BOBOT MINGGU DESEMBER JANUARI

NO. JENIS PEKERJAAN


PEK. 02/12/13 09/12/13 16/12/13 23/12/13 30/12/13 06/01/14 13/01/14 20/01/14
08/12/13 15/12/13 22/12/13 29/12/13 05/01/14 12/01/14 19/01/14 26/01/14

(%) 01- 07 08 - 14 15-21 22-28 29-35 36-42 43-49 50-56

1 2 3 4 5 6 7 8
I PEKERJAAN PERSIAPAN 1.7064 28 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061
II PEKERJAAN 1 TWIN BLOK
2.1. PEKERJAAN STRUKTUR
A. PEKERJAAN LANTAI DASAR 12.7200 8 1.500 1.600 1.700 1.700 1.700 1.600 1.500
A.1. PONDASI, PILE CAP & TIE BEAM 8.08044

A.2. LANTAI DASAR 4.63951

B. PEKERJAAN LANTAI 2 ELV. + 3.15 M 40,57 6.3589 6 1.000 1.200 1.200 1.200
C. PEKERJAAN LANTAI 3 ELV. + 5.95 M 6.1608 6 0.500 1.000
D. PEKERJAAN LANTAI 4 ELV. + 8.75 M 6.1608 6
E. PEKERJAAN LANTAI 5 ELV. + 11.55 M 5.9582 6
F. PEKERJAAN LANTAI ATAP ELV. + 14.27 M 3.2511 5
G. PEKERJAAN RANGKA ATAP BAJA RINGAN 0.8857 3
H. PEKERJAAN GROUND TANK DAN RUMAH POMPA 2.2284 6
I. PEKERJAAN SEPTIC TANK BIOTECH 2 BUAH 0.2526 2
J. PEKERJAAN SUMUR RESAPAN 2 BUAH 0.0816 2 3.5 BULAN = 14 MING
2.2. PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DAN PLESTERAN 14.3209 20 0.500
B. PEKERJAAN LANTAI 7.8367 16
C. PEKERJAAN KUSEN PINTU / JENDELA + ASSESORIES 8.7576 16
D. PEKERJAAN PENUTUP ATAP 0.7933 2
E. PEKERJAAN SANITAIR 1.5108 4
F. PEKERJAAN PLAFOND 0.5319 8
G. PEKERJAAN PENGECATAN 2.4962 10
H. PEKERJAAN CEROBONG SAMPAH 0.6108 10
I. PEKERJAAN ENTRANCE 0.2489 6
J. PEK. PERKERASAN DI DALAM & KELILING BAGIAN LUAR BANG. 0.5490 8
K. PEKERJAAN DRAINASE DI DALAM & KELILING BAGIAN LUAR BANG. (*) 0.7113 8
L. PEKERJAAN GROUND TANK DAN R. POMPA DI LUAR BANGUNAN 0.9130 5
2.3. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A. INSTALASI PLAMBING 4.2065 17 1
C. PEKERJAAN PEMADAM KEBAKARAN 0.3062 17
D. PEKERJAAN INSTALASI ELEKTRIKAL 4.0909 18 14.127

E PEKERJAAN INSTALASI ELEKTRONIK 0.6252 18 10.766


F PEKERJAAN LUAR BANGUNAN 4.9733 18 7.805
5.044
III PEK. PERKERASAN DI JALAN MASUK KE ENTRANCE 0.7533 9 3.283
1.622
- 0.061
TOTAL : 100 1 2 3 4 5 6 7 8

PROGRES RENCANA MINGGUAN 0.061 1.561 1.661 1.761 2.761 2.961 3.361 4.261

PROGRES KOMULATIF RENCANA MINGGUAN 0 0.061 1.622 3.283 5.044 7.805 10.766 14.127 18.388

PROGRES REALISASI MINGGUAN


PROGRES KOMULATIF REALISASI MINGGUAN 0
DEVIASI PROGRES REALISASI
25 %
3.33333
2013 - 2014

FEBRUARI MARET APRIL MEI

27/01/14 03/02/14 10/02/14 17/02/14 24/02/14 03/03/14 10/03/14 17/03/14 24/03/14 31/03/14 07/04/14 14/04/14 21/04/14 28/04/14 05/05/14 12/05/14 19/05/14
02/02/14 09/02/14 16/02/14 23/02/14 02/03/14 09/03/14 16/03/14 23/03/14 30/03/14 06/04/14 13/04/14 20/04/14 27/04/14 04/05/14 11/05/14 18/05/14 25/05/14

