I PEKERJAAN PERSIAPAN
1 Mobilisasi 1.00 Ls Ls 1.00 5,900,000.00 5,900,000.00 5,900,000.00
2 serobong kerja & stocking 1.00 Ls Ls - 1.00 7,500,000.00 7,500,000.00 7,500,000.00
3 construction drawing 1.00 Ls Ls - 1.00 5,000,000.00 5,000,000.00 5,000,000.00
4 pelaporan, test Mutu, Dan dokumentasi 1.00 ls ls - 1.00 8,000,000.00 8,000,000.00 8,000,000.00
5 pembersihan lokasi 1,250.00 m2 m2 - 1,250.00 10,258.00 12,822,500.00 12,822,500.00
6 Langsiran Material 387.20 m3 m3 - 387.20 118,019.00 45,696,956.80 45,696,956.80
SUB JUMLAH 84,919,456.80 84,919,456.80
II.2 Pekerjaan Saluran
1 Beton B0 133.10 M3 115.90 M3 - 17.20 115.90 1,762,369.00 234,571,313.90 204,257,670.05
2 Beton K-225 254.10 M3 256.70 M3 + (2.60) 256.70 1,928,398.00 490,005,931.80 495,016,821.94
3 Pembesian 10,248.70 Kg 9,739.88 Kg - 508.82 9,739.88 26,786.00 274,521,678.20 260,892,481.77
4 Bekisting 1,210.00 M2 1,348.32 M2 + (138.32) 1,348.32 182,735.00 221,109,350.00 246,386,141.46
5 Galian Tanah 404.65 m3 484.84 m3 + (80.19) 484.84 103,615.00 41,927,809.75 50,236,696.60
6 pancang kayu galam 1,210.00 Titik 1,348.32 Titik + (138.32) 1,348.32 38,652.00 46,768,920.00 52,115,452.10
SUB JUMLAH 1,308,905,003.65 1,308,905,263.93
II.4 Pekerjaan Bangunan pintu air
1 Beton B0 0.60 M3 M3 0.60 1,762,369.00 1,057,421.40 1,057,421.40
2 Beton K-225 1.50 M3 M3 1.50 1,928,398.00 2,892,597.00 2,892,597.00
3 Pembesian 60.00 Kg Kg 60.00 26,786.00 1,607,160.00 1,607,160.00
4 Bekisting 10.00 M2 M2 10.00 182,735.00 1,827,350.00 1,827,350.00
5 Pintu uk. B = 0.7 ; h = 1.3 2.00 Bh Bh 2.00 5,000,000.00 10,000,000.00 10,000,000.00
6 Pancang Kayu galam 12.00 Titik Titik 12.00 38,652.00 463,824.00 463,824.00
SUB JUMLAH 17,848,352.40 17,848,352.40
JUMLAH TOTAL 1,411,672,812.85 1,411,673,073.13
PPN 10 % ( A ) 141,167,281.29 141,167,307.31
TOTAL ( A + B ) 1,552,840,094.14 1,552,840,380.44
DIBULATKAN 1,552,840,000.00 1,552,840,000.00
JADWAL PELAKSANAAN PEKERJAAN
KONSULTAN PENGAWAS : CV. ARCSIND
DINAS : PEKERJAAN UMUN DAN PENATAAN RUANG NO. KONTRAK : 611/SP-24.350.0
KEGIATAN : PENINGKATAN IRIGASI TEKNIS D.I BANTUAS DALAM KONTRAKTOR PELAKSANA : CV. WARNA P
PEKERJAAN NO. KONTRAK : 611/SP-24.350.0
LOKASI : BANTUAS DALAM KONSULTAN PENGAWAS : CV. PUSAKA D
TAHUN ANGGARAN : 2019 PERIODE : 22 APRIL - 22 D
KONTRAK WAKTU PELAKSANAAN PEKERJAAN
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT MC 01 MC 02 MC 03 MC 04 MC 05 MC 06
VOL
( Rp. ) ( Rp. ) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A. PEKERJAAN PENDAHULUAN
1 mobilisasi ls 1.00 5,900,000.00 5,900,000.00 0.418 0.2 0.2
4 pelaporan, test mutu, dan dokumentasi ls 1.00 8,000,000.00 8,000,000.00 0.567 0.1 0.1 0.1 0.1 0.1 0.1
5 pembersihan lokasi m2 1250.00 10,258.00 12,822,500.00 0.908 0.2 0.2 0.2 0.2
6 langsiran material m3 387.20 118,019.00 45,696,956.80 3.237 0.5 0.5 0.5 0.5 0.5 0.5
