.921,06 0,16 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/12 m' 28,95 66.803,71 1.933.967,45 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/13 m' 22,00 66.803,71 1.469.681,66 0,21 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/14 m' 25,00 66.803,71 1.670.092,79 0,24 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/15 m' 28,00 66.803,71 1.870.503,93 0,27 - - - 0,00%
- NYM 3 x 4 mm2 ke P-Unit/16 m' 32,00 66.803,71 - - - 0,00%

7, INSTALASI KABEL TRAY 188.397,93 0,03


- Kabel Tray W200 x H100 m' 56,00 280.540,50 - - - 0,00%
Fitting-Fitting :
- Elbow W200 x H100 bh 1,00 184.703,85 184.703,85 0,03 - - - 0,00%

Page 7
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- Material bantu ( mur, baut, hanger rod, supporting, dll ) lot 1,00 3.694,08 3.694,08 0,00 - - - 0,00%

8, INSTALASI ARMATUR LAMPU, SAKLAR & STOP KONTAK 13.269.252,09 1,88


- Lampu LED 9 Watt bh 12,00 166.317,46 1.995.809,52 0,28 - - - 0,00%
- Lampu LED 9 Watt, c/w battery charger (Selasar) bh 3,00 197.911,96 593.735,88 0,08 - - - 0,00%
- Lampu LED 7 Watt bh 12,00 99.969,01 1.199.628,12 0,17 - - - 0,00%
- Lampu Baret isi TL Bulat-32 watt c/w battery charger bh 2,00 758.844,73 1.517.689,45 0,22 - - - 0,00%
- Exit Lamp-18 watt c/w battery charger bh 2,00 1.035.925,98 2.071.851,97 0,29 - - - 0,00%
- Lampu TL 1 x 36 watt, Balk bh 2,00 673.905,67 1.347.811,34 0,19 - - - 0,00%
- Stop Kontak 1P, 220 Volt, 10A, Wall Type bh 24,00 52.533,53 1.260.804,70 0,18 - - - 0,00%
- Stop Kontak AC 1P, 220 Volt, 16A, Wall Type bh 12,00 83.074,88 996.898,55 0,14 - - - 0,00%
- Saklar 1 gang bh 24,00 42.002,03 1.008.048,70 0,14 - - - 0,00%
- Saklar 2 gang bh 16,00 63.065,03 1.009.040,47 0,14 - - - 0,00%
- Saklar Hotel 1 gang bh 3,00 40.948,88 122.846,64 0,02 - - - 0,00%
- Saklar Hotel 2 gang bh 2,00 72.543,38 145.086,76 0,02 - - - 0,00%

9, INSTALASI PENERANGAN & STOP KONTAK 26.671.305,09 3,79


- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Lampu ttk 33,00 316.579,90 10.447.136,67 1,48 - - - 0,00%
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak ttk 24,00 409.412,44 9.825.898,53 1,40 - - - 0,00%
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak AC ttk 12,00 533.189,16 6.398.269,90 0,91 - - - 0,00%

A.4. LANTAI ATAP


1, PEMIPAAN AIR BERSIH 4.572.102,76 0,65
Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- PVC AW dia. 50 m 8,00 80.661,49 645.291,90 0,09 - - - 0,00%
- PVC AW dia. 32 (Pipa Drain) m 6,00 72.646,20 435.877,20 0,06 - - - 0,00%
- PVC AW dia. 100 (Header) m 4,00 207.885,94 831.543,75 0,12 - - - 0,00%
Peralatan Katup-katup
(Ball Valve & Gate Valve)
- dia. 50 bh 4,00 504.441,40 2.017.765,59 0,29 - - - 0,00%
- dia. 32 bh 2,00 320.812,16 641.624,32 0,09 - - - 0,00%

2, PEMIPAAN AIR HUJAN 7.040.219,60 1,00


Pipa PVC Kelas AW (Incl. Fitting & Accessories)
- dia. 100 m 32,00 166.308,75 5.321.880,00 0,76 - - - 0,00%

Roof Drain, Cast Iron


- dia. 100 bh 4,00 429.584,90 1.718.339,60 0,24 - - - 0,00%
- dia. 80 bh 12,00 319.254,90 - - - 0,00%

3, INSTALASI ARMATUR LAMPU, SAKLAR & STOP KONTAK 2.016.226,19 0,29


- Lampu LED 9 Watt bh 2,00 166.317,46 332.634,92 0,05 - - - 0,00%
- Lampu Baret isi TL Bulat-32 watt c/w battery charger bh 2,00 758.844,73 1.517.689,45 0,22 - - - 0,00%
- Saklar 1 gang bh 2,00 42.002,03 84.004,06 0,01 - - - 0,00%
- Saklar Hotel 1 gang bh 2,00 40.948,88 81.897,76 0,01 - - - 0,00%

