Anda di halaman 1dari 26

HARGA SATUAN

NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA


SATUAN Rp

X PASANGAN INSTALASI AIR


Instalasi Air Bersih
1 Pasangan pipa PVC diameter 3/4 inci 9.00 M’ 26,000.00 234,000.00
2 Pasangan pipa PVC diameter 3 inci 8.50 M’ 154,000.00 1,309,000.00
3 Pasangan pipa PVC diameter 4 inci 5.00 M’ 256,000.00 1,280,000.00
4 Accesoris lain (lem pipa, ampelas, sambungan, dll 10 % pipa) 1.00 Ls 280,000.00 280,000.00
5 Pekerjaan septic tank dan rembesan 1.00 Unit 8,012,500.00 8,012,500.00
Jumlah 11,115,500.00
Dibulatkan 11,115,500.00

XI PEKERJAAN INSTALASI LISTRIK


1 Pasangan lengkap lampu terpasang 11.00 Ttk 113,800.00 1,251,800.00
2 Saklar single 2.00 Ttk 101,000.00 202,000.00
3 Saklar double 1.00 Ttk 105,800.00 105,800.00
4 Saklar triple 2.00 Ttk 108,500.00 217,000.00
5 Stop kontak 8.00 Ttk 37,500.00 300,000.00
6 Panel box 1.00 Bh 550,000.00 550,000.00
Jumlah 2,626,600.00
Dibulatkan 2,626,600.00

XII PEKERJAAN PENGECATAN


1 Pengecatan dinding dengan cat tembok kwalitas baik 210.34 M² 35,700.00 7,509,138.00
2 Pengecatan plafon dengan cat tembok kwalitas sedang 30.50 M² 29,700.00 905,850.00
3 Pengecatan kusen dengan cat minyak 0.40 M² 32,000.00 12,800.00
5 Pengecatan daun pintu dengan cat minyak 5.67 M² 32,000.00 181,440.00
6 Pengecatan daun jendela dengan cat minyak 1.40 M² 32,000.00 44,800.00
Jumlah 8,654,028.00
Dibulatkan 8,654,020.00

HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME JUMLAH HARGA
SATUAN Rp

XIII PEKERJAAN LAIN-LAIN


1 Pembersihan lahan setelah selesai pekerjaan 55.00 M² 12,500.00 687,500.00
Jumlah 687,500.00
Dibulatkan 687,500.00
REKAPITULASI BIAYA KESELURUHAN

NO URAIAN PEKERJAAN JUMLAH HARGA (Rp)


I PEKERJAAN PERSIAPAN, GALIAN DAN URUGAN 4,913,990.00
II PEKERJAAN PONDASI DAN BETON 49,691,300.00
III PEKERJAAN PASANGAN DAN PLESTERAN 20,085,000.00
IV PEKERJAAN LANTAI DAN DINDING 6,468,820.00
V PEKERJAAN ATAP 8,598,150.00
VI PEKERJAAN PLAFON 3,669,150.00
VII PEKERJAAN KUSEN PINTU DAN JENDELA 5,768,460.00
VIII PEKERJAAN PERLENGKAPAN PINTU DAN JENDELA 3,753,600.00
IX PEKERJAAN SANITAIR 1,439,500.00
X PEKERJAAN INSTALASI AIR 11,115,500.00
XI PEKERJAAN INSTALASI LISTRIK 2,626,600.00
XII PEKERJAAN PENGECATAN 8,654,020.00
XIII PEKERJAAN PEMBERSIHAN 687,500.00
JUMLAH 127,471,590.00
DIBULATKAN 127,471,000.00
X PASANGAN INSTALASI AIR
Instalasi Air Bersih
1 Pasangan pipa PVC diameter 3/4 inci 9.00 M’
2 Pasangan pipa PVC diameter 3 inci 8.50 M’
3 Pasangan pipa PVC diameter 4 inci 5.00 M’
4 Accesoris lain (lem pipa, ampelas, sambungan, dll 10 % pipa) 1.00 Ls
5 Pekerjaan septic tank dan rembesan 1.00 Unit

XI PEKERJAAN INSTALASI LISTRIK


1 Pasangan instalasi titik nyala lampu kabel NYM 3 x 2,5 mm 11.00 Ttk
2 Pasangan instalasi titik nyala daya stop kontak lampu kabel NYM 3x2,5 mm 6.00 Ttk
3 Pasangan lampu taman 3.00 Bh
4 Pasangan titik lampu 8.00 Bh
5 Pasangan panel listrik 1.00 Bh
6 Pasangan penyambung daya ke PLN 1.00 Ls

XII PEKERJAAN PENGECATAN


1 Pengecatan dinding dengan cat tembok kwalitas baik 210.34 M²
2 Pengecatan plafon dengan cat tembok kwalitas sedang 30.50 M²
3 Pengecatan kusen dengan cat minyak 0.40 M²
5 Pengecatan daun pintu dengan cat minyak 5.67 M²
6 Pengecatan daun jendela dengan cat minyak 1.40 M²

XIII PEKERJAAN LAIN-LAIN


1 Pembersihan lahan setelah selesai pekerjaan 55.00 m2