-
B. PEKERJAAN SALURAN
Beton B0 m3 115.90 1,762,369.00 204,257,670.05 14.469 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Beton Fc ' 20 Mpa m3 256.70 1,928,398.00 495,016,821.94 35.066 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8
Pembesian kg 9,739.88 26,786.00 260,892,481.77 18.481 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Bekisting m2 1,348.32 182,735.00 246,386,141.46 17.453 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Galian Tanah m3 484.84 103,615.00 50,236,437.56 3.559 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
-
C. PEKERJAAN BANGUNAN PINTU AIR
Beton B0 m3 0.600 1,762,369.00 1,057,421.40 0.075 0.0
Beton Fc ' 20 Mpa m3 1.500 1,928,398.00 2,892,597.00 0.205 0.1
Pembesian kg 60.000 26,786.00 1,607,160.00 0.114 0.1
Bekisting m2 10.000 182,735.00 1,827,350.00 0.129 0.1
RENCANA KEMAJUAN PEKERJAAN - - - 0.2 0.4 0.7 0.9 1.3 2.2 3.9 5.4 5.4 4.8 4.8 4.8 4.8 4.8 4.9 4.9 5.1 4.8 4.8
RENCANA KOMULATIF KEMAJUAN PEKERJAAN - - - - 0.2 0.6 1.3 2.2 3.5 5.6 9.5 14.9 20.3 25.1 29.9 34.7 39.5 44.2 49.1 54.1 59.2 64.0 68.8
REALISASI KEMAJUAN PEKERJAAN 1.3 1.0 1.2 1.3 1.7 6.5 6.9 8.7 7.1 8.6 9.3 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9
REALISASI KOMULATIF KEMAJUAN PEKERJAAN - 1.3 2.3 3.5 4.9 6.6 13.1 20.0 28.6 35.7 44.3 53.6 55.5 57.4 59.3 61.2 63.1 65.0 66.9 68.8 70.7 72.7 74.6
PERBEDAAN KOMULATIF 1.3 2.3 3.5 4.6 6.0 11.8 17.8 25.2 30.1 34.8 38.7 35.2 32.3 29.5 26.6 23.7 20.8 17.82 14.78 11.55 8.67 5.79
0.2 0.2
0.2 0.2
0.0
0.1
0.1
0.1
0.4
0.0
73.5 78.3 82.7 87.0 91.5 95.2 98.2 100.0 100.0 100.0 100.0 100.0
76.5 78.4 89.3 100.1 100.1 100.1 100.6 101.9 101.9 101.9 101.9 101.9
2.91 0.03 6.60 13.02 8.56 4.85 2.38 1.90 1.90 1.90 1.90 1.90
WINDY IMELDA
DIREKTUR
JADWAL PELAKSANAAN PEKERJAAN
KONSULTAN PENGAWAS : CV. ARCSIND
DINAS : PEKERJAAN UMUN DAN PENATAAN RUANG NO. KONTRAK : 611/SP-24.350.0
KEGIATAN : PENINGKATAN IRIGASI TEKNIS D.I BANTUAS DALAM KONTRAKTOR PELAKSANA : CV. WARNA P
PEKERJAAN NO. KONTRAK : 611/SP-24.350.0
LOKASI : BANTUAS DALAM KONSULTAN PENGAWAS : CV. PUSAKA D
TAHUN ANGGARAN : 2019 PERIODE : 08 OKTOBER
KONTRAK WAKTU PELAKSANAAN PEKERJAAN
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT MC 01 MC 02 MC 03 MC 04 MC 05 MC 06
VOL
( Rp. ) ( Rp. ) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A. PEKERJAAN PENDAHULUAN
1 mobilisasi ls 1.00 5,900,000.00 5,900,000.00 0.418 0.2 0.2
4 pelaporan, test mutu, dan dokumentasi ls 1.00 8,000,000.00 8,000,000.00 0.567 0.1 0.1 0.1 0.1 0.1 0.1
5 pembersihan lokasi m2 1250.00 10,258.00 12,822,500.00 0.908 0.2 0.2 0.2 0.2
6 langsiran material m3 387.20 118,019.00 45,696,956.80 3.237 0.5 0.5 0.5 0.5 0.5 0.5
-
B. PEKERJAAN SALURAN