4, INSTALASI PENERANGAN & STOP KONTAK 1.266.319,60 0,18


- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Lampu TTK 4,00 316.579,90 1.266.319,60 0,18 - - - 0,00%

A.5. PEKERJAAN UTILITAS


1, INSTALASI PANEL 25.261.457,70 3,59
a P-PLN
- MCCB 3P, 200 A : 1 bh BY PLN
- Accessories & Termination : 1 lot
- Box Panel : 1 unit

b P-MDP
Pengadaan dan pemasangan MDP, dengan komponen panel, sbb : unit 1,00 4.035.720,95 4.035.720,95 0,57 - - - 0,00%
- Mgs 3P, 63 A
- MCCB 3P, 200 A
- MCCB 3P, 80 A
- MCCB 3P, 32 A
- MCB 3P, 32 A
- Contacto, (timer switch)

Page 8
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- Earth Fault Relay


- Over Current Relay
- Over / Under Voltage Relay
- Power Factor-meter
- Frequency-metr
- Ampere-meter 300/5 A
- Ampere-meter 50/5 A
- Volt-meter 0-500 Volt
- Volt Selector Switch
- CT 300/5 A
- CT 50/5 A
- Fuse Carrier 4 A
- Indicator Lamp
- Rel MCCB 3P
- CU Bar 5 x 400 A
- Accessories & Termination
- Box Panel

c P-PENGELOLA
Pengadaan dan pemasangan P-PENGELOLA dengan komponen panel, sbb : unit 1,00 3.478.052,95 3.478.052,95 0,49 - - - 0,00%
- MCCB 3P, 80 A
- MCB 3P, 63 A
- MCB 3P, 32 A
- MCB 1P, 6 A
- Ampere-meter 50/5 A
- Volt-meter 0-500 Volt
- Volt Selector Switch
- Fuse 2 A
- Indicator Lamp
- Rel MCB 3P
- Cu Bar 5 x 80 A
- Accessories & Termination
- Box Panel
- KW-meter/3ph/80A bh 1,00 1.244.773,15 1.244.773,15 0,18 - - - 0,00%

d P-POMPA AIR BERSIH


Pengadaan dan pemasangan P-POMPA AIR BERSIH, dengan komponen panel, sbb : unit 1,00 1.440.207,70 1.440.207,70 0,20 - - - 0,00%
- MCB 3P, 32 A
- MCB 3P, 10 A
- WLC 61F G-AP 220 Volt
- DOL ( Direct On Line )
- Radar diantaki air atas
- Fuse 2 A
- Indicator Lamp
- Rel MCB 3P
- Cu Bar 5 x 32 A
- Accessories & Termination
- Box Panel

e P-POMPA HYDRANT
Pengadaan dan pemasangan P-POMPA HYDRANT, dengan komponen panel, sbb : unit 1,00 15.062.702,95 15.062.702,95 2,14 - - - 0,00%
- MCB 3P, 40 A
- MCB 3P, 16 A
- WLC 61F G-AP 220 Volt
- DOL ( Direct On Line )
- Fuse 2 A
- Indicator Lamp
- Rel MCB 3P
- Cu Bar 5 x 32 A
- Accessories & Termination
- Box Panel

2, INSTALASI KABEL FEEDER 31.716.548,91 4,51


- NYY 4 x 70 mm2 + E-NYA 35 mm2 Dari P-PLN ke MDP m' 18,84 973.400,37 18.338.007,33 2,60 - - - 0,00%

Page 9
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

Kabel Distribusi Daya dari MDP :


- NYY 4 x 16 mm2 + E-NYA 10 mm2 ke P-PENGELOLA-LT.1 m' 10,00 283.850,40 2.838.504,04 0,40 - - - 0,00%

Kabel Distribusi Daya dari P-PENGELOLA :


- NYY 4 x 6 mm2 + E-NYA 6 mm2 ke P-Air Bersih m' 40,00 148.783,92 5.951.356,67 0,85 - - - 0,00%
- NYY 4 x 4 mm2 + E-NYA 4 mm2 ke P-Shallow Well Pump m' 40,00 114.717,02 4.588.680,87 0,65 - - - 0,00%

