Anda di halaman 1dari 318

RENCANA ANGGARAN BIAYA

Kegiatan :
Pekerjaan :
Lokasi :

HARGA SATUAN JUMLAH HARGA (RP) +


NO JENIS PEKERJAAN VOLUME SAT ( Rp ) PPN 10 % JUMLAH PPN 10% PPN 10%
1 2 3.00 4 5 6
I PEKERJAAN PERSIAPAN
1 Pek. Pasang Papan Nama Proyek 1.00 ls 100,000.00 10.00 10,000.00 110,000.00
2 Pek. Pengukuran dan Pemasangan Bowplank 78.00 m2
3 Pek. Perlengkapan Smkk (Sistem Manajemen Keselamatan Kontruksi)
- Sosialisasi dan Promosi K3 80,000.00 10.00 - -
Spanduk K3 1.00 bh 80,000.00 10.00 8,000.00 88,000.00
- Rambu - Rambu K3
Rambu - Rambu 1.00 bh 80,000.00 10.00 8,000.00 88,000.00
- Fasilitas Sarana Kesehatan
Kotak P3K 1.00 set 250,000.00 10.00 25,000.00 275,000.00
- Kelengkapan Pekerja
Helm proyek 10.00 bh 45,000.00 10.00 45,000.00 495,000.00
Rompi proyek 10.00 bh 25,000.00 10.00 25,000.00 275,000.00
Masker 10.00 bh 10,000.00 10.00 10,000.00 110,000.00
Sepatu proyek 10.00 Pasang 90,000.00 10.00 90,000.00 990,000.00
Sarung tangan proyek 10.00 Pasang 7,000.00 10.00 7,000.00 77,000.00

II PEKERJAAN STRUKTUR
PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi Telapak 164.25 m3 21,742.80 10.00 357,125.49 3,928,380.39
2 Pek. Galian Tanah Pondasi Menerus 53.88 m3 77,438.00 10.00 417,235.94 4,589,595.38
3 Pek. Urugan Pasir Bawah Pondasi Telapak t=50 mm 4.11 m3 150,975.20 10.00 62,050.81 682,558.88
4 Pek. Urugan Pasir Bawah Pondasi Menerus t=50 mm 0.69 m3 337,311.92 10.00 23,274.52 256,019.75
5 Pek. Urugan Tanah Kembali 72.71 m3 620,699.76 10.00 4,513,107.99 49,644,187.88
6 Pek. Urugan Tanah Peninggian Lantai + Dipadatkan 103.68 m3 57,703.80 10.00 598,273.00 6,581,002.98
7 Pek. Urugan Pasir Bawah Lantai t=50 mm 16.20 m3 27,478.00 10.00 44,514.36 489,657.96
8 Pek. Pembuangan Sisa Galian Sejauh 30 m 1,435.00 m3
544,522.83 10.00 - -

676,626.41 10.00 - -
10,628.79 10.00 - -
10,628.79 10.00 - -
88,516.72 10.00 - -

676,626.41 10.00 - -
23,733.12 10.00 - -

676,626.41 10.00 - -
10,628.79 10.00 - -
10,628.79 10.00 - -
141,457.76 10.00 - -

676,626.41 10.00 - -
10,628.79 10.00 - -
10,628.79 10.00 - -
294,915.52 10.00 - -

676,626.41 10.00 - -
10,628.79 10.00 - -
141,457.76 10.00 - -

135,272.00 10.00 - -
135,272.00 10.00 - -
65,979.60 10.00 - -
86,568.82 10.00 - -
56,654.40 10.00 - -
35,468.15 10.00 - -

129,060.40 10.00 - -

69,944.00 10.00 - -
NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN PPN 10 % JUMLAH PPN 10% JUMLAH HARGA (RP) +
( Rp ) PPN 10%
1 2 3.00 4 5 6

13,672.66 10.00 - -
13,672.66 10.00 - -
66,956.96 10.00 - -
53,756.96 10.00 - -

70,943.20 10.00 - -
31,075.12 10.00 - -
3 Pek. Pas. Bubungan Atap Genteng Metal Prima Roof 42.64 m1 42,765.76 10.00 182,353.20 2,005,885.21
4 Pek. Pas. Tatab Fibercement Uk. 8x100x3000 mm 62.00 m1 33,124.00 10.00 205,368.80 2,259,056.80
5 Pek. Pas. Listplank Fibercement Uk. 16x240x3000 mm x 2 62.00 m1 33,774.00 10.00 209,398.80 2,303,386.80
6 Pek. Pas. Murda Fibercemet 2.00 bh 7,507.98 10.00 1,501.60 16,517.55
7 Pek. Pas. Ikut Celedu Fibercemet 4.00 bh 7,507.98 10.00 3,003.19 33,035.09
VIII PEKERJAAN MEKANIKAL ELEKTRIKAL
A PEKERJAAN PANEL
Pengadaan, Pemasangan dan Pengetesan lengkap dengan fitting dan acecories lainnya
Power Panel (PP) 1.00 unit 5,000,000.00 10.00 500,000.00 5,500,000.00
B PEKERJAAN INSTALASI LISTRIK
- Pekerjaan Instalasi titik lampu dan stopkontak dengan
kabel NYM 3 x 2.5 mm2 didalam konduit high impact
1 Instalasi Titik Lampu NYM D106 mm2 didalam konduit 14.00 titik 29,478.40 10.00 41,269.76 453,967.36
2 Instalasi Titik Stop kontak NYM 3x2.5 mm2 didalam konduit 38.00 titik 112,200.00 10.00 426,360.00 4,689,960.00
C Aksesoris
1 Lampu TL 36 Watt RMI Philips TL LED 14.00 bh 28,728.00 10.00 40,219.20 442,411.20
2 Stop kontak Clipsal Classic E426/16S 38.00 bh 79,928.00 10.00 303,726.40 3,340,990.40
3 Saklar Seri Clipsal Classic E32/1/2A 1.00 bh 29,928.00 10.00 2,992.80 32,920.80
IX PEKERJAAN PEMBUATAN PAGAR TYPE I
A PEKERJAAN TANAH DAN PONDASI
1 Pek. Pengukuran Dan Pemasangan Bowplank 9.58 m1 21,742.80 10.00 20,829.60 229,125.63
2 Pek. Galian Pondasi Menerus 6.13 m3 77,438.00 10.00 47,469.49 522,164.43
3 Pek. Urugan Pasir Dibawah Pondasi T=5 cm 0.38 m3 150,975.20 10.00 5,737.06 63,107.63
4 Pek. Pondasi Batu Kosong T=20 cm 1.53 m3 337,311.92 10.00 51,608.72 567,695.97
5 Pek. Pondasi Batu Kali 1 PC 5 PS 3.03 m3 620,699.76 10.00 188,072.03 2,068,792.32
6 Pek. Urugan Tanah Kembali 2.04 m3 57,703.80 10.00 11,771.58 129,487.33
NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN PPN 10 % JUMLAH PPN 10% JUMLAH HARGA (RP) +
( Rp ) PPN 10%
1 2 3.00 4 5 6
B PEKERJAAN BETON
1 Pek. Beton Rabatan Lantai Kerja T = 5 cm, K - 100 0.38 m3 544,522.83 10.00 20,691.87 227,610.54
2 Pekerjaan Beton Sloof 15/20
- Beton K250 0.28 m3 676,626.41 10.00 18,945.54 208,400.93
- Pembesian 610 23.61 kg 10,628.79 10.00 25,094.58 276,040.36
- Pembesian sengkang 8-150 16.87 kg 10,628.79 10.00 17,930.77 197,238.49
- Bekisting (2x Pakai) 3.83 m2 88,516.72 10.00 33,901.90 372,920.94
3 Pekerjaan Beton Kolom 15/15
- Beton K250 0.18 m3 676,626.41 10.00 12,179.28 133,972.03
- Pembesian 410 26.61 kg 10,628.79 10.00 28,283.22 311,115.37
- Pembesian sengkang 8-150 16.42 kg 10,628.79 10.00 17,452.48 191,977.24
- Bekisting (2x Pakai) 2.52 m2 141,457.76 10.00 35,647.36 392,120.91
4 Pekerjaan Ring Balok 15/20
- Beton K250 0.27 m3 676,626.41 10.00 18,268.91 200,958.04
- Pembesian 510 29.51 kg 10,628.79 10.00 31,365.57 345,021.22
- Pembesian sengkang 8-150 16.87 kg 10,628.79 10.00 17,930.77 197,238.49
- Bekisting (2x Pakai) 3.83 m2 147,457.76 10.00 56,476.32 621,239.54
C PEKERJAAN PASANGAN DINDING
1 Pek. Pas. Pengeresek Pada Bagian Bawah Dinding 2.45 m3 544,522.83 10.00 133,408.09 1,467,489.04
2 Pek. Pas. Peengeresek Pada Bagian Bawah Paduraksa 0.23 m3 544,522.83 10.00 12,524.03 137,764.28
3 Pek. Pas. Bata Merah Tebal 1/2 Bata Camp. 1PC 5 PS Pada Pembatas Los Pada Dinding 8.14 m2 135,272.00 10.00 110,111.41 1,211,225.49
4 Pek. Pas. Bata Merah Tebal 1/2 Bata Camp. 1PC 5 PS Pada Pembatas Los Pada Paduraksa 3.08 m2 135,272.00 10.00 41,663.78 458,301.54
5 Pek. Pas. Andesit 30 x30, t=3 cm 14.32 m2 215,601.25 10.00 308,740.99 3,396,150.89
D PEKERJAAN FINISHING
1 Pek. Fin. Coating Batu Alam, Propan, 2 Lapis 14.32 m2 22,362.26 10.00 32,022.75 352,250.26
X PEKERJAAN PEMBUATAN PAGAR TYPE II
A PEKERJAAN TANAH DAN PONDASI
1 Pek. Pengukuran Dan Pemasangan Bowplank 130.95 m1 21,742.80 10.00 284,721.97 3,131,941.63
2 Pek. Galian Pondasi Menerus 125.71 m3 77,438.00 10.00 973,473.10 10,708,204.08
3 Pek. Urugan Pasir Dibawah Pondasi T=5 cm 5.24 m3 150,975.20 10.00 79,111.00 870,221.05
4 Pek. Pondasi Batu Kosong T=20 cm 20.95 m3 337,311.92 10.00 706,668.48 7,773,353.30
5 Pek. Pondasi Batu Kali 1 PC 5 PS 71.47 m3 620,699.76 10.00 4,436,141.22 48,797,553.40
6 Pek. Urugan Tanah Kembali 41.90 m3 57,703.80 10.00 241,778.92 2,659,568.14
B PEKERJAAN BETON - -
1 Pek. Beton Rabatan Lantai Kerja T = 5 cm, K - 100 5.24 m3 544,522.83 10.00 285,329.97 3,138,629.62
2 Pekerjaan Beton Sloof 15/20
- Beton K250 3.86 m3 676,626.41 10.00 261,177.79 2,872,955.72
- Pembesian 410 322.66 kg 10,628.79 10.00 342,948.60 3,772,434.63
- Pembesian sengkang 8-150 227.81 kg 10,628.79 10.00 242,134.51 2,663,479.62
- Bekisting (2x Pakai) 52.38 m2 88,516.72 10.00 463,650.58 5,100,156.37
3 Pekerjaan Beton Kolom 15/15
- Beton K250 2.04 m3 676,626.41 10.00 138,031.79 1,518,349.65
- Pembesian 410 282.79 kg 10,628.79 10.00 300,571.61 3,306,287.70
- Pembesian sengkang 8-150 172.69 kg 10,628.79 10.00 183,548.61 2,019,034.70
- Bekisting (2x Pakai) 28.02 m2 141,457.76 10.00 396,364.64 4,360,011.08
4 Pekerjaan Ring Balok 15/20 - -
Beton K250 3.77 m3 676,626.41 10.00 255,088.15 2,805,969.70
Pembesian 510 403.33 kg 10,628.79 10.00 428,691.07 4,715,601.75
Pembesian sengkang 8-150 230.81 kg 10,628.79 10.00 245,323.15 2,698,554.63
NO JENIS PEKERJAAN VOLUME SAT HARGA SATUAN PPN 10 % JUMLAH PPN 10% JUMLAH HARGA (RP) +
( Rp ) PPN 10%
1 2 3.00 4 5 6
Bekisting (2x Pakai) 52.38 m2 147,457.76 10.00 772,383.75 8,496,221.22
C PEKERJAAN PASANGAN DINDING
1 Pek. Pas. Pengeresek Pada Bagian Bawah Dinding 33.52 m3 544,522.83 10.00 1,825,240.54 20,077,645.95
2 Pek. Pas. Peengeresek Pada Bagian Bawah Paduraksa 4.12 m3 544,522.83 10.00 224,343.41 2,467,777.48
3 Pek. Pas. Bata Merah Tebal 1/2 Bata Camp. 1PC 5 PS Pada Pembatas Los Pada Dinding 229.16 m2 135,272.00 10.00 3,099,893.15 34,098,824.67
4 Pek. Pas. Bata Merah Tebal 1/2 Bata Camp. 1PC 5 PS Pada Pembatas Los Pada Paduraksa 74.73 m2 135,272.00 10.00 1,010,887.66 11,119,764.22
5 Pek. Plesteran Camp. 1 PC 5 PS , Tebal 15 mm Pada Dinding 458.32 m2 56,654.40 10.00 2,596,584.46 28,562,429.07
6 Pek. Plesteran Camp. 1 PC 5 PS , Tebal 15 mm Pada Paduraksa 74.73 m2 56,654.40 10.00 423,378.33 4,657,161.64
7 Pek. Acian semen 533.06 m2 35,468.15 10.00 1,890,665.20 20,797,317.24
8 Pek. Cat Texture KCA 533.06 m2 19,384.48 10.00 1,033,309.09 11,366,400.00
D PEKERJAAN PEMBUATAN CANDI BENTAR
PEKERJAAN TANAH DAN PONDASI
1 Pek. Pengukuran Dan Pemasangan Bowplank 2.50 m1 21,742.80 10.00 5,435.70 59,792.70
2 Pek. Galian Pondasi Telapak 4.25 m3 94,424.40 10.00 40,130.37 441,434.07
3 Pek. Galian Pondasi Menerus 13.07 m3 77,438.00 10.00 101,211.47 1,113,326.13
4 Pek. Urugan Pasir Dibawah Pondasi T=5 cm 0.44 m3 150,975.20 10.00 6,642.91 73,072.00
5 Pek. Pondasi Batu Kosong T=20 cm 1.77 m3 337,311.92 10.00 59,704.21 656,746.32
6 Pek. Pondasi Batu Kali 1 PC 5 PS 7.02 m3 620,699.76 10.00 435,731.23 4,793,043.58
7 Pek. Urugan Tanah Kembali 8.61 m3 57,703.80 10.00 49,682.97 546,512.69
E PEKERJAAN BETON
1 Pekerjaan Beton Rabat T=5 cm Lantai Kerja Pondasi Telapak 0.12 m3 472,674.46 10.00 5,672.09 62,393.03
2 Pekerjaan Pondasi Telapak
- Beton K250 0.93 m3 676,626.41 10.00 62,926.26 692,188.81
- Pembesian Tulangan Bawah dia. 19mm 201.99 kg 10,628.79 10.00 214,690.97 2,361,600.67
- Pembesian Tulangan Atas dia. 13 mm 54.57 kg 10,628.79 10.00 58,001.32 638,014.50
- Bekesting Batako 3.52 m2 179,731.00 10.00 63,265.31 695,918.43
3 Pekerjaan Beton Kolom Struktur 30/30
Beton K250 1.90 m3 676,626.41 10.00 128,559.02 1,414,149.19
Pembesian 12D16 422.53 kg 10,628.79 10.00 449,098.35 4,940,081.83
Pembesian sengkang 10 - 150 mm 126.42 kg 10,628.79 10.00 134,369.19 1,478,061.07
Bekisting (2x Pakai) 25.34 m2 141,457.76 10.00 358,453.96 3,942,993.60
4 Pekerjaan Beton Sloof 20/30
Beton K250 0.60 m3 676,626.41 10.00 40,597.58 446,573.43
Pembesian 6D13 62.98 kg 10,628.79 10.00 66,940.13 736,341.45
Pembesian sengkang 8 - 150 mm 20.27 kg 10,628.79 10.00 21,544.56 236,990.18
Bekisting (2x Pakai) 2.02 m2 88,516.72 10.00 17,880.38 196,684.15
F PEKERJAAN PASANGAN DINDING
Pek. Pas. Andesit 30 x30, t=3 cm 137.18 m2 215,601.25 10.00 2,957,617.95 32,533,797.42
G PEKERJAAN FINISHING
Pek. Fin. Coating Batu Alam, Propan, 2 Lapis 138.18 m2 22,362.26 10.00 309,001.65 3,399,018.19
TOTAL SELURUH PEKERJAAN + PPN 10% 420,051,525.03
RENCANA ANGGARAN BIAYA ( RAB )
Kegiatan : Penataan Bangunan dan Pengembangan Kawasan Permukiman
Pekerjaan : Pembangunan Wantilan dan Penataan Halaman Pura Ponjok Batu
Lokasi : Desa Penuktukan, Kec. Tejakula Kab. Buleleng

Satuan HARGA SATUAN PPN 10 JUMLAH HARGA (RP) +


NO Jenis Barang/Jasa Unit Volume ( Rp ) % JUMLAH PPN 10% PPN 10% KET.

a b c d e f g h i
I PEKERJAAN PERSIAPAN
1 Pek. Pasang Papan Nama Proyek ls 1.00 100,000.00 10.00 10,000.00 110,000.00
2 Pek. Pengukuran dan Pemasangan Bowplank m1 78.00 54,182.80 10.00 422,625.84 4,648,884.24
3 Pek. Perlengkapan Smkk (Sistem Manajemen Keselamatan Kontruksi)
Sosialisasi dan Promosi K3
Spanduk K3 Bh 1.00 80,000.00 10.00 8,000.00 88,000.00
Rambu - Rambu K3
Rambu - Rambu Bh 1.00 100,000.00 10.00 10,000.00 110,000.00
Fasilitas Sarana Kesehatan
Kotak P3K Set 1.00 200,000.00 10.00 20,000.00 220,000.00
Kelengkapan Pekerja
Helm proyek Bh 10.00 50,000.00 10.00 50,000.00 550,000.00
Rompi proyek Bh 10.00 25,000.00 10.00 25,000.00 275,000.00
Masker Bh 10.00 7,000.00 10.00 7,000.00 77,000.00
Sepatu proyek Pasang 10.00 90,000.00 10.00 90,000.00 990,000.00
Sarung tangan proyek Pasang 10.00 9,000.00 10.00 9,000.00 99,000.00
II PEKERJAAN STRUKTUR
PEKERJAAN TANAH DAN PASIR
1 Pek. Galian Tanah Pondasi Telapak m3 164.25 94,424.40 10.00 1,550,920.77 17,060,128.47
2 Pek. Galian Tanah Pondasi Menerus m3 53.88 77,438.00 10.00 417,235.94 4,589,595.38
3 Pek. Urugan Pasir Bawah Pondasi Telapak t=50 mm m3 4.11 150,975.20 10.00 62,050.81 682,558.88
4 Pek. Urugan Pasir Bawah Pondasi Menerus t=50 mm m3 0.69 150,975.20 10.00 10,417.29 114,590.18
5 Pek. Urugan Tanah Kembali m3 72.71 54,956.00 10.00 399,585.08 4,395,435.84
6 Pek. Urugan Tanah Peninggian Lantai + Dipadatkan m3 103.68 153,975.20 10.00 1,596,414.87 17,560,563.61
7 Pek. Urugan Pasir Bawah Lantai t=50 mm m3 16.20 150,975.20 10.00 244,579.82 2,690,378.06
8 Pek. Pembuangan Sisa Galian Sejauh 30 m m3 1,435.00 38,972.80 10.00 5,592,596.80 61,518,564.80
III PEKERJAAN PONDASI
1 Pek. Pasangan Pondasi Batu Kosong m3 2.07 337,311.92 10.00 69,823.57 768,059.25
2 Pek. Pasangan Pondasi Batu Belah 1 PC5 PP m3 45.46 620,699.76 10.00 2,821,701.13 31,038,712.43
IV PEKERJAAN BETON
Lantai 1
1 Pek. Beton Rabat Bawah Pondasi Telapak t=50 mm m3 3.81 581,877.23 10.00 221,695.23 2,438,647.49
2 Pek. Beton Rabat Bawah Lantai t=50 mm m3 16.20 729,092.68 10.00 1,181,130.13 12,992,431.48
3 Pek. Pondasi Telapak P1 1750 x 1500 mm
Beton K250 m3 24.15 786,433.95 10.00 1,899,237.98 20,891,617.76
Pembesian Pondasi kg 3,600.53 10,628.79 10.00 3,826,928.45 42,096,212.91
Bekisting Batako m2 64.40 129,823.00 10.00 836,060.12 9,196,661.32
4 Pek. Pondasi Telapak P2 1200 x 1200 mm
Beton K250 m3 1.30 786,433.95 10.00 102,236.41 1,124,600.54
Pembesian Pondasi kg 266.23 10,628.79 10.00 282,970.33 3,112,673.62
Bekisting Pondasi m2 4.32 167,233.44 10.00 72,244.85 794,693.31
5 Pek. Kolom Pedestal C1 400 x 400 mm
Beton K250 m3 3.12 786,433.95 10.00 245,367.39 2,699,041.30
Pembesian Kolom kg 814.76 10,628.79 10.00 865,991.46 9,525,906.03
Bekisting Kolom Pedestal m2 31.20 293,315.52 10.00 915,144.42 10,066,588.65
6 Pek. Kolom Pedestal C1A 400 x 400 mm
Beton K250 m3 2.40 786,433.95 10.00 188,744.15 2,076,185.62
Pembesian Kolom kg 1,158.27 10,628.79 10.00 1,231,101.09 13,542,112.00
Bekisting Kolom Pedestal m2 24.00 293,315.52 10.00 703,957.25 7,743,529.73
7 Pek. Kolom Pedestal C2 250 x 250 mm
Beton K250 m3 0.28 786,433.95 10.00 22,020.15 242,221.66
Pembesian Kolom kg 122.08 10,628.79 10.00 129,756.29 1,427,319.22
Bekisting Kolom Pedestal m2 4.50 293,315.52 10.00 131,991.98 1,451,911.82
8 Pek. Sloof-1 200 x 400 mm
Beton K250 m3 3.60 786,433.95 10.00 283,116.22 3,114,278.42
Pembesian Sloof kg 1,058.98 10,628.79 10.00 1,125,567.82 12,381,245.97
Bekisting Sloof m2 48.00 177,233.44 10.00 850,720.51 9,357,925.63
9 Pek. Sloof-2 200 x 350 mm
Beton K250 m3 5.05 786,433.95 10.00 397,149.14 4,368,640.57
Pembesian Sloof kg 1,506.54 10,628.79 10.00 1,601,270.03 17,613,970.33
Bekisting Sloof m2 70.70 177,233.44 10.00 1,253,040.42 13,783,444.63
10 Pek. Lantai Bawah t= 100 mm
Beton K250 m3 34.31 786,433.95 10.00 2,698,254.87 29,680,803.53
Pembesian Lantai Wiremesh M6 1 lapis kg 1,106.12 18,813.81 10.00 2,081,033.15 22,891,364.66
11 Pek. Kolom C1 400 x 400 mm
Beton K250 m3 5.99 786,433.95 10.00 471,073.93 5,181,813.27
Pembesian Kolom kg 1,193.90 10,628.79 10.00 1,268,971.48 13,958,686.25
Bekisting Kolom m2 70.30 293,315.52 10.00 2,062,008.11 22,682,089.16
12 Pek. Kolom C1A 400 x 400 mm
Beton K250 m3 4.61 786,433.95 10.00 362,546.05 3,988,006.54
Pembesian Kolom kg 1,502.21 10,628.79 10.00 1,596,667.76 17,563,345.39
Bekisting Kolom m2 54.08 293,315.52 10.00 1,586,250.33 17,448,753.65
13 Pek. Kolom C2 250 x 250 mm
Beton K250 m3 0.54 786,433.95 10.00 42,467.43 467,141.76
Pembesian Kolom kg 222.91 10,628.79 10.00 236,926.40 2,606,190.43
Bekisting Kolom m2 10.14 293,315.52 10.00 297,421.94 3,271,641.31
14 Pek. Tangga
Beton K250 m3 2.86 786,433.95 10.00 224,920.11 2,474,121.19
Pembesian Tangga kg 285.12 10,628.79 10.00 303,048.12 3,333,529.29
Bekisting Tangga m2 16.58 273,215.52 10.00 452,991.33 4,982,904.65
15 Pek. Beton Kolom Praktis m1 10.14 88,803.82 10.00 90,047.07 990,517.81
Pek. Meja Beton m3 0.45 786,433.95 10.00 35,389.53 389,284.80
Pembesian Meja kg 33.41 10,628.79 10.00 35,510.79 390,618.73
Bekisting Meja m2 3.75 313,315.52 10.00 117,493.32 1,292,426.52
Lantai 2
1 Pek. Balok Induk BI-1 300 x 500 mm
Beton K250 m3 5.86 786,433.95 10.00 460,850.29 5,069,353.21
Pembesian Balok kg 2,432.63 10,628.79 10.00 2,585,591.83 28,441,510.11
Bekisting Balok m2 58.59 305,315.52 10.00 1,788,843.63 19,677,279.95
2 Pek. Balok Induk BI-2 300 x 500 mm
Beton K250 m3 8.28 786,433.95 10.00 651,167.31 7,162,840.37
Pembesian Balok kg 1,123.98 10,628.79 10.00 1,194,654.96 13,141,204.60
Bekisting Balok m2 43.57 305,315.52 10.00 1,330,259.72 14,632,856.93
3 Pek. Balok Induk BI-3 250 x 450 mm
Beton K250 m3 5.45 786,433.95 10.00 428,606.50 4,714,671.50
Pembesian Balok kg 1,142.73 10,628.79 10.00 1,214,583.95 13,360,423.43
Bekisting Balok m2 11.83 305,315.52 10.00 361,188.26 3,973,070.86
4 Pek. Balok Induk BI-4 200 x 350 mm
Beton K250 m3 1.19 786,433.95 10.00 93,585.64 1,029,442.03
Pembesian Balok kg 291.50 10,628.79 10.00 309,829.29 3,408,122.15
Bekisting Balok m2 11.70 305,315.52 10.00 357,219.16 3,929,410.74
5 Pek. Balok Anak BA-1 250 x 350 mm
Beton K250 m3 2.84 786,433.95 10.00 223,347.24 2,456,819.65
Pembesian Balok kg 960.19 10,628.79 10.00 1,020,565.98 11,226,225.77
Bekisting Balok m2 35.07 305,315.52 10.00 1,070,741.53 11,778,156.82
6 Pek. Beton Pelat Lantai 2 t=120 mm
Beton K250 m3 26.67 786,433.95 10.00 2,097,419.33 23,071,612.66
Pembesian Pelat kg 5,247.77 10,628.79 10.00 5,577,745.58 61,355,201.37
Bekisting Pelat m2 188.21 313,315.52 10.00 5,896,911.40 64,866,025.42
V PEKERJAAN ARSITEKTUR
PEKERJAAN DINDING
Lantai 1
1 Pek. Pasangan Dinding Bata Merah 1PC 6PP m2 57.03 134,290.00 10.00 765,855.87 8,424,414.57
2 Pek. Plesteran Dinding 1PC 6PP t=15 mm m2 56.40 55,948.80 10.00 315,551.23 3,471,063.55
3 Pek. Acian Dinding m2 65.56 35,468.15 10.00 232,529.19 2,557,821.11
4 Pek. Acian Beton m2 446.33 35,468.15 10.00 1,583,049.94 17,413,549.33
Lantai 2
1 Pek. Pasangan Dinding Bata Merah 1PC 6PP m2 23.03 134,290.00 10.00 309,269.87 3,401,968.57

PEKERJAAN KUSEN, PINTU, DAN JENDELA


Lantai 1
1 Pek. Pintu P1
Kusen Kayu Profil 55 x 110 mm Kamper m1 0.03 8,994,814.00 10.00 26,984.44 296,828.86
Daun Pintu Panel Kayu Kamper m2 1.36 720,652.00 10.00 98,008.67 1,078,095.39
Engsel Pintu Solid ps 1.00 58,788.96 10.00 5,878.90 64,667.86
Kunci Tanam Biasa Solid bh 1.00 184,956.00 10.00 18,495.60 203,451.60
Handle Pintu Solid unit 1.00 280,000.00 10.00 28,000.00 308,000.00
Kunci Slot bh 1.00 62,478.00 10.00 6,247.80 68,725.80
2 Pek. Jendela J1
Kusen Kayu Profil 55 x 110 mm Kamper m1 0.06 8,994,814.00 10.00 53,968.88 593,657.72
Daun Jendela Kayu Kamper m2 0.59 888,652.00 10.00 52,430.47 576,735.15
Kaca Bening 5 mm m2 1.23 290,760.96 10.00 35,763.60 393,399.58
Engsel Jendela Solid ps 2.00 60,991.20 10.00 12,198.24 134,180.64
Grendel Jendela Solid bh 2.00 62,478.00 10.00 12,495.60 137,451.60
Kait Angin Solid bh 4.00 60,091.92 10.00 24,036.77 264,404.45
VI PEKERJAAN PENUTUP LANTAI DAN DINDING
Lantai 1
1 Pek. Lantai Granit 600 x 600 mm (Polished) m2 296.47 147,769.28 10.00 4,380,915.84 48,190,074.29
2 Pek. Border Batu Candi 250 x 300 mm m2 9.43 609,471.25 10.00 574,731.39 6,322,045.28
3 Pek. Lantai Batu Candi 300 x 300 mm m2 4.45 609,471.25 10.00 271,214.71 2,983,361.77
VII PEKERJAAN FINISHING
Lantai 1
1 Pek. Pengecatan Dinding Vinilex m2 511.89 22,772.66 10.00 1,165,709.49 12,822,804.37
2 Pek. Polituran Kayu Profil m2 7.08 66,956.96 10.00 47,405.53 521,460.80
3 Pek. Handraill Tangga Hollow Galvanis 2 + Fin. Cat ls 1.00 4,000,000.00 10.00 400,000.00 4,400,000.00
VIII PEKERJAAN STYLE BALI
Lantai 1
1 Pek. Tempelan Kolom dengan Batu Tabas Karangasem m2 70.99 713,971.25 10.00 5,068,481.90 55,753,300.94
2 Pek. Pengresek m3 3.55 918,409.09 10.00 326,035.23 3,586,387.49
IX PEKERJAAN ELEKTRIKAL DAN PLUMBING
PEKERJAAN INSTALASI LISTRIK
Lantai 1
1 Pek. Instalasi Titik Lampu titik 7.00 159,978.40 10.00 111,984.88 1,231,833.68
2 Pek. Instalasi Stop Kontak titik 1.00 173,978.40 10.00 17,397.84 191,376.24
3 Pek. Lampu LED 11 WATT+Fitting bh 6.00 84,228.40 10.00 50,537.04 555,907.44
4 Pek. Saklar Tunggal bh 2.00 76,228.40 10.00 15,245.68 167,702.48
5 Pek. Stop Kontak bh 1.00 81,228.40 10.00 8,122.84 89,351.24
6 Pek. Box MCB (lengkap) set 1.00 700,000.00 10.00 70,000.00 770,000.00
PEKERJAAN PLUMBING DAN SANITAIR
Lantai 1
1 Pek. Washtafel Komplit bh 1.00 633,418.00 10.00 63,341.80 696,759.80
2 Pek. Kran Washtafel bh 1.00 161,041.20 10.00 16,104.12 177,145.32
3 Pek Bak Cuci Piring bh 1.00 227,470.00 10.00 22,747.00 250,217.00
4 Pek. Pipa Air Bersih PVC AW 1/2 m1 10.00 22,791.68 10.00 22,791.68 250,708.48
5 Pek. Pipa Air Bersih PVC AW 3/4 m1 10.00 25,891.68 10.00 25,891.68 284,808.48
6 Pek. Pipa Air Bersih PVC AW 1 m1 10.00 34,187.52 10.00 34,187.52 376,062.72
7 Pek. Pipa Air Kotor PVC AW 3 m1 15.00 54,331.32 10.00 81,496.98 896,466.78
X PEKERJAAN SENDERAN
1 Pek. Galian Tanah Pematangan Lahan 1,45 m m3 496.21 101,924.40 10.00 5,057,590.65 55,633,497.18
2 Pek. Galian Tanah Pematangan Lahan 3,45 m m3 863.25 119,110.64 10.00 10,282,226.00 113,104,485.98
3 Pek. Pasangan Batu Belah 1 PC5 PP pada DPT m3 68.95 620,699.76 10.00 4,279,724.88 47,076,973.65
4 Pek. Plesteran 1PC 6PP t=15 mm m2 176.74 55,948.80 10.00 988,839.09 10,877,230.00
XI PEKERJAAN PEMATANGAN SITE
PEKERJAAN PELEBARAN TANGGA
1 Pek. Pasangan Batako 15 m2 73.12 129,823.00 10.00 949,265.78 10,441,923.54
2 Pek. Urugan Tanah pada Anak Tangga m3 3.60 138,975.20 10.00 50,031.07 550,341.79
3 Pek. Plesteran Anak Tangga 1PC 6PP m3 137.24 55,948.80 10.00 767,841.33 8,446,254.64
PEKERJAAN PLAT BETON
1 Pek. Galian Batu Eksisting m3 0.77 1,398,880.00 10.00 107,713.76 1,184,851.36
2 Pek. Pasang Buis Beton 30 x 100 cm bh 12.00 151,914.80 10.00 182,297.76 2,005,275.36
3 Beton K250 m3 0.85 786,433.95 10.00 66,846.89 735,315.74
4 Pembesian kg 33.42 10,628.79 10.00 35,521.42 390,735.65
5 Pek. Pasangan Batu Belah 1 PC5 PP m3 1.30 620,699.76 10.00 80,690.97 887,600.66
6 Pek. Balok 200 x 300 mm
Beton K250 m3 1.63 786,433.95 10.00 128,188.73 1,410,076.06
Pembesian Balok kg 177.20 10,628.79 10.00 188,342.19 2,071,764.14
Bekisting Balok m2 8.14 305,315.52 10.00 248,526.83 2,733,795.17
7 Pek. Beton Pelat Lantai t=150 mm
Beton K250 m3 6.55 786,433.95 10.00 515,114.23 5,666,256.58
Penulangan Wiremesh M7 (2 Lapis) kg 364.68 28,258.25 10.00 1,030,522.02 11,335,742.25
Bekisting Plat m2 35.38 313,315.52 10.00 1,108,510.31 12,193,613.41
Pek. Pasangan Batu Pilah Karangasem m2 43.71 713,971.25 10.00 3,120,768.33 34,328,451.67

TOTAL HARGA + PPN 10 % 1,297,496,172.87


DAFTAR HARGA SATUAN BAHAN
TAHUN 2019

A. Harga Satuan Bahan

NAMA TOKO
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp) UD. Astiti Merta TB. Aneka Makmur UD. Kusuma Indah

1 2 3 4 5 6 7 8 9 10 11

BIDANG UMUM
1 Jaring Sungar m2 170,000.00 165,000.00 150,000.00 170,000.00
2 Tali Seling m' 9,500.00 8,000.00 7,500.00 9,500.00
3 Tali m' 5,600.00 4,500.00 5,000.00 5,600.00
4 Sekop Datar bh 165,000.00 145,000.00 165,000.00 150,000.00
5 Selang Air m' 8,000.00 7,500.00 7,000.00 8,000.00
6 Terpal m2 9,500.00 8,500.00 9,000.00 9,500.00

BIDANG BINA MARGA


1 Uditch 1000 x 1000 x 1200 K 350 unit 1,950,000.00 1,950,000.00 1,900,000.00
2 Uditch 1200 x 1200 x 1200 K 350 unit 2,950,000.00 2,820,000.00 2,950,000.00 2,900,000.00
3 Plat Penutup 400 x 1200 K 350 unit 450,000.00 450,000.00 500,000.00 475,000.00
4 Plat Penutup 1200 x 1200 x 1200 K 350 unit 1,250,000.00 1,250,000.00 1,350,000.00 1,370,000.00
5 Frame Manhole 1200 x 1200 unit 950,000.00 965,000.00 970,000.00 950,000.00
6 Cover Manhole 1200 x 1200 unit 950,000.00 965,000.00 970,000.00 950,000.00
7 Abu Batu m3 256,000.00 255,000.00 265,000.00

BAHAN K3
A Alat Pelindung Diri
1 Topi Pelindung (safety Helmet) bh 55,000.00 50,000.00 45,000.00 55,000.00
2 Pelindung Mata (Goggles, Spectacles) bh 95,000.00 80,000.00 95,000.00
3 Tameng Mata (face Shield) bh 215,000.00 215,000.00
4 Masker Selam (Breathing Apparatus) bh 350,000.00 340,000.00 350,000.00
5 Pelindung Telinga (Ear Plug, Ear Muff) bh 250,000.00 211,000.00 250,000.00
6 Pelindung Pernafasan dan Mulut (Masker) bh 45,000.00 45,000.00 40,000.00
7 Sarung Tangan (Safety Gloves) bh 40,000.00 30,000.00 35,000.00 40,000.00
8 Penunjang Seluruh Tubuh (Full Body Harness) bh 130,000.00 100,000.00 110,000.00 130,000.00
9 Jaket Pelampung (Life Vest) bh 150,000.00 140,000.00 145,000.00 150,000.00
10 Celemek (Apron/Coverralls) bh 90,000.00 77,500.00 87,000.00 90,000.00
11 Pelindung Jatuh (Fall Arrester) bh 990,000.00 770,000.00 990,000.00

B Rambu-Rambu K3 bh 150,000.00 150,000.00


1 Rambu Petunjuk bh 150,000.00 150,000.00
2 Rambu Larangan bh 150,000.00 150,000.00
3 Rambu Peringatan bh 150,000.00 150,000.00
4 Rambu Kewajiban bh 150,000.00 150,000.00
5 Rambu Informasi bh 150,000.00 150,000.00
6 Rambu Pekerjaan Sementara bh 150,000.00 150,000.00
7 Tongkat Pengatur Lalu Lintas (Warning Light Stck) bh 60,000.00 53,000.00 60,000.00
8 Kerucut Lalu Lintas (Traffic Cone) bh 125,000.00 115,000.00 125,000.00
9 Lampu Putar (Rotary Lamp) bh 97,000.00 95,000.00 95,000.00 97,000.00
10 Lampu Selang Lalu Lintas bh

C Pengendaliang Resiko K3
1 Alat Pemadam Api Ringan (APAR) bh 550,000.00 450,000.00 550,000.00
NAMA TOKO
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp) UD. Astiti Merta TB. Aneka Makmur UD. Kusuma Indah

1 2 3 4 5 6 7 8 9 10 11
2 Sirine bh 450,000.00 400,000.00 450,000.00
NAMA TOKO
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp) UD. Astiti Merta TB. Aneka Makmur UD. Kusuma Indah

1 2 3 4 5 6 7 8 9 10 11
3 Bendera K3 bh
4 Lampu Darurat (Emergency Lamp) bh 170,000.00 162,000.00 170,000.00

BAHAN TAMBAHAN
1 List Gypsum Profil 5 cm m' 11,500.00 11,000.00 11,500.00
2 Bubungan Genteng glazur bh 44,651.10 41,730.00 44,651.10
3 Tempat Sabun bh 149,800.00 149,800.00 151,000.00 150,000.00
4 Kusen Aluminum m' 110,000.00 110,000.00 115,000.00
5 Rangka Jendela Aluminium m' 115,500.00 115,500.00 115,500.00 117,000.00
6 Rangka Pintu Aliminium m' 121,000.00 121,000.00 125,000.00
7 Door Stoper bh 210,000.00 200,000.00 210,000.00 215,000.00
8 Door Closer bh 380,000.00 375,000.00 380,000.00 385,000.00
9 Kusen dan Pintu PVC Toilet unit 800,000.00 750,000.00 755,000.00 800,000.00
10 Genteng Keramik ex Jatiwangi bh 7,500.00 7,000.00 7,500.00
11 Genteng Keramik Glazur ex KANMURI bh 22,500.00 22,500.00 24,000.00
12 Nok Genteng Keramik EX Jatiwangi bh 42,000.00 40,000.00 42,000.00
13 Nok Genteng Keramik Ex Kanmuri bh 47,000.00 45,000.00 47,000.00
14 Kran Zink bh 485,000.00 485,000.00 490,000.00 485,000.00
15 Kran Dinding bh 240,000.00 240,000.00 245,000.00 240,000.00
16 Kitchen Zink bh 850,000.00 800,000.00 785,000.00 850,000.00
17 Floor Drain bh 110,000.00 110,000.00 112,000.00 110,000.00
18 Bak Air Fibergles bh 395,000.00 380,000.00 385,000.00 395,000.00
19 Klep Diameter 3/4" bh 112,000.00 110,000.00 114,000.00 112,000.00
20 Tangkin Air 1000 Liter bh 1,850,000.00 1,850,000.00 1,870,000.00 1,900,000.00
21 Tangki Air 500 Liter bh 845,000.00 850,000.00 835,000.00 845,000.00
22 Pelampung Otomatis bh 170,000.00 155,000.00 165,000.00 170,000.00
23 Roof Drain Metal bh 97,000.00 95,000.00 98,000.00 97,000.00
24 Mesin Jet Pump kap 250 watt ex Grounfos bh 5,600,000.00 5,650,000.00 5,700,000.00 5,600,000.00
25 Mesin Pompa Tekan kap. 150 watt ex Grounfos bh 3,450,000.00 3,500,000.00 3,550,000.00 3,450,000.00
26 Box Panel PVC isi 4 MCB ex Legran bh 210,000.00 190,000.00 195,000.00 210,000.00
27 MCB 6 A ex Legran bh 52,000.00 50,000.00 55,000.00 52,000.00
28 MCB 4 A ex Legran bh 48,000.00 45,000.00 47,000.00 48,000.00
29 Kabel telephone 4 x 0.5 mm m' 22,000.00 14,000.00 17,000.00 22,000.00
30 Oulet TV Broco bh 220,000.00 210,000.00 215,000.00 220,000.00
31 Outlet Telephone bh 230,000.00 220,000.00 225,000.00 230,000.00
32 Dowlight/PLC 13 W bh 62,000.00 65,000.00 60,000.00 62,000.00
DAFTAR HARGA SATUAN BAHAN
TAHUN 2019

NAMA TOKO
Keterangan

12 13 14
NAMA TOKO
Keterangan

12 13 14
NAMA TOKO
Keterangan

12 13 14
DAFTAR HARGA SATUAN BAHAN
TAHUN 2019

A. Harga Satuan Bahan

NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9

BATU KALI DAN BATU ALAM


1 Batu Kali/batu bulat 15-30 cm m3 305,000.00 574,200.00 305,000.00 308,000.00
2 Batu Belah 1.0-5.0 cm m3 345,000.00 594,000.00 350,000.00 345,000.00
3 Batu Pecah Besar 15/30 cm m3 205,000.00 462,000.00 205,000.00 208,000.00
4 Batu Pecah 5/7 cm m3 310,000.00 607,200.00 310,000.00 315,000.00
5 Batu Pecah 3/5 cm m3 316,000.00 462,000.00 316,000.00 318,000.00
6 Batu Pecah 3-4 cm m3 335,000.00 613,800.00 345,000.00 335,000.00
7 m3 396,000.00 620,400.00 398,000.00 396,000.00
8 Batu Pecah Mesin 1 - 2 cm m3 475,000.00 495,000.00 485,000.00 475,000.00
9 Batu Pecah 2-3 cm m3 450,000.00 620,400.00 450,000.00 460,000.00
10 Batu Pecah 1 - 2 cm m3 550,000.00 858,000.00 550,000.00 570,000.00
11 Batu Pecah 0,5 - 1 Cm m3 385,000.00 462,000.00 385,000.00 390,000.00
12 Batu Alam Andesit Bintik Bakar 40 x 40 m2 116,000.00 23,111.88 118,000.00 116,000.00
13 Batu Alam Andesit Alur m2 120,000.00 235,356.00 125,000.00 120,000.00
14 Batu Alam Live Grendia m2 119,000.00 162,360.00 210,000.00 119,000.00
15 Batu Candi m2 125,000.00 148,500.00 125,000.00 125,000.00
16 Batu Candi Hitam (Ukuran 30 x 30 x 2 Cm) Cirebon m2 112,000.00 151,800.00 115,000.00 112,000.00
17 Batu Candi Hitam (Ukuran 30 x 30 x 3 Cm) Cirebon m2 162,000.00 219,120.00 172,000.00 162,000.00
18 Batu Candi Hitam (Ukuran 30 x 30 x 5 Cm) Cirebon m2 238,000.00 316,800.00 240,000.00 238,000.00
19 Batu Candi Hitam (Ukuran 20 x 20 x 2 Cm) Cirebon m2 99,500.00 139,920.00 110,000.00 99,500.00
20 Batu Candi Hitam (Ukuran 20 x 30 x 5 Cm) Cirebon m2 218,000.00 300,696.00 218,000.00 219,000.00
21 Batu Putih Jogya / Palimanan (30 x 30 x 2 Cm) m2 107,000.00 141,240.00 110,000.00 107,000.00
22 Batu Putih Jogya / Palimanan (30 x 30 x 3 Cm) m2 148,000.00 195,360.00 151,000.00 148,000.00
23 Batu Putih Jogya / Palimanan (30 x 30 x 5 Cm) m2 214,000.00 290,400.00 218,000.00 214,000.00
24 Batu Alam Palimanan Putih Super m2 118,000.00 161,700.00 125,000.00 118,000.00
25 Batu hitam Jember 5 x 20 halus m2 89,500.00 117,150.00 90,000.00 89,500.00
26 Batu hitam Jember 20 x 40 halus m2 94,500.00 125,400.00 110,000.00 94,500.00
27 Batu hitam Jember 15 x 30 halus m2 88,500.00 115,869.60 91,000.00 88,500.00
28 Batu hitam Singaraja 15 x 30 halus m2 95,000.00 125,400.00 198,000.00 95,000.00
29 Batu hitam Singaraja 20 x 40 halus m2 90,000.00 125,400.00 98,000.00 90,000.00
30 Batu hitam karangasem/Batu Tabas (20 x 40 x 3) m2 160,000.00 792,000.00 165,000.00 160,000.00
31 Paras Silakarang Tipis (Ukuran 15 x 30 x 5 Cm) m2 318,000.00 422,400.00 320,000.00 318,000.00
32 Paras Silakarang Tebal (Ukuran 15 x 30 x 8 Cm) m2 348,500.00 462,000.00 350,000.00 348,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
33 Batu Paras Bali/Pawon (Abu - Abu Terang) m2 274,000.00 359,040.00 274,000.00 280,000.00
34 Paras Kelating / Kerobokan (Ukuran 3 x 20 x 40 Cm) bh 10,000.00 19,800.00 17,000.00 10,000.00
35 Batu pilah m2 125,000.00 132,000.00 125,000.00 127,000.00
36 Batu pilah Singaraja 30 x 30 m2 130,000.00 124,812.60 130,000.00 135,000.00
37 Batu pilah Singaraja 20 x 20 m2 117,000.00 117,189.60 117,000.00 118,000.00
38 Split Kasar m3 320,000.00 562,320.00 320,000.00 325,000.00
39 Split Halus m3 312,000.00 607,200.00 312,000.00 318,000.00
40 Koral Beton diameter 1 - 2 cm m3 412,000.00 858,000.00 412,000.00 415,000.00
41 Batu Sikat Hitam Lokal Super kampil 95,000.00 144,804.00 95,000.00 98,000.00
42 Batu Sikat Akik Merah kampil 25,000.00 36,498.00 25,000.00 27,000.00
43 Batu Sikat Putih Salju kampil 35,000.00 56,166.00 35,000.00 35,000.00
44 Koral Sikat (Lokal) sak 55,000.00 66,000.00 55,000.00 57,000.00
45 Kerikil m3 410,000.00 510,000.00 410,000.00 420,000.00
46 Kerikil Beton m3 500,000.00 780,000.00 550,000.00 500,000.00
47 Kerikil Halus m3 420,000.00 540,000.00 420,000.00 425,000.00
48 Pasir Halus m3 258,000.00 627,000.00 258,000.00 258,000.00 261,000.00
49 Pasir Pasang m3 215,000.00 541,200.00 215,000.00 218,000.00
50 Pasir Cor m3 195,000.00 501,600.00 200,000.00 195,000.00
51 Pasir Urug m3 195,000.00 462,000.00 195,000.00 198,000.00
52 Tanah Urug m3 149,000.00 243,210.00 150,000.00 149,000.00
53 Tanah Urug Pilihan 125,000.00 189,600.00 125,000.00 130,000.00
54 Tanah Lempung m3 118,000.00 112,800.00 118,000.00 120,000.00
55 Sirtu m3 248,000.00 432,960.00 248,000.00 251,000.00
56 Batu Karang Bukit m3 318,000.00 283,800.00 318,000.00 319,000.00
57 Limestone m3 185,000.00 244,860.00 185,000.00 189,000.00
58 Abu Bata 450,000.00 576,000.00 450,000.00 450,000.00
59 Batako Lubang bh 2,700.00 4,620.00 2,700.00 3,000.00
60 Batako Buntu bh 2,800.00 4,686.00 2,800.00 2,800.00 3,100.00
61 Batu Bata bh 1,200.00 3,049.20 1,200.00 1,200.00 1,500.00
62 Bata Ringan setara falcon uk. 75 x 200 x 500 mm m3 785,000.00 1,295,910.00 785,000.00 885,000.00 875,000.00
63 Bata Ringan setara falcon uk. 100 x 200 x 600 mm m3 785,000.00 1,295,910.00 785,000.00 895,000.00 898,000.00
64 Bata Ringan setara falcon uk. 125 x 200 x 600 mm m3 795,000.00 1,295,910.00 795,000.00 893,000.00 899,000.00
65 Bata Ringan setara falcon uk. 150 x 200 x 600 mm m3 950,000.00 1,317,360.00 950,000.00 952,000.00 958,000.00
66 Bata Merah Klas I bh 2,800.00 5,544.00 2,800.00 2,900.00
67 Bata Merah Klas II bh 2,900.00 4,851.00 2,900.00 2,950.00
68 Bata Merah Klas III bh 2,950.00 3,465.00 2,950.00 3,000.00
69 Bata Merah Super (Pripian) ex tulikup bh 6,500.00 8,108.76 6,500.00 7,000.00
70 Bata Pres 22x10x6cm bh 3,400.00 4,147.44 3,400.00 3,600.00
71 Bata Pres 22x10x5cm bh 4,000.00 4,356.00 4,000.00 4,500.00
72 Batu Gosok bh 11,000.00 11,484.00 35,000.00 38,000.00 39,000.00
73 Filler kg 40,000.00 52,800.00 40,000.00 45,000.00 46,000.00
74 Additive liter 18,000.00 18,000.00 45,000.00 50,000.00 50,000.00
75 Agregat m3 300,000.00 330,000.00 300,000.00 320,000.00
76 Closeter bh 100,000.00 103,686.00 100,000.00 150,000.00
77 Lis Batu Alam L=7, T=40 bh 5,500.00 35,065.80 5,500.00 7,000.00
78 Lem Batu Alam kaleng 55,000.00 73,128.00 55,000.00 55,000.00 60,000.00
79 Coating (CP.27) kaleng 73,000.00 73,128.00 89,000.00 95,000.00 96,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
SEMEN
80 PC. Tiga Roda 50 Kg sak 75,000.00 98,753.16 75,000.00 76,000.00 76,000.00
81 PC Tiga Roda 40 Kg sak 50,000.00 79,200.00 50,000.00 52,000.00 54,000.00
82 PC. Tonasa 50 Kg / Busoa 50 Kg sak 47,000.00 95,634.00 47,000.00 48,000.00 49,000.00
83 PC. Gresik 40 Kg sak 50,000.00 80,520.00 50,000.00 52,000.00 53,000.00
84 PC. Gresik 50 Kg sak 63,000.00 100,980.00 63,000.00
85 PC Rajawali 40 Kg sak 46,500.00 69,300.00 46,500.00 49,500.00 50,000.00
86 PC Holcim 40 Kg sak 45,000.00 45,000.00 48,000.00 49,000.00
87 PC Conch 40 Kg sak 43,500.00 43,500.00 46,000.00 48,000.00
88 Semen Gresik kg 1,250.00 2,046.00 50,000.00 54,000.00 55,000.00
89 Semen Tiga Roda kg 1,250.00 1,980.00 50,000.00 54,000.00 56,000.00
90 Semen Tonasa kg 1,000.00
91 Semen Bosowa kg 1,150.00 1,980.00 46,000.00 48,000.00 49,000.00
92 Semen Holcim kg 1,150.00 1,980.00 46,000.00 48,000.00 49,000.00
93 Semen Conch kg 1,150.00 46,000.00 48,000.00 49,000.00
94 Semen Warna MU 408/ Nat kg 14,000.00 36,960.00 14,000.00 16,000.00 18,000.00
95 Semen Tipe V kg 3,000.00 3,168.00
96 Semen Portland kg 2,300.00 2,337.72

Mortar Utama
97 ThinBedMAX/Perekat Bata Ringan (MU 380) @40 Kg sak 128,000.00 194,040.00 128,000.00 131,000.00 130,000.00
98 PlasterPlus/Pas. Bata & Plester (MU-301) @40 kg sak 86,200.00 130,680.00 86,200.00 87,000.00 88,000.00
99 Plester premium (MU-100)@ 40 kg sak 91,000.00 145,200.00 91,000.00 93,000.00 94,000.00
100 Finish Plesteran/ Render (MU 290)@ 40 kg sak 159,500.00 246,840.00 159,500.00 161,000.00 161,500.00
101 SkimWall/Acian Plesteran & Beton (Skimcoat) 20 kg (MU-200) sak 72,000.00 105,600.00 72,000.00 73,000.00 74,000.00
102 SkimWall/Acian Plesteran & Beton (Skimcoat) 40 kg (MU-200) sak 136,500.00 198,000.00 136,500.00 140,000.00 142,000.00
103 Acian Putih (MU-270)@25 kg sak 152,000.00 231,000.00 152,000.00 153,000.00 160,000.00
104 Perata Lantai (MU-440)@40kg sak 90,000.00 131,788.80 90,000.00 91,000.00 94,000.00
105 Perata Lantai Expose (MU 445) 40 kg sak 171,000.00 258,192.00 171,000.00 172,000.00 174,000.00
106 Self Leveling Floor /Underlayment (MU-410) @25kg sak 146,000.00 409,860.00 146,000.00 148,000.00 150,000.00
107 Primer Self Leveling Floor (MU-L410) @ 5lt Set 75,000.00 458,040.00 75,000.00 76,000.00 78,000.00
108 Floor Hardener (MU 700) 25 kg sak 140,000.00 209,880.00 140,000.00 141,000.00 142,000.00
109 Granitfix/Perekat Granite Tile & Batu Alam (MU-400) @25kg sak 117,000.00 180,840.00 117,000.00 118,000.00 119,000.00
110 Cerafix/Perekat Keramik (MU-420)@25 kg sak 82,000.00 125,136.00 82,000.00 83,000.00 84,000.00
111 Poolfix White/Perekat keramik area terendam (MU-460)@25 kg sak 385,000.00 592,812.00 385,000.00 390,000.00 391,000.00
112 Renofix/Perekat keramik diatas keramik (MU-480)@25 kg sak 231,000.00 355,212.00 231,000.00 232,000.00 233,000.00
113 Powerfix Flex/Perekat keramik serba guna (MU-485)@25 kg sak 298,000.00 454,740.00 298,000.00 298,000.00 299,000.00
114 Rapidfix Flex/Perekat keramik Fast Setting (MU-490)@25 kg sak 300,000.00 491,832.00 310,000.00 300,000.00 320,000.00
115 Colorfill/ Pengisi nat interior & eksterior (MU-408C) kg 9,200.00 16,500.00 9,200.00 9,500.00 10,000.00
116 ColorPlus/Pengisi nat interior,eksterior,area basah(MU-408P) kg 16,000.00 28,380.00 16,000.00 17,000.00 18,500.00
117 Glliter/Pengisi nat dengan efek Glliter (MU-408G)@ 2kg set 30,000.00 235,884.00 30,000.00 31,000.00 32,000.00
118 PowerPool/Pengisi nat area terendam(MU-408PP)@2kg set 87,000.00 126,852.00 87,000.00 88,000.00 89,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
119 FixGrout/Perbaikan struktur beton (MU-800)@20kg sak 79,500.00 118,800.00 79,500.00 81,500.00
120 PatchCrete/Perbaikan permukaan beton(MU-830)@40kg sak 248,000.00 378,180.00 248,000.00 249,600.00
121 SkimRep/Perbaikan permukaan acian(MU-840)@25kg sak 231,000.00 470,052.00 231,000.00 233,500.00
122 DryShield/Pelapis kedap air (MU-600)@3kg set 101,000.00 156,420.00 101,000.00 105,000.00
123 ArcyBond/Perekat Mortar & Beton akrilik (MU-L500)@900ml set 40,000.00 48,180.00 40,000.00 42,000.00

Uzin
124 Beton Instan (UZ K300) 50 kg sak 110,000.00 110,600.16 135,000.00 138,000.00
125 Plester dinding instan (UZ Plester) 50 Kg sak 80,000.00 109,148.16 80,000.00 82,000.00
126 Plester Finish tanpa Aci (UZ Render) 50 kg sak 120,000.00 139,574.16 120,000.00 121,000.00
127 Acian diatas beton (UZ SC100) 40 kg sak 101,000.00 155,713.80 101,000.00 102,000.00
128 Acian dinding instan interior (UZ SC 50) 40 kg sak 118,000.00 145,259.40 118,000.00 119,000.00
129 Acian dinding instan eksterior (UZ SC 75) 40 kg sak 120,500.00 148,170.00 120,500.00 122,000.00
130 Perekat Bata Ringan (UZ TB20) 50 kg sak 98,000.00 157,897.08 98,000.00 99,500.00

Bostik
Perekat Keramik & Batu Alam
131 Fix Crete 25kg sak 75,000.00 448,800.00 75,000.00 80,000.00
132 Fix all 20kg sak 85,000.00 207,476.28 85,000.00 86,000.00
133 Super Fix all 20kg sak 65,000.00 295,307.76 65,000.00 70,000.00
134 Super Fix all trade/white 20kg sak 265,000.00 358,513.32 265,000.00 268,000.00
135 Asaflex 45 kg (15lt +30 kgp) set 1,350,000.00 1,793,286.00 1,350,000.00 1,353,000.00
136 Mortar Fix 100kg set 151,000.00 1,985,676.00 151,000.00 153,000.00
137 Mortar Fix 50 kg set 860,000.00 1,913,340.00 860,000.00 865,000.00
138 Mortar Fix 5 kg set 90,000.00 1,131,240.00 90,000.00 93,000.00
139 Renofix 25 kg Zak 350,000.00 448,800.00 350,000.00 350,000.00
140 Grout ( Semen Nat) 20 kg sak 340,000.00 536,024.28 340,000.00 343,000.00
141 Grout ( Semen Nat) 1 kg sak 17,000.00 24,090.00 17,000.00 18,000.00
142 Liquid Grout Adictive (LGA) 20 Lt pail 951,000.00 1,291,374.48 951,000.00 961,000.00
143 Mega Lastic Acrilic Base 20Lt pail 951,000.00 1,291,374.48 951,000.00 961,000.00

Wall System
144 Skim Plas 25 Kg sak 70,000.00 156,057.00 70,000.00 75,500.00
145 Skim Crete 25 Kg sak 78,000.00 204,996.00 78,000.00 80,500.00
146 Fix. Plas 40 kg sak 65,000.00 142,560.00 65,000.00 70,000.00
147 Fix T. 40 kg sak 70,000.00 207,906.60 70,000.00 75,000.00

Waterproofing
148 Ultra Coat RC2 20 Lt pail 850,000.00 1,636,088.52 850,000.00 875,000.00
149 Boscosem Slury 33 Kg set 520,000.00 684,937.44 520,000.00 535,000.00
150 Damplix 2 20 kg set 355,000.00 2,136,761.88 355,000.00 365,000.00
151 Damplix 3 45 kg set 2,175,000.00 2,834,892.72 2,175,000.00 2,185,000.00
152 Damplix 3E 35 kg set 1,285,000.00 1,572,453.96 1,285,000.00 1,350,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
153 Boscoseal Tom (Wp membran Bakar) Uk. 1m x 10 m rol 950,000.00 1,244,451.12 950,000.00 960,000.00
154 Indo primer ( lapisan primer WP membran) 20 Lt pail 810,000.00 1,018,963.44 810,000.00 815,000.00
155 Integral Kristalisasi (Waterproofing kristal) 20 kg pail 1,625,000.00 2,186,647.32 1,625,000.00 1,725,000.00
156 Sika Top Seal Set 20 kg + cairan set 345,000.00 345,000.00 375,000.00 380,000.00

Sealent
156 No More Nail (320 GR) bh 80,600.00 106,920.00 82,000.00 81,500.00 80,600.00
157 Seal n Flex 1 (600 ML) bh 110,000.00 154,805.64 113,000.00 110,000.00 112,000.00
158 Boscosil 313 (300 ML) bh 60,000.00 80,388.00 60,000.00 65,000.00 67,000.00
159 Boscosil 616 (300 ML) bh 62,000.00 80,520.00 62,000.00 66,000.00 67,500.00
160 Fil A Gap (300 ML) bh 40,000.00 51,387.60 40,000.00 40,000.00 41,000.00
161 Boscosil Mastic (300 ML) khusus R. Pendingin bh 50,800.00 67,594.56 51,600.00 50,800.00 51,900.00
162 Bostik Z Bond 6S (300 ML) bh 145,000.00 193,011.72 145,000.00 148,000.00 149,500.00
163 Bostik Z PU Contrcuction (600 ML) bh 128,000.00 168,810.84 128,000.00 130,000.00 131,000.00
164 Quelyd Super Express (250 GR) bh 40,000.00 49,665.00 40,000.00 42,000.00 44,000.00
165 Expanda Foam (340 GR) bh 185,000.00 237,911.52 185,000.00 189,000.00 189,500.00
166 Barel Gun bh 540,000.00 725,993.40 540,000.00 545,000.00 546,000.00
167 Flash Band rol 188,000.00 228,513.12 188,000.00 190,000.00 191,000.00

BAMBU
168 Bambu Ukuran 8"- 10" panjang 4 m btg 15,000.00 21,060.00 15,000.00 16,000.00
169 Bambu Ukuran 3"-6" panjang 4 m btg 8,500.00 14,400.00 8,500.00 9,000.00
170 Gedeg kulit kelas I m2 15,000.00 53,220.00 15,000.00 20,000.00
171 Gedeg kulit kelas II m2 10,000.00 49,440.00 10,000.00 12,000.00
172 Gedeg Biasa m2 9,000.00 48,510.00 9,000.00 10,000.00

KAYU
173 Kayu jati Balok m3 9,500,000.00 45,012,000.00 9,500,000.00 10,000,000.00
174 Kayu jati papan m3 12,000,000.00 51,018,000.00 12,000,000.00 12,500,000.00
175 Kayu jati Usuk m3 7,500,000.00 21,780,000.00 7,500,000.00 8,000,000.00
176 Kayu jati Reng m3 8,750,000.00 21,417,000.00 8,750,000.00 8,800,000.00
177 Kayu merbau Balok m3 18,500,000.00 23,284,800.00 18,500,000.00 19,100,000.00
178 Kayu merbau papan m3 8,900,000.00 25,940,100.00 8,900,000.00 8,950,000.00
179 Kayu kamper balok m3 8,850,000.00 14,541,600.00 8,850,000.00 8,900,000.00
180 Kayu kamper usuk/reng m3 9,500,000.00 13,871,280.00 9,500,000.00 9,510,000.00
181 Kayu kamper papan m3 9,500,000.00 17,820,000.00 9,500,000.00 9,510,000.00
182 Kayu Profil 4/5 kamper m3 9,500,000.00 13,825,680.00 9,500,000.00 9,510,000.00
183 List Kayu m' 48,500.00 53,400.00 48,500.00 48,500.00
184 List profil 2/4 kamper m' 48,800.00 51,600.00 48,800.00 48,800.00
185 Kayu kruing balok m3 6,750,000.00 10,362,000.00 6,850,000.00 6,750,000.00
186 Kayu kruing papan m3 7,450,000.00 10,494,000.00 7,500,000.00 7,450,000.00
187 Kayu Usuk Kruing m3 7,450,000.00 10,362,000.00 7,500,000.00 7,450,000.00
188 Kayu Reng Kruing m3 7,450,000.00 10,362,000.00 7,500,000.00 7,450,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
189 Kayu Papan Meranti m3 6,715,000.00 8,976,000.00 6,715,000.00 6,750,000.00
190 Kayu Balok Meranti m3 6,816,000.00 9,009,000.00 6,816,000.00 6,850,000.00
191 Kayu Usuk Meranti m3 6,800,000.00 8,976,000.00 6,800,000.00 6,855,000.00
192 Kayu Reng Meranti m3 6,500,000.00 8,976,000.00 6,500,000.00 6,510,000.00
193 Kayu Bangkirai Papan m3 11,600,000.00 23,572,560.00 13,550,000.00 11,600,000.00
194 Kayu Bangkirai Balok m3 11,100,000.00 20,790,000.00 11,100,000.00 11,600,000.00
195 Kayu Begisting 5/7 m3 2,500,000.00 6,120,000.00 2,500,000.00 2,700,000.00
196 Kayu Seseh Balok m3 4,150,000.00 4,177,800.00 4,500,000.00 4,600,000.00
197 Kayu Dolken / Skapolding 8,000.00 27,720.00 8,000.00 9,000.00
198 Kayu Seseh Dolken D 20 Panjang 3 m btg 240,000.00 244,800.00 350,000.00 360,000.00
199 Kayu Seseh Dolken D 8-10 Panjang 4m btg 12,000.00 153,120.00 12,000.00 13,000.00
200 Kayu Usuk Albesia 5/7 Panjang 4 m btg 65,000.00 75,240.00 65,000.00 67,000.00
201 Kayu Reng mekanis Uk 2 x 3 x 400 cm m3 4,500,000.00 6,402,000.00 4,500,000.00 4,500,000.00
202 Kayu Reng mekanis Uk 3 x 5 x 400 cm m3 5,650,000.00 6,800,640.00 5,650,000.00 5,660,000.00
203 Kayu Usuk mekanis Uk 4 x 6 x 400 cm m3 5,650,000.00 7,128,000.00 5,650,000.00 5,660,000.00
204 Kayu Usuk mekanis Uk 5 x 7 x 400 cm m3 6,700,000.00 6,903,600.00 6,700,000.00 6,750,000.00
205 Kayu Balok mekanis Uk. 6 x 12 x 400 cm m3 6,700,000.00 7,458,000.00 6,700,000.00 6,750,000.00
206 Kayu Balok mekanis Uk. 6 x 15 x 400 cm m3 6,700,000.00 7,656,000.00 6,700,000.00 6,750,000.00
207 Kayu Balok mekanis Uk. 6 x 20 x 400 cm m3 6,700,000.00 8,857,200.00 6,700,000.00 6,750,000.00
208 Kayu Kelas III lokal m3 2,000,000.00 3,967,200.00 2,000,000.00 2,150,000.00
209 Kayu 7/7, Kelas III m3 3,500,000.00 3,720,000.00 3,500,000.00 3,700,000.00
210 Kayu Cempaka lokal m3 2,995,000.00 3,963,960.00 2,995,000.00 3,100,000.00
211 Kayu Bakar m3 850,000.00 976,800.00 850,000.00 870,000.00
212 Papan Bakesting m3 1,450,000.00 4,587,660.00 1,600,000.00 1,450,000.00
213 Papan Kayu Ulin m3 5,300,000.00 20,790,000.00 5,300,000.00 5,310,000.00
214 Papan Kayu, Kelas II m3 13,500,000.00 207,900.00 13,500,000.00 13,500,000.00
215 Balok Kayu Ulin m3 5,300,000.00 20,790,000.00 5,300,000.00 5,310,000.00
216 Lem Aica Aibond kg 60,000.00 83,160.00 60,000.00 65,000.00
217 Lem Kayu setara Fox ltr 16,000.00 27,720.00 16,000.00 17,000.00
218 Minyak bekisting setara Calform NX*R ltr 45,000.00 53,118.12 48,000.00 45,000.00
219 Jaro bubut bh 30,000.00 30,000.00 36,000.00
220 Kayu Perancah m3 48,000.00 48,000.00 48,500.00