Beton B0 m3 115.90 1,762,369.00 204,257,670.05 14.469 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Beton Fc ' 20 Mpa m3 256.70 1,928,398.00 495,016,821.94 35.066 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8
Pembesian kg 9,739.88 26,786.00 260,892,481.77 18.481 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Bekisting m2 1,348.32 182,735.00 246,386,141.46 17.453 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Galian Tanah m3 484.84 103,615.00 50,236,437.56 3.559 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
-
C. PEKERJAAN BANGUNAN PINTU AIR
Beton B0 m3 0.600 1,762,369.00 1,057,421.40 0.075 0.0
Beton Fc ' 20 Mpa m3 1.500 1,928,398.00 2,892,597.00 0.205 0.1
Pembesian kg 60.000 26,786.00 1,607,160.00 0.114 0.1
Bekisting m2 10.000 182,735.00 1,827,350.00 0.129 0.1
RENCANA KEMAJUAN PEKERJAAN - - - 0.2 0.4 0.7 0.9 1.3 2.2 3.9 5.4 5.4 4.8 4.8 4.8 4.8 4.8 4.9 4.9 5.1 4.8 4.8
RENCANA KOMULATIF KEMAJUAN PEKERJAAN - - - - 0.2 0.6 1.3 2.2 3.5 5.6 9.5 14.9 20.3 25.1 29.9 34.7 39.5 44.2 49.1 54.1 59.2 64.0 68.8
REALISASI KEMAJUAN PEKERJAAN 1.3 1.0 1.2 1.3 1.7 6.5 6.9 8.7 7.1 8.6 9.3 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9
REALISASI KOMULATIF KEMAJUAN PEKERJAAN - 1.30 2.33 3.55 4.86 6.60 13.09 19.96 28.62 35.69 44.29 53.64 55.54 57.44 59.34 61.25 63.15 65.05 66.95 68.85 70.75 72.65 74.55
PERBEDAAN KOMULATIF 1.3 2.3 3.5 4.6 6.0 11.8 17.8 25.2 30.1 34.8 38.7 35.2 32.3 29.5 26.6 23.7 20.8 17.82 14.78 11.55 8.67 5.79
0.2 0.2
0.2 0.2
0.0
0.1
0.1
0.1
0.4
0.0
73.5 78.3 82.7 87.0 91.5 95.2 98.2 100.0 100.0 100.0 100.0 100.0
WINDY IMELDA
DIREKTUR
JADWAL PELAKSANAAN PEKERJAAN
KONSULTAN PENGAWAS : CV. ARCSIND
DINAS : PEKERJAAN UMUN DAN PENATAAN RUANG NO. KONTRAK : 611/SP-24.350.0
KEGIATAN : PENINGKATAN IRIGASI TEKNIS D.I BANTUAS DALAM KONTRAKTOR PELAKSANA : CV. WARNA P
PEKERJAAN NO. KONTRAK : 611/SP-24.350.0
LOKASI : BANTUAS DALAM KONSULTAN PENGAWAS : CV. PUSAKA D
TAHUN ANGGARAN : 2019 PERIODE : 06 NOVEMBER
KONTRAK WAKTU PELAKSANAAN PEKERJAAN
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT MC 01 MC 02 MC 03 MC 04 MC 05 MC 06
VOL
( Rp. ) ( Rp. ) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A. PEKERJAAN PENDAHULUAN
1 mobilisasi ls 1.00 5,900,000.00 5,900,000.00 0.418 0.2 0.2
4 pelaporan, test mutu, dan dokumentasi ls 1.00 8,000,000.00 8,000,000.00 0.567 0.1 0.1 0.1 0.1 0.1 0.1
5 pembersihan lokasi m2 1250.00 10,258.00 12,822,500.00 0.908 0.2 0.2 0.2 0.2
6 langsiran material m3 387.20 118,019.00 45,696,956.80 3.237 0.5 0.5 0.5 0.5 0.5 0.5
-
B. PEKERJAAN SALURAN
Beton B0 m3 115.90 1,762,369.00 204,257,670.05 14.469 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Beton Fc ' 20 Mpa m3 256.70 1,928,398.00 495,016,821.94 35.066 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8