57-63 64-70 71-77 78-84 85-91 92-98 99-105 106-112 113-119 120-126 127-133 134-140 141-147 148-154 155-161 162-168 169-175

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061

1.420
8

85.659
1.000 0.759
1.200 1.200 1.200 1.061 81.438
0.500 1.200 1.200 1.200 1.061 1.000
0.500 1.200 1.200 1.058 1.000 1.000 77.437

0.650 0.650 0.650 0.650 0.650


72.940
0.295 0.295 0.295
0.371 0.371 0.371 68.751
0.371 0.371 0.371
0.126 0.126
MINGGU 40.57 64.913
0.041 0.041
61.004

57.016
0.500 0.500 0.750 0.750 0.750 0.750 0.750 0.750 1.000 1.000 0.821 0.750 0.750 0.750 0.750 0.750 0.750
0.300 0.300 0.400 0.40053.096 0.500 0.500 0.600 0.600 0.700 0.700 0.600 0.600 0.537
0.200 0.300 0.400 0.400 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700 0.700
48.825
0.397 0.397

44.816 0.378 0.378


0.066 0.066 0.066 0.066
40.049 0.250 0.250 0.250 0.250 0.250
0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061 0.061
35.189 0.041 0.041 0.041 0.041 0.041 0.041
0.069 0.069 0.069 0.069
30.499
0.089 0.089 0.089 0.089
26.788 0.183 0.183
48.825

44.816

40.049

35.189

30.499

26.788

23.068

18.388 0.200 0.200 0.200 0.200 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.206 0.200
0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018 0.018
127 0.200 0.200 0.200 0.200 0.300 0.300 0.300 0.300 0.300 0.200 0.200 0.200 0.200 0.200
0.020 0.030 0.030 0.030 0.030 0.040 0.040 0.040 0.040 0.040 0.040 0.040 0.040
0.200 0.200 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300 0.300

0.084 0.084 0.084 0.084

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

4.681 3.720 3.711 4.690 4.860 4.767 4.009 4.270 3.920 3.988 3.909 3.838 4.189 4.497 4.000 4.221 4.151

23.068 26.788 30.499 35.189 40.049 44.816 48.825 53.096 57.016 61.004 64.913 68.751 72.940 77.437 81.438 85.659 89.810

25 % 50 % 75 %
(STRUKTU, ARSITEKTUR, ME)
MEI JUNI
SKALA
26/05/14 02/06/14 09/06/14 16/06/14 23/06/14
01/06/14 08/06/14 15/06/14 22/06/14 29/06/14

176-182 183-189 190-196 197-203 204-210

26 27 28 29 30
0.061 0.061 0.061 100

99.441 100.000
98.463
96.341

93.204
89.810

85.659

81.438

77.437

75
72.940

68.751

64.913

0.500 0.500
0.400 0.400 0.300
0.558 0.300 0.300 50

0.378 0.378
0.066 0.066 0.066 0.066
0.250 0.250 0.250 0.250 0.250

0.069 0.069 0.069 0.069


0.089 0.089 0.089 0.089
0.183 0.183 0.183 25
0.200 0.200 0.200
0.018 0.018 0.018
0.200 0.200 0.200 0.191
0.040 0.040 0.030 0.030 0.025
0.300 0.300 0.273 0.200 0.200

0.084 0.084 0.084 0.084 0.084


0
26 27 28 29 30

3.394 3.137 2.122 0.978 0.559

93.204 96.341 98.463 99.441 100.000

FINISHING
R E KAP ITU LAS I
RENCANA ANGGARAN BIAYA (RAB)