Flooring/ Lantai
221 Parket Jati lokal Uk. 1,2 x 5 x 20 cm m2 255,000.00 403,920.00 255,000.00 265,000.00
222 Parket Jati lokal Uk. 1,2 x 5 x 25 cm m2 275,000.00 409,200.00 275,000.00 285,000.00
223 Parket Jati lokal Uk. 1,2 x 5 x 30 cm m2 310,000.00 415,800.00 310,000.00 315,000.00
224 Jati Eksport Uk. 1,2 x 5 x 20 cm m2 380,000.00 429,000.00 380,000.00 385,000.00
225 Jati Eksport Uk. 1,2 x 5 x 25 cm m2 395,000.00 456,720.00 395,000.00 398,000.00
226 Jati Eksport Uk. 1,2 x 5 x 30 cm m2 410,000.00 469,920.00 410,000.00 412,000.00
227 Jati Eksport Uk. 1,5 x 9 x 30 - 120 cm m2 510,000.00 637,560.00 510,000.00 515,000.00
228 Jati Eksport Uk. 1,5 x 12 x 30 - 120 cm m2 535,000.00 866,250.00 535,000.00 540,000.00
229 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 20 cm m2 340,000.00 391,776.00 340,000.00 345,000.00
230 Parket Kayu Merbau Kelas I Uk. 1 x 5 x 30 cm m2 345,000.00 403,920.00 345,000.00 346,000.00
231 Parket Kayu Merbau Kelas I Uk. 1 x 9 x 30 - 120 cm m2 518,000.00 623,700.00 518,000.00 519,000.00
232 Parket Kayu Merbau Export Uk. 1 x 9 x 30 - 120 cm m2 540,000.00 679,140.00 540,000.00 545,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
233 Parket Kayu Merbau Export Uk. 1 x 9 x 60 - 120 cm m2 516,000.00 658,350.00 516,000.00
234 Decking Bangkirai Uk. 1,9 x 9 x 180 - 390 cm m2 548,000.00 654,720.00 548,000.00
235 Decking Krewing Uk. 1,9 x 9 x 180 - 400 cm m2 415,000.00 623,700.00 415,000.00
236 Decking Merbau Uk. 1,9 x 9 x 180 - 400 cm m2 445,000.00 720,720.00 445,000.00
237 Decking Ulin Sulawesi Uk. 1,9 x 9 x 200 cm m2 685,000.00 957,000.00 685,000.00

Lambersering
238 Lambersering Bangkirai Uk. 1 x 9 x 200 cm m2 469,000.00 583,440.00 469,000.00
239 Lambersering Kruing Uk. 2 x 9 x 200 cm m2 385,000.00 446,160.00 385,000.00

Lis Kayu
240 Lis plapond kayu mekanis Uk. 1 x 5 x 400 cm btg 26,000.00 30,360.00 26,000.00 26,500.00
241 Lis Plapond dobel kayu mekanis Uk. 1 x 5 x 400 cm btg 28,000.00 28,776.00 28,500.00 28,000.00
242 Lis Plapond Uk. 0,8 x 5 x 400 cm btg 21,000.00 24,420.00 21,000.00 21,000.00
243 Lis Plapond Uk.1 x 3 x 400 cm btg 19,500.00 22,440.00 19,500.00 19,600.00
244 Lis Plapond tanpa profil Uk. 1 x 5 x 400 cm btg 32,000.00 33,000.00 44,000.00 45,000.00
245 Lisplang kayu mekanis Uk. 2 x 6 x 400 cm btg 51,000.00 58,080.00 51,000.00 52,000.00
246 Lisplang kayu mekanis Uk. 2 x 7 x 400 cm btg 57,000.00 69,960.00 57,000.00 58,000.00
247 Lisplang kayu mekanis Uk. 2 x 8 x 400 cm btg 65,000.00 76,560.00 65,000.00 67,000.00
248 Lisplang kayu mekanis Uk. 2 x 10 x 400 cm btg 81,000.00 104,940.00 81,000.00 82,000.00
249 Lisplang kayu mekanis Uk. 2 x 12 x 400 cm btg 101,000.00 127,080.00 101,000.00 102,000.00
250 Lisplang kayu mekanis Uk. 2 x 15 x 400 cm btg 122,000.00 122,760.00 125,500.00 126,000.00
251 Lisplang kayu mekanis Uk. 2 x 20 x 400 cm btg 122,500.00 123,000.00 130,000.00 131,000.00
252 Lis Kaca Uk. 1,5 x 3 cm m' 16,500.00 16,896.00 16,500.00 17,000.00
253 Lis Dowel Kecil Uk. 1 x 2 cm m' 6,000.00 6,120.00 7,000.00 8,000.00
254 Lis Dowel Besar Uk. 1,3 x 3 cm m' 6,500.00 6,732.00 7,500.00 8,500.00
255 Lis Kusen m' 6,200.00 6,336.00 8,500.00 9,000.00

CONWOOD
Flooring/Deck Application
256 Conwood Deck 4" ( 102 x 3050 x 14 mm) Pcs 81,500.00 103,620.00 81,500.00 83,000.00
257 Conwood Deck 6" ( 152 x 3050 x 14 mm) Pcs 138,000.00 176,880.00 138,000.00 139,500.00
258 Conwood Deck 8" ( 203 x 3050 x 14 mm) Pcs 168,000.00 201,960.00 168,000.00 170,000.00
259 Conwood Deck 4" ( 102 x 3050 x 25 mm) Pcs 168,000.00 203,280.00 168,000.00 170,000.00
260 Conwood Deck 6" ( 152 x 3050 x 25 mm) Pcs 250,500.00 298,320.00 250,500.00 251,000.00
261 Conwood Deck 8" ( 203 x 3050 x 25 mm) Pcs 325,000.00 392,040.00 325,000.00 326,000.00
262 Conwood Deck 12"( 300 x 3050 x 25 mm) Pcs 475,000.00 591,360.00 475,000.00 480,000.00

Decorative Stair
263 Conwood Stair 8" (Vertical) (200 x 1200 x 16 mm) Pcs 91,000.00 113,652.00 91,000.00 93,000.00
264 Conwood Stair 12" (Horisontal) (300 x 1200 x 25 mm) Pcs 189,800.00 235,752.00 189,800.00 189,800.00
265 Conwood Handrail (85 x 3050 x 30 mm) Pcs 148,500.00 204,072.00 148,500.00 149,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9

Ceiling Application
266 Celling Border (50 X 3050 X 11 mm) Pcs 40,000.00 60,456.00 40,000.00 45,600.00
267 Conwood Lath 3" Cut (76 x 3050 x 11 mm) Pcs 61,000.00 72,336.00 61,000.00 63,500.00
268 Conwood Lath 4" Cut (100 x 3050 x 11 mm) Pcs 75,000.00 91,740.00 75,000.00 78,900.00
269 Conwood Lath 3"(UG)(600 x 1200 x 8 mm) Pcs 125,000.00 147,840.00 125,000.00 128,600.00
270 Conwood Lath 3"(UG)(1200 x 2400 x 8 mm) Pcs 515,000.00 620,520.00 515,000.00 518,500.00

Eave/lisplank
271 Conwood Eave 2 IN 1 (235 x 3050 x 16 mm) Pcs 178,000.00 214,500.00 178,000.00 181,000.00

Wall Application
272 Conwood Lap Siding 6" BG (152 x 3050 x 11mm) Pcs 85,000.00 88,565.40 85,000.00 90,000.00
273 Conwood Lap Siding 8" GO (200 x 3050 x 11mm) Pcs 98,000.00 115,453.80 98,000.00 98,500.00
274 Conwood Decorative Panel (600 x 1200 x 11mm) Pcs 180,000.00 214,500.00 180,000.00 181,000.00
275 Conwood Decorative Panel " V-Groove" (305 x 3050 x 14mm) Pcs 215,000.00 262,800.00 215,000.00 217,000.00

Moulding Application
276 Conwood Floor Mould 4" (Louis) (102 x 3050 x 11mm) Pcs 125,000.00 71,280.00 125,000.00 126,500.00
277 Conwood Floor Mould 4" (Louis) (102 x 3050 x 14mm) Pcs 41,000.00 80,520.00 41,000.00 43,500.00
278 Conwood Floor Mould 4" (Classic) (102 x 3050 x 11mm) Pcs 65,000.00 65,003.40 65,000.00 66,500.00
279 Conwood Floor Mould 4" (Classic) (102 x 3050 x 14mm) Pcs 60,000.00 87,780.00 60,000.00 61,000.00
38,000.00 40,100.00
Decorative Application
280 Conwood Plank 1" (100 x 3050 x 25 mm) Pcs 110,000.00 130,680.00 110,000.00 115,000.00
281 Conwood Plank 2" (50 x 3050 x 16 mm) Pcs 45,000.00 51,084.00 45,000.00 46,500.00
282 Conwood Plank 2" (50 x 3050 x 25 mm) Pcs 65,000.00 78,672.00 65,000.00 66,500.00
283 Conwood Sun Shade 3" (76 x 3050 x 14 mm) Pcs 53,000.00 64,800.00 53,000.00 54,100.00
284 Conwood Fence 4" Arrow - 1M (100x 1000 x 16 mm) Pcs 40,000.00 40,920.00 40,000.00 41,600.00
285 Conwood Fence 4" Arrow - 1,5M (100x 1500 x 16 mm) Pcs 52,000.00 64,680.00 52,000.00 53,000.00
286 Conwood Fence 4" Botany - 1M (100x 1000 x 16 mm) Pcs 38,000.00 52,272.00 38,000.00 41,000.00
287 Conwood Fence 4" Botany - 1,5M (100x 1500 x 16 mm) Pcs 53,000.00 61,560.00 53,000.00 54,000.00
288 Conwood Fence 4" Classic - 1,5M (100x 1500 x 16 mm) Pcs 55,000.00 64,548.00 55,000.00 56,000.00
289 Conwood Fence 4" Branch - 1M (100x 1000 x 16 mm) Pcs 40,000.00 48,840.00 40,000.00 41,500.00

Planks
290 Conwood Plank 8" Textured (200 x 3050 x 8 mm) Pcs 94,000.00 79,200.00 94,000.00 98,500.00
291 Conwood Plank 8" Plain (200 x 3050 x 8 mm) Pcs 91,000.00 79,200.00 91,000.00 93,000.00

BESI
292 Mour + Bout bh 2,950.00 12,600.00 2,950.00 3,100.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
293 Besi strip kg 13,000.00 20,097.00 13,000.00 15,000.00 16,000.00
294 Besi strip 30x3 mm m' 18,000.00 29,280.00 18,000.00 20,000.00 25,000.00
295 Baja Strip (0,2 x 2) cm / Plat Strip Kg 15,833.33 24,120.00 95,000.00 98,500.00 99,000.00
296 Besi Beton U24 (Polos) Kg 9,800.00 18,018.00 9,800.00 9,900.00 10,100.00
297 Besi Beton Ulir U 32 Kg 12,500.00 18,714.00 12,500.00 12,700.00 12,750.00
298 Besi Ulir 13,0x 12 sni (Ts-40) Kg 12,000.00 12,234.00 115,000.00 118,000.00 119,500.00
299 Besi Ulir 16,0x 12 sni (Ts-40) kg 11,000.00 11,829.60 170,800.00 172,000.00 173,000.00
300 Besi Ø5 (3,8 x 6,0) btg 4,950.00 9,108.00 4,950.00 5,100.00 6,000.00
301 Besi Ø6 (5,0 x 12) btg 18,200.00 24,684.00 18,200.00 18,300.00 19,000.00
302 Besi Ø6 (5,2 x 12) btg 21,000.00 27,192.00 21,850.00 21,900.00 21,000.00
303 Besi Ø6 (5,7 x 12) btg 27,400.00 30,600.00 27,400.00 28,500.00 29,000.00
304 Besi Ø8 (6,5 x 12) btg 29,100.00 40,920.00 29,100.00 30,100.00 31,000.00
305 Besi Ø8 (6,7 x 12) btg 30,400.00 43,800.00 30,400.00 32,000.00 33,000.00
306 Besi Ø8 (6,9 x 12) SNI btg 31,800.00 46,200.00 31,800.00 34,000.00 35,000.00
307 Besi Ø8 (7,1 x 12) SNI btg 36,100.00 52,560.00 36,100.00 38,000.00 39,000.00
308 Besi Ø8 (7,4 x 12) SNI btg 38,200.00 52,800.00 38,200.00 41,000.00 42,000.00
309 Besi Ø8 (7,6 x 12) SNI btg 39,100.00 55,440.00 39,100.00 42,500.00 43,000.00
310 Besi Ø8 (7,7 x 12) SNI btg 40,100.00 54,600.00 40,100.00 41,600.00 42,500.00
311 Besi Ø8 (7,8 x 12) SNI btg 42,000.00 56,760.00 42,000.00 43,500.00 44,000.00
312 Besi Ø8 SNI U 24 btg 39,600.00 63,360.00 39,600.00 40,600.00 41,000.00
313 Besi Ø10 (8,4 x 12) SNI btg 46,900.00 64,800.00 46,900.00 48,500.00 49,000.00
314 Besi Ø10 (8,6 x 12) SNI btg 50,200.00 68,760.00 50,200.00 52,300.00 53,000.00
315 Besi Ø10 (8,9 x 12) SNI btg 52,200.00 69,900.00 52,200.00 53,600.00 54,000.00
316 Besi Ø10 (9,2 x 12) SNI btg 54,750.00 71,400.00 54,750.00 55,600.00 56,000.00
317 Besi Ø10 (9,4 x 12) SNI btg 58,500.00 75,108.00 58,500.00 59,100.00 60,000.00
318 Besi Ø10 (9,6 x 12) SNI btg 61,050.00 82,080.00 61,050.00 63,000.00 64,000.00
319 Besi Ø10 (9,8 x 12) SNI btg 63,500.00 85,392.00 63,500.00 64,500.00 65,000.00
320 Besi Ø10 SNI U 24 btg 64,000.00 67,560.00 64,000.00 65,000.00 66,000.00
321 Besi Ø10 Ulir (9,5 x 12) SNI btg 58,500.00 77,880.00 58,500.00 61,500.00 62,000.00
322 Besi Ø10 Ulir (9,7 x 12) SNI btg 56,000.00 78,936.00 56,000.00 60,000.00 61,000.00
323 Besi Ø12 (11,5 x 12) SNI btg 84,500.00 108,360.00 84,500.00 85,500.00 86,000.00
324 Besi Ø13 Ulir (11,5 x 12) SNI btg 80,500.00 108,240.00 80,500.00 81,600.00 82,000.00
325 Besi Ø13 Ulir (11,7 x 12) SNI btg 93,000.00 117,600.00 93,000.00 94,500.00 95,000.00
326 Besi Ø13 Ulir (12,0 x 12) SNI btg 96,500.00 118,692.00 96,500.00 97,800.00 98,500.00
327 Besi Ø13 Ulir (12,5 x 12) SNI btg 101,000.00 127,380.00 101,000.00 111,000.00 112,000.00
328 Besi Ø13 Ulir (12,7 x 12) SNI btg 101,000.00 132,240.00 108,500.00 109,600.00 101,000.00
329 Besi Ø16 Ulir (14 x 12) SNI btg 130,000.00 149,400.00 130,000.00 131,000.00 132,000.00
330 Besi Ø16 Ulir (14,5 x 12) SNI btg 132,000.00 161,040.00 132,000.00 133,000.00 134,000.00
331 Besi Ø16 Ulir (15,0 x 12) SNI btg 140,000.00 171,600.00 140,000.00 142,500.00 142,000.00
332 Besi Ø16 Ulir (15,5 x 12) SNI btg 150,500.00 195,360.00 150,500.00 153,000.00 154,000.00
333 Besi Ø16 Ulir (15,7 x 12) SNI btg 154,800.00 201,960.00 154,800.00 156,000.00 157,000.00
334 Wiremesh M6@50m rol 2,300,500.00 3,504,600.00 2,300,500.00 2,350,600.00 2,352,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
335 Wiremesh M7 (D6,5mm) Uk. 2,1 x 5,4 m lbr 450,000.00 515,400.00 450,000.00 452,000.00 455,000.00
336 Wiremesh M8 (D7,5mm) Uk. 2,1 x 5,4 m lbr 695,000.00 788,040.00 695,000.00 698,000.00 698,000.00
337 Wermes Diameter 8 (U 50) lbr 3,011,000.00 711,334.80 3,011,000.00 3,115,000.00 3,116,000.00
338 Beugel Besi O8 kg 20,000.00 17,569.20 20,000.00 23,000.00 22,000.00
339 Beugel penguat /plaat kg 18,000.00 103,080.00 18,000.00 196,000.00 19,700.00
340 Kawat Beton RRT kg 32,000.00 35,400.00 32,000.00 33,500.00 34,000.00
341 Kawat berduri m' 120,000.00 246,360.00 215,000.00 218,000.00 219,000.00
342 Kawat Ayak / Kuasa 5 X 5 cm m2 65,000.00 69,960.00 65,000.00 68,000.00 69,000.00
343 Kawat Harmonika 3 X 3 cm m2 62,000.00 64,260.00 62,000.00 64,500.00 64,500.00
344 Kawat Nyamuk m2 48,000.00 51,000.00 48,000.00 50,100.00 51,000.00
345 Kawat Jaring m2 49,500.00 36,300.00 49,500.00 50,500.00 51,800.00
346 Kawat Bronjong kg 50,000.00 64,140.00 50,000.00 51,600.00 52,000.00
347 Besi / Baja profil kg 15,000.00 39,060.00 15,000.00 16,700.00 17,000.00
348 Besi Baja L60 X 60 X 6 / L50 x 50 x 5 kg 18,500.00 19,770.00 18,500.00 19,600.00 19,800.00
349 Baja WF (150 x 12 GG) btg 1,950,000.00 2,195,424.00 1,950,000.00 2,000,000.00 2,000,000.00
350 Baja WF (200 x 12 GG) btg 2,500,000.00 3,345,408.00 2,500,000.00 2,700,000.00 2,750,000.00
351 Besi Baja WF 200 x 100 x 4,5 x 7 kg 15,000.00 16,968.00 15,000.00 16,000.00 17,000.00
352 Besi Baja WF 200 x 100 x 5,5x8 kg 14,500.00 14,500.00 15,000.00 16,000.00
353 Besi Baja WF 250 x 125 x 5 x 7 kg 16,000.00 16,968.00 19,800.00 20,500.00 21,000.00
354 Besi Baja C 100 x 50 x 3,2 kg 14,000.00 16,698.00 14,000.00 15,000.00 16,000.00
355 Baja Ringan Type C- 75, 0.8 m' 19,800.00 25,740.00 19,800.00 20,500.00 21,000.00
356 Baja Ringan Type C- 75, 0.6 m' 14,000.00 130,800.00 14,000.00 15,000.00 16,000.00
357 Reng Baja m' 11,250.00 11,420.40 11,250.00 11,350.00 11,450.00
358 Profil Canal "C" Tipe C71.075 btg 85,000.00 446,760.00 85,000.00 97,000.00 100,000.00
359 Profil Canal "C" Tipe C81.075 btg 96,000.00 137,280.00 96,000.00 97,000.00 98,000.00
360 Profil Canal "C" Tipe C81.065 btg 90,000.00 132,240.00 90,000.00 92,000.00 95,000.00
361 Profil "Omega / reng Tipe AA btg 45,000.00 90,780.00 45,000.00 55,000.00 55,500.00
362 Profil "Omega / reng Tipe A btg 55,000.00 77,484.00 55,000.00 57,000.00 60,000.00
363 Profil "Omega / reng Tipe AB btg 65,000.00 67,322.40 65,000.00 67,000.00 68,000.00
364 Profil Aluminium Kaca 3/4 m' 18,000.00 22,044.00 18,000.00 19,000.00 18,500.00
365 Profil Aluminium L 3 cm lis Kaca m' 18,000.00 22,044.00 18,000.00 19,000.00 18,500.00
366 Profil Aluminium 4" m' 22,000.00 101,160.00 22,000.00 23,000.00 24,000.00
367 Besi Plat kg 23,000.00 36,096.72 23,000.00 28,000.00 28,000.00
368 Besi plat 3 X 6 tebal 1,2 mm btg 90,000.00 313,411.20 90,000.00 95,000.00 96,000.00
369 Besi plat 4 X 8 tebal 1,8 mm btg 22,000.00 705,962.40 22,000.00 24,000.00 25,000.00
370 Baja Plat Hitam L = 10 lbr 285,000.00 2,621,220.00 285,000.00 288,000.00 299,000.00
371 Baja Plat Hitam L = 8 lbr 510,000.00 2,103,948.00 510,000.00 515,000.00 516,000.00
372 Baut Galvanis 3/4 x 2 " bh 9,500.00 10,200.00 9,800.00 9,500.00 9,700.00
373 Baut Galvanis 3/4 x 2 1/2 " bh 10,000.00 11,311.08 10,000.00 10,500.00 10,600.00
374 Baut Galvanis 3/4 x 3 " bh 12,000.00 12,390.00 12,000.00 12,500.00 13,000.00
375 Baut Galvanis 3/4 x 3 1/2 " bh 12,000.00 13,757.04 12,000.00 13,500.00 13,000.00
376 Baut Galvanis 3/4 x 4 " bh 13,500.00 14,942.40 13,500.00 14,000.00 14,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
377 Baut Galvanis 3/4 x 4 1/2 " bh 15,000.00 16,117.20 15,000.00 15,500.00 15,200.00
378 Baut Galvanis 3/4 x 5 " bh 17,000.00 17,133.60 17,000.00 17,500.00 18,000.00
379 Baut Galvanis 3/4 x 5 1/2 " bh 9,500.00 10,860.00 9,500.00 10,000.00 10,500.00
380 Baut Galvanis 3/4 x 6 " bh 17,000.00 20,037.60 17,000.00 18,000.00 18,000.00
381 Plat Siku Panjang 30 cm bh 21,000.00 35,208.00 21,000.00 22,000.00 23,000.00
382 Plat Siku Panjang 40 cm bh 28,000.00 37,752.00 28,000.00 30,000.00 31,000.00
383 Plat Siku Panjang 50 cm bh 15,000.00 43,920.00 15,000.00 16,500.00 17,000.00
384 Plat Siku Panjang 60 cm bh 18,500.00 50,820.00 18,500.00 19,000.00 19,000.00
385 Plat Aluminium 2mm m2 30,500.00 399,540.00 30,500.00 31,000.00 32,000.00
386 Besi siku / engsel m' 38,500.00 38,500.00 40,000.00 41,000.00
387 Besi Siku L.30.30.3 mm btg 34,500.00 107,496.84 34,500.00 36,500.00 37,000.00
388 Baut UNC 5/8 x 2" bh 3,500.00 5,820.00 4,200.00 3,500.00 4,000.00
389 Baut UNC 5/8 x 2 1/2" bh 4,250.00 4,920.00 4,500.00 4,550.00 4,250.00
390 Baut UNC 5/8 x 3" bh 2,100.00 5,577.00 2,100.00 2,500.00 3,000.00
391 Baut UNC 5/8 x 3 1/2" bh 2,800.00 5,662.80 2,800.00 3,100.00 4,000.00
392 Baut UNC 5/8 x 4" bh 3,100.00 6,316.20 3,100.00 3,500.00 4,500.00
393 Baut UNC 5/8 x 4 1/2" bh 3,800.00 6,824.40 3,800.00 4,000.00 4,800.00
394 Baut UNC 5/8 x 5" bh 4,100.00 7,729.20 4,100.00 4,500.00 5,000.00
395 Baut UNC 5/8 x 5 1/2" bh 4,300.00 7,898.88 4,300.00 4,700.00 5,000.00
396 Baut UNC 5/8 x 6" bh 4,500.00 8,661.60 4,500.00 5,000.00 6,000.00
397 Baut UNC 3/4 x 2" bh 4,600.00 7,695.60 4,600.00 5,500.00 5,000.00
398 Baut UNC 3/4 x 2 1/2" bh 4,900.00 8,349.00 4,900.00 5,800.00 6,000.00
399 Baut UNC 3/4 x 3" bh 8,900.00 9,147.60 8,900.00 9,500.00 10,000.00
400 Baut UNC 3/4 x 3 1/2" bh 10,000.00 10,500.00 10,000.00 10,200.00 10,300.00
401 Baut UNC 3/4 x 4" bh 11,000.00 11,190.00 11,000.00 11,100.00 11,200.00
402 Baut UNC 3/4 x 4 1/2" bh 11,500.00 11,616.00 11,500.00 11,600.00 11,700.00
403 Baut UNC 3/4 x 5" bh 12,000.00 12,559.80 12,500.00 12,000.00 12,600.00
404 Baut UNC 3/4 x 5 1/2" bh 13,000.00 13,620.00 13,500.00 13,000.00 13,700.00
405 Baut UNC 3/4 x 6" bh 5,000.00 14,229.60 5,000.00 7,000.00 8,000.00
406 Baut CB 3/8 x 5" bh 2,500.00 2,814.00 2,500.00 2,650.00 2,700.00
407 Baut CB 3/8 x 3" bh 1,200.00 1,597.20 1,500.00 1,200.00 3,000.00
408 Baut CB 3/8 x 2" bh 1,345.00 1,346.40 1,345.00 1,350.00 1,360.00
409 Behel 7/8 bh 5,100.00 172,920.00 5,100.00 5,800.00 7,000.00
410 Baut Baja A325 16 x 50 bh 8,500.00 9,900.00 8,500.00 8,700.00 8,900.00
411 Baut Baja A325 16 x 60 bh 9,500.00 9,732.00 9,500.00 9,700.00 9,750.00
412 Baut Baja A325 16 x 70 bh 10,000.00 10,164.00 10,000.00 10,200.00 10,100.00
413 Baut Baja A325 16 x 80 bh 11,500.00 11,616.00 11,500.00 11,650.00 11,600.00
414 Baut Baja A325 16 x 90 bh 12,350.00 12,705.00 12,400.00 12,350.00 13,000.00
415 Baut Baja A325 16 x 100 bh 13,500.00 13,866.60 13,500.00 13,500.00 13,800.00
416 Baut Baja A325 16 x 110 bh 15,500.00 15,972.00 15,500.00 15,600.00 15,700.00
417 Baut Baja A325 16 x 120 bh 17,000.00 17,424.00 17,000.00 17,200.00 17,300.00
418 Baut Baja A325 16 x 130 bh 18,000.00 18,876.00 18,000.00 18,500.00 18,700.00
419 Baut Baja A325 16 x 140 bh 20,300.00 20,328.00 20,300.00 20,400.00 20,450.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
420 Baut Baja A325 16 x 150 bh 20,500.00 21,054.00 21,000.00 20,500.00 21,500.00
421 Baut Baja A325 19 x 50 bh 13,500.00 13,939.20 13,500.00 13,600.00 13,650.00
422 Baut Baja A325 19 x 60 bh 15,000.00 15,318.60 15,200.00 15,350.00 15,000.00
423 Baut Baja A325 19 x 70 bh 16,500.00 16,589.76 16,500.00 16,789.00 16,567.00
424 Baut Baja A325 19 x 80 bh 17,325.00 17,424.00 17,425.00 17,325.00 17,550.00
425 Baut Baja A325 19 x 90 bh 19,500.00 20,110.20 20,110.00 19,500.00 20,000.00
426 Baut Baja A325 19 x 100 bh 21,000.00 21,344.40 21,300.00 21,200.00 21,000.00
427 Baut Baja A325 19 x 110 bh 21,000.00 23,232.00 23,200.00 22,500.00 21,000.00
428 Baut Baja A325 19 x 120 bh 24,000.00 24,684.00 24,000.00 24,300.00 24,500.00
429 Baut Baja A325 19 x 130 bh 25,000.00 27,370.20 25,000.00 26,000.00 27,000.00
430 Baut Baja A325 19 x 140 bh 27,200.00 27,297.60 27,200.00 27,300.00 28,000.00
431 Baut Baja A325 19 x 150 bh 28,000.00 29,040.00 28,000.00 29,000.00 28,500.00
432 Baut Galvanis 3/8 x 2 " bh 2,000.00 2,007.60 2,000.00 2,000.00 2,000.00
433 Baut Galvanis 3/8 x 2 1/2 " bh 2,100.00 2,100.00 2,500.00 2,100.00 2,200.00
434 Baut Galvanis 3/8 x 3 " bh 2,250.00 2,250.60 2,250.00 2,250.00 2,300.00
435 Baut Galvanis 3/8 x 3 1/2 " bh 2,700.00 2,702.40 2,750.00 2,700.00 2,740.00
436 Baut Galvanis 3/8 x 4 " bh 2,800.00 2,911.20 2,900.00 2,800.00 2,850.00
437 Baut Galvanis 3/8 x 4 1/2 " bh 2,900.00 2,970.00 2,950.00 2,900.00 2,965.00
438 Baut Galvanis 3/8 x 5 " bh 3,000.00 3,121.80 3,100.00 3,000.00 3,200.00
439 Baut Galvanis 3/8 x 5 1/2 " bh 3,200.00 3,552.00 3,450.00 3,500.00 3,200.00
440 Baut Galvanis 3/8 x 6 " bh 3,800.00 3,870.00 3,800.00 3,850.00 4,000.00
441 Baut Galvanis 5/8 x 2 " bh 5,100.00 5,160.00 5,200.00 5,100.00 5,120.00
442 Baut Galvanis 5/8 x 2 1/2 " bh 5,740.00 5,844.96 5,840.00 5,740.00 5,840.00
443 Baut Galvanis 5/8 x 3 " bh 6,200.00 6,353.16 6,300.00 6,200.00 6,350.00
444 Baut Galvanis 5/8 x 3 1/2 " bh 7,000.00 7,114.80 7,100.00 7,000.00 7,250.00
445 Baut Galvanis 5/8 x 4 " bh 7,600.00 7,623.00 7,600.00 7,650.00 7,655.00
446 Baut Galvanis 5/8 x 4 1/2 " bh 8,200.00 8,203.80 8,200.00 8,250.00 8,450.00
447 Baut Galvanis 5/8 x 5 " bh 8,650.00 8,682.96 8,650.00 8,680.00 8,750.00
448 Baut Galvanis 5/8 x 5 1/2 " bh 9,850.00 10,041.60 9,850.00 10,100.00 12,000.00
449 Baut Galvanis 5/8 x 6 " bh 10,100.00 10,309.20 10,100.00 11,000.00 13,000.00
450 Besi Pipa Galvanis lonjor 120,500.00 1,118,040.00 120,500.00 123,000.00 124,000.00
451 besi tangga D 19, enamel cat bh 85,500.00 85,500.00 90,000.00 91,000.00
452 Handle Besi Ø 12, enamel cat bh 95,800.00 95,800.00 96,500.00 97,000.00
453 Angker diameter 12mm bh 21,000.00 21,489.60 108,500.00 110,000.00 112,000.00
454 Skruf Fixer 5 cm bh 1,000.00 1,098.00 18,500.00 19,500.00 19,600.00
455 Dynabolt bh 4,500.00 6,600.00 4,500.00 4,650.00 5,000.00
456 Rapidrant gln 98,500.00 98,500.00 99,100.00 101,000.00
457 Sealant tube 40,000.00 54,912.00 40,000.00 43,500.00 45,000.00
458 Silicon kg 43,500.00 102,148.20 43,500.00 44,600.00 45,000.00
459 Elektrode 0,6 % bh 118,500.00 190,575.00 118,500.00 119,600.00 120,000.00
460 Elektrode 2 % bh 315,000.00 353,232.00 315,000.00 318,000.00 319,000.00

BESI PAGAR
461 Pagar Setara BRC T.90 diameter 6mm m' 245,000.00 274,032.00 245,000.00 265,000.00 270,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
462 Pagar Setara BRC T.120 diameter 6mm m' 289,000.00 312,180.00 289,000.00 289,800.00 291,000.00
463 Pagar Setara BRC T.150 diameter 6mm m' 289,000.00 320,760.00 289,000.00 289,800.00 293,000.00
464 Pagar Setara BRC T.175 diameter 7mm m' 485,000.00 485,760.00 485,000.00 486,000.00 495,000.00
465 Pagar Setara BRC T.190 diameter 7mm m' 685,000.00 722,700.00 685,000.00 695,000.00 691,000.00
466 Pagar HotDip Galvanized T.90 diameter 6mm m' 234,000.00 234,300.00 235,000.00 240,000.00 241,000.00
467 Pagar HotDip Galvanized T.120 diameter 6mm m' 250,000.00 250,800.00 255,000.00 265,000.00 265,800.00
468 Pagar HotDip Galvanized T.150 diameter 7mm m' 285,000.00 320,400.00 285,000.00 295,000.00 295,000.00
469 Pagar HotDip Galvanized T.175 diameter 7mm m' 309,000.00 353,760.00 309,000.00 310,000.00 311,000.00
470 Pagar HotDip Galvanized T.190 diameter 7mm m' 248,000.00 372,504.00 345,000.00 248,000.00 249,000.00

CAT
471 Cat Marka Jalan Kg 61,000.00 61,192.80 97,775.00 98,500.00 98,000.00
472 Glas Bit Kg 38,000.00 38,115.00 70,000.00 72,000.00 73,000.00
473 Cat besi kg 57,000.00 129,733.20 57,000.00 60,000.00 61,000.00
474 Cat Menie besi Kg 40,000.00 69,492.00 40,000.00 45,000.00 45,000.00
475 Cat menie Kayu kg 30,000.00 68,607.00 30,000.00 32,000.00 33,000.00
476 Cat Dasar Tembok Setara Emco Kg 65,000.00 82,928.40 65,000.00 66,800.00 65,000.00
477 Cat Setara weldon biasa Kg 33,000.00 52,512.00 33,000.00 35,000.00 40,000.00
478 Cat Setara weldon warna Kg 35,000.00 64,500.00 35,000.00 38,500.00 38,500.00
479 Cat Setara weldon warna tua Kg 38,000.00 72,672.00 38,000.00 41,000.00 42,000.00
480 Cat Setara emco Lux Biasa kg 33,000.00 83,400.00 33,000.00 38,000.00 39,000.00
481 Cat Setara emco Lux Warna kg 35,000.00 91,836.00 35,000.00 42,000.00 43,000.00
482 Cat Setara emco Lux Warna Tua kg 40,000.00 106,722.00 40,000.00 43,500.00 44,000.00
483 Cat tembok Setara Decolith kg 38,000.00 55,680.00 38,000.00 41,000.00 41,000.00
484 Cat tembok Setara Dulux Exterior kg 145,000.00 175,929.60 145,000.00 148,000.00 149,000.00
485 Cat tembok Setara Dulux Interior kg 110,000.00 130,191.60 110,000.00 118,000.00 119,000.00
486 Cat tembok Setara Vinilex kg 26,500.00 56,064.00 26,500.00 28,500.00 29,000.00
487 Cat Galvanis kg 55,000.00 122,263.20 55,000.00 58,500.00 58,000.00
488 Cat Kayu Emco kg 65,000.00 89,016.00 65,000.00 68,000.00 69,000.00
489 Cat Baja Chromate (anti karat) Kg 57,000.00 153,060.00 57,000.00 58,500.00 59,000.00
490 Cat Kansteen Kg 82,000.00 82,440.00 115,000.00 118,000.00 118,500.00
491 Kalkarium Kg 110,500.00 110,500.00 115,000.00 116,000.00
492 Kapur sirih Kg 15,000.00 15,000.00 18,500.00 19,000.00
493 Amplas lbr 5,000.00 9,786.00 5,000.00 5,000.00 6,000.00
494 Kuas Bh 12,000.00 22,110.00 12,000.00 13,500.00 14,000.00

Cat KCA
495 Cat Natural@25 kg Pail 890,000.00 894,960.00 890,000.00 898,000.00 899,000.00
496 Cat Flakes@25 kg Pail 985,000.00 1,171,500.00 985,000.00 989,000.00 989,000.00
497 Cat Genteng @25kg Pail 288,000.00 1,079,760.00 288,000.00 310,000.00 315,000.00

Stone Coating :
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
498 Clear gloss air kg 75,000.00 105,336.00 75,000.00 75,000.00 80,000.00
499 Black gloss air kg 88,000.00 115,500.00 88,000.00 88,500.00 89,000.00
500 Clear gloss solvent kg 79,500.00 105,072.00 79,500.00 80,000.00 82,000.00
501 Black gloss solvent kg 89,000.00 112,200.00 89,000.00 89,500.00 90,000.00
502 Clear doft solvent kg 89,500.00 112,200.00 89,500.00 90,000.00 91,000.00
503 Black doft solvent kg 89,800.00 113,124.00 89,800.00 90,500.00 91,000.00
504 Dempul / Plamir ltr 45,000.00 73,180.80 45,000.00 46,500.00 50,000.00
505 Dempul / Plamir Altik ltr 42,500.00 64,491.24 42,500.00 43,500.00 44,000.00
506 Dempul Impra Kayu ltr 40,000.00 68,607.00 40,000.00 41,000.00 42,000.00
507 Kuas untuk mengecat bh 8,000.00 21,720.00 8,000.00 9,000.00 10,000.00
508 Lem Fox (Rajawali Kuning) Gln 135,000.00 221,067.00 135,000.00 145,000.00 146,000.00
509 Lem Wall Paper Kg 80,000.00 42,600.00 80,000.00 81,000.00 82,000.00
510 Mild zak 10,000.00 18,600.00 10,000.00 11,000.00 13,000.00
511 Minyak cat ltr 28,000.00 64,491.24 28,000.00 30,000.00 31,000.00
512 Melamine Lack / Imfra ltr 89,500.00 106,722.00 89,500.00 90,500.00 91,500.00
513 Okear / Veap Kg 25,000.00 124,080.00 25,000.00 26,100.00 27,100.00
514 Plamir kayu kg 28,000.00 69,000.00 28,000.00 30,100.00 31,000.00
515 Plamir tembok setara wall Putty kg 32,000.00 221,067.00 32,000.00 33,000.00 34,000.00
516 Politur ultra ltr 65,000.00 104,129.52 65,000.00 66,500.00 65,000.00
517 Politur Jadi ltr 70,000.00 105,197.40 70,000.00 71,500.00 73,000.00
518 vernis ltr 40,000.00 83,853.00 40,000.00 41,500.00 43,000.00
519 Residu / Teer Ltr 45,000.00 50,160.00 45,000.00 46,500.00 47,000.00
520 Roll Buah 28,500.00 53,361.00 28,500.00 30,100.00 31,000.00
521 Sending Seaker ltr 89,500.00 105,600.00 89,500.00 89,500.00 90,000.00
522 Soda Api Kg 11,000.00 34,080.00 11,000.00 11,500.00 12,000.00
523 Thiner A Spesial ltr 28,500.00 38,715.60 28,500.00 30,000.00 31,000.00
524 Thiner B ltr 30,000.00 38,715.60 30,000.00 31,000.00 32,000.00
525 Teack Oil ltr 65,000.00 92,238.96 65,000.00 68,000.00 70,000.00
526 Wall Paper Setara Silk House m2 775,000.00 915,360.00 775,000.00 785,000.00 795,000.00
527 Wood Filler ltr 45,000.00 84,453.60 45,000.00 48,500.00 49,000.00
528 Cat Scotlight Ltr 195,000.00 236,040.00 195,000.00 198,500.00 199,000.00
529 Mowilex Kg 78,000.00 78,000.00 81,000.00 83,000.00

KACA
530 Bingkai Nako Silver daun 47,500.00 62,640.00 47,500.00 48,000.00 49,000.00
531 Bingkai Nako Coklat daun 49,500.00 57,780.00 49,500.00 50,000.00 51,000.00
532 Glass Block bh 28,500.00 56,520.00 28,500.00 30,000.00 31,000.00
533 Kaca 2 mm bening m2 106,000.00 106,722.00 175,000.00 185,000.00 180,000.00
534 Kaca 3 mm bening m2 130,000.00 131,040.00 185,000.00 195,000.00 196,000.00
535 Kaca 5 mm bening m2 110,000.00 209,160.00 110,000.00 112,000.00 115,000.00
536 Kaca 6 mm bening m2 259,000.00 259,182.00 310,000.00 311,500.00 311,000.00
537 Kaca 8 mm bening m2 315,000.00 440,609.40 315,000.00 318,000.00 319,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
538 Kaca 10 mm bening m2 341,000.00 533,610.00 395,000.00 341,000.00 345,000.00
539 Kaca 12 mm bening m2 585,000.00 686,070.00 585,000.00 595,000.00 595,000.00
540 Kaca Cermin 3 mm m2 198,000.00 235,560.00 198,000.00 200,000.00 201,000.00
541 Kaca Cermin 5 mm m2 365,000.00 426,888.00 365,000.00 368,000.00 369,000.00
542 Kaca Es/Kapur 3 mm m2 231,000.00 274,428.00 231,000.00 321,000.00 332,000.00
543 Kaca Es/Kapur 5 mm m2 235,000.00 356,400.00 235,000.00 336,000.00 338,000.00
544 Kaca Nako Bening m2 137,000.00 137,814.00
545 Kaca Nako Rayben m2 182,500.00 182,952.00
546 Kaca ryben 3 mm m2 118,000.00 138,600.00 118,000.00 119,000.00 119,500.00
547 Kaca ryben 5 mm m2 185,000.00 213,444.00 185,000.00 195,000.00 196,000.00
548 Kaca asahi tebal 3 mm polos clear m2 101,000.00 105,600.00 101,000.00 102,000.00 102,000.00
549 Kaca asahi tebal 3 mm ryben dark grey m2 115,000.00 123,420.00 115,000.00 118,000.00 119,000.00
550 Kaca asahi tebal 3 mm cermin mirror m2 180,000.00 195,960.00 180,000.00 182,000.00 183,000.00
551 Kaca asahi tebal 3 mm es mislet m2 195,000.00 201,663.00 195,000.00 198,000.00 199,000.00
552 Kaca asahi tebal 3 mm biru dark blue m2 285,000.00 326,403.00 285,000.00 295,000.00 296,000.00
553 Kaca asahi tebal 3 mm one way m2 415,000.00 485,100.00 415,000.00 418,000.00 419,000.00
554 Kaca asahi tebal 5 mm polos clear m2 118,000.00 130,020.00 118,000.00 120,000.00 121,000.00
555 Kaca asahi tebal 5 mm ryben dark grey m2 145,000.00 157,311.00 145,000.00 150,000.00 151,000.00
556 Kaca asahi tebal 5 mm cermin mirror m2 255,000.00 510,840.00 255,000.00 258,000.00 259,000.00
557 Kaca asahi tebal 5 mm es mislet m2 263,000.00 263,340.00 265,000.00 268,000.00 269,000.00
558 Kaca asahi tebal 6 mm polos clear m2 185,000.00 200,970.00 185,000.00 186,000.00 187,000.00
559 Kaca asahi tebal 8 mm polos clear m2 365,000.00 400,554.00 365,000.00 375,000.00 376,000.00
560 Kaca asahi tebal 10 mm polos clear m2 415,000.00 485,100.00 415,000.00 418,000.00 419,000.00
561 Kaca asahi tebal 12 mm polos clear m2 430,000.00 502,425.00 430,000.00 431,000.00 432,000.00
562 Kaca tempered asahimas tebal 3mm polos clear m2 245,000.00 282,051.00 245,000.00 246,000.00 246,000.00
563 Kaca tempered asahimas tebal 3mm ryben dark grey m2 275,000.00 335,412.00 275,000.00 285,000.00 286,000.00
564 Kaca tempered asahimas tebal 3mm sanergy clear m2 310,000.00 837,144.00 310,000.00 315,000.00 319,000.00
565 Kaca tempered asahimas tebal 4mm polos clear m2 245,000.00 283,800.00 245,000.00 248,000.00 249,000.00
566 Kaca tempered asahimas tebal 4mm sanergy clear m2 798,000.00 959,112.00 798,000.00 798,000.00 799,000.00
567 Kaca tempered asahimas tebal 5mm polos clear m2 265,000.00 311,157.00 265,000.00 265,000.00 266,000.00
568 Kaca tempered asahimas tebal 5mm ryben dark grey m2 269,000.00 385,308.00 368,000.00 269,000.00 269,000.00
569 Kaca tempered asahimas tebal 5mm stopsol m2 518,000.00 604,296.00 518,000.00 518,500.00 519,000.00
570 Kaca tempered asahimas tebal 5mm warna m2 445,000.00 515,592.00 445,000.00 448,000.00 448,000.00
571 Kaca tempered asahimas tebal 5mm sanergy clear m2 950,000.00 1,125,432.00 953,000.00 950,000.00 957,000.00
572 Kaca tempered asahimas tebal 6mm polos clear m2 370,000.00 418,440.00 370,000.00 375,000.00 376,000.00
573 Kaca tempered asahimas tebal 6mm ryben dark grey m2 475,000.00 562,716.00 475,000.00 480,000.00 481,000.00
574 Kaca tempered asahimas tebal 6mm stopsol m2 575,000.00 1,143,450.00 575,000.00 578,000.00 579,000.00
575 Kaca tempered asahimas tebal 6mm warna m2 540,000.00 646,569.00 540,000.00 545,000.00 546,000.00
### 576 Kaca tempered asahimas tebal 6mm diamon m2 735,000.00 861,399.00 735,000.00 738,000.00 738,000.00
577 Kaca tempered asahimas tebal 6mm sanergy clear m2 1,235,000.00 1,392,600.00 1,235,000.00 1,238,000.00 1,239,000.00
578 Kaca tempered asahimas tebal 8mm polos clear m2 495,000.00 547,800.00 495,000.00 498,000.00 498,000.00
579 Kaca tempered asahimas tebal 8mm stopsol m2 1,345,000.00 1,568,952.00 1,345,000.00 1,365,000.00 1,365,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
580 Kaca tempered asahimas tebal 8mm warna m2 910,000.00 1,013,859.00 910,000.00 911,000.00 912,000.00
### 581 Kaca tempered asahimas tebal 8mm diamon m2 1,250,000.00 1,494,108.00 1,250,000.00 1,250,000.00 1,251,000.00
582 Kaca tempered asahimas tebal 8mm sanergy clear m2 1,610,000.00 1,905,750.00 1,610,000.00 1,610,000.00 1,615,000.00
583 Kaca tempered asahimas tebal 10mm polos clear m2 610,000.00 668,052.00 610,000.00 615,000.00 618,000.00
584 Kaca tempered asahimas tebal 10mm diamon m2 1,810,000.00 2,134,440.00 1,810,000.00 1,815,000.00 1,815,000.00
585 Kaca tempered asahimas tebal 12mm polos clear m2 685,000.00 783,090.00 685,000.00 695,000.00 695,000.00
586 Kaca tempered asahimas tebal 12mm diamon m2 2,310,000.00 2,720,025.00 2,310,000.00 2,315,000.00 2,318,000.00
587 Kaca tempered asahimas tebal 15mm polos clear m2 5,410,000.00 6,398,469.00 5,410,000.00 5,415,000.00 5,415,000.00
588 Kaca tempered asahimas tebal 15mm diamon m2 6,918,000.00 8,316,000.00 6,918,000.00 6,919,000.00 6,920,000.00
589 Kaca tempered asahimas tebal 19mm polos clear m2 6,210,000.00 7,363,818.00 6,210,000.00 6,215,000.00 6,215,000.00
590 Kaca tempered asahimas tebal 19mm diamon m2 9,500,000.00 10,130,967.00 9,500,000.00 9,600,000.00 9,600,000.00
591 Kaca tebal 3+3 mm laminet biasa m2 418,000.00 478,170.00 418,000.00 418,000.00 419,000.00
592 Kaca tebal 4+4 mm laminet biasa m2 510,000.00 584,892.00 510,000.00 515,000.00 515,000.00
593 Kaca tebal 5+5 mm laminet biasa m2 565,000.00 658,350.00 565,000.00 570,000.00 570,000.00
594 Kaca tebal 6+6 mm laminet biasa m2 700,000.00 791,736.00 700,000.00 715,000.00 715,000.00
595 Kaca tebal 8+8 mm laminet biasa m2 910,000.00 1,280,400.00 910,000.00 915,000.00 920,000.00
596 Kaca tebal 10+10 mm laminet biasa m2 1,215,000.00 1,442,826.00 1,215,000.00 1,216,000.00 1,218,000.00
597 Kaca tebal 12+12 mm laminet biasa m2 1,110,000.00 1,641,024.00 1,110,000.00 1,115,000.00 1,118,000.00
598 Kaca tebal 3+3 mm laminet tempered m2 1,410,000.00 1,326,402.00 1,410,000.00 1,415,000.00 1,417,000.00
599 Kaca tebal 4+4 mm laminet tempered m2 1,420,000.00 1,463,616.00 1,420,000.00 1,421,000.00 1,425,000.00
600 Kaca tebal 5+5 mm laminet tempered m2 1,430,000.00 1,501,038.00 1,430,000.00 1,435,000.00 1,445,000.00
601 Kaca tebal 6+6 mm laminet tempered m2 1,850,000.00 1,905,750.00 1,850,000.00 1,855,000.00 1,856,000.00
602 Kaca tebal 8+8 mm laminet tempered m2 1,950,000.00 2,314,620.00 1,950,000.00 1,960,000.00 1,960,000.00
603 Kaca tebal 10+10 mm laminet tempered m2 2,350,000.00 2,686,068.00 2,350,000.00 2,350,000.00 2,350,000.00
604 Kaca tebal 12+12 mm laminet tempered m2 2,960,000.00 2,957,724.00 2,960,000.00 2,965,000.00 2,965,000.00
605 Ongkos polin kaca tempered tebal 5mm m' 28,500.00 29,040.00 31,000.00 35,000.00 35,000.00
606 Ongkos polin kaca tempered tebal 6mm m' 30,000.00 30,360.00 35,000.00 38,000.00 39,000.00
607 Ongkos polin kaca tempered tebal 8mm m' 41,000.00 44,880.00 41,000.00 41,500.00 41,600.00
608 Ongkos polin kaca tempered tebal 10mm m' 40,000.00 40,920.00 43,000.00 43,500.00 43,000.00
609 Ongkos polin kaca tempered tebal 12mm m' 30,000.00 43,560.00 30,000.00 50,600.00 50,600.00
610 Ongkos polin kaca tempered tebal 19mm m' 65,000.00 147,840.00 65,000.00 68,000.00 69,000.00