Pembesian kg 9,739.88 26,786.00 260,892,481.77 18.481 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Bekisting m2 1,348.32 182,735.00 246,386,141.46 17.453 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Galian Tanah m3 484.84 103,615.00 50,236,437.56 3.559 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
-
C. PEKERJAAN BANGUNAN PINTU AIR
Beton B0 m3 0.600 1,762,369.00 1,057,421.40 0.075 0.0
Beton Fc ' 20 Mpa m3 1.500 1,928,398.00 2,892,597.00 0.205 0.1
Pembesian kg 60.000 26,786.00 1,607,160.00 0.114 0.1
Bekisting m2 10.000 182,735.00 1,827,350.00 0.129 0.1
RENCANA KEMAJUAN PEKERJAAN - - - 0.2 0.4 0.7 0.9 1.3 2.2 3.9 5.4 5.4 4.8 4.8 4.8 4.8 4.8 4.9 4.9 5.1 4.8 4.8
RENCANA KOMULATIF KEMAJUAN PEKERJAAN - - - - 0.2 0.6 1.3 2.2 3.5 5.6 9.5 14.9 20.3 25.1 29.9 34.7 39.5 44.2 49.1 54.1 59.2 64.0 68.8
REALISASI KEMAJUAN PEKERJAAN 1.3 1.0 1.2 1.3 1.7 6.5 6.9 8.7 7.1 8.6 9.3 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9
REALISASI KOMULATIF KEMAJUAN PEKERJAAN - 1.3 2.3 3.5 4.9 6.6 13.1 20.0 28.6 35.7 44.3 53.6 55.5 57.4 59.3 61.2 63.1 65.0 66.9 68.8 70.7 72.7 74.6
PERBEDAAN KOMULATIF 1.3 2.3 3.5 4.6 6.0 11.8 17.8 25.2 30.1 34.8 38.7 35.2 32.3 29.5 26.6 23.7 20.8 17.82 14.78 11.55 8.67 5.79
0.2 0.2
0.2 0.2
0.0
0.1
0.1
0.1
0.4
0.0
73.5 78.3 82.7 87.0 91.5 95.2 98.2 100.0 100.0 100.0 100.0 100.0
76.5 76.5 87.4 98.2 98.2 98.2 98.72 100.0 100.0 100.0
WINDY IMELDA
DIREKTUR
JADWAL PELAKSANAAN PEKERJAAN
KONSULTAN PENGAWAS : CV. ARCSIND
DINAS : PEKERJAAN UMUN DAN PENATAAN RUANG NO. KONTRAK : 611/SP-24.350.0
KEGIATAN : PENINGKATAN IRIGASI TEKNIS D.I BANTUAS DALAM KONTRAKTOR PELAKSANA : CV. WARNA P
PEKERJAAN NO. KONTRAK : 611/SP-24.350.0
LOKASI : BANTUAS DALAM KONSULTAN PENGAWAS : CV. PUSAKA D
TAHUN ANGGARAN : 2019 PERIODE : 04 DESEMBER
KONTRAK WAKTU PELAKSANAAN PEKERJAAN
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT MC 01 MC 02 MC 03 MC 04 MC 05 MC 06
VOL
( Rp. ) ( Rp. ) (%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A. PEKERJAAN PENDAHULUAN
1 mobilisasi ls 1.00 5,900,000.00 5,900,000.00 0.418 0.2 0.2
4 pelaporan, test mutu, dan dokumentasi ls 1.00 8,000,000.00 8,000,000.00 0.567 0.1 0.1 0.1 0.1 0.1 0.1
5 pembersihan lokasi m2 1250.00 10,258.00 12,822,500.00 0.908 0.2 0.2 0.2 0.2
6 langsiran material m3 387.20 118,019.00 45,696,956.80 3.237 0.5 0.5 0.5 0.5 0.5 0.5
-
B. PEKERJAAN SALURAN
Beton B0 m3 115.90 1,762,369.00 204,257,670.05 14.469 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8 0.8
Beton Fc ' 20 Mpa m3 256.70 1,928,398.00 495,016,821.94 35.066 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8 1.8
Pembesian kg 9,739.88 26,786.00 260,892,481.77 18.481 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Bekisting m2 1,348.32 182,735.00 246,386,141.46 17.453 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9 0.9
Galian Tanah m3 484.84 103,615.00 50,236,437.56 3.559 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2