3, INSTALASI ARMATUR LAMPU, SAKLAR & STOP KONTAK 988.315,28 0,14


a Ruang Pompa
- TL 1 x 18 W, TL Balk Type bh 2,00 410.618,17 821.236,34 0,12 - - - 0,00%
- Stop Kontak 1P, 220 Volt, 13A, Wall Type bh 1,00 83.074,88 83.074,88 0,01 - - - 0,00%
- Saklar 1 gang bh 2,00 42.002,03 84.004,06 0,01 - - - 0,00%

b Lampu Taman
- Lampu Taman/ Penerangan Luar ( t = 2,5 m ) SL 26 watt bh 12,00 1.263.102,98 - - - 0,00%

4, INSTALASI PENERANGAN & STOP KONTAK 2.110.342,37 0,30


a Ruang Pompa
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Lampu ttk 2,00 316.579,90 633.159,80 0,09 - - - 0,00%
- NYM 3 x 2,5 mm2 + PVC Conduit dia.20 untuk Stop Kontak ttk 1,00 409.412,44 409.412,44 0,06 - - - 0,00%

b Lampu Taman
- NYFGBY 3 x 2,5 mm2 untuk Lampu Taman ttk 12,00 10.760.110,18 - - - 0,00%

- Testing & Commissioning lot 1,00 1.067.770,13 1.067.770,13 0,15 - - - 0,00%

A.6. PEKERJAAN SISTEM PENTANAHAN

1, INSTALASI 11.391.375,89 1,62


Pentanahan (Grounding) Netral Sistem & Pentanahan Body

a Body Panel
Item SBB:
Grounding Rod GIP 1' ( untuk R lebih kecil dari 2 ohm ) Copper Rod, kabel BC, clamp rod, Bar CU, kontrol Box bh 1,00 811.440,24 811.440,24 0,12 - - - 0,00%
Termination R.Supporting Material lot 1,00 1.451.070,89 1.451.070,89 0,21 - - - 0,00%
Kabel BC 50 mm2 m 30,00 97.179,57 2.915.387,00 0,41 - - - 0,00%
Testing & Commissioning lot 1,00 517.789,81 517.789,81 0,07 - - - 0,00%

b Body Peralatan pada Sistem Elektronik Item SBB:


Grounding Rod GIP 1' ( untuk R lebih kecil dari 2 ohm ) Copper Rod, kabel BC, clamp rod, Bar CU, kontrol Box bh 1,00 811.440,24 811.440,24 0,12 - - - 0,00%
Termination R.Supporting Material lot 1,00 1.451.070,89 1.451.070,89 0,21 - - - 0,00%
Kabel BC 50 mm2 m 30,00 97.179,57 2.915.387,00 0,41 - - - 0,00%
Testing & Commissioning lot 1,00 517.789,81 517.789,81 0,07 - - - 0,00%

A.7. PEKERJAAN PENANGKAL PETIR 18.659.797,86 2,65

INSTALASI
- Splitzen T=1 meter, pipa galvanized c/w : peralatan bantu unit 11,00 501.951,35 5.521.464,85 0,78 - - - 0,00%
- Bak kontrol 40x40x30 cm unit 2,00 634.511,04 1.269.022,08 0,18 - - - 0,00%
- Down Conduktor BC 50mm + accessories m' 84,28 97.179,57 8.189.904,04 1,16 - - - 0,00%
- Grounding System max. 2 ohm lot 2,00 811.440,24 1.622.880,48 0,23 - - - 0,00%
Copper Rod, kabel BC, clamp rod, Bar CU, kontrol Box
- Biaya Instalasi lot 1,00 411.981,79 411.981,79 0,06 - - - 0,00%
- Material Bantu lot 1,00 329.585,43 329.585,43 0,05 - - - 0,00%
- Testing & Comissioning included perijinan dari DEPNAKER lot 1,00 1.067.770,13 1.067.770,13 0,15 - - - 0,00%
- Bracket, Seal , Test Box , dls lot 1,00 247.189,07 247.189,07 0,04 - - - 0,00%

B. PEKERJAAN MEKANIKAL & ELEKTRIKAL NON STANDART


B.1. PEKERJAAN PEMADAM KEBAKARAN
1, INSTALASI APAR 4.375.336,75 0,62

LANTAI 1
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :

Page 10
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- Type Class ABC 3,5 kg DCP Seamless, c/w support bh 3,00 386.455,90 1.159.367,70 0,16 - - - 0,00%
- Type Class BC 4,6 kg CO2 Seamless, c/w support bh 1,00 897.233,65 897.233,65 0,13 - - - 0,00%

LANTAI 2
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :
- Type Class ABC 3,5 kg DCP Seamless, c/w support bh 3,00 386.455,90 1.159.367,70 0,16 - - - 0,00%

LANTAI 3
Fire Extinguisher Tabung Cat Oven sesuai SPEK & Skedul :
- Type Class ABC 3,5 kg DCP Seamless, c/w support bh 3,00 386.455,90 1.159.367,70 0,16 - - - 0,00%