PIPA
611 Pipa Galvanis 1" m' 70,000.00 77,131.56 70,000.00 75,000.00 850,000.00
612 Pipa Galvanis 1,5 BSA m' 91,000.00 116,424.00 98,500.00 98,000.00 91,000.00
613 Pipa Galvanis 2" m' 121,000.00 163,548.00 121,000.00 125,000.00 125,000.00
614 Pipa Galvanis 3" m' 178,500.00 250,866.00 178,500.00 180,000.00 181,000.00
615 Pipa Maspion AW 1/2 m' 7,510.00 12,458.40 30,040.00 31,000.00 35,000.00
616 Pipa Maspion AW 3/4 m' 9,160.00 17,186.40 36,640.00 37,000.00 40,000.00
617 Pipa Maspion AW 1 m' 11,530.00 20,569.20 46,120.00 46,500.00 47,000.00
618 Pipa Maspion AW 1-1/2 m' 21,250.00 36,540.00 85,000.00 85,600.00 85,000.00
619 Pipa Maspion AW 1-1/4 m' 16,325.00 31,820.40 65,300.00 65,900.00 66,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
620 Pipa Maspion AW 2 m' 31,550.00 42,000.00 126,200.00 127,000.00 130,000.00
621 Pipa Maspion AW 2-1/2 m' 41,075.00 53,340.00 164,300.00 164,500.00 165,000.00
622 Pipa Maspion AW 3 m' 60,250.00 73,080.00 241,000.00 241,000.00 241,000.00
623 Pipa Maspion AW 4 m' 85,250.00 104,730.00 341,000.00 342,000.00 343,000.00
624 Pipa Maspion AW 5 m' 134,500.00 18,436.80 538,410.00 538,500.00 538,000.00
625 Pipa Maspion AW 6 m' 178,250.00 217,680.00 713,000.00 715,000.00 716,000.00
626 Pipa Maspion AW 8 m' 276,750.00 385,788.00 1,107,000.00 1,107,500.00 1,108,000.00
627 Pipa Maspion AW 10 m' 394,500.00 544,260.00 1,578,000.00 1,578,000.00 1,579,000.00
628 Pipa Maspion AW 12 m' 563,000.00 877,224.00 2,252,000.00 2,253,000.00 2,254,000.00
629 Pipa Maspion AW 14 m' 792,000.00 1,114,122.00 3,168,000.00 3,168,000.00 3,169,000.00
630 Pipa Maspion AW 16 m' 992,500.00 1,360,767.60 3,970,000.00 3,970,000.00 3,975,000.00
631 Pipa Maspion C 3/4 m' 3,625.00 7,104.00 14,500.00 14,500.00 15,000.00
632 Pipa Maspion C 5/8 m' 2,010.00 3,657.60 8,040.00 8,500.00 9,000.00
633 Pipa Maspion C 1 m' 5,375.00 11,592.00 21,500.00 21,600.00 22,000.00
634 Pipa Maspion C 1-1/2 m' 8,000.00 16,743.60 32,000.00 32,000.00 33,000.00
635 Pipa Maspion C 1-1/4 m' 6,700.00 26,800.00 27,000.00 28,000.00
636 Pipa Maspion C 2 m' 12,700.00 17,541.60 50,800.00 51,000.00 52,000.00
637 Pipa Maspion C 2-1/2 m' 16,200.00 21,819.60 64,800.00 65,000.00 67,000.00
638 Pipa Maspion C 3 m' 18,750.00 31,353.60 75,000.00 76,000.00 77,000.00
639 Pipa Maspion C 3-1/2 m' 21,250.00 42,318.00 85,000.00 87,000.00 88,000.00
640 Pipa Maspion C 4 m' 24,200.00 64,281.60 96,800.00 97,900.00 98,000.00
641 Pipa Maspion D 1/2 m' 11,500.00 92,100.00 46,000.00 47,000.00 48,000.00
642 Pipa Maspion D 1-1/2 m' 11,725.00 111,234.00 46,900.00 47,900.00 48,000.00
643 Pipa Maspion D 1-1/4 m' 10,175.00 193,221.60 40,700.00 41,000.00 41,500.00
644 Pipa Maspion D 2 m' 15,237.50 335,535.60 60,950.00 61,000.00 61,000.00
645 Pipa Maspion D 2-1/2 m' 22,510.00 455,025.60 90,040.00 91,000.00 93,000.00
646 Pipa Maspion D 3 m' 32,750.00 47,514.00 131,000.00 132,000.00 133,000.00
647 Pipa Maspion D 4 m' 46,000.00 66,036.00 184,200.00 184,000.00 185,000.00
648 Pipa Maspion D 5 m' 75,600.00 106,914.00 302,400.00 303,000.00 304,000.00
649 Pipa Maspion D 6 m' 92,250.00 129,219.60 369,620.00 369,000.00 369,000.00
650 Pipa Maspion D 8 m' 160,000.00 226,386.00 640,000.00 640,000.00 641,000.00
651 Pipa Maspion D 10 m' 283,750.00 391,140.00 1,135,000.00 1,136,000.00 1,136,000.00
652 Pipa Maspion D 12 m' 386,500.00 532,482.00 1,546,000.00 1,548,000.00 1,549,000.00
653 Pipa Maspion D 14 m' 513,500.00 695,962.80 2,054,000.00 2,054,000.00 2,055,000.00
654 Pipa Maspion D 16 m' 657,500.00 899,224.80 2,630,000.00 2,631,000.00 2,632,000.00
655 Pipa / selang spiral sel kran m' 28,570.00 49,585.20 28,570.00 28,900.00 29,000.00
656 Pipa langgeng warna abu - abu AW 1/2 m' 7,225.00 15,648.00 28,900.00 28,900.00 29,000.00
657 Pipa langgeng warna abu - abu AW 3/4 m' 8,712.50 16,716.00 34,850.00 35,000.00 35,600.00
658 Pipa langgeng warna abu - abu AW 1 m' 10,960.00 19,838.40 43,840.00 44,000.00 45,000.00
659 Pipa langgeng warna abu - abu AW 1 1/4 m' 15,510.00 24,856.80 62,040.00 63,000.00 64,000.00
660 Pipa langgeng warna abu - abu AW 1 1/2 m' 20,187.50 32,964.00 80,750.00 81,000.00 83,000.00
661 Pipa langgeng warna abu - abu AW 2 m' 30,400.00 45,084.00 121,600.00 122,500.00 123,000.00
662 Pipa langgeng warna abu - abu AW 2 1/2 m' 38,475.00 153,900.00 154,000.00 155,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
663 Pipa langgeng warna abu - abu AW 3 m' 55,625.00 55,620.00 222,500.00 224,000.00 228,000.00
664 Pipa langgeng warna abu - abu AW 4 m' 81,227.50 75,930.00 324,910.00 325,000.00 326,000.00
665 Pipa langgeng warna abu - abu AW 5 m' 127,945.00 107,340.00 511,780.00 512,000.00 513,000.00
666 Pipa langgeng warna abu - abu AW 6 m' 169,525.00 212,520.00 678,100.00 679,000.00 679,000.00
667 Pipa langgeng warna abu - abu AW 8 m' 263,227.50 324,870.00 1,052,910.00 1,053,000.00 1,053,000.00
668 Pipa langgeng warna abu - abu AW 10 m' 375,000.00 453,900.00 1,500,360.00 1,500,000.00 1,500,000.00
669 Pipa langgeng warna abu - abu AW 12 m' 535,325.00 648,540.00 2,141,300.00 2,142,000.00 2,143,000.00
670 Pipa langgeng warna abu - abu AW 16 m' 943,625.00 1,131,660.00 3,774,500.00 3,775,000.00 3,776,000.00
671 Pipa langgeng warna abu - abu D 1 1/4 m' 9,500.00 1,165,680.00 38,870.00 39,000.00 38,000.00
672 Pipa langgeng warna abu - abu D 1 1/2 m' 11,030.00 16,140.00 44,120.00 45,000.00 46,000.00
673 Pipa langgeng warna abu - abu D 2 m' 14,495.00 19,848.00 57,980.00 58,000.00 59,000.00
674 Pipa langgeng warna abu - abu D 2 1/2 m' 21,400.00 29,100.00 85,600.00 86,000.00 86,000.00
675 Pipa langgeng warna abu - abu D 3 m' 31,130.00 40,020.00 124,520.00 125,000.00 129,000.00
676 Pipa langgeng warna abu - abu D 4 m' 43,745.00 55,500.00 174,980.00 175,000.00 176,000.00
677 Pipa langgeng warna abu - abu D 5 m' 71,750.00 89,250.00 287,520.00 287,000.00 289,000.00
678 Pipa langgeng warna abu - abu D 6 m' 63,250.00 108,540.00 351,430.00 352,000.00 253,000.00
679 Pipa langgeng warna abu - abu D 8 m' 154,750.00 190,140.00 619,070.00 619,000.00 619,000.00
680 Pipa langgeng warna abu - abu D 10 m' 269,500.00 324,600.00 1,078,040.00 1,078,000.00 1,079,000.00
681 Pipa langgeng warna abu - abu D 12 m' 367,700.00 442,110.00 1,470,800.00 1,471,000.00 1,481,000.00
682 Pipa langgeng warna abu - abu D 14 m' 482,525.00 590,520.00 1,930,100.00 1,931,000.00 1,932,000.00
683 Pipa langgeng warna abu - abu D 16 m' 625,000.00 749,928.00 2,500,550.00 2,500,000.00 2,500,000.00
684 Pipa langgeng warna abu - abu D 20 m' 1,076,890.00 1,288,125.60 4,307,560.00 4,308,000.00 4,309,000.00
685 Pipa langgeng warna abu - abu C 5/8 m' 2,020.00 1,325,029.20 8,080.00 9,500.00 10,000.00
686 Pipa langgeng warna abu - abu C 1/2 m' 3,345.00 6,720.00 13,380.00 14,500.00 14,600.00
687 Pipa langgeng warna abu - abu C 3/4 m' 3,620.00 8,418.00 14,480.00 15,000.00 15,000.00
688 Pipa langgeng warna abu - abu C 1 m' 5,045.00 10,740.00 20,180.00 21,000.00 21,000.00
689 Pipa langgeng warna abu - abu C 1 1/4 m' 6,685.00 13,038.00 26,740.00 27,500.00 30,000.00
690 Pipa langgeng warna abu - abu C 1 1/2 m' 7,997.50 12,300.00 31,990.00 32,000.00 33,000.00
691 Pipa langgeng warna abu - abu C 2 m' 12,060.00 18,408.00 48,240.00 49,500.00 49,000.00
692 Pipa langgeng warna abu - abu C 2 1/2 m' 15,365.00 23,880.00 61,460.00 62,000.00 63,000.00
693 Pipa langgeng warna abu - abu C 3 m' 18,730.00 26,265.60 74,920.00 75,000.00 75,000.00
694 Pipa langgeng warna abu - abu C 4 m' 23,870.00 32,475.60 95,480.00 96,000.00 96,000.00
695 Pipa langgeng warna abu - abu C 5 m' 32,300.00 46,068.00 129,200.00 130,000.00 130,000.00
696 Pipa winlon warna abu - abu AW 1/2 m' 6,175.00 9,906.00 24,700.00 25,000.00 25,000.00
697 Pipa winlon warna abu - abu AW 3/4 m' 7,750.00 13,020.00 31,600.00 31,600.00 31,000.00
698 Pipa winlon warna abu - abu AW 1 m' 10,250.00 17,448.00 41,040.00 41,500.00 41,000.00
699 Pipa winlon warna abu - abu AW 1 1/4 m' 14,925.00 20,326.80 59,700.00 60,000.00 62,000.00
700 Pipa winlon warna abu - abu AW 1 1/2 m' 17,700.00 26,256.00 70,800.00 71,000.00 71,000.00
701 Pipa winlon warna abu - abu AW 2 m' 25,400.00 36,860.40 101,600.00 102,000.00 103,000.00
702 Pipa winlon warna abu - abu AW 2 1/2 m' 33,150.00 44,037.60 132,600.00 133,000.00 133,000.00
703 Pipa winlon warna abu - abu AW 3 m' 46,500.00 61,467.60 186,000.00 187,000.00 189,000.00
704 Pipa winlon warna abu - abu AW 4 m' 71,875.00 89,472.00 287,500.00 288,000.00 289,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
705 Pipa winlon warna abu - abu AW 5 m' 113,625.00 139,218.00 454,500.00 455,000.00
706 Pipa winlon warna abu - abu AW 6 m' 143,550.00 175,080.00 574,200.00 575,000.00
707 Pipa winlon warna abu - abu AW 8 m' 227,950.00 275,400.00 911,800.00 912,000.00
708 Pipa winlon warna abu - abu AW 10 m' 324,250.00 394,920.00 1,297,000.00 1,297,000.00
709 Pipa winlon warna abu - abu AW 12 m' 545,250.00 651,306.00 2,181,000.00 2,181,000.00
710 Pipa winlon warna abu - abu D 1 1/4 m' 8,662.50 14,070.00 34,650.00 35,000.00
711 Pipa winlon warna abu - abu D 1 1/2 m' 9,850.00 16,272.00 39,400.00 39,500.00
712 Pipa winlon warna abu - abu D 2 m' 12,760.00 19,320.00 51,040.00 51,600.00
713 Pipa winlon warna abu - abu D 2 1/2 m' 18,225.00 26,400.00 72,900.00 73,000.00
714 Pipa winlon warna abu - abu D 3 m' 26,450.00 34,920.00 105,800.00 107,000.00
715 Pipa winlon warna abu - abu D 4 m' 37,510.00 35,022.00 150,040.00 151,000.00
716 Pipa winlon warna abu - abu D 6 m' 59,625.00 48,660.00 238,500.00 239,000.00
717 Pipa winlon warna abu - abu D 8 m' 131,037.50 159,660.00 524,150.00 525,000.00
718 Pipa winlon warna abu - abu D 10 m' 243,100.00 292,719.60 972,400.00 973,500.00
719 Pipa winlon warna abu - abu D 12 m' 330,750.00 395,220.00 1,323,000.00 1,335,000.00
720 Pipa winlon warna abu - abu C 5/8 m' 1,677.50 4,512.00 6,710.00 6,800.00
721 Pipa winlon warna abu - abu C 1/2 m' 3,025.00 5,056.80 12,100.00 14,000.00
722 Pipa winlon warna abu - abu C 3/4 m' 3,250.00 5,862.00 13,000.00 15,000.00
723 Pipa winlon warna abu - abu C 1 m' 4,625.00 8,136.00 18,500.00 19,000.00
724 Pipa winlon warna abu - abu C 1 1/4 m' 5,850.00 10,404.00 23,400.00 24,000.00
725 Pipa winlon warna abu - abu C 1 1/2 m' 7,625.00 11,853.60 30,500.00 31,000.00
726 Pipa winlon warna abu - abu C 2 m' 10,260.00 15,147.60 41,040.00 45,000.00
727 Pipa winlon warna abu - abu C 2 1/2 m' 12,900.00 18,822.00 51,600.00 60,000.00
728 Pipa winlon warna abu - abu C 3 m' 15,977.50 22,606.80 63,910.00 64,000.00
729 Pipa winlon warna abu - abu C 4 m' 22,025.00 29,332.80 88,100.00 89,000.00
730 Pipa wavin warna putih AW 1/2 m' 5,825.00 9,156.00 23,300.00 24,000.00
731 Pipa wavin warna putih AW 3/4 m' 7,925.00 11,790.00 31,700.00 31,800.00
732 Pipa wavin warna putih AW 1 m' 10,825.00 15,528.00 43,300.00 43,900.00
733 Pipa wavin warna putih AW 1 1/4 m' 16,200.00 21,777.60 64,800.00 65,000.00
734 Pipa wavin warna putih AW 1 1/2 m' 18,600.00 24,699.60 74,400.00 75,000.00
735 Pipa wavin warna putih AW 2 m' 23,825.00 30,891.60 95,300.00 101,000.00
736 Pipa wavin warna putih AW 2 1/2 m' 34,725.00 47,220.00 138,900.00 139,000.00
737 Pipa wavin warna putih AW 3 m' 48,900.00 61,110.00 195,600.00 196,000.00
738 Pipa wavin warna putih AW 4 m' 81,025.00 100,200.00 324,100.00 325,000.00
739 Pipa wavin warna putih AW 5 m' 128,400.00 156,720.00 513,600.00 519,000.00
740 Pipa wavin warna putih AW 6 m' 180,000.00 219,360.00 720,000.00 731,000.00
741 Pipa wavin warna putih AW 8 m' 302,200.00 364,950.00 1,208,800.00 1,209,000.00
742 Pipa wavin warna putih AW 10 m' 465,750.00 563,718.00 1,868,000.00 1,863,000.00
743 Pipa wavin warna putih AW 12 m' 658,750.00 799,560.00 2,635,000.00 2,645,000.00
744 Pipa wavin warna putih D 1 1/4 m' 10,175.00 14,340.00 40,700.00 40,800.00
745 Pipa wavin warna putih D 1 1/2 m' 11,500.00 15,420.00 46,000.00 47,000.00
746 Pipa wavin warna putih D 2 m' 14,750.00 20,550.00 59,000.00 60,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
747 Pipa wavin warna putih D 2 1/2 m' 19,925.00 27,300.00 79,700.00 80,000.00
748 Pipa wavin warna putih D 3 m' 26,450.00 34,455.60 105,800.00 106,000.00
749 Pipa wavin warna putih D 4 m' 41,600.00 53,994.00 166,400.00 167,000.00
750 Pipa wavin warna putih D 5 m' 64,200.00 80,178.00 256,800.00 257,000.00
751 Pipa wavin warna putih D 6 m' 84,525.00 104,190.00 338,100.00 339,000.00
752 Pipa wavin warna putih D 8 m' 148,650.00 182,070.00 594,600.00 595,000.00
753 Pipa wavin warna putih D 10 m' 244,875.00 298,410.00 979,500.00 979,800.00
754 Pipa wavin warna putih D 12 m' 343,500.00 431,280.00 1,374,000.00 1,374,000.00
755 Pipa langgeng warna putih AW 1/2 m' 5,372.50 9,381.60 21,490.00 21,490.00
756 Pipa langgeng warna putih AW 3/4 m' 7,357.50 19,264.80 29,430.00 29,431.00
757 Pipa langgeng warna putih AW 1 m' 10,057.50 14,012.40 40,230.00 40,231.00
758 Pipa langgeng warna putih AW 1 1/4 m' 15,085.00 23,277.60 60,340.00 60,400.00
759 Pipa langgeng warna putih AW 1 1/2 m' 17,325.00 25,602.00 69,300.00 69,400.00
760 Pipa langgeng warna putih AW 2 m' 22,175.00 28,376.40 88,700.00 88,900.00
761 Pipa langgeng warna putih AW 2 1/2 m' 32,350.00 148,320.00 129,400.00 129,500.00
762 Pipa langgeng warna putih AW 3 m' 43,625.00 55,747.20 174,500.00 174,600.00
763 Pipa langgeng warna putih AW 4 m' 72,250.00 88,473.60 289,000.00 289,000.00
764 Pipa langgeng warna putih AW 5 m' 119,500.00 142,659.60 478,000.00 478,000.00
765 Pipa langgeng warna putih AW 6 m' 167,750.00 199,164.00 671,000.00 672,000.00
766 Pipa langgeng warna putih AW 8 m' 281,750.00 331,806.00 1,127,000.00 1,128,000.00
767 Pipa langgeng warna putih AW 10 m' 435,750.00 511,762.80 1,743,000.00 1,845,000.00
768 Pipa langgeng warna putih AW 12 m' 614,250.00 599,080.80 2,457,000.00 2,458,000.00
769 Pipa langgeng warna putih AW 14 m' 841,000.00 982,945.20 3,364,000.00 3,364,000.00
770 Pipa langgeng warna putih AW 16 m' 1,051,500.00 1,229,052.00 4,206,000.00 4,300,000.00
771 Pipa langgeng warna putih D 1 1/4 m' 9,450.00 12,300.00 37,800.00 38,900.00
772 Pipa langgeng warna putih D 1 1/2 m' 10,725.00 15,258.00 42,900.00 43,900.00
773 Pipa langgeng warna putih D 2 m' 13,500.00 19,005.60 54,900.00 54,000.00
774 Pipa langgeng warna putih D 2 1/2 m' 18,562.50 23,936.40 74,250.00 75,000.00
775 Pipa langgeng warna putih D 3 m' 23,575.00 30,244.80 94,300.00 98,000.00
776 Pipa langgeng warna putih D 4 m' 37,075.00 428,340.00 148,300.00 149,000.00
777 Pipa langgeng warna putih D 5 m' 59,750.00 72,705.60 239,600.00 239,000.00
778 Pipa langgeng warna putih D 6 m' 78,825.00 94,846.80 315,300.00 316,000.00
779 Pipa langgeng warna putih D 8 m' 138,600.00 164,952.00 554,400.00 558,500.00
780 Pipa langgeng warna putih D 10 m' 228,250.00 269,392.80 913,000.00 915,000.00
781 Pipa langgeng warna putih D 12 m' 320,500.00 376,370.40 1,282,000.00 1,282,000.00
782 Pipa langgeng warna putih D 14 m' 536,500.00 633,900.00 2,146,000.00 2,147,000.00
783 Pipa langgeng warna putih D 16 m' 694,500.00 821,102.40 2,778,000.00 2,800,000.00
784 Pipa langgeng warna putih D 20 m' 1,099,675.00 1,297,730.40 4,398,700.00 4,400,000.00
785 Pipa langgeng warna putih C 5/8 m' 2,125.00 4,899.60 8,500.00 9,000.00
786 Pipa setara warna putih C 1/2 m' 3,450.00 7,500.00 13,800.00 13,900.00
787 Pipa langgeng warna putih C 3/4 m' 4,100.00 8,400.00 16,400.00 17,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
788 Pipa langgeng warna putih C 1 m' 5,200.00 8,190.00 20,800.00 21,000.00
789 Pipa langgeng warna putih C 1 1/4 m' 6,900.00 12,780.00 27,600.00 30,000.00
790 Pipa langgeng warna putih C 1 1/2 m' 8,520.00 13,797.60 34,080.00 40,000.00
791 Pipa langgeng warna putih C 2 m' 12,485.00 20,019.60 49,940.00 51,000.00
792 Pipa langgeng warna putih C 2 1/2 m' 15,815.00 20,908.80 63,260.00 64,000.00
793 Pipa langgeng warna putih C 3 m' 19,270.00 25,480.80 77,080.00 78,000.00
794 Pipa langgeng warna putih C 4 m' 24,830.00 31,065.60 99,320.00 101,000.00
795 Pipa winlon warna putih AW 1/2 m' 4,300.00 11,460.00 17,200.00 18,000.00
796 Pipa winlon warna putih AW 3/4 m' 5,725.00 10,473.60 22,900.00 23,000.00
797 Pipa winlon warna putih AW 1 m' 7,975.00 12,910.80 31,900.00 31,900.00
798 Pipa winlon warna putih AW 1 1/4 m' 11,100.00 21,054.00 44,400.00 45,000.00
799 Pipa winlon warna putih AW 1 1/2 m' 14,400.00 24,510.00 57,600.00 57,900.00
800 Pipa winlon warna putih AW 2 m' 19,850.00 33,978.00 79,400.00 80,000.00
801 Pipa winlon warna putih AW 2 1/2 m' 26,625.00 30,180.00 106,500.00 108,000.00
802 Pipa winlon warna putih AW 3 m' 36,725.00 58,860.00 146,900.00 148,000.00
803 Pipa winlon warna putih AW 4 m' 60,875.00 88,428.00 243,500.00 245,000.00
804 Pipa winlon warna putih AW 5 m' 90,475.00 138,393.60 361,900.00 365,000.00
805 Pipa winlon warna putih AW 6 m' 129,950.00 173,178.00 519,800.00 520,000.00
806 Pipa winlon warna putih AW 8 m' 203,800.00 273,360.00 815,200.00 819,000.00
807 Pipa winlon warna putih AW 10 m' 293,750.00 388,695.60 1,175,000.00 1,178,000.00
808 Pipa winlon warna putih D 1 1/4 m' 6,875.00 9,622.80 27,500.00 28,000.00
809 Pipa winlon warna putih D 1 1/2 m' 8,375.00 13,486.80 33,500.00 35,000.00
810 Pipa winlon warna putih D 2 m' 11,200.00 16,590.00 44,800.00 45,000.00
811 Pipa winlon warna putih D 2 1/2 m' 15,200.00 21,386.40 60,800.00 61,000.00
812 Pipa winlon warna putih D 3 m' 18,950.00 25,197.60 75,800.00 78,000.00
813 Pipa winlon warna putih D 4 m' 30,725.00 41,214.00 122,900.00 123,000.00
814 Pipa winlon warna putih D 5 m' 45,200.00 58,898.40 180,800.00 185,000.00
815 Pipa winlon warna putih D 6 m' 64,650.00 82,980.00 258,600.00 259,000.00
816 Pipa winlon warna putih D 8 m' 110,137.50 140,017.20 440,550.00 445,000.00
817 Pipa winlon warna putih D 10 m' 207,450.00 261,306.00 829,800.00 830,000.00
818 Pipa winlon warna putih C 5/8 m' 1,575.00 4,785.60 6,300.00 6,400.00
819 Pipa winlon warna putih C 1/2 m' 2,915.00 6,740.40 11,660.00 12,000.00
820 Pipa winlon warna putih C 3/4 m' 3,190.00 7,650.00 12,760.00 13,000.00
821 Pipa winlon warna putih C 1 m' 4,725.00 8,352.00 18,900.00 19,900.00
822 Pipa winlon warna putih C 1 1/4 m' 5,500.00 10,200.00 22,000.00 22,000.00
823 Pipa winlon warna putih C 1 1/2 m' 6,875.00 11,688.00 27,500.00 28,000.00
824 Pipa winlon warna putih C 2 m' 9,652.50 15,180.00 38,610.00 39,700.00
825 Pipa winlon warna putih C 2 1/2 m' 12,155.00 17,700.00 48,620.00 50,000.00
826 Pipa winlon warna putih C 3 m' 15,150.00 21,936.00 60,600.00 61,000.00
### 827 Pipa winlon warna putih C 4 m' 20,185.00 28,226.40 80,740.00 82,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
828 Pipa vilano warna putih AW 1/2 m' 4,000.00 8,640.00 16,000.00 17,500.00
829 Pipa vilano warna putih AW 3/4 m' 5,500.00 9,912.00 22,000.00 23,000.00
830 Pipa vilano warna putih AW 1 m' 7,177.50 11,940.00 28,710.00 29,800.00
831 Pipa vilano warna putih AW 1 1/4 m' 10,450.00 16,465.20 41,800.00 45,000.00
832 Pipa vilano warna putih AW 3 m' 32,650.00 43,363.20 130,600.00 132,000.00
833 Pipa vilano warna putih AW 4 m' 46,975.00 61,273.20 187,900.00 195,000.00
834 Pipa vilano warna putih AW 5 m' 78,250.00 98,842.80 313,000.00 315,000.00
835 Pipa vilano warna putih AW 6 m' 112,000.00 140,486.40 448,000.00 450,000.00
836 Pipa vilano warna putih D 1 1/4 m' 6,517.50 12,890.40 26,070.00 27,000.00
837 Pipa vilano warna putih D 1 1/2 m' 7,750.00 14,745.60 31,500.00 31,000.00
838 Pipa vilano warna putih D 2 m' 10,025.00 15,870.00 40,500.00 40,100.00
839 Pipa vilano warna putih D 2 1/2 m' 13,750.00 19,920.00 55,000.00 55,600.00
840 Pipa vilano warna putih D 3 m' 17,625.00 24,006.00 70,500.00 75,000.00
841 Pipa vilano warna putih D 4 m' 27,250.00 36,434.40 109,000.00 109,500.00
842 Pipa vilano warna putih D 5 m' 35,900.00 47,016.00 143,600.00 145,000.00
843 Pipa vilano warna putih D 6 m' 62,000.00 78,488.40 248,000.00 249,000.00
844 PVC Pipe dia. 150 mm m 25,000.00 216,015.60 25,000.00 26,000.00
845 Elbow 90̊, dia 150 mm bh 175,000.00 201,903.60 175,000.00 185,000.00
846 Elbow 45, dia 150 mm bh 185,000.00 176,010.00 185,000.00 195,000.00
847 Sochet dia. 150 bh 115,000.00 94,476.00 115,000.00 118,000.00
848 shortpipe ke HI dan pipa bh 22,000.00 383,910.00 22,000.00 25,000.00
849 saddle branch bh 420,000.00 460,020.00 450,000.00 420,000.00
850 solvent cement kg 15,000.00 62,370.00 15,000.00 16,000.00
851 PVC Pipe dia. 200 mm m 350,000.00 301,870.80 350,000.00 352,000.00
852 Sochet dia. 200 bh 315,000.00 190,575.00 315,000.00 316,000.00
853 Tee dia 200 x 150 mm bh 730,000.00 734,144.40 730,000.00 735,000.00
854 Pipa PVC ( class D ) dia 150 mm m' 90,000.00 91,440.00 90,000.00 91,000.00
855 Bend dia 150, 90 (DV) bh 40,000.00 45,738.00 45,700.00 40,000.00
856 Bend dia 150, 45 (DV) bh 45,750.00 45,738.00 45,750.00 45,800.00
857 sochet dia 150 mm (DV) bh 36,720.00 36,729.00 36,720.00 36,800.00
858 Pipa PVC ( class D ) dia 4" dia 100 mm, length = 4 m m' 48,700.00 48,752.88 48,700.00 48,750.00
859 Sochet dia. 100 mm bh 49,000.00 49,333.68 49,000.00 49,300.00
860 Bend dia 100, 90 bh 50,000.00 52,058.16 50,000.00 52,000.00
861 Bend dia 100, 45 bh 26,099.00 26,099.04 26,099.00 27,000.00
862 Tee Y 45 ; 4" x 2" bh 58,500.00 36,202.32 58,500.00 58,600.00
863 Tee Y 45 ; 4" x 3" bh 65,000.00 49,729.68 65,000.00 65,000.00
864 Tee Y 45 ; 4" x 4" bh 85,000.00 56,036.64 85,000.00 95,000.00
865 Dop PVC 4" bh 12,500.00 20,679.12 12,500.00 13,000.00
866 Reducer 150 x 100 mm bh 48,000.00 48,000.00 48,000.00 48,000.00
867 Pipa PVC ( class D ) dia 3" dia. 75mm, length 4 m m 31,100.00 31,132.20 31,100.00 32,000.00
868 Large Radius Elbow dia. 75, 90o bh 45,000.00 25,031.16 45,000.00 46,000.00
869 Bend dia 75, 45 bh 14,000.00 14,512.08 14,500.00 14,000.00
870 Sochet dia. 75 mm bh 9,000.00 9,051.24 9,100.00 9,000.00
871 Dop PVC 3" bh 10,500.00 10,991.64 10,500.00 10,600.00
872 Reducer 100 x 75 mm bh 50,000.00 51,600.00 50,000.00 51,500.00
873 Pipa PVC ( class D ) dia 2" m 30,000.00 16,080.00 30,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
874 Sochet dia. 50 mm bh 17,000.00 6,306.96 18,500.00 19,000.00 17,000.00
875 Large Radius Elbow dia. 50, 90o bh 11,000.00 11,032.56 11,300.00 11,000.00
876 Bend dia 50, 45 bh 6,500.00 6,501.00 6,500.00 6,550.00 6,551.00
877 Dop PVC 2" bh 9,000.00 9,702.00 9,000.00 10,000.00 10,000.00
878 Pipa PVC (class D), Ø 2 1/2" (63 mm) SCJ m 27,500.00 27,600.00 27,500.00 28,000.00 28,500.00
879 Socket dia 63 mm bh 8,000.00 9,000.00 8,500.00 8,000.00 8,650.00
880 Bend dia 63, 90o bh 7,200.00 7,200.00 7,200.00 7,250.00 7,400.00
881 Bend dia 63, 45o bh 5,200.00 5,280.00 5,280.00 5,200.00 5,400.00
882 Dop PVC 1 1/2" bh 4,100.00 4,200.00 4,100.00 4,300.00 4,100.00
883 Pipa PVC (class D), Ø 1 1/2" (40 mm) SCJ m 10,500.00 10,800.00 10,500.00 10,700.00 10,650.00
884 Socket dia 40 mm bh 5,200.00 5,400.00 5,200.00 5,350.00 5,400.00
885 Bend dia 40, 90o bh 2,600.00 2,640.00 2,620.00 2,670.00 2,600.00
886 Bend dia 40, 45o bh 3,100.00 3,120.00 3,100.00 3,120.00 3,400.00
887 Dop PVC 1 1/2" bh 2,100.00 2,160.00 2,120.00 2,100.00 2,150.00
888 Pipa PVC D, Ø 1 1/4" (30 mm) SCJ m 10,000.00 12,000.00 10,000.00 11,500.00 13,000.00
889 Socket dia 30 mm bh 3,500.00 3,780.00 3,700.00 3,500.00 3,800.00
890 Bend dia 30, 90o bh 1,500.00 1,800.00 1,500.00 1,700.00 1,900.00
891 Bend dia 30, 45o bh 1,610.00 1,620.00 1,610.00 1,650.00 1,621.00
892 Dop PVC 1 1/4" bh 1,040.00 1,080.00 1,085.00 1,040.00 1,100.00
893 Pipa PVC D, Ø 1" (25 mm) SCJ m 6,400.00 6,660.00 6,600.00 6,650.00 6,400.00
894 Socket dia 25 mm bh 2,200.00 2,220.00 2,200.00 2,250.00 2,350.00
895 Bend dia 25, 90o bh 1,025.00 1,020.00 1,025.00 1,200.00 1,250.00
896 Bend dia 25, 45o bh 1,000.00 1,020.00 1,035.00 1,200.00 1,000.00
897 Dop PVC 1 1/4" bh 850.00 900.00 850.00 900.00 950.00
898 Tee Y; 3" x 3" bh 21,000.00 21,000.00 21,000.00 22,000.00 23,000.00
899 Tee Y; 3" x 2" bh 26,000.00 26,400.00 26,500.00 26,000.00 27,000.00
900 Tee ; 2" x 2" bh 11,200.00 11,400.00 11,250.00 11,200.00 11,300.00
901 Sifon Crom Leher Angsa bh 350,000.00 184,143.96 350,000.00 351,000.00 351,500.00
902 Pipa PVC Ø 6" M 210,000.00 292,238.76 210,000.00 211,000.00 215,000.00
903 Pipa PVC Ø 4" M 89,000.00 136,798.20 89,000.00 90,000.00 91,000.00
904 Pipa PVC Ø 3" M 75,000.00 94,014.36 75,000.00 76,000.00 78,000.00
905 Pipa PVC Ø 2" M 50,000.00 43,797.60 50,000.00 51,000.00 53,000.00
906 Pipa GI Ø 4" M 16,000.00 557,997.00 16,000.00 17,000.00 18,000.00
907 Pipa GI Ø 3" M 18,000.00 401,940.00 18,000.00 19,000.00 19,800.00
908 Pipa GI Ø 2" M 12,000.00 255,717.00 12,000.00 13,000.00 14,000.00
909 PVC Tee R-R Ø 10" x 3" bh 90,000.00 7,185,994.20 90,000.00 91,000.00 92,000.00
910 PVC Tee R-R Ø 6" x 4" bh 87,000.00 1,704,780.00 87,000.00 88,000.00 89,000.00
911 PVC Tee R-R Ø 6" x 3" bh 66,000.00 1,801,800.00 66,000.00 67,000.00 68,000.00
912 PVC Tee R-R Ø 4" x 4" bh 63,000.00 942,480.00 63,000.00 64,000.00 65,000.00
913 PVC Tee R-R Ø 4" x 3" bh 53,000.00 824,670.00 53,000.00 54,000.00 56,000.00
914 PVC Tee R-R Ø 3" x 3" bh 48,000.00 418,294.80 48,000.00 49,000.00 50,000.00
915 PVC Tee R-R Ø 2" x 3" bh 73,000.00 436,590.00 73,000.00 74,000.00 75,000.00
916 PVC Tee R-SC Ø 4" x 2" bh 69,000.00 658,350.00 69,000.00 70,000.00 71,000.00
917 PVC Tee R-SC Ø 3" x 2" bh 51,000.00 416,640.00 51,000.00 52,000.00 53,000.00
918 PVC Tee SC-SC Ø 2" x 2" bh 415,000.00 93,990.00 415,000.00 416,000.00 418,000.00
919 CI Giboult Joint Std Jis Ø 10" bh 395,000.00 2,201,370.60 395,000.00 398,000.00 399,000.00
920 CI Giboult Joint Std SII Ø 6" bh 380,000.00 968,814.00 380,000.00 385,000.00 386,000.00
921 CI Giboult Joint Std SII Ø 4" bh 310,000.00 755,730.00 310,000.00 315,000.00 316,000.00
922 CI Giboult Joint Std SII Ø 3" bh 256,000.00 548,856.00 256,000.00 267,000.00 269,000.00
923 CI Gate Valve FL- FL Ø 4" bh 278,000.00 5,821,200.00 278,000.00 279,000.00 279,000.00
924 CI Plat Cap Ø 4" bh 186,000.00 278,933.16 186,000.00 187,000.00 188,000.00
925 PVC Tapper Core Ø 4" bh 115,000.00 839,130.00 115,000.00 116,000.00 117,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
926 PVC Tapper Core Ø 3" bh 101,000.00 637,560.00 101,000.00 101,000.00 102,000.00
927 BS Bend FL- FL Ø 4" x 45 ̊ bh 115,000.00 996,534.00 115,000.00 116,000.00 118,000.00
928 BS Bend FL- FL Ø 3" x 45 ̊ bh 110,000.00 717,948.00 110,000.00 112,000.00 113,000.00
929 BS Flenge Ø 4" bh 55,000.00 215,384.40 55,000.00 56,000.00 58,000.00
930 BS Flange Ø 3" bh 50,000.00 172,972.80 50,000.00 51,000.00 53,000.00
931 Karet Packing Ø 4" bh 99,000.00 29,106.00 99,000.00 101,000.00 102,000.00
932 Karet Packing Ø 3" bh 90,000.00 24,948.00 90,000.00 95,000.00 98,000.00
933 Bronze Gate Valve Ø 3" bh 60,000.00 1,940,400.00 60,000.00 62,000.00 63,000.00
934 Bronze Gate Valve Ø 2" bh 55,000.00 708,246.00 55,000.00 56,000.00 56,000.00
935 PVC Valve Sochet Ø 3" bh 90,000.00 90,000.00 91,000.00 93,000.00
936 PVC Valve Sochet Ø 2" bh 66,000.00 66,000.00 67,000.00 67,000.00
937 GI Cap Ø 3" bh 42,000.00 58,257.60 42,000.00 43,000.00 43,000.00
938 GI Cap Ø 2" bh 41,000.00 26,749.80 41,000.00 44,000.00 45,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
939 GI Elbow Ø 2" bh 6,000.00 50,011.20 6,000.00
940 PVC Bend R- R Ø 4" x 90 ̊ bh 38,000.00 284,647.20 38,000.00
941 PVC Bend R- R Ø 4" x 45 ̊ bh 40,000.00 182,034.60 40,000.00
942 PVC Bend R- R Ø 3" x 45 ̊ bh 25,000.00 132,315.60 25,000.00
943 PVC Bend R- R Ø 3" x 90 ̊ bh 21,000.00 138,784.80 21,000.00
944 PVC Elbow Ø 2" bh 10,000.00 51,282.00 10,000.00
945 PVC Reducer R-R Ø 4" x 3" bh 65,000.00 136,548.00 65,000.00
946 PVC Reducer R-R Ø 3" x 2" bh 60,000.00 65,742.00 60,000.00
947 Beton Path box bh 30,000.00 381,390.00 30,000.00
948 Beton KS bh 15,000.00 69,360.00 15,000.00
949 Pipa Selubung Valve M 30,000.00 98,024.52 30,000.00
950 Penutup Pipa bh 18,000.00 22,358.40 18,000.00
951 Patok UP bh 65,000.00 4,065.60 65,000.00
952 Beton Penahan Ø 10" bh 920,000.00 926,762.76 920,000.00 925,000.00
953 Beton Penahan Ø 6" bh 195,000.00 198,600.60 198,000.00 195,000.00
954 Beton Penahan Ø 4" bh 68,000.00 68,967.36 68,000.00 68,500.00
955 Beton Penahan Ø 3" bh 135,000.00 158,835.60 155,000.00 135,000.00
956 Beton Penahan Ø 2" bh 2,500.00 2,719.20 2,500.00 2,700.00
957 Baut Dynabol bh 4,000.00 56,040.00 4,000.00

BAHAN LISTRIK
958 Coaxial cable 5C - 75 ohm commscof m1 25,000.00 28,380.00 25,000.00
959 Box Panel (3 mm) (400 x 600) Bh 850,000.00 829,862.40 850,000.00
960 Figting lampu Broco Bh 15,000.00 30,492.00 15,000.00
961 Inbow dos plastik clipsal E 157 P OB bj 8,000.00 16,542.24 8,000.00
962 Kabel NYM 2 x 1.5 mm Suprime NYM m1 7,000.00 15,246.00 7,000.00
963 Kabel NYY 2 x 1.5 mm m1 8,900.00 22,107.36 8,900.00
964 Kabel NYM 2 x 2.5 mm m1 12,000.00 22,869.00 12,000.00
965 Kabel NYY 3 x 1.5 mm m1 14,000.00 27,442.80 14,000.00
966 Kabel NYM 3 x 2.5 mm m1 15,500.00 29,700.00 15,500.00
967 Kabel NYY 3 x 2.5 mm m1 19,500.00 38,643.00 19,500.00
968 Kabel NYM 4 mm m1 30,000.00 60,093.00 30,000.00
969 Kabel NYY 2 x 2,5 mm m1 17,000.00 29,729.04 17,000.00
970 Kabel Twisteed 2 x 16 mm m1 5,500.00 24,717.00 5,500.00
971 Kabel telephone m1 3,000.00 24,231.24 3,000.00
972 Klem clipsal 20 mm bj 2,500.00 15,280.32 2,500.00
973 Casing Lampu Bawah Air bh 85,000.00 88,704.00 85,000.00
974 Casing Lampu Tangga bh 90,000.00 92,169.00 90,000.00
975 Kap Lampu 14 Inchi Aluminium bh 120,000.00 124,740.00 120,000.00
976 Fitting Gantung E27 bh 10,000.00 21,422.40 10,000.00
977 Lampu Son 150 Watt Setara Philips Set 80,000.00 83,760.00 80,000.00
978 Lampu Mercury (halaman) bh 550,000.00 640,932.00 550,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
979 Lampu Mercury 125 Watt Setara Philips Set 60,000.00 70,032.00 60,000.00 60,500.00
980 Lampu Mercury 250 Watt Setara Philips Set 66,000.00 112,140.00 66,000.00 66,500.00
981 Lampu Mercury 400 Watt Setara Philips Set 150,000.00 152,640.00 150,000.00 151,000.00
982 Lampu pijar 10 Watt Setara Philips bh 9,000.00 11,110.80 9,000.00 9,500.00
983 Lampu pijar 15 Watt Setara Philips bh 10,000.00 11,820.00 10,000.00 11,000.00
984 Lampu pijar 25 Watt Setara Philips bh 12,000.00 12,480.00 12,000.00 12,000.00
985 Lampu pijar 40 Watt Setara Philips bh 15,500.00 13,495.20 15,500.00 16,000.00
986 Lampu TL 20 Watt Komplit (Ballast Philips) bh 151,000.00 160,083.00 151,000.00 153,000.00
987 Lampu TL 25 Watt Komplit (Ballast Philips) bh 185,000.00 197,280.00 185,000.00 185,600.00
988 Lampu LED (5 Watt) Setara Philips Bh 60,000.00 78,632.40 60,000.00 61,000.00
989 Lampu LED (7 Watt) Setara Philips Bh 75,000.00 114,936.00 75,000.00 76,000.00
990 Lampu LED (10) Setara Philips Bh 85,000.00 161,276.40 85,000.00 89,000.00
991 Lampu LED (13 Watt) Setara Philips Bh 94,000.00 207,141.60 94,000.00 95,000.00
992 Lampu Sorot LED (5 Watt) Setara Philips Bh 32,000.00 290,274.00 32,000.00 32,000.00
993 Lampu Sorot LED (7 Watt) Setara Philips Bh 35,000.00 334,461.60 35,000.00 38,000.00

994 Lampu Sorot LED (10 Watt) Setara Philips Bh 40,000.00 390,951.00 40,000.00 41,000.00
995 Lampu Sorot LED (13 Watt) Setara Philips Bh 48,000.00 503,838.00 48,000.00 49,000.00
996 Lampu Sorot LED (25 Watt) Setara Philips Bh 65,000.00 1,050,042.00 65,000.00 68,000.00
997 Lampu Sorot LED (100 Watt) Setara Philips (ip65) Bh 68,000.00 2,009,700.00 68,000.00 68,600.00
998 Lampu Sorot Cahaya RGB (LED) 100 watt setara Philips (ip65) Bh 40,000.00 3,327,600.00 40,000.00 41,000.00
999 Lampu Sorot Bawah Cahaya Warm White (bolam) 400 watt setara Philips Bh 110,000.00 4,436,400.00 110,000.00 111,000.00
1000 Lampu Sorot Bawah Cahaya Warm White (LED) 10 watt setara Philips (ip Bh 45,000.00 381,870.00 45,000.00 46,000.00
1001 Lampu Sorot Bawah Cahaya Warm White (LED) 30 watt setara Philips (ip Bh 65,000.00 527,400.00 65,000.00 67,000.00
1002 Lampu Esensial (5 Watt) Setara Philips Bh 39,000.00 42,928.80 39,000.00 40,000.00
1003 Lampu Esensial (8 Watt) Setara Philips Bh 41,000.00 53,361.00 41,000.00 42,000.00
1004 Lampu Esensial (11 Watt) Setara Philips Bh 50,000.00 61,344.00 50,000.00 51,000.00
1005 Lampu Esensial (14 Watt) Setara Philips Bh 56,500.00 73,780.80 56,500.00 57,000.00
1006 Lampu Esensial (18 Watt) Setara Philips Bh 59,000.00 81,404.40 59,000.00 60,500.00
1007 Scot Light m2 65,000.00 123,354.00 65,000.00 66,000.00
1008 Magnet Contactor 80 A SN - 50 Bh 19,000.00 1,698,160.20 19,000.00 19,800.00
1009 MCB 3 phase 40 A MG Bh 445,000.00 481,704.96 445,000.00 447,000.00
1010 MCB 3 phase 63 A MG Bh 345,000.00 915,384.36 345,000.00 346,000.00
1011 Panel MDP Unit 36,500,000.00 47,256,000.00 36,500,000.00 36,800,000.00
1012 Panel SDP Unit 19,000,000.00 23,760,000.00 19,000,000.00 19,500,000.00
1013 Pipa clipsal 20 mm bt 12,000.00 21,344.40 12,000.00 13,000.00
1014 Pipa flexible clipsal 20 mm m1 4,000.00 15,846.00 4,000.00 5,000.00
1015 Saklar ganda Setara Broco Bh 18,000.00 56,040.00 18,000.00 19,000.00
1016 Saklar tunggal Setara Broco Bh 15,000.00 28,042.80 15,000.00 16,500.00
1017 SL 18 Watt Komplit bh 225,000.00 114,162.00 225,000.00 228,000.00
1018 Sock clipsal 20 mm bj 2,000.00 5,054.40 2,000.00 3,000.00
1019 Steker bh 15,000.00 21,030.00 15,000.00 16,000.00
1020 Stop Kontak bh 26,000.00 53,148.00 26,000.00 27,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1021 Stop Kontak Khusus (Kedap Air) bh 35,000.00 77,070.00 35,000.00 44,000.00 40,000.00
1022 Travo max 50 watt bh 147,000.00 1,040,460.00 148,000.00 149,000.00 147,000.00
1023 Tee dos clipsal 20 mm bh 8,000.00 10,966.80 8,000.00 9,000.00 9,000.00
1024 Time Switch Bh 585,000.00 654,885.00 585,000.00 595,000.00 590,000.00
1025 T Foring Bh 11,000.00 69,900.00 12,000.00 15,000.00 11,000.00

MARMER / GRANIT
1026 Marmer (30 x 30) m2 375,000.00 429,528.00 375,000.00 380,000.00
1027 Marmer (40 x 40) m2 417,000.00 417,780.00
1028 Granit (30 x 30) Tekstur Kasar Tebal 3 cm m2 495,000.00 1,107,000.00 495,000.00 496,000.00
1029 Batu Andesit (30 x 30 x 5 cm) m2 460,000.00 535,524.00 461,000.00 460,000.00
1030 Roster Keramik (12 x 11 x 24) bh 55,000.00 65,617.20 55,000.00 58,000.00

GRANIT TILE
1031 Essenza 40 x 40 m2 395,000.00 437,398.80 395,000.00 396,000.00
1032 Essenza 60 x 60 m2 470,000.00 537,259.20 470,000.00 470,000.00
1033 Granito 40 x 40 cm m2 435,000.00 483,136.80 435,000.00 436,000.00
1034 Nero Granito 30 x 60 cm m2 385,000.00 424,318.80 385,000.00 386,000.00
1035 Nero Granito 40 x 40 cm m2 430,000.00 483,256.80 430,000.00 432,000.00
1036 Nero Granito 60 x 60 cm m2 435,000.00 482,127.36 435,000.00 436,000.00
1037 Setara Ex Cina 60 x 60 cm m2 220,000.00 506,160.00 220,000.00 221,000.00
1038 Setara Ex Cina 80 x 80 cm m2 235,000.00 377,040.00 235,000.00 236,000.00

KERAMIK
1039 Keramik Asia Tile 20 x 20 kelas I warna muda m2 68,000.00 102,399.00 68,000.00 68,000.00
1040 Keramik Setara Asia Tile 20 x 20 kelas I warna tua m2 68,000.00 106,216.80 69,000.00 68,000.00
1041 Keramik Setara Asia Tile 20 x 25 kelas I m2 70,000.00 107,586.00 71,000.00 70,000.00
1042 Keramik Setara Asia Tile 30 x 30 kelas I warna muda m2 55,000.00 100,524.00 55,000.00 56,000.00
1043 Keramik Setara Asia Tile 30 x 30 kelas I warna tua m2 62,000.00 82,183.20 62,000.00 62,000.00
1044 Keramik Setara Asia Tile 40 x 40 kelas I m2 70,000.00 103,890.00 70,000.00 71,000.00
1045 Keramik Setara Asia Tile 60 x 60 kelas I Setara Platinum m2 148,000.00 198,000.00 148,000.00 149,000.00
1046 Keramik Setara ARWANA ( warna putih) M2 58,000.00 94,260.00 58,000.00 59,000.00
1047 Keramik Setara ARWANA ( warna tua) M2 65,000.00 93,060.00 65,000.00 66,000.00
1048 Keramik Setara Diamond 10/20 cm (Warna Muda) M2 70,000.00 93,984.00 70,000.00 71,000.00
1049 Keramik Setara Diamond 20/20 cm (Kelas I Warna Muda) M2 75,000.00 88,506.00 75,000.00 78,000.00
1050 Keramik Setara Diamond 30/30 cm (Kelas I Warna Muda) M2 76,000.00 91,476.00 76,000.00 77,000.00
1051 Keramik Setara Diamond 10/20 cm (Warna tua) M2 80,000.00 118,650.00 80,000.00 81,000.00
1052 Keramik Setara Diamond 20/20 cm (Kelas I Warna Tua) M2 71,000.00 92,076.00 71,000.00 72,000.00
1053 Keramik Setara Diamond 30/30 cm (Kelas I Warna Tua) M2 70,000.00 91,476.00 70,000.00 72,000.00
1054 Keramik Setara Ikad (Keramik) Kw. I 10 x 20 cm (DK warna muda) M2 66,000.00 91,476.00 66,000.00 68,000.00
1055 Keramik Setara Ikad (Keramik) Kw. I 10 x 20 cm (DK warna tua) M2 68,000.00 117,150.00 68,000.00 69,000.00
1056 Keramik Setara Ikad (Keramik) Kw. I 20 x 20 cm (warna tua) m2 70,000.00 91,740.00 70,000.00 71,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1057 Keramik Setara Ikad (Keramik) Kw. I 20 x 20 cm (warna muda) m2 65,000.00 91,740.00 65,000.00 66,000.00
1058 Keramik Setara Ikad (Keramik) Kw. I 30 x 30 cm m2 68,000.00 96,162.00 68,000.00 70,000.00
1059 Keramik Setara Ikad (Keramik) Kw. I 40 x 40 cm m2 71,000.00 106,722.00 71,000.00 72,000.00
1060 Keramik Setara Ikad (Keramik) Kw. I 50 x 50 cm m2 75,000.00 124,806.00 75,000.00 77,000.00
1061 Keramik Setara KIA 20/20 cm warna muda m2 70,000.00 105,072.00 70,000.00 72,000.00
1062 Keramik Setara KIA 30/30 cm warna muda m2 75,000.00 109,560.00 75,000.00 76,000.00
1063 Keramik Setara KIA 20/20 cm warna tua m2 65,000.00 100,623.60 65,000.00 68,000.00
1064 Keramik Setara KIA 30/30 cm warna tua m2 68,000.00 113,520.00 68,000.00 69,000.00
1065 Keramik Setara Mulia Warna Putih m2 105,000.00 107,484.96
1066 Keramik Setara Mulia Warna Tua m2 65,000.00 69,300.00
1067 Keramik Setara Mulia 20 x 20 cm Warna Tua m2 58,000.00 71,280.00 58,000.00 60,000.00
1068 Keramik Setara Mulia 20 x 20 cm Warna Muda m2 60,000.00 71,656.20 60,000.00 62,000.00
1069 Keramik Setara Mulia 30 x 30 cm Warna Putih m2 62,000.00 68,640.00 62,000.00 63,000.00
1070 Keramik Setara Mulia 30 x 30 Warna Marbel m2 70,000.00 69,960.00 70,000.00 72,000.00
1071 Keramik Setara Mulia 30 x 30 Warna Impresso m2 75,000.00 78,936.00 75,000.00 78,000.00
1072 Keramik Setara Mulia 40 x 40 cm kelas I m2 78,000.00 87,120.00 78,000.00 78,500.00
1073 Keramik Setara ROMAN 20/20 cm m2 85,000.00 134,640.00 85,000.00 86,000.00
1074 Keramik Setara ROMAN 30/30 cm m2 88,000.00 155,760.00 88,000.00 88,000.00
1075 Tegel PC abu - abu 20/20 cm m2 95,000.00 122,100.00 95,000.00 96,500.00
1076 Tegel PC Warna 20/20 cm m2 95,000.00 122,100.00 95,000.00 96,500.00
1077 Tegel PC Warna 30/30 cm m2 95,000.00 122,100.00 95,000.00 96,500.00
1078 Tegel 30 x 30 TB PC m2 95,000.00 122,100.00 95,000.00 96,500.00
1079 Tegel 30 x 30 TB PC Kuning m2 96,000.00 122,100.00 96,000.00 96,500.00
1080 Tegel 30 x 30 Warna Merah m2 96,000.00 122,100.00 96,000.00 96,500.00
1081 Tegel Bata 20 x 20 Merah m2 96,000.00 122,100.00 96,000.00 96,500.00
1082 Tegel Bata 20 x 20 PC m2 96,000.00 122,100.00 96,000.00 96,500.00
1083 Tegel B/TB 20 x 20 Kuning m2 96,000.00 122,100.00 96,000.00 96,500.00
1084 Tegel Mozaik Porselint 30/30 cm m2 118,000.00 117,810.00 118,000.00 119,000.00
1085 Tegel Wafel 20/20 cm Warna m2 121,000.00 106,722.00 121,000.00 123,000.00
1086 Ubin PC Warna bh 90,000.00 9,702.00 90,000.00 93,000.00
1087 Ubin PC Warna 20 / 20 Cm m2 90,000.00 114,345.00 90,000.00 93,000.00
1088 Batu Lahar 30/30 bh 135,000.00 38,808.00 135,000.00 135,000.00
1089 Porselint 11/11 cm bh 90,000.00 69,300.00 90,000.00 92,000.00
1090 Porselen m2 98,000.00 98,000.00 99,000.00

ATAP
1091 Alang-alang panjang 2,4 meter lbr 28,500.00 28,800.00 28,500.00
1092 Alluminium foil M2 Double rol 356,000.00 412,920.00 356,000.00 359,000.00
1093 Akustik 60 cm x 120 cm lbr 76,000.00 83,160.00 76,000.00 77,000.00
1094 Asbes Bubungan lbr 58,000.00 68,514.00 58,000.00 59,000.00
1095 Asbes Gelombang 1,80 m x 0,80 m lbr 48,000.00 53,961.60 48,000.00 49,000.00
1096 Asbes Gelombang 1,80 m x 1,05 m lbr 52,000.00 66,600.00 52,000.00 53,000.00
1097 Asbes Gelombang 2,10 m x 1,05 m lbr 68,000.00 78,672.00 68,000.00 68,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1098 Asbes Gelombang 2,4 m x 1,05 m lbr 81,000.00 92,136.00 81,000.00
1099 Asbes Rata 2 m x 1 m x 4 mm lbr 76,000.00 88,200.00 76,000.00
1100 Bentala tanah liat Ex Pejaten bh 82,000.00 129,726.00 82,000.00
1101 Bentala Ex Kapal 83,000.00 114,780.00 83,000.00
1102 Bentala Besar polos Lubang 24 cm bh 97,000.00 116,985.00 97,000.00
1103 Bentala Besar Warna Lubang 25 cm bh 133,000.00 155,040.00 133,000.00
1104 Bentala Besar polos Lubang 90 cm bh 202,000.00 231,600.00 202,000.00
1105 Bentala Besar Warna Lubang 90 cm bh 203,000.00 233,640.00 203,000.00
1106 Bubungan Besar bh 8,500.00 27,084.00 8,500.00
1107 Bubungan Kecil bh 7,000.00 21,060.00 7,000.00
1108 Bubungan Bambe Kecil bh 12,000.00 27,280.80 12,000.00
1109 Bubungan Bulat Karang Pilang bh 29,000.00 35,250.00 29,000.00
1110 Bubungan Bulat Jati Wangi bh 21,000.00 26,184.00 21,000.00
1111 Bubungan Bulat Ngalayur isi 3,5/m bh 18,000.00 25,020.00 18,000.00
1112 Bubungan Besar Good Year bh 28,000.00 34,920.00 28,000.00
1113 Bubungan Beton Cisangkan bh 21,000.00 38,880.00 21,000.00
1114 Bubungan Gerard lbr 18,000.00 97,200.00 18,000.00
1115 Bubungan Karang Pilang isi 3,5/m bh 28,000.00 38,808.00 28,000.00
1116 Bubungan Pletong Jatiwangi bh 33,000.00 23,469.60 33,000.00
1117 Bubungan SL Utama bh 18,000.00 24,360.00 18,000.00
1118 Bubungan SL Ngalayur bh 17,500.00 17,760.00 20,000.00
1119 Bubungan Segi Tiga Karang Pilang bh 27,000.00 29,640.00 27,000.00
1120 Bubungan Utama isi 3,5/m bh 11,500.00 23,700.00 11,500.00
1121 Genteng Bambe bh 7,000.00 11,760.00 7,000.00
1122 Genteng Bambe Karang Pilang bh 8,000.00 11,760.00 8,000.00
1123 Genteng Bambe Kecil bh 6,000.00 9,840.00 6,000.00
1124 Genteng Beton Cisangkan bh 12,000.00 22,620.00 12,000.00
1125 Genteng Gemini bh 6,800.00 11,760.00 6,800.00
1126 Genteng Gerard Polos m2 350,000.00 363,720.00
1127 Genteng Good Year m2 8,500.00 9,840.00 8,500.00
1128 Genteng Kanmuri (glazur) isi 14/m2 bh 4,100.00 19,800.00 4,100.00
1129 Genteng Kodok Lokal bh 6,000.00 50,640.00 6,000.00
1130 Genteng Kodok Kamulan bh 5,100.00 7,320.00 5,100.00
1131 Genteng Kodok Karang Pilang (Bambe) isi 20/m2 bh 6,000.00 8,520.00 6,000.00
1132 Genteng Kodok Karang Pilang (Bisma) isi 20/m2 bh 7,000.00 9,180.00 7,000.00
1133 Genteng Kodok Karang Pilang (Good Year) isi 20/m2 bh 7,000.00 9,960.00 7,000.00
1134 Genteng Kodok Karang Pilang (Surabaya) bh 6,500.00 6,120.00 6,500.00
1135 Genteng Kodok Soka bh 4,000.00 7,320.00 4,000.00
1136 Genteng Lestari bh 3,900.00 66,000.00 3,900.00
1137 Genteng Metal 59,000.00 60,000.00
1138 Genteng Metal 80 x 77,6 (Polos) lbr 53,000.00 92,400.00 53,000.00
1139 Genteng Metal 80 x 77,6 (Pasir) lbr 78,000.00 87,060.00 78,000.00
1140 Genteng Morando Abadi isi 18/m2 bh 10,800.00 10,800.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1141 Genteng Morando Jatiwangi isi 18/m2 bh 6,500.00 12,942.00 6,500.00
1142 Genteng Morando Ngalayur isi 20/m2 bh 5,100.00 7,500.00 5,100.00
1143 Genteng Morando Metal bh 75,000.00 92,400.00 75,000.00
1144 Genteng Pejaten Mini bh 3,900.00 5,280.00 3,900.00
1145 Genteng Plentong bh 3,100.00 5,880.00 3,100.00
1146 Genteng plentong dicat bh 4,000.00 6,120.00 4,000.00
1147 Genteng Plentong Mantili bh 2,800.00 6,240.00 2,800.00
1148 Genteng Plentong Pejaten / Darmasaba bh 3,000.00 7,440.00 3,000.00
1149 Genteng Plentong Jatiwangi / Surabaya bh 3,500.00 9,240.00 3,500.00
1150 Genteng Portugis bh 2,800.00 13,800.00 2,800.00
1151 Genteng Pres Besar bh 3,500.00 5,640.00 3,500.00
1152 Genteng Pres Besar Cat bh 4,000.00 5,880.00 4,000.00
1153 Genteng Pres Mini bh 2,900.00 3,600.00 2,900.00
1154 Genteng Pres Mini Cat bh 3,000.00 5,880.00 3,000.00
1155 Genteng Terreal bh 15,000.00 16,200.00
1156 Genteng T. Romana bh 15,000.00 16,200.00
1157 Genteng Besar polos Lubang 35 cm bh 3,500.00 6,120.00 3,500.00
1158 Genteng Besar Warna Lubang 35 cm bh 3,800.00 6,120.00 3,800.00
1159 Fiberglas (1.80 x 0.80) M2 lbr 60,000.00 66,000.00 60,000.00
1160 Ijuk kg 4,500.00 6,120.00 4,500.00
1161 Ijuk Bersih bh 17,000.00 19,200.00
1162 Ijuk Lampung bh 15,000.00 16,440.00
1163 Ikut Celedu bh 290,000.00 290,400.00
1164 Ikut Celedu Besar Polos bh 109,000.00 125,400.00 109,000.00
1165 Ikut Celedu Besar Warna bh 120,000.00 138,600.00 120,000.00
1166 Ikut Celedu Kecil Polos bh 92,500.00 93,060.00 187,000.00
1167 Ikut Celedu Kecil Warna bh 125,000.00 125,400.00 189,000.00
1168 Kawat las kg 80,500.00 112,200.00 80,500.00
1169 Kawat Diameter 4 mm kg 35,000.00 125,400.00 35,000.00
1170 Murda / Puntal Paras bh 165,000.00 316,800.00 165,000.00
1171 Murda tanah liat Ex Pejaten bh 145,000.00 171,600.00 145,000.00
1172 Murda Kecil Polos Lubang 25 cm bh 108,000.00 122,760.00 108,000.00
1173 Murda Kecil Warna Lubang 25 cm bh 128,000.00 145,200.00 128,000.00
1174 Profil Aluminium "T" m3 255,000.00 316,800.00 255,000.00
1175 Seng BJLS 0,18 gelombang lbr 125,000.00 145,200.00 125,000.00
1176 Seng BJLS 0,22 gelombang lbr 135,000.00 151,800.00 135,000.00
1177 Seng BJLS 0,30 gelombang lbr 140,000.00 167,640.00 140,000.00
1178 Seng Zincalume Panjang 6m Tebal 0,5 mm lbr 118,000.00 132,000.00 118,000.00
1179 Seng Plat Lebar 0,90 M lbr 61,000.00 73,920.00 61,000.00
1180 Seng Plat 3" x 6" BJLS 28 lbr 87,000.00 99,000.00 87,000.00
1181 Seng Plat Aluminium lbr 65,000.00 76,560.00 65,000.00
1182 Sirap lbr 10,000.00 12,120.00 10,000.00
1183 Subeng Besar Polos lbr 15,600.00 17,160.00 15,600.00
1184 Subeng Besar Warna lbr 8,500.00 8,976.00 8,500.00
1185 Subeng Kecil Polos lbr 8,500.00 10,560.00 8,500.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1186 Subeng Kecil Warna bh 5,500.00 5,793.48 8,500.00

TALI
1187 Tali Ijuk kg 11,000.00 11,160.00 11,500.00
1188 Tali pengikat ikat 25,500.00 25,832.40 30,000.00
1189 Tali pengikat alang-alang ikat 34,000.00 34,320.00 35,000.00
1190 Tali Rafia Gulung 6,500.00 6,870.00 25,500.00

SANITAIR
1191 Bak mandi fibre glass 70x70x66 cm bh 370,000.00 488,400.00 370,000.00
1192 Bak mandi porselin/ keramik bh 365,000.00 509,454.00 365,000.00
1193 Bak mandi keramik 50x50 bh 209,000.00 394,482.00 209,000.00
1194 Floor Drain " TOTO TypeTx 1 Bv 1 " Square Flange " bh 218,000.00 657,720.00 218,000.00
1195 Floor Drain Plastic bh 27,000.00 27,600.00
1196 Floor Drain Stainless bh 90,000.00 92,301.00
1197 Floor drain plastik Setara Alianco bh 30,000.00 40,359.00 30,000.00
1198 Floor drain stainless Setara Wasser bh 185,000.00 257,400.00 185,000.00
1199 Dudukan Kloset dan Perlengkapannya bh 2,800,000.00 2,917,860.00
1200 Kloset duduk INA Komplit bh 1,100,000.00 2,445,564.00 1,100,000.00
1201 closet duduk INA (putih) STD bh 975,000.00 1,684,260.00 975,000.00
1202 closet duduk INA (warna) bh 995,000.00 2,100,000.00 995,000.00
1203 Kloset duduk Amerika Standar Winplus bh 1,875,000.00 3,814,800.00 1,875,000.00
1204 closet duduk TOTO (putih) STD bh 1,945,000.00 1,815,600.00 1,945,000.00
1205 closet duduk TOTO (warna) bh 2,000,000.00 2,376,660.00 2,000,000.00
1206 Kloset duduk " TOTO Type AVANTE CW 821 PJ / SW 821JP COMPLIT bh 6,550,000.00 2,707,188.00 6,550,000.00
1207 Kloset duduk " TOTO Type AVANTE CW 821J"/ SW 821JP COMPLIT bh 6,700,000.00 8,955,018.60 6,700,000.00
1208 Kloset duduk " TOTO Type AVANTE CW 823 J bh 10,500,000.00 12,210,000.00 10,500,000.00
1209 Kloset duduk " TOTO Type CW 660J bh 1,850,000.00 1,151,317.20 1,850,000.00
1210 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT bh 1,950,000.00 2,839,716.00 1,950,000.00
1211 Kloset duduk " TOTO Type CW 660J / SW 660J COMPLIT WARNA bh 2,250,000.00 3,630,000.00 2,250,000.00
1212Kloset duduk " TOTO Type CW 660J WARNA COMPLIT bh 2,350,000.00 1,287,706.20 2,350,000.00
1213 Kloset duduk " TOTO Type CW 661JT1 BODI COMPLIT bh 3,100,000.00 4,695,768.00 3,100,000.00
1214 Kloset duduk " TOTO Type CW 661JT1" / SW 661JP COMPLIT bh 3,950,000.00 6,006,396.00 3,950,000.00
1215 Kloset duduk " TOTO Type CW 661JT1" / SW 784JP COMPLIT bh 4,500,000.00 5,431,800.00 4,500,000.00
1216 Kloset jongkok " TOTO Type CE 6 COMPLIT bh 565,000.00 667,557.00 565,000.00
1217 Kloset jongkok " TOTO Type CE 7 COMPLIT bh 575,000.00 498,138.96 575,000.00
1218 closet jongkok porselin/ keramik bh 215,000.00 473,626.56 215,000.00
1219 Kloset porselin jongkok TOTO (standar) bh 315,000.00 632,148.00 315,000.00
1220 Kloset porselin jongkok Ina (standar) bh 118,000.00 391,281.00 118,000.00
1221 Kran biasa Setara Onda bh 25,000.00 76,230.00 25,000.00
1222 Kran SunEi PI/3 JHR bh 215,000.00 126,720.00 215,000.00
1223 Kran TOTO T 205 LCSC bh 275,000.00 353,040.00 275,000.00
1224 Kran TOTO T 205 MC bh 385,000.00 514,800.00 385,000.00
1225 Kran TOTO T 23 B13 bh 395,000.00 389,400.00 395,000.00
1226 Kran TOTO T 23 B13V7NB bh 375,000.00 393,600.00 375,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1227 Kran TOTO T 26 - 13 bh 395,000.00 525,360.00 395,000.00
1228 Kran TOTO TX 109 LH bh 985,000.00 1,173,600.00 985,000.00
1229 Penyekat Urinoir " TOTO " Type A 100 " bh 1,425,000.00 2,079,330.00 1,425,000.00
1230 Shower Spray " TOTO Tx 403SPIV ( Pastel Ivory ) bh 375,000.00 737,160.00 375,000.00
1231 Soap holder " TOTO " Type S 6 N " bh 165,000.00 208,560.00 165,000.00
1232 Seal tape bh 5,000.00 8,218.80 5,000.00
1233 Urinoir TOTO (STD) bh 3,100,000.00 3,818,100.00 3,100,000.00
1234 Urinoir " TOTO U 57 M bh 1,615,000.00 4,116,720.96 1,615,000.00
1235 Urinoir " TOTO U 57 M BODI bh 495,000.00 2,079,620.40 495,000.00
1236 Urinoir INA (STD) bh 610,000.00 3,796,980.00 610,000.00
1237 Wastagel KIA Standard bh 850,000.00 548,400.00 850,000.00
1238 Wastagel KIA Warna bh 510,000.00 549,960.00 510,000.00
1239 Wastafel TOTO (putih) bh 535,000.00 96,924.00 535,000.00
1240 Wastafel TOTO (warna) bh 475,000.00 1,816,056.00 475,000.00
1241 Wastafel Komplit " TOTO Tx " Type L 521V1A " bh 1,600,000.00 2,146,440.00 1,600,000.00
1242 Wastafel Komplit top Counter" TOTO " Type CERABO LW 523 " bh 1,750,000.00 1,305,117.00 1,750,000.00
1243 Wastafel INA (putih) bh 250,000.00 1,265,220.00 250,000.00
1244 Wastafel INA (warna) bh 275,000.00 1,265,220.00 275,000.00

KUNCI DAN PENGGANTUNG


1245 Engsel H ( 80 x 50) Ps 35,000.00 37,620.00 35,000.00
1246 Engsel kupu-kupu Rafes 4' 304 ps 70,000.00 93,390.00 70,000.00
1247 Engsel pintu Setara ECOLING Ps 52,000.00 102,966.60 52,000.00
1248 Engsel jendela Setara ECOLING Ps 45,000.00 67,156.32 45,000.00
1249 Engsel jendela Setara CAMEL Ps 60,000.00 64,620.00 60,000.00
1250 Espagnoleth Setara Rafes 60 cm Ps 75,000.00 92,340.00 75,000.00
1251 Grendel Setara ESBELA Bh 160,000.00 208,236.60 160,000.00
1252 Grendel tanam Setara CAMEL Bh 175,000.00 317,226.00 175,000.00
1253 Kait angin biasa Setara CAMEL Bh 35,000.00 78,150.00 35,000.00
1254 Kait angin diameter 10 mm Bh 40,000.00 40,000.00
1255 Kait angin lipat Setara ESBELA Bh 70,000.00 122,605.56 70,000.00
1256 Kait angin tarik Setara ESBELA Bh 55,000.00 87,219.00 55,000.00
1257 Kunci kuda 2 x putar Bh 95,000.00 95,000.00
1258 Kunci lif 1 x putar Setara BELLEZA Bh 225,000.00 287,760.00 225,000.00
1259 Kunci lif 2 x putar Bh 135,000.00 243,414.60 135,000.00
1260 Kunci pintu TOP Setara ESBELA bh 85,000.00 497,940.00 85,000.00
1261 Kunci pintu Vanesa Setara CAMEL bh 215,000.00 588,000.00 215,000.00
1262 Kunci pintu Setara ESBELLA bh 265,000.00 429,000.00 265,000.00
1263 Kunci Pintu 2 x putar Setara SES Bh 395,000.00 641,400.00 395,000.00
1264 Kunci pintu Setara DELWIN) bh 295,000.00 300,900.00 295,000.00
1265 Kunci shang hae 2 x putar Bh 298,000.00 271,200.00 298,000.00
1266 Kunci slot / Grendel Pintu Setara DELLWYN bh 310,000.00 407,580.00 310,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1267 Kunci tanam 2 slag Setara Dexon bh 245,000.00 406,791.00 245,000.00
1268 Kunci silinder bh 95,000.00 95,000.00
1269 Door holder bh 80,000.00 80,000.00
1270 Rel pintu sorong m' 415,000.00 415,000.00
1271 Rolling door plaat M2 495,000.00 617,760.00 495,000.00
1272 Rolling Door Aluminium M2 375,000.00 928,230.00 595,000.00
1273 Besi Tangga D 19, Enamel Cat bh 53,000.00 54,000.00
1274 Handle Besi Ø 12, Enamel Cat bh 29,000.00 30,000.00

PAKU
1273 Paku Beton Kg 58,000.00 47,835.60 58,000.00
1274 Paku Usuk Kg 15,000.00 23,700.00 15,000.00
1275 Paku Reng Kg 15,000.00 20,790.00 15,000.00
1276 Paku List Kg 22,000.00 31,680.00 22,000.00
1277 Paku Seng Ulir bh 2,500.00 2,100.00 2,500.00
1278 Paku 2-4 cm kg 18,000.00 29,640.00 18,000.00
1279 Paku Pancing 60 x 230 Kg 25,000.00 409,200.00 25,000.00
1280 Paku 5-12 cm kg 18,000.00 32,280.00 18,000.00
1281 Paku 2 cm (30 kg) 3/4 inch SQ dus 450,000.00 666,738.60 450,000.00
1282 Paku 2,5 cm (30 kg) 1 inch SQ dus 455,000.00 707,520.00 455,000.00
1283 Paku 3 cm (30 kg) 1 1/4 inch SQ dus 460,000.00 711,480.00 460,000.00
1284 Paku 4 cm (30 kg) 1 1/2 inch SQ dus 475,000.00 711,480.00 475,000.00
1285 Paku 5 cm (30 kg) 2 inch SQ dus 485,000.00 711,480.00 485,000.00
1286 Paku 7,10,12 cm (3,4,5) inch SQ dus 486,000.00 640,800.00 486,000.00
1287 Paku 5 -12 cm (27kg) 2,3,4,5 inch dus 486,000.00 640,200.00 486,000.00
1288 Paku skrup 1/2" Kg 48,000.00 33,660.00 48,000.00
1289 Paku skrup 2" Kg 49,000.00 38,940.00 49,000.00
1290 Paku skrup 3.5" Kg 45,000.00 46,200.00 45,000.00
1291 Bendrat 20 kg rol 302,000.00 594,000.00 302,000.00
1292 Sekrup Kalisiboard buah 550.00 1,320.00 550.00