Pekerjaan : RUSUNAWA BERBASIS DESAIN PROTOTYPE T-24


Lokasi : KEL. SUKAKARYA, KEC. WARUDOYONG, SUKABUMI - JAWA BARAT
Tahun Anggaran : 2013
Zone : 3-4
Pondasi : Tiang Pancang 25x25, Kedalaman = 9 M

JUMLAH HARGA
No. JENIS PEKERJAAN
( Rp. )

I. PEKERJAAN PERSIAPAN TOTAL I : Rp 209,531,720.10

A. PEKERJAAN PERSIAPAN Rp 209,531,720.10

II. PEKERJAAN 1 TWIN BLOK TOTAL II : Rp 11,977,012,328.41

2.1. PEKERJAAN STRUKTUR Rp 5,409,890,189.74


A. LANTAI DASAR Rp 1,561,888,864.21
A.1. PONDASI, PILE CAP & TIE BEAM (*) Rp 992,201,183.35
A.2. LANTAI DASAR Rp 569,687,680.86
B. LANTAI 2 Elev. +3.15 Rp 780,809,808.86
C. LANTAI 3 Elev. +5.95 Rp 756,485,073.28
D. LANTAI 4 Elev. +8.75 Rp 756,485,073.28
E. LANTAI 5 Elev. +11.55 Rp 731,608,217.21
F. LANTAI ATAP Elv.+14.55 ; +14.27 Rp 399,201,472.95
G. ATAP BAJA RINGAN Rp 108,751,500.00
H. GROUND TANK + RUMAH POMPA (*) Rp 273,625,600.21
I. PEKERJAAN SEPTIC TANK BIOTECH 2 (DUA) BUAH Rp 31,012,878.38
J. PEKERJAAN SUMUR RESAPAN 2 (DUA) BUAH Rp 10,021,701.38

2.2. PEKERJAAN ARSITEKTUR (2 TB) Rp 4,823,247,905.26


A. PEKERJAAN PASANGAN DAN PLESTERAN Rp 1,758,474,382.37
B. PEKERJAAN LANTAI Rp 962,267,650.37
C. PEKERJAAN KUSEN PINTU / JENDELA + ASSESORIES Rp 1,075,350,765.78
D. PEKERJAAN PENUTUP ATAP Rp 97,403,967.07
E. PEKERJAAN SANITAIR Rp 185,508,922.34
F. PEKERJAAN PLAFOND Rp 65,308,777.23
G. PEKERJAAN PENGECATAN Rp 306,511,999.41
H. PEKERJAAN CEROBONG SAMPAH Rp 75,000,000.00
I. PEKERJAAN ENTRANCE Rp 30,556,863.46
J. PEK. PERKERASAN DI DALAM & KELILING BAGIAN LUAR BANG. Rp 67,409,070.85
K. PEKERJAAN DRAINASE DI DALAM & KELILING BAGIAN LUAR BANG. (*) Rp 87,346,653.89
L. PEKERJAAN GROUND TANK DAN R. POMPA DI LUAR BANGUNAN Rp 112,108,852.50
REKAPITULASI PEK. STRUKTUR, ARSITEKTUR, M/E (ZONE 3 - 4) 7/12
JUMLAH HARGA
No. JENIS PEKERJAAN
( Rp. )

2.3. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL (2 TB) Rp 1,743,874,233.40


A. PEKERJAAN INSTALASI PLAMBING Rp 516,512,361.50
B. PEKERJAAN PEMADAM KEBAKARAN Rp 37,592,900.00
C. PEKERJAAN INSTALASI ELEKTRIKAL Rp 502,321,467.90
D. PEKERJAAN INSTALASI ELEKTRONIK Rp 76,772,729.00
E. PEKERJAAN LUAR BANGUNAN Rp 610,674,775.00

III. PEK. PERKERASAN DI JALAN MASUK KE ENTRANCE TOTAL III : Rp 92,497,977.75

REKAPITULASI PEK. STRUKTUR, ARSITEKTUR, M/E (ZONE 3 - 4) 8/12


JUMLAH HARGA
No. JENIS PEKERJAAN
( Rp. )