B.2 PEKERJAAN VENTILASI UDARA


I EXHAUST FAN 80.788.812,00 11,48
LANTAI 1
- Exhaust kap 100 Cfm ( ceiling Mounted ) unit 12,00 917.143,20 11.005.718,40 1,56 - - - 0,00%
Pipa PVC Class D
- dia. 100 m 48,00 155.526,98 7.465.294,80 1,06 - - - 0,00%
- Grille 200 x 200 (Alumunium) bh 12,00 308.221,90 3.698.662,80 0,53 - - - 0,00%
LANTAI 2 & 3
- Exhaust kap 200 CMH ( ceiling Mounted ) unit 32,00 917.143,20 29.348.582,40 4,17 - - - 0,00%
Pipa PVC Class D
- dia. 100 m 124,79 155.526,98 19.407.452,80 2,76 - - - 0,00%
- Grille 200 x 200 (Alumunium) bh 32,00 308.221,90 9.863.100,80 1,40 - - - 0,00%
B.3. PEKERJAAN INSTALASI ELEKTRONIK
I. PEKERJAAN SYSTEM TV 33.024.694,47 4,69
a PERALATAN UTAMA SYSTEM TV
Pengadaan dan pemasangan peralatan utama Sistem TV ditempatkan di Lantai Atap, dipasang secara lengkap termasuk pondasi dan
tiang penyangga sesuai diuraikan dalam Gambar dan Spesifikasi Teknis.
- Antena UHF unit 1,00 633.232,92 633.232,92 0,09 - - - 0,00%
- Antena VHF unit 1,00 643.764,42 643.764,42 0,09 - - - 0,00%
- MA (Master Amplifier) / Mixer bh 1,00 1.903.113,20 1.903.113,20 0,27 - - - 0,00%
- Coaxial 7C/2V, dari Antena ke Mixer mtr 50,00 38.842,58 1.942.128,96 0,28 - - - 0,00%
- Termination & supporting material lot 1,00 512.223,95 512.223,95 0,07 - - - 0,00%

b SPLITTER TV
Pengadan dan pemasangan Splitter TV, berikut alat/material bantu lainnya sesuai Gambar dan Spesifikasi Teknis.
LANTAI 1
Splitter 7 ports bh 3,00 93.606,38 280.819,14 0,04 - - - 0,00%
TB-Splitter-TV/LT.1 bh 1,00 96.126,42 96.126,42 0,01 - - - 0,00%
Lantai 2
Splitter 7 ports bh 4,00 93.606,38 374.425,52 0,05 - - - 0,00%
TB-Splitter-TV/LT.2 bh 1,00 96.126,42 96.126,42 0,01 - - - 0,00%
Lantai 3
Splitter 7 ports bh 4,00 93.606,38 374.425,52 0,05 - - - 0,00%
TB-Splitter-TV/LT.3 bh 1,00 96.126,42 96.126,42 0,01 - - - 0,00%
c INSTALASI KABEL FEEDER SPLITTER TV
Instalasi Kabel Feeder Splitter TV menggunakan kabel coaxial berikut semua aksesoris, material / alat bantu
pemasangan sesuai detail Gambar dan Spesifikasi Teknis.
Lantai 1
Coaxial 7C/2V dari TB-Splitter-TV/lt.2 ke TB-Splitter-Lt.1 mtr 10,00 38.842,58 388.425,79 0,06 - - - 0,00%
Lantai 2
Coaxial 7C/2V dari TB-Splitter-TV/lt.3 ke TB-Splitter-Lt.2 mtr 14,69 38.842,58 570.415,54 0,08 - - - 0,00%
Lantai 3
Coaxial 7C/2V dari TB-Splitter-TV/lt.4 ke TB-Splitter-Lt.3 mtr 10,00 38.842,58 388.425,79 0,06 - - - 0,00%
d TV OUTLET
Pengadan dan pemasangan TV Outlet, berikut alat/material bantu lainnya sesuai Gambar dan Spesifikasi teknis
Lantai 1
TV Outlet bh 12,00 72.543,38 870.520,55 0,12 - - - 0,00%
Lantai 2
TV Outlet bh 16,00 72.543,38 1.160.694,07 0,16 - - - 0,00%
Lantai 3
TV Outlet bh 16,00 72.543,38 1.160.694,07 0,16 - - - 0,00%
e INSTALASI OUTLET TV
Instalasi kabel Outlet TV menggunakan kabel Coaxial 5C/2V dalam conduit PVC HI dia.20 mm2 lengkap dengan

Page 11
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

bobokan dan perapihan kembali, peralatan bantu dan aksesoris sesuai detail Gambar dan Spesifikasi Teknis.