BETON CETAK
1293 Paving Arahan 30 x 30 tebal 6 cm (K225) m2 115,000.00 207,900.00 115,000.00 120,000.00
1294 Paving Arahan 20 x 20 tebal 6 cm (K225) m2 90,000.00 207,900.00 90,000.00 115,000.00
1295 Paving 10 x 20 cm tebal 6 cm K225 (Polos) m2 85,000.00 138,600.00 85,000.00 98,000.00
1296 Paving 10 x 20 cm tebal 6 cm K225 (Warna) m2 70,000.00 217,800.00 95,000.00 106,000.00 70,000.00
1297 Paving 20 x 20 cm tebal 6 cm K225 (Polos) m2 90,000.00 138,600.00 98,000.00 96,000.00 90,000.00
1298 Paving 20 x 20 cm tebal 6 cm K225 (Warna) m2 100,000.00 217,800.00 100,000.00 130,000.00
1299 Paving 10 x 20 cm tebal 6 cm K350 (Polos) m2 109,000.00 153,120.00 110,000.00 109,000.00
1300 Paving 10 x 20 cm tebal 6 cm K350 (Warna) m2 115,000.00 232,320.00 115,000.00 140,000.00
1301 Paving 20 x 20 cm tebal 6 cm K350 (Polos) m2 125,000.00 233,640.00 125,000.00 150,000.00
1302 Paving 20 x 20 cm tebal 6 cm K350 (Warna) m2 135,000.00 236,280.00 135,000.00 149,000.00
1303 Paving 10 x 20 cm tebal 8 cm K225 (Polos) m2 80,000.00 137,280.00 145,000.00 99,000.00 80,000.00
1304 Paving 10 x 20 cm tebal 8 cm K225 (Warna) m2 105,000.00 236,280.00 150,000.00 156,000.00 105,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1305 Paving 20 x 20 cm tebal 8 cm K225 (Polos) m2 102,000.00 137,280.00 158,000.00 102,000.00
1306 Paving 20 x 20 cm tebal 8 cm K225 (Warna) m2 120,000.00 236,280.00 160,000.00 165,500.00 120,000.00
1307 Paving 10 x 20 cm tebal 8 cm K350 (Polos) m2 119,000.00 174,240.00 120,000.00 119,000.00
1308 Paving 10 x 20 cm tebal 8 cm K350 (Warna) m2 145,000.00 251,460.00 145,000.00 185,000.00
1309 Paving 20 x 20 cm tebal 8 cm K350 (Polos) m2 135,000.00 195,360.00 135,000.00 138,000.00
1310 Paving 20 x 20 cm tebal 8 cm K350 (Warna) m2 145,000.00 251,460.00 145,000.00 178,000.00
1311 Paving 20 x 20 cm tebal 8 cm K400 (Polos) m2 146,000.00 208,560.00 185,000.00 146,000.00
1312 Paving 20 x 20 cm tebal 8 cm K400 (Warna) m2 186,000.00 262,020.00 195,000.00 186,000.00
1313 Paving Tiga Berlian tebal 6 Cm K225 (Polos) m2 85,000.00 130,020.00 85,000.00 96,000.00
1314 Paving Tiga Berlian tebal 6 cm K225 (Warna) m2 95,000.00 208,560.00 95,000.00 146,000.00
1315 Paving segi enam xexagon 6 cm K225 pc m2 96,800.00 108,000.00 96,800.00
1316 Paving segi enam xexagon 6 cm K225 merah m2 105,000.00 118,000.00 105,000.00
1317 Paving segi enam xexagon 6 cm K225 hitam m2 119,000.00 120,000.00 119,000.00
1318 Paving segi enam xexagon 6 cm K300 pc m2 110,000.00 110,000.00 126,000.00
1319 Paving segi enam xexagon 6 cm K300 merah m2 105,000.00 105,000.00 136,000.00
1320 Paving segi enam xexagon 6 cm K300 hitam m2 146,000.00 175,000.00 146,000.00
1321 Paving segi enam xexagon 6 cm K350 pc m2 156,000.00 165,000.00 156,000.00
1322 Paving segi enam xexagon 6 cm K350 merah m2 158,000.00 175,000.00 158,000.00
1323 Paving segi enam xexagon 6 cm K350 hitam m2 160,000.00 185,000.00 160,000.00
1324 Paving segi enam xexagon 6 cm K400 pc m2 178,000.00 188,000.00 178,000.00
1325 Paving segi enam xexagon 6 cm K400 merah m2 165,000.00 165,000.00 185,000.00
1326 Paving segi enam xexagon 6 cm K400 hitam m2 160,000.00 160,000.00 196,000.00
1327 Paving bujur sangkar tanpa tias 6 cm K225 pc m2 160,000.00 160,000.00 175,000.00
1328 Paving bujur sangkar tanpa tias 6 cm K225 merah m2 175,000.00 175,000.00 196,000.00
1329 Paving bujur sangkar tanpa tias 6 cm K225 hitam m2 185,000.00 185,000.00 206,000.00
1330 Paving bujur sangkar tanpa tias 8 cm K225 pc m2 205,000.00 205,000.00 211,000.00
1331 Paving bujur sangkar tanpa tias 8 cm K225 merah m2 210,000.00 210,000.00 218,000.00
1332 Paving bujur sangkar tanpa tias 8 cm K225 hitam m2 215,000.00 215,000.00 220,000.00
1333 Box Culvert Type 600x600x1200 K 350 Bh 1,800,000.00 3,893,911.20 1,800,000.00
1334 Box Culvert Type 800x800x1200 K 350 Bh 2,430,000.00 4,853,199.60 2,430,000.00
1335 Box Culvert Type 1000x1000X1200 K 350 Bh 3,540,000.00 5,981,168.16 3,540,000.00
1336 Box Culvert Type 1200x1200X1200 K 350 Bh 4,764,000.00 6,231,456.00 4,764,000.00
1337 Box Culvert Type 1500x1500x1200 K 350 Bh 7,650,000.00 13,796,640.00 7,650,000.00
1338 Box Culvert Type 2000x2000x1200 K 350 Bh 11,325,000.00 19,863,690.00 11,325,000.00
1339 Box Culvert Type 3000x2000x1200 K 350 Bh 18,540,000.00 20,346,480.00 18,540,000.00
1340 Box Culvert Type 3000x2500x1200 K 350 Bh 21,400,000.00 22,075,515.00 21,400,000.00
1341 Box Culvert Type 3000x3000x1200 K 350 Bh 23,500,000.00 23,867,613.00 25,100,000.00
1342 Saluran Berbentuk U Type 300x300x1200 K350 Bh 412,300.00 557,040.00 412,300.00
1343 Saluran Berbentuk U Type 300x400x1200 K350 Bh 435,000.00 663,300.00 435,000.00
1344 Saluran Berbentuk U Type 300x500x1200 K350 Bh 475,000.00 769,560.00 475,000.00
1345 Saluran Berbentuk U Type 400x400x1200 K350 Bh 447,000.00 771,540.00 447,000.00
1346 Saluran Berbentuk U Type 400x600x1200 K350 Bh 679,400.00 1,076,460.00 679,400.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1347 Saluran Berbentuk U Type 400x700x1200 K350 Bh 698,200.00 1,584,000.00 750,000.00 800,000.00 698,200.00
1348 Saluran Berbentuk U Type 500x500x1200 K350 Bh 565,400.00 1,584,000.00 800,000.00 850,000.00 565,400.00
1349 Saluran Berbentuk U Type 500x600x1200 K350 Bh 699,000.00 1,704,000.00 850,000.00 875,000.00 699,000.00
1350 Saluran Berbentuk U Type 500x700x1200 K350 Bh 844,000.00 1,848,000.00 895,000.00 898,000.00 844,000.00
1351 Saluran Berbentuk U Type 600x600x1200 K350 Bh 762,300.00 1,833,523.20 905,000.00 910,000.00 762,300.00
1352 Saluran Berbentuk U Type 600x700x1200 K350 Bh 879,200.00 1,519,749.00 975,000.00 985,000.00 879,200.00
1353 Saluran Berbentuk U Type 700x700x1200 K350 Bh 937,100.00 2,288,230.56 1,100,000.00 1,115,000.00 937,100.00
1354 Saluran Berbentuk U Type 600x800x1200 K350 Bh 897,300.00 1,618,320.00 1,125,000.00 1,200,000.00 897,300.00
1355 Saluran Berbentuk U Type 800x800x1200 K350 Bh 1,230,000.00 2,629,572.00 1,315,000.00 1,350,000.00 1,230,000.00
1356 Saluran Berbentuk U Type 800x1000x1200 K350 Bh 1,540,000.00 2,428,964.40 1,895,000.00 1,900,000.00 1,540,000.00
1357 Saluran Berbentuk U Type 1000x1000x1200 K350 Bh 1,930,000.00 2,550,240.00 2,250,000.00 2,300,000.00 1,930,000.00
1358 Bentala Exs Kapal (Paras) bh 25,000.00 94,248.00 25,000.00 30,000.00
1359 Bentala Exs Kapal (Terakota) bh 30,000.00 94,248.00 30,000.00 35,000.00
1360 Kanstein Segi Lima P40 bh 51,500.00 51,600.00 55,000.00
1361 Kanstein Segi Lima P50 bh 60,000.00 61,380.00 60,000.00
1362 Kanstein 40x28x15/12 cm bh 65,000.00 109,800.00 65,000.00
1363 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) m' 98,000.00 98,000.00
1364 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) bh 49,000.00
1365 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) m' 88,000.00 88,000.00
1366 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) bh 44,000.00
1367 Kansteen K.250 Bh 45,000.00 83,160.00 45,000.00 70,000.00
1368 Kansteen Pendek K.250 Bh 34,500.00 34,650.00 50,000.00 75,000.00
1369 Kansteen Jalan Masuk K.250 Bh 80,000.00 90,090.00 80,000.00
1370 Kansteen Jalan Masuk 15x40x50 K.300 Bh 85,000.00 85,000.00
1371 Kansteen Segilima P.50, T.20, L.15 K.250 Bh 49,000.00 49,550.16 90,000.00
1372 Kansteen Bulat P.50, T.30, LA.10 LB.15 K.250 Bh 83,000.00 83,160.00 95,000.00
1373 Kanstein Jumbo (P:50,L:15,T:30 cm K225) m' 62,000.00 62,370.00 100,000.00 105,000.00
1374 Kansteen Jumbo P.50, T.30, L.15 K.250 Bh 115,000.00 130,284.00 125,000.00
1375 Kansteen Jumbo 15x30x50 K.300 Bh 55,000.00 120,582.00 45,000.00
1376 Kansteen Jumbo Mini 15x20x50 K.300 Bh 45,000.00 158,004.00 155,000.00
1377 Kansteen Persegi T 15, P50, L 20 K 225 Bh 76,000.00 76,230.00 112,000.00
1378 Kasnteen Kursi K225 120,000.00 126,819.00
1379 Kansteen Kursi T 15, L 40, P 50 K 225 160,000.00 166,320.00
1380 Kansteen Kursi T 10, L 40, P 50 K 225 130,000.00 131,670.00
1381 Kansteen Jumbo 15 x 30 x 50 K.300 m' 110,000.00 92,862.00
1382 Kansteen Jumbo Mini 15 x 20 x 50 K.300 m' 90,000.00 81,081.00
1383 Kansteen Kursi (Jalan Masuk) 15 x 40 x 60 K.300 110,000.00 113,652.00
1384 Kansteen kotak (P:50,t.20,La.10,Lb.16cm) K225 m' 100,000.00 100,000.00
1385 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) m' 105,000.00 105,000.00
1386 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) m' 95,000.00 95,000.00
1387 Tutup Got (Grill) (P:45, L:24, T:9 cm) Bh 67,000.00 83,160.00 67,000.00
1388 Tutup Got (Grill) (P:30, L:24, T:9 cm) Bh 67,000.00 83,160.00 645,000.00
1389 Plat Penutup 600 x 1200 Bh 541,000.00 789,327.00 541,000.00
1390 Plat Penutup 800 x 1200 Bh 675,000.00 1,096,326.00 675,000.00
1391 Plat Penutup 1000 x 1200 Bh 890,000.00 1,297,362.00 890,000.00
1392 Frame Manhole 600x600 Bh 543,200.00 706,200.00 543,200.00
1393 Frame Manhole 800x800 Bh 675,400.00 820,512.00 675,400.00
1394 Frame Manhole 1000x1000 Bh 763,200.00 1,015,938.00 763,200.00
1395 Cover manhole 600x600 Bh 534,500.00 1,161,468.00 534,500.00
1396 Cover manhole 800x800 Bh 675,400.00 1,431,045.00 1,100,000.00 675,400.00
1397 Cover manhole 1000x1000 Bh 763,200.00 1,663,200.00 763,200.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1398 Grass Block 36 X 54 cm tebal 9 cm K 225 m2 105,000.00 136,620.00 105,000.00 110,000.00
1399 Grass Block lobang 5, 30 X 30 cm tebal 7 cm K 225 m2 85,000.00 113,520.00 90,000.00 85,000.00
1400 Beton Cetak Greas Blok K.250 bh 20,500.00 20,790.00 78,000.00 75,000.00
1401 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) bh 47,500.00
1402 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) bh 52,500.00

PLAFOND & TIRPLEK


1401 Acustik 30/30 lbr 167,500.00 196,680.00 167,500.00 168,000.00
1402 Celling teak (0,62 x 2,40) m2 lbr 235,000.00 274,560.00 235,000.00 238,000.00
1403 Eternit lbr 30,000.00 34,320.00 30,000.00 32,000.00
1404 Playwood 3 mm Lbr 75,000.00 75,826.08 198,000.00 199,000.00
1405 Playwood 4 mm Setara Meranti Lbr 180,000.00 180,840.00 225,000.00 235,000.00
1406 Plywood 5 mm lbr 189,000.00 232,320.00 189,000.00 190,000.00
1407 Playwood 9 mm Setara Meranti lbr 210,000.00 258,720.00 210,000.00 215,000.00
1408 Playwood aluminium lbr 155,000.00 192,720.00 155,000.00 158,000.00
1409 Gypsum Board (120x240x9) lbr 68,000.00 1,155,000.00 68,000.00 70,000.00
1410 Kalsiboard (4,5 x 1220 x 2420) mm lbr 78,500.00 156,728.88 78,500.00 80,000.00
1411 Tea Block 18 mm 300,000.00 327,360.00
1412 Hard board MDF lbr 305,000.00 196,673.40 310,000.00 305,000.00
1413 Multiplek 6 mm lbr 195,800.00 246,840.00 195,800.00 196,000.00
1414 Multiplek 9mm lbr 243,000.00 311,520.00 243,000.00 244,000.00
1415 Multiplek 12 mm lbr 280,000.00 280,000.00 295,000.00
1416 Triplek tebal 3mm (2,7mm) kayu sengon lbr 48,500.00 78,600.00 48,500.00 49,000.00
1417 Triplek tebal 3mm (2,7mm) kayu semi meranti lbr 57,800.00 89,760.00 57,800.00 58,000.00
1418 Triplek tebal 4mm (3,6mm) kayu sengon lbr 60,000.00 76,890.00 60,500.00 60,000.00
1419 Triplek tebal 4mm (3,6mm) kayu semi meranti lbr 71,000.00 90,420.00 71,500.00 71,000.00
1420 Triplek tebal 6mm (5,2mm) kayu sengon I lbr 71,000.00 99,000.00 71,500.00 71,000.00
1421 Triplek tebal 6mm (5,2mm) kayu sengon II lbr 64,400.00 91,740.00 64,400.00 65,000.00
1422 Triplek tebal 6mm (5,2mm) kayu semi meranti lbr 87,800.00 107,679.00 87,800.00 88,000.00
1423 Triplek tebal 6mm (5,2mm) kayu semi meranti II lbr 79,000.00 103,620.00 80,800.00 79,000.00
1424 Triplek tebal 8,0mm kayu sengon I lbr 101,750.00 141,966.00 101,750.00 102,000.00
1425 Triplek tebal 8,0mm kayu sengon II lbr 97,400.00 126,390.00 97,400.00 98,000.00
1426 Triplek tebal 8,0mm kayu semi meranti lbr 122,500.00 157,080.00 122,500.00 123,000.00
1427 Triplek tebal 9,0mm kayu semi meranti II lbr 112,500.00 261,360.00 112,500.00 113,000.00
1428 Triplek tebal 12 mm kayu sengon I lbr 148,500.00 192,720.00 148,500.00 148,500.00
1429 Triplek tebal 12 mm kayu semi meranti lbr 210,800.00 236,280.00 210,800.00 211,000.00
1430 Triplek tebal 15 mm kayu semi meranti lbr 250,000.00 292,380.00 250,000.00 255,000.00
1431 Triplek tebal 18 mm kayu semi meranti lbr 211,000.00 324,192.00 211,500.00 211,000.00
1432 Teakwood 122 x 244 x 2,7 mm lbr 89,100.00 121,506.00 89,100.00 89,100.00
1433 Melamine Putih/Biru 2,7 lbr 102,900.00 125,400.00 102,900.00 103,000.00
1434 Triplek aluminium jruk asli lbr 120,500.00 151,800.00 120,500.00 122,000.00
1435 Triplek aluminium jruk standar lbr 98,500.00 134,640.00 98,500.00 99,000.00
1436 Block board 18 mm sengon lbr 200,200.00 250,668.00 200,200.00 205,000.00
1437 Block board 18 mm meranti super lbr 232,000.00 288,360.00 232,000.00 232,000.00
1438 Teak block 18mm lbr 257,900.00 305,520.00 257,900.00 258,000.00
1439 Rangka Aluminium m1 38,500.00 38,760.00 38,500.00 40,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1440 Rangka Metal Furing (2 x 4 cm) panjang 4 m btg 55,200.00 67,800.00 55,200.00 56,000.00
1441 Rangka Metal Furing (4 x 4 cm) panjang 4 m btg 57,000.00 83,160.00 67,850.00 57,000.00
1442 Teak wood (1,20x2,40x 0,4) lbr 88,900.00 118,020.00 89,000.00 88,900.00
1443 Teak wood (0,90x2,00 x 0,4) lbr 145,800.00 198,000.00 145,800.00 146,000.00
1444 Jabar Wood 4 mm lbr 146,500.00 146,916.00 175,000.00 178,000.00

BUIS BETON
1445 Buis beton Diameter 25 x 75 bh 89,600.00 105,072.00 89,600.00 90,000.00
1446 Buis beton Diameter 30 x 75 bh 113,900.00 130,812.00 113,900.00 115,000.00
1447 Buis beton Diameter 50 x 75 bh 201,000.00 245,520.00 201,000.00 205,000.00
1448 Buis Beton diameter 80 cm bh 156,500.00 156,710.40 225,000.00 250,000.00
1449 Buis Beton diameter 25 cm bh 85,000.00 76,461.00 85,000.00 90,000.00
1450 Buis Beton diameter 50 cm bh 95,000.00 69,762.00 95,000.00 100,000.00
1451 Buis Beton diameter 100 cm bh 250,000.00

BETON READY MIX


1452 Beton Ready Mix K-175 TM Kap 7 m3 m3 850,000.00 1,379,400.00 850,000.00 880,000.00
1453 Beton Ready Mix K-225 TM Kap 7 m3 m3 905,000.00 1,800,480.00 905,000.00 946,000.00
1454 Beton Ready Mix K-250 TM Kap 7 m3 m3 930,000.00 1,947,000.00 930,000.00 979,000.00
1455 Beton Ready Mix K-275 TM Kap 7 m3 m3 945,000.00 1,999,800.00 945,000.00 1,012,000.00
1456 Beton Ready Mix K-300 TM Kap 7 m3 m3 965,000.00 2,047,320.00 965,000.00 1,045,000.00
1457 Beton Ready Mix K-350 TM Kap 7 m3 m3 1,025,000.00 2,151,600.00 1,025,000.00 1,111,000.00
1458 Sewa Concrete pump/M3 ls 35,000.00 46,200.00 35,000.00 35,000.00
1459 Formite/penjaga jarak bekisting/spacer bh 3,000.00 3,900.00 3,000.00 32,000.00

TALANG
1460 Talang Karet L = 0.50 m' 20,000.00 137,214.00 20,000.00 21,600.00 22,000.00
1461 Talang Karet L = 0.90 m' 29,000.00 175,329.00 29,000.00 30,500.00 31,000.00
1462 Pipa Talang PVC Setara Maspion 6" Setengah Lingkaran m' 110,000.00 130,680.00 110,000.00 112,700.00 115,000.00
1463 Pipa Talang PVC Setara Maspion 6" Kotak m' 200,000.00 153,120.00 200,000.00 201,500.00 205,000.00

ASPAL, BBM DAN PELUMAS


1464 Aspal Penetrasi 60/70 Kg 15,600.00 16,632.00
1465 Aspal Curah Kg 15,500.00 16,632.00
1466 Aspal RC Kg 12,000.00 13,860.00
1467 Aspal Emulsi ltr 18,000.00 19,681.20
1468 Aspal Emulsi CRS 1 ltr 13,000.00 14,275.80
1469 Aspal Emulsi CRS 1 Modif 14,500.00 15,107.40
1470 Aspal Emulsi CRS 2 ltr 15,500.00 16,147.56
1471 Aspal Emulsi CSS 1 h Modif ltr 13,000.00 14,414.40
1472 Aspal Emulsi CSS 1 h ltr 12,500.00 13,375.56
1473 Aspal Emulsi CSS 1 / PCE ltr 14,000.00 14,137.20
1474 Minyak Aspal ( fluck oil ) Ltr 8,500.00 9,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1475 Minyak Tanah Ltr 17,200.00 18,503.76
1476 Minyak Tanah Industri Ltr 14,500.00 15,840.00
1477 Solar Ltr 9,150.00 10,567.92
1478 Solar Industri Ltr 9,662.50 10,395.00
1479 Premium Ltr 10,000.00 11,484.00
1480 Premium (industri) Ltr 8,700.00 9,240.00
1481 Pelumas ( olie ) Ltr 35,000.00 39,293.76
1482 Kayu Api M3 425,000.00 533,610.00
1483 Gas elpiji Kg 470,000.00 528,000.00
1484 Minyak Begesting ( B 115 ) Ltr 40,000.00 42,504.00
1485 Aspal Cold Mix (Readymix) Kg 2,500.00 3,360.00

ALAT PEMADAM KEBAKARAN


1486 Instalasi pipa induk BS 3" Sch M' 254,000.00 282,051.00
1487 Intalasi pipa distribusi BS 2" Sch M' 187,000.00 190,575.00
1488 Seamesi conection Bh 2,600,000.00 2,744,280.00
1489 Box hidran dengan kelengkapannya Bh 3,700,000.00 3,811,500.00
1490 Selang pemadam 30 m Bh 4,500,000.00 4,878,720.00
1491 Pemadam api ringan 6 kg Bh 1,533,000.00 1,677,720.00

TANAMAN
1492 Pohon Lianglio / Salix Babylonica pohon 750,000.00 720,720.00 750,000.00
1493 Palem Ekor Tupai / Wodyetia Bifurcata pohon 75,000.00 2,148,300.00 350,000.00 75,000.00
1494 Pohon Hias pohon 56,000.00 57,600.00
1495 Pohon Jepun / Plumeria Rubra pohon 400,000.00 2,079,000.00 400,000.00
1496 Pohon Pudak / Pandanus Tectorius pohon 250,000.00 2,772,000.00 1,500,000.00 250,000.00
1497 Pohon Ketapag Kencana / Terminalia Molineti pohon 150,000.00 2,217,600.00 750,000.00 150,000.00
1498 Pohon Sente Batang Hitam / Alokasia 'black' pohon 60,000.00 97,020.00 75,000.00
1499 Pohon Dadap Merah / Erythrina Crista Galli pohon 300,000.00 1,940,400.00 750,000.00 300,000.00
1500 Pohon Jepun Pagoda / Plumeria 'pagoda' pohon 350,000.00 2,217,600.00 350,000.00 500,000.00
1501 Pohon Tabebuya / Chrysotricha sp pohon 500,000.00 1,801,800.00 500,000.00 500,000.00
1502 Rumput (Sekelas rumput mutiara) m2 21,000.00 21,600.00
1503 Semak Jempiring / Gardenia Jasminioides polybag 5,000.00 11,781.00 5,000.00 10,000.00
1504 Semak Spathyphilum / Spathyphylum sp polybag 7,500.00 12,474.00 15,000.00 8,000.00
1505 Semak Reulia Besar / Reulia Malacosperma Giant polybag 250,000.00 5,544.00 350,000.00
1506 Semak Anturium Bunga / Anthurium Andreanum polybag 10,000.00 55,440.00 45,000.00 50,000.00
1507 Semak Hemigrapis / Hemigrapis sp polybag 2,500.00 6,930.00 3,000.00
1508 Semak Puring / Codeaium variegatum polybag 5,000.00 12,474.00 5,000.00 35,000.00
1509 Semak Pakis Bulu / Nephrolepis biserrata polybag 7,500.00 18,018.00 7,500.00
1510 Tanaman rumput mutiara/jepang m2 25,000.00 33,000.00
1511 Tanaman perdu m2 33,000.00 33,600.00
1512 Lili Bangkok / Hymenocalis litoralis polybag 3,500.00 12,474.00 10,000.00 10,000.00
1513 Jempiring / Gardenia jasminioides polybag 10,000.00 9,702.00 15,000.00 10,000.00
1514 Kaki Laba-laba / Oxmosilum Liniare Yellow polybag 22,000.00 22,176.00 -
1515 Semak Bawang-bawangan / Ornithogalum umbrellatum polybag 3,000.00 6,514.20 3,500.00 3,500.00
1516 Semak Kebang Kertas Daun Kecil / Bogenvile small leave polybag 17,500.00 22,176.00 17,500.00 20,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1517 Semak Lily Paris / Hymenocallis Speciosa polybag 2,500.00 5,544.00 3,000.00
1518 Semak Daun Philodendron / Philodendron sp polybag 7,000.00 18,018.00 17,500.00
1519 Semak Bunga Yolanda / Yolanda white flower polybag 8,500.00 13,860.00 17,500.00
1520 Semak Karembusa Putih / Tebermontana carembusa 'white' polybag 7,000.00 20,790.00 10,000.00 7,000.00
1521 Semak Simbang Darah / Excoecaria Cochinechinensis polybag 7,000.00 11,088.00 10,000.00 8,000.00
1522 Semak Bromelia / Bromelia sp polybag 50,000.00 207,900.00 75,000.00 50,000.00
1523 Pupuk Kandang m3 15,000.00 224,532.00 15,000.00 15,000.00

LAIN - LAIN
1524 Air Bersih Ltr 100.00 252.00 100.00
1525 Bak Cuci Aluminium 2 Lubang Bh 495,000.00 640,200.00 495,000.00
1526 Belanja Foto Copy Lembar 420.00 420.00 500.00 420.00
1527 Cangkul Bh 98,000.00 129,360.00 98,000.00
1528 Cangkul Gigi Bh 165,000.00 221,067.00 165,000.00
1529 Ember Bh 13,000.00 36,590.40 13,000.00
1530 Ember Hitam Bh 17,000.00 18,000.00 17,000.00 17,500.00
1531 Gerinding bh 575,000.00 748,440.00 575,000.00
1532 Helm Proyek Bh 45,000.00 111,295.80 45,000.00
1533 Hammer 3 kg Bh 110,000.00 145,200.00 110,000.00
1534 Instalasi Tata Suara Titik 475,000.00 543,840.00 475,000.00
1535 Isi Bay Fresh Ruangan Buah 60,000.00 60,000.00 65,000.00 60,000.00
1536 Isi Staples No 30. Pack 70,000.00 72,600.00 72,000.00 70,000.00
1537 Isi Sabun Hand Soap Buah 21,400.00 21,600.00 21,400.00 21,500.00
1538 Isi Kapur Barus Kg 50,000.00 52,800.00 50,000.00 51,000.00
1539 Kapi Bh 18,000.00 25,680.00 18,000.00
1540 Keni 2" Bh 7,000.00 22,107.36 7,000.00
1541 Keranjang Sampah Bh 45,000.00 151,800.00 45,000.00
1542 Keset Bh 95,000.00 98,400.00 95,000.00 97,000.00
1543 Lap Kanebo Bh 80,000.00 90,000.00 80,000.00 85,000.00
1544 Lap Pel / Alat Pengepelan Buah 230,000.00 234,000.00 235,000.00 230,000.00
1545 Linggis bh 75,000.00 126,000.00 75,000.00
1546 Masker Bh 15,000.00 76,560.00 15,000.00
1547 Ompreng Besar (bak Adonan) Bh 375,000.00 706,200.00 375,000.00
1548 Panyong Bh 115,000.00 129,960.00 115,000.00
1549 Pembersih Ban Ltr 45,000.00 49,200.00 45,000.00
1550 Pembersih Lantai Galon 65,000.00 68,400.00 65,000.00
1551 Pembersih Lantai Toilet Buah 20,000.00 21,000.00 20,000.00
1552 Pembersih Kaca Galon 60,000.00 64,800.00 60,000.00
1553 Pembersih Toilet Galon 45,000.00 50,400.00 45,000.00
1554 Pengelasan cm 25,000.00 25,080.00 25,000.00
1555 Pengharum Mobil Cair Ltr 40,000.00 42,000.00 40,000.00
1556 Pengharum Ruangan Buah 33,500.00 33,600.00 33,500.00
1557 Sabun Buah 13,000.00 13,200.00 13,000.00
1558 Sabit Bh 45,000.00 93,000.00 45,000.00
1559 Sapu lidi Ikat 10,000.00 10,500.00 10,000.00
1560 Sapu Ijuk Bh 30,000.00 34,800.00 30,000.00
1561 Sapu Bulu Ayam Super Bh 60,000.00 72,000.00 60,000.00
1562 Shampo Mobil Bh 40,000.00 43,200.00 40,000.00
1563 Sepatu Karet Ltr 145,000.00 184,503.00 145,000.00
1564 Sikat baja Bh 28,000.00 46,042.92 28,000.00
1565 Sikat Ban 17,400.00 17,400.00
1566 Skop Bh 78,000.00 113,400.00 78,000.00
NAMA TOKO
HARGA SATUAN HARGA
NO NAMA BARANG SAT.
2019 (Rp) WALIKOTA Ud Astiti Merta Aneka Makmur Ud. Kusuma Indah

1 2 3 4 5 6 7 8 9
1567 Tempat Sampah Tutup Buah 270,000.00 270,000.00
1568 Tissue Gulung Buah 54,000.00 54,000.00
1569 Tissue Kotak Pack 18,000.00 18,000.00
1570 Water mur Bh 48,000.00 85,800.00 48,000.00
1571 Pipa Tremi dan Casing pelindung Ls 145,000.00 178,200.00 145,000.00
1572 Pelumas (Oli) Ltr 47,280.00 47,280.00
1573 Ramset m' 10,000.00 19,800.00 10,000.00
1574 Pembuangan lumpur eks. Bor m3 132,000.00 132,000.00
1575 Mobilisasi dan demobilisasi alat bor auger ZKL28 unit 174,240,000.00 174,240,000.00
1576 Mobilisasi dan demobilisasi alat bor auger ZKL28 Unit 178,200,000.00 178,200,000.00
1577 Service Crane kapasitas 50 ton bln 15,000,000.00 174,900,000.00 15,000,000.00
1578 Excavator PC200 bln 123,420,000.00 123,420,000.00
1579 Pengadaan rail beam untuk pemancangan ls 22,440,000.00 22,440,000.00
1580 Pemotongan kepala tiang pancang turap m' 125,400.00 125,400.00
1581 Galian tanah untuk capping beam m3 138,600.00 138,600.00
1582 Pembuangan tanah galian m3 125,400.00 125,400.00
1583 Pekerjaan Cetakan/Tutup Kepala Kolom bh 330,000.00 330,000.00
1584 Pek. Pembuatan papan nama proyek ls 1,320,000.00 1,320,000.00
FTAR HARGA SATUAN BAHAN
TAHUN 2019

Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10
Keterangan

10

(Mengacu ke ASHP Bina Marga )


(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
Keterangan

10
(Mengacu ke ASHP Bina Marga )
10,670.00 (Mengacu ke ASHP Bina Marga )
9,800.00
10,000.00
7,000.00
8,500.00
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )
(Mengacu ke ASHP Bina Marga )

230,000.00

60,000.00

5,000.00
7,500.00
250,000.00
10,000.00
2,500.00
5,000.00

3,500.00

3,000.00
20,000.00
Keterangan

10
2,500.00
7,000.00
8,500.00
7,000.00
7,000.00
Keterangan

10
DAFTAR ANALISA PEKERJAAN TAMBAHAN
TAHUN 2019

1 1 M2 PEMBUATAN STEGGER DENGAN SCAFHOLDING 120 x 180 h 190 (Sewa)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0170 99,920.00 1,698.64
Tukang Kayu OH 0.0020 99,920.00 199.84
Kepala Tukang OH 0.2500 99,920.00 24,980.00
Mandor OH 0.0130 99,920.00 1,298.96
JUMLAH TENAGA KERJA 28,177.44
B. BAHAN
Kayu Balok Seseh btg 0.0350 - -
Paku 10 kg 0.2000 13,000.00 2,600.00
Main Frame Bh 2.0000 7,500.00 15,000.00
End Frame Bh 2.0000 5,500.00 11,000.00
Cros brace Bh 4.0000 4,500.00 18,000.00
Join Pen Bh 4.0000 1,500.00 6,000.00
U Head Bh 4.0000 4,500.00 18,000.00
Jack Base Bh 4.0000 4,500.00 18,000.00
JUMLAH HARGA BAHAN 88,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 116,777.44
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 116,777.44

2 PEMBESIAN 10 KG DENGAN BESI POLOS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0700 99,920.00 6,994.40
Tukang Besi OH 0.0700 99,920.00 6,994.40
Kepala Tukang OH 0.0070 99,920.00 699.44
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 15,087.92
B. BAHAN
Besi Polos kg 10.5000 8,500.00 89,250.00
Kawat Beton m3 0.1500 13,000.00 1,950.00
JUMLAH HARGA BAHAN 91,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 106,287.92
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 106,287.92
Harga Satuan Pekerjaan untuk 1 Kg 10,628.79
1 PEMBESIAN 10 KG DENGAN BESI ULIR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0700 99,920.00 6,994.40
Tukang Besi OH 0.0700 99,920.00 6,994.40
Kepala Tukang OH 0.0070 99,920.00 699.44
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 15,087.92
B. BAHAN
Besi Ulir kg 10.5000 8,500.00 89,250.00
Kawat Beton m3 0.1500 13,000.00 1,950.00
JUMLAH HARGA BAHAN 91,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 106,287.92
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 106,287.92
Harga Satuan Pekerjaan untuk 1 Kg 10,628.79

8 1 BH PEKERJAAN PASANGAN MURDA/BETALA/IKUT CELEDU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0500 99,920.00 4,996.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 7,494.00
B. BAHAN
Murda / Puntal Paras lbr 1.0000 - -
Semen kg 0.0130 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 7,494.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 7,494.00
XV PEKERJAAN STYLE BALI
1 1 M2 PASANGAN BATA GOSOK 2 MUKA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 99,920.00 99,920.00
JUMLAH TENAGA KERJA 99,920.00
B. BAHAN
Bata Gosok bh 110.0000 - -
Semen 50 Kg kg 8.4000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 99,920.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 99,920.00

1 1 M2 PASANGAN BATA GOSOK 1 MUKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 99,920.00 99,920.00
JUMLAH TENAGA KERJA 99,920.00
B. BAHAN
Bata Gosok bh 55.0000 1,100.00 60,500.00
Semen 50 Kg kg 4.2000 - -
JUMLAH HARGA BAHAN 60,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 160,420.00
E. Overhead & Profit 5 %xD 8,021.00
F. Harga Satuan Pekerjaan (D+E) 168,441.00

2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 99,920.00 99,920.00
JUMLAH TENAGA KERJA 99,920.00
B. BAHAN
Paras Kerobokan bh 13.7500 - -
Semen 50 Kg kg 8.4000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 99,920.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 99,920.00

3 1 M2 PASANGAN BATA PRESS 1 MUKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata Press bh 55.0000 - -
Semen 50 Kg kg 4.2000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -
4 1 M2 PASANGAN PARAS 1 MUKA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu Paras bh 18.3333 - -
Semen 50 Kg kg 4.2000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 5 %xD -
F. Harga Satuan Pekerjaan (D+E) -

5 1 M2 PASANGAN BATU PALIMANAN TEBAL 3 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu Palimanan bh 12.5000 10,833.33 135,416.67
Semen kg 4.2000 - -
JUMLAH HARGA BAHAN 135,416.67
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 135,416.67
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 135,416.67

6 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata Gosok bh 55.0000 - -
Batu Paras bh 4.4917 - -
Semen kg 5.2500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -
7 1 M2 PASANGAN BATA GOSOK DIUKIR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata Gosok bh 55.0000 - -
Semen 50 Kg kg 4.2000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -

8 1 M2 PASANGAN BATU TABAS KARANGASEM DIUKIR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu Tabas bh 18.3333 - -
Semen 50 Kg kg 4.2000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -
9 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata Gosok bh 55.0000 - -
Batu Paras bh 4.4917 - -
Semen 50 Kg kg 5.2500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -

10 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP IJUK


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 30.0000 - -
Semen 40 kg gresik sak 1.0000 - -
kayu cempaka m3 0.9800 - -
ijuk kg 90.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -
11 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP GENTENG
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 26.0000 - -
Semen 40 kg gresik sak 1.0000 - -
kayu cempaka m3 0.7600 - -
genteng plentong bh 90.0000 - -
bubungan mini bh 20.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -

12 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP IJUK


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata gosok ex tulikup bh 150.0000 2,000.00 300,000.00
paras silakarang bh 100.0000 - -
Semen 40 kg gresik sak 1.0000 - -
kayu cempaka m3 0.9800 - -
ijuk kg 98.0000 - -
JUMLAH HARGA BAHAN 300,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 300,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 300,000.00
13 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP GENTENG
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata gosok ex tulikup bh 125.0000 2,000.00 250,000.00
paras silakarang bh 82.0000 - -
kayu cempaka m3 0.7650 - -
Semen 40 kg gresik sak 1.0000 - -
genteng plentong bh 90.0000 - -
bubungan mini bh 20.0000 - -
JUMLAH HARGA BAHAN 250,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 250,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 250,000.00

14 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP IJUK 190cmX190cm


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 65.0000 - -
Semen 40 kg gresik sak 1.2000 - -
kayu cempaka m3 1.8500 - -
ijuk kg 315.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -
15 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP GENTENG 190cmx190cm Err:508
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 65.0000 - -
Semen 40 kg gresik sak 1.2000 - -
kayu cempaka m3 1.4000 - -
genteng plentong bh 110.0000 - -
bubungan mini bh 40.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -

16 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP IJUK 190cmx190cm


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata ex tulikup bh 305.0000 2,000.00 610,000.00
paras silakarang bh 210.0000 - -
Semen 40 kg gresik sak 1.2000 - -
kayu cempaka m3 1.8800 - -
ijuk kg 315.0000 - -
JUMLAH HARGA BAHAN 610,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 610,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 610,000.00
17 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP GENTENG 190cmx190cm
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata ex tulikup bh 305.0000 2,000.00 610,000.00
paras silakarang bh 210.0000 - -
Semen 40 kg gresik sak 1.4300 - -
kayu cempaka m3 1.8800 - -
genteng plentong m3 110.0000 - -
bubungan mini kg 40.0000 - -
JUMLAH HARGA BAHAN 610,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 610,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 610,000.00

18 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP IJUK 200CMX200CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 230.0000 - -
Semen 40 kg gresik sak 4.0000 - -
kayu cempaka m3 3.2400 - -
ijuk kg 470.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -
19 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP GENTENG 200CMX200CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 230.0000 - -
Semen 40 kg gresik sak 4.0000 - -
kayu cempaka m3 3.0000 - -
genteng plentong bh 225.0000 - -
bubungan mini bh 75.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -

20 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP IJUK 200CMX200CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata ex tulikup bh 525.0000 2,000.00 1,050,000.00
paras silakarang bh 350.0000 - -
Semen 40 kg gresik sak 5.5000 - -
kayu cempaka m3 3.2400 - -
ijuk kg 470.0000 - -
JUMLAH HARGA BAHAN 1,050,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,050,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 1,050,000.00

21 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP GENTENG 200CMX200CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata ex tulikup bh 525.0000 2,000.00 1,050,000.00
paras silakarang bh 350.0000 - -
Semen 40 kg gresik sak 5.5000 - -
kayu cempaka m3 3.0000 - -
genteng plentong bh 225.0000 - -
bubungan mini bh 75.0000 - -
JUMLAH HARGA BAHAN 1,050,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,050,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 1,050,000.00
22 1 UNIT SANGGAH TAKSU BATU HITAM ATAP IJUK 40cmx40cm
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 20.0000 - -
Semen 40 kg gresik sak 0.7500 - -
kayu cempaka m3 0.6300 - -
ijuk kg 75.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -

23 1 UNIT SANGGAH TAKSU BATU HITAM ATAP GENTENG 40cmx40cm


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Batu hitam singaraja 20 x 40 bh 21.0000 - -
Semen 40 kg gresik sak 0.7500 - -
kayu cempaka m3 0.6300 - -
genteng plentong bh 75.0000 - -
bubungan mini bh 16.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -
24 1 UNIT SANGGAH TAKSU PARAS BATA ATAP IJUK 40cmx40cm
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata gosok ex tulikup bh 100.0000 2,000.00 200,000.00
paras silakarang bh 75.0000 - -
Semen 40 kg gresik sak 0.8500 - -
kayu cempaka m3 0.6150 - -
ijuk kg 75.0000 - -
JUMLAH HARGA BAHAN 200,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 200,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 200,000.00

25 1 UNIT SANGGAH TAKSU PARAS BATA ATAP GENTENG 40cmx40cm


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata gosok ex tulikup bh 100.0000 2,000.00 200,000.00
paras silakarang bh 75.0000 - -
Semen 40 kg gresik sak 0.8500 - -
kayu cempaka m3 0.6000 - -
genteng plentong bh 70.0000 - -
bubungan mini bh 16.0000 - -
JUMLAH HARGA BAHAN 200,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 200,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 200,000.00

XVI PEKERJAAN HARDDSCAPE


1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
Paving 10 x 20 cm tebal 6 cm K225 m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
2 1 M2 PASANGAN Paving 10 x 20 cm tebal 6 cm K350
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
Paving 10 x 20 cm tebal 6 cm K350 m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

3 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K225


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
Paving 10 x 20 cm tebal 8 cm K225 m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

4 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K350


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
Paving 10 x 20 cm tebal 8 cm K350 m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
5 1 M2 PASANGAN Paving 20 x 20 cm tebal 6 cm K350
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving 20 x 20 cm tebal 6 cm K350 m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

6 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225 m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

7 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K350


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K350 m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
8 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 pc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 pc m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

9 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 merah


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 merah m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

10 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 hitam


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 hitam m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
11 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 pc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 pc m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

12 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 merah


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 merah m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

13 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 hitam


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 merah m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
14 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 pc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 pc m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

15 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 merah


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 merah m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

16 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 hitam


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 hitam m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
17 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 pc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 pc m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

18 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 merah


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 merah m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

19 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 hitam


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 hitam m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
20 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 pc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 pc m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

21 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 merah


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 merah m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

22 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 hitam


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 hitam m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
23 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 pc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 pc m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

24 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 merah


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 merah m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

25 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 hitam


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 hitam m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00
26 1 M2 PASANGAN Paving Tiga Berlian tebal 6 cm K225 pc
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Pekerja OH 0.5000 99,920.00 49,960.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
1 M2 PASANGAN Paving Tiga Berlian tebal 6 cm K225 pc m2 1.0500 - -

JUMLAH HARGA BAHAN -


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 77,438.00

27 1 M2 PASANGAN GRASS BLOCK


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.5000 99,920.00 49,960.00
Kepala Tukang OH 0.0500 99,920.00 4,996.00
Pekerja OH 1.0000 99,920.00 99,920.00
Mandor OH 0.0500 99,920.00 154,876.00
JUMLAH TENAGA KERJA
B. BAHAN
Grass Block m2 1.0000 - -

-
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) -

28 1 M2 PASANGAN KORAL SIKAT


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.2500 99,920.00 24,980.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Pekerja OH 0.6250 99,920.00 62,450.00
Mandor OH 0.0310 99,920.00 3,097.52
JUMLAH TENAGA KERJA 91,526.72
B. BAHAN
Koral Sikat zak 1.2000 - -
Semen zak 9.2800 - -
Pasir pasang m3 0.2000 100,000.00 20,000.00
JUMLAH HARGA BAHAN 20,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 20,000.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 20,000.00
29 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
Kanstein Bulat(P:50,T:30,La:10,Lb:16 cm K225 bh 2.0000 - -
Semen 50 Kg kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70

30 Kanstein Jumbo (P:50,L:15,T:30 cm K225)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
Kanstein Jumbo (P:50,L:15,T:30 cm K225) bh 2.0000 - -
Semen kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70

31 Kanstein kotak (P:50,t.20,La.10,Lb.16cm) K225


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
Kanstein kotak (P:50,t.20,La.10,Lb.16cm) K225 bh 2.0000 - -
Semen kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70
32 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 )
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) bh 2.0000 - -
Semen kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70

33 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 )


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) bh 2.0000 - -
Semen kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70

34 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) bh 2.0000 - -
Semen kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70
35 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) bh 2.0000 - -
Semen kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70

36 1 Buah Pasangan Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA KERJA 131,514.70
B. BAHAN
1 Buah Pasangan Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) bh 2.0000 - -
Semen kg 2.1000 - -
Pasir Urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,114.70

37 1 M2 PENGECATAN KANSTEIN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Cat OH 0.0300 99,920.00 2,997.60
Kepala Tukang OH 0.0030 99,920.00 299.76
Pekerja OH 0.1500 99,920.00 14,988.00
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 19,784.16
B. BAHAN
Cat kg 0.2840 - -
Thiner kg 0.0710 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 19,784.16
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 19,784.16
38 PASANGAN BUIS BETON DIAMETER 80 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0075 99,920.00 749.40
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA KERJA 30,225.80
B BAHAN
Buis Beton Diameter 80 cm BJ 1.0000 - -
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 1,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 31,785.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 31,785.80

39 PASANGAN Buis Beton Diameter 50 x 75


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 99,920.00 7,494.00
Kepala Tukang Batu OH 0.0075 99,920.00 749.40
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA KERJA 30,225.80
B BAHAN
Buis Beton Diameter 50 x 75 BJ 1.0000 - -
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 1,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 31,785.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 31,785.80

40 PASANGAN BUIS BETON DIAMETER 25 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 99,920.00 7,494.00
Kepala Tukang Batu OH 0.0075 99,920.00 749.40
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA KERJA 30,225.80
B BAHAN
Buis Beton Diameter 80 cm BJ 1.0000 - -
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 1,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 31,785.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 31,785.80
41 1 M2 BONGKARAN PAVING LAMA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 10,491.60
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 10,491.60
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 10,491.60

42 1 M3 PENGURUGAN DENGAN LIMESTONE


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500 99,920.00 24,980.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Limestone m3 1.2000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 27,478.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 27,478.00

43 PASANGAN BUIS BETON DIAMETER 100 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0075 99,920.00 749.40
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA K ` 30,225.80
B. BAHAN
Buis Beton Diameter 100 cm Bj 1.0000 120,000.00 120,000.00
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 121,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 151,785.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 151,785.80
1 M' Pasangan Buis Beton Diameter 100 cm = 2 x 285.070,00 303,571.60
44 PASANGAN BUIS BETON DIAMETER 80 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 99,920.00 7,494.00
Kepala Tukang Batu OH 0.0075 99,920.00 749.40
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA K ` 30,225.80
B. BAHAN
Buis Beton Diameter 80 cm BJ 1.0000 - -
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 1,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 31,785.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 31,785.80
1 M' Pasangan Buis Beton Diameter 80 cm = 2 x 130.070,00 63,571.60

45 PASANGAN BUIS BETON DIAMETER 50 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 115,000.00 8,625.00
Kepala Tukang Batu OH 0.0075 120,000.00 900.00
Pekerja OH 0.2000 99,920.00 20,000.00
Mandor OH 0.0200 130,000.00 2,600.00
JUMLAH TENAGA K ` 32,125.00
B. BAHAN
Buis Beton Diameter 50 cm BJ 1.0000 - -
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 1,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,685.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 33,685.00
1 M' Pasangan Buis Beton Diameter 50 cm = 1.33 x 130.070,00 44,801.05

46 PASANGAN BUIS BETON DIAMETER 25 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 115,000.00 8,625.00
Kepala Tukang Batu OH 0.0075 120,000.00 900.00
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 130,000.00 2,600.00
JUMLAH TENAGA K ` 32,109.00
B. BAHAN
Buis Beton Diameter 25 cm BJ 1.0000 - -
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 1,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,669.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 33,669.00
1 M' Pasangan Buis Beton Diameter 25 cm = 1,33 x 130.070,00 44,779.77
1 M' Pasangan 1/2 Buis Beton Diameter 25 cm = 0,5 x 120.070,00 16,834.50
47 1 M' KANSTEIN SEGI LIMA (P:50:15,T:20)K-225
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA K ` 131,514.70
B. BAHAN
Kanstein Segi Lima (P:50, L:15, T:20 cm K-225) BJ 2.0000 - -
Semen kg 2.1000 - -
Pasir urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 132,114.70

48 1 M' KANSTEIN KURSI K-225


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.3500 99,920.00 34,972.00
Pekerja OH 0.9500 99,920.00 94,924.00
Mandor OH 0.0162 99,920.00 1,618.70
JUMLAH TENAGA K ` 131,514.70
B. BAHAN
Kanstein Kursi K-225 BJ 2.0000 - -
Semen kg 2.1000 - -
Pasir urug m3 0.0060 100,000.00 600.00
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,114.70
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 132,114.70
49 1 M3 PASANGAN PONDASI SIKLOP, 60% BETON CAMPURAN 1 SP : 2 PB : 3 KR DAN 40% BATU BELAH
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 3.400 99,920.00 339,728.00
Tukang Batu OH 0.850 99,920.00 84,932.00
Kepala Tukang OH 0.085 99,920.00 8,493.20
Mandor OH 0.170 99,920.00 16,986.40
JUMLAH TENAGA KERJA 450,139.60
B. BAHAN
Batu Belah m3 0.480 141,176.47 67,764.71
Semen portland (Gersik) kg 194.000 - -
Pasir Beton m3 0.312 120,000.00 37,440.00
Koral Beton m3 0.468 - -
JUMLAH HARGA BAHAN 105,204.71
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 555,344.31
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 555,344.31
TIME SCHEDULE & BAR CHART
Kegiatan : Penataan Bangunan dan Pengembangan Kawasan Permukiman 7/23/2020
Pekerjaan : Pembangunan Wantilan dan Penataan Halaman Pura Ponjok Batu 119
Lokasi : Desa Penuktukan, Kec. Tejakula Kab. Buleleng 11/19/2020

JANGKA WAKTU PELAKSANAAN 120 HARI KALENDER


NO Jenis Barang/Jasa Satuan Volume BOBOT % BULAN 1 BULAN 2 BULAN 3 BULAN 4 BULAN 5
Unit
Mg1 Mg2 Mg3 Mg4 Mg5 Mg6 Mg7 Mg8 Mg9 Mg10 Mg11 Mg12 Mg13 Mg14 Mg15 Mg16 Mg17 Mg18
a b c d 7/23/2020 7/30/2020 8/6/2020 8/13/2020 8/20/2020 8/27/2020 9/3/2020 9/10/2020 9/17/2020 9/24/2020 10/1/2020 10/8/2020 10/15/2020 10/22/2020 10/29/2020 11/5/2020 11/12/2020 11/19/2020
7/29/2020 8/5/2020 8/12/2020 8/19/2020 8/26/2020 9/2/2020 9/9/2020 9/16/2020 9/23/2020 9/30/2020 10/7/2020 10/14/2020 10/21/2020 10/28/2020 11/4/2020 11/11/2020 11/18/2020
I PEKERJAAN PERSIAPAN
1 Pek. Pasang Papan Nama Proyek ls 1.00 0.008 0.008
2 Pek. Pengukuran dan Pemasangan Bowplank m1 78.00 0.359 0.180 0.180
3 Pek. Perlengkapan Smkk (Sistem Manajemen Keselamatan Kontruksi) -
Sosialisasi dan Promosi K3 -
Spanduk K3 Bh 1.00 0.007 0.003 0.003
Rambu - Rambu K3 -
Rambu - Rambu Bh 1.00 0.008 0.004 0.004
Fasilitas Sarana Kesehatan -
Kotak P3K Set 1.00 0.017 0.008 0.008
Kelengkapan Pekerja -
Helm proyek Bh 10.00 0.042 0.021 0.021
Rompi proyek Bh 10.00 0.021 0.011 0.011
Masker Bh 10.00 0.006 0.003 0.003
Sepatu proyek Pasang 10.00 0.076 0.038 0.038
Sarung tangan proyek Pasang 10.00 0.008 0.004 0.004
II PEKERJAAN STRUKTUR -
PEKERJAAN TANAH DAN PASIR -
1 Pek. Galian Tanah Pondasi Telapak m3 164.25 1.318 0.439 0.439 0.439
2 Pek. Galian Tanah Pondasi Menerus m3 53.88 0.354 0.177 0.177
3 Pek. Urugan Pasir Bawah Pondasi Telapak t=50 mm m3 4.11 0.053 0.026 0.026
4 Pek. Urugan Pasir Bawah Pondasi Menerus t=50 mm m3 0.69 0.009 0.004 0.004
5 Pek. Urugan Tanah Kembali m3 72.71 0.339 0.170 0.170
6 Pek. Urugan Tanah Peninggian Lantai + Dipadatkan m3 103.68 1.356 0.339 0.339 0.339 0.339
7 Pek. Urugan Pasir Bawah Lantai t=50 mm m3 16.20 0.208 0.208
8 Pek. Pembuangan Sisa Galian Sejauh 30 m m3 1,435.00 4.751 0.528 0.528 0.528 0.528 0.528 0.528 0.528 0.528 0.528
III PEKERJAAN PONDASI -
1 Pek. Pasangan Pondasi Batu Kosong m3 2.07 0.059 0.020 0.020 0.020
2 Pek. Pasangan Pondasi Batu Belah 1 PC5 PP m3 45.46 2.397 0.599 0.599 0.599 0.599
IV PEKERJAAN BETON -
Lantai 1 -
1 Pek. Beton Rabat Bawah Pondasi Telapak t=50 mm m3 3.81 0.188 0.094 0.094
2 Pek. Beton Rabat Bawah Lantai t=50 mm m3 16.20 0.801 0.400 0.400
3 Pek. Pondasi Telapak P1 1750 x 1500 mm -
Beton K250 m3 24.15 1.613 0.807 0.807
Pembesian Pondasi kg 3,600.53 3.251 1.625 1.625
Bekisting Batako m2 64.40 0.710 0.355 0.355
4 Pek. Pondasi Telapak P2 1200 x 1200 mm -
Beton K250 m3 1.30 0.087 0.043 0.043
Pembesian Pondasi kg 266.23 0.240 0.120 0.120
Bekisting Pondasi m2 4.32 0.061 0.031 0.031
5 Pek. Kolom Pedestal C1 400 x 400 mm -
Beton K250 m3 3.12 0.208 0.069 0.069 0.069
Pembesian Kolom kg 814.76 0.736 0.245 0.245 0.245
Bekisting Kolom Pedestal m2 31.20 0.777 0.259 0.259 0.259
6 Pek. Kolom Pedestal C1A 400 x 400 mm -
Beton K250 m3 2.40 0.160 0.053 0.053 0.053
Pembesian Kolom kg 1,158.27 1.046 0.349 0.349 0.349
Bekisting Kolom Pedestal m2 24.00 0.598 0.199 0.199 0.199
7 Pek. Kolom Pedestal C2 250 x 250 mm -
Beton K250 m3 0.28 0.019 0.006 0.006 0.006
Pembesian Kolom kg 122.08 0.110 0.037 0.037 0.037
Bekisting Kolom Pedestal m2 4.50 0.112 0.037 0.037 0.037
8 Pek. Sloof-1 200 x 400 mm -
Beton K250 m3 3.60 0.241 0.080 0.080 0.080
Pembesian Sloof kg 1,058.98 0.956 0.319 0.319 0.319
Bekisting Sloof m2 48.00 0.723 0.241 0.241 0.241
9 Pek. Sloof-2 200 x 350 mm -
Beton K250 m3 5.05 0.337 0.112 0.112 0.112
Pembesian Sloof kg 1,506.54 1.360 0.453 0.453 0.453
Bekisting Sloof m2 70.70 1.064 0.355 0.355 0.355
10 Pek. Lantai Bawah t= 100 mm -
Beton K250 m3 34.31 2.292 2.292
Pembesian Lantai Wiremesh M6 1 lapis kg 1,106.12 1.768 0.884 0.884
11 Pek. Kolom C1 400 x 400 mm -
Beton K250 m3 5.99 0.400 0.133 0.133 0.133
Pembesian Kolom kg 1,193.90 1.078 0.359 0.359 0.359
Bekisting Kolom m2 70.30 1.752 0.584 0.584 0.584
12 Pek. Kolom C1A 400 x 400 mm -
Beton K250 m3 4.61 0.308 0.103 0.103 0.103
Pembesian Kolom kg 1,502.21 1.356 0.452 0.452 0.452
Bekisting Kolom m2 54.08 1.348 0.449 0.449 0.449
13 Pek. Kolom C2 250 x 250 mm -
Beton K250 m3 0.54 0.036 0.012 0.012 0.012
Pembesian Kolom kg 222.91 0.201 0.067 0.067 0.067
Bekisting Kolom m2 10.14 0.253 0.084 0.084 0.084
14 Pek. Tangga -
Beton K250 m3 2.86 0.191 0.096 0.096
Pembesian Tangga kg 285.12 0.257 0.086 0.086 0.086
Bekisting Tangga m2 16.58 0.385 0.128 0.128 0.128
15 Pek. Beton Kolom Praktis m1 10.14 0.076 0.038 0.038
Pek. Meja Beton m3 0.45 0.030 0.015 0.015
Pembesian Meja kg 33.41 0.030 0.015 0.015
Bekisting Meja m2 3.75 0.100 0.050 0.050
Lantai 2 -
1 Pek. Balok Induk BI-1 300 x 500 mm -
Beton K250 m3 5.86 0.391 0.196 0.196
Pembesian Balok kg 2,432.63 2.196 0.732 0.732 0.732
Bekisting Balok m2 58.59 1.520 0.507 0.507 0.507
2 Pek. Balok Induk BI-2 300 x 500 mm -
Beton K250 m3 8.28 0.553 0.277 0.277
Pembesian Balok kg 1,123.98 1.015 0.338 0.338 0.338
Bekisting Balok m2 43.57 1.130 0.377 0.377 0.377
3 Pek. Balok Induk BI-3 250 x 450 mm -
Beton K250 m3 5.45 0.364 0.182 0.182
Pembesian Balok kg 1,142.73 1.032 0.344 0.344 0.344
Bekisting Balok m2 11.83 0.307 0.102 0.102 0.102
4 Pek. Balok Induk BI-4 200 x 350 mm -
Beton K250 m3 1.19 0.080 0.040 0.040
Pembesian Balok kg 291.50 0.263 0.088 0.088 0.088
Bekisting Balok m2 11.70 0.303 0.101 0.101 0.101
5 Pek. Balok Anak BA-1 250 x 350 mm -
Beton K250 m3 2.84 0.190 0.095 0.095
Pembesian Balok kg 960.19 0.867 0.289 0.289 0.289
Bekisting Balok m2 35.07 0.910 0.303 0.303 0.303
6 Pek. Beton Pelat Lantai 2 t=120 mm -
Beton K250 m3 26.67 1.782 0.891 0.891
Pembesian Pelat kg 5,247.77 4.738 1.579 1.579 1.579
Bekisting Pelat m2 188.21 5.009 1.670 1.670 1.670
V PEKERJAAN ARSITEKTUR -
PEKERJAAN DINDING -
Lantai 1 -
1 Pek. Pasangan Dinding Bata Merah 1PC 6PP m2 57.03 0.651 0.325 0.325
2 Pek. Plesteran Dinding 1PC 6PP t=15 mm m2 56.40 0.268 0.134 0.134
3 Pek. Acian Dinding m2 65.56 0.198 0.099 0.099
4 Pek. Acian Beton m2 446.33 1.345 0.448 0.448 0.448
Lantai 2 -
1 Pek. Pasangan Dinding Bata Merah 1PC 6PP m2 23.03 0.263 0.131 0.131
PEKERJAAN KUSEN, PINTU, DAN JENDELA -
Lantai 1 -
1 Pek. Pintu P1 -
Kusen Kayu Profil 55 x 110 mm Kamper m1 0.03 0.023 0.023
Daun Pintu Panel Kayu Kamper m2 1.36 0.083 0.083
Engsel Pintu Solid ps 1.00 0.005 0.005
Kunci Tanam Biasa Solid bh 1.00 0.016 0.016
Handle Pintu Solid unit 1.00 0.024 0.024
Kunci Slot bh 1.00 0.005 0.005
2 Pek. Jendela J1 -
Kusen Kayu Profil 55 x 110 mm Kamper m1 0.06 0.046 0.046
Daun Jendela Kayu Kamper m2 0.59 0.045 0.045
Kaca Bening 5 mm m2 1.23 0.030 0.030
Engsel Jendela Solid ps 2.00 0.010 0.010
Grendel Jendela Solid bh 2.00 0.011 0.011
Kait Angin Solid bh 4.00 0.020 0.020
VI PEKERJAAN PENUTUP LANTAI DAN DINDING -
Lantai 1 -
1 Pek. Lantai Granit 600 x 600 mm (Polished) m2 296.47 3.722 0.930 0.930 0.930 0.930
2 Pek. Border Batu Candi 250 x 300 mm m2 9.43 0.488 0.122 0.122 0.122 0.122
3 Pek. Lantai Batu Candi 300 x 300 mm m2 4.45 0.230 0.058 0.058 0.058 0.058
VII PEKERJAAN FINISHING -
Lantai 1 -
1 Pek. Pengecatan Dinding Vinilex m2 511.89 0.990 0.330 0.330 0.330
2 Pek. Polituran Kayu Profil m2 7.08 0.040 0.013 0.013 0.013
3 Pek. Handraill Tangga Hollow Galvanis 2 + Fin. Cat ls 1.00 0.340 0.113 0.113 0.113
VIII PEKERJAAN STYLE BALI -
Lantai 1 -
1 Pek. Tempelan Kolom dengan Batu Tabas Karangasem m2 70.99 4.306 1.435 1.435 1.435
2 Pek. Pengresek m3 3.55 0.277 0.092 0.092 0.092
IX PEKERJAAN ELEKTRIKAL DAN PLUMBING -
PEKERJAAN INSTALASI LISTRIK -
Lantai 1 -
1 Pek. Instalasi Titik Lampu titik 7.00 0.095 0.095
2 Pek. Instalasi Stop Kontak titik 1.00 0.015 0.015
3 Pek. Lampu LED 11 WATT+Fitting bh 6.00 0.043 0.043
4 Pek. Saklar Tunggal bh 2.00 0.013 0.013
5 Pek. Stop Kontak bh 1.00 0.007 0.007
6 Pek. Box MCB (lengkap) set 1.00 0.059 0.059
PEKERJAAN PLUMBING DAN SANITAIR -
Lantai 1 -
1 Pek. Washtafel Komplit bh 1.00 0.054 0.054
2 Pek. Kran Washtafel bh 1.00 0.014 0.014
3 Pek Bak Cuci Piring bh 1.00 0.019 0.019
4 Pek. Pipa Air Bersih PVC AW 1/2 m1 10.00 0.019 0.010 0.010
5 Pek. Pipa Air Bersih PVC AW 3/4 m1 10.00 0.022 0.011 0.011
6 Pek. Pipa Air Bersih PVC AW 1 m1 10.00 0.029 0.015 0.015
7 Pek. Pipa Air Kotor PVC AW 3 m1 15.00 0.069 0.035 0.035
X PEKERJAAN SENDERAN -
1 Pek. Galian Tanah Pematangan Lahan 1,45 m m3 496.21 4.296 0.430 0.430 0.430 0.430 0.430 0.430 0.430 0.430 0.430 0.430
2 Pek. Galian Tanah Pematangan Lahan 3,45 m m3 863.25 8.735 0.873 0.873 0.873 0.873 0.873 0.873 0.873 0.873 0.873 0.873
3 Pek. Pasangan Batu Belah 1 PC5 PP pada DPT m3 68.95 3.636 0.727 0.727 0.727 0.727 0.727
4 Pek. Plesteran 1PC 6PP t=15 mm m2 176.74 0.840 0.420 0.420
XI PEKERJAAN PEMATANGAN SITE -
PEKERJAAN PELEBARAN TANGGA -
1 Pek. Pasangan Batako 15 m2 73.12 0.806 0.806
2 Pek. Urugan Tanah pada Anak Tangga m3 3.60 0.043 0.043
3 Pek. Plesteran Anak Tangga 1PC 6PP m3 137.24 0.652 0.652
PEKERJAAN PLAT BETON -
1 Pek. Galian Batu Eksisting m3 0.77 0.092 0.046 0.046
2 Pek. Pasang Buis Beton 30 x 100 cm bh 12.00 0.155 0.077 0.077
3 Beton K250 m3 0.85 0.057 0.019 0.019 0.019
4 Pembesian kg 33.42 0.030 0.010 0.010 0.010
5 Pek. Pasangan Batu Belah 1 PC5 PP m3 1.30 0.069 0.023 0.023 0.023
6 Pek. Balok 200 x 300 mm -
Beton K250 m3 1.63 0.109 0.054 0.054
Pembesian Balok kg 177.20 0.160 0.053 0.053 0.053
Bekisting Balok m2 8.14 0.211 0.070 0.070 0.070
7 Pek. Beton Pelat Lantai t=150 mm -
Beton K250 m3 6.55 0.438 0.146 0.146 0.146
Penulangan Wiremesh M7 (2 Lapis) kg 364.68 0.875 0.292 0.292 0.292
Bekisting Plat m2 35.38 0.942 0.314 0.314 0.314
Pek. Pasangan Batu Pilah Karangasem m2 43.71 2.651 0.530 0.530 0.530 0.530 0.530
JUMLAH NILAI PEKERJAAN % 100.000
JUMLAH KEMAJUAN PEKERJAAN % 0.008 0.093 0.093 0.180 0.619 5.645 6.682 8.019 8.300 9.842 12.756 12.280 11.588 8.692 7.012 5.660 2.074 0.457
JUMLAH KEMAJUAN PEKERJAAN KOMULATIF % 0.008 0.102 0.195 0.374 0.993 6.638 13.320 21.338 29.638 39.480 52.236 64.517 76.105 84.797 91.809 97.470 99.543 100.000
DAFTAR ANALISA PEKERJAAN
TAHUN 2020

I HARGA SATUAN PEKERJAAN PERSIAPAN (PERMEN PUPR 28/PRT/M/2016)

1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang kayu OH 0.100 99,920.00 9,992.00
Kepala tukang OH 0.010 99,920.00 999.20
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 21,482.80
B. BAHAN
Kayu balok 5/7 m3 0.012 2,000,000.00 24,000.00
Paku 2" - 3" Kg 0.020 15,000.00 300.00
Kayu Papan 3/20 m3 0.007 1,200,000.00 8,400.00
JUMLAH HARGA BAHAN 32,700.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,182.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 54,182.80

II HARGA SATUAN PEKERJAAN TANAH (PERMEN PUPR 28/PRT/M/2016)

1 1 M3 GALIAN TANAH BIASA DALAM 1 METER


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.750 99,920.00 74,940.00
Mandor OH 0.025 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 77,438.00

2 1 M3 GALIAN TANAH BIASA DALAM 2 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.900 99,920.00 89,928.00
Mandor OH 0.045 99,920.00 4,496.40
JUMLAH TENAGA KERJA 94,424.40
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 94,424.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 94,424.40
3 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.050 99,920.00 4,996.00
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 5,495.60
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 5,495.60
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 5,495.60

4 1 M3 PEMBUANGAN TANAH SEJAUH 30 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.330 99,920.00 32,973.60
Mandor OH 0.010 99,920.00 999.20
JUMLAH TENAGA KERJA 33,972.80
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN 5,000.00 5,000.00
JUMLAH HARGA ALAT 5,000.00

D. Jumlah (A + B + C) 38,972.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 38,972.80

5 1 M3 PENGURUGAN KEMBALI GALIAN TANAH


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500 99,920.00 49,960.00
Mandor OH 0.050 99,920.00 4,996.00
JUMLAH TENAGA KERJA 54,956.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,956.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 54,956.00
6 1 M3 PEMADATAN TANAH ( Per 20 Cm )
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500 99,920.00 49,960.00
Mandor OH 0.050 99,920.00 4,996.00
JUMLAH TENAGA KERJA 54,956.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,956.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 54,956.00

7 1 M3 URUGAN PASIR
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Mandor OH 0.010 99,920.00 999.20
JUMLAH TENAGA KERJA 30,975.20
B. BAHAN
Pasur Urug m3 1.200 100,000.00 120,000.00
JUMLAH HARGA BAHAN 120,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 150,975.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 150,975.20

8 1 m3 Urugan Tanah Peninggian Lantai + Dipadatkan


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Mandor OH 0.010 99,920.00 999.20
JUMLAH TENAGA KERJA 30,975.20
B. BAHAN
Tanah Urug m3 1.200 90,000.00 108,000.00
JUMLAH HARGA BAHAN 108,000.00
C. PERALATAN 15,000.00 15,000.00
JUMLAH HARGA ALAT 15,000.00

D. Jumlah (A + B + C) 153,975.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 153,975.20
9 1 m3 Urugan Tanah
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Mandor OH 0.010 99,920.00 999.20
JUMLAH TENAGA KERJA 30,975.20
B. BAHAN
Bata Pres 22x10x5cm m3 1.200 90,000.00 108,000.00
JUMLAH HARGA BAHAN 108,000.00
C. PERALATAN -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 138,975.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 138,975.20

III HARGA SATUAN PEKERJAAN PONDASI (PERMEN PUPR 28/PRT/M/2016)

1 1 M3 PASANGAN BATU KOSONG


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.780 99,920.00 77,937.60
Tukang Batu OH 0.390 99,920.00 38,968.80
Kepala Tukang OH 0.039 99,920.00 3,896.88
Mandor OH 0.039 99,920.00 3,896.88
JUMLAH TENAGA KERJA 124,700.16
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Pasir Urug m3 0.432 100,000.00 43,200.00
JUMLAH HARGA BAHAN 212,611.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 337,311.92
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 337,311.92

2 1 M3 BATU BELAH CAMP. 1 SP : 5 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland kg 136.000 1,075.00 146,200.00
Pasir Pasang m3 0.544 120,000.00 65,280.00
JUMLAH HARGA BAHAN 380,891.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 620,699.76
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 620,699.76
III PEKERJAAN BETON ( PERMEN PUPR 28/PRT/M/2016))

1 MEMBUAT 1 M³ LANTAI KERJA BETON MUTU F'C = 7,4 MPA SLUMP (3-6)CM, W/C =0.87
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.200 99,920.00 119,904.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.060 99,920.00 5,995.20
JUMLAH TENAGA KERJA 147,881.60
B. BAHAN
Semen portland kg 230.0000 1,075.00 247,250.00
Pasir Beton kg 893 88.89 79,377.78
Koral Beton kg 1,027 103.57 106,367.86
Air lt 200 5.00 1,000.00
JUMLAH HARGA BAHAN 433,995.63
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 581,877.23
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 581,877.23