SUB TOTAL I + II + III : Rp 12,279,042,026.25

DIBULATKAN : Rp 12,279,040,000.00

PPN 10 % : Rp 1,227,904,000.00

TOTAL : Rp 13,506,944,000.00
DI BULATKAN : Rp 13,506,944,000.00

Terbilang : Tiga Belas Milyar Lima Ratus Enam Juta Sembilan Ratus E

CATT : ITEM PEKERJAAN YANG MASUK UNIT PRICES

REKAPITULASI PEK. STRUKTUR, ARSITEKTUR, M/E (ZONE 3 - 4) 9/12


ITEM PEKERJAAN DENGAN ITEM PEKERJAAN DENGAN
KONTRAK LUMPSUM KONTRAK UNIT PRICES

JUMLAH HARGA JUMLAH HARGA


( Rp. ) ( Rp. )

1.71 Rp 209,531,720.10 Rp -
-
1.71 Rp 209,531,720.10 Rp -
-
97.54 Rp 10,897,464,491.17 Rp 1,079,547,837.24
-
44.06 Rp 4,417,689,006.39 Rp 992,201,183.35
12.72
8.08 Rp 992,201,183.35
4.64 Rp 569,687,680.86
6.36 Rp 780,809,808.86
6.16 Rp 756,485,073.28
6.16 Rp 756,485,073.28
5.96 Rp 731,608,217.21
3.25 Rp 399,201,472.95
0.89 Rp 108,751,500.00
2.23 Rp 273,625,600.21 Rp -
0.25 Rp 31,012,878.38
0.08 Rp 10,021,701.38
-
39.28 Rp 4,735,901,251.38 Rp 87,346,653.89
14.32 Rp 1,758,474,382.37
7.84 Rp 962,267,650.37
8.76 Rp 1,075,350,765.78
0.79 Rp 97,403,967.07
1.51 Rp 185,508,922.34
0.53 Rp 65,308,777.23
2.50 Rp 306,511,999.41
0.61 Rp 75,000,000.00
0.25 Rp 30,556,863.46
0.55 Rp 67,409,070.85
0.71 Rp 87,346,653.89
0.91 Rp 112,108,852.50
REKAPITULASI PEK. STRUKTUR, ARSITEKTUR, M/E (ZONE 3 - 4) 10/12
ITEM PEKERJAAN DENGAN ITEM PEKERJAAN DENGAN
KONTRAK LUMPSUM KONTRAK UNIT PRICES

JUMLAH HARGA JUMLAH HARGA


( Rp. ) ( Rp. )

-
14.20 Rp 1,743,874,233.40 Rp -
4.21 Rp 516,512,361.50
0.31 Rp 37,592,900.00
4.09 Rp 502,321,467.90
0.63 Rp 76,772,729.00
4.97 Rp 610,674,775.00
-
0.75 Rp 92,497,977.75

REKAPITULASI PEK. STRUKTUR, ARSITEKTUR, M/E (ZONE 3 - 4) 11/12


ITEM PEKERJAAN DENGAN ITEM PEKERJAAN DENGAN
KONTRAK LUMPSUM KONTRAK UNIT PRICES

JUMLAH HARGA JUMLAH HARGA


( Rp. ) ( Rp. )

Rp 11,106,996,211.27 Rp 1,172,045,814.98

Rp 11,106,990,000.00 Rp 1,172,040,000.00

Rp 1,110,699,000.00 Rp 117,204,000.00

Rp 12,217,689,000.00 Rp 1,289,244,000.00
Rp 12,217,689,000.00 Rp 1,289,244,000.00

us Enam Juta Sembilan Ratus Empat Puluh Empat Ribu Rupiah

BANDUNG, 25 OKTOBER 2013


PT. MARGUSTA BANGUN PERKASA

Ir. H. MARWAL RASJID, MBA


DIREKTUR UTAMA

REKAPITULASI PEK. STRUKTUR, ARSITEKTUR, M/E (ZONE 3 - 4) 12/12