II. PEKERJAAN PENGANGKUTAN MATERIAL
A. PENGIRIMAN DARI PABRIK KE GUDANG SITE LOT 1.00 7.1900 5.5163 0.0861 5.6024 77.9198
B. PENGANGKUTAN DARI GUDANG SITE KE TEPI JALAN LOT 1.00 0.6699 0.2182 - 0.2182 32.5670
C. LANGSIR DARI TEPI JALAN - LOKASI TITIK TOWER LOT 1.00 10.6944 9.6623 0.0094 9.6717 90.4364
III. PEKERJAAN PONDASI TOWER LOT 1.00 27.2384 25.6401 0.4332 26.0733 95.7225
IV. PEKERJAAN PENGADAAN & PEMASANGAN ACCESSORIES TOWER LOT 1.00 6.0737 0.4062 0.7214 1.1276 18.5659
V. PEKERJAAN ERECTION , FINAL CHEK LOT 1.00 5.5471 2.9642 0.0038 2.9680 53.5050
VI. PENGADAAN KONDUKTOR, GSW, DAN OPGW LOT 1.00 3.5265 3.5265 - 3.5265 100.0000
VII. PENGADAAN INSULATOR SET + HARDWARE, ACCESSORIES + FITTING LOT 1.00 22.3314 22.3314 - 22.3314 100.0000
VIII. PEKERJAAN STRINGING / PENARIKAN KAWAT LOT 1.00 14.1952 0.0000 - 0.0000 0.0000
TOTAL 100.0000 72.1256 1.2692 73.3949
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
PROGRESS PEKERJAAN - S CURVE Overall
Progress Engineering
A 100,00% 65
B 0,00% 0
TOTAL 100,00% 65
A 100,00% 28
B 0,00% 0
TOTAL 100,00% 28
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
REKAP TOWER
SECTION TARIK
BELUM BELUM ON
ON SITE ON SITE ON SITE SITE ISOLATOR KONDUKTOR OPGW GSW FITTING ACC
Section Tarik 1
(T.61 - T.83) 21 1 13 8 100% 25% 100% 100% 100%
Section Tarik 2
(T.83 – T.106) 23 1 16 7 100% 25% 100% 100% 100%
Section Tarik 3
(T.106-T.126) 21 0 12 9 100% 25% 100% 100% 100%
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2
Progress Procurement
SUB DETAIL PROGRESS
62 3 41 1 60 2 39 1
TIM PEKERJA
5 6 12 13
1 Tanah belum bebas sebanyak 3 Titik : 62, 63, 119 Sosialisasi dengan warga dan PT. SMA
2 Tower DD2 sebanyak 7 Set ( Sampai saat ini belum ada ) Belum mengetahui untuk pengganti PT. KAM
3 Tower AA2+9 = 7 Set, AA2+12 = 4 Set, AA2+15 = 5 Set (sampai Belum mengetahui untuk pengganti PT. KAM
saat ini belum ada )
7
PT. PLN (PERSERO) UIP KALBABAR
UPP KITRING KBB 2