Lantai 1
TV Outlet ttk 10,00 717.766,86 7.177.668,60 1,02 - - - 0,00%
Lantai 2
TV Outlet ttk 10,00 717.766,86 7.177.668,60 1,02 - - - 0,00%
Lantai 3
TV Outlet ttk 10,00 717.766,86 7.177.668,60 1,02 - - - 0,00%
II PEKERJAAN FIRE ALARM 85.085.268,23 12,09
a PERALATAN UTAMA FIRE ALARM SYSTEM
Pengadaan dan pemasangan peralatan Sistem Fire Alarm ditempatkan di Ruang Kontrol secara lengkap termasuk
pengkabelan dan koneksi meliputi peralatan sesuai diuraikan dlm Gambar dan Spesifikasi Teknis, tetapi tidak
terbats pada item sebagai berikut :
MCFA, kapasitas 10 Zone unit 1,00 10.952.748,16 10.952.748,16 1,56 - - - 0,00%
MDF, kapasitas 10 Zone set 1,00 6.647.997,54 6.647.997,54 0,94 - - - 0,00%
Rectifier bh 1,00 1.539.166,89 1.539.166,89 0,22 - - - 0,00%
Power Surge Arrester bh 1,00 1.304.630,38 1.304.630,38 0,19 - - - 0,00%
Battery & Charger 4 jam bh 1,00 1.508.659,24 1.508.659,24 0,21 - - - 0,00%
Grounding u/ MCFA dan Surge Arrester ( R < 0,5 Ohm ) lot 1,00 811.440,24 811.440,24 0,12 - - - 0,00%

b INSTALASI KABEL FEEDER FIRE ALARM


INSTALASI FEEDER MELALUI RISER / SHAFT
Kabel NYA 5 x 2 x 2,5 mm2 in conduit Dia.32 dari MCFA ke MDF mtr 8,00 1.099.364,63 8.794.917,03 1,25 - - - 0,00%
Kabel NYA 3 x 2 x 2,5 mm2 in conduit Dia.32 dari MDF ke TB-FA-LT.1 mtr 2,00 1.099.364,63 2.198.729,26 0,31 - - - 0,00%
Kabel NYA 3 x 2 x 2,5 mm2 in conduit Dia.32 dari MDF ke TB-FA-LT.2 mtr 6,00 1.099.364,63 6.596.187,78 0,94 - - - 0,00%
Kabel NYA 3 x 2 x 2,5 mm2 in conduit Dia.32 dari MDF ke TB-FA-LT.3 mtr 5,00 1.099.364,63 5.496.823,15 0,78 - - - 0,00%

c PERALATAN PENGINDERA dan PENANDA KEBAKARAN


Pengadaan dan pemasangan peralatan pengindera dan penanda kebakaran berikut alat / material bantu lainnya
Gambar dan Spesifikasi Teknis.
Lantai 1
- Rate Of Rise Temperature - Heat detector bh 10,00 476.952,98 4.769.529,79 0,68 - - - 0,00%
- Manual push button bh 1,00 198.921,38 198.921,38 0,03 - - - 0,00%
- Lampu Indikator bh 1,00 40.948,88 40.948,88 0,01 - - - 0,00%
- Bell alarm bh 1,00 241.047,38 241.047,38 0,03 - - - 0,00%
- End of Line Resistor bh 2,00 46.214,63 92.429,26 0,01 - - - 0,00%
- TB-FA-LT.1 bh 1,00 494.217,12 494.217,12 0,07 - - - 0,00%
Lantai 2
- Rate Of Rise Temperature - Heat detector bh 10,00 476.952,98 4.769.529,79 0,68 - - - 0,00%
- Manual push button bh 1,00 198.921,38 198.921,38 0,03 - - - 0,00%
- Lampu Indikator bh 1,00 40.948,88 40.948,88 0,01 - - - 0,00%
- Bell alarm bh 1,00 241.047,38 241.047,38 0,03 - - - 0,00%
- End of Line Resistor bh 2,00 46.214,63 92.429,26 0,01 - - - 0,00%
- TB-FA-LT.2 bh 1,00 494.217,12 494.217,12 0,07 - - - 0,00%
Lantai 3
- Rate Of Rise Temperature - Heat detector bh 10,00 476.952,98 4.769.529,79 0,68 - - - 0,00%
- Manual push button bh 1,00 198.921,38 198.921,38 0,03 - - - 0,00%
- Lampu Indikator bh 1,00 40.948,88 40.948,88 0,01 - - - 0,00%
- Bell alarm bh 1,00 241.047,38 241.047,38 0,03 - - - 0,00%
- End of Line Resistor bh 2,00 46.214,63 92.429,26 0,01 - - - 0,00%
- TB-FA-LT.3 bh 1,00 494.217,12 494.217,12 0,07 - - - 0,00%
d PERALATAN PENGINDERA dan PENANDA KEBAKARAN
Instalasi titik detector dari TB-FA dengan kabel NYA 2 x 1,5 mm2 didalam conduit dia. 20 mm2 lengkap dengan
aksesoris dan semua peralatan / material bantu pemasangan sesuai detail Gambar dan Spesifikasi Teknis.
Lantai 1
- Rate Of Rise Temperature - Heat detector ttk 10,00 485.547,29 4.855.472,85 0,69 - - - 0,00%
- Manual push button ttk 1,00 602.277,83 602.277,83 0,09 - - - 0,00%
- Lampu Indikator ttk 1,00 824.943,83 824.943,83 0,12 - - - 0,00%
- Bell alarm ttk 1,00 602.277,83 602.277,83 0,09 - - - 0,00%
Lantai 2
- Rate Of Rise Temperature - Heat detector ttk 10,00 485.547,29 4.855.472,85 0,69 - - - 0,00%
- Manual push button ttk 1,00 602.277,83 602.277,83 0,09 - - - 0,00%
- Lampu Indikator ttk 1,00 824.943,83 824.943,83 0,12 - - - 0,00%
- Bell alarm ttk 1,00 602.277,83 602.277,83 0,09 - - - 0,00%

