Anda di halaman 1dari 3

JADWAL PEMBANGUNAN GUDANG BAHAN PELEDAK DAN KURVA S PROGRES PEMBANGUNAN

WAKTU PE
PERKIRAAN BIAYA BOBOT PEKERJAAN AKUMULASI BOBOT DURASI PEKERJAAN MING
NO KEGIATAN
(RP) (%) (%) (HARI)
I II
1 PENENTUAN LAHAN - 0.00 0.00 1
2 CLEARING LAHAN 5,000,000 2.00 2.00 2
3 PEMBUATAN DRAINASE 3,000,000 1.20 3.20 1
4 PEMADATAN DAN PENATAAN LAHAN 15,000,000 6.00 9.20 3
5 PEMBANGUNAN PONDASI 30,000,000 12.00 21.20 4
6 PEMBANGUNAN DINDING 80,000,000 32.00 53.20 7
7 PEMASANGAN ATAP 30,000,000 12.00 65.20 7
8 PEMBUATAN TANGGUL PENGAMAN 20,000,000 8.00 73.20 7
9 PEMASANGAN PAGAR PENGAMAN 15,000,000 6.00 79.20 7
10 PEMBANGUNAN POS JAGA 15,000,000 6.00 85.20 5
11 PEMASANGAN TIANG LAMPU DAN CCTV 15,000,000 6.00 91.20 2
12 PEMASANGAN PENANGKAL PETIR 10,000,000 4.00 95.20 1
13 INSTALASI HIDRANT/AIR BERTEKANAN 5,000,000 2.00 97.20 2
14 LAPORAN 80% 1,000,000 0.40 97.60 1
15 PEMASANGAN RAMBU K3 2,500,000 1.00 98.60 1
16 UJI COBA HIDRANT/AIR BERTEKANAN 250,000 0.10 98.70 1
17 UJI COBA LAMPU DAN CCTV 250,000 0.10 98.80 1
18 PENGUJIAN TAHANAN PEMBUMIAN 1,500,000 0.60 99.40 1
19 FINISHING AREA GUDANG HANDAK 1,000,000 0.40 99.80 1
20 LAPORAN 100% 500,000 0.20 100.00 1
TOTAL 250,000,000 100.00 100.00 56
BANGUNAN
WAKTU PELAKSANAAN
MINGGU KE JADWAL PEMBANGUNAN GUDANG BAHAN PELEDAK
III IV V VI VII VIII DAN KURVA S PROGRES PEMBANGUNAN
100.00

90.00

80.00

70.00

60.00

50.00

40.00

30.00

20.00

10.00

0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
JADWAL PEMBANGUNAN GUDANG BAHAN PELEDAK DAN KURVA S PROGRES
100.00 PEMBANGUNAN

90.00

80.00

70.00

60.00

50.00

40.00

30.00

20.00

10.00

0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Anda mungkin juga menyukai