1 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland kg 326.0000 1,075.00 350,450.00
Pasir Beton kg 760 88.89 67,555.56
Koral Beton kg 1,029 103.57 106,575.00
Air liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 525,655.56
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 729,092.68
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 729,092.68

2 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen portland kg 384.000 1,075.00 412,800.00
Pasir Beton kg 692 88.89 61,511.11
Koral Beton kg 1,039 103.57 107,610.71
Air liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 582,996.83
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 786,433.95
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 786,433.95
3 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.070 99,920.00 6,994.40
Tukang Besi OH 0.070 99,920.00 6,994.40
Kepala Tukang OH 0.007 99,920.00 699.44
Mandor OH 0.004 99,920.00 399.68
JUMLAH TENAGA KERJA 15,087.92
B. BAHAN
Besi Beton (Polos/ Ulir) kg 10.500 8,500.00 89,250.00
Kawat Beton kg 0.150 13,000.00 1,950.00
JUMLAH HARGA BAHAN 91,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 106,287.92
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 106,287.92
Harga Satuan Pekerjaan untuk 1 Kg 10,628.79

4 1 M2 PASANG BEKISTING UNTUK PONDASI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.520 99,920.00 51,958.40
Tukang Kayu OH 0.260 99,920.00 25,979.20
Kepala Tukang OH 0.026 99,920.00 2,597.92
Mandor OH 0.026 99,920.00 2,597.92
JUMLAH TENAGA KERJA 83,133.44
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5 - 10 cm kg 0.300 13,000.00 3,900.00
Minyak Bekisting ltr 0.100 2,000.00 200.00
JUMLAH HARGA BAHAN 84,100.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 167,233.44
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 167,233.44
5 1 M2 PASANG BEKISTING UNTUK KOLOM
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660 99,920.00 65,947.20
Tukang Kayu OH 0.330 99,920.00 32,973.60
Kepala Tukang OH 0.033 99,920.00 3,297.36
Mandor OH 0.033 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5cm - 12cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.200 2,000.00 400.00
Balok kayu kelas II m3 0.015 4,000,000.00 60,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu 8 - 10 cm /4 m Batang 2.000 5,000.00 10,000.00
JUMLAH HARGA BAHAN 187,800.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 293,315.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 293,315.52

6 1 M2 PASANG BEKISTING UNTUK SLOOF


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.5200 99,920.00 51,958.40
Tukang Kayu OH 0.2600 99,920.00 25,979.20
Kepala Tukang OH 0.0260 99,920.00 2,597.92
Mandor OH 0.0260 99,920.00 2,597.92
JUMLAH TENAGA KERJA 83,133.44
B. BAHAN
Kayu Kelas III m3 0.045 2,000,000.00 90,000.00
Paku Biasa 5cm - 10cm kg 0.300 13,000.00 3,900.00
Minyak Bekisting ltr 0.100 2,000.00 200.00
JUMLAH HARGA BAHAN 94,100.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 177,233.44
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 177,233.44

7 Pemasangan 10 Kg jaring kawat baja (wiremesh) M6


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.025 99,920.00 2,498.00
Tukang Besi OH 0.025 99,920.00 2,498.00
Kepala Tukang OH 0.025 99,920.00 2,498.00
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 7,593.92
B. BAHAN
Jaring kawat baja dilas M6 kg 10.200 17,636.68 179,894.18
Kawat Beton kg 0.0500 13,000.00 650.00
JUMLAH HARGA BAHAN 180,544.18
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 188,138.10
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 188,138.10
Harga Satuan Pekerjaan untuk 1 Kg 18,813.81
1 Pemasangan 10 Kg jaring kawat baja (wiremesh) M7
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.025 99,920.00 2,498.00
Tukang Besi OH 0.025 99,920.00 2,498.00
Kepala Tukang OH 0.025 99,920.00 2,498.00
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 7,593.92
B. BAHAN
Jaring kawat baja dilas M7 kg 10.200 26,895.94 274,338.62
Kawat Beton kg 0.0500 13,000.00 650.00
JUMLAH HARGA BAHAN 274,988.62
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 282,582.54
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 282,582.54
Harga Satuan Pekerjaan untuk 1 Kg 28,258.25

8 1 M2 PASANG BEKISTING UNTUK TANGGA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6600 99,920.00 65,947.20
Tukang Kayu OH 0.3300 99,920.00 32,973.60
Kepala Tukang OH 0.0330 99,920.00 3,297.36
Mandor OH 0.0330 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.030 2,000,000.00 60,000.00
Paku Biasa 5cm - 12 cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.150 2,000.00 300.00
Balok kayu kelas II m3 0.015 4,000,000.00 60,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu Ø (8 - 10)cm /4 m btg 2.000 5,000.00 10,000.00
JUMLAH HARGA BAHAN 167,700.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 273,215.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 273,215.52
9 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.297 99,920.00 29,676.24
Tukang Batu OH 0.033 99,920.00 3,297.36
Tukang Kayu OH 0.033 99,920.00 3,297.36
Tukang Besi OH 0.033 99,920.00 3,297.36
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,066.32
B. BAHAN
Kayu Kelas III m3 0.003 2,000,000.00 6,000.00
Paku Biasa 5 cm - 12 cm kg 0.020 13,000.00 260.00
Minyak bekisting Liter 0.030 2,000.00 60.00
Besi Beton Polos kg 3.600 8,500.00 30,600.00
Kawat Beton kg 0.050 13,000.00 650.00
Semen kg 5.500 1,075.00 5,912.50
Pasir Beton m3 0.009 120,000.00 1,080.00
Koral Beton m3 0.015 145,000.00 2,175.00
JUMLAH HARGA BAHAN 46,737.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 88,803.82
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 88,803.82

10 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660 99,920.00 65,947.20
Tukang Kayu OH 0.330 99,920.00 32,973.60
Kepala Tukang OH 0.033 99,920.00 3,297.36
Mandor OH 0.033 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5cm - 12cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.200 2,000.00 400.00
Balok kayu kelas II m3 0.015 4,000,000.00 60,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu Ø( 8 - 10) cm /4 m btg 6.000 5,000.00 30,000.00
JUMLAH HARGA BAHAN 207,800.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 313,315.52
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 313,315.52
11 1 M2 PASANG BEKISTING UNTUK BALOK
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660 99,920.00 65,947.20
Tukang Kayu OH 0.330 99,920.00 32,973.60
Kepala Tukang OH 0.033 99,920.00 3,297.36
Mandor OH 0.033 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5 cm - 12 cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.200 2,000.00 400.00
Balok kayu kelas II m3 0.018 4,000,000.00 72,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu Ø (8 - 10)cm /4 m btg 2.000 5,000.00 10,000.00
JUMLAH HARGA BAHAN 199,800.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 305,315.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 305,315.52

IV PEKERJAAN DINDING (PERMEN PUPR 28/PRT/M/2016))

1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen Portland kg 8.320 1,075.00 8,944.00
Pasir Pasang m3 0.049 120,000.00 5,880.00
JUMLAH HARGA BAHAN 91,824.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 134,290.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 134,290.00

2 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 4 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
HB-15 bh 12.5000 2,000.00 25,000.00
Semen Portland Kg 15.160 1,075.00 16,297.00
Pasir Pasang m3 0.364 120,000.00 43,680.00
Besi Beton 8 mm kg 0.280 8,500.00 2,380.00
JUMLAH HARGA BAHAN 87,357.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 129,823.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 129,823.00
V PEKERJAAN PLESTERAN (PERMEN PUPR 28/PRT/M/2016)

1 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland kg 4.416 1,075.00 4,747.20
Pasir Pasang m3 0.027 120,000.00 3,240.00
JUMLAH HARGA BAHAN 7,987.20
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 55,948.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 55,948.80

2 1 M2 PEKERJAAN ACIAN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.200 99,920.00 19,984.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.01 99,920.00 999.20
Mandor OH 0.01 99,920.00 999.20
JUMLAH TENAGA KERJA 31,974.40
B. BAHAN
Semen Portland kg 3.25 1,075.00 3,493.75
JUMLAH HARGA BAHAN 3,493.75
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 35,468.15
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 35,468.15

VI PEKERJAAN KAYU (PERMEN PUPR 28/PRT/M/2016)

1 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000 99,920.00 99,920.00
Tukang kayu OH 3.0000 99,920.00 299,760.00
Kepala Tukang OH 0.3000 99,920.00 29,976.00
Mandor OH 0.0500 99,920.00 4,996.00
JUMLAH TENAGA KERJA 434,652.00
B. BAHAN
Papan Kayu Kamper m3 0.0400 7,000,000.00 280,000.00
Lem Kayu Kg 0.5000 12,000.00 6,000.00
JUMLAH HARGA BAHAN 286,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 720,652.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 720,652.00
2 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000 99,920.00 99,920.00
Tukang kayu OH 3.0000 99,920.00 299,760.00
Kepala Tukang OH 0.3000 99,920.00 29,976.00
Mandor OH 0.0500 99,920.00 4,996.00
JUMLAH TENAGA KERJA 434,652.00
B. BAHAN
Papan Kayu Kamper m3 0.0640 7,000,000.00 448,000.00
Lem Kayu Kg 0.5000 12,000.00 6,000.00
JUMLAH HARGA BAHAN 454,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 888,652.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 888,652.00

VII PEKERJAAN KUNCI DAN KACA PERMEN PUPR 28/PRT/M/2016)

1 1 PS PASANG ENGSEL PINTU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1250 99,920.00 12,490.00
Kepala Tukang OH 0.0130 99,920.00 1,298.96
Mandor OH
JUMLAH TENAGA KERJA 13,788.96
B. BAHAN
Engsel Pintu ps 1.0000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 58,788.96
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 58,788.96

2 1 BH PASANG KUNCI TANAM BIASA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.5000 99,920.00 49,960.00
Kepala Tukang OH 0.0500 99,920.00 4,996.00
Mandor OH
JUMLAH TENAGA KERJA 54,956.00
B. BAHAN
Kunci Tanam Biasa bh 1.0000 130,000.00 130,000.00
JUMLAH HARGA BAHAN 130,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 184,956.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 184,956.00
3 1 BH PASANG KUNCI SLOT PINTU
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.2500 99,920.00 24,980.00
Kepala Tukang OH 0.0250 99,920.00 2,498.00
Mandor OH
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Kunci Slot Pintu bh 1.0000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 62,478.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 62,478.00

4 1 M2 PASANG KACA, TEBAL5 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1600 99,920.00 15,987.20
Tukang Besi OH 0.1600 99,920.00 15,987.20
Kepala Tukang OH 0.1600 99,920.00 15,987.20
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 48,760.96
B. BAHAN
Kaca bh 1.1000 220,000.00 242,000.00
JUMLAH HARGA BAHAN 242,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 290,760.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 290,760.96

5 1 PS PASANG ENGSEL JENDELA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH
JUMLAH TENAGA KERJA 10,991.20
B. BAHAN
Engsel Jendela ps 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 60,991.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 60,991.20
6 1 BH PASANG GRENDEL JENDELA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.2500 99,920.00 24,980.00
Kepala Tukang OH 0.0250 99,920.00 2,498.00
Mandor OH
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Grendel Jendela bh 1.0000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 62,478.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 62,478.00

7 1 BH PASANG KAIT ANGIN


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0010 99,920.00 99.92
Mandor OH
JUMLAH TENAGA KERJA 10,091.92
B. BAHAN
Kait Angin ps 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 60,091.92
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 60,091.92

VIII PEKERJAAN PENUTUP LANTAI DAN DINDING (PERMEN PUPR 28/PRT/M/2016)

1 1 M2 PASANG LANTAI GRANIT 60 X 60 (Polished)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.24 99,920.00 23,980.80
Tukang batu OH 0.12 99,920.00 11,990.40
Kepala Tukang batu OH 0.01 99,920.00 1,199.04
Mandor OH 0.01 99,920.00 1,199.04
JUMLAH TENAGA KERJA 38,369.28
B. BAHAN
Granit 60 cm x 60 cm Bh 3.10 22,800.00 70,680.00
Semen Portland Kg 9.60 1,075.00 10,320.00
Pasir Pasang M3 0.05 120,000.00 5,400.00
Semen warna/semen grouting Kg 1.50 2,000.00 3,000.00
JUMLAH HARGA BAHAN 89,400.00
C. PERALATAN
JUMLAH HARGA ALAT
1 20,000.00 20,000.00

D. Jumlah (A + B + C) 147,769.28
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 147,769.28
13 1 M2 Pekerjaan Style Bali Batu hitam Karangasem / Batu Tabas
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.0000 99,920.00 199,840.00
Tukang Style Bali OH 2.0000 99,920.00 199,840.00
Kepala Tukang style bali OH 0.4000 99,920.00 39,968.00
Mandor OH 0.1000 99,920.00 9,992.00
JUMLAH TENAGA KERJA 449,640.00
B. BAHAN
Batu hitam karangasem m2 1.1000 225,000.00 247,500.00
Semen Portland kg 11.7500 1,075.00 12,631.25
Pasir Pasang m3 0.0350 120,000.00 4,200.00
JUMLAH HARGA BAHAN 264,331.25
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 713,971.25
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 713,971.25

13 1 M2 PASANG DINDING BATU PARAS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.0000 99,920.00 199,840.00
Tukang batu OH 2.0000 99,920.00 199,840.00
Kepala Tukang OH 0.4000 99,920.00 39,968.00
Mandor OH 0.1000 99,920.00 9,992.00
JUMLAH TENAGA KERJA 449,640.00
B. BAHAN
Batu Candi Hitam m2 1.1000 130,000.00 143,000.00
Semen Portland kg 11.7500 1,075.00 12,631.25
Pasir Pasang m3 0.0350 120,000.00 4,200.00
JUMLAH HARGA BAHAN 159,831.25
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 609,471.25
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 609,471.25
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 6.0000 99,920.00 599,520.00
Tukang batu OH 1.0000 99,920.00 99,920.00
Kepala Tukang OH 0.1000 99,920.00 9,992.00
Mandor OH 0.3000 99,920.00 29,976.00
JUMLAH TENAGA KERJA 739,408.00
B. BAHAN
Batu Pecah m3 0.4000 141,176.47 56,470.59
Kerikil m3 0.2328 145,000.00 33,756.00
Pasir beton m3 0.1308 120,000.00 15,696.00
Semen portland kg 67.9800 1,075.00 73,078.50
JUMLAH HARGA BAHAN 179,001.09
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 918,409.09
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 918,409.09

PEKERJAAN PENGECATAN (PERMEN PUPR 28/PRT/M/2016)

3 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0200 99,920.00 1,998.40
Tukang cat OH 0.0630 99,920.00 6,294.96
Kepala Tukang OH 0.0063 99,920.00 629.50
Mandor OH 0.0025 99,920.00 249.80
JUMLAH TENAGA KERJA 9,172.66
B. BAHAN
Plamir kg 0.1000 17,000.00 1,700.00
Cat dasar kg 0.1000 28,000.00 2,800.00
Cat Penutup 2x kg 0.2600 35,000.00 9,100.00
JUMLAH HARGA BAHAN 13,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 22,772.66
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 22,772.66

40 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN POLITUR 2 LAPIS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500 99,920.00 24,980.00
Tukang cat OH 0.2500 99,920.00 24,980.00
Kepala Tukang OH 0.0250 99,920.00 2,498.00
Mandor OH 0.0130 99,920.00 1,298.96
JUMLAH TENAGA KERJA 53,756.96
B. BAHAN
Wood Filler Kg 0.1000 16,000.00 1,600.00
Politur Jadi Ltr 0.2000 32,000.00 6,400.00
Amplas Lbr 1.0000 5,000.00 5,000.00
Kuas Bh 0.0200 10,000.00 200.00
JUMLAH HARGA BAHAN 13,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 66,956.96
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 66,956.96
PEKERJAAN ELEKTRIKAL (PERMEN PUPR 28/PRT/2016)

KOEFISIEN HARGA SATUAN JUMLAH HARGA


NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang Listrik OH 0.100 99,920.00 9,992.00
Kepala tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.020 99,920.00 1,998.40
JUMLAH TENAGA KERJA 26,978.40
B. BAHAN
Kabel NYM 3x2.5 mM2 m1 9.0000 10,000.00 90,000.00
Pipa listrik 20 mm m1 9.0000 4,000.00 36,000.00
Sock Ø 20 mm Bh 2.0000 900.00 1,800.00
Tee dos clipsal 20 mm Bh 1.0000 500.00 500.00
klem 19 mm Bh 12.0000 100.00 1,200.00
outbow dos Bh 1.0000 3,000.00 3,000.00
Isolasi Bh 0.1000 5,000.00 500.00
JUMLAH HARGA BAHAN 133,000.00
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 159,978.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 159,978.40

KOEFISIEN HARGA SATUAN JUMLAH HARGA


NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang Listrik OH 0.100 99,920.00 9,992.00
Kepala tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.020 99,920.00 1,998.40
JUMLAH TENAGA KERJA 26,978.40
B. BAHAN
Kabel NYM 3x2.5 mM2 bh 10.0000 10,000.00 100,000.00
Pipa listrik 20 mm m1 10.0000 4,000.00 40,000.00
Sock Ø 20 mm bh 2.0000 900.00 1,800.00
Tee dos clipsal 20 mm bh 1.0000 500.00 500.00
klem 19 mm bh 12.0000 100.00 1,200.00
outbow dos bh 1.0000 3,000.00 3,000.00
Isolasi bh 0.1000 5,000.00 500.00
JUMLAH HARGA BAHAN 147,000.00
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 173,978.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 173,978.40
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang Listrik OH 0.100 99,920.00 9,992.00
Kepala tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.020 99,920.00 1,998.40
JUMLAH TENAGA KERJA 26,978.40
B. BAHAN
Lampu led 11 watt bh 1.0000 50,000.00 50,000.00
Fitting Kotak bh 1.0000 6,000.00 6,000.00
Isolasi m1 0.2500 5,000.00 1,250.00
JUMLAH HARGA BAHAN 57,250.00
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 84,228.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 84,228.40

1 Bh Pasang Saklar Tunggal

KOEFISIEN HARGA SATUAN JUMLAH HARGA


NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang Listrik OH 0.100 99,920.00 9,992.00
Kepala tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.020 99,920.00 1,998.40
JUMLAH TENAGA KERJA 26,978.40
B. BAHAN
Saklar tunggal bh 1.0000 45,000.00 45,000.00
outbow dos bh 1.0000 3,000.00 3,000.00
Isolasi m1 0.2500 5,000.00 1,250.00
JUMLAH HARGA BAHAN 49,250.00
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 76,228.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 76,228.40

KOEFISIEN HARGA SATUAN JUMLAH HARGA


NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang Listrik OH 0.100 99,920.00 9,992.00
Kepala tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.020 99,920.00 1,998.40
JUMLAH TENAGA KERJA 26,978.40
B. BAHAN
Stop Kotak bh 1.0000 50,000.00 50,000.00
outbow dos bh 1.0000 3,000.00 3,000.00
Isolasi m1 0.2500 5,000.00 1,250.00
JUMLAH HARGA BAHAN 54,250.00
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 81,228.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 81,228.40
PEKERJAAN SANITASI ( PERMEN PUPR 28/PRT/M/2016) )

1 MEMASANG 1 BUAH WASHTAFEL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.2000 99,920.00 119,904.00
Tukang Batu OH 1.4500 99,920.00 144,884.00
Kepala Tukang OH 0.1500 99,920.00 14,988.00
Mandor OH 0.1000 99,920.00 9,992.00
JUMLAH TENAGA KERJA 289,768.00
B. BAHAN
Wastafel bh 1.0000 300,000.00 300,000.00
Perlengkapan 12% x harga wast 36,000.00 36,000.00
Semen kg 6.0000 1,075.00 6,450.00
Pasir Pasang m3 0.0100 120,000.00 1,200.00
JUMLAH HARGA BAHAN 343,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 633,418.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 633,418.00

2 MEMASANG 1 BUAH KRAN


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Pipa OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 10,991.20
B. BAHAN
Kran wastafel bh 1.0000 150,000.00 150,000.00
Seal tape bh 0.0250 2,000.00 50.00
JUMLAH HARGA BAHAN 150,050.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 161,041.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 161,041.20

3 1 Bh Pemasangan Bak Cuci Piring Stailesssteel


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0300 99,920.00 2,997.60
Tukang Batu OH 0.3000 99,920.00 29,976.00
Kepala Tukang OH 0.0300 99,920.00 2,997.60
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 37,470.00
B. BAHAN
Bak Cuci piring stainlees bh 1.0000 150,000.00 150,000.00
Waterdrain bh 1.0000 40,000.00 40,000.00
JUMLAH HARGA BAHAN 190,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 227,470.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 227,470.00
4 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 1/2
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0360 99,920.00 3,597.12
Tukang Pipa OH 0.0600 99,920.00 5,995.20
Kepala Tukang OH 0.0060 99,920.00 599.52
Mandor OH 0.0020 99,920.00 199.84
JUMLAH TENAGA KERJA 10,391.68
B. BAHAN
Pipa PVC m' 1.2000 8,000.00 9,600.00
Perlengkapan 35% x harga pipa 2,800.00 2,800.00
JUMLAH HARGA BAHAN 12,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 22,791.68
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 22,791.68

5 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 3/4


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0360 99,920.00 3,597.12
Tukang Pipa OH 0.0600 99,920.00 5,995.20
Kepala Tukang OH 0.0060 99,920.00 599.52
Mandor OH 0.0020 99,920.00 199.84
JUMLAH TENAGA KERJA 10,391.68
B. BAHAN
Pipa PVC m' 1.2000 10,000.00 12,000.00
Perlengkapan 35% x harga pipa 3,500.00 3,500.00
JUMLAH HARGA BAHAN 15,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 25,891.68
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 25,891.68

6 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 1"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0540 99,920.00 5,395.68
Tukang Pipa OH 0.0900 99,920.00 8,992.80
Kepala Tukang OH 0.0090 99,920.00 899.28
Mandor OH 0.0030 99,920.00 299.76
JUMLAH TENAGA KERJA 15,587.52
B. BAHAN
Pipa PVC m' 1.2000 12,000.00 14,400.00
Perlengkapan 35% x harga pipa 4,200.00 4,200.00
JUMLAH HARGA BAHAN 18,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 34,187.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 34,187.52
7 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 3"
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0810 99,920.00 8,093.52
Tukang Pipa OH 0.1350 99,920.00 13,489.20
Kepala Tukang OH 0.0135 99,920.00 1,348.92
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 23,331.32
B. BAHAN
Pipa PVC m' 1.2000 20,000.00 24,000.00
Perlengkapan 35% x harga pipa 7,000.00 7,000.00
JUMLAH HARGA BAHAN 31,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,331.32
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 54,331.32

1 BH PASANGAN BUIS BETON DIAMETER 100 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0075 99,920.00 749.40
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA KERJA 30,225.80
B BAHAN
Buis Beton Diameter 100 cm BJ 1.0000 120,000.00 120,000.00
Semen 40 Kg Zak 0.0030 43,000.00 129.00
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 121,689.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 151,914.80
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 151,914.80
1 M3 Galian Tanah Pematangan Lahan 1,45 m
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.900 99,920.00 89,928.00
Mandor OH 0.045 99,920.00 4,496.40
JUMLAH TENAGA KERJA 94,424.40
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN 1.0000 7,500.00 7,500.00
JUMLAH HARGA ALAT 7,500.00

D. Jumlah (A + B + C) 101,924.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 101,924.40

1 1 M3 Galian Tanah Pematangan Lahan 3,45 m


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.050 99,920.00 104,916.00
Mandor OH 0.067 99,920.00 6,694.64
JUMLAH TENAGA KERJA 111,610.64
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN 1.0000 7,500.00 7,500.00
JUMLAH HARGA ALAT 7,500.00

D. Jumlah (A + B + C) 119,110.64
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 119,110.64
MEMASANG 1 M' Kusen Kayu Profil 55 x 110 mm Kamper
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang kayu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 32,474.00
B. BAHAN
Papan Kayu Kamper m3 1.2800 7,000,000.00 8,960,000.00
Paku 7 Cm dan 10 Cm Kg 0.1800 13,000.00 2,340.00
JUMLAH HARGA BAHAN 8,962,340.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 8,994,814.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 8,994,814.00

1 M3 GALIAN BATU EXSITING


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 13.334 99,920.00 1,332,333.28
Mandor OH 0.666 99,920.00 66,546.72
JUMLAH TENAGA KERJA 1,398,880.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,398,880.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,398,880.00
DAFTAR HARGA BAHAN
CV. KRISNA PUTRA BALI/TAHUN 2020
HARGA
NO NAMA BAHAN SAT
(RP)
1 2 3 4
BATU KALI DAN BATU ALAM
3 Batu Pecah Besar 15/30 cm m3 141,176.47
###
18 Batu Candi Hitam (Ukuran 30 x 30 x 5 Cm) Cirebon m2 130,000.00
###
30 Batu hitam karangasem/Batu Tabas (20 x 40 x 3) m2 225,000.00
###
46 Kerikil Beton m3 145,000.00
###
49 Pasir Pasang m3 120,000.00
###
50 Pasir Beton m3 120,000.00
###
51 Pasir Urug m3 100,000.00
###
52 Tanah Urug m3 90,000.00
###
60 Batako Buntu bh 2,000.00
###
66 Bata Merah Klas I bh 1,100.00
###
SEMEN ###
87 PC Conch 40 Kg sak 43,000.00
###
94 Semen Warna MU 408/ Nat kg 2,000.00
96 Semen Portland 40 KG kg 1,075.00
###
KAYU ###
182 Kayu kamper papan m3 7,000,000.00
###
192 Kayu Balok Meranti m3 4,000,000.00
###
197 Kayu Begisting 5/7 m3 2,000,000.00
###
201 Kayu Seseh Dolken D 8-10 Panjang 4m btg 5,000.00
210 Kayu Kelas III lokal m3 2,000,000.00
###
214 Papan Bakesting m3 1,200,000.00
###
219 Lem Kayu setara Fox ltr 12,000.00
###

###
BESI ###
299 Besi Beton U24 (Polos) Kg 8,500.00
###
300 Besi Beton Ulir U 32 Kg 8,500.00
###
337 Wiremesh M6@50m rol 200,000.00
###
338 Wiremesh M7 (D6,5mm) Uk. 2,1 x 5,4 m lbr 305,000.00
###
345 Kawat Beton RRT kg 13,000.00
###
###
CAT ###
482 Cat Dasar Tembok Setara Emco Kg 28,000.00
###
492 Cat tembok Setara Vinilex kg 35,000.00
###
499 Amplas lbr 5,000.00
###
500 Kuas Bh 10,000.00
###
###
Stone Coating ###
510 Dempul / Plamir ltr 17,000.00
###
523 Politur Jadi ltr 32,000.00
###
533 Wood Filler ltr 16,000.00
###
###
HARGA
NO NAMA BAHAN SAT
(RP)
1 2 3 4
KACA ###
541 Kaca 5 mm bening m2 220,000.00
###
###
PIPA ###
621 Pipa Maspion AW 1/2 m' 8,000.00
###
622 Pipa Maspion AW 3/4 m' 10,000.00
###
623 Pipa Maspion AW 1 m' 12,000.00
###
628 Pipa Maspion AW 3 m' 20,000.00
###

BAHAN LISTRIK
972 Kabel NYM 3 x 2.5 mm m 10,000.00
978 Klem clipsal 20 mm bj 100.00
997 Lampu LED (11 Watt) Setara Philips bh 50,000.00
1023 Pipa clipsal 20 mm bt 4,000.00
1026 Saklar tunggal Setara Broco bh 45,000.00
1028 Sock clipsal 20 mm bj 900.00
1030 Stop Kontak bh 50,000.00
1033 Tee dos clipsal 20 mm bh 500.00
1042 Isolasi unit 5,000.00
1048 outbow dos bh 3,000.00
1049 Fitting Kotak bh 6,000.00

GRANIT TILE ###


1060 Setara Ex Cina 60 x 60 cm m2 95,000.00
###
###
SANITAIR ###
1245 Kran TOTO TOTO T23B13 bh 150,000.00
###
1255 Seal tape bh 2,000.00
###
1262 Wastafel TOTO (putih) bh 300,000.00
###

KUNCI DAN PENGGANTUNG ###


1270 Engsel pintu Setara SOLID Ps 45,000.00
###
1271 Engsel jendela Setara SOLID Ps 50,000.00
###
1274 Grendel Jendela SOLID bh 35,000.00
###
1277 Kait angin biasa Setara SOLID bh 50,000.00
###
1290 Kunci slot / Grendel Pintu Setara DELLWYN bh 35,000.00
###
1291 Kunci tanam 2 slag Setara SOLID bh 130,000.00
###

PAKU ###
1305 Paku 2-4 cm kg 15,000.00
###
1307 Paku 5-12 cm kg 13,000.00
###
###
PLAFOND & TIRPLEK
1454 Triplek tebal 9,0mm kayu semi meranti II lbr 92,000.00
###
HARGA
NO NAMA BAHAN SAT
(RP)
1 2 3 4
BUIS BETON ###
1478 Buis Beton diameter 100 cm bj 120,000.00
###

ASPAL, BBM DAN PELUMAS ###


1511 Minyak Begesting ( B 115 ) ltr 2,000.00
###

LAIN - LAIN ###


1551 Air Bersih ltr 5.00
###
1552 Bak Cuci Aluminium bh 150,000.00
###
Waterdrain bh 40,000.00
DAFTAR HARGA SEWA
SCAFOLDING
KOTA DENPASAR TAHUN 2019

HARGA
NO NAMA BAHAN SAT
(RP)
1 2 3 4
1 Main Frame m3 7,500.00
2 Cross brace 220 m3 4,500.00
3 End Frame m3 5,500.00
4 Join Pen m3 1,500.00
5 U-Head m3 4,500.00
6 Jack Base m3 4,500.00
DAFTAR HARGA SATUAN UPAH
CV. KRISNA PUTRA BALI/TAHUN 2020
HARGA
NO NAMA SATUAN
Rp
1 2 3 4
1 Pekerja Hari 99,920.00
2 Tukang Gali Hari 99,920.00
3 Tukang batu/tembok Hari 99,920.00
4 Tukang Kayu Hari 99,920.00
5 Tukang besi/besi beton Hari 99,920.00
6 Tukang Cat/pelitur Hari 99,920.00
7 Tukang pipa Hari 99,920.00
8 Tukang pipa/operator pompa Hari 99,920.00
9 Tukang Style Bali Hari 99,920.00
10 Tukang Listrik Hari 99,920.00
11 Tukang Las Hari 99,920.00
12 Tukang aluminium Hari 99,920.00
13 Kepala Tukang Hari 99,920.00
14 Kepala Tukang Style Bali Hari 99,920.00
15 Mandor Style Bali Hari 99,920.00
16 Mandor Hari 99,920.00
17 Juru Ukur Hari 99,920.00
18 Pembantu Juru Ukur Hari 99,920.00
19 Mekanik alat berat Hari 99,920.00
20 Operator alat berat Hari 99,920.00
21 Pembantu operator Hari 99,920.00
22 Supir truk Hari 99,920.00
23 Kernet truk Hari 99,920.00
24 Juru gambar (drafter) Hari 99,920.00
25 Operator printer/plotter Hari 99,920.00
26 Tukang Masak Aspal Hari 99,920.00
27 Tukang Cor Aspal Hari 99,920.00
28 Pekerja Pembantu Tukang Aspal Hari 99,920.00
29 Penjaga Api Hari 99,920.00
30 Sopir SIM A Hari 99,920.00
31 Sopir SIM B1 Hari 99,920.00
32 Sopir SIM B2 Hari 99,920.00
33 Operator Hari 99,920.00
34 Operator Semi Terampil Hari 99,920.00
35 Pembantu Operator Hari 99,920.00
36 Pembantu Sopir Hari 99,920.00
37 Mekanik Terampil Hari 99,920.00
38 Masinis Hari 99,920.00
39 Pembantu Masinis Hari 99,920.00
40 Ongkos Kerja Pemasangan dan Pengelasan Hari 99,920.00
42 Ongkos tukang Ls 200,000.00
43 Ongkos Pemasangan Panel Ls
44 Pembantu Mekanik Hari
45 Pasang Atap Alang-Alang Hari
46 Pasang Bata Gosok Dua Muka m2
47 Pasang Bata Gosok Satu Muka m2
48 Pasang Batu Paras Diukir m2
49 Pasang Patu Paras Siap Diukir m2
1 2 3 4
50 Ongkos Ngebor O 30 cm m'
51 Ongkos Polis Kaca Tempered Tebal 5mm m'
52 Ongkos Polis Kaca Tempered Tebal 6mm m'
53 Ongkos Polis Kaca Tempered Tebal 8mm m'
54 Ongkos Polis Kaca Tempered Tebal 10mm m'
55 Ongkos Polis Kaca Tempered Tebal 12mm m'
56 Ongkos Polis Kaca Tempered Tebal 19mm m'

UPAH KERJA LAINNYA :


57 Pasangan Bata Gosok 2 Muka m2
58 Pasangan Paras Kerobokan 1 Muka m2
59 Pasangan Bata Press 1 Muka m2
60 Pasangan Paras 1 Muka m2
61 Pasangan Batu Palimanan Tebal 3 cm m2
62 Pasangan Paras + Bata Gosok 1 Muka m2
63 Pasangan Bata Gosok Diukir m2
64 Pasangan Batu Tabas Karangasem Diukir m2
65 Pasangan Paras + Bata Gosok Diukir m2
66 Membuat Sanggah Kemulan Batu Hitam 40cm x 90cm Atap Ijuk Unit
67 Membuat Sanggah Kemulan Batu Hitam 40cm x 90cm Atap Genteng Unit
68 Membuat Sanggah Kemulan Paras Bata 40cm x 90cm Atap Ijuk Unit
69 Membuat Sanggah Kemulan Paras Bata 40cm x 90cm Atap Genteng Unit
70 Membuat Sanggah Pertiwi Batu Hitam Atap Ijuk 190cm x 190cm Unit
71 Membuat Sanggah Pertiwi Batu Hitam Atap Genteng 190cm x 190cm Unit
72 Membuat Sanggah Pertiwi Paras Bata Atap Ijuk 190cm x 190cm Unit
73 Membuat Sanggah Pertiwi Paras Bata Atap Genteng 190cm x 190cm Unit
74 Membuat Sanggah Hyang Ibu Batu Hitam Atap Ijuk 200cm x 200cm Unit
75 Membuat Sanggah Hyang Ibu Batu Hitam Atap Genteng 200cm x 200cm Unit
76 Membuat Sanggah Hyang Ibu Paras Bata Atap Ijuk 200cm x 200cm Unit
77 Membuat Sanggah Hyang Ibu Paras Bata Atap Genteng 200cm x 200cm Unit
78 Membuat Sanggah Taksu Batu Hitam Atap Ijuk 40cmx40cm Unit
79 Membuat Sanggah Taksu Batu Hitam Atap Genteng 40cm x 40cm Unit
80 Membuat Sanggah Taksu Paras Bata Atap Ijuk 40cm x 40cm Unit
81 Membuat Sanggah Taksu Paras Bata Atap Genteng 40cm x 40cm Unit
82 1 Titik Instalasi Stop Kontak, Lampu Exhaust Fan dan Celling Pan titik 15,000.00
83 1 Tititk Instalasi AC titik
84 1 Titik Instalasi Telephone titik
85 1 Titik Instalasi MATV titik
86 Upah Membuat Peresapan Air ls
87 Upah Membuat Septitank ls
88 Upah Membuat Groundtank ls 110,000.00
89 Upah Membuat Septictank ls
90 1 bh Pasang Jaro bh 30,000.00
91 1 bh Pasang Pintu Shaft bh 60,000.00
92 1 bh Pasang Ceilling Speaker bh 70,000.00
93 1 bh Pasang Central Soundsystem bh 70,000.00
DAFTAR HARGA BAHAN TAMBAHAN
PADA DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KOTA DENPASAR TAHUN 2020

HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp)

1 2 3 4

BIDANG UMUM
1 Jaring Sungar m2 170,000.00
2 Tali Seling m' 9,500.00
3 Tali m' 5,600.00
4 Sekop Datar bh 165,000.00
5 Selang Air m' 8,000.00
6 Terpal m2 9,500.00

BIDANG BINA MARGA


1 Uditch 1000 x 1000 x 1200 K 350 unit 1,950,000.00
2 Uditch 1200 x 1200 x 1200 K 350 unit 2,950,000.00
3 Plat Penutup 400 x 1200 K 350 unit 450,000.00
4 Plat Penutup 1200 x 1200 x 1200 K 350 unit 1,250,000.00
5 Frame Manhole 1200 x 1200 unit 450,000.00
6 Cover Manhole 1200 x 1200 unit 650,000.00
7 Abu Batu m3 ###

BAHAN K3
A Alat Pelindung Diri
1 Topi Pelindung (safety Helmet) bh 55,000.00
2 Pelindung Mata (Goggles, Spectacles) bh 95,000.00
3 Tameng Mata (face Shield) bh 215,000.00
4 Masker Selam (Breathing Apparatus) bh 350,000.00
5 Pelindung Telinga (Ear Plug, Ear Muff) bh 250,000.00
6 Pelindung Pernafasan dan Mulut (Masker) bh 45,000.00
7 Sarung Tangan (Safety Gloves) bh 40,000.00
8 Penunjang Seluruh Tubuh (Full Body Harness) bh 130,000.00
9 Jaket Pelampung (Life Vest) bh 150,000.00
10 Celemek (Apron/Coverralls) bh 90,000.00
11 Pelindung Jatuh (Fall Arrester) bh 990,000.00

B Rambu-Rambu K3 bh 150,000.00
1 Rambu Petunjuk bh 150,000.00
2 Rambu Larangan bh 150,000.00
3 Rambu Peringatan bh 150,000.00
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp)

1 2 3 4
4 Rambu Kewajiban bh 150,000.00
5 Rambu Informasi bh 150,000.00
6 Rambu Pekerjaan Sementara bh 150,000.00
7 Tongkat Pengatur Lalu Lintas (Warning Light Stck) bh 60,000.00
8 Kerucut Lalu Lintas (Traffic Cone) bh 125,000.00
9 Lampu Putar (Rotary Lamp) bh 97,000.00
10 Lampu Selang Lalu Lintas bh
HARGA SATUAN
NO NAMA BARANG SAT.
2019 (Rp)

1 2 3 4

C Pengendaliang Resiko K3
1 Alat Pemadam Api Ringan (APAR) bh 550,000.00
2 Sirine bh 450,000.00
3 Bendera K3 bh
4 Lampu Darurat (Emergency Lamp) bh 170,000.00

BAHAN TAMBAHAN
1 List Gypsum Profil 5 cm m' 11,500.00
2 Bubungan Genteng glazur bh 44,651.10
3 Tempat Sabun bh 149,800.00
4 Kusen Aluminum m' 110,000.00
5 Rangka Jendela Aluminium m' 115,500.00
6 Rangka Pintu Aliminium m' 121,000.00
7 Door Stoper bh 210,000.00
8 Door Closer bh 380,000.00
9 Kusen dan Pintu PVC Toilet unit 800,000.00
10 Genteng Keramik ex Jatiwangi bh 7,500.00
11 Genteng Keramik Glazur ex KANMURI bh 22,500.00
12 Nok Genteng Keramik EX Jatiwangi bh 42,000.00
13 Nok Genteng Keramik Ex Kanmuri bh 47,000.00
14 Kran Zink bh 485,000.00
15 Kran Dinding bh 240,000.00
16 Kitchen Zink bh 850,000.00
17 Floor Drain bh 110,000.00
18 Bak Air Fibergles bh 395,000.00
19 Klep Diameter 3/4" bh 112,000.00
20 Tangkin Air 1000 Liter bh 1,850,000.00
21 Tangki Air 500 Liter bh 845,000.00
22 Pelampung Otomatis bh 170,000.00
23 Roof Drain Metal bh 97,000.00
24 Mesin Jet Pump kap 250 watt ex Grounfos bh 5,600,000.00
25 Mesin Pompa Tekan kap. 150 watt ex Grounfos bh 3,450,000.00
26 Box Panel PVC isi 4 MCB ex Legran bh 210,000.00
27 MCB 6 A ex Legran bh 52,000.00
28 MCB 4 A ex Legran bh 48,000.00
29 Kabel telephone 4 x 0.5 mm m' 22,000.00
30 Oulet TV Broco bh 220,000.00
31 Outlet Telephone bh 230,000.00
32 Dowlight/PLC 13 W bh 62,000.00
-
REKAPITULASI DAFTAR HARGA SATUAN PEKERJAAN
TAHUN 2019

NO URAIAN PEKERJAAN HARGA


1 2 3
I HARGA SATUAN PEKERJAAN PERSIAPAN (PERMEN PUPR 28/PRT/M/2016)
1 1 M2 PAGAR SEMENTARA DARI KAYU TINGGI 2 METER Rp. 71,578.80
2 1 M2 PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 METER Rp. 71,578.80
3 1 M2 PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER Rp. 58,956.80
4 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK Rp. 21,742.80
5 1 M2 PEMBUATAN KANTOR SEMENTARA, DENGAN LANTAI PLESTERAN Rp. 634,372.00
6 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT Rp. 340,740.00
7 1 M2 PEMBUATAN RUMAH JAGA/KONSTRUKSI KAYU Rp. 293,884.00
8 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN Rp. 14,988.00
9 1 M2 PEMBUATAN BEDENG BURUH Rp. 338,490.00
10 1 M2 PEMBUATAN BAK ADUKAN UKURAN (40X50X25) CM Rp. 33,555.60
11 1 M2 PEMBUATAN STEGGER DARI BAMBU Rp. 324,740.00
12 1 M2 PEMBUATAN JALAN SEMENTARA Rp. 114,325.48
13 1 M3 BONGKARAN BETON BERTULANG Rp. 1,398,880.00
14 1 M3 BONGKARAN DINDING TEMBOK BATA Rp. 699,440.00
15 1 M2 PEMASANGAN PAGAR KAWAT JARING GALVANIS PANJANG 240 CM Rp. 8,992.80
16 1 M2 PEMASANGAN PANEL BETON PRACETAK 5X50X240 CM UNTUK PAGAR Rp. 62,057.52
17 BONGKAR 1 M3 BETON SECARA KONVENSIONAL Rp. 395,683.20

II HARGA SATUAN PEKERJAAN TANAH (PERMEN PUPR 28/PRT/M/2016)


1 1 M3 GALIAN TANAH BIASA DALAM 1 METER Rp. 77,438.00
2 1 M3 GALIAN TANAH BIASA DALAM 2 METER Rp. 94,424.40
3 1 M3 GALIAN TANAH BIASA DALAM 3 METER Rp. 111,610.64
4 1 M3 GALIAN TANAH KERAS DALAM 1METER Rp. 103,117.44
5 1 M3 GALIAN TANAH CADAS DALAM 1 METER Rp. 155,875.20
6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER Rp. 124,400.40
7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER Rp. 5,495.60
8 1 M3 PEMBUANGAN TANAH SEJAUH 30 METER Rp. 33,972.80
9 1 M3 PENGURUGAN KEMBALI GALIAN TANAH Rp. 57,703.80
10 1 M3 PEMADATAN TANAH ( Per 20 Cm ) Rp. 54,956.00
11 1 M3 URUGAN PASIR Rp. 150,975.20
12 1 M3 PEMASANGAN LAPISAN PUDEL CAMPURAN 1KP : 3PP : 7TL Rp. 179,894.40
13 1 M2 PEMASANGAN LAPISAN IJUK TEBAL 10 CM Rp. 16,486.80
14 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan Rp. 27,478.00
15 1 M3 TIMBUNAN PASIR SEBAGAI BAHAN PENGISI Rp. 303,200.00

III HARGA SATUAN PEKERJAAN PONDASI (PERMEN PUPR 28/PRT/M/2016)


1 1 M3 BATU BELAH CAMP. 1 SP : 3 PP Rp. 467,419.76
2 1 M3 BATU BELAH CAMP. 1 SP : 4 PP Rp. 471,619.76
3 1 M3 BATU BELAH CAMP. 1 SP : 5 PP Rp. 620,699.76
4 1 M3 BATU BELAH CAMP. 1 SP : 6 PP Rp. 602,314.76
5 1 M3 BATU BELAH CAMP. 1 SP : 8 PP Rp. 577,124.76
6 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 1KP : 2PP Rp. 400,694.75
7 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 3KP : 10PP Rp. 533,834.76
8 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1/4 SP : 1KP : 4PP Rp. 521,978.47
9 1 M3 PASANGAN PONDASI SIKLOP, 60% BETON CAMPURAN 1 SP : 2 PB : 3 KR DAN 40% BATU BELAH Rp. 1,858,294.31
10 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M 649,147.49
11 1 M3 PASANGAN BATU KOSONG 337,311.92
NO URAIAN PEKERJAAN HARGA
1 2 3

IV PEKERJAAN DINDING (PERMEN PUPR 28/PRT/M/2016))


1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS Rp. 101,931.25
2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS Rp. 146,699.44
3 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS Rp. 136,988.50
4 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS Rp. 135,272.00
5 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS Rp. 134,290.00
6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS Rp. 132,453.50
7 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP Rp. 130,303.50
8 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP Rp. 130,303.50
9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SM : 1 KP : 2 PP Rp. 122,841.05
10 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 2 PP Rp. 296,369.50
11 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 PP Rp. 285,273.25
12 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 4 PP Rp. 278,633.25
13 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 5 PP Rp. 275,037.00
14 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 6 PP Rp. 273,459.50
15 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 KP : 10 PP Rp. 260,868.00
16 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 pc : 3 ps Rp. 189,800.00
17 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 psp : 4 pp Rp. 188,565.50
18 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 3 pp Rp. 180,771.50
19 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 4 pp Rp. 179,731.00
20 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 3 pp Rp. 129,823.00
21 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 4 pp Rp. 129,823.00
22 1 M2 PASANGAN ROSTER camp 1 Pc : 3 Ps Rp. 16,025.00
23 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM camp 1 Pc : 4 Ps Rp. 61,415.55
24 1 M2 PASANGAN DINDING Bata Berongga Ekspose (12 x 11 x 24) CM camp 1 Pc : 3 PP Rp. 58,491.00
25 1 M2 PASANGAN DINDING BATA RINGAN TEBAL 7.5 CM DENGAN MORTAR SIAP PAKAI Rp. 210,131.76
26 1 M2 PASANGAN DINDING BATA RINGAN TEBAL 10 CM DENGAN MORTAR SIAP PAKAI Rp. 216,426.72

V PEKERJAAN PLESTERAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PLESTERAN CAMP. 1 PC : 1 PP TEBAL 15 MM Rp. 66,548.40
2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM Rp. 61,352.40
3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM Rp. 59,080.80
4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM Rp. 57,549.60
5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM Rp. 56,654.40
6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM Rp. 55,948.80
7 1 M2 PLESTERAN CAMP. 1 PC : 7 PS TEBAL 15 MM Rp. 55,552.80
8 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM Rp. 55,156.80
9 1 M2 PLESTERAN CAMP. 1 PC : 2PP TEBAL 20 MM Rp. 82,043.04
10 1 M2 PLESTERAN CAMP. 1 PC : 3PS TEBAL 20 MM Rp. 64,126.16
11 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM Rp. 78,114.96
12 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM Rp. 76,932.64
13 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM Rp. 75,779.04
14 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM Rp. 74,798.24
15 1 M2 PLESTERAN CAMP. 1 PC : 1 KP : 2 PS TEBAL 20 MM Rp. 74,798.24
16 1 M2 PLESTERAN BERAPEN 1 PS : 5PP TEBAL 15 MM Rp. 32,773.52
17 1 M' PLESTERAN SKONING 1 PC : 3 PS, TEBAL 10 MM Rp. 54,455.58
18 1 M2 PLESTERAN GRANIT 1 SP : 2 GRANIT TEBAL 1 CM Rp. 1,882,792.32
19 1 M2 PLESTERAN TRASO 1 SP : 2 TRASO TEBAL 1 CM Rp. 1,882,792.32
20 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS Rp. 47,830.00
21 1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH Rp. 27,421.82
NO URAIAN PEKERJAAN HARGA
1 2 3
22 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE Rp. 13,010.96
23 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS Rp. 56,217.10
24 1 M2 PLESTERAN MENGGUNAKAN SEMEN MU - 301, TEBAL 10 MM Rp. 64,148.64
25 1 M2 ACIAN MENGGUNAKAN SEMEN MU - 200,TEBAL 1,5MM Rp. 64,148.64
26 1 M2 PEKERJAAN ACIAN Rp. 35,468.15
NO URAIAN PEKERJAAN HARGA
1 2 3

VI PEKERJAAN KAYU (PERMEN PUPR 28/PRT/M/2016)


1 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I Rp. 3,070,814.00
2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS III Rp. 2,636,162.00
3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II Rp. 432,828.16
4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III Rp. 152,828.16
5 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II Rp. 720,652.00
6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS II Rp. 519,321.60
7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS II Rp. 888,652.00
8 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm) Rp. 485,646.40
9 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS II Rp. 533,311.60
10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS II Rp. 742,193.60
11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I Rp. 351,711.60
12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II Rp. 554,494.16
13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II Bentang 6 M' Rp. 1,811,408.00
14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I Rp. 2,984,968.40
15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II Rp. 1,082,164.80
16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II Rp. 24,732.80
17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II Rp. 24,732.80
18 MEMASANG 1 M2 USUK EXPOSE KAYU KLS I KAMPER Rp. 24,732.80
19 MEMASANG 1 M2 RENG KAYU KLS I KAMPER Rp. 24,732.80
20 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II Rp. 28,379.36
21 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II Rp. 58,055.60
22 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II Rp. 57,206.80
23 MEMASANG 1 M' LISPLANK Rp. 33,774.00
24 MEMASANG 1 M' LISPLANK & TATAB Rp. 33,124.00
25 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II Rp. 67,197.76
26 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II Rp. 73,917.76
27 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II Rp. 95,600.40
28 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA HOLO Rp. 73,917.76
29 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA HOLO Rp. 95,600.40
30 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I Rp. 262,091.20
31 MEMASANG 1 M2 LAMBRIZIRING DARI CONWOOD UKURAN (100 x 3050 x 11 mm) Rp. 11,541.28
32 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM Rp. 11,541.28

VII PEKERJAAN BETON ( PERMEN PUPR 28/PRT/M/2016))


1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87 Rp. 544,522.83
2 MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c = 0,78 Rp. 572,183.55
3 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72 Rp. 594,422.83
4 MEMBUAT 1 M³ LANTAI KERJA BETON MUTU F'C = 7,4 MPA SLUMP (3-6)CM, W/C =0.87 Rp. 472,674.46
5 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66 Rp. 620,104.98
6 MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61 Rp. 645,569.26
7 MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58 Rp. 663,165.69
8 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56 Rp. 676,626.41
9 MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53 Rp. 699,590.69
10 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52 Rp. 706,858.55
11 MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49 Rp. 789,221.37
12 MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48 Rp. 798,639.23
13 PEMBESIAN 1 KG DENGAN BESI POLOS ATAU BESI ULIR Rp. 10,628.79
14 PEMBESIAN 1 KG kabel prategang (prestressed) polos/strands Rp. 10,134.14
15 PEMBESIAN 1 KG DENGAN BESI POLOS Rp. 2,447.54
NO URAIAN PEKERJAAN HARGA
1 2 3
16 Pemasangan 10 Kg jaring kawat baja (wiremesh) Rp. 1,927,730.92
17 1 M2 PASANG BEKISTING UNTUK PONDASI Rp. 167,033.44
18 1 M2 PASANG BEKISTING UNTUK SLOOF Rp. 177,033.44
19 1 M2 PASANG BEKISTING UNTUK KOLOM Rp. 282,915.52
20 1 M2 PASANG BEKISTING UNTUK BALOK Rp. 294,915.52
21 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI Rp. 282,915.52
22 1 M2 PASANG BEKISTING UNTUK DINDING Rp. 282,915.52
23 1 M2 PASANG BEKISTING UNTUK TANGGA Rp. 157,400.00
24 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON Rp. 81,882.96
25 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM) Rp. 65,979.60
26 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM) Rp. 86,568.82
27 1 M2 BEKISTING DINDING BETON BIASA DENGAN MULTIFLEX 12 mm *2 kali pakai* Rp. 60,688.32
28 1 M2 BEKISTING PONDASI DAN SLOOF BETON BIASA MENGGUNAKAN PAPAN 3/20 CM *2 kali pakai* Rp. 110,980.40
29 1 M2 PERANCAH/PENYOKONG BEKISTING DINDING BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks 2,5 m *2 kali pakai* Rp. 97,672.48
30 1 M2 PERANCAH/PENYOKONG BEKISTING PONDASI DAN SLOOF BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks 2,0 m *2 kali pakai* Rp. 74,223.60
NO URAIAN PEKERJAAN HARGA
1 2 3

VIII HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)
1 1 KG PEMASANGAN BESI PROFIL Rp. 12,889.68
2 1 KG PEMASANGAN RANGKA KUDA-KUDA BAJA IWF Rp. 12,889.68
3 100 KG PENGERJAAN PEKERJAAN PERAKITAN Rp. 12,889.68
4 1 M2 PEMASANGAN PINTU ROLLING DOOR BESI Rp. 252,397.92
5 1 M2 PEMASANGAN ROLLING DOOR ALLUMINIUM Rp. 214,828.00
6 1 M2 PEMASANGAN KUSEN PINTU ALLUMINIUM Rp. 9,232.61
7 1 M2 PEMASANGAN PINTU ALLUMINIUM STRIP LEBAR 8 CM Rp. 18,255.38
8 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1 X40.40.2MM, MODUL 60 X 120 CM, UNTUK PARTISI Rp. 53,756.96
9 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1 X40.40.2MM, MODUL 60 X 120 CM, UNTUK PLAFON Rp. 75,239.76
10 1 M2 PEMASANGAN ATAP PELANA RANGKA ATAP BAJA CANAI DINGIN PROFIL C75 Rp. 157,673.76
11 1 M2 PEMASANGAN ATAP JURAI RANGKA ATAP BAJA CANAI DINGIN PROFIL C75 Rp. 163,349.22

IX PEKERJAAN PENUTUP ATAP (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PEKERJAAN ATAP GENTENG GOODYEAR Rp. 24,080.72
2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT Rp. 24,080.72
3 1 M1 PASANG BUBUNGAN GENTENG GOODYEAR Rp. 77,600.24
4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM Rp. 22,082.32
5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M Rp. 22,581.92
6 1 M2 PASANGAN LAPISAN ALUMINIUM FOIL Rp. 7,094.32
7 1 M1 BUBUNGAN ATAP Bubungan Genteng Metal Prima Roof Rp. 42,765.76
8 1 BH PEKERJAAN PASANGAN IKUT CELEDU Rp. 7,507.98

X PEKERJAAN PLAFOND / LANGIT - LANGIT (PERMEM PUPR 28/PRT/M/2016))


1 MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN 6 MM Rp. 11,091.12
2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/3 MM, 4MM, 6MM Rp. 21,482.80
3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING Rp. 276,862.40
4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL Rp. 10,791.36
5 1 M1 PASANG LIST LANGIT-LANGIT GYPSUM PROFIL Rp. 10,791.36
6 1 M2 PASANG LANGIT-LANGIT AKUSTIK UKURAN (60 x 120) CM + RANGKA ALUMINIUM Rp. 107,414.00
7 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA Rp. 54,056.72
8 1 M2 PLAFOND GYPSUM, RANGKA KAYU Rp. 73,441.20
9 1 M2 PLAFOND GYPSUM, RANGKA HOLO Rp. 69,944.00
10 1 M2 PLAFOND KALSIBOARD, RANGKA KAYU Rp. 69,944.00
11 1 M2 PLAFOND KALSIBOARD, RANGKA HOLO Rp. 69,944.00

XI PEKERJAAN SANITASI ( PERMEN PUPR 28/PRT/M/2016) )


1 MEMASANG 1 BUAH KLOSET DUDUK Rp. 478,521.88
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN Rp. 423,317.20
3 MEMASANG 1 BUAH URINOIR Rp. 227,474.00
4 MEMASANG 1 BUAH WASHTAFEL KIA Rp. 297,418.00
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 Rp. 514,588.00
6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 " Rp. 17,985.60
7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3" Rp. 31,115.09
8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5" Rp. 10,371.70
9 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 1" Rp. 34,187.52
10 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 3" Rp. 54,331.32
11 MEMASANG 1 M1 PIPA PVC TYPE AW f Ø 4" Rp. 23,331.32
12 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5" Rp. 160,991.20
NO URAIAN PEKERJAAN HARGA
1 2 3

XII PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)


1 1 KG MEMASANG RANGKA BAJA IWF Rp. 7,224.22
2 1 M2 PASANG JENDELA NAKO & TRALIS Rp. 192,066.32
3 1 M1 PASANG TALANG DATAR, SENG BJLS 28 Rp. 63,674.20

XIII PEKERJAAN KUNCI DAN KACA PERMEN PUPR 28/PRT/M/2016)


1 1 BH PASANG KUNCI TANAM BIASA Rp. 184,956.00
2 1 PS PASANG ENGSEL PINTU Rp. 58,788.96
3 1 PS PASANG ENGSEL JENDELA KUPU-KUPU Rp. 60,991.20
4 1 BH PASANG KAIT ANGIN Rp. 60,091.92
5 1 BH PASANG KUNCI SLOT PINTU Rp. 65,601.90
6 1 M2 PASANG KACA, TEBAL5 MM Rp. 48,760.96
7 1 M2 PASANG KACA TEMPERED TEBAL 5 MM Rp. 48,760.96
8 1 M2 PASANG KACA TEMPERED TEBAL 6 MM Rp. 48,760.96
9 1 M2 PASANG KACA TEMPERED TEBAL 12 MM Rp. 48,760.96

XIV PEKERJAAN PENUTUP LANTAI DAN DINDING (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PASANG LANTAI UBIN PC ABU - ABU UKURAN (40 X 40) CM Rp. 44,168.96
2 1 M2 PASANG LANTAI UBIN PC ABU - ABU UKURAN (30 X 30) CM Rp. 44,168.96
3 1 M2 PASANG LANTAI UBIN PC ABU - ABU UKURAN (20 X 20) CM Rp. 47,266.48
4 1 M2 PASANG LANTAI UBIN WARNA UKURAN (40 X 40) CM Rp. 56,002.92
5 1 M2 PASANG LANTAI UBIN WARNA 30 X 30 CM Rp. 58,916.72
6 1 M2 PASANG LANTAI UBIN WARNA 20 X 20 CM Rp. 61,845.36
7 1 M2 PASANG LANTAI UBIN TERASO UKURAN 40 X 40 CM Rp. 206,692.92
8 1 M2 PASANG LANTAI UBIN TERASO UKURAN 30 X 30 CM Rp. 232,406.72
9 1 M2 PASANG LANTAI UBIN GRANIT UKURAN 40 X 40 CM Rp. 206,692.92
10 1 M2 PASANG LANTAI UBIN GRANIT UKURAN 30 X 30 CM Rp. 232,406.72
11 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 40 X 40 CM Rp. 207,192.52
12 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 30 X 30 CM Rp. 232,406.72
13 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 60 X 60 CM Rp. 57,089.28
14 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM Rp. 131,730.40
15 1 M' PASANGPLINT UBIN PC ABU-ABU UKURAN 15 CM X 20 CM Rp. 21,638.23
16 1 M' PASANGPLINT UBIN PC ABU-ABU UKURAN 10 CM X 30 CM Rp. 21,077.48
17 1 M' PASANGPLINT UBIN PC ABU-ABU UKURAN 10 CM X 40 CM Rp. 21,077.48
18 1 M' PASANGPLINT UBIN WARNA UKURAN 10 CM X 20 CM Rp. 21,269.98
19 1 M' PASANGPLINT UBIN WARNA UKURAN 10 CM X 30 CM Rp. 21,269.98
20 1 M' PASANGPLINT UBIN WARNA UKURAN 10 CM X 40 CM Rp. 21,169.98
21 1 M' PASANGPLINT UBIN TERASO UKURAN 10 CM X 30 CM Rp. 21,169.98
22 1 M' PASANG PLINT UBIN TERASO UKURAN 10 CM X 40 CM Rp. 21,169.98
23 1 M' PASANG PLINT UBIN GRANIT UKURAN 10 CM X 40 CM Rp. 20,969.98
24 1 M' PASANG PLINT UBIN GRANIT UKURAN 10 CM X 30 CM Rp. 21,169.98
25 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 CM X 40 CM Rp. 21,169.98
26 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 CM X 30 CM Rp. 21,169.98
27 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 CM X 60 CM Rp. 21,169.98
28 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 CM X 40 CM Rp. 21,169.98
29 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 CM X 30 CM Rp. 21,169.98
30 1 M2 PASANG LANTAI KERAMIK UKURAN 33 CM X 33 CM Rp. 30,134.48
31 1 M2 PASANG LANTAI KERAMIK UKURAN 40 CM X 40 CM Rp. 129,060.40
32 1 M2 PASANG LANTAI KERAMIK UKURAN 20 CM X 20 CM Rp. 17,580.00
33 1 M2 PASANG LANTAI KERAMIK UKURAN 10 CM X 33 CM Rp. 178,500.52
NO URAIAN PEKERJAAN HARGA
1 2 3
34 1 M2 PASANG LANTAI KERAMIK MOZAIK UKURAN 30 CM X 30 CM Rp. 127,121.65
35 1 M' PASANG PLINT KERAMIK UKURAN 10 CM X 20 CM Rp. 1,635.50
36 1 M' PASANG PLINT KERAMIK UKURAN 10 CM X 10 CM Rp. 23,207.90
37 1 M' PASANG PLINT KERAMIK UKURAN 5 CM X 20 CM Rp. 22,595.15
38 1 M2 PASANG DINDING KERAMIK 10 CM X 20 CM Rp. 153,882.30
39 1 M2 PASANG DINDING KERAMIK 20 CM X 25 CM Rp. 16,037.50
40 1 M2 PASANG DINDING MARMER 100 CM X 100 CM Rp. 221,206.60
41 1 M2 PEMASANGAN PAVING BLOCK NATURAL Tebal 6 cm ( 20x20 cm) Rp. 84,069.19
42 1 M2 PEMASANGAN PAVING BLOCK BERWARNA Tebal 6 cm ( 20x20 cm) Rp. 189,669.00
43 1 M2 PEMASANGAN PAVING BLOCK BERWARNA Tebal 8 cm ( 20x20 cm) Rp. 113,629.00
44 1 M2 PEMASANGAN PAVING BLOCK NATURAL Tebal 8 cm ( 20x20 cm) Rp. 113,629.00
NO URAIAN PEKERJAAN HARGA
1 2 3

XV PEKERJAAN PENGECATAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PEKERJAAN MENGIKIS ATAU MENGEROK CAT TEMBOK CARA MANUAL Rp. 15,787.36
2 1 M2 PEKERJAAN LAPIS PLAMIR Rp. 5,395.68
3 1 M2 PENGECATAN TEMBOK BARU INTERIOR (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) Rp. 13,672.66
4 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN KUAS Rp. 20,340.56
5 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN ROLL Rp. 23,944.00
6 1 M2 PEKERJAAN PENGECATAN LANGIT -LANGIT 2 LAPIS DENGAN CAT TEMBOK MENGGUNAKAN KUAS TERMASUK PLAMIR Rp. 23,538.00
7 1 M2 PEKERJAAN PENGECATAN PLAFOND 2 LAPIS DENGAN CAT TEMBOK MENGGUNAKAN ROLL Rp. 14,891.44
8 1 M2 WATERPROOFING Rp. 19,384.48
9 1 M2 PEKERJAAN PASANG WALL PAPER DENGAN PEREKAT SILK HOUSE Rp. 12,490.00
10 1 M2 PEKERJAAN MELAPIS MENI KAYU Rp. 8,043.68
11 1 M2 PEKERJAAN MENDEMPUL ATAU MEMPLAMIR DAN MENGGOSOK KAYU Rp. 17,240.32
12 1 M2 PEKERJAAN PENGECATAN DASAR 1 LAPIS PADA KAYU Rp. 13,443.36
13 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA KAYU Rp. 42,974.16
14 1 M2 PEKERJAAN MENGEROK KARAT ATAU CAT PADA PERMUKAAN BAJA DENGAN SODA API Rp. 33,974.80
15 1 M2 PEKERJAAN MELAPIS MENI PADA PERMUKAAN BAJA Rp. 10,543.68
16 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA SECARA MANUAL Rp. 32,474.16
17 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA/KAYU DENGAN SEMPROT Rp. 17,186.24
18 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN TEAK OIL Rp. 13,641.20
19 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN POLITUR Rp. 66,956.96
20 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN VERNIS 2 LAPIS Rp. 13,691.20
1 M2 Pekerjaan Finish Court Coating 2 Kali
21 Rp. 22,362.26

XIV PEKERJAAN ELEKTRIKAL (PERMEN PUPR 28/PRT/2016)


1 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN Rp. 112,200.00
2 1 TITIK INSTALASI AC Rp. 186,600.00
3 1 TITIK INSTALASI TELEPHONE Rp. 104,500.00
4 1 TITIK INSTALASI MATV Rp. 78,800.00
5 1 TITIK PEMASANGAN LAMPU Rp. 15,000.00

XV PEKERJAAN ANGKUT MATERIAL DAN/ ATAU HASIL GALIAN (PERMEN PUPR 28/PRT/M/2016)
1 MENGANGKUT 1 M3 MATERIAL ATAU HASIL GALIAN DENGAN JARAK ANGKUT 50 M' Rp 44,274.55
2 MENGANGKUT 1 M3 MATERIAL ATAU HASIL GALIAN DENGAN JARAK ANGKUT 100 M' Rp 63,852.00
REKAPITULASI DAFTAR HARGA SATUAN PEKERJAAN TAMBAHAN
TAHUN 2019

NO URAIAN PEKERJAAN HARGA


1 2 3

1 1 M2 PEMBUATAN STEGGER DENGAN SCAFHOLDING 120 x 180 h 190 (Sewa) Rp 116,777.44


2 PEMBESIAN 10 KG DENGAN BESI POLOS Rp 106,287.92
3 PEMBESIAN 1 KG DENGAN BESI POLOS Rp 10,628.79
4 PEMBESIAN 10 KG DENGAN BESI ULIR Rp 106,287.92
5 PEMBESIAN 1 KG DENGAN BESI ULIR Rp 10,628.79
6 1 BH PEKERJAAN PASANGAN MURDA/BETALA/IKUT CELEDU Rp 7,494.00