Page 12
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

Lantai 3
- Rate Of Rise Temperature - Heat detector ttk 10,00 485.547,29 4.855.472,85 0,69 - - - 0,00%
- Manual push button ttk 1,00 602.277,83 602.277,83 0,09 - - - 0,00%
- Lampu Indikator ttk 1,00 824.943,83 824.943,83 0,12 - - - 0,00%
- Bell alarm ttk 1,00 602.277,83 602.277,83 0,09 - - - 0,00%
Testing & Comissioning included perijinan dari DEPNAKER lot 1,00 1.067.770,13 1.067.770,13 0,15 - - - 0,00%

B.4. PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN)


I PEKERJAAN INSTALASI PLAMBING
1, INSTALASI AIR BERSIH 16.130.054,31 2,29
PERALATAN UTAMA
Pengadaan dan pemasangan unit
1 Lift Pump bh 2,00 1.932.660,64 3.865.321,28 0,55 - - - 0,00%
Type : Centrifugal end suction
Kapasitas : 200 l/menit
Head : 36 mtr
Speed : 2900 rpm
Daya : 5,5 KW/380V/50Hz/3ph
1 duty, 1 standby ( bergantian ), lengkap dengan panel control, wlc di Tanki Air Atas dan accessories set 1,00 2.496.366,70 2.496.366,70 0,35 - - - 0,00%

2 Distribution Pump set 1,00 53.465.215,90 - - - 0,00%


Type : Packaged Booster Pump
Kapasitas : 2 x 150 l/menit
Head : 20 mtr
Speed : 1450 rpm
Daya : 2,2 KW/380V/50Hz/3ph
Operasi : Parallel Alternate
( lengkap dengan Pump & Electromotor, Pressure Tank, Panel Kontrol, Pressure switch, Presure Gauge,
Accessories, Gate Valve, Header & base Plat )
3 Tangki Air Atas ( Type Cylinder ) unit 2,00 4.322.197,81 - - - 0,00%
Kapasitas : 2,5 m3
Glass Rainforcement Plastic (GRP), lengkap dengan Assesories dan dudukan/ pondasi
4 PEKERJAAN SHALLOW WELL unit 1,00 2.881.568,85 - - - 0,00%
a Pembuatan / Pengeboran sumur shallow well
- Kedalaman + 50 Meter, Pipa Casing , Pipa GIP Medium dia 150mm, Pipa Rising dia 80mm, Pipa screen dia 80mm
b Pengadaan dan pemasangan pompa shallow well
- Kapasitas(deb air)150 s/d 200 Lpm, pengadaan dan pemasangan pipa konstruksi : 1 unit
c Instalasi kabel Kontrol WLC : 1 unit
d Instalasi Pipa GIP dia 50 mm ke GWT : 1 unit
e Gate Valve dia 2" : 1 unit
f Bak Kontrol Valve uk, 600 x 600 mm dengan tutup bordes tebal 2 mm : 1 unit
g Panel kontrol shallow well type outdoor : 1 unit
h Pengujian kwalitas air ke laboratorium : 1 unit
i Testing Comissioning & Training : 1 unit
j Material & Alat Bantu : 1 unit
5 Ground Water Tank unit by sipil by sipil
Kapasitas : 25 m3
Rainforced Concrete Made
6 ACCESSORIES POMPA AIR BERSIH
- Gate Valve
dia. 80 ( Untuk Penghubung/penyeimbang GWT) bh 2,00 774.105,37 1.548.210,74 0,22 - - - 0,00%
dia. 50 bh 4,00 309.157,30 1.236.629,19 0,18 - - - 0,00%
- Check Valve ( CV )
dia. 50 bh 2,00 190.000,90 380.001,80 0,05 - - - 0,00%
- Strainer ( STR )
dia. 50 bh 2,00 337.843,10 675.686,20 0,10 - - - 0,00%
- Flexible Joint ( FJ )
dia. 50 bh 4,00 369.838,80 1.479.355,19 0,21 - - - 0,00%
- Foot Valve
dia. 50 bh 2,00 190.000,90 380.001,80 0,05 - - - 0,00%
- Pressure Gauge bh 2,00 - -
- GIP med dia. 100 ( pipa header ) m 2,00 512.566,73 1.025.133,45 0,15 - - - 0,00%
- Instalasi pemipaan area pompa lot 1,00 672.501,84 672.501,84 0,10 - - - 0,00%
c/w fiting-fitting & support.

