MONTHLY MEETING

LAPORAN KEMAJUAN PEKERJAAN

JUNI 2022

UNIT INDUK PEMBANGUNAN KALIMANTAN BAGIAN BARAT


UNIT PELAKSANA PROYEK PEMBANGKIT DAN JARINGAN
KALIMANTAN BAGIAN BARAT 2
PT. PLN (PERSERO) UIP KALBABAR ROUTE MAP PROJECT : SND – TX, SECTION 2
UPP KITRING KBB 2
PT. PLN (PERSERO) UIP
KALBABAR PROGRESS PEKERJAAN
UPP KITRING KBB 2
LAPORAN KEMAJUAN PEKERJAAN – MARET 2022

              KEMAJUAN PEKERJAAN
SAT VOLUME BOBOT PRESENTASE
NO URAIAN PEKERJAAN S/D BULAN LALU BULAN INI S/D BULAN INI
      PEKERJAAN
            % % % % %
1 2 3 4 5 6 7 8 9
                     

I.   PEKERJAAN PERSIAPAN LOT 1.00 1.9432 1.8912 0.0154 1.9066 98.1146

                     
II.   PEKERJAAN PENGANGKUTAN MATERIAL              

   A. PENGIRIMAN DARI PABRIK KE GUDANG SITE LOT 1.00 7.1900 5.6024 - 5.6024 77.9198

   B. PENGANGKUTAN DARI GUDANG SITE KE TEPI JALAN LOT 1.00 0.6699 0.2329 - 0.2329 34.7631

   C. LANGSIR DARI TEPI JALAN - LOKASI TITIK TOWER LOT 1.00 10.6944 9.7364 - 9.7364 91.0413

                     

III.   PEKERJAAN PONDASI TOWER LOT 1.00 27.2384 26.5300 0.7084 27.2384 100.0000

                     

IV.   PEKERJAAN PENGADAAN & PEMASANGAN ACCESSORIES TOWER LOT 1.00 6.0737 1.1313 0.0024 1.1337 18.6649

                     

V.   PEKERJAAN ERECTION , FINAL CHEK LOT 1.00 5.5471 3.0920 0.0075 3.0995 55.8767

                     

VI.   PENGADAAN KONDUKTOR, GSW, DAN OPGW LOT 1.00 3.5265 3.5265 - 3.5265 100.0000

                     

VII.   PENGADAAN INSULATOR SET + HARDWARE, ACCESSORIES + FITTING LOT 1.00 22.3314 22.3314 - 22.3314 100.0000

                     

VIII.   PEKERJAAN STRINGING / PENARIKAN KAWAT LOT 1.00 14.1952 0.0000 - 0.0000 0.0000

                     

IX   PEKERJAAN COMMISIONING LOT 1.00 0.5901 0.0000 - 0.0000 0.0000

                     
                     
  TOTAL     100.0000 74.0740 0.7338 74.8077  
                     
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
PROGRESS PEKERJAAN - S CURVE Overall

Plan & Aktual Progress :

Komulatif s/d Bulan


Progres Bulan Lalu Bulan Ini Ini

Plan Progress 87,0694 % 06,0784 % 93,1478 %

Aktual Progress 74,0740 % 0,7338 % 74,8077 %

Deviasi - 12,9954 % - 5,3447 % - 18,3401 %


PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Engineering

Progress Engineering

A 100,00% 65

B 0,00% 0

STATUS CIVIL ( Pasca C 0,00% 0


Recheck )
BELUMSUBMIT 0,00% 0

TOTAL 100,00% 65

A 100,00% 28

B 0,00% 0

STATUS ELMEK C 0,00% 0

BELUM SUBMIT 0,00% 0

TOTAL 100,00% 28
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
REKAP TOWER
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Procurement

MATERIAL STUB MATERIAL TOWER MATERIAL ELMEK

SECTION TARIK
BELUM BELUM ON
ON SITE ON SITE ON SITE SITE ISOLATOR KONDUKTOR OPGW GSW FITTING ACC

Section Tarik 1
(T.61 - T.83) 21 1 13 8 100% 25% 100% 100% 100%

Section Tarik 2
(T.83 – T.106) 23 1 16 7 100% 25% 100% 100% 100%

Section Tarik 3
(T.106-T.126) 21 0 12 9 100% 25% 100% 100% 100%
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Procurement

TIM PEKERJA
 

Pembukaan Lahan Grup Langsir Grup Pondasi Grup Erection

5 6 12 13

Orang Orang Orang Orang


PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Procurement

Lahan bebas bermasalah dgn warga = 0 Titik

Lahan Bebas Stub belum ada = 0 Titik

Lahan Bebas Drawing belum approved = 0 Titik

Pondasi Selesai = 64 Titik

Pondasi On Progress = 1 Titik ( 62 )

Lahan bebas belum dikerjakan = 0 Titik

Erection Selesai = 39 titik

Erection On Progress = 0 titik

Pondasi Siap Erection Twr Ready = 2 titik ( 65, 66 )

Pemasangan Insulator Set = 39 titik


PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2

KEGIATAN YANG SEDANG BERJALAN

No. ITEM KEGIATAN

1. Gudang Pal 20 - Perbaikan Mesin Molen


- Perapian Isi Gudang

2. Pondasi - Rencana Cor Chimney 2 Leg, T. 62


- Perapian & Pasang patok Batas, T. 62

3. Erection - Tidak ada


PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress

Dokumentasi Progress
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress

Dokumentasi Progress
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress

Dokumentasi Progress
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress

Dokumentasi Progress
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress

Dokumentasi Progress
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2

Rencana Kegiatan Bulan Depan

No. ITEM KEGIATAN

1. Persiapan a. Pembersihan Lahan (Tapak Tower) yang bebas.


b. Potong, Bengkok, Pembesian untuk Pondasi
c. Pembuatan Bekisting
d. Pembuatan Jalan Masuk & Langsir Material

2. Pondasi FINISH 65 TITIK

3. Erection Grup Erection :


- 1 Grup :
PT. PLN (PERSERO) UIP KALBAGBAR
UPP KITRING KBB 2
KENDALA DAN PERMASALAHAN

NO Terkait PLN Terkait Kontraktor

1 Pengadaan Tim erection

2 Pengadaan Tim Kerja dan Alat Stringing

7
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2