XVI PEKERJAAN STYLE BALI


1 1 M2 PASANGAN BATA GOSOK 2 MUKA Rp 99,920.00
2 1 M2 PASANGAN PARAS KEROBOKAN 1 MUKA Rp 99,920.00
3 1 M2 PASANGAN BATA PRESS 1 MUKA Rp -
4 1 M2 PASANGAN PARAS 1 MUKA Rp -
5 1 M2 PASANGAN BATU PALIMANAN TEBAL 3 CM Rp 135,416.67
6 1 M2 PASANGAN PARAS + BATA GOSOK 1 MUKA Rp -
7 1 M2 PASANGAN BATA GOSOK DIUKIR Rp -
8 1 M2 PASANGAN BATU TABAS KARANGASEM DIUKIR Rp -
9 1 M2 PASANGAN PARAS + BATA GOSOK DIUKIR Rp -
10 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP IJUK Rp -
11 1 UNIT SANGGAH KEMULAN BT HITAM 40cm x 90cm ATAP GENTENG Rp -
12 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP IJUK Rp 300,000.00
13 1 UNIT SANGGAH KEMULAN PARAS BATA 40cm x 90cm ATAP GENTENG Rp 250,000.00
14 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP IJUK 190cmX190cm Rp -
15 1 UNIT SANGGAH PERTIWI BATU HITAM ATAP GENTENG 190cmx190cm Rp -
16 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP IJUK 190cmx190cm Rp -
17 1 UNIT SANGGAH PERTIWI PARAS BATA ATAP GENTENG 190cmx190cm Rp 610,000.00
18 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP IJUK 200CMX200CM Rp -
19 1 UNIT SANGGAH HYANG IBU BATU HITAM ATAP GENTENG 200CMX200CM Rp -
20 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP IJUK 200CMX200CM Rp 1,050,000.00
21 1 UNIT SANGGAH HYANG IBU PARAS BATA ATAP GENTENG 200CMX200CM Rp 1,050,000.00
22 1 UNIT SANGGAH TAKSU BATU HITAM ATAP IJUK 40cmx40cm Rp -
23 1 UNIT SANGGAH TAKSU BATU HITAM ATAP GENTENG 40cmx40cm Rp -
24 1 UNIT SANGGAH TAKSU PARAS BATA ATAP IJUK 40cmx40cm Rp 200,000.00
25 1 UNIT SANGGAH TAKSU PARAS BATA ATAP GENTENG 40cmx40cm Rp 200,000.00

XVII PEKERJAAN HARDDSCAPE


1 1 M2 PASANGAN PAVING BETON 10/20 CM TEBAL 6 CM K 225 Rp. 77,438.00
2 1 M2 PASANGAN Paving 10 x 20 cm tebal 6 cm K350 Rp. 77,438.00
3 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K225 Rp. 77,438.00
4 1 M2 PASANGAN Paving 10 x 20 cm tebal 8 cm K350 Rp. 77,438.00
5 1 M2 PASANGAN Paving 20 x 20 cm tebal 6 cm K350 Rp. 77,438.00
6 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K225 Rp. 77,438.00
7 1 M2 PASANGAN Paving 20 x 20 cm tebal 8 cm K350 Rp. 77,438.00
8 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 pc Rp. 77,438.00
9 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 merah Rp. 77,438.00
10 1 M2 PASANGAN Paving segi enam xexagon 6 cm K225 hitam Rp. 77,438.00
11 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 pc Rp. 77,438.00
NO URAIAN PEKERJAAN HARGA
1 2 3
12 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 merah Rp. 77,438.00
13 1 M2 PASANGAN Paving segi enam xexagon 6 cm K300 hitam Rp. 77,438.00
14 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 pc Rp. 77,438.00
15 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 merah Rp. 77,438.00
16 1 M2 PASANGAN Paving segi enam xexagon 6 cm K350 hitam Rp. 77,438.00
17 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 pc Rp. 77,438.00
18 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 merah Rp. 77,438.00
19 1 M2 PASANGAN Paving segi enam xexagon 6 cm K400 hitam Rp. 77,438.00
NO URAIAN PEKERJAAN HARGA
1 2 3
20 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 pc Rp. 77,438.00
21 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 merah Rp. 77,438.00
22 1 M2 PASANGAN Paving bujur sangkar tanpa tias 6 cm K225 hitam Rp. 77,438.00
23 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 pc Rp. 77,438.00
24 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 merah Rp. 77,438.00
25 1 M2 PASANGAN Paving bujur sangkar tanpa tias 8 cm K225 hitam Rp. 77,438.00
26 1 M2 PASANGAN Paving Tiga Berlian tebal 6 cm K225 pc Rp. 77,438.00
27 1 M2 PASANGAN GRASS BLOCK Rp. -
28 1 M2 PASANGAN KORAL SIKAT Rp. 20,000.00
29 1 M1 KANSTEIN BULAT (50 x 30 x 10 ) CM K225 Rp. 132,114.70
30 Kanstein Jumbo (P:50,L:15,T:30 cm K225) Rp. 132,114.70
31 Kanstein kotak (P:50,t.20,La.10,Lb.16cm) K225 Rp. 132,114.70
32 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K225 ) Rp. 132,114.70
33 Kanstein kursi ( P.50, L.10, T.40cm,lb 17,5 cm K300 ) Rp. 132,114.70
34 Kanstein Segi Lima Jumbo (P:50,L:15, T:20 cm K225) Rp. 132,114.70
35 Kanstein Segi Lima Jumbo (P:40,L:10, T:20 cm K225) Rp. 132,114.70
36 1 Buah Pasangan Kanstein Segi Lima Jumbo (P:50,L:15, T:40 cm K225) Rp. 132,114.70
37 1 M2 PENGECATAN KANSTEIN Rp. 19,784.16
38 PASANGAN BUIS BETON DIAMETER 80 CM Rp. 31,785.80
39 PASANGAN Buis Beton Diameter 50 x 75 Rp. 31,785.80
40 PASANGAN BUIS BETON DIAMETER 25 CM Rp. 31,785.80
41 1 M2 BONGKARAN PAVING LAMA Rp. 10,491.60
42 1 M3 PENGURUGAN DENGAN LIMESTONE Rp. 27,478.00
43 PASANGAN BUIS BETON DIAMETER 100 CM Rp. 151,785.80
44 1 M' PASANGAN BUIS BETON DIAMETER 100 CM Rp 303,571.60
45 PASANGAN BUIS BETON DIAMETER 80 CM Rp. 31,785.80
46 1 M' PASANGAN BUIS BETON DIAMETER 80 CM Rp. 63,571.60
47 PASANGAN BUIS BETON DIAMETER 50 CM Rp. 33,685.00
48 1 M' PASANGAN BUIS BETON DIAMETER 50 CM Rp 44,801.05
49 PASANGAN BUIS BETON DIAMETER 25 CM Rp. 33,669.00
50 1 M' PASANGAN BUIS BETON DIAMETER 25 CM Rp 44,779.77
51 1 M' PASANGAN1/2 BUIS BETON DIAMETER 25 CM Rp. 16,834.50
52 1 M' KANSTEIN SEGI LIMA (P:50:15,T:20)K-225 Rp 132,114.70
53 1 M' KANSTEIN KURSI K-225 Rp 132,114.70
DAFTAR HARGA SEWA ALAT BERAT
TAHUN 2019

HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4

1 Asphalt Mixing Plant Jam 5,146,022.47


2 Asphalt Finisher Jam 507,700.00
3 Asphalt Sprayer Jam 115,346.00
4 Bulldozer 100-150 HP Jam 435,566.00
5 Compressor 4000-6500 L\M Jam 170,800.00
6 Concrete Mixer 0.3-0.6 M3 Jam 85,573.00
7 Mixer Kyukuto Hino Kapasitas 7 m3 / 25 hari 95,000,000.00
kerja / 200
jam
8 Mixer Kyukuto Hino Kapasitas 2,5 m3 / 25 hari 62,500,000.00
kerja / 200
jam
9 Crane 10-15 TON Jam 521,072.00
10 Dump Truck 3-4 M3 Jam 249,651.00
11 Dump Truck Jam 387,651.00
12 Excavator 80-140 HP Jam 470,000.00
13 Flat Bed Truck 3-4 M3 Jam 373,577.00
14 Generator Set Jam 419,800.00
15 Motor Grader >100 HP Jam 455,299.00
16 Track Loader 75-100 HP Jam 378,324.00
17 Wheel Loader 1.0-1.6 M3 Jam 335,000.00
18 Loader WA 200-1 / 25 hari
kerja / 200
jam
19 Sift Loader dengan Crane / Hiap Crane 8 ton / 8 jam 4,500,000.00
20 Sift Loader dengan Crane / Hiap Crane 5 ton / 8 jam 3,880,000.00
21 Dolly Scania 18 ton / 8 jam 3,885,000.00
22 Three Wheel Roller 6-8 T Jam 302,037.00
23 Tandem Roller 6-8 T. Jam 320,300.00
24 Tire Roller 8-10 T. Jam 298,200.00
25 Vibratory Roller 5-8 T. Jam 497,000.00
26 Concrete Vibrator Jam 50,200.00
27 Stone Crusher Jam 735,332.00
HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4
28 Water Pump 70-100 mm Jam 46,600.00
29 Water Tanker 3000-4500 L. Jam 253,386.00
30 Pedestrian Roller Jam 74,338.00
31 Tamper Jam 58,096.00
32 Jack Hammer Jam 78,800.00
33 Fulvi Mixer Jam 148,400.00
34 Concrete Pump Jam 308,178.00
35 Concrate Pump Standart IHI IPF 8E 21, 21 m / 25 hari 65,000,000.00
kerja / 200
jam
HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4
36 Concrate Pump Long Boom IHI IPF 8 N 29, 29 m / 25 hari
kerja / 200 60,000,000.00
jam
37 Concrate Pump Mini IHI IPN4N17, 17 m / 25 hari
kerja / 200 50,000,000.00
jam
38 Trailer 20 TON Jam 285,292.00
39 Pile Driver + Hammer Jam 193,967.00
40 Crane on Track 35 TON Jam 399,665.00
41 Welding Set Jam 165,293.00
42 Bore Pile Machine Jam 993,707.00
43 Asphalt Liquid Mixer Jam 85,865.00
44 Trailer Jam 355,050.00
45 Cold Milling Jam 493,500.00
46 Rock Drill Breaker Jam 60,810.00
47 Alat Stressing Jam 13,500.00
48 Alat Grouting Jam 18,000.00
49 Baro Mixer Jam 65,000.00
50 Bole Mixer Jam 65,000.00
51 Prenater Jam 65,000.00
52 Asphalt Cutter Jam 62,111.00
53 Concrete Pan Mixer Jam 456,635.00
54 Truck Mixer Jam 546,182.00
55 Blending Equipment Jam 192,768.87
56 Asphalt Distributor Jam 348,305.00
57 Crane Tadano Bulan 115,000,000.00
58 Crane Tadano Bulan 97,000,000.00
59 Crane Tadano Bulan 90,000,000.00
60 Crane Tadano Bulan 85,000,000.00
61 Crane Tadano Bulan 60,000,000.00
62 Crane Tadano Hari 15,000,000.00
63 Crane Tadano Hari 10,000,000.00
64 Crane Tadano Hari 9,500,000.00
65 Crane Tadano Hari 8,500,000.00
66 Crane Tadano Hari 7,000,000.00
67 Excavator PC.200-8 / MO Jam 570,000.00
HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4
68 Excavator PC.200-8 / MO Jam 500,000.00
69 Mobilisasi Excavator PC.200-8 (Denpasar, Kuta, Nusa Dua) LS 4,000,000.00
70 Excavator PC.78 UU (breaker) Jam 450,000.00
71 Excavator PC.78 UU (bucket) Jam 390,000.00
72 Mobilisasi Excavator PC.78 UU (Denpasar, Kuta, Nusa Dua) LS 2,500,000.00
73 Sewa TC Potain MC 205B made in Prancis, jib length 60 m Bulan 120,000,000.00
kapasitas 2,4 ton
74 Jaminan Angkur TC Potain MC 205B Set 60,000,000.00
75 Pasang Angkur TC Potain MC 205B Set 6,500,000.00
76 Erexsion TC Potain MC 205B Set 50,000,000.00
HARGA
NO NAMA BARANG SATUAN
Rp
1 2 3 4
77 Dismantling Normal TC Potain MC 205B Set 50,000,000.00
78 Mob-Demob TC Potain MC 205B wilayah Bali Set 95,000,000.00
79 Gaji Operator TC Potain MC 205B / bulan 3,500,000.00
80 Sewa Mesin Bor Jam 65,000.00
81 Alat Bantu Pekerjaan Pengeboran Bored Pile LS 4,500,000.00
82 Batching Plant (di luar genset, listrik dan loader) / 1 bulan / 30 115,000,000.00
Hari

Catatan : Harga Belum Termasuk PPN dan Apabila dikemudian hari terdapat kekeliruan, akan dilakukan revisi /
penyesuaian
RENCANA KESELAMATAN DAN KESEHATAN
KERJA KONTRAK ( RK3K )

HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME SAT
SATUAN HARGA (RP)
1 2 3 4 5 6
1 RK3K
Kelengkapan Pendukung di Lapangan
- Spanduk K3 1.00 bh - -
- Poster K3 1.00 bh - -
- Papan Informasi K3 2.00 bh - -
- Rambu-rambu K3 3.00 bh - -
- Kotak P3K 2.00 set - -
Kelengkapan Pekerja
- Pembuatan Kartu Nama pekerja 10.00 bh - -
- Helm Proyek 10.00 bh - -
- Rompi proyek 10.00 bh - -
- Masker 10.00 bh -
- Kaca Mata pelindung 10.00 bh - -
- Penutup telinga 10.00 Pasang - -
- Sepatu safety 10.00 Pasang - -
- Sarung tangan proyek 10.00 Pasang - -

TOTAL RK3K -
A. SPESIFIKASI BAHAN KONSTRUKSI DAN MEP

Pembangunan / Peningkatan Infrastruktur Gedung Pendidikan


Kegiatan :
Pembangunan Gedung SDN 13 Pedungan (5 RKB, Tangga), Lanjutan
Pekerjaan :
Lokasi : Jl. Gelogor Carik No. 94, Pemogan, Denpasar Selatan
Tahun : 2020

NO JENIS PEKERJAAN SPESIFIKASI TEKNIS MEREK/PABRIKAN

1 2 3 4
I PEKERJAAN PERSIAPAN
1 Papan nama proyek Print out lapis Vinyl Produk Lokal
2 RK3K Mencangkup P3K serta Kelengkapan Bekerja Sesuai ketersediaan dipasaran

II PEKERJAAN STRUKTUR
A Pekerjaan Beton
1 Lantai 1
l Pek. Tangga
Pek Beton K250 Mutu beton K250 Produk Lokal
Pembesian Tangga Ø10 Mutu baja fy=400 N/mm2 Hanil / SNI dengan dukungan sertifikat
Begesting Tebal plywood min. 9 mm Produk Lokal
2 Lantai 2
a Pek. kolom K1 30/40
Beton K250 Mutu beton K250 Produk Lokal
Tulangan pokok D 16 Mutu baja fy=400 N/mm2 Hanil / SNI dengan dukungan sertifikat
Sengkang Ø 8 Mutu baja fy=240 N/mm2 Hanil / SNI dengan dukungan sertifikat
Bekisting Tebal plywood min. 9 mm Produk Lokal
b Pek. kolom K2 30/30
Beton K250 Mutu beton K250 Produk Lokal
Tulangan pokok D 16 Mutu baja fy=400 N/mm2 Hanil / SNI dengan dukungan sertifikat
Sengkang Ø 8 Mutu baja fy=240 N/mm2 Hanil / SNI dengan dukungan sertifikat
Bekisting Tebal plywood min. 9 mm Produk Lokal
c Pek. kolom K3 20/20
Beton K250 Mutu beton K250
Tulangan pokok D 16 Mutu baja fy=400 N/mm2 Hanil / SNI dengan dukungan sertifikat
Sengkang Ø 8 Mutu baja fy=240 N/mm2 Hanil / SNI dengan dukungan sertifikat
Bekisting Tebal plywood min. 9 mm Produk Lokal
d Pek. kolom KP 11/11
Beton K225 Mutu beton K225 Produk Lokal
Tulangan pokok D 10 Mutu baja fy=400 N/mm2 Hanil / SNI dengan dukungan sertifikat
Sengkang Ø 6 Mutu baja fy=240 N/mm2 Hanil / SNI dengan dukungan sertifikat
Bekisting Tebal plywood min. 9 mm Produk Lokal
e Pek. Balok RB 20/30
Beton K250 Mutu beton K225 Produk Lokal
Tulangan pokok D 13 Mutu baja fy=400 N/mm2 Hanil / SNI dengan dukungan sertifikat
Tulangan Sengkang Ø 8 Mutu baja fy=240 N/mm2 Hanil / SNI dengan dukungan sertifikat
Bekisting Tebal plywood min. 9 mm Produk Lokal
3 Pekerjaan Atap Baja Ringan
Galvalume AZ-100, dengan mutu baja G 550 Mpa ex KAGE
a Pek. Atap Baja Ringan Ex. Jaindo Jaindo Bali
Steel

III PEKERJAAN ARSITEKTUR


1 Lantai 1
a Pek. Dinding
Pek. Pas. Dinding Bata Shaft Bata Merah 5 x 10 x 22 cm Produk Lokal pejaten
Pek. Plesteran camp 1 PC : 5 Psr Shaft Camp. 1 Pc : 5 Ps Tebal 15 mm Semen gresik
Pek. Acian dengan PC Tebal acian tidak kurang dari 1 mm Semen gresik
Pek. Pengecatan Interior 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup warna putih Cat Weldon
Pek. Pengecatan Eksterior 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup warna putih Cat Dulux
b Pek. Penutup Lantai
Pek. Pas. Keramik 40x40 cm Keramik Lantai ukuran 40 x 40 warna putih Asia Tile
Pek. Pas. Keramik 20x20 cm Keramik Lantai ukuran 20 x 20 warna putih Asia Tile
Pek. Pas. Keramik 40x40 cm tangga Keramik Lantai ukuran 40 x 40 warna putih Asia Tile
Pek. Pas. Keramik dinding 20x25 cm Keramik Dinding ukuran 20 x 25 Asia Tile
Pek. List Keramik Dinding Toilet List Keramik Dinding ukuran 10 x 20 Asia Tile
Pek. Plin Keramik Lantai Plin Keramik Lantai ukuran 10 x 40 Asia Tile
c Pekerjaan Railling tangga
Pek. Pas. Dinding Bata Railling Tangga Bata Merah 5 x 10 x 22 cm Produk Lokal pejaten
Pek. Plesteran camp 1 PC : 5 Psr Camp. 1 Pc : 5 Ps Tebal 15 mm Semen gresik
Pek. Acian dengan PC Tebal acian tidak kurang dari 1 mm Semen gresik
Pek. Pengecatan 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup warna putih Cat Weldon
d Pekerjaan Plafond
Kalsiboard (4,5 x 1220 x 2420 mm) + Rangka Usuk Kayu Kruing
Pek. Plafond Kalsiboard + rangka kayu Produk Lokal
(jarak 60 x 60 cm)
Pek. List Plafond List Gypsum 2/5 cm Produk Lokal
Pek. Pengecatan Plafond 2 Lapis cat tembok warna putih menggunakan roll Cat Weldon
Pek. Pengecatan list Plafond 2 Lapis cat tembok warna putih menggunakan roll Cat Weldon
f Pekerjaan Lain-lain
Finishing Politur Pintu P2 Politur 2 lapis Impra
Pek. Plesteran pepalihan dinding Camp. 1 Pc : 5 Ps Semen gresik
Pek. Acian plesteran pepalihan dinding Tebal acian tidak kurang dari 1 mm Semen gresik
Pas. Bata Gosok pada pintu Bata Gosok Produk Lokal
Pas. Paras pada pintu Batu Paras Produk Lokal
Pek. Bata Gosok Pilar Style Bali Bata Gosok Produk Lokal
Pek. Pintu Harmonika Pintu Harmonika Besi Produk Lokal
2 Lantai 2
a Pek. Dinding
Pek. Pas. Dinding Bata Bata Merah 5 x 10 x 22 cm Produk Lokal pejaten
Pek. Pas. Dinding Bata Toilet Bata Merah 5 x 10 x 22 cm Produk Lokal pejaten
Pek. Plesteran camp 1 PC : 5 Psr Camp. 1 Pc : 5 Ps Tebal 15 mm Semen gresik
Pek. Acian dengan PC Tebal acian tidak kurang dari 1 mm Semen gresik
Pek. Pengecatan Interior 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup warna putih Cat Weldon
Pek. Pengecatan Eksterior 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup warna putih Cat Dulux
b Pek. Penutup Lantai
Pek. Pas. Keramik 40x40 cm Keramik Lantai ukuran 40 x 40 warna putih Asia Tile
Pek. Pas. Keramik 20x20 cm Keramik Lantai ukuran 20 x 20 warna putih Asia Tile
Pek. Pas. Keramik dinding 20x25 cm Keramik Dinding ukuran 20 x 25 Asia Tile
Pek. List Keramik Dinding Toilet List Keramik Dinding ukuran 10 x 20 Asia Tile
Pek. Plin Keramik Lantai Plin Keramik Lantai ukuran 10 x 40 Asia Tile
c Pekerjaan Plafond + Rangka Kayu
Pek. Plafond Kalsiboard Kalsiboard (4,5 x 1220 x 2420 mm) + Rangka Usuk Kayu Kruing (Produk Lokal
Pek. List Plafond List Gypsum 2/5 cm Produk Lokal
Pek. Pengecatan Plafond 2 Lapis cat tembok warna putih menggunakan roll Cat Weldon
Pek. Pengecatan list Plafond 2 Lapis cat tembok warna putih menggunakan roll Cat Weldon
d Pekerjaan Kusen, Pintu dan Jendela
- Pek. Pas. Pintu P1
Kusen Pintu Kayu Kusen kayu kamper 6/12 cm Produk Lokal
Daun Pintu Kayu Daun Pintu dengan papan kayu kamper Produk Lokal
Finishing Politur Politur 2 lapis Impra
Engsel Pintu Engsel pintu perdaun berisi 3 bh Solid
Kunci Pintu Dan Handle Kunci tanam 2 slag Dekson
- Pek. Pas. Pintu P2
Kusen Pintu Kayu Kusen kayu kamper 6/12 cm Produk Lokal
Daun Pintu Kayu Daun Pintu dengan papan kayu kamper Produk Lokal
Finishing Politur Politur 2 lapis Impra
Engsel Pintu Engsel pintu perdaun berisi 3 bh Solid
Kunci Pintu Dan Handle Kunci tanam 2 slag Dekson
- Pek. Pas. Jendela J1
Kusen Jendela Kayu Kusen kayu kamper 6/12 cm Produk Lokal
Daun Jendela Kayu + Kaca Daun Jendela dengan kayu kamper + kaca 5 mm Produk Lokal
Finishing Politur Politur 2 lapis Impra
Engsel Jendela Engsel Kupu - kupu Solid
Grendel Jendela Grendel jendela biasa Solid
Kait Angin Kait Angin biasa Solid
Pasang Jaro jendela Jaro jendela sesuai gambar dengan kayu kamper Produk Lokal
e Pekerjaan Railling Selasar
Pek. Pas. Dinding Bata Bata Merah 5 x 10 x 22 cm Produk Lokal pejaten
Pek. Plesteran camp 1 PC : 5 Psr Camp. 1 Pc : 5 Ps Semen gresik
Pek. Acian dengan PC Tebal acian tidak kurang dari 1 mm Semen gresik
Pek. Plesteran Pepalihan Camp. 1 Pc : 5 Ps Semen gresik
Pek. Pengecatan Eksterior 1 Lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup warna putih Cat Dulux
Pek. Railling Besi Hollow Railling dengan hollow ukuran 4/4 cm + Cat Hitam
Pas. Roster Beton Roster beton ukuran 20/20 cm Produk Lokal
f Pekerjaan Lain-lain
Pek. Plesteran pepalihan dinding Camp. 1 Pc : 5 Ps Tebal 15 mm Semen gresik
Pek. Acian plesteran pepalihan dinding Tebal acian tidak kurang dari 1 mm Semen gresik
Pas. Bata Gosok pada pintu Bata Gosok Produk Lokal
Pas. Paras pada pintu Batu Paras Produk Lokal
Pek. Bata Gosok Pilar Style Bali Bata Gosok Produk Lokal
Pekerjaan Pagar BRC Pagar BRC t = 1.2 m Ø 6 lengkap dengan tiang Produk Lokal
3 PEKERJAAN ATAP
a Pas.Lisplank double Papan Kayu Kamper Produk Lokal
b Pas. Tatab Papan Kayu Kamper Produk Lokal
c Atap Genteng Goodyear Genteng Good Year Produk Lokal
d Pas. Bubungan atap goodyear Bubungan Good Year Produk Lokal
e Pas. Ikut Celedu Ikut Celedu Paras Produk Lokal
f Pas. Murdha Murda Paras Produk Lokal

IV PEKERJAAN MEP
A PEKERJAAN ELEKTRIKAL LANTAI 1 & 2
1 Pek. Instalasi titik lampu Kabel NYM 3 x 2.5 mm Supreme
2 Pek. Instalasi stop kontak Kabel NYM 3 x 2.5 mm Supreme
3 Pek. Instalasi Pompa Air Kabel NYM 3 x 2.5 mm Supreme
4 Pek. Pasang saklar ganda Saklar Seri / double 2 gang 2 way, 10 A Broco
5 Pek. Pasang Saklar Tunggal Saklar Tunggal / single 1 gang 1 way, 10 A Broco
6 Pek. Pasang Exhause Fan Ceiling Exhaust Fan 50 cfm type sirocco Panasonic
7 Pek.Pas. Lampu TL 2x36 W RMI TL 2 x 36 W recessed mounted Philips
8 Pek.Pas. LED Lampu 13 W Lampu LED Philip 13 watt Philips
9 Pek. Pasang MCB MCB 3 phase 40 A MG Merlin Gerin Domae
10 Penangkal Petir Produk Lokal
- Air terminal penangkal petir c/w tiang galvanized Ø ¾" tiang galvanized Ø ¾ Produk Lokal
Bor tanah untuk grounding dalam 6 m, Blitzem, BC 50 mm², Box
- Grounding penangkal petir Produk Lokal
control,
- Instalasi Grounding BC 50 mm² , conduit Produk Lokal
- Bak Kontrol Penangkal Petir Produk Lokal
11 Pintu Shaft Bahan aluminium Produk Lokal
13 Pek. Pas. Ceilling Speaker Speaker bulat posisi diplafond TOA
14 Pek. Pas. Central Soundsystem Amplifier 120 watt TOA

B PEKERJAAN PLUMBING DAN SANITASI


1 Pas. Pipa diameter 1 dim saluran air bersih Pipa PVC Diameter 1 dim Maspion
2 Pas. Pipa diameter 3 dim saluran air bekas Pipa PVC Diameter 3 dim Maspion
3 Pas.pipa diameter 4 dim pembuangan air kotor Pipa PVC Diameter 4 dim Maspion
4 Pas.Kloset Jongkok Kloset Jongkok Porselin Toto
5 Floordrain Floor Drain Stainless Onda
6 Kran Air Keran Biasa Toto
7 Gate Valve Gate Valve Onda
8 Check Valve Ø 1" Check Valve Ø 1" Onda
9 Pekerjaan Pas. Pompa Air Pompa Booster JP Basic 3 Grundfos
10 Panel Elektrikal Pompa Booster MCB 16 A, MCB 10 S, Pilot Lamp, Fuse-3A, Push Button,dll Standart SNI
9 Pekerjaan Peresapan
- Galian Galian Sedalam 2 m
- Pek. Beton Buis Ø 100 Buis Beton Ø 100 Produk Lokal
- Lapisan ijuk Lapisan ijuk Tebal 10 cm Produk Lokal
- Batu karang + pasir Campuran Batu karang dan Pasir untuk peresapan Produk Lokal
- Urugan Tanah Kembali Urugan tanah kembali beserta pemadatan tanah
- Pas.pipa diameter 4 dim peresapan Pipa PVC Diameter 4 dim Maspion
10 Pekerjaan Septictank
- Galian Galian sedalam 2 m
- Beton Alas Bawah Mutu beton K250 tebal 12 cm Produk Lokal
- Pasir urug Pasir Urug dengan tebal 10 cm Produk Lokal
- Pas. Bata 1 pc : 2 ps Pas. Bata dengan campuran 1 pc : 2 ps Produk Lokal
- Plesteran 1 pc : 5 ps Plestran dengan campuran 1 pc : 5 ps Produk Lokal
- Balok 15/20
- Beton K250 Mutu beton K250 Produk Lokal
- Tulangan tulangan utama 4 ∅ 12 dan begel ∅8 - 20 Hanil / SNI dengan dukungan sertifikat
- Begisting Plywood tebal 9 mm dan Dolken Kayu Ø (8 - 10)cm /4 m Produk Lokal
- Pas.pipa diameter 4 dim Septitank Pipa PVC Diameter 4 dim Maspion
- Beton atas tutup septitank
- Beton K250 Mutu beton K250 Produk Lokal
- Tulangan tulangan dengan besi ∅ 18 - 15 Hanil / SNI dengan dukungan sertifikat
- Begisting Plywood tebal 9 mm dan Dolken Kayu Ø (8 - 10)cm /4 m Produk Lokal
11 Pekerjaan Ground Tank Ground tank Kapasitas 5 m3 Penguin

Denpasar, 2020
Dibuat Oleh :
CV. RUSMA INDAH

I GEDE RUSTIAWAN, ST
Direktur
B. SPESIFIKASI PERALATAN KONSTRUKSI DAN PERALATAN BANGUNAN

Pembangunan / Peningkatan Infrastruktur Gedung Pendidikan


Kegiatan :
Pembangunan Gedung SDN 13 Pedungan (5 RKB, Tangga), Lanjutan
Pekerjaan :
Lokasi : Jl. Gelogor Carik No. 94, Pemogan, Denpasar Selatan
Tahun : 2020

NO JENIS PERALATAN JUMLAH SATUAN KAPASITAS SPESIFIKASI


1 2 3 4 5 6
1 Truck 1 unit 8 m3 Umur kendaraan min 10 thn,kondisi baik,layak jalan
2 Pick Up L 300 Bak 1 unit 3 m3 Umur kendaraan min 10 thn,kondisi baik,layak jalan
3 Bar Cutter / Pemotong Besi 2 bh - Mesin Potong Besi Cut Off Saw 14"
4 Bar Bending / Penekuk Besi 1 bh - Besi Ulir D 19 / D22
5 Mesin Mixer Beton 1 unit 500 ltr/0,5 m3 Merk Dongfeng,Golden
6 Skafolding 100 set 2500 kg/tiang Main frame,brace cross,jackbase,uhead,jointpin,cat walk

Denpasar, 2020
Dibuat Oleh :
CV. RUSMA INDAH

I GEDE RUSTIAWAN, ST
Direktur
KEPEMILIKAN
7
Sewa/Milik Sendiri
Sewa/Milik Sendiri
Sewa/Milik Sendiri
Sewa/Milik Sendiri
Sewa/Milik Sendiri
Sewa/Milik Sendiri

2020

N, ST
C. IDENTIFIKASI BAHAYA KEGIATAN KONSTRUKSI

Pembangunan / Peningkatan Infrastruktur Gedung Pendidikan


Kegiatan :
Pembangunan Gedung SDN 13 Pedungan (5 RKB, Tangga), Lanjutan
Pekerjaan :
Lokasi : Jl. Gelogor Carik No. 94, Pemogan, Denpasar Selatan
Tahun : 2020

NO JENIS PEKERJAAN IDENTIFIKASI BAHAYA

1 2 3
I PEKERJAAN PERSIAPAN
1 Papan nama proyek tangan / kaki terkena paku
2 RK3K

II PEKERJAAN STRUKTUR
A Pekerjaan Beton
1 Lantai 1
l Pek. Tangga
Pek Beton K250 tangan terkena beton cair
Pembesian Tangga Ø10 tertusuk besi, terkena mesin pemotong besi
Begesting tertusuk paku, terkena gergaji kayu
2 Lantai 2
a Pek. kolom K1 30/40
Beton K250 tangan terkena beton cair
Tulangan pokok D 16 tertusuk besi, terkena mesin pemotong besi
Sengkang Ø 8 tertusuk besi, terkena mesin pemotong besi
Bekisting tertusuk paku, terkena gergaji kayu
b Pek. kolom K2 30/30
Beton K250 tangan terkena beton cair
Tulangan pokok D 16 tertusuk besi, terkena mesin pemotong besi
Sengkang Ø 8 tertusuk besi, terkena mesin pemotong besi
Bekisting tertusuk paku, terkena gergaji kayu
c Pek. kolom K3 20/20
Beton K250 tangan terkena beton cair
Tulangan pokok D 16 tertusuk besi, terkena mesin pemotong besi
Sengkang Ø 8 tertusuk besi, terkena mesin pemotong besi
Bekisting tertusuk paku, terkena gergaji kayu
NO JENIS PEKERJAAN IDENTIFIKASI BAHAYA

1 2 3
d Pek. kolom KP 11/11
Beton K225 tangan terkena beton cair
Tulangan pokok D 10 tertusuk besi, terkena mesin pemotong besi
Sengkang Ø 6 tertusuk besi, terkena mesin pemotong besi
Bekisting tertusuk paku, terkena gergaji kayu
e Pek. Balok RB 20/30
Beton K250 tangan terkena beton cair
Tulangan pokok D 13 tertusuk besi, terkena mesin pemotong besi
Tulangan Sengkang Ø 8 tertusuk besi, terkena mesin pemotong besi
Bekisting tertusuk paku, terkena gergaji kayu
3 Pekerjaan Atap Baja Ringan
a Pek. Atap Baja Ringan Ex. Jaindo terjatuh dari ketinggian

III PEKERJAAN ARSITEKTUR


1 Lantai 1
a Pek. Dinding
Pek. Pas. Dinding Bata Shaft tangan/kaki tertimpa bata merah
Pek. Plesteran camp 1 PC : 5 Psr Shaft mata terkena cipratan pasir dan semen
Pek. Acian dengan PC Tangan terkena semen /tergores
Pek. Pengecatan Interior terpapar bau cat dan tangan terkena cat
Pek. Pengecatan Eksterior terpapar bau cat dan tangan terkena cat
b Pek. Penutup Lantai
Pek. Pas. Keramik 40x40 cm tangan/kaki terkena mesin pemotong keramik
Pek. Pas. Keramik 20x20 cm tangan/kaki terkena mesin pemotong keramik
Pek. Pas. Keramik 40x40 cm tangga tangan/kaki terkena mesin pemotong keramik
Pek. Pas. Keramik dinding 20x25 cm tangan/kaki terkena mesin pemotong keramik
Pek. List Keramik Dinding Toilet tangan/kaki terkena mesin pemotong keramik
Pek. Plin Keramik Lantai tangan/kaki terkena mesin pemotong keramik
c Pekerjaan Railling tangga
Pek. Pas. Dinding Bata Railling Tangga tangan/kaki tertimpa bata merah
Pek. Plesteran camp 1 PC : 5 Psr mata terkena cipratan pasir dan semen
Pek. Acian dengan PC tangan terkena semen /tergores
Pek. Pengecatan terpapar bau cat dan tangan terkena cat
d Pekerjaan Plafond
NO JENIS PEKERJAAN IDENTIFIKASI BAHAYA

1 2 3
Pek. Plafond Kalsiboard + rangka kayu terjatuh dari ketinggian
Pek. List Plafond terjatuh dari ketinggian
Pek. Pengecatan Plafond terjatuh dari ketinggian, terpapar bau cat dan tangan terkena cat
Pek. Pengecatan list Plafond terjatuh dari ketinggian, terpapar bau cat dan tangan terkena cat
f Pekerjaan Lain-lain
Finishing Politur Pintu P2 terpapar bau politur, tangan terkena politur
Pek. Plesteran pepalihan dinding mata terkena cipratan pasir dan semen
Pek. Acian plesteran pepalihan dinding tangan terkena semen /tergores
Pas. Bata Gosok pada pintu tangan terkena gerinda
Pas. Paras pada pintu tangan terkena gerinda dan terpapar debu
Pek. Bata Gosok Pilar Style Bali tangan terkena gerinda
Pek. Pintu Harmonika tangan/kaki tertimpa pintu, terpapar bau saat proses pengelasan pintu
2 Lantai 2
a Pek. Dinding
Pek. Pas. Dinding Bata tangan/kaki tertimpa bata merah
Pek. Pas. Dinding Bata Toilet tangan/kaki tertimpa bata merah
Pek. Plesteran camp 1 PC : 5 Psr mata terkena cipratan pasir dan semen
Pek. Acian dengan PC Tangan terkena semen /tergores
Pek. Pengecatan Interior terpapar bau cat dan tangan terkena cat
Pek. Pengecatan Eksterior terpapar bau cat dan tangan terkena cat
b Pek. Penutup Lantai
Pek. Pas. Keramik 40x40 cm tangan/kaki terkena mesin pemotong keramik
Pek. Pas. Keramik 20x20 cm tangan/kaki terkena mesin pemotong keramik
Pek. Pas. Keramik dinding 20x25 cm tangan/kaki terkena mesin pemotong keramik
Pek. List Keramik Dinding Toilet tangan/kaki terkena mesin pemotong keramik
Pek. Plin Keramik Lantai tangan/kaki terkena mesin pemotong keramik
c Pekerjaan Plafond + Rangka Kayu
Pek. Plafond Kalsiboard terjatuh dari ketinggian
Pek. List Plafond terjatuh dari ketinggian
Pek. Pengecatan Plafond terjatuh dari ketinggian, terpapar bau cat dan tangan terkena cat
Pek. Pengecatan list Plafond terjatuh dari ketinggian, terpapar bau cat dan tangan terkena cat
d Pekerjaan Kusen, Pintu dan Jendela
- Pek. Pas. Pintu P1
Kusen Pintu Kayu tangan/kaki tertimpa kusen saat proses pemasangan
NO JENIS PEKERJAAN IDENTIFIKASI BAHAYA

1 2 3
Daun Pintu Kayu tangan/kaki tertimpa kusen saat proses pemasangan
Finishing Politur terpapar bau politur, tangan terkena politur
Engsel Pintu tangan / Kaki tertusuk paku
Kunci Pintu Dan Handle tangan / Kaki tertusuk paku
- Pek. Pas. Pintu P2
Kusen Pintu Kayu tangan/kaki tertimpa kusen saat proses pemasangan
Daun Pintu Kayu tangan/kaki tertimpa kusen saat proses pemasangan
Finishing Politur terpapar bau politur, tangan terkena politur
Engsel Pintu tangan / Kaki tertusuk paku
Kunci Pintu Dan Handle tangan / Kaki tertusuk paku
- Pek. Pas. Jendela J1
Kusen Jendela Kayu tangan/kaki tertimpa kusen saat proses pemasangan
Daun Jendela Kayu + Kaca tangan/kaki tertimpa kusen saat proses pemasangan
Finishing Politur terpapar bau politur, tangan terkena politur
Engsel Jendela tangan / Kaki tertusuk paku
Grendel Jendela tangan / Kaki tertusuk paku
Kait Angin tangan / Kaki tertusuk paku
Pasang Jaro jendela tangan / Kaki tertusuk paku
e Pekerjaan Railling Selasar
Pek. Pas. Dinding Bata tangan/kaki tertimpa bata merah
Pek. Plesteran camp 1 PC : 5 Psr mata terkena cipratan pasir dan semen
Pek. Acian dengan PC Tangan terkena semen /tergores
Pek. Plesteran Pepalihan mata terkena cipratan pasir dan semen
Pek. Pengecatan terpapar bau cat dan tangan terkena cat
Pek. Railling Besi Hollow terpapar bau saat proses pengelasan dan pengecatan
Pas. Roster Beton mata terkena cipratan pasir dan semen
f Pekerjaan Lain-lain
Pek. Plesteran pepalihan dinding mata terkena cipratan pasir dan semen
Pek. Acian plesteran pepalihan dinding tangan terkena semen /tergores
Pas. Bata Gosok pada pintu tangan terkena gerinda
Pas. Paras pada pintu tangan terkena gerinda dan terpapar debu
Pek. Bata Gosok Pilar Style Bali tangan terkena gerinda
Pekerjaan Pagar BRC terpapar bau saat proses pengelasan pagar
3 PEKERJAAN ATAP
NO JENIS PEKERJAAN IDENTIFIKASI BAHAYA

1 2 3
a Pas.Lisplank double terjatuh dari ketinggian
b Pas. Tatab terjatuh dari ketinggian
c Atap Genteng Goodyear terjatuh dari ketinggian
d Pas. Bubungan atap goodyear terjatuh dari ketinggian
e Pas. Ikut Celedu terjatuh dari ketinggian
f Pas. Murdha terjatuh dari ketinggian

IV PEKERJAAN MEP
A PEKERJAAN ELEKTRIKAL LANTAI 1 & 2
1 Pek. Instalasi titik lampu tersengat aliran listrik dan jatuh dari tangga
2 Pek. Instalasi stop kontak tersengat aliran listrik dan jatuh dari tangga
3 Pek. Instalasi Pompa Air tersengat aliran listrik dan jatuh dari tangga
4 Pek. Pasang saklar ganda tersengat aliran listrik dan jatuh dari tangga
5 Pek. Pasang Saklar Tunggal tersengat aliran listrik dan jatuh dari tangga
6 Pek. Pasang Exhause Fan tersengat aliran listrik dan jatuh dari tangga
7 Pek.Pas. Lampu TL 2x36 W tersengat aliran listrik dan jatuh dari tangga
8 Pek.Pas. LED Lampu 13 W tersengat aliran listrik dan jatuh dari tangga
9 Pek. Pasang MCB tersengat aliran listrik dan jatuh dari tangga
10 Penangkal Petir
- Air terminal penangkal petir c/w tiang galvanized Ø ¾" terjatuh dari ketinggian
- Grounding penangkal petir tangan / Kaki tertusuk paku
- Instalasi Grounding tersengat aliran listrik dan jatuh dari tangga
- Bak Kontrol Penangkal Petir tangan / kaki tertusuk paku
11 Pintu Shaft mata terkena cipratan pasir dan semen
13 Pek. Pas. Ceilling Speaker tersengat aliran listrik dan jatuh dari tangga
14 Pek. Pas. Central Soundsystem tersengat aliran listrik dan jatuh dari tangga

B PEKERJAAN PLUMBING DAN SANITASI


1 Pas. Pipa diameter 1 dim saluran air bersih terkena gergaji pemotong pipa
2 Pas. Pipa diameter 3 dim saluran air bekas terkena gergaji pemotong pipa
3 Pas.pipa diameter 4 dim pembuangan air kotor terkena gergaji pemotong pipa
4 Pas.Kloset Jongkok mata terkena cipratan pasir dan semen
5 Floordrain mata terkena cipratan pasir dan semen
6 Kran Air mata terkena cipratan pasir dan semen
NO JENIS PEKERJAAN IDENTIFIKASI BAHAYA

1 2 3
7 Gate Valve mata terkena cipratan pasir dan semen
8 Check Valve Ø 1" mata terkena cipratan pasir dan semen
9 Pekerjaan Pas. Pompa Air mata terkena cipratan pasir dan semen
10 Panel Elektrikal Pompa Booster mata terkena cipratan pasir dan semen
9 Pekerjaan Peresapan
- Galian tangan/kaki terluka terkena skop
- Pek. Beton Buis Ø 100 mata terkena cipratan pasir dan semen
- Lapisan ijuk tangan/kaki terluka pada saat proses pemasangan ijuk
- Batu karang + pasir tangan/kaki terluka pada saat proses pemasangan karang + pasir
- Urugan Tanah Kembali tangan/kaki terluka terkena skop
- Pas.pipa diameter 4 dim peresapan terkena gergaji pemotong pipa
10 Pekerjaan Septictank
- Galian tangan/kaki terluka terkena skop
- Beton Alas Bawah tangan terkena beton cair
- Pasir urug tangan/kaki terluka terkena skop
- Pas. Bata 1 pc : 2 ps tangan/kaki tertimpa bata merah
- Plesteran 1 pc : 5 ps mata terkena cipratan pasir dan semen
- Balok 15/20
- Beton K250 tangan terkena beton cair
- Tulangan tertusuk besi, terkena mesin pemotong besi
- Begisting tertusuk paku, terkena gergaji kayu
- Pas.pipa diameter 4 dim Septitank terkena gergaji pemotong pipa
- Beton atas tutup septitank
- Beton K250 tangan terkena beton cair
- Tulangan tertusuk besi, terkena mesin pemotong besi
- Begisting tertusuk paku, terkena gergaji kayu
11 Pekerjaan Ground Tank tangan tertusuk paku, terkena cipratas semen dan pasir
PENCEGAHAN/PENANGGULANGAN

memakai sepatu safety dan sarung tangan

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
PENCEGAHAN/PENANGGULANGAN

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan

memakai helm, sepatu safety, rompi, dan sarung tangan

memakai sarung tangan dan sepatu safety


memakai kacamata safety
memakai sepatu safety dan sarung tangan.
memakai masker dan sarung tangan
memakai masker dan sarung tangan

memakai sarung tangan dan sepatu safety


memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety

memakai sarung tangan dan sepatu safety


memakai kacamata safety
memakai sepatu safety dan sarung tangan.
memakai masker dan sarung tangan
PENCEGAHAN/PENANGGULANGAN

4
memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, masker, sepatu safety, rompi, dan sarung tangan
memakai helm, masker, sepatu safety, rompi, dan sarung tangan

memakai masker dan sarung tangan


memakai kacamata safety
memakai sepatu safety dan sarung tangan.
memakai sarung tangan dan sepatu safety
memakai masker dan sarung tangan, sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai helm, sepatu safety, rompi, dan sarung tangan

memakai sarung tangan dan sepatu safety


memakai sarung tangan dan sepatu safety
memakai kacamata safety
memakai sepatu safety dan sarung tangan.
memakai masker dan sarung tangan
memakai masker dan sarung tangan

memakai sarung tangan dan sepatu safety


memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety

memakai helm, sepatu safety, rompi, dan sarung tangan


memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, masker, sepatu safety, rompi, dan sarung tangan
memakai helm, masker, sepatu safety, rompi, dan sarung tangan

memakai sarung tangan dan sepatu safety


PENCEGAHAN/PENANGGULANGAN

4
memakai sarung tangan dan sepatu safety
memakai masker dan sarung tangan
memakai sepatu safety dan sarung tangan.
memakai sepatu safety dan sarung tangan.

memakai sarung tangan dan sepatu safety


memakai sarung tangan dan sepatu safety
memakai masker dan sarung tangan
memakai sepatu safety dan sarung tangan.
memakai sepatu safety dan sarung tangan.

memakai sarung tangan dan sepatu safety


memakai sarung tangan dan sepatu safety
memakai masker dan sarung tangan
memakai sepatu safety dan sarung tangan.
memakai sepatu safety dan sarung tangan.
memakai sepatu safety dan sarung tangan.
memakai sepatu safety dan sarung tangan.

memakai sarung tangan dan sepatu safety


memakai kacamata safety
memakai sepatu safety dan sarung tangan.
memakai kacamata safety
memakai masker dan sarung tangan
memakai kacamata safety, masker dan sarung tangan
memakai kacamata safety

memakai kacamata safety


memakai sepatu safety dan sarung tangan.
memakai sarung tangan dan sepatu safety
memakai masker dan sarung tangan, sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai kacamata safety, masker dan sarung tangan
PENCEGAHAN/PENANGGULANGAN

4
memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, sepatu safety, rompi, dan sarung tangan
memakai helm, sepatu safety, rompi, dan sarung tangan

matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan

memakai helm, sepatu safety, rompi, dan sarung tangan


memakai sepatu safety dan sarung tangan.
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
memakai sepatu safety dan sarung tangan.
memakai kacamata safety
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan
matikan arus listrik sementara, memakai helm, sepatu safety, rompi, dan sarung tangan

memakai sarung tangan dan sepatu safety


memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai kacamata safety
memakai kacamata safety
memakai kacamata safety
PENCEGAHAN/PENANGGULANGAN

4
memakai kacamata safety
memakai kacamata safety
memakai kacamata safety
memakai kacamata safety

memakai sarung tangan dan sepatu safety


memakai kacamata safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety

memakai sarung tangan dan sepatu safety


memakai sarung tangan
memakai sarung tangan dan sepatu safety
memakai sarung tangan dan sepatu safety
memakai kacamata safety

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
memakai sarung tangan dan sepatu safety

memakai sarung tangan


memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, dan sarung tangan
memakai sepatu safety, rompi, kacamata safety dan sarung tangan

Denpasar, 2020
Dibuat Oleh :
CV. RUSMA INDAH

I GEDE RUSTIAWAN, ST
Direktur
E. SPESIFIKASI JABATAN KONSTRUKSI

Pembangunan / Peningkatan Infrastruktur Gedung Pendidikan


Kegiatan :
Pembangunan Gedung SDN 13 Pedungan (5 RKB, Tangga), Lanjutan
Pekerjaan :
Lokasi : Jl. Gelogor Carik No. 94, Pemogan, Denpasar Selatan
Tahun : 2020

NO JENIS PERSONIL / JABATAN JUMLAH SATUAN SPESIFIKASI STATUS KEPEGAWAIAN


Pendidikan SMK, Pengalaman Minimal 8 Thn,Memiliki
SKT Pelaksana Bangunan Gedung ( TA 022), dilengkapi
1 Kepala Pelaksana 1 Orang Tetap/ Tidak Tetap
referensi pengalaman kerja dibidang gedung yang
dibuktikan dengan dokumen kontrak.

Pendidikan SMK, Pengalaman Minimal 5 Thn,Memiliki


SKT Pelaksana Bangunan Gedung ( TA 022), dilengkapi
2 Personil K3 1 Orang Tetap/ Tidak Tetap
referensi pengalaman kerja dibidang gedung yang
dibuktikan dengan dokumen kontrak.

Denpasar, 2020
Dibuat Oleh :
CV. RUSMA INDAH

I GEDE RUSTIAWAN, ST
Direktur
DAFTAR ANALISA PEKERJAAN
TAHUN 2020

I HARGA SATUAN PEKERJAAN PERSIAPAN (PERMEN PUPR 28/PRT/M/2016)

4 1 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.10 99,920.00 9,992.00
Tukang kayu OH 0.10 99,920.00 9,992.00
Kepala tukang OH 0.01 99,920.00 999.20
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 21,482.80
B. BAHAN
Kayu balok 5/7 m3 0.012 - -
Paku 2" - 3" Kg 0.02 13,000.00 260.00
Kayu Papan 3/20 m3 0.007 - -
JUMLAH HARGA BAHAN 260.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,742.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 21,742.80

II HARGA SATUAN PEKERJAAN TANAH (PERMEN PUPR 28/PRT/M/2016)


1 1 M3 GALIAN TANAH BIASA DALAM 1 METER
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.750 99,920.00 74,940.00
Mandor OH 0.025 99,920.00 2,498.00
JUMLAH TENAGA KERJA 77,438.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,438.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 77,438.00

2 1 M3 GALIAN TANAH BIASA DALAM 2 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.900 99,920.00 89,928.00
Mandor OH 0.045 99,920.00 4,496.40
JUMLAH TENAGA KERJA 94,424.40
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 94,424.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 94,424.40

3 1 M3 GALIAN TANAH BIASA DALAM 3 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.050 99,920.00 104,916.00
Mandor OH 0.067 99,920.00 6,694.64
JUMLAH TENAGA KERJA 111,610.64
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 111,610.64
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 111,610.64

4 1 M3 GALIAN TANAH KERAS DALAM 1METER


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.000 99,920.00 99,920.00
Mandor OH 0.032 99,920.00 3,197.44
JUMLAH TENAGA KERJA 103,117.44
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 103,117.44
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 103,117.44

5 1 M3 GALIAN TANAH CADAS DALAM 1 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Mandor OH 0.060 99,920.00 5,995.20
JUMLAH TENAGA KERJA 155,875.20
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATANP
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 155,875.20
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 155,875.20

6 1 M3 GALIAN TANAH LUMPUR DALAM 1 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.200 99,920.00 119,904.00
Mandor OH 0.045 99,920.00 4,496.40
JUMLAH TENAGA KERJA 124,400.40
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 124,400.40
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 124,400.40

7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.050 99,920.00 4,996.00
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 5,495.60
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 5,495.60
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 5,495.60

8 1 M3 PEMBUANGAN TANAH SEJAUH 30 METER


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.330 99,920.00 32,973.60
Mandor OH 0.010 99,920.00 999.20
JUMLAH TENAGA KERJA 33,972.80
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,972.80
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 33,972.80

9 1 M3 PENGURUGAN KEMBALI GALIAN TANAH


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500 99,920.00 49,960.00
Mandor OH 0.050 99,920.00 4,996.00
JUMLAH TENAGA KERJA 54,956.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,956.00
E. Overhead & Profit 5 %xD 2,747.80
F. Harga Satuan Pekerjaan (D+E) 57,703.80

10 1 M3 PEMADATAN TANAH ( Per 20 Cm )


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500 99,920.00 49,960.00
Mandor OH 0.050 99,920.00 4,996.00
JUMLAH TENAGA KERJA 54,956.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,956.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 54,956.00

11 1 M3 URUGAN PASIR
HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Mandor OH 0.010 99,920.00 999.20
JUMLAH TENAGA KERJA 30,975.20
B. BAHAN
Pasur Urug m3 1.200 100,000.00 120,000.00
JUMLAH HARGA BAHAN 120,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 150,975.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 150,975.20

12 1 M3 PEMASANGAN LAPISAN PUDEL CAMPURAN 1KP : 3PP : 7TL


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.800 99,920.00 79,936.00
Tukang OH 0.400 99,920.00 39,968.00
Kepala Tukang OH 0.040 99,920.00 3,996.80
Mandor OH 0.080 99,920.00 7,993.60
JUMLAH TENAGA KERJA 131,894.40
B. BAHAN
Kapur Padam m3 0.135 - -
Pasir Pasang m3 0.400 120,000.00 48,000.00
Tanah Liat m3 0.948 - -

JUMLAH HARGA BAHAN 48,000.00


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 179,894.40
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 179,894.40

13 1 M2 PEMASANGAN LAPISAN IJUK TEBAL 10 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150 99,920.00 14,988.00
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 16,486.80
B. BAHAN
Ijuk m3 6.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 16,486.80
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 16,486.80
14 1 M3 URUGAN SIRTU PADAT Untuk Peninggian Lantai Bangunan
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500 99,920.00 24,980.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Sirtu m3 1.200 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 27,478.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 27,478.00

15 1 M3 TIMBUNAN PASIR SEBAGAI BAHAN PENGISI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 99,920.00 40,000.00
Mandor OH 0.0400 130,000.00 5,200.00
JUMLAH TENAGA KERJA 45,200.00
B. BAHAN
Pasir Pasang M3 1.2000 215,000.00 258,000.00
JUMLAH HARGA BAHAN 258,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 303,200.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 303,200.00

III HARGA SATUAN PEKERJAAN PONDASI (PERMEN PUPR 28/PRT/M/2016)


1 1 M3 BATU BELAH CAMP. 1 SP : 3 PP
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland (Gersik) Kg 202.000 - -
Pasir Pasang m3 0.485 120,000.00 58,200.00
JUMLAH HARGA BAHAN 227,611.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 467,419.76
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 467,419.76

2 1 M3 BATU BELAH CAMP. 1 SP : 4 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland (Gersik) Kg 163.000 - -
Pasir Pasang m3 0.520 120,000.00 62,400.00
JUMLAH HARGA BAHAN 231,811.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 471,619.76
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 471,619.76

3 1 M3 BATU BELAH CAMP. 1 SP : 5 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland kg 136.000 1,075.00 146,200.00
Pasir Pasang m3 0.544 120,000.00 65,280.00
JUMLAH HARGA BAHAN 380,891.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 620,699.76
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 620,699.76

4 1 M3 BATU BELAH CAMP. 1 SP : 6 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland kg 117.000 1,075.00 125,775.00
Pasir Pasang m3 0.561 120,000.00 67,320.00
JUMLAH HARGA BAHAN 362,506.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 602,314.76
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 602,314.76

5 1 M3 BATU BELAH CAMP. 1 SP : 8 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland (Gersik) kg 91.000 1,075.00 97,825.00
Pasir Pasang m3 0.584 120,000.00 70,080.00
JUMLAH HARGA BAHAN 337,316.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 577,124.76
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 577,124.76

6 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 1KP : 2PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 99,920.00 119,904.00
Kapur kg 0.170 - -
Semen portland (Gersik) m3 0.170 1,075.00 182.75
Pasir Pasang m3 0.340 120,000.00 40,800.00
JUMLAH HARGA BAHAN 160,886.75
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 400,694.75
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 400,694.75

7 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1SP : 3KP : 10PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 99,920.00 149,880.00
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 239,808.00
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland (Gersik) kg 61.000 1,075.00 65,575.00
Kapur m3 0.147 - -
Pasir Pasang m3 0.492 120,000.00 59,040.00
JUMLAH HARGA BAHAN 294,026.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 533,834.76
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 533,834.76

8 1 M3 PASANGAN PONDASI BATU BELAH CAMPURAN 1/4 SP : 1KP : 4PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.500 141,176.47 211,764.71
Tukang Batu OH 0.750 99,920.00 74,940.00
Kepala Tukang OH 0.075 99,920.00 7,494.00
Mandor OH 0.075 99,920.00 7,494.00
JUMLAH TENAGA KERJA 301,692.71
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Semen portland (Gersik) kg 41.000 1,075.00 44,075.00
Kapur m3 0.131 - -
Pasir Pasang m3 0.523 13,000.00 6,799.00
JUMLAH HARGA BAHAN 220,285.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 521,978.47
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 521,978.47

9 1 M3 PASANGAN PONDASI SIKLOP, 60% BETON CAMPURAN 1 SP : 2 PB : 3 KR DAN 40% BATU BELAH
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 3.400 99,920.00 339,728.00
Tukang Batu OH 0.850 99,920.00 84,932.00
Kepala Tukang OH 0.085 99,920.00 8,493.20
Mandor OH 0.170 99,920.00 16,986.40
JUMLAH TENAGA KERJA 450,139.60
B. BAHAN
Batu Belah m3 0.480 141,176.47 67,764.71
Semen portland (Gersik) kg 194.000 1,075.00 208,550.00
Pasir Beton m3 0.312 120,000.00 37,440.00
Koral Beton m3 0.468 - -
Besi Beton kg 126.000 8,500.00 1,071,000.00
Kawat Beton kg 1.800 13,000.00 23,400.00
JUMLAH HARGA BAHAN 1,408,154.71
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,858,294.31
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 1,858,294.31

10 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 1 M


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.400 99,920.00 239,808.00
Tukang Batu OH 0.800 99,920.00 79,936.00
Kepala Tukang OH 0.080 99,920.00 7,993.60
Mandor OH 0.119 99,920.00 11,890.48
JUMLAH TENAGA KERJA 339,628.08
B. BAHAN
Batu Belah m3 0.4500 141,176.47 63,529.41
Semen portland (Gersik) kg 194.0000 1,075.00 208,550.00
Pasir Beton m3 0.3120 120,000.00 37,440.00
Koral Beton m3 0.4680 - -
JUMLAH HARGA BAHAN 309,519.41
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 649,147.49
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 649,147.49

11 1 M3 PASANGAN BATU KOSONG


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.780 99,920.00 77,937.60
Tukang Batu OH 0.390 99,920.00 38,968.80
Kepala Tukang OH 0.039 99,920.00 3,896.88
Mandor OH 0.039 99,920.00 3,896.88
JUMLAH TENAGA KERJA 124,700.16
B. BAHAN
Batu Belah m3 1.200 141,176.47 169,411.76
Pasir Urug m3 0.432 100,000.00 43,200.00
JUMLAH HARGA BAHAN 212,611.76
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 337,311.92
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 337,311.92

IV PEKERJAAN DINDING (PERMEN PUPR 28/PRT/M/2016))


1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 2 PS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 -
Tukang Batu OH 0.1000 99,920.00 -
Kepala Tukang OH 0.0100 99,920.00 -
Mandor OH 0.0150 99,920.00 -
JUMLAH TENAGA KERJA -
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen kg 18.950 1,075.00 20,371.25
Pasir Pasang m3 0.038 120,000.00 4,560.00
JUMLAH HARGA BAHAN 101,931.25
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 101,931.25
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 101,931.25

1 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 3 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Batu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen kg 14.370 1,075.00 15,447.75
Pasir Pasang m3 0.040 120,000.00 4,800.00
JUMLAH HARGA BAHAN 97,247.75
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 139,713.75
E. Overhead & Profit 5 %xD 6,985.69
F. Harga Satuan Pekerjaan (D+E) 146,699.44

2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 4 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen kg 11.500 1,075.00 12,362.50
Pasir Pasang m3 0.043 120,000.00 5,160.00
JUMLAH HARGA BAHAN 94,522.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 136,988.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 136,988.50

2 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 5 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen kg 9.680 1,075.00 10,406.00
Pasir Pasang m3 0.045 120,000.00 5,400.00
JUMLAH HARGA BAHAN 92,806.00
C. PERALATAN
JUMLAH HARGA ALAT -
D. Jumlah (A + B + C) 135,272.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 135,272.00
3 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 6 PS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen kg 8.320 1,075.00 8,944.00
Pasir Pasang m3 0.049 120,000.00 5,880.00
JUMLAH HARGA BAHAN 91,824.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 134,290.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 134,290.00

4 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 PC : 8 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen kg 6.500 1,075.00 6,987.50
Pasir Pasang m3 0.050 120,000.00 6,000.00
JUMLAH HARGA BAHAN 89,987.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 132,453.50
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 132,453.50

5 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen Portland (Gersik) kg 4.500 1,075.00 4,837.50
Kapur Padam m3 0.015 - -
Pasir Pasang m3 0.050 120,000.00 6,000.00
JUMLAH HARGA BAHAN 87,837.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 130,303.50
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 130,303.50

6 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SP : 3 KP : 10 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen Portland (Gersik) kg 4.500 1,075.00 4,837.50
Kapur Padam m3 0.015 - -
Pasir Pasang m3 0.050 120,000.00 6,000.00
JUMLAH HARGA BAHAN 87,837.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 130,303.50
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 130,303.50

7 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA CAMP. 1 SM : 1 KP : 2 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 70.000 1,100.00 77,000.00
Semen Merah kg 0.014 1,075.00 15.05
Kapur Padam m3 0.014 - -
Pasir Pasang m3 0.028 120,000.00 3,360.00
JUMLAH HARGA BAHAN 80,375.05
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 122,841.05
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 122,841.05

8 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 2 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600 99,920.00 59,952.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.030 99,920.00 2,997.60
JUMLAH TENAGA KERJA 84,932.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000 1,100.00 154,000.00
Semen Portland (Gersik) kg 44.5 1,075.00 47,837.50
Pasir Pasang m3 0.08 120,000.00 9,600.00
JUMLAH HARGA BAHAN 211,437.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 296,369.50
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 296,369.50

9 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600 99,920.00 59,952.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.030 99,920.00 2,997.60
JUMLAH TENAGA KERJA 84,932.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000 1,100.00 154,000.00
Semen Portland (Gersik) kg 32.950 1,075.00 35,421.25
Pasir Pasang m3 0.091 120,000.00 10,920.00
JUMLAH HARGA BAHAN 200,341.25
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 285,273.25
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 285,273.25

10 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 4 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600 99,920.00 59,952.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.030 99,920.00 2,997.60
JUMLAH TENAGA KERJA 84,932.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000 1,100.00 154,000.00
Semen Portland (Gersik) kg 26.550 1,075.00 28,541.25
Pasir Pasang m3 0.093 120,000.00 11,160.00
JUMLAH HARGA BAHAN 193,701.25
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 278,633.25
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 278,633.25

11 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 5 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600 99,920.00 59,952.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.030 99,920.00 2,997.60
JUMLAH TENAGA KERJA 84,932.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000 1,100.00 154,000.00
Semen Portland (Gersik) kg 22.200 1,075.00 23,865.00
Pasir Pasang m3 0.102 120,000.00 12,240.00
JUMLAH HARGA BAHAN 190,105.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 275,037.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 275,037.00

12 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 6 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600 99,920.00 59,952.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.030 99,920.00 2,997.60
JUMLAH TENAGA KERJA 84,932.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000 1,100.00 154,000.00
Semen Portland (Gersik) kg 18.500 1,075.00 19,887.50
Pasir Pasang m3 0.122 120,000.00 14,640.00
JUMLAH HARGA BAHAN 188,527.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 273,459.50
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 273,459.50

13 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA CAMP. 1 SP : 3 KP : 10 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.600 99,920.00 59,952.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.030 99,920.00 2,997.60
JUMLAH TENAGA KERJA 84,932.00
B. BAHAN
Bata Merah 5 x 11 x 22 cm bh 140.000 1,100.00 154,000.00
Semen Portland (Gersik) kg 10.080 1,075.00 10,836.00
Kapur padam m3 0.0275 - -
Pasir Pasang m3 0.0925 120,000.00 11,100.00
JUMLAH HARGA BAHAN 175,936.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 260,868.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 260,868.00

14 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 pc : 3 ps


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Batu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
HB-20 bh 12.5000 2,000.00 25,000.00
Semen Portland (Gersik) Kg 30.320 1,075.00 32,594.00
Pasir Pasang m3 0.7280 120,000.00 87,360.00
Besi Beton 8 mm kg 0.2800 8,500.00 2,380.00
JUMLAH HARGA BAHAN 147,334.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 189,800.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 189,800.00

15 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 20), campuran spesi 1 psp : 4 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Batu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
HB-20 bh 12.5000 2,000.00 25,000.00
Semen Portland (Gersik) Kg 24.260 1,075.00 26,079.50
Pasir Pasang m3 0.7720 120,000.00 92,640.00
Besi Beton 8 mm kg 0.2800 8,500.00 2,380.00
JUMLAH HARGA BAHAN 146,099.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 188,565.50
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 188,565.50

16 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 3 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Batu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
HB-15 bh 22.7400 2,000.00 45,480.00
Semen Portland (Gersik) Kg 22.740 1,075.00 24,445.50
Pasir Pasang m3 0.550 120,000.00 66,000.00
Besi Beton 8 mm kg 0.2800 8,500.00 2,380.00
JUMLAH HARGA BAHAN 138,305.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 180,771.50
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 180,771.50