Page 13
KONTRAK PROGRES MINGGU INI
s/d MINGGU LALU MINGGU INI s/d MINGGU INI PERSENTASE
NO. URAIAN PEKERJAAN SAT. HARGA JUMLAH BOBOT
VOLUME Waktu BOBOT BOBOT BOBOT TERHADAP ITEM
SATUAN HARGA (%) VOLUME VOLUME VOLUME
(%) ( %) (%) PEKERJAAN ( % )

- Meteran Air c/w GV dia. 50 & Box Meteran unit 1,00 1.564.231,26 1.564.231,26 0,22 - - - 0,00%
7 INSTALASI PEMIPAAN
Pengadaan dan pemasangan unit.
Pemipaan PVC AW (Incl. Fitting & All Accessories)
a SITE PLAN
1. Dari Box Meter PDAM ke GWT
- PVC AW dia. 50 (Dari Box Meter PDAM ke GWT) m 10,00 80.661,49 806.614,88 0,11 - - - 0,00%
2. Pemipaan R.Pompa ke Tanki Air Atas
- GIP dia. 65 m 46,00 194.949,90
b Penyambungan pipa PDAM, pipa gip dia. 65 termasuk lot tidak ditawarkan -
Perijinan.
2, INSTALASI AIR KOTOR & AIR BEKAS 6.200.803,17 0,88
Septic Tank Anaerobic Biological Filtration unit 2,00 37.089.937,00 - - - 0,00%
Kapasitas : 9 m3 / hari
Resapan unit 2,00 2.566.516,52 5.133.033,04 0,73 - - - 0,00%
Kapasitas : 5 m3
- Struktur Pondasi By Sipil
Portable Grease Trap unit 44,00 597.055,81 - - - 0,00%
Kapasitas
TESTING COMMISSIONING lot 1,00 1.067.770,13 1.067.770,13 0,15 - - - 0,00%

II. PENYAMBUNGAN DAYA PLN -


Pekerjaan Pasang Baru Daya Listrik PLN 82 KVA va - 3.941.000,00 - - - - 0,00%
- BP ( Biaya penyambungan )
- UJL ( Uang Jaminan Langanan )
- Biaya Instalatir
- Concuil
- Pemasangan dan material yang dibutuhkan, seperti : ( kabel, tiang, pondasi, galian & urugan kembali, dll )

III PEKERJAAN INSTALASI KABEL FEEDER 4.286.610,56 0,61


Kabel Distribusi Daya dari Panel Pompa - Air Bersih
- NYY 4 x 4 mm2 ke LP-1 m' 10,00 114.717,02 1.147.170,22 0,16 - - - 0,00%
- NYY 4 x 4 mm2 ke LP-2 m' 10,00 114.717,02 1.147.170,22 0,16 - - - 0,00%
- Proteksi Kabel dengan Pipa Gip Dia 100 Pengadaan Pipa Gip Dia 100, termasuk galian dan material bantu lainya m' 20,00 46.225,00 924.500,00 0,13 - - - 0,00%
- Testing & Commissioning lot 1,00 1.067.770,13 1.067.770,13 0,15 - - - 0,00%