-
C. PEKERJAAN BANGUNAN PINTU AIR
Beton B0 m3 0.600 1,762,369.00 1,057,421.40 0.075 0.0
Beton Fc ' 20 Mpa m3 1.500 1,928,398.00 2,892,597.00 0.205 0.1
Pembesian kg 60.000 26,786.00 1,607,160.00 0.114 0.1
Bekisting m2 10.000 182,735.00 1,827,350.00 0.129 0.1
RENCANA KEMAJUAN PEKERJAAN - - - 0.2 0.4 0.7 0.9 1.3 2.2 3.9 5.4 5.4 4.8 4.8 4.8 4.8 4.8 4.9 4.9 5.1 4.8 4.8
RENCANA KOMULATIF KEMAJUAN PEKERJAAN - - - - 0.2 0.6 1.3 2.2 3.5 5.6 9.5 14.9 20.3 25.1 29.9 34.7 39.5 44.2 49.1 54.1 59.2 64.0 68.8
REALISASI KEMAJUAN PEKERJAAN 1.3 1.0 1.2 1.3 1.7 6.5 6.9 8.7 7.1 8.6 9.3 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9 1.9
REALISASI KOMULATIF KEMAJUAN PEKERJAAN - 1.3 2.3 3.5 4.9 6.6 13.1 20.0 28.6 35.7 44.3 53.6 55.5 57.4 59.3 61.2 63.1 65.0 66.9 68.8 70.7 72.7 74.6
PERBEDAAN KOMULATIF 1.3 2.3 3.5 4.6 6.0 11.8 17.8 25.2 30.1 34.8 38.7 35.2 32.3 29.5 26.6 23.7 20.8 17.82 14.78 11.55 8.67 5.79
0.2 0.2
0.2 0.2
0.0
0.1
0.1
0.1
0.4
0.0
73.5 78.3 82.7 87.0 91.5 95.2 98.2 100.0 100.0 100.0 100.0 100.0
76.5 76.5 87.4 98.2 98.2 98.2 98.7 100.0 100.0 100.0 100.0 100.0
WINDY IMELDA
DIREKTUR
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
serobong kerja dan stocking ls 1.00 7,500,000.00 7,500,000.00 0.531 1.00 100.00 0.531
pelaporan, test mutu, dan dokumentasi ls 1.00 8,000,000.00 8,000,000.00 0.567 1.00 100.00 0.567
B. PEKERJAAN SALURAN
2.10 2.097
0.209
2.097
2.097
1.89
LAPORAN KEMAJUAN MINGGUAN
BULAN KE 1 (SATU)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D BULAN LALU BULAN INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
serobong kerja dan stocking ls 1.00 7,500,000.00 7,500,000.00 0.531 1.00 100.00 0.531
pelaporan, test mutu, dan dokumentasi ls 1.00 8,000,000.00 8,000,000.00 0.567 1.00 100.00 0.567
B. PEKERJAAN SALURAN
2.10 2.097
0.209
2.097
2.097
1.89
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
0.98 0.978
0.595
0.978
0.978
0.38
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
16.18 2,977.039
1.303
2,977.039
2,977.039
2,975.74
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 134.83 10.00 0.369
14.73 138.896
2.164
138.896
138.896
136.73
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
0.81 0.814
3.452
0.814
0.814
(2.64)
LAPORAN KEMAJUAN MINGGUAN
BULAN KE 1 (SATU)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D BULAN LALU BULAN INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 269.66 20.00 0.738
1.63 1.628
3.452
1.628
1.628
(1.82)
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
Galian Tanah m3 484.84 103,615.00 50,236,437.56 3.559 121.2 587.7 0.44 56.00 11.55
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 269.7 3,636.0 0.37 84.00 6.23
5.612
11.171
11.171
5.56
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