17 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 15), campuran spesi 1 psp : 4 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Batu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
HB-15 bh 22.7400 2,000.00 45,480.00
Semen Portland (Gersik) Kg 18.200 1,075.00 19,565.00
Pasir Pasang m3 0.582 120,000.00 69,840.00
Besi Beton 8 mm kg 0.280 8,500.00 2,380.00
JUMLAH HARGA BAHAN 137,265.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 179,731.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 179,731.00

18 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 3 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
HB-15 bh 12.5000 2,000.00 25,000.00
Semen Portland (Gersik) Kg 15.160 1,075.00 16,297.00
Pasir Pasang m3 0.364 120,000.00 43,680.00
Besi Beton 8 mm kg 0.280 8,500.00 2,380.00
JUMLAH HARGA BAHAN 87,357.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 129,823.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 129,823.00

19 1 M2 PASANGAN DINDING BATAKO / HOLLOWBLOCK (HB. 10), campuran spesi 1 psp : 4 pp


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
HB-15 bh 12.5000 2,000.00 25,000.00
Semen Portland (Gersik) Kg 15.160 1,075.00 16,297.00
Pasir Pasang m3 0.364 120,000.00 43,680.00
Besi Beton 8 mm kg 0.280 8,500.00 2,380.00
JUMLAH HARGA BAHAN 87,357.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 129,823.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 129,823.00
3 1 M2 PASANGAN ROSTER camp 1 Pc : 3 Ps
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 -
Tukang Batu OH 0.100 99,920.00 -
Kepala Tukang OH 0.010 99,920.00 -
Mandor OH 0.015 99,920.00 -
JUMLAH TENAGA KERJA -
B. BAHAN
Roster Beton bh 30.000 - -
Semen Portland (Gersik) kg 11.000 1,075.00 11,825.00
Pasir Pasang m3 0.035 120,000.00 4,200.00
JUMLAH HARGA BAHAN 16,025.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 16,025.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 16,025.00

4 1 M2 PASANGAN DINDING Terawang/Roster (12 x 11 x 24) CM camp 1 Pc : 4 Ps


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata roster bh 30.000 - -
Semen Portland (Gersik) kg 11.000 1,075.00 11,825.00
Pasir Pasang m3 0.035 120,000.00 4,200.00
JUMLAH HARGA BAHAN 16,025.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 58,491.00
E. Overhead & Profit 5 %xD 2,924.55
F. Harga Satuan Pekerjaan (D+E) 61,415.55

5 1 M2 PASANGAN DINDING Bata Berongga Ekspose (12 x 11 x 24) CM camp 1 Pc : 3 PP


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Bata berongga bh 30.000 - -
Semen Portland (Gersik) kg 11.000 1,075.00 11,825.00
Pasir Pasang m3 0.035 120,000.00 4,200.00
JUMLAH HARGA BAHAN 16,025.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 58,491.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 58,491.00

6 1 M2 PASANGAN DINDING BATA RINGAN TEBAL 7.5 CM DENGAN MORTAR SIAP PAKAI
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.670 99,920.00 66,946.40
Tukang Batu OH 1.300 99,920.00 129,896.00
Kepala Tukang OH 0.13 99,920.00 12,989.60
Mandor OH 0.003 99,920.00 299.76
JUMLAH TENAGA KERJA 210,131.76
B. BAHAN
Bata ringan tebal 7,5 cm bh 8.400 - -
Mortar siap pakai kg 0.473 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan % 10
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 210,131.76
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 210,131.76

7 1 M2 PASANGAN DINDING BATA RINGAN TEBAL 10 CM DENGAN MORTAR SIAP PAKAI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.670 99,920.00 66,946.40
Tukang Batu OH 1.300 99,920.00 129,896.00
Kepala Tukang OH 0.13 99,920.00 12,989.60
Mandor OH 0.003 99,920.00 299.76
JUMLAH TENAGA KERJA 210,131.76
B. BAHAN
Bata ringan tebal 10 cm bh 8.400 - -
Mortar siap pakai kg 0.063 99,920.00 6,294.96
JUMLAH HARGA BAHAN 6,294.96
C. PERALATAN
Peralatan % 10
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 216,426.72
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 216,426.72

V PEKERJAAN PLESTERAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PLESTERAN CAMP. 1 PC : 1 PP TEBAL 15 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 15.504 1,075.00 16,666.80
Pasir Pasang m3 0.016 120,000.00 1,920.00
JUMLAH HARGA BAHAN 18,586.80
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 66,548.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 66,548.40

2 1 M2 PLESTERAN CAMP. 1 PC : 2 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 10.224 1,075.00 10,990.80
Pasir Pasang m3 0.020 120,000.00 2,400.00
JUMLAH HARGA BAHAN 13,390.80
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 61,352.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 61,352.40
3 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 15 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 7.776 1,075.00 8,359.20
Pasir Pasang m3 0.023 120,000.00 2,760.00
JUMLAH HARGA BAHAN 11,119.20
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 59,080.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 59,080.80

4 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 6.240 1,075.00 6,708.00
Pasir Pasang m3 0.024 120,000.00 2,880.00
JUMLAH HARGA BAHAN 9,588.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 57,549.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 57,549.60

5 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 5.184 1,075.00 5,572.80
Pasir Pasang m3 0.026 120,000.00 3,120.00
JUMLAH HARGA BAHAN 8,692.80
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 56,654.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 56,654.40
G. Plesteran Pepalihan (50 % x E )+ E 84,981.60

6 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 4.416 1,075.00 4,747.20
Pasir Pasang m3 0.027 120,000.00 3,240.00
JUMLAH HARGA BAHAN 7,987.20
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 55,948.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 55,948.80

7 1 M2 PLESTERAN CAMP. 1 PC : 7 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 3.936 1,075.00 4,231.20
Pasir Pasang m3 0.028 120,000.00 3,360.00
JUMLAH HARGA BAHAN 7,591.20
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 55,552.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 55,552.80

8 1 M2 PLESTERAN CAMP. 1 PC : 8 PS TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 3.456 1,075.00 3,715.20
Pasir Pasang m3 0.029 120,000.00 3,480.00
JUMLAH HARGA BAHAN 7,195.20
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 55,156.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 55,156.80

9 1 M2 PLESTERAN CAMP. 1 PC : 2PP TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.400 99,920.00 39,968.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.022 99,920.00 2,198.24
JUMLAH TENAGA KERJA 64,148.64
B. BAHAN
Semen Portland (Gersik) Kg 13.632 1,075.00 14,654.40
Pasir Pasang m3 0.027 120,000.00 3,240.00
JUMLAH HARGA BAHAN 17,894.40
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 82,043.04
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 82,043.04

10 1 M2 PLESTERAN CAMP. 1 PC : 3PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.260 99,920.00 25,979.20
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 49,260.56
B. BAHAN
Semen Portland (Gersik) kg 10.368 1,075.00 11,145.60
Pasir Pasang m3 0.031 120,000.00 3,720.00
JUMLAH HARGA BAHAN 14,865.60
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 64,126.16
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 64,126.16

11 1 M2 PLESTERAN CAMP. 1 PC : 3 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 99,920.00 39,968.00
Tukang Batu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0130 99,920.00 1,298.96
JUMLAH TENAGA KERJA 63,249.36
B. BAHAN
Semen Portland (Gersik) kg 10.3680 1,075.00 11,145.60
Pasir Pasang m3 0.0310 120,000.00 3,720.00
JUMLAH HARGA BAHAN 14,865.60
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 78,114.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 78,114.96

12 1 M2 PLESTERAN CAMP. 1 PC : 4 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.400 99,920.00 39,968.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.022 99,920.00 2,198.24
JUMLAH TENAGA KERJA 64,148.64
B. BAHAN
Semen Portland (Gersik) kg 8.320 1,075.00 8,944.00
Pasir Pasang m3 0.032 120,000.00 3,840.00
JUMLAH HARGA BAHAN 12,784.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 76,932.64
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 76,932.64

13 1 M2 PLESTERAN CAMP. 1 PC : 5 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 99,920.00 39,968.00
Tukang Batu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0220 99,920.00 2,198.24
JUMLAH TENAGA KERJA 64,148.64
B. BAHAN
Semen Portland (Gersik) kg 6.9120 1,075.00 7,430.40
Pasir Pasang m3 0.0350 120,000.00 4,200.00
JUMLAH HARGA BAHAN 11,630.40
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 75,779.04
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 75,779.04

14 1 M2 PLESTERAN CAMP. 1 PC : 6 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 99,920.00 39,968.00
Tukang Batu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0220 99,920.00 2,198.24
JUMLAH TENAGA KERJA 64,148.64
B. BAHAN
Semen Portland (Gersik) kg 5.8880 1,075.00 6,329.60
Pasir Pasang m3 0.0360 120,000.00 4,320.00
JUMLAH HARGA BAHAN 10,649.60
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 74,798.24
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 74,798.24

15 1 M2 PLESTERAN CAMP. 1 PC : 1 KP : 2 PS TEBAL 20 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 99,920.00 39,968.00
Tukang Batu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0220 99,920.00 2,198.24
JUMLAH TENAGA KERJA 64,148.64
B. BAHAN
Semen Portland (Gersik) kg 5.8880 1,075.00 6,329.60
Pasir Pasang m3 0.0360 120,000.00 4,320.00
JUMLAH HARGA BAHAN 10,649.60
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 74,798.24
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 74,798.24

16 1 M2 PLESTERAN BERAPEN 1 PS : 5PP TEBAL 15 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150 99,920.00 14,988.00
Tukang Batu OH 0.075 99,920.00 7,494.00
Kepala Tukang OH 0.008 99,920.00 799.36
Mandor OH 0.008 99,920.00 799.36
JUMLAH TENAGA KERJA 24,080.72
B. BAHAN
Semen Portland (Gersik) kg 5.184 1,075.00 5,572.80
Pasir Pasang m3 0.026 120,000.00 3,120.00
JUMLAH HARGA BAHAN 8,692.80
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 32,773.52
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 32,773.52

17 1 M' PLESTERAN SKONING 1 PC : 3 PS, TEBAL 10 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.080 99,920.00 7,993.60
Tukang Batu OH 0.400 99,920.00 39,968.00
Kepala Tukang OH 0.040 99,920.00 3,996.80
Mandor OH 0.004 99,920.00 399.68
JUMLAH TENAGA KERJA 52,358.08
B. BAHAN
Semen Portland (Gersik) kg 0.500 1,075.00 537.50
Pasir Pasang m3 0.013 120,000.00 1,560.00
JUMLAH HARGA BAHAN 2,097.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,455.58
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 54,455.58

18 1 M2 PLESTERAN GRANIT 1 SP : 2 GRANIT TEBAL 1 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.450 99,920.00 44,964.00
Tukang Batu OH 0.225 99,920.00 22,482.00
Kepala Tukang OH 0.023 99,920.00 2,298.16
Mandor OH 0.023 99,920.00 2,298.16
JUMLAH TENAGA KERJA 72,042.32
B. BAHAN
Semen Portland (Gersik) Kg 10.000 1,075.00 10,750.00
Batu Granit Kg 15.000 120,000.00 1,800,000.00
JUMLAH HARGA BAHAN 1,810,750.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,882,792.32
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 1,882,792.32

19 1 M2 PLESTERAN TRASO 1 SP : 2 TRASO TEBAL 1 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.450 99,920.00 44,964.00
Tukang Batu OH 0.225 99,920.00 22,482.00
Kepala Tukang OH 0.023 99,920.00 2,298.16
Mandor OH 0.023 99,920.00 2,298.16
JUMLAH TENAGA KERJA 72,042.32
B. BAHAN
Semen Portland (Gersik) Kg 10.000 1,075.00 10,750.00
Batu Granit Kg 15.000 120,000.00 1,800,000.00
JUMLAH HARGA BAHAN 1,810,750.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,882,792.32
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 1,882,792.32

20 1 M2 PLESTERAN CIPRAT 1 PC : 2 PS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,466.00
B. BAHAN
Semen Portland (Gersik) kg 4.320 1,075.00 4,644.00
Pasir Pasang m3 0.006 120,000.00 720.00
JUMLAH HARGA BAHAN 5,364.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 47,830.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 47,830.00
21 1 M2 FINISHING SIAR PASANGAN DINDING BATA MERAH
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150 99,920.00 14,988.00
Tukang Batu OH 0.075 99,920.00 7,494.00
Kepala Tukang OH 0.008 99,920.00 799.36
Mandor OH 0.008 99,920.00 799.36
JUMLAH TENAGA KERJA 24,080.72
B. BAHAN
Semen Portland (Gersik) kg 3.108 1,075.00 3,341.10
JUMLAH HARGA BAHAN 3,341.10
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 27,421.82
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 27,421.82

22 1 M2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.070 99,920.00 6,994.40
Tukang Batu OH 0.035 99,920.00 3,497.20
Kepala Tukang OH 0.004 99,920.00 399.68
Mandor OH 0.004 99,920.00 399.68
JUMLAH TENAGA KERJA 11,290.96
B. BAHAN
Semen Portland (Gersik) kg 1.600 1,075.00 1,720.00
JUMLAH HARGA BAHAN 1,720.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 13,010.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 13,010.96

23 1 M2 FINISHING SIAR PASANGAN BATU KALI ADUKAN 1PC : 2 PS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Batu OH 0.150 99,920.00 14,988.00
Kepala Tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 47,961.60
B. BAHAN
Semen Portland (Gersik) kg 6.340 1,075.00 6,815.50
Pasir Pasang m3 0.012 120,000.00 1,440.00
JUMLAH HARGA BAHAN 8,255.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 56,217.10
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 56,217.10

24 1 M2 PLESTERAN MENGGUNAKAN SEMEN MU - 301, TEBAL 10 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.400 99,920.00 39,968.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.022 99,920.00 2,198.24
JUMLAH TENAGA KERJA 64,148.64
B. BAHAN
Semen MU-301 kg 2.00 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 64,148.64
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 64,148.64

25 1 M2 ACIAN MENGGUNAKAN SEMEN MU - 200,TEBAL 1,5MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.400 99,920.00 39,968.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.022 99,920.00 2,198.24
JUMLAH TENAGA KERJA 64,148.64
B. BAHAN
Semen MU-200 kg 3.500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 64,148.64
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 64,148.64
6 1 M2 PEKERJAAN ACIAN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.200 99,920.00 19,984.00
Tukang Batu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.01 99,920.00 999.20
Mandor OH 0.01 99,920.00 999.20
JUMLAH TENAGA KERJA 31,974.40
B. BAHAN
Semen Portland kg 3.25 1,075.00 3,493.75
JUMLAH HARGA BAHAN 3,493.75
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 35,468.15
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 35,468.15

VI PEKERJAAN KAYU (PERMEN PUPR 28/PRT/M/2016)


7 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS I
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 7.0000 99,920.00 699,440.00
Tukang kayu OH 21.0000 99,920.00 2,098,320.00
Kepala Tukang OH 2.1000 99,920.00 209,832.00
Mandor OH 0.3500 99,920.00 34,972.00
JUMLAH TENAGA KERJA 3,042,564.00
B. BAHAN
Balok Kayu Kamper m3 1.1000 - -
Paku 10 Cm Kg 1.2500 13,000.00 16,250.00
Lem Kayu Kg 1.0000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 28,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 3,070,814.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 3,070,814.00
2 MEMBUAT DAN MEMASANG 1 M3 KUSEN PINTU DAN JENDELA KAYU KELAS III
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 6.0000 99,920.00 599,520.00
Tukang kayu OH 18.0000 99,920.00 1,798,560.00
Kepala Tukang OH 1.8000 99,920.00 179,856.00
Mandor OH 0.3000 99,920.00 29,976.00
JUMLAH TENAGA KERJA 2,607,912.00
B. BAHAN
Balok Kayu Kruing m3 1.2000 - -
Paku 10 Cm Kg 1.2500 13,000.00 16,250.00
Lem Kayu Kg 1.0000 12,000.00 12,000.00
JUMLAH HARGA BAHAN 28,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 2,636,162.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 2,636,162.00

3 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP STANDAR KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3500 99,920.00 34,972.00
Tukang kayu OH 1.0500 99,920.00 104,916.00
Kepala Tukang OH 0.1050 99,920.00 10,491.60
Mandor OH 0.0180 99,920.00 1,798.56
JUMLAH TENAGA KERJA 152,178.16
B. BAHAN
Papan Kayu Kamper m3 0.0400 7,000,000.00 280,000.00
Paku 5-7 Cm Kg 0.0500 13,000.00 650.00
JUMLAH HARGA BAHAN 280,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 432,828.16
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 432,828.16

4 MEMBUAT DAN MEMASANG 1 M2 PINTU KLAMP SEDERHANA KAYU KELAS III


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3500 99,920.00 34,972.00
Tukang kayu OH 1.0500 99,920.00 104,916.00
Kepala Tukang OH 0.1050 99,920.00 10,491.60
Mandor OH 0.0180 99,920.00 1,798.56
JUMLAH TENAGA KERJA 152,178.16
B. BAHAN
Papan Kayu Kruing m3 0.0400 - -
Paku 5-7 Cm Kg 0.0500 13,000.00 650.00
JUMLAH HARGA BAHAN 650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 152,828.16
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 152,828.16

8 MEMBUAT DAN MEMASANG 1 M2 DAUN PINTU PANEL KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000 99,920.00 99,920.00
Tukang kayu OH 3.0000 99,920.00 299,760.00
Kepala Tukang OH 0.3000 99,920.00 29,976.00
Mandor OH 0.0500 99,920.00 4,996.00
JUMLAH TENAGA KERJA 434,652.00
B. BAHAN
Papan Kayu Kamper m3 0.0400 7,000,000.00 280,000.00
Lem Kayu Kg 0.5000 12,000.00 6,000.00
JUMLAH HARGA BAHAN 286,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 720,652.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 720,652.00

6 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA KACA, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000 99,920.00 79,936.00
Tukang kayu OH 2.4000 99,920.00 239,808.00
Kepala Tukang OH 0.2400 99,920.00 23,980.80
Mandor OH 0.0400 99,920.00 3,996.80
JUMLAH TENAGA KERJA 347,721.60
B. BAHAN
Papan Kayu Kamper m3 0.0240 7,000,000.00 168,000.00
Lem Kayu Kg 0.3000 12,000.00 3,600.00
JUMLAH HARGA BAHAN 171,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 519,321.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 519,321.60

9 MEMBUAT DAN MEMASANG 1 M2 DAUN JENDELA KACA, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.0000 99,920.00 199,840.00
Tukang kayu OH 6.0000 99,920.00 599,520.00
Kepala Tukang OH 0.6000 99,920.00 59,952.00
Mandor OH 0.1000 99,920.00 9,992.00
JUMLAH TENAGA KERJA 869,304.00
B. BAHAN
Papan Kayu Kamper m3 0.0150 - -
Kaca 5 mm m2 0.8000 220,000.00 176,000.00
Paku List Kg 0.1000 - -
JUMLAH HARGA BAHAN 176,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,045,304.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 1,045,304.00
7 MEMBUAT DAN MEMASANG 1 M2 PINTU DAN JENDELA JALUSI, KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000 99,920.00 99,920.00
Tukang kayu OH 3.0000 99,920.00 299,760.00
Kepala Tukang OH 0.3000 99,920.00 29,976.00
Mandor OH 0.0500 99,920.00 4,996.00
JUMLAH TENAGA KERJA 434,652.00
B. BAHAN
Papan Kayu Kamper m3 0.0640 7,000,000.00 448,000.00
Lem Kayu Kg 0.5000 12,000.00 6,000.00
JUMLAH HARGA BAHAN 454,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 888,652.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 888,652.00

8 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA TERTUTUP, KAYU KELAS II (Lebar Sampai 90 Cm)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000 99,920.00 69,944.00
Tukang kayu OH 2.1000 99,920.00 209,832.00
Kepala Tukang OH 0.2100 99,920.00 20,983.20
Mandor OH 0.0350 99,920.00 3,497.20
JUMLAH TENAGA KERJA 304,256.40
B. BAHAN
Papan Kayu Kamper m3 0.0250 7,000,000.00 175,000.00
Paku 1-2,5 Cm Kg 0.0300 13,000.00 390.00
Lem Kayu Kg 0.5000 12,000.00 6,000.00
Plywood 4 mm Lbr 1.0000 - -
JUMLAH HARGA BAHAN 181,390.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 485,646.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 485,646.40

9 MEMBUAT 1 M2 DAUN PINTU PLYWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000 99,920.00 79,936.00
Tukang kayu OH 2.4000 99,920.00 239,808.00
Kepala Tukang OH 0.2400 99,920.00 23,980.80
Mandor OH 0.0400 99,920.00 3,996.80
JUMLAH TENAGA KERJA 347,721.60
B. BAHAN
Papan Kayu Kamper m3 0.0256 7,000,000.00 179,200.00
Paku 1-2,5 Cm Kg 0.0300 13,000.00 390.00
Lem Kayu Kg 0.5000 12,000.00 6,000.00
Plywood 4 mm Lbr 1.0000 - -
JUMLAH HARGA BAHAN 185,590.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 533,311.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 533,311.60

10 MEMASANG 1 M2 JALUSI KUSEN, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6700 99,920.00 66,946.40
Tukang kayu OH 2.0000 99,920.00 199,840.00
Kepala Tukang OH 0.2000 99,920.00 19,984.00
Mandor OH 0.3350 99,920.00 33,473.20
JUMLAH TENAGA KERJA 320,243.60
B. BAHAN
Papan Kayu Kamper m3 0.0600 7,000,000.00 420,000.00
Paku 1-2,5 Cm Kg 0.1500 13,000.00 1,950.00
JUMLAH HARGA BAHAN 421,950.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 742,193.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 742,193.60

11 MEMBUAT 1 M2 TEAKWOOD RANGKAP RANGKA EXPOSE, KAYU KELAS I


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000 99,920.00 79,936.00
Tukang kayu OH 2.4000 99,920.00 239,808.00
Kepala Tukang OH 0.2400 99,920.00 23,980.80
Mandor OH 0.0400 99,920.00 3,996.80
JUMLAH TENAGA KERJA 347,721.60
B. BAHAN
Papan Kayu Jati m3 0.0250 - -
Paku 1-2,5 Cm Kg 0.0300 13,000.00 390.00
Lem Kayu Kg 0.3000 12,000.00 3,600.00
Teakwood 4 mm uk 90x220 cm Lbr 1.0000 - -
JUMLAH HARGA BAHAN 3,990.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 351,711.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 351,711.60

12 MEMBUAT 1 M2 TEAKWOOD RANGKAP LAPIS FORMIKA RANGKA EXPOSE, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8500 99,920.00 84,932.00
Tukang kayu OH 2.5500 99,920.00 254,796.00
Kepala Tukang OH 0.2550 99,920.00 25,479.60
Mandor OH 0.0430 99,920.00 4,296.56
JUMLAH TENAGA KERJA 369,504.16
B. BAHAN
Papan Kayu Kamper m3 0.0250 7,000,000.00 175,000.00
Paku 1-2,5 Cm Kg 0.0300 13,000.00 390.00
Lem Kayu Kg 0.8000 12,000.00 9,600.00
Teakwood 4 mm uk 90x220 cm Lbr 1.0000 - -
Formika Lbr 0.5000 - -
JUMLAH HARGA BAHAN 184,990.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 554,494.16
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 554,494.16

13 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS II Bentang 6 M'


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 4.0000 99,920.00 399,680.00
Tukang kayu OH 12.0000 99,920.00 1,199,040.00
Kepala Tukang OH 1.2000 99,920.00 119,904.00
Mandor OH 0.2000 99,920.00 19,984.00
JUMLAH TENAGA KERJA 1,738,608.00
B. BAHAN
Balok Kayu Kamper m3 1.1000 - -
Besi Strip Tebal 5 cm Kg 15.0000 - -
Paku 12 Cm Kg 5.6000 13,000.00 72,800.00
JUMLAH HARGA BAHAN 72,800.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,811,408.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 1,811,408.00

14 MEMASANG 1 M3 KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 6.7000 99,920.00 669,464.00
Tukang kayu OH 20.1000 99,920.00 2,008,392.00
Kepala Tukang OH 2.0100 99,920.00 200,839.20
Mandor OH 0.3350 99,920.00 33,473.20
JUMLAH TENAGA KERJA 2,912,168.40
B. BAHAN
Balok Kayu Jati m3 1.2000 - -
Besi Strip Tebal 5 cm Kg 15.0000 - -
Paku 12 Cm Kg 5.6000 13,000.00 72,800.00
JUMLAH HARGA BAHAN 72,800.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 2,984,968.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 2,984,968.40

15 MEMASANG 1 M3 KONSTRUKSI GORDENG, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.4000 99,920.00 239,808.00
Tukang kayu OH 7.2000 99,920.00 719,424.00
Kepala Tukang OH 0.7200 99,920.00 71,942.40
Mandor OH 0.1200 99,920.00 11,990.40
JUMLAH TENAGA KERJA 1,043,164.80
B. BAHAN
Balok Kayu Jati m3 1.1000 - -
Besi Strip Tebal 5 cm Kg 15.0000 - -
Paku 12 Cm Kg 3.0000 13,000.00 39,000.00
JUMLAH HARGA BAHAN 39,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,082,164.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 1,082,164.80

16 MEMASANG 1 M2 RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang kayu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 21,482.80
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0140 - -
Reng ( 2 x 3 ) Cm m3 0.0036 - -
Paku 5 Cm dan 10 Cm Kg 0.2500 13,000.00 3,250.00
JUMLAH HARGA BAHAN 3,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 24,732.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 24,732.80

17 MEMASANG 1 M2 RANGKA ATAP GENTENG BETON, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang kayu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 21,482.80
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0140 - -
Reng ( 2 x 3 ) Cm Kg 0.0072 - -
Paku 5 Cm dan 10 Cm Kg 0.2500 13,000.00 3,250.00
JUMLAH HARGA BAHAN 3,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 24,732.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 24,732.80

18 MEMASANG 1 M2 USUK EXPOSE KAYU KLS I KAMPER


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang kayu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 21,482.80
B. BAHAN
Usuk ( 5 x 7 ) Cm m3 0.0105 - -
Paku 5 Cm dan 10 Cm Kg 0.2500 13,000.00 3,250.00
JUMLAH HARGA BAHAN 3,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 24,732.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 24,732.80

19 MEMASANG 1 M2 RENG KAYU KLS I KAMPER


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang kayu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 21,482.80
B. BAHAN
Reng ( 2 x 3 ) Cm m3 0.0036 - -
Paku 5 Cm dan 10 Cm Kg 0.2500 13,000.00 3,250.00
JUMLAH HARGA BAHAN 3,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 24,732.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 24,732.80

20 MEMASANG 1 M2 RANGKA ATAP SIRAP, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1200 99,920.00 11,990.40
Tukang kayu OH 0.1200 99,920.00 11,990.40
Kepala Tukang OH 0.0120 99,920.00 1,199.04
Mandor OH 0.0060 99,920.00 599.52
JUMLAH TENAGA KERJA 25,779.36
B. BAHAN
Balok Kayu Kamper m3 0.1650 - -
Paku 5 Cm dan 10 Cm Kg 0.2000 13,000.00 2,600.00
JUMLAH HARGA BAHAN 2,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 28,379.36
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 28,379.36
21 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (50 X 100), KAYU KELAS II
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang kayu OH 0.3000 99,920.00 29,976.00
Kepala Tukang OH 0.0300 99,920.00 2,997.60
Mandor OH 0.0750 99,920.00 7,494.00
JUMLAH TENAGA KERJA 55,455.60
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0154 - -
Paku 7 Cm dan 10 Cm Kg 0.2000 13,000.00 2,600.00
JUMLAH HARGA BAHAN 2,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 58,055.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 58,055.60

22 MEMASANG 1 M2 RANGKA LANGIT-LANGIT (60 X 60) CM, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 99,920.00 19,984.00
Tukang kayu OH 0.3000 99,920.00 29,976.00
Kepala Tukang OH 0.0300 99,920.00 2,997.60
Mandor OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 53,956.80
B. BAHAN
Kaso-Kaso ( 5 x 7 ) Cm m3 0.0163 - -
Paku 7 Cm dan 10 Cm Kg 0.2500 13,000.00 3,250.00
JUMLAH HARGA BAHAN 3,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 57,206.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 57,206.80

23 MEMASANG 1 M' LISPLANK


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang kayu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 32,474.00
B. BAHAN
Listplank Fibercement m1 1.0000 - -
Paku 7 Cm dan 10 Cm Kg 0.1000 13,000.00 1,300.00
JUMLAH HARGA BAHAN 1,300.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,774.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 33,774.00

10 MEMASANG 1 M' LISPLANK & TATAB


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang kayu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 32,474.00
B. BAHAN
Tatab Fibercement Uk. 8x100x3000 mm m1 1.0000 - -
Paku 7 Cm dan 10 Cm Kg 0.0500 13,000.00 650.00
JUMLAH HARGA BAHAN 650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 33,124.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 33,124.00

25 MEMASANG 1 M2 RANGKA DINDING PEMISAH (60 X 120) CM, KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang kayu OH 0.4500 99,920.00 44,964.00
Kepala Tukang OH 0.0450 99,920.00 4,496.40
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 65,247.76
B. BAHAN
Balok Kayu Kamper m3 0.0280 - -
Paku 5 Cm dan 7 Cm Kg 0.1500 13,000.00 1,950.00
JUMLAH HARGA BAHAN 1,950.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 67,197.76
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 67,197.76

26 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang kayu OH 0.4500 99,920.00 44,964.00
Kepala Tukang OH 0.0450 99,920.00 4,496.40
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 65,247.76
B. BAHAN
Balok Kayu Kamper m3 0.0280 - -
Paku 5 Cm dan 7 Cm Kg 0.1500 13,000.00 1,950.00
Teakwood 4 mm uk 90x220 cm Lbr 0.8600 - -
Lem Kayu Kg 0.5600 12,000.00 6,720.00
JUMLAH HARGA BAHAN 8,670.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 73,917.76
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 73,917.76

27 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 99,920.00 19,984.00
Tukang kayu OH 0.6000 99,920.00 59,952.00
Kepala Tukang OH 0.0600 99,920.00 5,995.20
Mandor OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 86,930.40
B. BAHAN
Balok Kayu Kamper m3 0.0280 - -
Paku 5 Cm dan 7 Cm Kg 0.1500 13,000.00 1,950.00
Plywood tebal 4 mm uk 120 x 240 cm Lbr 0.8600 - -
Lem Kayu Kg 0.5600 12,000.00 6,720.00
JUMLAH HARGA BAHAN 8,670.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 95,600.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 95,600.40

28 MEMASANG 1 M2 RANGKA DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA HOLO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang kayu OH 0.4500 99,920.00 44,964.00
Kepala Tukang OH 0.0450 99,920.00 4,496.40
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 65,247.76
B. BAHAN
Rangka Holo Btg 1.5000 -
Paku 5 Cm dan 7 Cm Kg 0.1500 13,000.00 1,950.00
Teakwood 4 mm uk 90x220 cm Lbr 0.8600 - -
Lem Kayu Kg 0.5600 12,000.00 6,720.00
JUMLAH HARGA BAHAN 8,670.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 73,917.76
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 73,917.76

29 MEMASANG 1 M2 RANGKA DINDING PEMISAH PLYWOOD RANGKAP, RANGKA HOLO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 99,920.00 19,984.00
Tukang kayu OH 0.6000 99,920.00 59,952.00
Kepala Tukang OH 0.0600 99,920.00 5,995.20
Mandor OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 86,930.40
B. BAHAN
Rangka Holo Btg 1.5000 - -
Paku 5 Cm dan 7 Cm Kg 0.1500 13,000.00 1,950.00
Plywood tebal 4 mm uk 120 x 240 cm Lbr 0.8600 - -
Lem Kayu Kg 0.5600 12,000.00 6,720.00
JUMLAH HARGA BAHAN 8,670.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 95,600.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 95,600.40

30 MEMASANG 1 M2 LAMBRIZIRING DARI PAPAN KAYU KELAS I


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6000 99,920.00 59,952.00
Tukang kayu OH 1.8000 99,920.00 179,856.00
Kepala Tukang OH 0.1800 99,920.00 17,985.60
Mandor OH 0.0300 99,920.00 2,997.60
JUMLAH TENAGA KERJA 260,791.20
B. BAHAN
Papan Kayu Kamper m3 0.0070 - -
Paku 5 Cm dan 10 Cm Kg 0.1000 13,000.00 1,300.00
Paku Skrup 10 cm Kg 0.1500 - -
JUMLAH HARGA BAHAN 1,300.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 262,091.20
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 262,091.20

31 MEMASANG 1 M2 LAMBRIZIRING DARI CONWOOD UKURAN (100 x 3050 x 11 mm)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0250 99,920.00 2,498.00
Tukang kayu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0080 99,920.00 799.36
Mandor OH 0.0010 99,920.00 99.92
JUMLAH TENAGA KERJA 10,891.28
B. BAHAN
- m3 4.0000 - -
Paku 1 Cm dan 2.5 Cm Kg 0.0500 13,000.00 650.00
JUMLAH HARGA BAHAN 650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 11,541.28
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 11,541.28

32 MEMASANG 1 M2 LAMBRIZIRING DARI PLYWOOD UKURAN (120 X 240) CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0250 99,920.00 2,498.00
Tukang kayu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0080 99,920.00 799.36
Mandor OH 0.0010 99,920.00 99.92
JUMLAH TENAGA KERJA 10,891.28
B. BAHAN
Plywood tebal 4 mm uk 120 x 240 cm Lbr 0.4000 - -
Paku 1 Cm dan 2.5 Cm Kg 0.0500 13,000.00 650.00
JUMLAH HARGA BAHAN 650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 11,541.28
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 11,541.28

VII PEKERJAAN BETON ( PERMEN PUPR 28/PRT/M/2016))


1 MEMBUAT 1 M³ BETON MUTU f'C= 7,4 Mpa (K100), Slump (12 ± 2)cm, w/c = 0,87
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland kg 247.000 1,075.00 265,525.00
Pasir Beton kg 869 85.71 74,485.71
Koral Beton kg 999 - -
Air Liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 341,085.71
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 544,522.83
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 544,522.83

2 MEMBUAT 1 M³ BETON MUTU f'C= 9,8 Mpa (K125), Slump (12 ± 2)cm, w/c = 0,78
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland kg 276.000 1,075.00 296,700.00
Pasir Beton kg 828 85.71 70,971.43
Koral Beton kg 1,012 - -
Air lt 215 5.00 1,075.00
JUMLAH HARGA BAHAN 368,746.43
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 572,183.55
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 572,183.55

3 MEMBUAT 1 M³ BETON MUTU f'C= 12,2 Mpa (K150), Slump (12 ± 2)cm, w/c = 0,72
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.6500 99,920.00 164,868.00
Tukang Batu OH 0.2750 99,920.00 27,478.00
Kepala Tukang OH 0.0280 99,920.00 2,797.76
Mandor OH 0.0830 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland (Gersik) kg 299.0000 1,075.00 321,425.00
Pasir Beton kg 799 85.71 68,485.71
Koral Beton kg 1,017 - -
Air lt 215 5.00 1,075.00
JUMLAH HARGA BAHAN 390,985.71
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 594,422.83
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 594,422.83

4 MEMBUAT 1 M³ LANTAI KERJA BETON MUTU F'C = 7,4 MPA SLUMP (3-6)CM, W/C =0.87
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.200 99,920.00 119,904.00
Tukang Batu OH 0.200 99,920.00 19,984.00
Kepala Tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.060 99,920.00 5,995.20
JUMLAH TENAGA KERJA 147,881.60
B. BAHAN
Semen Portland (Gersik) kg 230.0000 1,075.00 247,250.00
Pasir Beton kg 893 85.71 76,542.86
Koral Beton kg 1,027 - -
Air lt 200 5.00 1,000.00
JUMLAH HARGA BAHAN 324,792.86
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 472,674.46
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 472,674.46

5 MEMBUAT 1 M³ BETON MUTU f'C= 14,5 Mpa (K175), Slump (12 ± 2)cm, w/c = 0,66
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland (Gersik) kg 326.0000 1,075.00 350,450.00
Pasir Beton kg 760 85.71 65,142.86
Koral Beton kg 1,029 - -
Air liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 416,667.86
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 620,104.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 620,104.98

6 MEMBUAT 1 M³ BETON MUTU f'C= 16,9 Mpa (K200), Slump (12 ± 2)cm, w/c = 0,61
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland (Gersik) kg 352.0000 1,075.00 378,400.00
Pasir Beton kg 731 85.71 62,657.14
Koral Beton kg 1,031 - -
Air liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 442,132.14
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 645,569.26
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 645,569.26

7 MEMBUAT 1 M³ BETON MUTU f'C= 19,3 Mpa (K225), Slump (12 ± 2)cm, w/c = 0,58
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland (Gersik) kg 371.000 1,075.00 398,825.00
Pasir Beton kg 698 85.71 59,828.57
Koral Beton kg 1,047 - -
Air lietr 215 5.00 1,075.00
JUMLAH HARGA BAHAN 459,728.57
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 663,165.69
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 663,165.69

11 MEMBUAT 1 M³ BETON MUTU f'C= 21,7 Mpa (K250), Slump (12 ± 2)cm, w/c =0,56
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland kg 384.000 1,075.00 412,800.00
Pasir Beton kg 692 85.71 59,314.29
Koral Beton kg 1,039 - -
Air liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 473,189.29
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 676,626.41
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 676,626.41
12 MEMBUAT 1 M³ BETON MUTU f'C= 24,0 Mpa (K275), Slump (12 ± 2)cm, w/c =0,53
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland (Gersik) kg 406.000 1,075.00 436,450.00
Pasir Beton kg 684 85.71 58,628.57
Koral Beton kg 1,026 - -
Air Liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 496,153.57
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 699,590.69
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 699,590.69

13 MEMBUAT 1 M³ BETON MUTU f'C= 26,4 Mpa (K300), Slump (12 ± 2)cm, w/c =0,52
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.650 99,920.00 164,868.00
Tukang Batu OH 0.275 99,920.00 27,478.00
Kepala Tukang OH 0.028 99,920.00 2,797.76
Mandor OH 0.083 99,920.00 8,293.36
JUMLAH TENAGA KERJA 203,437.12
B. BAHAN
Semen Portland (Gersik) kg 413.000 1,075.00 443,975.00
Pasir Beton kg 681 85.71 58,371.43
Koral Beton kg 1,021 - -
Air liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 503,421.43
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 706,858.55
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 706,858.55

14 MEMBUAT 1 M³ BETON MUTU f'C= 28,8 Mpa (K325), Slump (12 ± 2)cm, w/c =0,49
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.100 99,920.00 209,832.00
Tukang Batu OH 0.350 99,920.00 34,972.00
Kepala Tukang OH 0.035 99,920.00 3,497.20
Mandor OH 0.105 99,920.00 10,491.60
JUMLAH TENAGA KERJA 258,792.80
B. BAHAN
Semen Portland (Gersik) kg 439.0000 1,075.00 471,925.00
Pasir Beton kg 670 85.71 57,428.57
Koral Beton kg 1,006 - -
Air lt 215 5.00 1,075.00
JUMLAH HARGA BAHAN 530,428.57
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 789,221.37
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 789,221.37

15 MEMBUAT 1 M³ BETON MUTU f'C= 31,2 Mpa (K350), Slump (12 ± 2)cm, w/c =0,48
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 2.100 99,920.00 209,832.00
Tukang Batu OH 0.350 99,920.00 34,972.00
Kepala Tukang OH 0.035 99,920.00 3,497.20
Mandor OH 0.105 99,920.00 10,491.60
JUMLAH TENAGA KERJA 258,792.80
B. BAHAN
Semen Portland (Gersik) kg 448.0000 1,075.00 481,600.00
Pasir Beton kg 667 85.71 57,171.43
Koral Beton kg 1,000 - -
Air liter 215 5.00 1,075.00
JUMLAH HARGA BAHAN 539,846.43
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 798,639.23
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 798,639.23

12 PEMBESIAN 10 KG DENGAN BESI POLOS ATAU BESI ULIR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.070 99,920.00 6,994.40
Tukang Besi OH 0.070 99,920.00 6,994.40
Kepala Tukang OH 0.007 99,920.00 699.44
Mandor OH 0.004 99,920.00 399.68
JUMLAH TENAGA KERJA 15,087.92
B. BAHAN
Besi Beton (Polos/ Ulir) kg 10.500 8,500.00 89,250.00
Kawat Beton kg 0.150 13,000.00 1,950.00
JUMLAH HARGA BAHAN 91,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 106,287.92
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 106,287.92
Harga Satuan Pekerjaan untuk 1 Kg 10,628.79

16 1 M2 PASANG BEKISTING UNTUK PONDASI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.520 99,920.00 51,958.40
Tukang Kayu OH 0.260 99,920.00 25,979.20
Kepala Tukang OH 0.026 99,920.00 2,597.92
Mandor OH 0.026 99,920.00 2,597.92
JUMLAH TENAGA KERJA 83,133.44
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5 - 10 cm kg 0.300 13,000.00 3,900.00
Minyak Bekisting ltr 0.100 - -
JUMLAH HARGA BAHAN 83,900.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 167,033.44
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 167,033.44

17 1 M2 PASANG BEKISTING UNTUK SLOOF


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.5200 99,920.00 51,958.40
Tukang Kayu OH 0.2600 99,920.00 25,979.20
Kepala Tukang OH 0.0260 99,920.00 2,597.92
Mandor OH 0.0260 99,920.00 2,597.92
JUMLAH TENAGA KERJA 83,133.44
B. BAHAN
Kayu Kelas III m3 0.045 2,000,000.00 90,000.00
Paku Biasa 5cm - 10cm kg 0.300 13,000.00 3,900.00
Minyak Bekisting ltr 0.100 - -
JUMLAH HARGA BAHAN 93,900.00
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 177,033.44
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 177,033.44
G. Harga Satuan Pekerjaan (2x Pakai) 88,516.72

18 1 M2 PASANG BEKISTING UNTUK KOLOM


HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN KOEFISIEN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660 99,920.00 65,947.20
Tukang Kayu OH 0.330 99,920.00 32,973.60
Kepala Tukang OH 0.033 99,920.00 3,297.36
Mandor OH 0.033 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5cm - 12cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.200 - -
Balok kayu kelas II m3 0.015 4,000,000.00 60,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu 8 - 10 cm /4 m Batang 2.000 - -
JUMLAH HARGA BAHAN 177,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 282,915.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 282,915.52
G. Harga Satuan Pekerjaan (2x pakai) 141,457.76
13 1 M2 PASANG BEKISTING UNTUK BALOK
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660 99,920.00 65,947.20
Tukang Kayu OH 0.330 99,920.00 32,973.60
Kepala Tukang OH 0.033 99,920.00 3,297.36
Mandor OH 0.033 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5 cm - 12 cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.200 - -
Balok kayu kelas II m3 0.018 4,000,000.00 72,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu Ø (8 - 10)cm /4 m btg 2.000 - -
JUMLAH HARGA BAHAN 189,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 294,915.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 294,915.52
G. Harga Satuan Pekerjaan (2x pakai) 147,457.76

14 1 M2 PASANG BEKISTING UNTUK PLAT LANTAI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.660 99,920.00 65,947.20
Tukang Kayu OH 0.330 99,920.00 32,973.60
Kepala Tukang OH 0.033 99,920.00 3,297.36
Mandor OH 0.033 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.040 2,000,000.00 80,000.00
Paku Biasa 5cm - 12cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.200 - -
Balok kayu kelas II m3 0.015 4,000,000.00 60,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu Ø( 8 - 10) cm /4 m btg 6.000 - -
JUMLAH HARGA BAHAN 177,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 282,915.52
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 282,915.52
G. Harga Satuan Pekerjaan (2 x pakai) 141,457.76

15 1 M2 PASANG BEKISTING UNTUK DINDING


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6600 99,920.00 65,947.20
Tukang Kayu OH 0.3300 99,920.00 32,973.60
Kepala Tukang OH 0.0330 99,920.00 3,297.36
Mandor OH 0.0330 99,920.00 3,297.36
JUMLAH TENAGA KERJA 105,515.52
B. BAHAN
Kayu Kelas III m3 0.030 2,000,000.00 60,000.00
Paku Biasa 5cm - 12 cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.200 - -
Balok kayu kelas II m3 0.020 4,000,000.00 80,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu Ø ( 8 - 10)cm/4 m btg 3.000 - -
Formite/penjaga jarak bekisting/spacer Bh 4.000 - -
JUMLAH HARGA BAHAN 177,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 282,915.52
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 282,915.52

14 1 M2 PASANG BEKISTING UNTUK TANGGA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6600 99,920.00 -
Tukang Kayu OH 0.3300 99,920.00 -
Kepala Tukang OH 0.0330 99,920.00 -
Mandor OH 0.0330 99,920.00 -
JUMLAH TENAGA KERJA -
B. BAHAN
Kayu Kelas III m3 0.030 2,000,000.00 60,000.00
Paku Biasa 5cm - 12 cm kg 0.400 13,000.00 5,200.00
Minyak Bekisting ltr 0.150 - -
Balok kayu kelas II m3 0.015 4,000,000.00 60,000.00
Plywood tebal 9 mm lbr 0.350 92,000.00 32,200.00
Dolken Kayu Ø (8 - 10)cm /4 m btg 2.000 - -
JUMLAH HARGA BAHAN 157,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 157,400.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 157,400.00
15 1 M2 PASANG JEMBATAN UNTUK PENGECORAN BETON
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.150 99,920.00 14,988.00
Tukang Kayu OH 0.050 99,920.00 4,996.00
Kepala Tukang OH 0.005 99,920.00 499.60
Mandor OH 0.008 99,920.00 799.36
JUMLAH TENAGA KERJA 21,282.96
B. BAHAN
Kayu Kelas III (papan) m3 0.0264 2,000,000.00 52,800.00
Paku Biasa 5 cm - 12 cm kg 0.600 13,000.00 7,800.00
Dolken Kayu Ø (8 - 10) cm /4 m btg 0.500 - -
JUMLAH HARGA BAHAN 60,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 81,882.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 81,882.96

16 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11 CM)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.180 99,920.00 17,985.60
Tukang Batu OH 0.020 99,920.00 1,998.40
Tukang Kayu OH 0.020 99,920.00 1,998.40
Tukang Besi OH 0.020 99,920.00 1,998.40
Kepala Tukang OH 0.006 99,920.00 599.52
Mandor OH 0.009 99,920.00 899.28
JUMLAH TENAGA KERJA 25,479.60
B. BAHAN
Kayu Kelas III m3 0.002 2,000,000.00 4,000.00
Paku Biasa 5cm - 12cm kg 0.010 13,000.00 130.00
Minyak bekisting Liter 0.0150 - -
Besi Beton polos kg 3.000 8,500.00 25,500.00
Kawat Beton kg 0.450 13,000.00 5,850.00
Semen Portland ( Gersik) kg 4.000 1,075.00 4,300.00
Pasir Beton m3 0.006 120,000.00 720.00
Koral Beton m3 0.009 - -
JUMLAH HARGA BAHAN 40,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 65,979.60
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 65,979.60

17 1 M1 MEMBUAT KOLOM PENGUAT BETON BERTULANG (10 X 15 CM)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.297 99,920.00 29,676.24
Tukang Batu OH 0.033 99,920.00 3,297.36
Tukang Kayu OH 0.033 99,920.00 3,297.36
Tukang Besi OH 0.033 99,920.00 3,297.36
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.015 99,920.00 1,498.80
JUMLAH TENAGA KERJA 42,066.32
B. BAHAN
Kayu Kelas III m3 0.003 2,000,000.00 6,000.00
Paku Biasa 5 cm - 12 cm kg 0.020 13,000.00 260.00
Minyak bekisting Liter 0.015 - -
Besi Beton Polos kg 3.600 8,500.00 30,600.00
Kawat Beton kg 0.050 13,000.00 650.00
Semen kg 5.500 1,075.00 5,912.50
Pasir Beton m3 0.009 120,000.00 1,080.00
Koral Beton m3 0.015 - -
JUMLAH HARGA BAHAN 44,502.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 86,568.82
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 86,568.82

27 1 M2 BEKISTING DINDING BETON BIASA DENGAN MULTIFLEX 12 mm *2 kali pakai*


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2400 99,920.00 23,980.80
Tukang Kayu OH 0.1200 99,920.00 11,990.40
Kepala Tukang OH 0.0120 99,920.00 1,199.04
Mandor OH 0.0240 99,920.00 2,398.08
JUMLAH TENAGA KERJA 39,568.32
B. BAHAN
Multiflex 12 mm Lbr 0.2030 - -
Kaso 5/7 cm M3 0.0090 2,000,000.00 18,000.00
Paku 5 cm dan 7 cm Kg 0.2400 13,000.00 3,120.00
Minyak Bekisting L 0.2000 - -
JUMLAH HARGA BAHAN 21,120.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 60,688.32
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 60,688.32

28 1 M2 BEKISTING PONDASI DAN SLOOF BETON BIASA MENGGUNAKAN PAPAN 3/20 CM *2 kali pakai*
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Kayu OH 0.1500 99,920.00 14,988.00
Kepala Tukang OH 0.0150 99,920.00 1,498.80
Mandor OH 0.0300 99,920.00 2,997.60
JUMLAH TENAGA KERJA 49,460.40
B. BAHAN
Papan 3/20 cm Kayu Kelas II Lbr 0.0220 1,200,000.00 26,400.00
Kaso 5/7 cm M3 0.0160 2,000,000.00 32,000.00
Paku 5 cm dan 7 cm Kg 0.2400 13,000.00 3,120.00
Minyak Bekisting L 0.2000 - -
JUMLAH HARGA BAHAN 61,520.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 110,980.40
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 110,980.40

29 1 M2 PERANCAH/PENYOKONG BEKISTING DINDING BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks 2,5 m *2 kali pakai*
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3600 99,920.00 35,971.20
Tukang Kayu OH 0.1800 99,920.00 17,985.60
Kepala Tukang OH 0.0180 99,920.00 1,798.56
Mandor OH 0.0360 99,920.00 3,597.12
JUMLAH TENAGA KERJA 59,352.48
B. BAHAN
Kaso 5/7 cm M3 0.0170 2,000,000.00 34,000.00
Paku 5 cm dan 7 cm Kg 0.2400 18,000.00 4,320.00
JUMLAH HARGA BAHAN 38,320.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 97,672.48
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 97,672.48

30 1 M2 PERANCAH/PENYOKONG BEKISTING PONDASI DAN SLOOF BETON MENGGUNAKAN KAYU 5/7 ,Tinggi Maks 2,0 m *2 kali pakai*
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 99,920.00 19,984.00
Tukang Kayu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA KERJA 32,973.60
B. BAHAN
Kaso 5/7 cm M3 0.0190 2,000,000.00 38,000.00
Paku 5 cm dan 7 cm Kg 0.2500 13,000.00 3,250.00
JUMLAH HARGA BAHAN 41,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 74,223.60
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 74,223.60

VIII HARGA SATUAN PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)
1 1 KG PEMASANGAN BESI PROFIL
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.060 99,920.00 5,995.20
Tukang las konstruksi OH 0.060 99,920.00 5,995.20
Kepala tukang OH 0.006 99,920.00 599.52
Mandor OH 0.003 99,920.00 299.76
JUMLAH TENAGA KERJA 12,889.68
B. BAHAN
Besi Profil Kg 1.150 - -

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 12,889.68
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 12,889.68

2 1 KG PEMASANGAN RANGKA KUDA-KUDA BAJA IWF


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.060 99,920.00 5,995.20
Tukang las konstruksi OH 0.060 99,920.00 5,995.20
Kepala tukang OH 0.006 99,920.00 599.52
Mandor OH 0.003 99,920.00 299.76
JUMLAH TENAGA KERJA 12,889.68
B. BAHAN
Besi baja IWF Kg 1.150 - -

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 12,889.68
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 12,889.68

3 100 KG PENGERJAAN PEKERJAAN PERAKITAN


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.060 99,920.00 5,995.20
Tukang las konstruksi OH 0.060 99,920.00 5,995.20
Kepala tukang OH 0.006 99,920.00 599.52
Mandor OH 0.003 99,920.00 299.76
JUMLAH TENAGA KERJA 12,889.68
B. BAHAN
Besi baja IWF Kg 1.150 - -

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 12,889.68
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 12,889.68

4 1 M2 PEMASANGAN PINTU ROLLING DOOR BESI


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.200 99,920.00 119,904.00
Tukang las biasa OH 1.200 99,920.00 119,904.00
Kepala tukang OH 0.120 99,920.00 11,990.40
Mandor OH 0.006 99,920.00 599.52
JUMLAH TENAGA KERJA 252,397.92
B. BAHAN
Pintu gulung besi m2 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 252,397.92
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 252,397.92

5 1 M2 PEMASANGAN ROLLING DOOR ALLUMINIUM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.000 99,920.00 99,920.00
Tukang khusus aluminium OH 1.000 99,920.00 99,920.00
Kepala tukang OH 0.100 99,920.00 9,992.00
Mandor OH 0.050 99,920.00 4,996.00
JUMLAH TENAGA KERJA 214,828.00
B. BAHAN
Rolling door alluminium m2 1.000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 214,828.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 214,828.00

6 1 M2 PEMASANGAN KUSEN PINTU ALLUMINIUM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.043 99,920.00 4,296.56
Tukang khusus aluminium OH 0.043 99,920.00 4,296.56
Kepala tukang OH 0.004 99,920.00 429.66
Mandor OH 0.002 99,920.00 209.83
JUMLAH TENAGA KERJA 9,232.61
B. BAHAN
Profil alluminium m 1.100 - -
Skrup fixer buah 2.000 - -
Sealant Tube 0.060 - -

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 9,232.61
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 9,232.61

7 1 M2 PEMASANGAN PINTU ALLUMINIUM STRIP LEBAR 8 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.085 99,920.00 8,493.20
Tukang khusus aluminium OH 0.085 99,920.00 8,493.20
Kepala tukang OH 0.0085 99,920.00 849.32
Mandor OH 0.0042 99,920.00 419.66
JUMLAH TENAGA KERJA 18,255.38
B. BAHAN
Profil alluminium m 4.400 - -
Alluminium strip m 14.600 - -

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 18,255.38
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 18,255.38

8 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1 X40.40.2MM, MODUL 60 X 120 CM, UNTUK PARTISI
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang besi OH 0.250 99,920.00 24,980.00
Kepala Tukang OH 0.025 99,920.00 2,498.00
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 53,756.96
B. BAHAN
Rangka metal hollow 40.40.2 mm m 3.500 - -
Assesoris (perkuatan, las dll) Ls 100% x rangka - -

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 53,756.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 53,756.96

9 1 M2 PEMASANGAN RANGKA BESI HOLLOW 1 X40.40.2MM, MODUL 60 X 120 CM, UNTUK PLAFON
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.350 99,920.00 34,972.00
Tukang besi OH 0.350 99,920.00 34,972.00
Kepala Tukang OH 0.035 99,920.00 3,497.20
Mandor OH 0.018 99,920.00 1,798.56
JUMLAH TENAGA KERJA 75,239.76
B. BAHAN
Rangka metal hollow 40.40.2 mm m 4.000 - -
Assesoris (perkuatan, las dll) Ls 100% x rangka - -

JUMLAH HARGA BAHAN -


C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 75,239.76
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 75,239.76

15 1 M2 PEMASANGAN RAILLING RANGKA BESI HOLLOW


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang besi OH 0.250 99,920.00 24,980.00
Kepala Tukang OH 0.025 99,920.00 2,498.00
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 53,756.96
B. BAHAN
Rangka metal hollow 40.40.2 mm m 4.000 - -
Assesoris (perkuatan, las dll) Ls 100% x rangka - -
Cat Besi kg 1.020 - -
JUMLAH HARGA BAHAN -
C. PERALATAN

JUMLAH HARGA ALAT


D. Jumlah (A + B + C) 53,756.96
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 53,756.96

10 1 M2 PEMASANGAN ATAP PELANA RANGKA ATAP BAJA CANAI DINGIN PROFIL C75
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.734 99,920.00 73,341.28
Tukang besi OH 0.734 99,920.00 73,341.28
Kepala Tukang OH 0.073 99,920.00 7,294.16
Mandor OH 0.037 99,920.00 3,697.04
JUMLAH TENAGA KERJA 157,673.76
B. BAHAN
Baja ringan canai dingin C75 kg 3.065 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan % 10 - -

JUMLAH HARGA ALAT -


D. Jumlah (A + B + C) 157,673.76
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 157,673.76

11 1 M2 PEMASANGAN ATAP JURAI RANGKA ATAP BAJA CANAI DINGIN PROFIL C75
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.760 99,920.00 75,979.17
Tukang besi OH 0.760 99,920.00 75,979.17
Kepala Tukang OH 0.0760 99,920.00 7,593.92
Mandor OH 0.0380 99,920.00 3,796.96
JUMLAH TENAGA KERJA 163,349.22
B. BAHAN
Baja ringan canai dingin C75 kg 4.050 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
Peralatan % 10 - -

JUMLAH HARGA ALAT -


D. Jumlah (A + B + C) 163,349.22
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 163,349.22

IX PEKERJAAN PENUTUP ATAP (PERMEN PUPR 28/PRT/M/2016)


16 1 M2 PEKERJAAN ATAP GENTENG GOODYEAR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang Kayu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0080 99,920.00 799.36
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 24,080.72
B. BAHAN
Genteng Goodyear bh 25.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 24,080.72
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 24,080.72
2 1 M2 PEKERJAAN ATAP GENTENG PLENTONG DI CAT
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang Kayu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0080 99,920.00 799.36
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 24,080.72
B. BAHAN
Genteng Plentong dicat bh 25.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 24,080.72
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 24,080.72

Pemasangan 1 m2 atap genteng metal uk. 0,77 x 0,8 m, tebal 0,3 mm


Harga Satuan Jumlah Harga
No. Uraian Satuan Koefisien
(RP) (RP)
A. TENAGA
Pekerja OH 0.200 99,920.00 19,984.00
Tukang Kayu OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 31,075.12
B. BAHAN
Genteng metal Bh 1.020 - -
Paku biasa 1/2"-1" Kg 0.200 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
-
JUMLAH HARGA ALAT
D. Jumlah ( A+B+C) 31,075.12
E. Profit 10% * D
F. Harga Satuan Pekerjaan (D+E) 31,075.12

17 1 M1 PASANG BUBUNGAN GENTENG GOODYEAR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4000 99,920.00 39,968.00
Tukang Kayu OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0020 99,920.00 199.84
JUMLAH TENAGA KERJA 62,150.24
B. BAHAN
Bubungan Goodyear bh 5.0000 - -
Semen kg 10.8000 1,075.00 11,610.00
Pasir Pasang m3 0.0320 120,000.00 3,840.00
JUMLAH HARGA BAHAN 15,450.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 77,600.24
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 77,600.24

4 1 M2 PASANG ATAP GENTENG ASBES GELOMBANG 1.8 M X 0.92 M X 5 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1400 99,920.00 13,988.80
Tukang Kayu OH 0.0670 99,920.00 6,694.64
Kepala Tukang OH 0.0070 99,920.00 699.44
Mandor OH 0.0070 99,920.00 699.44
JUMLAH TENAGA KERJA 22,082.32
B. BAHAN
Asbes Gelombang 1.8 mx0.92mx5mm lbr 0.6600 - -
Paku Pancing 60 x 230 kg 2.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 22,082.32
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 22,082.32

5 1 M1 PASANG BUBUNGAN STEL GELOMBANG 0.92 M


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0840 99,920.00 8,393.28
Tukang Kayu OH 0.1250 99,920.00 12,490.00
Kepala Tukang OH 0.0130 99,920.00 1,298.96
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 22,581.92
B. BAHAN
Bubungan Stel Gelombang lbr 2.4000 - -
Paku Skrup 3,5" kg 4.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 22,581.92
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 22,581.92

6 1 M2 PASANGAN LAPISAN ALUMINIUM FOIL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0330 99,920.00 3,297.36
Tukang Kayu OH 0.0330 99,920.00 3,297.36
Kepala Tukang OH 0.0030 99,920.00 299.76
Mandor OH 0.0020 99,920.00 199.84
JUMLAH TENAGA KERJA 7,094.32
B. BAHAN
Aluminium Foil m2 1.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 7,094.32
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 7,094.32

7 1 M1 BUBUNGAN ATAP Bubungan Genteng Metal Prima Roof


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500 99,920.00 24,980.00
Tukang kayu OH 0.1500 99,920.00 14,988.00
Kepala Tukang OH 0.0150 99,920.00 1,498.80
Mandor OH 0.0130 99,920.00 1,298.96
JUMLAH TENAGA KERJA 42,765.76
B. BAHAN
Bubungan Genteng Metal Prima Roof lmbr 1.2000 - -
Paku biasa 1/2" - 1" bh 6.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) k 42,765.76
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 42,765.76

18 1 BH PEKERJAAN PASANGAN IKUT CELEDU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0500 99,920.00 4,996.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 7,494.00
B. BAHAN
Ikut Celedu lbr 1.0000 - -
Semen kg 0.0130 1,075.00 13.98
JUMLAH HARGA BAHAN 13.98
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 7,507.98
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 7,507.98
19 1 BH PEKERJAAN PASANGAN MURDA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0500 99,920.00 4,996.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 7,494.00
B. BAHAN
Murda lbr 1.0000 - -
Semen kg 0.0130 1,075.00 13.98
JUMLAH HARGA BAHAN 13.98
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 7,507.98
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 7,507.98

X PEKERJAAN PLAFOND / LANGIT - LANGIT (PERMEM PUPR 28/PRT/M/2016))


1 MEMASANG 1 M2 LANGIT-LANGIT ASBES SEMEN, TEBAL 4 MM, 5 MM DAN 6 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0300 99,920.00 2,997.60
Tukang Kayu OH 0.0700 99,920.00 6,994.40
Kepala Tukang OH 0.0070 99,920.00 699.44
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 11,091.12
B. BAHAN
Asbes Semen lbr 1.1000 - -
Paku biasa 1/2" - 1" kg 0.0100 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 11,091.12
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 11,091.12

2 1 M2 PASANG LANGIT-LANGIT TRIPLEKS 120X240 CM/3 MM, 4MM, 6MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1000 99,920.00 9,992.00
Tukang Kayu OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 21,482.80
B. BAHAN
TRIIPLEKS lbr 0.3750 - -
Paku biasa 1/2" - 1" kg 0.0300 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,482.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,482.80

3 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.8000 99,920.00 79,936.00
Tukang Kayu OH 0.8000 99,920.00 79,936.00
Kepala Tukang OH 0.0800 99,920.00 7,993.60
Mandor OH 0.0400 99,920.00 3,996.80
JUMLAH TENAGA KERJA 171,862.40
B. BAHAN
Kayu Papan Kamper m3 0.0150 7,000,000.00 105,000.00
Paku biasa 1/2" - 1" kg 0.0100 - -
JUMLAH HARGA BAHAN 105,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 276,862.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 276,862.40

4 1 M1 PASANG LIST LANGIT-LANGIT KAYU PROFIL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0500 99,920.00 4,996.00
Tukang Kayu OH 0.0500 99,920.00 4,996.00
Kepala Tukang OH 0.0050 99,920.00 499.60
Mandor OH 0.0030 99,920.00 299.76
JUMLAH TENAGA KERJA 10,791.36
B. BAHAN
List Kayu Profil 4/5 cm m3 1.0500 - -
Paku list kg 0.0100 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 10,791.36
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 10,791.36

20 1 M1 PASANG LIST LANGIT-LANGIT GYPSUM PROFIL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0500 99,920.00 4,996.00
Tukang Kayu OH 0.0500 99,920.00 4,996.00
Kepala Tukang OH 0.0050 99,920.00 499.60
Mandor OH 0.0030 99,920.00 299.76
JUMLAH TENAGA KERJA 10,791.36
B. BAHAN
List Gypsum 2/5 cm m' 1.0500 - -
Paku list kg 0.0100 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 10,791.36
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 10,791.36
6 1 M2 PASANG LANGIT-LANGIT AKUSTIK UKURAN (60 x 120) CM + RANGKA ALUMINIUM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.5000 99,920.00 49,960.00
Tukang Besi OH 0.5000 99,920.00 49,960.00
Kepala Tukang OH 0.0500 99,920.00 4,996.00
Mandor OH 0.0250 99,920.00 2,498.00
JUMLAH TENAGA KERJA 107,414.00
B. BAHAN
Profil Aluminium "T" m1 3.6000 - -
Kawat Diameter 4 mm kg 0.1500 - -
Ramset m1 1.0500 - -
Akustik 60 cm x 120 cm lbr 1.5000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 107,414.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 107,414.00

7 1 M2 PASANG LANGIT-LANGIT ASBES + RANGKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1800 99,920.00 17,985.60
Tukang Kayu OH 0.3200 99,920.00 31,974.40
Kepala Tukang OH 0.0320 99,920.00 3,197.44
Mandor OH 0.0090 99,920.00 899.28
JUMLAH TENAGA KERJA 54,056.72
B. BAHAN
Kamper Usuk 4/6 cm m3 0.0230 - -
Paku Biasa 2" - 5" kg 0.0600 - -
Asbes lbr 1.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,056.72
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 54,056.72

8 1 M2 PLAFOND GYPSUM, RANGKA KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Kayu OH 0.3500 99,920.00 34,972.00
Kepala Tukang OH 0.0350 99,920.00 3,497.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 69,944.00
B. BAHAN
Gypsum Board (120x240x9) Lbr 0.3640 - -
Kayu Kruing Usuk M3 0.0230 - -
Paku Kalsiboard Kg 0.2600 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 69,944.00
E. Overhead & Profit 5 %xD 3,497.20
F. Harga Satuan Pekerjaan (D+E) 73,441.20

9 1 M2 PLAFOND GYPSUM, RANGKA HOLO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Kayu OH 0.3500 99,920.00 34,972.00
Kepala Tukang OH 0.0350 99,920.00 3,497.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 69,944.00
B. BAHAN
Gypsum Board (120x240x9) Lbr 0.3640 - -
Rangka Metal Furing (4 x 4 cm) panjang 4 m Btg 1.0000 - -
Paku Kalsiboard Kg 0.1100 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 69,944.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 69,944.00

21 1 M2 PLAFOND KALSIBOARD, RANGKA KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Kayu OH 0.3500 99,920.00 34,972.00
Kepala Tukang OH 0.0350 99,920.00 3,497.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 69,944.00
B. BAHAN
Kalsiboard (4,5 x 1220 x 2420) mm Lbr 0.3640 - -
Kayu Kruing Usuk M3 0.0230 - -
Paku Kalsiboard Kg 0.2600 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 69,944.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 69,944.00