JUMLAH TOTAL 703.998.308,18 100,00 - 4,04 4,04 4,04%

PPN 11% 77.439.813,90

JUMLAH TOTAL (TERMASUK PPN) 781.438.122,08

PEMBULATAN 781.438.000,00

Merauke, 26 November 2023


Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :
Pejabat Pembuat Komitmen KONSULTAN PENGAWAS PENYEDIA JASA KONSTRUKSI
Rumah Susun dan Rumah Khusus CV. MEGA DALLES ENGINEERING CV. DUNSADA ENGINEERING
Paket Perawatan Rumah Susun Polres Marauke

ADOLF LEONARD BATLOLONA, S.T MALIK ASO DEREK WAINYAMBE, SH


NIP. 19740111 200502 1 004 Direktur Direktur

Page 14
PEKERJAAN : PERAWATAN RUMAH RUSUN KELUARGA TNI/POLRI (POLRES MERAUKE)
TIPE PROTOTYPE : RUMAH SUSUN T-36 KDS-D
JUMLAH LANTAI : 3 LANTAI
LOKASI PEKERJAAN : JL. RAYA MERDEKA KAB. MERAUKE, POV. PAPUA (POLRES MERAUKE)
PENYEDIA JASA KONSTRUKSI : CV. DUNSADA ENGINEERING
TAHUN ANGGARAN : 2023
LAPORAN KEMAJUAN PEKERJAAN MINGGU KE - 1

( 22 November s/d 26 November 2024 )


Progres Mingguan

NO. URAIAN PEKERJAAN M1 M2 M3 M4 M5 M6


JUMLAH BOBOT
22/11/2023 27/11/2023 04/12/2023 11/12/2023 18/12/2023 25/12/2023
HARGA (%)
26/11/2023 03/12/2023 10/12/2023 17/12/2023 24/12/2023 30/12/2023

I. PEKERJAAN PERSIAPAN STANDAR DAN PEKERJAAN RK3K KONSTRUKSI


I.A PEKERJAAN PERSIAPAN STANDAR 13.797.790,00 1,96 1,96

I.B. PEKERJAAN RK3K KONSTRUKSI 89.321.000,00 12,69 6,34 6,34

II. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL


II. A PEKERJAAN MEKANIKAL DAN ELEKTRIKAL STANDART
A.1 LANTAI 1 102.688.436,98 14,59 4,86 4,86 4,86

A.2 LANTAI 2 79.218.185,09 11,25 5,63 5,63

A.3. LANTAI 3 84.058.610,47 11,94 5,97 5,97

A.4. LANTAI ATAP 14.894.868,14 2,12 1,06 1,06

A.5. PEKERJAAN UTILITAS 60.076.664,26 8,53


REncAnA 2,84 2,84 2,84
KOnTRAK
A.6. PEKERJAAN SISTEM PENTANAHAN 30.051.173,75 4,27 2,13 2,13

B. PEKERJAAN MEKANIKAL & ELEKTRIKAL NON STANDART


B.1. PEKERJAAN PEMADAM KEBAKARAN 4.375.336,75 0,62 0,62

B.2 PEKERJAAN VENTILASI UDARA 80.788.812,00 11,48 2,87 2,87 2,87 2,87

B.3. PEKERJAAN INSTALASI ELEKTRONIK 118.109.962,70 16,78 3,36 3,36 3,36 3,36 3,36

B.4. PEKERJAAN SARANA DAN PRASARANA LINGKUNGAN (LUAR BANGUNAN)


I PEKERJAAN INSTALASI PLAMBING 22.330.857,48 3,17 3,17

II. PENYAMBUNGAN DAYA PLN -


REALISASI

III PEKERJAAN INSTALASI KABEL FEEDER 4.286.610,56 0,61


0,61
JUMLAH TOTAL 703.998.308,18 100,00

BOBOT RENCANA MINGGU INI (%) 8,30 30,08 26,59 16,69 11,20 7,14
BOBOT KOMULATIS RENCANA S/D MINGGU INI(%) 8,30 38,39 64,97 81,66 92,86 100,00
BOBOT REALISASI MINGGU INI (%) -
BOBOT KOMULATIS REALISASI S/D MINGGU INI (%) -
DEVIASI KOMULATIS S/D MINGGU INI (%) - 8,30

Merauke, 26 November 2023


Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :
Pejabat Pembuat Komitmen KONSULTAN PENGAWAS PENYEDIA JASA KONSTRUKSI
Rumah Susun dan Rumah Khusus CV. MEGA DALLES ENGINEERING CV. DUNSADA ENGINEERING
Paket Perawatan Rumah Susun Polres Marauke

ADOLF LEONARD BATLOLONA, S.T MALIK ASO DEREK WAINYAMBE, SH


NIP. 19740111 200502 1 004 Direktur Direktur

Page 15