IV PEKERJAAN ARSITEKTUR
I LANTAI DASAR 7.26 39 2.810 14 1.050 53 3.860
II LANTAI 1 6.96 73 5.072 3 0.182 75 5.254
III LANTAI 2 6.86 75 5.160 1 0.065 76 5.225
IV LANTAI 3 6.90 44 3.042 28 1.921 72 4.963
V LANTAI 4 ( MEZZANINE ) 4.37 24 1.056 26 1.118 50 2.173
VI LANTAI 5 (Dak Beton) 1.46 24 0.355 0 0.005 25 0.361
IV ATAP 0.41 95 0.388 - - 95 0.388
34.23 17.88 4.34 22.22
VI PEKERJAAN ME
I PERSIAPAN 1.81 80 1.449 - - 80 1.449
II PEKERJAAN VAC 0.64 - - - - - -
III PEKERJAAN PLUMBING 5.24 80 4.193 - - 80 4.193
IV PEKERJAAN FIRE FIGHTING 5.07 75 3.802 5 0.253 80 4.056
V PEKERJAAN ELEKTRIKAL 6.26 75 4.692 5 0.313 80 5.005
VI PEKERJAAN GENSET -
PEKERJAAN PERSIAPAN 0.71 25 0.178 - - 25 0.178
PEKERJAAN GENSET 0.80 - - - - - -
20.53 14.31 0.57 14.88