11 1 M2 PLAFOND KALSIBOARD, RANGKA HOLO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Tukang Kayu OH 0.3500 99,920.00 34,972.00
Kepala Tukang OH 0.0350 99,920.00 3,497.20
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 69,944.00
B. BAHAN
Kalsiboard (4,5 x 1220 x 2420) mm Lbr 0.3640 - -
Rangka Metal Furing (4 x 4 cm) panjang 4 m M3 1.0000 - -
Paku Kalsiboard Kg 0.1100 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 69,944.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 69,944.00

XI PEKERJAAN SANITASI ( PERMEN PUPR 28/PRT/M/2016) )


1 MEMASANG 1 BUAH KLOSET DUDUK
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 3.3000 99,920.00 329,736.00
Tukang Batu OH 1.1000 99,920.00 109,912.00
Kepala Tukang OH 0.0010 99,920.00 99.92
Mandor OH 0.1600 99,920.00 15,987.20
JUMLAH TENAGA KERJA 455,735.12
B. BAHAN
Kloset duduk INA Komplit bh 1.0000 - -
Perlengkapan 6% x harga kloset - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 455,735.12
E. Overhead & Profit 5 %xD 22,786.76
F. Harga Satuan Pekerjaan (D+E) 478,521.88
22 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000 99,920.00 99,920.00
Tukang Batu OH 1.5000 99,920.00 149,880.00
Kepala Tukang OH 1.5000 99,920.00 149,880.00
Mandor OH 0.1600 99,920.00 15,987.20
JUMLAH TENAGA KERJA 415,667.20
B. BAHAN
Kloset jongkok porselen bh 1.0000 - -
Semen kg 6.0000 1,075.00 6,450.00
Pasir Pasang m3 0.0100 120,000.00 1,200.00
JUMLAH HARGA BAHAN 7,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 423,317.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 423,317.20
3 MEMASANG 1 BUAH URINOIR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.0000 99,920.00 99,920.00
Tukang Batu OH 1.0000 99,920.00 99,920.00
Kepala Tukang OH 0.1000 99,920.00 9,992.00
Mandor OH 0.1000 99,920.00 9,992.00
JUMLAH TENAGA KERJA 219,824.00
B. BAHAN
Urinoir bh 1.0000 - -
Perlengkapan 30% x harga Urinoir - -
Semen kg 6.0000 1,075.00 6,450.00
Pasir Pasang m3 0.0100 120,000.00 1,200.00
JUMLAH HARGA BAHAN 7,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 227,474.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 227,474.00

4 MEMASANG 1 BUAH WASHTAFEL KIA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.2000 99,920.00 119,904.00
Tukang Batu OH 1.4500 99,920.00 144,884.00
Kepala Tukang OH 0.1500 99,920.00 14,988.00
Mandor OH 0.1000 99,920.00 9,992.00
JUMLAH TENAGA KERJA 289,768.00
B. BAHAN
Wastafel bh 1.0000 - -
Perlengkapan 12% x harga wast - -
Semen kg 6.0000 1,075.00 6,450.00
Pasir Pasang m3 0.0100 120,000.00 1,200.00
JUMLAH HARGA BAHAN 7,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 297,418.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 297,418.00

5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.8000 99,920.00 179,856.00
Tukang Batu OH 2.7000 99,920.00 269,784.00
Kepala Tukang OH 0.5400 99,920.00 53,956.80
Mandor OH 0.1100 99,920.00 10,991.20
JUMLAH TENAGA KERJA 514,588.00
B. BAHAN
Bak Fibreglass bh 1.0000 - -
Perlengkapan 18% x harga bak - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 514,588.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 514,588.00

6 MEMASANG 1 M1 PIPA GALVANIS f 0,5" - 1 "


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0540 99,920.00 5,395.68
Tukang Pipa OH 0.0900 99,920.00 8,992.80
Kepala Tukang OH 0.0090 99,920.00 899.28
Mandor OH 0.0270 99,920.00 2,697.84
JUMLAH TENAGA KERJA 17,985.60
B. BAHAN
Pipa Galvanis m' 1.2000 - -
Perlengkapan 35% x harga pipa - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 17,985.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 17,985.60

7 MEMASANG 1 M1 PIPA GALVANIS f 1,5" - 3"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1080 99,920.00 10,791.36
Tukang Pipa OH 0.1800 99,920.00 17,985.60
Kepala Tukang OH 0.0180 99,920.00 1,798.56
Mandor OH 0.0054 99,920.00 539.57
JUMLAH TENAGA KERJA 31,115.09
B. BAHAN
Pipa Galvanis m' 1.2000 - -
Perlengkapan 35% x harga pipa - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 31,115.09
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 31,115.09
8 MEMASANG 1 M1 PIPA PVC TYPE AW f 0,5" - 1,5"
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0360 99,920.00 3,597.12
Tukang Pipa OH 0.0600 99,920.00 5,995.20
Kepala Tukang OH 0.0060 99,920.00 599.52
Mandor OH 0.0018 99,920.00 179.86
JUMLAH TENAGA KERJA 10,371.70
B. BAHAN
Pipa PVC m' 1.2000 - -
Perlengkapan 35% x harga pipa - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 10,371.70
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 10,371.70

23 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 1"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0540 99,920.00 5,395.68
Tukang Pipa OH 0.0900 99,920.00 8,992.80
Kepala Tukang OH 0.0090 99,920.00 899.28
Mandor OH 0.0030 99,920.00 299.76
JUMLAH TENAGA KERJA 15,587.52
B. BAHAN
Pipa PVC m' 1.2000 12,000.00 14,400.00
Perlengkapan 35% x harga pipa 4,200.00 4,200.00
JUMLAH HARGA BAHAN 18,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 34,187.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 34,187.52
24 MEMASANG 1 M1 PIPA PVC TYPE AW Ø 3"
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0810 99,920.00 8,093.52
Tukang Pipa OH 0.1350 99,920.00 13,489.20
Kepala Tukang OH 0.0135 99,920.00 1,348.92
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 23,331.32
B. BAHAN
Pipa PVC m' 1.2000 20,000.00 24,000.00
Perlengkapan 35% x harga pipa 7,000.00 7,000.00
JUMLAH HARGA BAHAN 31,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 54,331.32
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 54,331.32

25 MEMASANG 1 M1 PIPA PVC TYPE AW f Ø 4"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0810 99,920.00 8,093.52
Tukang Pipa OH 0.1350 99,920.00 13,489.20
Kepala Tukang OH 0.0135 99,920.00 1,348.92
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 23,331.32
B. BAHAN
Pipa PVC m' 1.2000 - -
Perlengkapan 35% x harga pipa - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 23,331.32
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 23,331.32
26 MEMASANG 1 BUAH KRAN f 0,75" ATAU 0,5"
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Pipa OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 10,991.20
B. BAHAN
Kran air bh 1.0000 150,000.00 150,000.00
Seal tape bh 0.0250 - -
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 160,991.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 160,991.20

XII PEKERJAAN BESI DAN ALUMINIUM (PERMEN PUPR 28/PRT/M/2016)


1 1 KG MEMASANG RANGKA BAJA IWF
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0060 99,920.00 599.52
Tukang besi OH 0.0600 99,920.00 5,995.20
Kepala Tukang OH 0.0060 99,920.00 599.52
Mandor OH 0.0003 99,920.00 29.98
JUMLAH TENAGA KERJA 7,224.22
B. BAHAN
Besi Baja WF kg 1.1500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 7,224.22
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 7,224.22

2 1 M2 PASANG JENDELA NAKO & TRALIS


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 99,920.00 19,984.00
Tukang Besi OH 0.2000 99,920.00 19,984.00
Kepala Tukang OH 0.0200 99,920.00 1,998.40
Mandor OH 0.0010 99,920.00 99.92
JUMLAH TENAGA KERJA 42,066.32
B. BAHAN
Rangka + Kaca Nako m2 1.1000 - -
Paku biasa 1 cm - 2,5 cm bh 10.0000 15,000.00 150,000.00
Besi strip m' 7.0000 - -
JUMLAH HARGA BAHAN 150,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 192,066.32
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 192,066.32

3 1 M1 PASANG TALANG DATAR, SENG BJLS 28


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 99,920.00 19,984.00
Tukang Besi OH 0.4000 99,920.00 39,968.00
Kepala Tukang OH 0.0250 99,920.00 2,498.00
Mandor OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 63,449.20
B. BAHAN
Seng plat lbr 1.0500 - -
Paku biasa 0,5" - 1" kg 0.0150 15,000.00 225.00
Kayu papan kelas II/III m3 0.0190 - -
JUMLAH HARGA BAHAN 225.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 63,674.20
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 63,674.20

XII PEKERJAAN KUNCI DAN KACA PERMEN PUPR 28/PRT/M/2016)


27 1 BH PASANG KUNCI TANAM BIASA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.5000 99,920.00 49,960.00
Kepala Tukang OH 0.0500 99,920.00 4,996.00
Mandor OH -
JUMLAH TENAGA KERJA 54,956.00
B. BAHAN
Kunci Tanam Biasa bh 1.0000 130,000.00 130,000.00
JUMLAH HARGA BAHAN 130,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 184,956.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 184,956.00
28 1 PS PASANG ENGSEL PINTU
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1250 99,920.00 12,490.00
Kepala Tukang OH 0.0130 99,920.00 1,298.96
Mandor OH
JUMLAH TENAGA KERJA 13,788.96
B. BAHAN
Engsel Pintu ps 1.0000 45,000.00 45,000.00
JUMLAH HARGA BAHAN 45,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 58,788.96
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 58,788.96

29 1 PS PASANG ENGSEL JENDELA KUPU-KUPU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH
JUMLAH TENAGA KERJA 10,991.20
B. BAHAN
Engsel Jendela ps 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 60,991.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 60,991.20
30 1 BH PASANG KAIT ANGIN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0010 99,920.00 99.92
Mandor OH
JUMLAH TENAGA KERJA 10,091.92
B. BAHAN
Kait Angin ps 1.0000 50,000.00 50,000.00
JUMLAH HARGA BAHAN 50,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 60,091.92
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 60,091.92

31 1 BH PASANG KUNCI SLOT PINTU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.2500 99,920.00 24,980.00
Kepala Tukang OH 0.0250 99,920.00 2,498.00
Mandor OH
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Kunci Slot Pintu bh 1.0000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 62,478.00
E. Overhead & Profit 5 %xD 3,123.90
F. Harga Satuan Pekerjaan (D+E) 65,601.90

32 1 BH PASANG GRENDEL JENDELA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH
Tukang Besi OH 0.2500 99,920.00 24,980.00
Kepala Tukang OH 0.0250 99,920.00 2,498.00
Mandor OH
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Grendel Jendela bh 1.0000 35,000.00 35,000.00
JUMLAH HARGA BAHAN 35,000.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 62,478.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 62,478.00
6 1 M2 PASANG KACA, TEBAL5 MM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1600 99,920.00 15,987.20
Tukang Besi OH 0.1600 99,920.00 15,987.20
Kepala Tukang OH 0.1600 99,920.00 15,987.20
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 48,760.96
B. BAHAN
Kaca bh 1.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 48,760.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 48,760.96

7 1 M2 PASANG KACA TEMPERED TEBAL 5 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1600 99,920.00 15,987.20
Tukang Besi OH 0.1600 99,920.00 15,987.20
Kepala Tukang OH 0.1600 99,920.00 15,987.20
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 48,760.96
B. BAHAN
Kaca bh 1.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 48,760.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 48,760.96

8 1 M2 PASANG KACA TEMPERED TEBAL 6 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1600 99,920.00 15,987.20
Tukang Besi OH 0.1600 99,920.00 15,987.20
Kepala Tukang OH 0.1600 99,920.00 15,987.20
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 48,760.96
B. BAHAN
Kaca bh 1.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 48,760.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 48,760.96

9 1 M2 PASANG KACA TEMPERED TEBAL 12 MM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1600 99,920.00 15,987.20
Tukang Besi OH 0.1600 99,920.00 15,987.20
Kepala Tukang OH 0.1600 99,920.00 15,987.20
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 48,760.96
B. BAHAN
Kaca bh 1.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 48,760.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 48,760.96

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PASANG LANTAI UBIN PC ABU - ABU UKURAN (40 X 40) CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang Batu OH 0.125 99,920.00 12,490.00
Kepala Tukang OH 0.013 - -
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 38,768.96
B. BAHAN
Ubin abu-abu bh 6.63 - -
Semen kg 9.80 - -
Pasir Pasang m3 0.045 120,000.00 5,400.00
JUMLAH HARGA BAHAN 5,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 44,168.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 44,168.96

2 1 M2 PASANG LANTAI UBIN PC ABU - ABU UKURAN (30 X 30) CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang Batu OH 0.125 99,920.00 12,490.00
Kepala Tukang OH 0.013 - -
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 38,768.96
B. BAHAN ###
Ubin abu-abu bh 11.87 - -
Semen kg 10.00 - -
Pasir Pasang m3 0.045 120,000.00 5,400.00
JUMLAH HARGA BAHAN 5,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 44,168.96
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 44,168.96

3 1 M2 PASANG LANTAI UBIN PC ABU - ABU UKURAN (20 X 20) CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.270 99,920.00 26,978.40
Tukang Batu OH 0.135 99,920.00 13,489.20
Kepala Tukang OH 0.014 - -
Mandor OH 0.014 99,920.00 1,398.88
JUMLAH TENAGA KERJA 41,866.48
B. BAHAN
Ubin abu-abu bh 26.50 - -
Semen kg 10.40 - -
Pasir Pasang m3 0.045 120,000.00 5,400.00
JUMLAH HARGA BAHAN 5,400.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 47,266.48
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 47,266.48

4 1 M2 PASANG LANTAI UBIN WARNA UKURAN (40 X 40) CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang Batu OH 0.125 99,920.00 12,490.00
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 40,067.92
B. BAHAN
Ubin Warna 40 x 40 bh 6.63 - -
Semen kg 9.80 1,075.00 10,535.00
Pasir Pasang m3 0.045 120,000.00 5,400.00
Semen warna/semen grouting kg 0.60 - -
JUMLAH HARGA BAHAN 15,935.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 56,002.92
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 56,002.92

5 1 M2 PASANG LANTAI UBIN WARNA 30 X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.260 99,920.00 25,979.20
Tukang Batu OH 0.13 99,920.00 12,989.60
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 41,566.72
B. BAHAN
Ubin Warna 30 x 30 bh 11.87 - -
Semen kg 10.00 1,075.00 10,750.00
Pasir Pasang m3 0.045 120,000.00 5,400.00
Semen warna/semen grouting kg 0.60 2,000.00 1,200.00
JUMLAH HARGA BAHAN 17,350.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 58,916.72
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 58,916.72

6 1 M2 PASANG LANTAI UBIN WARNA 20 X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.270 99,920.00 26,978.40
Tukang Batu OH 0.135 99,920.00 13,489.20
Kepala Tukang OH 0.014 99,920.00 1,398.88
Mandor OH 0.014 99,920.00 1,398.88
JUMLAH TENAGA KERJA 43,265.36
B. BAHAN
Ubin Warna 20 x 20 bh 26.50 - -
Semen kg 10.40 1,075.00 11,180.00
Pasir Pasang m3 0.045 120,000.00 5,400.00
Semen warna/semen grouting kg 1.00 2,000.00 2,000.00
JUMLAH HARGA BAHAN 18,580.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 61,845.36
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 61,845.36

7 1 M2 PASANG LANTAI UBIN TERASO UKURAN 40 X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang Batu OH 0.125 99,920.00 12,490.00
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 40,067.92
B. BAHAN
Ubin Teraso 40 x 40 bh 6.63 - -
Semen Portland (Gersik) kg 9.80 1,075.00 10,535.00
Pasir Pasang m3 1.30 120,000.00 156,000.00
Semen warna/semen grouting kg 0.045 2,000.00 90.00
JUMLAH HARGA BAHAN 166,625.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 206,692.92
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 206,692.92
8 1 M2 PASANG LANTAI UBIN TERASO UKURAN 30 X 30 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.260 99,920.00 25,979.20
Tukang Batu OH 0.130 99,920.00 12,989.60
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 41,566.72
B. BAHAN
Ubin Teraso 40 x 40 bh 11.87 - -
Semen Portland (Gersik) kg 10.00 1,075.00 10,750.00
Pasir Pasang m3 1.50 120,000.00 180,000.00
Semen warna/semen grouting kg 0.045 2,000.00 90.00
JUMLAH HARGA BAHAN 190,840.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 232,406.72
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 232,406.72

9 1 M2 PASANG LANTAI UBIN GRANIT UKURAN 40 X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang Batu OH 0.125 99,920.00 12,490.00
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 40,067.92
B. BAHAN
Ubin Teraso 40 x 40 bh 6.63 - -
Semen Portland (Gersik) kg 9.80 1,075.00 10,535.00
Pasir Pasang m3 1.30 120,000.00 156,000.00
Semen warna/semen grouting kg 0.045 2,000.00 90.00
JUMLAH HARGA BAHAN 166,625.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 206,692.92
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 206,692.92

10 1 M2 PASANG LANTAI UBIN GRANIT UKURAN 30 X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.260 99,920.00 25,979.20
Tukang Batu OH 0.130 99,920.00 12,989.60
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 41,566.72
B. BAHAN
Ubin Granit 30 x 30 bh 11.87 - -
Semen Portland (Gersik) kg 10.00 1,075.00 10,750.00
Pasir Pasang m3 1.50 120,000.00 180,000.00
Semen warna/semen grouting kg 0.045 2,000.00 90.00
JUMLAH HARGA BAHAN 190,840.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 232,406.72
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 232,406.72

11 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 40 X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Pekerja OH 0.250 99,920.00 24,980.00
Tukang Batu OH 0.130 99,920.00 12,989.60
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 40,567.52
B. BAHAN
Marmer Granit 40 x 40 bh 6.63 - -
Semen Portland (Gersik) kg 9.80 1,075.00 10,535.00
Pasir Pasang m3 1.30 120,000.00 156,000.00
Semen warna/semen grouting kg 0.045 2,000.00 90.00
JUMLAH HARGA BAHAN 166,625.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 207,192.52
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 207,192.52

12 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 30 X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.260 99,920.00 25,979.20
Tukang Batu OH 0.130 99,920.00 12,989.60
Kepala Tukang OH 0.013 99,920.00 1,298.96
Mandor OH 0.013 99,920.00 1,298.96
JUMLAH TENAGA KERJA 41,566.72
B. BAHAN
Ubin Granit 30 x 30 bh 11.87 - -
Semen Portland (Gersik) kg 10.00 1,075.00 10,750.00
Pasir Pasang m3 1.50 120,000.00 180,000.00
Semen warna/semen grouting kg 0.045 2,000.00 90.00
JUMLAH HARGA BAHAN 190,840.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 232,406.72
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 232,406.72

13 1 M2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 60 X 60 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.24 99,920.00 23,980.80
Tukang Batu OH 0.12 99,920.00 11,990.40
Kepala Tukang OH 0.012 99,920.00 1,199.04
Mandor OH 0.012 99,920.00 1,199.04
JUMLAH TENAGA KERJA 38,369.28
B. BAHAN
Keramik 60 x 60 bh 3.10 - -
Semen kg 9.60 1,075.00 10,320.00
Pasir Pasang m3 0.045 120,000.00 5,400.00
Semen warna/semen grouting kg 1.50 2,000.00 3,000.00
JUMLAH HARGA BAHAN 18,720.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 57,089.28
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 57,089.28

14 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.7000 99,920.00 69,944.00
Tukang Batu OH 0.3500 99,920.00 34,972.00
Kepala Tukang OH 0.0350 99,920.00 3,497.20
Mandor OH 0.0350 99,920.00 3,497.20
JUMLAH TENAGA KERJA 111,910.40
B. BAHAN
Keramik 20 x 20 bh 26.5000 - -
Semen kg 10.4000 1,075.00 11,180.00
Pasir Pasang m3 0.0450 120,000.00 5,400.00
Semen warna/semen grouting kg 1.6200 2,000.00 3,240.00
JUMLAH HARGA BAHAN 19,820.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 131,730.40
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 131,730.40

15 1 M' PASANGPLINT UBIN PC ABU-ABU UKURAN 15 CM X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin PC bh 5.30 - -
Semen Portland kg 1.65 1,075.00 1,773.75
Pasir Pasang m3 0.004 120,000.00 480.00
JUMLAH HARGA BAHAN 2,253.75
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,638.23
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,638.23

16 1 M' PASANGPLINT UBIN PC ABU-ABU UKURAN 10 CM X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin PC bh 3.53 - -
Semen Portland kg 1.24 1,075.00 1,333.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,693.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,077.48
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,077.48

17 1 M' PASANGPLINT UBIN PC ABU-ABU UKURAN 10 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin PC bh 2.65 - -
Semen Portland kg 1.24 1,075.00 1,333.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,693.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,077.48
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,077.48

18 1 M' PASANGPLINT UBIN WARNA UKURAN 10 CM X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin warna bh 2.65 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.15 2,000.00 300.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,885.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,269.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,269.98

19 1 M' PASANGPLINT UBIN WARNA UKURAN 10 CM X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin warna bh 2.65 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.15 2,000.00 300.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,885.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,269.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,269.98

20 1 M' PASANGPLINT UBIN WARNA UKURAN 10 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin warna bh 2.65 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

21 1 M' PASANGPLINT UBIN TERASO UKURAN 10 CM X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin teraso bh 3.53 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98
22 1 M' PASANG PLINT UBIN TERASO UKURAN 10 CM X 40 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin teraso bh 2.65 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

23 1 M' PASANG PLINT UBIN GRANIT UKURAN 10 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin granit bh 2.65 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,585.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 20,969.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 20,969.98

24 1 M' PASANG PLINT UBIN GRANIT UKURAN 10 CM X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint ubin granit bh 3.53 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

25 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint teralux kerang bh 2.63 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

26 1 M' PASANG PLINT UBIN TERALUX KERANG UKURAN 10 CM X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint teralux kerang bh 3.53 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

27 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 CM X 60 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint teralux marmer bh 1.70 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

28 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint teralux marmer bh 2.65 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

29 1 M' PASANG PLINT UBIN TERALUX MARMER UKURAN 10 CM X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Plint teralux marmer bh 2.65 - -
Semen Portland kg 1.14 1,075.00 1,225.50
Semen Warna kg 0.10 2,000.00 200.00
Pasir Pasang m3 0.003 120,000.00 360.00
JUMLAH HARGA BAHAN 1,785.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 21,169.98
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 21,169.98

30 1 M2 PASANG LANTAI KERAMIK UKURAN 33 CM X 33 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.009 99,920.00 899.28
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Ubin keramik Doos 1.05 - -
Semen Portland (Gersik) Kg 10.00 1,075.00 10,750.00
Pasir Pasang M3 0.045 120,000.00 5,400.00
Semen Warna Kg 0.50 2,000.00 1,000.00

JUMLAH HARGA BAHAN 10,750.00


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 30,134.48
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 30,134.48

33 1 M2 PASANG LANTAI KERAMIK UKURAN 40 CM X 40 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.70 99,920.00 69,944.00
Tukang Batu OH 0.35 99,920.00 34,972.00
Kepala Tukang OH 0.035 99,920.00 3,497.20
Mandor OH 0.035 99,920.00 3,497.20
JUMLAH TENAGA KERJA 111,910.40
B. BAHAN
Keramik asia tile 40 x 40 Doos 1.05 - -
Semen Portland Kg 10.00 1,075.00 10,750.00
Pasir Pasang M3 0.045 120,000.00 5,400.00
Semen Warna Kg 0.50 2,000.00 1,000.00

JUMLAH HARGA BAHAN 17,150.00


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 129,060.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 129,060.40

34 1 M2 PASANG LANTAI KERAMIK UKURAN 20 CM X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.70 99,920.00 -
Tukang Batu OH 0.35 99,920.00 -
Kepala Tukang OH 0.035 99,920.00 -
Mandor OH 0.035 99,920.00 -
JUMLAH TENAGA KERJA -
B. BAHAN
Keramik asia tile 20 x 20 Doos 1.05 - -
Semen Portland (Gersik) Kg 10.40 1,075.00 11,180.00
Pasir Pasang M3 0.045 120,000.00 5,400.00
Semen Warna Kg 0.50 2,000.00 1,000.00

JUMLAH HARGA BAHAN 17,580.00


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 17,580.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 17,580.00
35 1 M2 PASANG LANTAI KERAMIK UKURAN 10 CM X 33 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.05 99,920.00 104,916.00
Tukang Batu OH 0.525 99,920.00 52,458.00
Kepala Tukang OH 0.053 99,920.00 5,295.76
Mandor OH 0.053 99,920.00 5,295.76
JUMLAH TENAGA KERJA 167,965.52
B. BAHAN
Ubin keramik bh 33.00 - -
Semen Portland (Gersik) Kg 9.80 1,075.00 10,535.00
Pasir Pasang M3 0.045 120,000.00 5,400.00
Semen Warna Kg 4.37 2,000.00 8,740.00

JUMLAH HARGA BAHAN 10,535.00


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 178,500.52
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 178,500.52

36 1 M2 PASANG LANTAI KERAMIK MOZAIK UKURAN 30 CM X 30 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.70 99,920.00 69,944.00
Tukang Batu OH 0.350 99,920.00 34,972.00
Kepala Tukang OH 0.035 99,920.00 3,497.20
Mandor OH 0.035 99,920.00 3,497.20
JUMLAH TENAGA KERJA 111,910.40
B. BAHAN
Ubin keramik Doos 11.87 - -
Semen Portland (Gersik) Kg 14.15 1,075.00 15,211.25
Pasir Pasang M3 0.039 120,000.00 4,680.00
Semen Warna Kg 2.00 2,000.00 4,000.00

JUMLAH HARGA BAHAN 15,211.25


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 127,121.65
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 127,121.65

35 1 M' PASANG PLINT KERAMIK UKURAN 10 CM X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 -
Tukang Batu OH 0.09 99,920.00 -
Kepala Tukang OH 0.035 99,920.00 -
Mandor OH 0.005 99,920.00 -
JUMLAH TENAGA KERJA -
B. BAHAN
Plint keramik Bh 5.30 - -
Semen Portland (Gersik) Kg 1.14 1,075.00 1,225.50
Pasir Pasang M3 0.003 120,000.00 360.00
Semen Warna Kg 0.025 2,000.00 50.00

JUMLAH HARGA BAHAN 1,635.50


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 1,635.50
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 1,635.50

36 1 M' PASANG PLINT KERAMIK UKURAN 10 CM X 10 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.035 99,920.00 3,497.20
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 21,982.40
B. BAHAN
Plint keramik Bh 10.60 - -
Semen Portland (Gersik) Kg 1.14 1,075.00 1,225.50
Pasir Pasang M3 0.003 120,000.00 360.00
Semen Warna Kg 0.05 2,000.00 100.00

JUMLAH HARGA BAHAN 1,225.50


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 23,207.90
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 23,207.90

37 1 M' PASANG PLINT KERAMIK UKURAN 5 CM X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.09 99,920.00 8,992.80
Tukang Batu OH 0.09 99,920.00 8,992.80
Kepala Tukang OH 0.035 99,920.00 3,497.20
Mandor OH 0.005 99,920.00 499.60
JUMLAH TENAGA KERJA 21,982.40
B. BAHAN
Plint keramik Bh 5.30 - -
Semen Portland (Gersik) Kg 0.57 1,075.00 612.75
Pasir Pasang M3 0.0015 120,000.00 180.00
Semen Warna Kg 0.013 2,000.00 26.00

JUMLAH HARGA BAHAN 612.75


C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 22,595.15
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 22,595.15

38 1 M2 PASANG DINDING KERAMIK 10 CM X 20 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.90 99,920.00 89,928.00
Tukang Batu OH 0.45 99,920.00 44,964.00
Kepala Tukang OH 0.045 99,920.00 4,496.40
Mandor OH 0.045 99,920.00 4,496.40
JUMLAH TENAGA KERJA 143,884.80
B. BAHAN
Keramik dinding buah 53.00 - -
Semen Portland Kg 9.30 1,075.00 9,997.50
Pasir pasang M3 0.018 120,000.00 2,160.00
Semen warna Kg 2.75 2,000.00 5,500.00
JUMLAH HARGA BAHAN 9,997.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 153,882.30
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 153,882.30

36 1 M2 PASANG DINDING KERAMIK 20 CM X 25 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.90 99,920.00 -
Tukang Batu OH 0.45 99,920.00 -
Kepala Tukang OH 0.045 99,920.00 -
Mandor OH 0.045 99,920.00 -
JUMLAH TENAGA KERJA -
B. BAHAN
Keramik asia tile 20 x 25 buah 26.50 - -
Semen Portland Kg 9.30 1,075.00 9,997.50
Pasir pasang M3 0.018 120,000.00 2,160.00
Semen warna Kg 1.94 2,000.00 3,880.00
JUMLAH HARGA BAHAN 16,037.50
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 16,037.50
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 16,037.50
37 1 M2 PASANG DINDING MARMER 100 CM X 100 CM
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.30 99,920.00 129,896.00
Tukang Batu OH 0.65 99,920.00 64,948.00
Kepala Tukang OH 0.065 99,920.00 6,494.80
Mandor OH 0.065 99,920.00 6,494.80
JUMLAH TENAGA KERJA 207,833.60
B. BAHAN
Keramik dinding buah 1.06 - -
Semen Portland Kg 12.44 1,075.00 13,373.00
Pasir pasang M3 0.025 120,000.00 3,000.00
Semen warna Kg 0.65 2,000.00 1,300.00
Paku 12 cm buah 3.03 13,000.00 39,390.00
JUMLAH HARGA BAHAN
13,373.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 221,206.60
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 221,206.60

37 1 M2 PEMASANGAN PAVING BLOCK NATURAL Tebal 6 cm ( 20x20 cm)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.5000 99,920.00 49,960.00
Pekerja OH 0.2500 99,920.00 24,980.00
Kepala tukang OH 0.0500 99,920.00 4,996.00
Mandor OH 0.0013 99,920.00 129.90
JUMLAH TENAGA K ` 80,065.90
B. BAHAN
Paving 20 x 20 cm tebal 6 cm K225 m2 1.01 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT C.

D. Jumlah (A + B + C) 80,065.90
E. Overhead & Profit 5 %xD 4,003.29
F. Harga Satuan Pekerjaan (D+E) 84,069.19
F.

42 1 M2 PEMASANGAN PAVING BLOCK BERWARNA Tebal 6 cm ( 20x20 cm)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.5000 115,000.00 57,500.00
Pekerja OH 0.2500 99,920.00 24,980.00
Kepala tukang OH 0.0500 120,000.00 6,000.00
Mandor OH 0.0013 130,000.00 169.00
JUMLAH TENAGA K ` 88,649.00
B. BAHAN
Paving 20 x 20 cm tebal 6 cm K225 ( Warna ) m2 1.01 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 189,669.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 189,669.00

43 1 M2 PEMASANGAN PAVING BLOCK BERWARNA Tebal 8 cm ( 20x20 cm)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.5000 115,000.00 57,500.00
Pekerja OH 0.5000 99,920.00 49,960.00
Kepala tukang OH 0.0500 120,000.00 6,000.00
Mandor OH 0.0013 130,000.00 169.00
JUMLAH TENAGA K ` 113,629.00
B. BAHAN
Paving 20 x 20 cm tebal 8 cm K225 ( Warna ) m2 1.01 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 113,629.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 113,629.00

44 1 M2 PEMASANGAN PAVING BLOCK NATURAL Tebal 8 cm ( 20x20 cm)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.5000 115,000.00 57,500.00
Pekerja OH 0.5000 99,920.00 49,960.00
Kepala tukang OH 0.0500 120,000.00 6,000.00
Mandor OH 0.0013 130,000.00 169.00
JUMLAH TENAGA K ` 113,629.00
B. BAHAN
Paving 20 x 20 cm tebal 8 cm K225 ( Natural ) m2 1.01 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 113,629.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 113,629.00

XIV PEKERJAAN PENGECATAN (PERMEN PUPR 28/PRT/M/2016)


1 1 M2 PEKERJAAN MENGIKIS ATAU MENGEROK CAT TEMBOK CARA MANUAL
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 15,787.36
B. BAHAN
Kapi bh 0.0500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 15,787.36
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 15,787.36

2 1 M2 PEKERJAAN LAPIS PLAMIR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0200 99,920.00 1,998.40
Tukang cat OH 0.0300 99,920.00 2,997.60
Kepala Tukang OH 0.0030 99,920.00 299.76
Mandor OH 0.0010 99,920.00 99.92
JUMLAH TENAGA KERJA 5,395.68
B. BAHAN
Plamir Tembok kg 0.1000 -
Amplas Lbr 0.5000 -
Kapi bh 0.0500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 5,395.68
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 5,395.68

38 1 M2 PENGECATAN TEMBOK BARU INTERIOR (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0200 99,920.00 1,998.40
Tukang cat OH 0.0630 99,920.00 6,294.96
Kepala Tukang OH 0.0063 99,920.00 629.50
Mandor OH 0.0025 99,920.00 249.80
JUMLAH TENAGA KERJA 9,172.66
B. BAHAN
Plamir kg 0.1000 17,000.00 1,700.00
Cat dasar kg 0.1000 28,000.00 2,800.00
Cat Penutup 2x (dulux) kg 0.2600 - -
JUMLAH HARGA BAHAN 4,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 13,672.66
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 13,672.66

38 1 M2 PENGECATAN TEMBOK BARU EKSTERIOR (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0200 99,920.00 1,998.40
Tukang cat OH 0.0630 99,920.00 6,294.96
Kepala Tukang OH 0.0063 99,920.00 629.50
Mandor OH 0.0025 99,920.00 249.80
JUMLAH TENAGA KERJA 9,172.66
B. BAHAN
Plamir kg 0.1000 17,000.00 1,700.00
Cat dasar kg 0.1000 28,000.00 2,800.00
Cat Penutup 2x (Dulux) kg 0.2600 - -
JUMLAH HARGA BAHAN 4,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 13,672.66
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 13,672.66
4 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN KUAS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0600 99,920.00 5,995.20
Tukang cat OH 0.0500 99,920.00 4,996.00
Kepala Tukang OH 0.0050 99,920.00 499.60
Mandor OH 0.0030 99,920.00 299.76
JUMLAH TENAGA KERJA 11,790.56
B. BAHAN
Cat Tembok Vinilex kg 0.2400 35,000.00 8,400.00
Kuas Bh 0.0150 10,000.00 150.00
JUMLAH HARGA BAHAN 8,550.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 20,340.56
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 20,340.56

5 1 M2 PEKERJAAN PENGECATAN BIDANG TEMBOK LAMA 2 LAPIS DENGAN ROLL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0400 99,920.00 3,996.80
Tukang cat OH 0.0300 99,920.00 2,997.60
Kepala Tukang OH 0.0030 99,920.00 299.76
Mandor OH 0.0020 99,920.00 199.84
JUMLAH TENAGA KERJA 7,494.00
B. BAHAN
Cat Tembok Vinilex kg 0.4700 35,000.00 16,450.00
Roll Bh 0.0100 - -
JUMLAH HARGA BAHAN 16,450.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 23,944.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 23,944.00

6 1 M2 PEKERJAAN PENGECATAN LANGIT -LANGIT 2 LAPIS DENGAN CAT TEMBOK MENGGUNAKAN KUAS TERMASUK PLAMIR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0800 99,920.00 7,993.60
Tukang cat OH 0.0600 99,920.00 5,995.20
Kepala Tukang OH 0.0060 99,920.00 599.52
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 14,988.00
B. BAHAN
Plamir Tembok kg 0.1000 -
Cat Tembok Vinilex Kg 0.2400 35,000.00 8,400.00
Amplas Lbr 0.5000 -
Kuas Bh 0.0150 10,000.00 150.00
Kapi Bh 0.0500 - -
JUMLAH HARGA BAHAN 8,550.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 23,538.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 23,538.00

39 1 M2 PEKERJAAN PENGECATAN PLAFOND 2 LAPIS DENGAN CAT TEMBOK MENGGUNAKAN ROLL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0600 99,920.00 5,995.20
Tukang cat OH 0.0400 99,920.00 3,996.80
Kepala Tukang OH 0.0040 99,920.00 399.68
Mandor OH 0.0030 99,920.00 299.76
JUMLAH TENAGA KERJA 10,691.44
B. BAHAN
Plamir Tembok kg 0.1000 17,000.00 1,700.00
Cat Tembok (Weldon) Kg 0.4700 - -
Amplas Lbr 0.5000 5,000.00 2,500.00
Roll Bh 0.0100 - -
Kapi Bh 0.0500 - -
JUMLAH HARGA BAHAN 4,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 14,891.44
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 14,891.44

8 1 M2 WATERPROOFING
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0150 99,920.00 1,498.80
Tukang cat OH 0.1600 99,920.00 15,987.20
Kepala Tukang OH 0.0140 99,920.00 1,398.88
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Waterprofing dumplix 3 kg 0.4500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 19,384.48
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 19,384.48

9 1 M2 PEKERJAAN PASANG WALL PAPER DENGAN PEREKAT SILK HOUSE


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0100 99,920.00 999.20
Tukang cat OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 12,490.00
B. BAHAN
Wall Paper m2 1.1000 - -
Perekat Kg 0.2000 -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 12,490.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 12,490.00

10 1 M2 PEKERJAAN MELAPIS MENI KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0750 99,920.00 7,494.00
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 7,893.68
B. BAHAN
Meni kg 0.1700 - -
Minyak Cat ltr 0.1000 - -
Kuas bh 0.0150 10,000.00 150.00
JUMLAH HARGA BAHAN 150.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 8,043.68
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 8,043.68

11 1 M2 PEKERJAAN MENDEMPUL ATAU MEMPLAMIR DAN MENGGOSOK KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)
A. TENAGA
Tukang cat OH 0.1100 99,920.00 10,991.20
Kepala Tukang OH 0.0110 99,920.00 1,099.12
JUMLAH TENAGA KERJA 12,090.32
B. BAHAN
Dempul kayu kg 0.1500 - -
Plamir Kayu Kg 0.0080 - -
Minyak Cat Ltr 0.1000 - -
Amplas Lbr 1.0000 5,000.00 5,000.00
Kuas Bh 0.0150 10,000.00 150.00
JUMLAH HARGA BAHAN 5,150.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 17,240.32
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 17,240.32

12 1 M2 PEKERJAAN PENGECATAN DASAR 1 LAPIS PADA KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang cat OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 8,293.36
B. BAHAN
Cat Dasar Kg 0.1700 - -
Minyak Cat Ltr 0.1000 - -
Amplas Lbr 1.0000 5,000.00 5,000.00
Kuas Bh 0.0150 10,000.00 150.00
JUMLAH HARGA BAHAN 5,150.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 13,443.36
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 13,443.36

13 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA KAYU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang cat OH 0.1500 99,920.00 14,988.00
Kepala Tukang OH 0.0150 99,920.00 1,498.80
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 32,274.16
B. BAHAN
Cat Tembok Vinilex kg 0.3000 35,000.00 10,500.00
Minyak Cat Ltr 0.2000 - -
Kuas Bh 0.0200 10,000.00 200.00
JUMLAH HARGA BAHAN 10,700.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 42,974.16
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 42,974.16

14 1 M2 PEKERJAAN MENGEROK KARAT ATAU CAT PADA PERMUKAAN BAJA DENGAN SODA API
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.3000 99,920.00 29,976.00
Mandor OH 0.0150 99,920.00 1,498.80
JUMLAH TENAGA KERJA 31,474.80
B. BAHAN
Amplas Lbr 0.5000 5,000.00 2,500.00
Sikat Baja Bh 0.0500 - -
Soda Api Kg 0.0500 - -
JUMLAH HARGA BAHAN 2,500.00
C. PERALATAN
JUMLAH HARGA ALAT
D. Jumlah (A + B + C) 33,974.80
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 33,974.80

15 1 M2 PEKERJAAN MELAPIS MENI PADA PERMUKAAN BAJA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0750 99,920.00 7,494.00
Mandor OH 0.0040 99,920.00 399.68
JUMLAH TENAGA KERJA 7,893.68
B. BAHAN
Meni kg 0.1000 - -
Minyak Cat Kg 0.1000 - -
Amplas Bh 0.5000 5,000.00 2,500.00
Kuas Bh 0.0150 10,000.00 150.00
JUMLAH HARGA BAHAN 2,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 10,543.68
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 10,543.68

16 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA SECARA MANUAL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang cat OH 0.1500 99,920.00 14,988.00
Kepala Tukang OH 0.0150 99,920.00 1,498.80
Mandor OH 0.0080 99,920.00 799.36
JUMLAH TENAGA KERJA 32,274.16
B. BAHAN
Cat Warna Zingkronasi Kg 0.2000 - -
Minyak Cat Kg 0.1000 - -
Kuas Bh 0.0200 10,000.00 200.00
JUMLAH HARGA BAHAN 200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 32,474.16
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 32,474.16

17 1 M2 PEKERJAAN MENGECAT PENUTUP 2 LAPIS PADA PERMUKAAN BAJA/KAYU DENGAN SEMPROT


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0200 99,920.00 1,998.40
Tukang cat OH 0.1500 99,920.00 14,988.00
Kepala Tukang OH 0.0010 99,920.00 99.92
Mandor OH 0.0010 99,920.00 99.92
JUMLAH TENAGA KERJA 17,186.24
B. BAHAN
Cat Warna Zingkronasi Kg 0.4000 - -
Minyak Cat Kg 0.1000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 17,186.24
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 17,186.24

18 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN TEAK OIL


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang cat OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 10,991.20
B. BAHAN
Teak Oil Ltr 0.3000 - -
Amplas Lbr 0.5000 5,000.00 2,500.00
Kuas Bh 0.0150 10,000.00 150.00
JUMLAH HARGA BAHAN 2,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 13,641.20
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 13,641.20

40 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN POLITUR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2500 99,920.00 24,980.00
Tukang cat OH 0.2500 99,920.00 24,980.00
Kepala Tukang OH 0.0250 99,920.00 2,498.00
Mandor OH 0.0130 99,920.00 1,298.96
JUMLAH TENAGA KERJA 53,756.96
B. BAHAN
Wood Filler Kg 0.1000 16,000.00 1,600.00
Politur Jadi Ltr 0.2000 32,000.00 6,400.00
Amplas Lbr 1.0000 5,000.00 5,000.00
Kuas Bh 0.0200 10,000.00 200.00
JUMLAH HARGA BAHAN 13,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 66,956.96
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 66,956.96
20 1 M2 PEKERJAAN PELAPISAN BIDANG KAYU DENGAN VERNIS 2 LAPIS
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang cat OH 0.1000 99,920.00 9,992.00
Kepala Tukang OH 0.0100 99,920.00 999.20
JUMLAH TENAGA KERJA 10,991.20
B. BAHAN
Vernis Ltr 0.3000 - -
Amplas Lbr 0.5000 5,000.00 2,500.00
Kuas Bh 0.0200 10,000.00 200.00
JUMLAH HARGA BAHAN 2,700.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 13,691.20
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 13,691.20

1 M2 Pekerjaan Finish Court Coating 2 Kali


21
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.1500 99,920.00 14,988.00
Tukang Cat OH 0.0630 99,920.00 6,294.96
Kepala Tukang OH 0.0063 99,920.00 629.50
Mandor OH 0.0025 99,920.00 249.80
JUMLAH TENAGA KERJA 22,162.26
B. BAHAN
(TENNOKOTE Tipe TNK-1000 WA) Ltr 1.5000 - -
Kuas Bh 0.0200 10,000.00 200.00
JUMLAH HARGA BAHAN 200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 22,362.26
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 22,362.26

XVII PEKERJAAN ELEKTRIKAL (PERMEN PUPR 28/PRT/2016)


41 1 TITIK INSTALASI STOP KONTAK, LAMPU, EXHAUST FAN DAN CEILING FAN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000 15,000.00 15,000.00
JUMLAH TENAGA KERJA 15,000.00
B. BAHAN
Kabel NYM 3 x 2.5 mm ex. Supreme m1 8.0000 10,000.00 80,000.00
Pipa Clipsal 20 mm hitam bt 3.0000 4,000.00 12,000.00
Tee dos clipsal 20 mm hitam bh 2.0000 500.00 1,000.00
Klem clipsal 20 mm hitam bj 15.0000 100.00 1,500.00
Sock clipsal 20 mm hitam bj 3.0000 900.00 2,700.00
Inbow dos plastik clipsal E 157 P bj 1.0000 - -
JUMLAH HARGA BAHAN 97,200.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 112,200.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 112,200.00

2 1 TITIK INSTALASI AC
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000 65,000.00 65,000.00
JUMLAH TENAGA KERJA 65,000.00
B. BAHAN
Kabel NYM 3 x 2.5 mm ex. Supreme m1 10.0000 10,000.00 100,000.00
Pipa Clipsal 20 mm hitam bt 3.0000 4,000.00 12,000.00
Tee dos clipsal 20 mm hitam bh 1.0000 500.00 500.00
Klem clipsal 20 mm hitam bj 15.0000 100.00 1,500.00
Sock clipsal 20 mm hitam bj 4.0000 900.00 3,600.00
Inbow dos plastik clipsal E 157 P bj 1.0000 - -
Pipa flexible clipsal 20 mm hitam m1 1.0000 4,000.00 4,000.00
JUMLAH HARGA BAHAN 121,600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 186,600.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 186,600.00

3 1 TITIK INSTALASI TELEPHONE


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000 65,000.00 65,000.00
JUMLAH TENAGA KERJA 65,000.00
B. BAHAN
Kabel Telephone m1 25.0000 - -
Pipa Clipsal 20 mm hitam bt 8.0000 4,000.00 32,000.00
Tee dos clipsal 20 mm hitam bh 1.0000 500.00 500.00
Klem clipsal 20 mm hitam bj 25.0000 100.00 2,500.00
Sock clipsal 20 mm hitam bj 5.0000 900.00 4,500.00
Inbow dos plastik clipsal E 157 P bj 1.0000 - -
JUMLAH HARGA BAHAN 39,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 104,500.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 104,500.00

4 1 TITIK INSTALASI MATV


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000 65,000.00 65,000.00
JUMLAH TENAGA KERJA 65,000.00
B. BAHAN
Coaxial cable 5C-75 ohm commscof m1 20.0000 - -
Pipa Clipsal 20 mm hitam bt 6.0000 900.00 5,400.00
Tee dos clipsal 20 mm hitam bh 2.0000 500.00 1,000.00
Klem clipsal 20 mm hitam bj 20.0000 100.00 2,000.00
Sock clipsal 20 mm hitam bj 6.0000 900.00 5,400.00
Inbow dos plastik clipsal E 157 P bj 1.0000 - -
JUMLAH HARGA BAHAN 13,800.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 78,800.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 78,800.00

42 1 TITIK PEMASANGAN LAMPU


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Biaya Pasang ttk 1.0000 15,000.00 15,000.00
JUMLAH TENAGA KERJA 15,000.00
B. BAHAN
Lampu LED Philip 13 watt bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 15,000.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 15,000.00
XVIII PEKERJAAN ANGKUT MATERIAL DAN/ ATAU HASIL GALIAN (PERMEN PUPR 28/PRT/M/2016)
1 MENGANGKUT 1 M3 MATERIAL ATAU HASIL GALIAN DENGAN JARAK ANGKUT 50 M'
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.4220 99,920.00 42,166.24
Mandor OH 0.0211 99,920.00 2,108.31
JUMLAH TENAGA KERJA 44,274.55
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 44,274.55
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 44,274.55

2 MENGANGKUT 1 M3 MATERIAL ATAU HASIL GALIAN DENGAN JARAK ANGKUT 100 M'
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.6000 99,920.00 59,952.00
Mandor OH 0.0300 130,000.00 3,900.00
JUMLAH TENAGA KERJA 63,852.00
B. BAHAN
JUMLAH HARGA BAHAN
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 63,852.00
E. Overhead & Profit 0 %xD -
F. Harga Satuan Pekerjaan (D+E) 63,852.00

33 1 M2 MEMASANG RANGKA KUDA - KUDA BAJA RINGAN C 75


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 -
Tukang Besi OH 0.4500 - -
Kepala Tukang OH 0.0100 - -
Mandor OH 0.0500 -
JUMLAH TENAGA KERJA -
B. BAHAN
C-75, 0.8 m' 0.4960 - -
C-75, 0.6 m' 0.7440 - -
Baut bh 5.6000 - -
Dynabolt bh 0.8000 - -
Reng m' 1.8000 - -
Talang Jurai m' 0.0620 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) -
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) -

43
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.120 99,920.00 11,990.40
Tukang listrik OH 0.060 99,920.00 5,995.20
Kepala tukang OH 0.010 99,920.00 999.20
Mandor OH 0.003 99,920.00 299.76
JUMLAH TENAGA KERJA 19,284.56
B. BAHAN
Kap Lampu RM TL 8 x 18 watt Philips unit 1.0000 - -
Lampu TL 18 Watt bh 2.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 19,284.56
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 19,284.56
44 1 BH SAKLAR TUNGGAL/SINGLE 1 GANG 1 WAY, 10 A
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang listrik OH 0.050 99,920.00 4,996.00
Kepala tukang OH 0.002 99,920.00 199.84
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 15,287.76
B. BAHAN
Saklar Tunggal / single 1 gang 1 way, 10 A unit 1.0000 45,000.00 45,000.00
Material bantu % 5.0000 45,000.00 2,250.00
JUMLAH HARGA BAHAN 47,250.00
C. PERALATAN
% 3.0000 47,250.00 1,417.50
JUMLAH HARGA ALAT 1,417.50

D. Jumlah (A + B + C) 63,955.26
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 63,955.26
45 1 BH PEMASANGAN MCB
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang listrik OH 0.050 99,920.00 4,996.00
Kepala tukang OH 0.002 99,920.00 199.84
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 15,287.76
B. BAHAN
MCB 3 phase 40 A MG unit 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 15,287.76
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 15,287.76

46 1 BH SAKLAR TUNGGAL/SINGLE 1 GANG 1 WAY, 10 A


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang listrik OH 0.050 99,920.00 4,996.00
Kepala tukang OH 0.002 99,920.00 199.84
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 15,287.76
B. BAHAN
Saklar Tunggal / single 1 gang 1 way, 10 A unit 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 15,287.76
E. Overhead & Profit 5 %xD 764.39
F. Harga Satuan Pekerjaan (D+E) 16,052.15
47 1 BH SAKLAR GANDA/DOUBLE 2 GANG 2 WAY, 10 A
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang listrik OH 0.100 99,920.00 9,992.00
Kepala tukang OH 0.002 99,920.00 199.84
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 20,283.76
B. BAHAN
Saklar Seri / double 2 gang 2 way, 10 A unit 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 20,283.76
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 20,283.76

48 1 BH CEILING EXHAUST FAN 50 CFM TYPE SIROCCO


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500 99,920.00 49,960.00
Tukang listrik OH 0.400 99,920.00 39,968.00
Kepala tukang OH 0.020 99,920.00 1,998.40
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 92,026.32
B. BAHAN
Ceiling Exhaust Fan 50 cfm type sirocco unit 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 92,026.32
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 92,026.32
49 1 BH GROUNDING PENANGKAL PETIR TAHANAN MAKSIMAL 5 Ω
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.000 99,920.00 99,920.00
Tukang listrik OH 1.000 99,920.00 99,920.00
Kepala tukang OH 0.500 99,920.00 49,960.00
Mandor OH 0.020 99,920.00 1,998.40
JUMLAH TENAGA KERJA 251,798.40
B. BAHAN
Bor tanah untuk grounding dalam 6 m los 1.0000 - -
Blitzem unit 1.0000 - -
BC 50 mm² m 10.0000 - -
Box control lot 1.0000 - -
Material bantu % 15.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 5.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 251,798.40
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 251,798.40

50 1 BH AIR TERMINAL PENANGKAL PETIR


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 1.000 99,920.00 99,920.00
Tukang listrik OH 1.000 99,920.00 99,920.00
Kepala tukang OH 0.500 99,920.00 49,960.00
Mandor OH 0.020 99,920.00 1,998.40
JUMLAH TENAGA KERJA 251,798.40
B. BAHAN
Tiang penangkal pipa galvanized Ø ¾" panjang 1,5 m unit 1.0000 - -
Blitzem unit 1.0000 - -
Isolasi unit 1.0000 5,000.00 5,000.00
Timah cor btg 1.0000 - -
Material bantu % 15.0000 5,000.00 750.00
JUMLAH HARGA BAHAN 5,750.00
C. PERALATAN
% 5.0000 5,750.00 287.50
JUMLAH HARGA ALAT 287.50

D. Jumlah (A + B + C) 257,835.90
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 257,835.90
51 1 M3 PASANGAN BATU KARANG & PASIR
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.500 99,920.00 49,960.00
Mandor OH 0.050 99,920.00 4,996.00
JUMLAH TENAGA KERJA 54,956.00
B. BAHAN
batu karang m 0.6000 - -
Pasir urug m 0.6000 100,000.00 60,000.00
JUMLAH HARGA BAHAN 60,000.00
C. PERALATAN

JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 114,956.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 114,956.00

38 1 M PASANGAN BUIS BETON DIAMETER 100 CM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Tukang Batu OH 0.0750 99,920.00 7,494.00
Kepala Tukang OH 0.0075 99,920.00 749.40
Pekerja OH 0.2000 99,920.00 19,984.00
Mandor OH 0.0200 99,920.00 1,998.40
JUMLAH TENAGA KERJA 30,225.80
B BAHAN
Buis Beton Diameter 100 cm BJ 1.0000 120,000.00 120,000.00
Semen 40 Kg Zak 0.0030 - -
Pasir Pasang m3 0.0130 120,000.00 1,560.00
JUMLAH HARGA BAHAN 121,560.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 151,785.80
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 151,785.80
51 INSTALASI GROUNDING BC 50 MM2 IN CONDUIT
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.060 99,920.00 5,995.20
Tukang listrik OH 0.050 99,920.00 4,996.00
Kepala tukang OH 0.001 99,920.00 99.92
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 11,191.04
B. BAHAN
BC 50 mm² m 1.0000 - -
conduit m 1.0000 - -
soket bh 0.3000 - -
klem bh 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 5.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 11,191.04
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 11,191.04

52 1 M2 PASANGAN PINTU HARMONIKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.440 99,920.00 43,964.80
Tukang OH 0.440 99,920.00 43,964.80
Kepala tukang OH 0.044 99,920.00 4,396.48
Mandor OH 0.022 99,920.00 2,198.24
JUMLAH TENAGA KERJA 94,524.32
B. BAHAN
Pintu Harmonika m2 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 94,524.32
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 94,524.32
53 1 BH PASANG JARO JENDELA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja ls 1.000 30,000.00 30,000.00
JUMLAH TENAGA KERJA 30,000.00
B. BAHAN
Jaro betet bh 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 30,000.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 30,000.00

54 1 BH PASANG PINTU SHAFT


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Pekerja ls 1.000 60,000.00 60,000.00
JUMLAH TENAGA KERJA 60,000.00
B. BAHAN
Pintu Shaft bh 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 60,000.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 60,000.00
55 1 UNIT PERESAPAN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Pekerja ls 1.000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Material Peresapan Komplit ls 1.0000 #REF! #REF!
Material bantu % 5.0000 #REF! #REF!
JUMLAH HARGA BAHAN #REF!
C. PERALATAN
% 3.0000 #REF! #REF!
JUMLAH HARGA ALAT #REF!

D. Jumlah (A + B + C) #REF!
E. Overhead & Profit 5 %xD #REF!
F. Harga Satuan Pekerjaan (D+E) #REF!

56 1 UNIT SEPTITANK
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Pekerja ls 1.000 - -
JUMLAH TENAGA KERJA -
B. BAHAN
Material Septitank Komplit ls 1.0000 #REF! #REF!
Material bantu % 10.0000 #REF! #REF!
JUMLAH HARGA BAHAN #REF!
C. PERALATAN
% 5.0000 #REF! #REF!
JUMLAH HARGA ALAT #REF!

D. Jumlah (A + B + C) #REF!
E. Overhead & Profit 5 %xD #REF!
F. Harga Satuan Pekerjaan (D+E) #REF!

57 1 UNIT GROUNDTANK
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Pekerja ls 1.000 110,000.00 110,000.00
JUMLAH TENAGA KERJA 110,000.00
B. BAHAN
Material Groundtank Komplit ls 1.0000 - -
Material bantu % 10.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 5.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 110,000.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 110,000.00

58 1 BH GATE VALVE Ø 1"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Pipa OH 0.300 99,920.00 29,976.00
Kepala tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 61,550.72
B. BAHAN
Gate Valve Ø 1" m 1.0000 - -
Material bantu % 10.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 5.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 61,550.72
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 61,550.72
59 1 BH Pompa Booster c/w acessories JP Basic 3
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang Pipa OH 0.300 99,920.00 29,976.00
Kepala tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 61,550.72
B. BAHAN
Pompa Booster JP Basic 3 unit 1.0000 - -
Material bantu & acessories % 5.0000 - -
Suport/dudukan lot 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 5.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 61,550.72
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 61,550.72

60 1 BH PANEL ELEKTRIKAL POMPA BOOSTER


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 3.000 99,920.00 299,760.00
Tukang Listrik OH 3.000 99,920.00 299,760.00
Kepala tukang OH 1.000 99,920.00 99,920.00
Mandor OH 0.500 99,920.00 49,960.00
JUMLAH TENAGA KERJA 749,400.00
B. BAHAN
MCB 16 A unit 1.0000 - -
MCB 10 A unit 3.0000 - -
PILOT LAMP unit 3.0000 - -
Fuse - 3 A unit 3.0000 - -
Push Button unit 2.0000 - -
Kontaktor unit 1.0000 - -
Water level control unit 1.0000 - -
Box panel 400 x 300 x 200 type outdoor unit 1.0000 - -
Material bantu % 10.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 5.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 749,400.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 749,400.00
61 1 UNIT WAYER LEVEL CONTROL (WLC)
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.350 99,920.00 34,972.00
Tukang listrik OH 0.300 99,920.00 29,976.00
Kepala tukang OH 0.100 99,920.00 9,992.00
Mandor OH 0.010 99,920.00 999.20
JUMLAH TENAGA KERJA 75,939.20
B. BAHAN
Water Level Control (WLC) unit 1.0000 - -
Material bantu % 10.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 75,939.20
E. Overhead & Profit 5 %xD 3,796.96
F. Harga Satuan Pekerjaan (D+E) 79,736.16

62 1 UNIT CHECK VALVE Ø 1"


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang pipa OH 0.300 99,920.00 29,976.00
Kepala tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 61,550.72
B. BAHAN
Check Valve Ø 1" unit 1.0000 - -
Material bantu % 10.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 61,550.72
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 61,550.72
63 1 BH FLOOR DRAIN
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.300 99,920.00 29,976.00
Tukang pipa OH 0.300 99,920.00 29,976.00
Kepala tukang OH 0.015 99,920.00 1,498.80
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 61,550.72
B. BAHAN
Floor Drain Stainless unit 1.0000 - -
Material bantu % 5.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
% 3.0000 - -
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 61,550.72
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 61,550.72

64 1 M2 MEMASANG ATAP BAJA RINGAN UK 75


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.2000 99,920.00 19,984.00
Tukang Besi OH 0.4500 99,920.00 44,964.00
Kepala Tukang OH 0.0100 99,920.00 999.20
Mandor OH 0.0500 99,920.00 4,996.00
JUMLAH TENAGA KERJA 70,943.20
B. BAHAN
UK Galvalume -75 m' 1.4880 - -
Baut bh 28.0000 - -
Dynabolt bh 1.6000 - -
Reng m' 3.6000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 70,943.20
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 70,943.20
65 1 M2 MEMASANG PAGAR BRC
KOEFISIEN
NO. URAIAN SATUAN

A. TENAGA
Pekerja OH 0.3750 99,920.00 -
Tukang Batu OH 0.1250 99,920.00 -
Kepala Tukang OH 0.0120 99,920.00 1,199.04
Mandor OH 0.0190 99,920.00 1,898.48
JUMLAH TENAGA KERJA 3,097.52
B. BAHAN
BRC t = 1.2 m Ø 6 lengkap dengan tiang lbr 0.4340 - -
Semen Portland kg 2.0000 - -
Kawat Duri kg 2.5000 - -
Pasir Beton m3 0.0050 120,000.00 600.00
Koral Beton m3 0.0090 - -
JUMLAH HARGA BAHAN 600.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 3,697.52
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 3,697.52

66 1 M2 PASANGAN BATA GOSOK 1 MUKA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 99,920.00 99,920.00
JUMLAH TENAGA KERJA 99,920.00
B. BAHAN
Bata Gosok bh 55.0000 1,100.00 60,500.00
Semen 50 Kg kg 4.2000 - -
JUMLAH HARGA BAHAN 60,500.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 160,420.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 160,420.00
67 1 M2 PASANGAN PARAS 1 MUKA
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 99,920.00 99,920.00
JUMLAH TENAGA KERJA 99,920.00
B. BAHAN
Batu Paras m2 18.3333 - -
Semen 50 Kg kg 4.2000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 99,920.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 99,920.00

68 1 BH PASANGAN CEILLING SPEAKER


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 70,000.00 70,000.00
JUMLAH TENAGA KERJA 70,000.00
B. BAHAN
Speaker Ceiling Toa ZS-646R bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 70,000.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 70,000.00

1 1 BH PASANGAN CENTRAL SOUNDSYSTEM


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Upah Kerja (Lumpsum) ls 1.0000 70,000.00 70,000.00
JUMLAH TENAGA KERJA 70,000.00
B. BAHAN
Amplifier TOA ZA 2120 ORIGINAL 120 WATT bh 1.0000 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT -

D. Jumlah (A + B + C) 70,000.00
E. Overhead & Profit 5 %xD
F. Harga Satuan Pekerjaan (D+E) 70,000.00

Pemasangan 1 buah titik lampu

Jumlah
Harga Satuan
No Uraian Satuan Koefisien Harga
(Rp)
(Rp)

A TENAGA
Pekerja OH 0.050 99,920.00 4,996.00
Tukang listrik OH 0.020 99,920.00 1,998.40
Kepala tukang OH 0.100 99,920.00 9,992.00
Mandor OH 0.1000 99,920.00 9,992.00
JUMLAH TENAGA KERJA 26,978.40
B BAHAN
Kabel NYM D106 mm2 m 6.000 - -
Isolasi bh 0.500 5,000.00 2,500.00
Klem bh 3.000 - -
JUMLAH HARGA BAHAN 2,500.00
C PERALATAN

JUMLAH HARGA ALAT -

D Jumlah (A+B+C) 29,478.40


E Overhead & Profit 0% ###
F Harga Satuan Pekerjaan (D+E) 29,478.40
Pemasangan 1 bh lampuRMI TL 2 x 36 watt
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang listrik OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.025 99,920.00 2,498.00
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Lampu TL 2 x 36 watt bh 1.000 - -
Isolasi bh 0.250 5,000.00 1,250.00
JUMLAH HARGA BAHAN 1,250.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 28,728.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 28,728.00

Pemasangan 1 bh stop kontak


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang listrik OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.025 99,920.00 2,498.00
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Stop kontak bh 1.000 50,000.00 50,000.00
Mangkok listrik bh 1.000 1,200.00 1,200.00
Isolasi bh 0.250 5,000.00 1,250.00
JUMLAH HARGA BAHAN 52,450.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 79,928.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 79,928.00

Pemasangan 1 bh saklar double


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang listrik OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.050 99,920.00 4,996.00
Mandor OH 0.025 99,920.00 2,498.00
JUMLAH TENAGA KERJA 27,478.00
B. BAHAN
Saklar ganda bh 1.000 - -
Mangkok listrik bh 1.000 1,200.00 1,200.00
Isolasi bh 0.250 5,000.00 1,250.00
JUMLAH HARGA BAHAN 2,450.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 29,928.00
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 29,928.00
Pemasangan 1 m2 jaring kawat baja (wiremesh) m 6 1 lapis
KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.100 99,920.00 9,992.00
Tukang Besi OH 0.100 99,920.00 9,992.00
Kepala Tukang OH 0.010 99,920.00 999.20
Mandor OH 0.001 99,920.00 99.92
JUMLAH TENAGA KERJA 21,083.12
B. BAHAN
Wiremesh M6@50m roll 0.010 200,000.00 2,000.00
Kawat Beton RRT kg 0.050 13,000.00 650.00
JUMLAH HARGA BAHAN 2,650.00
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 23,733.12
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 23,733.12

1 M2 Tempelan Batu Andesit (30 x 30 x 5 cm)


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Ongkos Tukang ls 1.000 200,000.00 200,000.00
JUMLAH TENAGA KERJA 200,000.00
B. BAHAN
Batu Andesit (30 x 30 x 5 cm) bh 1.050 - -
Semen kg 3.350 1,075.00 3,601.25
Pasir Pasang m3 0.100 120,000.00 12,000.00
JUMLAH HARGA BAHAN 15,601.25
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 215,601.25
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 215,601.25

8 1 M2 Cat Texture KCA


KOEFISIEN HARGA SATUAN JUMLAH HARGA
NO. URAIAN SATUAN
(Rp.) (Rp.)

A. TENAGA
Pekerja OH 0.0150 99,920.00 1,498.80
Tukang cat OH 0.1600 99,920.00 15,987.20
Kepala Tukang OH 0.0140 99,920.00 1,398.88
Mandor OH 0.0050 99,920.00 499.60
JUMLAH TENAGA KERJA 19,384.48
B. BAHAN
Cat Texture KCA kg 0.4500 - -
JUMLAH HARGA BAHAN -
C. PERALATAN
JUMLAH HARGA ALAT

D. Jumlah (A + B + C) 19,384.48
E. Overhead & Profit 0 %xD
F. Harga Satuan Pekerjaan (D+E) 19,384.48
Pembangunan Gedung SDN 6 Padang Sambian (lanjutan)

HPS 657,583,470.17

1 CV.PRISMA ALAM 455,487,269.17 202,096,201.00 30.733


2 CV. SARANA MULTY KREASI 459,512,792.18 198,070,677.99 30.121
3 CV. DUTA ADI PUTRA 460,752,282.87 196,831,187.30 29.933
4 CV. Patuh Karya 472,979,818.99 184,603,651.18 28.073

Renovasi Bale Banjar Celagi Gendong, Desa Pemecutan, Kecamatan Denpasar Barat

HPS 1,999,918,000.00

1 CV. SARI ARTA NADI 1,441,835,515.80 558,082,484.20 27.905


2 CV.PRISMA ALAM 1,491,347,916.90 508,570,083.10 25.430
3 CV. Giri Artha 1,492,377,055.87 507,540,944.13 25.378
4 CV. GRIYA MANDIRI TEKNIK 1,500,068,627.77 499,849,372.23 24.993
5 CV. KARYA UTAMA 1,504,892,585.20 495,025,414.80 24.752