Pembesian kg 9,739.88 26,786.00 260,892,481.77 18.481 2,000 194,798 3.79 2,000.00 20.53 3.795
Bekisting m2 1,348.32 182,735.00 246,386,141.46 17.453 337 4,545 4.36 325.00 24.10 4.207
Galian Tanah m3 484.84 103,615.00 50,236,437.56 3.559 177 859 0.41 75.00 15.47 0.550
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 354 4,769 0.23 54.00 4.00 0.148
44.00 51 3.121
0.41 19.471
9.500
19.471
19.471
9.97
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
Beton K-225 m3 256.70 1,928,398.00 495,016,821.94 35.066 56 144 7.6 79.00 30.78 10.792
Pembesian kg 9,739.88 26,786.00 260,892,481.77 18.481 4,000 389,595 3.8 1,200.00 12.32 2.277
Bekisting m2 1,348.32 182,735.00 246,386,141.46 17.453 662 8,927 4.2 200.00 14.83 2.589
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 408 5,497 0 125.00 9.27 0.342
1.11 52.569
14.915
16.000
52.569
37.65
LAPORAN KEMAJUAN MINGGUAN
MINGGU KE 4 (EMPAT)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D MIGGU LALU MINGGU INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
Beton K-225 m3 256.70 1,928,398.00 495,016,821.94 35.066 135 385 44.240 45.00 17.53 6.147
Pembesian kg 9,739.88 26,786.00 260,892,481.77 18.481 5,200 28,137 2.277 300.00 3.08 0.569
Bekisting m2 1,348.32 182,735.00 246,386,141.46 17.453 862 4,939 2.589 53.00 3.93 0.686
pancang kayu galam Titik 1,348.32 38,652.00 52,115,452.10 3.692 533 14,429 0.342 65.00 4.82 0.178
- - -
39.07 1,852.463
20.329
15.695
1,852.463
1,832.13
LAPORAN KEMAJUAN MINGGUAN
BULAN KE 1 (SATU)
KEGIATAN : Pengembangan Dan Peningkatan Jaringan Irigasi, Rawa Dan Jaringan Pengairan Lain nya NO. KONTRAK
PEKERJAAN : Peningkatan Irigasi Teknis D.I Bantuas Dalam ( Benkeu 2019 ) KONTRAKTOR PELAKSANA
LOKASI : Desa Bantuas, Kec. Palaran NO. KONTRAK
TAHUN ANGGARAN : 2019 KONSULTAN PENGAWAS
PERIODE
KONTRAK S/D BULAN LALU BULAN INI
NO. URAIAN PEKERJAAN SAT. HARGA SATUAN JUMLAH HARGA BOBOT THD THD THD THD
VOLUME VOLUME VOLUME
( Rp. ) ( Rp. ) (%) PEK TOTAL PEK TOTAL
A. PEKERJAAN PENDAHULUAN
B. PEKERJAAN SALURAN
5.414
-
-
(5.41)
BACK UP VOLUME
1 mobilisasi LS 1.00
LS LS VOLUME
2 sarana prasarana personil LS 2.00
LS LS VOLUME
B. PEKERJAAN SALURAN
LUASAN PANJANG VOLUME
Beton B0 m3 0.600
LUASAN PANJANG VOLUME
Pembesian kg 60.00
Bekisting m2 10.00
LUASAN PANJANG VOLUME
A. PEKERJAAN PENDAHULUAN
1 Pengukuran dan Pemasangan Bouwplank m 1,000 70,000.00 70,000,000.00 2.436 1,000.00 2.436
2 Penmbersihan Lokasi m2 431 17,500.00 7,542,500.00 0.263 431 0.263
: KU.003/03/829/LPU.2017
KONTRAKTOR PELAKSANA : PT. GITA LESTARI BULUNGAN
: KU.003/03/609/LPU.2017
KONSULTAN PENGAWAS : CV. NAMIRA CONSULTANT
: 30 MEI - 25 DESEMBER 2017 ( 210 HARI )
#REF!
BULAN INI S/D BULAN INI
BOBOT BOBOT KETERANGAN
VOLUME
(%) (%)
1,000.00 2.436
431.00 0.263
1,360.00 3.195
0.014 34.00 0.669
5.728 251.30 34.030
5.742 40.593
49.130
5.742
40.593
-8.537