Anda di halaman 1dari 17

LAPORAN KEMAJUAN PEKERJAAN

UIP KALIMANTAN BAGIAN


BARAT
UPP KITRING KBB 2
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
ROUTE MAP PROJECT
PT. PLN (PERSERO) UIP
KALBABAR PROGRESS PEKERJAAN
UPP KITRING KBB 2
LAPORAN KEMAJUAN PEKERJAAN – SEPTEMBER 2021
SAT VOLUME BOBOT PRESENTASE
NO URAIAN PEKERJAAN S/D BULAN LALU BULAN INI S/D BULAN INI
      PEKERJAAN
            % % % % %
1 2 3 4 5 6 7 8 9
                     

I.   PEKERJAAN PERSIAPAN LOT 1.00 1.9432 1.8604 0.0154 1.8758 96.5314

                     
II.   PEKERJAAN PENGANGKUTAN MATERIAL              

   A. PENGIRIMAN DARI PABRIK KE GUDANG SITE LOT 1.00 7.1900 5.5163 0.0861 5.6024 77.9198

   B. PENGANGKUTAN DARI GUDANG SITE KE TEPI JALAN LOT 1.00 0.6699 0.2182 - 0.2182 32.5670

   C. LANGSIR DARI TEPI JALAN - LOKASI TITIK TOWER LOT 1.00 10.6944 9.6623 0.0094 9.6717 90.4364

                     

III.   PEKERJAAN PONDASI TOWER LOT 1.00 27.2384 25.6401 0.4332 26.0733 95.7225

                     

IV.   PEKERJAAN PENGADAAN & PEMASANGAN ACCESSORIES TOWER LOT 1.00 6.0737 0.4062 0.7214 1.1276 18.5659

                     

V.   PEKERJAAN ERECTION , FINAL CHEK LOT 1.00 5.5471 2.9642 0.0038 2.9680 53.5050

                     

VI.   PENGADAAN KONDUKTOR, GSW, DAN OPGW LOT 1.00 3.5265 3.5265 - 3.5265 100.0000

                     

VII.   PENGADAAN INSULATOR SET + HARDWARE, ACCESSORIES + FITTING LOT 1.00 22.3314 22.3314 - 22.3314 100.0000

                     

VIII.   PEKERJAAN STRINGING / PENARIKAN KAWAT LOT 1.00 14.1952 0.0000 - 0.0000 0.0000

                     

IX   PEKERJAAN COMMISIONING LOT 1.00 0.5901 0.0000 - 0.0000 0.0000

                     
                     
  TOTAL     100.0000 72.1256 1.2692 73.3949  
                     
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
PROGRESS PEKERJAAN - S CURVE Overall

Plan & Aktual Progress

Komulatif s/d Bulan


Progres Bulan Lalu Bulan Ini Ini

Plan Progress 89.0640 % 5,1112 % 94.1750 %

Aktual Progress 72,1256 % 1,2693 % 73,3949 %

Deviasi - 16,9384 % - 3,8419 % - 20,7801 %


PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Engineering

Progress Engineering

A 100,00% 65

B 0,00% 0

STATUS CIVIL ( Pasca C 0,00% 0


Recheck )
BELUMSUBMIT 0,00% 0

TOTAL 100,00% 65

A 100,00% 28

B 0,00% 0

STATUS ELMEK C 0,00% 0

BELUM SUBMIT 0,00% 0

TOTAL 100,00% 28
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
REKAP TOWER

REKAP TOWER ( RECHECK SURVEY )


PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Procurement

MATERIAL STUB MATERIAL TOWER MATERIAL ELMEK

SECTION TARIK
BELUM BELUM ON
ON SITE ON SITE ON SITE SITE ISOLATOR KONDUKTOR OPGW GSW FITTING ACC

Section Tarik 1
(T.61 - T.83) 21 1 13 8 100% 25% 100% 100% 100%

Section Tarik 2
(T.83 – T.106) 23 1 16 7 100% 25% 100% 100% 100%

Section Tarik 3
(T.106-T.126) 21 0 12 9 100% 25% 100% 100% 100%
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Procurement
SUB DETAIL PROGRESS

Lahan Bor Pile Pondasi Erection

Bebas Belum Bebas Finish On going Finish On Going Finish On Going

62 3 41 1 60 2 39 1

Titik Titik Titik Titik Titik Titik Titik Titik

TIM PEKERJA

Pembukaan Lahan Grup Langsir Grup Pondasi Grup Erection

5 6 12 13

Orang Orang Orang Orang


PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2

KEGIATAN YANG SEDANG BERJALAN

No. ITEM KEGIATAN

1. Pondasi a. Pengecoran Pad & Chimney T 65


b. Borpile T 64
c. Persiapan Pembersihan Lahan, T : 63, 62
d. Potong Bengkok Besi & Buat Bekisting

2. Erection - Pemasangan Insulator


- Sortir Material tower di gudang
- Persiapan Langsir Mat. Tower T. 66
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress
Dokumentasi Progress T. 65 & 64
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress
Dokumentasi Progress T. 65 & 64
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress
Dokumentasi Progress T. 67 (Erection)
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress
Dokumentasi Progress Pemasangan Insulator
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Foto Progress
Dokumentasi Progress T.
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2

Rencana Kegiatan Bulan Depan

No. ITEM KEGIATAN

1. Persiapan a. Pembersihan Lahan (Tapak Tower) yang bebas.


b. Potong, Bengkok, Pembesian untuk Pondasi
c. Pembuatan Bekisting
d. Pembuatan Jalan Masuk & Langsir Material

2. Pondasi Grup Pondasi :


- 2 Grup : : T 95 dan 94

3. Erection Grup Erection :


- 1 Grup : T. 66 (Persiapan)
- Pemasangan Insulator
PT. PLN (PERSERO) UIP KALBAGBAR
UPP KITRING KBB 2
KENDALA DAN PERMASALAHAN

NO Terkait PLN Terkait Kontraktor

1 Tanah belum bebas sebanyak 3 Titik : 62, 63, 119 Sosialisasi dengan warga dan PT. SMA

2 Tower DD2 sebanyak 7 Set ( Sampai saat ini belum ada ) Belum mengetahui untuk pengganti PT. KAM

3 Tower AA2+9 = 7 Set, AA2+12 = 4 Set, AA2+15 = 5 Set (sampai Belum mengetahui untuk pengganti PT. KAM
saat ini belum ada )

7
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2

Anda mungkin juga menyukai